MTPS I BM AOH 2025 Unit IV Boiler pressure parts Cutting and removing of heavily worn out CRH and HRH tubes roof plate and fabrication and erection of new HR Sheet and allied works in the penthouse area at 52 mtr level
1) Partial repairing and reconditioning 2000 GPM, single stage, spilt case, 250mm x 200mm size, UP-200/56 type pump assembly, Sl.no.-1748918012 pump in respect of JOCP 2) Modification/fabrication of base frame of one no. 1000 GPM pump installed at m
Modification & fabrication of Base frame FOR2
Repairing of final drive tandem 03 nos brake assy, blade assy and its holes, its both adjuster, bushing and fabrication of 04 nos edge, edge side and bit end, fuel tank foundation, collar, both brackets, in the Motor grader G4 at Ashok OCP.
Repairing of blade assembly and its holes, both adjusters, bushings, and fabrication of 04 nos. edge, edge side and end bit; repairing of fuel tank foundation, collar, and both brackets of BG825 Motor Grader G4 at Ashok OCP.
Repairing of winding engine drum brake and other allied fittings at Pit No. B and fabrication and fitting of 4 set of GM bushes for cross head piston cylinder at pit no. A for safe and smooth winding operations under Pandaveswar colliery, Pandaveswar
Repairing of winding engine drum brake and other allied fittings at Pit No. B and fabrication & fitting of 4 set of GM bushes for cross head piston cylinder at pit no. A for safe and smooth winding operations under Pandaveswar colliery, Pandaveswar area. (Inclusive of EPF/CMPF)
MTPS I Mill Plant Unit IV Hard facing of MS bend and multiple port outlets in coal flow lines Fabrication of MS bend 15 22 deg to suit dia 508 mm 12 7 mm thick coal pipe line during AOH 2025 26
Charges for fabrication of 15º, 22º,10º bend including marking, the segments from straight pipe, gas cutting, ‘V’ groove forming grinding & welding the segments together (Pipe supplied by TNPGCL)
MTPS I Mill Plant Unit III Dismantling the damaged Mill outlet Elbows Orifices Transition pieces fabrication of spool pieces Mill port outlet 90deg bend and renewing with new from Coal mill outlet up to Mill floor in coal mill 3A 3B 3C 3F
Charges for dismantling the Spool pieces, multiple port outlet bodies and transition pipes 4 Nos. each after assembling the coal pipe inspection with center feed pipe structures including transportation of supporting material from stores to site and re-fixing the Spool piece, MPO bodies and transition pieces and assembling to its original position and carrying out necessary related works. and devolution of scraps to stores etc. for a mill.(3B , 3C & 3F)