The Executive Engineer
Restoration work in Panchtalav Distry (LD-16) and Italiya Distry (LD-18) under the command area of Limbdi Branch Canal for Year 2025-26.
280068
51 of 2025-26
Open
Civil Works - Canal
Works
Surendranagar
6 documents required · 6 mandatory
₹4,248
Yes
Executive Engineer SBC Dn No.4/1 Limbdi
₹1.3 L
Yes
24 Feb 2026
24 Feb 2026
24 Feb 2026
16 Mar 2026
24 Feb 2026
BILL OF QUANTITIES
BILL OF QUANTITIES
1. The bill of Quantities shall be read in conjunction with the Instructions to Bidder,
Conditions of Contract, Technical Specifications and Drawings.
2. The quantities given in the Bill of Quantities are estimated and provisional and are
given to provide a common basis for bidding. The basis of payment will be the actual
quantities of work ordered and carried out, as measured by the Contractor and verified
by the Engineer and valued at the rates and prices tendered in the priced Bill of
Quantities, where applicable, and otherwise at such rates and prices as the Engineer
may fix within the terms of the Contract.
3. The rates and prices tendered in the priced Bill of Quantities shall, except in so far as it
is otherwise provided under the Contract, include all construction plant, layout,
supervision, materials, erection, maintenance, insurance, profit, taxes and duties,
together with all general risks, liabilities and obligations set out or implied in the
4. The rates and prices shall be quoted entirely in Indian Currency.
5. A rate or prices shall be entered against each item in the Bill Quantities, whether
quantities are stated or not. The cost of Items against which Contractor has failed to
enter a rate or price shall be deemed to be covered by other rates and prices entered in
the Bill of Quantities (in case of Item rate contract).
6. The whole cost of complying with the provisions of the Contract shall be included in
the items provided in the priced Bill of Quantities, and where no Items are provided
the cost shall be deemed to be distributed among the rates and prices entered for the
related items of Work.
7. General direction and descriptions of work and materials are not necessarily repeated
or summarized in the Bill of Quantities. References to the relevant sections of the
contract documentation shall be made before entering rates or prices against each item
in the Bill of Quantities.
8. The method of completed work of payment shall be in accordance with the
specification for canal work Road and Bridge works. For building works
specifications for building are to be followed.
9. Errors will be corrected by the Employer for any arithmetic error pursuant to Clause
29 of the Instructions to Bidder.
10. Rock is defined as all materials which, in the opinion of the Engineer, required
blasting, or the use of metal wedges and sledgehammers, or the use of compressed air
drilling for its removal, and which cannot be extracted by ripping with a tractor of at
least 150 kw with a single rear mounted heavy duty ripper.
BILL OF QUANTITIES
(A) Percentage Rate Tender (Up to INR 50 Cr.)
Name of Division: Executive Engineer, S.B.C. Dn. No. 4/1, Limbdi.
Name of work: - Restoration work in Panchtalav Distry (LD-16) and Italiya Distry (LD-18)
under the command area of Limbdi Branch Canal for Year 2025-26.
Description Quantity Unit Rate Amount
Earthwork/Backfilling with selected earth
brought from outside borrow area or from
1 excavated useful material incl. watering 11266 Cum 141.00
ramming compaction with pneumatic temping
and all lead and lift etc. complete.
Excavation in all sort of strata and formations
incl. depositing the unuseful excavated stuff
as and where directed incl sorting and
stacking useful materials as directed up to 30
mt lead etc. complete incl. dewatering. (Depth
0 TO 3.0 mt ) (For all type canal &
foundation trenches of C.D. works) A) IN
OVERBURDEN INCL. HARD MURRUM
Dismantling the existing cement concrete
3 lining including removing the debris etc. 3192.00 Sq.mt 83.65
comp. as and where directed
Providing and Laying in position "Nominal
Mix" Cement Concrete Lining in Bed, Side
Slopes and curvature including batching,
mixing, transporting, placing, vibrating,
smooth finishing, membrane curing (by
curing compound only) & providing bitumen
joints at specified interval including minor
4 filling/depression with murrum / earth / soil 3001.00 Sq.mt 372.43
as per site condition to correct profile,
watering, compaction, trimming etc. to
provide lining.
For 7.5 cms thick cast-in-citu canal lining in
Concrete grade 1:2:4 with Cement level-300
kg & MSA-20 mm (Without Using Paver
Machinaries & without sleepers)
Providing and Laying in position "Nominal
Mix"Cement Concrete Lining in Bed, Side
Slopes and curvature including batching,
mixing, transporting, placing, vibrating,
smooth finishing, membrane curing (by
curing compound only) & providing bitumen
5 joints at specified interval including minor 838.00 Sq.mt 496.57
filling/depression with murrum / earth / soil
as per site condition to correct profile,
watering, compaction, trimming etc. to
provide lining.
For 10 cms thick cast-in-citu canal lining in
Concrete grade 1:2:4 with Cement level-300
kg & MSA-20 mm (Without Using Paver
Machinaries & without sleepers)
Providing, cutting, bending, binding and
fixing in position as per drawing. TMT BAR,
Fe-415 reinforcement for R.C.C. works and
anchor bars incl cost of black annealed 16 to
18 BWG M.S. Wire etc. complete with all
Prov. and Laying in position "Nominal Mix "
cement concrete using cement, sand and
crushed aggregate by mass and machine mix
for R.C.C/CC work including necessary
7 formworks centering scaffolding compaction 299.00 Cum 4303.00
by vibrator, curing as directed with all lead &
lift etc complete Excluding the cost of
reinforcement (For Plinth course & Coping)
A) Concrete grade 1:2:4 and MSA-20mm
Providing, supplying, Lowering, and laying
ISI Standard R.C.C. NP-3 Class pipes in
standard lengths of following Diameter
suitable for either collar joints or rubber ring
joints including all taxes, insurance,
transportation, freight charges, octroi,
inspection charges, loading, unloading,
conveyance to Site, and jointing in proper
position, grade and alignment at all level as
directed by Engineer-in-charge including all
labour, giving hydraulic testing as per ISI
code. (G) 900 mm dia.
Providing & laying dry rubble stone pucca
pitching with panel (of size not more than
10sqmt) of stone masonry 45cm thick wall in
C.M. 1:5, without base , inverted filter and
header stone but with 10 cms thick murrum
layer (for base ) incl hand packing and
trimming and dressing slopes etc. a) 45 cms
thick stone pitching with pointing in C.M. 1:2
Hand broken stone aggregate 40mm size to
63mm size. Including Spreading the stone
aggregate for rolling and W.B.M. including
filling the interstices to required camber and
gradient (excluding spreading of Blindage)(ii)
40mm to 63mm size aggregates (H.B.)
Total Amount Rs.
Total Amount Rs.
I/We am/are willing to carry out the work at… ....................... %above/below percent(Should
be written in figures and words) of the estimated rate mentioned above. Amount of my /our
tender works out as under.
Estimated amount put to tender Estimated amount put to tender
Deduct………%below Add………%Above
In words In words
(B) For Item Rate Tender (For above INR 50 Cr.):
Item Description of Item(with Quantity Unit Rate Amount
No brief specification and
reference to book of In In
specifications) figures Words
(A)Total Tendered Amount
(B)Rebate on above tendered amount (if any) % (in figure)
(C)NetTendered Amount(A-B) (in figure) ………………………………
1 The Contractor shall exhibit a board with detailed specification and details of work as
directed by the Engineer-In-Charge for which no extra payment shall be made.
2 The labour cess will be deducted as per prevailing rules i.e. 1% of the work done.
3 GST and Income tax TDS will be deducted at a source while making payments of bills
4 In all P.C.C./R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as
per vernacular office letter no. 04 of 2024, Dt. 20/01/2024 of The Chief Engineer, Quality
Control (SSNNL) as stated in S.O.R. therefore in P.C.C./R.C.C. items where there is a change
as per Nominal mix the cost of difference of cement consumption have been deducted from
the rate of original item at the rate of input rate (i.e. 5448.53 Rs / MT for OPC) in all the
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
SBD Restoration work LD-16 LD-18.pdf
MO Sheet Restoration work LD-16 LD-18.pdf
BOQ.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .