| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹17.5 LAccepted-AOC SHAZIYA MANZIL PUTHALAM AREACODE 673639 | MALAPPURAM | KERALA | 673639 | L1 | Accepted-AOC L1 | |
| 2 | L2₹18.5 L+₹96,607.79 (5.50%)Rejected-AOC VALAYIL HOUSE ATHAVANAD P O MALAPPURAM 676301 | MALAPPURAM | MALAPPURAM | KERALA | 676301 | L2 | Rejected-AOC L2 | |
| 3 | Rejected-Technical N M 3 638 VP BUILDING | - | Rejected-Technical Tender fees not remitted . Hence rejected |
Tender Value
₹16.1 L
EMD Value
₹40,252
Closing Date
28 Feb 2025, 3:00 pmClosed
EXECUTIVE ENGINEER
PWD BUILDINGS DIVISION MALAPPURAM
GENERAL General Education Department Annual plan 2023 24 Construction of Compound Wall in GHS Munderi in Nilambur Constituency General Civil Work
2025_PWD_740905_1
BL/DN/MPM/39/2024-25
Open Tender
Civil Works - Buildings
Item Rate
malappuram
Please refer Tender documents.
8 documents required · 8 mandatory
₹2,760
Yes
₹40,252
Yes
2 Apr 2025
20 Feb 2025
3 Mar 2025
20 Feb 2025
28 Feb 2025
20 Feb 2025
Amount
GHS MUNDERI NILAMBUR
15.7.1:Demolishing brick work manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-Charge.In mud mortar
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
2.26.1:Extra for every additional lift 1.5 m or part there of in excavation / banking excavated or stacked materials.All kinds of soil
2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
OD153689/2024-2025:Dry rubble mansonry with hard stone in foundation and plinth
5.1.3:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
5.9.5:Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
50.6.7.1:Laterate masonry with neatly dressed laterate stone of size 40x20x15cm or nearest size in cement mortar 1:6 for foundation and basement including all cost of materials, labour charges etc.
50.6.1.7:Solid block masonry using pre cast solid blocks ( Factory made) of size 40x20x15cm or nearest available size confirming to IS 2185 part I of 1979 for foundation and plinth with thickness 15 cm in : CM 1:6 ( 1 cement : 6 coarse sand ) etc complete
13.4.1:12 mm cement plaster of mix:1:4 ( 1 cement : 4 coarse sand)
13.46.1:Finishing walls with Acrylic Smooth exterior paint of required shade:New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied @ 2.20 kg/10 sqm)
2.25:Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
14.75:Repair to plaster of thickness 12mm to 20 mm in patches of area 2.5 sqm and under, including cutting the patch in proper shape, raking out joints and preparing plastering the wall surface with white cement based polymer modified self curing mortar, including disposal of rubbish, all complete as per the direction of Engineer-In-Charge.
V. LIYAKATHALI (BID ID -2130889)
V. JAYAFAR (BID ID -2130913)
Bidder Name
V. JAYAFAR
V. LIYAKATHALI
Nilambur Taluk Labour Contract Co-operative Society Limited
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .