Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹87.3 L
EMD Value
₹4.4 L
Closing Date
21 Oct 2026, 3:00 pm
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Chief Engineer
LDA Gomti Nagar Lucknow
Gomti Nagar Vistar Yojna isthit Janeshwar Park evam river view ke samantar chatigrast 24 mtr tatha sharda apartment se rohini apartment ke peeche 18 mtr road ke sudharikaran ka karya
2026_LDAUP_1194747_1
113/E-Nivida/CE/2026-27_11
Open Tender
Civil Works
Percentage
60 days
Lucknow
Please refer Tender documents.
3 documents required · 3 mandatory
₹4,366
Secratary LDA
₹4.4 L
9 Oct 2026
9 Oct 2026
22 Oct 2026
9 Oct 2026
21 Oct 2026
9 Oct 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5 m in width as well as 10 sqm on plan including getting out and disposal of excavated earth upto 50 m and lift up to 1.5 m, as directed by Engineer-in-Charge:, All kinds of soil | 5.96 | Cum | 102.58 | ₹611.68 |
| 2 | Mild steel or iron work in plain work such as in R.C.C. or R.B. (when not included in an over all rates ) including bending for proper completion of the work and including supply of steel and its wastage , bends, hooks and authorized overlaps shall be measured for development work. | 1.69 | Qtl | 7,150 | ₹12,083.5 |
| 3 | Centering and shuttering including strutting, propping etc. and removal of form for :, Centering and shuttering including strutting and propping and removal of items for: Foundations, footings, base of columns, etc DSR 2023/5.9.1 | 17.93 | Sqm | 309.78 | ₹5,552.81 |
| 4 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level :, 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) | 2.15 | Cum | 7,145.72 | ₹15,370.44 |
| 5 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth in:, Cement mortar 1:4 (1 cement : 4 coarse sand) | 2.31 | Cum | 5,822.47 | ₹13,444.08 |
| 6 | Scarifying metalled (water-bound) road surface including disposal of rubbish, lead upto 50m and consolidation of the aggregate received from scarifying with power road roller of 8 to 10 tonne capacity. | 214.05 | Sqm | 26.31 | ₹5,631.66 |
| 7 | Construction of granular sub-base by providing well graded matarial, spreading in uniformlayers with motor grader on prepared surface ,mixing by mix in place method with rotamator at OMC and compacting with smooth wheel roller to achieve the desired density ,complete as per technical specification clause 401 | 113.51 | Cum | 4,185 | ₹4,75,047.72 |
| 8 | providing, laying ,spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mix plant carriage of mixed material by tipper to site ,laying in uniform layers with paver in sub base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density . | 413.51 | Cum | 4,210 | ₹17,40,885.52 |
| 9 | Providing and laying bituminous macadam (B.M.) with 100-120 TPH hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading premixed with bituminous binder @3.30%, transported to site, laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled as per clauses 501.6 and 501.7 to achieve the desired compaction (Sanction Rate) | 69.75 | MT | 5,126 | ₹3,57,518 |
| 10 | Semi-Dense Bituminous Concrete (S.D.B.C.) (Using Water Plastic) providing and laying Semi-Dense Bituminous Concrete with 100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 5 per cent mix to work at site as per MORTH & H specification clause No. 508 complete in all respects(Reducing Bituminous Quantity by 8% and replacing it by Plastic wastage as per IRC : SP: 98-2013) (Sanction Rate) | 801.75 | MT | 6,185 | ₹49,58,823.75 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 4.97 MB
BOQ_2255650.xls
BOQ • 0.28 MB
T_2.pdf
Tender Documents • 9.72 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .