Work title and location
Provision of Sewage Treatment Plant (STP) at Bhaduriya Complex under GE (South) Pathankot (CA No. CEPZ-20/2025-26); executing agency GE (South) Pathankot.
- Schedule ‘A’ item locations name 75 KLD plant at Vijender Vihar Md Accn and 50 KLD plant at Unit 2/1 GR under GE (South) Pathankot—confirm exact sites vs title (see contradictions/pre-bid).
Plant capacities and technology
Design, supply, installation, testing and commissioning of two underground 100% FRP package STPs—75 KLD (1 No) and 50 KLD (1 No)—with built-in manholes/covers, mechanical/electrical works and tertiary treatment; contractor free to use any suitable technology subject to specified constraints; designs/working drawings to be IIT/NIT vetted and Accepting Officer approved.
- Also SCADA for each STP and CPRI-approved LT cubicle panels (BOQ items 1–6).
- BOQ/PS/layout/hydraulic/P&I drawings are tentative/guidance; contractor responsible for detailed design and complete electro-mechanical installation.
- Exposed piping SS-304; pipes under sewage UPVC Schedule 80.
- Raw sewage data to be collected by contractor and NABL-lab approved before design.
Treated sewage performance standards
Treated sewage to meet CPCB-2026 standards as specified: pH 6.5–8.3; COD <50 mg/L; BOD <10 mg/L; TSS <10 mg/L; TN 10 mg/L & TP 1 mg/L; fecal coliform Nil; no foul odour; ammoniacal N ≤5 mg/L; total N ≤10 mg/L.
- Treated water testing by SPCB or SPCB/NABL-approved lab required before completion; GE issues completion only after successful testing by IEM or Accepting Officer rep.
- Performance guarantee retained (see financials); performance test under design conditions with 72-hour average.
Associated civil & services scope (BOQ Parts)
Besides STPs/SCADA, BOQ covers building works, internal W/S, plumbing, internal electrics, earthwork, roads/paths, fencing/gates, area drainage, external electrics, external W/S, sewage disposal, miscellaneous items (18–47), then M&O of STP/SCADA (48–53) and comprehensive maintenance (54–57).
- Type of contract: drawings & specifications (IAFW-2159) with GCC IAFW-2249; lump sum for parts of Schedule A and rates for other parts; BOQ Excel to be priced online.
- Includes working in running sewage lines/foul conditions and connecting to existing lines (deemed in quote).
- Training of operational staff 4 weeks during DLP included in cost; as-built drawings and O&M manuals required.
Phased completion and long-term O&M
Phase I DPR (90 days from site handover); Phase II construction of BOQ 1–47 (6 months after Phase I); then multi-year manning/operation and comprehensive maintenance through Phase VIII; DLP 24 months on Phase II (comprehensive maintenance during DLP at no extra cost) and 1 month after each M&O phase.
- Separate work orders for each phase; comprehensive maintenance includes repair/replacement of equipment, plant and civil infrastructure.
- NIT headline duration: 6 months main + 96 months M&O/CM = 102 months (cross-check phased table—see contradictions).
Applicable standards / references
Work per Schedule A, particular specifications, drawings, MES Schedule (SSR), IAFW-2159/2249; where PS silent, relevant IS/code of practice; Acts/Rules/bye-laws and Government enactments binding; treated water to CPCB-2026 parameters.