| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.9 LAccepted-Finance | L1 | Accepted-Finance Since only one bidder |
| Sl No | Description | Qty | Unit | J.Jayalalitha L1 |
|---|---|---|---|---|
| 2.00SCAFFOLDING | ||||
| 3.00 | All the areas which are under consideration for the repair & rehabilitation are to be provided with double legged scaffolding independent of the work having two sets of vertical supports. The supports shall be sound and strong, tied together with horizontal pieces over which scaffolding planks shall be fixed. Supply and fixing of scaffolding with bracing including cost of all material, all labour charges etc., | 64.99 | Sq M | 345.67 ₹22,465.09 Lowest |
| 4.00SURFACE PREPARATION | ||||
| 5.00 | Labour charges for chipping the spalled and old concrete of the slab. Check for the phenopthaline
test and if there is no change in colour chip the same further down until, reaching the good or uncontaminated concrete. Clean the surface and make sure that surface is clean and free from loose particle at an average thickness of 50mm. | 64.99 | Sq M | 567.89 ₹36,907.17 Lowest |
| 6.00PRIMING OF REINFORCEMENT BARS | ||||
| 7.00 | Clean the rebars using the rust remover if there exists any rust, otherwise clean the rebar free of foreign material. Mix the base and hardner of the zinc rich epoxy resin mechanically using a slow speed heavy duty drilling machine fitted with mixing paddle. Apply the mixed materials to the cleaned rebar and allow it to dry complete. | 8.46 | Lts | 2,345.67 ₹19,844.37 Lowest |
| 8.00FORM WORK | ||||
| 9.00 | Providing slurry tight form work including strutting, propping, etc., which should not deform or leak due to pressure of micro concrete shall be fabricated in position using 6mm thick commercial plywood as per the required line and length at all different floor levels as per the standard specification-complete. Form work should be rigid to prevent loss of micro concrete at all stages & appropriate to the methods of placing & compacting as per standard specification. It should be made of suitable material. The form work should be coated with shutter release agent prior to fixing. The rate shall include the cost of all the operations and etc., | 64.99 | Sq M | 901.23 ₹58,570.94 Lowest |
| 10.00MICROCONCRETE | ||||
| 11.00 | Micro Concreting for the damaged structural element like slab/beam/column by Stocking sufficient quantity of micro concrete and 12mm downgraded chips on site to enable the completion of the pouring in a continuous operation. An approved concrete mixer or a slow speed heavy duty drilling machine fitted with mixing paddle shall be used. Mix the micro concrete and the 12mm down grade chips in the ratio of 1: 0.5 (one part of Rendroc RG and 0.5 part 12mm down chip) by weight with required quantity of water powder ratio 0.16 and place the same to the prefixed formwork well before the epoxy jointing compound dries up. Remove the formwork after 24 hours in the case of columns and after a period of 72 hours in the case of slab and beam and check for any surface defects and if so apply the polymer modified mortar - complete. The rate shall include the cost of all the operations and complete. | 2.63 | Cu M | 57,575.75 ₹1,51,424.22 Lowest |
Tender Value
₹4.1 L
EMD Value
₹4,079
Closing Date
6 Oct 2025, 2:00 pmClosed
Executive Engineer/O/Villupuram
230/110 kv auto ss, poothamedu, villupuram
structure modification of 230kv bus 2 south at villupuram 230 KV SS
2025_EB_607951_1
specno.05dt23.09.25
Open Tender
Civil Works
Works
Executive Engineer/O/Villupuram
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹4,079
Yes
25 Nov 2025
23 Sept 2025
7 Oct 2025
23 Sept 2025
6 Oct 2025
23 Sept 2025
23 Sept 2025 - 6 Oct 2025
Amount
SCAFFOLDING
All the areas which are under consideration for the repair & rehabilitation are to be provided with double legged scaffolding independent of the work having two sets of vertical supports. The supports shall be sound and strong, tied together with horizontal pieces over which scaffolding planks shall be fixed. Supply and fixing of scaffolding with bracing including cost of all material, all labour charges etc.,
SURFACE PREPARATION
Labour charges for chipping the spalled and old concrete of the slab. Check for the phenopthaline test and if there is no change in colour chip the same further down until, reaching the good or uncontaminated concrete. Clean the surface and make sure that surface is clean and free from loose particle at an average thickness of 50mm.
PRIMING OF REINFORCEMENT BARS
Clean the rebars using the rust remover if there exists any rust, otherwise clean the rebar free of foreign material. Mix the base and hardner of the zinc rich epoxy resin mechanically using a slow speed heavy duty drilling machine fitted with mixing paddle. Apply the mixed materials to the cleaned rebar and allow it to dry complete.
FORM WORK
Providing slurry tight form work including strutting, propping, etc., which should not deform or leak due to pressure of micro concrete shall be fabricated in position using 6mm thick commercial plywood as per the required line and length at all different floor levels as per the standard specification-complete. Form work should be rigid to prevent loss of micro concrete at all stages & appropriate to the methods of placing & compacting as per standard specification. It should be made of suitable material. The form work should be coated with shutter release agent prior to fixing. The rate shall include the cost of all the operations and etc.,
MICROCONCRETE
Micro Concreting for the damaged structural element like slab/beam/column by Stocking sufficient quantity of micro concrete and 12mm downgraded chips on site to enable the completion of the pouring in a continuous operation. An approved concrete mixer or a slow speed heavy duty drilling machine fitted with mixing paddle shall be used. Mix the micro concrete and the 12mm down grade chips in the ratio of 1: 0.5 (one part of Rendroc RG and 0.5 part 12mm down chip) by weight with required quantity of water powder ratio 0.16 and place the same to the prefixed formwork well before the epoxy jointing compound dries up. Remove the formwork after 24 hours in the case of columns and after a period of 72 hours in the case of slab and beam and check for any surface defects and if so apply the polymer modified mortar - complete. The rate shall include the cost of all the operations and complete.
PROTECTIVE COATING
Prepare the surface neatly ensuring there is no fine dust accumlated over the area, and wash the surface and allow it to dry prior to the application of the primer. Mix the high performacne, aliphatic acrylate based anticarbonation proteive coating primer Fosroc Deckguard S Primer to the prepared surface and allow the same ro dry over a period of 2 hours over which Deckguard S top coat shall be applied in two mutually perpendicular directions in order to obtain a DFT of 150 microns over the prepared area.
GST 18 % to be entered by the Biders
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .