Loading…
Loading…
Tender Value
₹15.8 L
EMD Value
₹47,318
Closing Date
20 Jul 2026, 6:00 pm
CHIEF ENGINEER (G)
Construction of Kitchen & renovation of GF toilet at KH bungalow at GSECL, Gandhinagar TPS
305251
EW-283
Open
Miscellaneous Works
Gandhinagar
2 documents required · 2 mandatory
₹1,770
Gujarat State Electricity Corporation Limited Payable at Gandhinagar
₹47,318
20 Jul 2026
20 May 2026
27 Jul 2026
20 May 2026
20 Jul 2026
20 May 2026
1. SECTION-A:
ACKNOWLEDGEMENT OF TENDER FEE /EMD.
TENDER NOTICE.
2. SECTION-B:
DECLARATION FORM CUM UNDER TAKING TO BE SIGNED
RTGS DETAILS OF BIDDER
PROJECT SYNOPSIS
SCOPE OF WORK AND SITE CONDITION
SPECIAL NOTE FOR PRE-QUALIFICATION
GENERAL INSTRUCTION TO THE TENDERER
3. SECTION-C:
GENERAL CONDITIONS OF CONTRACT
4. SECTION-D:
TERMS AND CONTRACT FOR WORKS
GENERAL SAFETY RULES & LIST OF SAFETY TOOLS
5. SECTION-E :
PERFORMA FOR BANK GUARANTEE
INTEGRITY PACT
CERTIFICATE – A
ANNEXURE – I (DETAILS OF BANK FOR SOLVEANCY & BG)
6. SECTION-F:
SPECIAL CONDITIONS FOR USE OF CEMENT
APPROVED NAME OF MANUFACTURERS OF
STEEL / CEMENT
GENERAL GUIDELINES RELEVANT TO I.S.
7. SECTION-G:
GENERAL SPECIFICATIONS
TECHNICAL SPECIFICATION
DETAIL SPECIFICATION
8. SECTION-H:
SCHEDULE-B
Safe Maintenance Procedure
EW- 283 PUR-F-006 RFQ-
ACKNOWLEDGEMENT OF TENDER FEE /EMD
TENDER NOTICE
EW- 283 PUR-F-006 RFQ-
GUJARAT STATE ELECTRICITY CORPORATION LIMITED
Gandhinagar Thermal Power Station, Gandhinagar, India–382041.
Ph. 91-79-23215663Fax: 91-79-23217673, e-mail:
[email protected] Website: www.gsecl.in
CIN:U40100GJ1993SGCO19988
ACKNOWLEDGMENT
e- Tender for the
“Construction of Kitchen & renovation of GF toilet at KH bungalow at GSECL,
Gandhinagar TPS.”
TENDER FEE PAID VIDE DEMAND DRAFT NO. _________________________________
DATED___________________________ RS. __________________________________
EARNEST MONEY DEPOSIT PAID VIDE D.D. NO. _______________________________
DATED ____________________ RS. _____________________
1. The undersigned reserves the right to reject any or all tenders without
assigning any reasons thereof.
2. The Tender fee will be accepted in form of Demand Draft and Earnest Money Deposit
will be accepted in form of Demand Draft or Bank Guarantee of any bank as prescribe in
ANNEXURE- I drawn in favour of “GUJARAT STATE ELECTRICITY CORPORATION
LTD.” payable at Gandhinagar TPS
Chief Engineer (Gen)
Signature Of Contractor GSECL: GTPS
EW- 283 PUR-F-006 RFQ-
GUJARAT STATE ELECTRICITY CORPORATION LIMITED
Gandhinagar Thermal Power Station, Gandhinagar, India–382041.
Ph. 91-79-23215663Fax: 91-79-23217673, e-mail:
[email protected] Website: www.gsecl.in
CIN:U40100GJ1993SGCO19988
Tender Notice No: GSECL/___/ __/ For Civil works
CE [Generation], Gandhinagar, TPS invites “On-line Tenders” (e-tendering) for the work of
“Construction of Kitchen & renovation of GF toilet at KH bungalow at GSECL,
Gandhinagar TPS.” Tender Papers & Specifications may be down loaded from Web site
https://gsecl.nprocure.com(For view, down load and on line submission) and GUVNL / GSECL
web sites www.gsecl.in (For view only).All tender documents are to be upload (Notarized / self-attested
copies of original – as specified in tender document) through online only (mandatory) on (n) procure portal
excluding Tender fee and EMD Tender fee and EMD are to be submitted physically by Registered Post A.D.
or Speed Post addressed to: CHIEF ENGINEER (GENERATION), GUJARAT STATE ELECTRICITY
CORPORATION LTD, THERMAL POWER STATION, GANDHINAGAR-382041, GUJARAT. “NO
COURIER SERVICE OR HAND DELIVERY” will be accepted.
Tender Estimated E.M.D.
No. Cost Rs. Rs.
“Construction of
EW-283 Kitchen & Rs. 1577234.89 04 (Month) Rs. 1500+ 270 Rs.
renovation of GF (In word Rupees Months (18% GST) = (Rupees Forty
toilet at KH Fifteen Lac from the Rs. 1770/- Seven
bungalow at Seventy Seven date of (Rupees One Thousand
GSECL, Thousand Two written Thousand Three Hundred
Seven Eighteen Only)
Gandhinagar Hundred Thirty order to
TPS.” Four and Eighty commence Hundred
Seventy (Non
Nine paisa only.) the work.
Refundable)
180 Days [From the opening of
1 Validity of Tender
Technical Bid].
Last Date for Online tender / offer submission through
2 As per Tender Notice
(n)Procure only up to 18:00 Hrs(This is Mandatory)
Last Date for physical receipt of cover for DD / Bank Guarantee
3 / Online payment reference for Tender Fee and EMD only up to As per Tender Notice
15:00 Hrs Through RPAD or Speed Post Only
Date of opening of online Technical Bid, all relevant documents
submitted through online process, Cover for Tender fee and
4 As per Tender Notice
EMD at 15:30 Hrs (Online technical bid will be opened for
Bidders who have submitted Cover for Tender Fee and EMD)
Tentative date of on-line opening of price bid (if possible) at Party has to be in touch with
15.30 hrs. website www.nprocure.com and
also with e-mail sent by above
Chief Engineer (Gen)
Signature Of Contractor GSECL: GTPS
EW- 283 PUR-F-006 RFQ-
1) Only following listed documents must be upload in n-process online only. No physical documents are to be
submitted except tender fee and EMD cover. Price Bid shall not be submitted in Hard copy.
1. Demand Draft for Tender Fee and EMD (Original) cover only to submit through RPAD/Speed post only.
2. The bidder shall have a separate Provident Fund Code of RPFC in the name of company. The bidder, who
does not possess such separate P.F. code, shall not be considered for acceptance of tender. The contractor
has to submit attested copy of such certificate showing P.F. code along with the tender.
3. Attested copy of PAN No.
4. Attested copy of work experience certificate for the similar works executed.
5. List of work in progress.
6. Attested copy of firm registration [Applicable only to the firms registered under Company Law]
7. Attested copy of partnership deed. [Applicable only to the partnership firms.]
8. Attested copy of power of attorney, if any, for signing the bid document.
9. Attested copy of balance sheet of profit & Loss account duly audited by Chartered Accountant of at least
financial years, if work estimate is more than Rs. 50 Lacks.
10. Attested copy of latest solvency certificate not older than 12 months issued by any nationalized bank OR
Banks as per Annexure – I.
11. Details of equipment, tools and plants immediately available with the tenderer for use of this work.
12. Details of technical personnel.
13. Undertaking duly Notarized as per attached Declaration Form
14. Any other documents required to verify technical, financial capability of the bidders & other Credentials
15. Attached The Copy Of GST Registration.
All such documents should be strictly uploaded in N-procure only expect Tender Fee and EMD details cover.
Otherwise the offer will not be considered and no any further communication in the matter will be
entertained.
2) In case any deviation is found in Data / Details / Documents uploaded on N-procure online offer (e-tendering)
documents then such tender will not be considered and no any further communication in the matter will be
entertained. Tenders must be un-conditional. Conditional Tenders will be rejected.
3) Further bidders are requested to submit Technical Bid documents and price – bid i.e. Schedule-B on line only
and not to submit the Technical bid and price bid in physical form expect Tender Fee and EMD details cover.
This is mandatory. If Technical bid document and price bid is submitted in physical form expect Tender Fee
and EMD details cover, same will not be opened and only on-line Uploaded/submitted Technical bid document
and price will be considered for evaluation. The bidder is requested not to upload/submit the by
online (n)procure while bid submission on in (n)procure tender document, condition of the
contract, specification & other relevant documents, except documents as stated here above.
Instead of the same, the bidder shall upload on (n) procure scan copy of the duly Notarized Undertaking as
stated below declaration form on the stamp paper of Rs. 300/-. However, bidder may download tender
document & preserve with them in Hard Copy for their future reference. Later on, L1 bidder shall
be asked to collect the tender documents from the tender inviting authorities for the purpose of
contract agreement execution and place their signature with seal of the company.
4) It is mandatory for all the bidders to submit their tender documents viz. on-line (e-tendering) and uploading
on (n) procure in scheduled time. Tender documents submitted in physical form will not be accepted and
considered expect Tender Fee and EMD details cover. Also, all bidders shall submit required Physical
documents as stated in Tender Notice
5) GSECL reserves the rights to reject any OR all tenders without assigning any reasons thereof.
6) Tender Notice Number & name of the work shall be clearly written on the covers of containing the Tender Fee
7) Technical / Price Bids will be opened on the day and time indicated in the tender notice by an Officer nominated
by the Purchaser in the presence of such of the bidders who wish to be present. Any technical questions,
information and clarifications that may be required pertaining to this tender should be referred to the CHIEF
ENGINEER (GEN.) Gandhinagar TPS. Also during pre-bid meeting (if arranged) the same may please be
The exemption in payment of Tender Fee & EMD shall be given to the,
1. Micro & small-scale enterprises which participate directly in tendering process
for the product which they are manufacturing / service which they are
providing and have Udyam registration for items / service under procurement.
2. Startups which participate directly in tendering process for the product which
they are manufacturing / service which they are providing and recognised by
DPIIT under the Start-up India Program and has obtained Udyam registration.
3. Organization which has registration certificate for the manufacturing product of
EW- 283 PUR-F-006 RFQ-
the tender, from Gujarat Khadi Gramodyog Board or Khadi and Village
Industries Commission(K.V.I.C)or Commissioner of Cottage Industries.
4. Board/Corporations/PSUs of the Central/State Government for their own
manufactured items.
5. State Government recognized organizations like(i) organizations for blinds,
dumb and deaf, disabled, mentally disabled persons;(ii)women's self-help group
recognized by Gujarat Livelihood Promotion Company; which participate
directly in tendering process for the product which they are manufacturing /
service which /they are providing.
1. Micro & Small Enterprises (MSEs) who participates directly in the tendering
process as Manufacturers or Service Providers, and holds a valid Udyam
Registration, are eligible for exemption from payment of Earnest Money Deposit
2. Agencies registered under Udyam in the capacity of Traders, Re-sellers, or
similar categories (i.e. other than Manufacturers/Service Providers) are not
eligible for EMD exemption.
3. Migration period for Reclassification of MSMEs: - ln case of an upward change
in terms of investment in plant and machinery or equipment or turnover or
both, and consequent re-classification, an enterprise shall continue to avail of
all non-tax benefits of the category (micro or small or medium) it was in before
the re-classification, for a period of three years from the date of such upward
Chief Engineer (Gen)
Signature Of Contractor GSECL: GTPS
EW- 283 PUR-F-006 RFQ-
DECLARATION FORM CUM UNDER TAKING TO
BE SIGNED BY BIDDER
RTGS DETAILS OF BIDDER
PROJECT SYNOPSIS
SCOPE OF WORK AND SITE CONDITION
SPECIAL NOTE FOR PRE-QUALIFICATION
GENERAL INSTRUCTION TO THE BIDDER
EW- 283 PUR-F-006 RFQ-
(To be uploaded on (n) procure online process duly notarized on Rs. 300/- Non –
Judicial Stamp Paper)
DECLARATION FORM
Gandhinagar TPS.”
Tender No/ RFQ No:
1. I/We hereby declare that I/We have carefully studied the entire tender placed on the
WEB site and conditions of contract, specifications and other documents of this work
mentioned in the tender and abide by the same. Also, I/We hereby agree to execute the
same accordingly.
2. I/We hereby abide to execute the contract agreement by downloading the copies of the
conditions of contract, specifications and other documents of this work of otherwise I/we
will be acceptable to me/us.
3. I/We hereby accept and confirm that any dispute on this regard shall not be entertained
4. I/We hereby declare that I/We have visited the work site and fully acquainted
myself/ourselves with the local situations regarding materials, labour and other factors
pertaining to the work before submitting the tender.
5. I/We hereby confirm that our offer is Un-conditional and without any technical &
commercial deviations.
6. Should this tender be accepted, I /We hereby agree to abide by to fulfill all the terms-
conditions and provision of the Tender and Contract for Works as applicable and default
thereof, to forfeit and to pay to the Gujarat State Electricity Corporation Limited the
sums of money due.
EW- 283 PUR-F-006 RFQ-
7. The full value of the “Earnest Money Deposit” paid herewith should be absolutely
forfeited to the Corporation, should I/ we do not execute / commence the work after
issuance of date of commencement by GSECL.
8. If, I fail to submit all required documents with application or tender copy ( in each
tender ) then my tender will be cancelled, which is binding to me.
9. If, full or part work will be given to me, it will be accepted to me with same terms, rate
& conditions.
10. I, ______ proprietor / owner / partner / Authorized Agent of M/s. ______ do hereby also
declare and undertake as under:
a) That in capacity of independent contractor for M/s. ______ (Sub-Contractor of
M/s. ______ ) worked as contractor at GSECL, ___________Thermal Power Station for
the nature of work of ______ against work Order No. ______ Dt. ______., I have
complied with the provisions of all laws as applicable. I have paid the wages for the
month/s of my contractual period which is / are not less than the minimum rates as
applicable, to all my employee/s and no other dues are payable to my employee/s.
b) That I have covered all the eligible employee/s under the Employees’ Provident
Funds and Miscellaneous Provisions Act, 1952 and deposited the contributions under my
PF Code No. ______, place: ______ for the month/s of my contractual period and as
such no amount towards contribution whatever is payable.
c) I further declare and undertake that in case any liability pertaining to any of my
worker, labour, employee/s is/are to be discharged by the principle employer i.e.
Gujarat State Electricity corporation Limited, ___________Thermal Power Station due
to my lapse, I undertake to reimburse the same or the principle employer is authorized
to deduct the same from my dues as payable.
d) I further declare and undertake the legal consequences which may arise in future
under the said work order awarded, and I bond myself to resolve the same at the risk
and cost of M/s. ______.
authorized signatory of M/s ______________________________________________
here by certify that M/s _________________________________________________
and their proprietor / any partner / any directors of the firm is not stop deal and / or
banned for business dealing and / or black listed by GUVNL and / or their any
subsidiary company viz. GSECL / GETCO / DGVCL / MGVCL / UGVCL / PGVCL as well as
Government and / or Semi Government company / department.
Seal & Signature of the Bidder
Phone / Mobile/ Fax No. & Company’s Seal
EW- 283 PUR-F-006 RFQ-
e- Tender for the work of “Construction of Kitchen & renovation of GF toilet at KH
bungalow at GSECL, Gandhinagar TPS.”
RTGS DETAIL OF BIDDER
Following RTGS details shall be submitted by agency along with the tender for direct deposit of
payment to the beneficiary account. Bidder has to submit the details as under:
1 Name of Bidder :-
2 Address for correspondence :-
3 E-Mail ID :-
4 Phone / Mobile No. :-
5 Name of Beneficiary :-
6 Bank Account Number of :-
beneficiary
7 Name of Bank of beneficiary :-
8 Name of Bank, branch & address :-
9 Type of account :-
10 Bank Code :-
11 RTGS Code :-
12 IFSC Code :-
EW- 283 PUR-F-006 RFQ-
Project Synopsis and Data
1) Location :- Gandhinagar Thermal power station
2) Purchaser :- GUJARAT STATE ELECTRICITY CORPORATION LTD
3) Engineer :- Chief Engineer(Gen)
4) Site of Project :- Gandhinagar,Gujarat State
5) Nearest town :- Gandhinagar
6) Nearest Railway Station :- Gandhinagar Capital(Ahmedabad is situated at a
distance of about 30.00Km)
7) Nearest Port :-
8) Nearest Air Port :- Ahmedabad-20Km(Approx)
9) Access Road :-
10) Site Elevation from MSL :- RL 81.5 M(floor level)
11) Meteorological Data
Ambient Air temperature
1] Highest monthly mean of daily Max. :- 35 C
Temperature ( In C)
2] Maximum dry bulb :- 45 C
Temperature ( In C)
3] Minimum dry bulb :- 8.6 C
Temperature ( In C)
Rainfall
1] Average annual rainfall (In mm) :- 1000 to 1200mm
2] For 01 hour ( In mm) :- 75 to 100mm
3] For 24 hour ( In mm) :- 250mm
Wind velocity
1] Maximum wind velocity (In m/sec) :-
2] Wind direction – N,NE & SW :-
3] For 24 hour ( In mm) :-
Relative Humidity
1] Annual mean humidity ( In %) :- 50 to 60%
2] Maximum humidity (In %) :- 98%
3] Minimum humidity (In %) :- 2%
4] Type of Atmosphere :- Dry
12) DESIGN DATA
Seismic Data :-
Zone :- Zone-III as per IS 1893-1975
Intensity :-
Ambient temperature :-
Other Data :-
EW- 283 PUR-F-006 RFQ-
SCOPE OF WORK AND SITE CONDITIONS
The main scope of the work is “Construction of Kitchen & renovation of GF toilet at KH
bungalow at GSECL, Gandhinagar TPS.”. The item work shall be carried out as per item
specification and as directed by E.I.C. includes all required materials, tools, tackles, and
required safety precautions for success completion of work.
Under the scope of this tender the agency has to carry out the subject work as per all items of
Schedule B and as per detail technical specification items. The quantities taken under
individual items are very tentative. However the agency has to carry out the works as and
when required & as per the Company’s requirements.
The agency has to carry out the works as per the priority & schedule given by EIC time to time
even in on or off working hours of the office. The agency will take complete care and will not
damage any other structure in premises of company.
The agency has to carry out all the works by taking all due cares of safety, security norms,
with all risks including scaffolding, strutting, shoring, etc up to any height irrespective of
quantum of the work.
Contractor has to make arrangement for workable site condition with the co operation of
departments of company and agencies, all necessary arrangement to get work permit is to be
made by contractor. Day to day cleaning is required after completion of job. The removed
materials and any other unwanted materials are to be transported and taken away as
instructed by E.I.C.
All safety measures shall be taken by the contractor with his own cost.
The scope of work to be carried out by the Contractor shall also include Clearance of the site,
Disposal of debris etc as directed by EIC to complete the work.
The major works involvement generally mentioned as per schedule-B.
Dismantling of tiled, GI sheet, door, window, steel work, RCC etc.
Excavation for foundation upto 1.5 m
Providing & laying 1:3:6
Providing and laying controlled cement concrete M.250 for foundation, column, slab
with formwork.
Providing TMT Bar FE 500/500D reinforcement for R.C.C. work
Brick work using conventional fly ash bricks in foundation and upto floor two level.
Providing 15mm thick cement plaster in single coat on Rough side
20 mm thick sand faced cement plaster on walls upto height 10 metres above
ground level
Steel work, welded in built up sections framed work including cutting, hoisting, fixing
in position
Providing and applying interior & exterior primer & paint to structure/building
Providing and laying Vitrified tiles 8 to 10 mm thick , 24'' x 24'' in flooring
Providing and laying Ceramic tiles 6mm thick in skrting
Providing and laying granite slab of telephone black or as approved by EIC
EW- 283 PUR-F-006 RFQ-
Providing & fixing 30mm th. Water proof flush door shutter - green, donear or
equivalent ISI make
Pro. And fixing single layer water proof gypsum board 12.5 mm thick sections using
water proof board
Providing and fixing extruded three track aluminum window having coloured
anodized section
Providing and constructing sandwich type cooking platform for kitchen
Providing and fixing shutter for kitchen cupboard below platform made of plywood
Providing and fixing ultra slim Drawer System including all channels for drawer slides
and all fittings with 'J' profile Handles with various type of basket
Providing and fixing MULTI FUNCTIONAL PULL-OUT 450mm.
Providing and fixing KITCHEN TALL UNIT (GLASS BASKET)
Providing and fixing Rolling Shutter
Providing laying and jointing in true line and level 15mm dia./25mm U.P.V.C. Pipe.
Providing and fixing Gun metal check or non-return fullway wheel valve.(A) 15mm
dia. & 25mm
Providing and Installation, testing and commissioning of 15 mm dia C.P. Bib tap
Providing and fixing Pillar SWAN NECK TAP, capstan head, screw down high pressure
Providing and fixing table top type wash basin
Providing and fixing wall hung type water closet
Providing and fixing all bathing fixture of Jaquar Brand
Providing and fixing to wall ceiling and floor 10.0 K pipe
Providing, laying and jointing in true line and level 160 diametre U.P.V.C pipe
Providing and fixing PVC SWR Nahni trap IS 14735 for drain - 100 mm diameter
Providing and fixing PVC Waste Pipe for Wash basin of 32 mm dia having 900mm
Providng and laying chine mosaic flooring for terrece using 12 mm to 20 mm broken
Providing and Fixing 6 mm thick Lexan Polycarbonate multi wall roofing sheet
Any item of Civil/Electrical GOG SOR / approved PO/ Rate analysis.
Chief Engineer (Gen)
Signature Of Contractor GSECL: GTPS
EW- 283 PUR-F-006 RFQ-
Registration in VMS System
Additional Note: Vendor gets to register in VMS System through vms.guvnl.com. For
registration following documents are required and mail to [email protected] and
[email protected]. After registration vendor have to upload the invoice in the VMS
system for smooth functioning of payment.
Documents required for Registration:
(1) PAN Copy
(2) GST Certificate Copy
(3) Email ID
(4) Full Name of Vendor
EW- 283 PUR-F-006 RFQ-
SPECIAL NOTE FOR PRE-QUALIFICATION
Gandhinagar TPS.”
The tender documents are of two separate bids i.e. technical and price bids. Bidder is
requested to submit the technical bid with the following credentials for post-qualification.
1. Bidder should produce evidence of having experience of successfully completed of
similar works as defined hereunder, carried out in Central & State Government / Semi-
Government / GSECL / GETCO / DGVCL / MGVCL / UGVCL/PGVCL during the last
seven years ending last day of the month previous to the one in which tender is invited.
Bidder should submit self-attested copies of documentary evidence, preferably photo
copies of work completion certificate, certificate regarding works on hand progressing
satisfactorily along with certificate of amount of work done, work order with Schedule-B,
etc. from the respective department. The amount of work completed should be either of
the following:-
a. Three similar completed works each costing not less than the amount equal to 40%
of the estimated cost.
b. Two similar completed works each costing not less than the amount equal to 50% of
the estimated cost
c. One similar completed works each costing not less than the amount equal to 80% of
the estimated cost
Similar work means – General Civil works related to building construction or building
renovation or civil maintenance work
2. Financial qualification criteria:
1) The Average Annual Turnover of the bidder, shall not be less than 30% of estimate amount during the
preceding three (3) financial years as one date of Techno-Commercial bid opening.
2) Net worth of bidder shall not be less than 100% of the bidder’s paid up share capital as on the last
day of the preceding financial year. In case the Bidder meets the requirement of Net worth based on the
strength of its Subsidiary (ies) and/or Holding company and/or Subsidiaries of its Holding Companies
wherever applicable, the Net worth of the Bidder and its Subsidiary (ies) and/or Holding company and/or
Subsidiary (ies) of the Holding Company, in combined manner should not be less than 100% of their total
paid up share capital. However individually, their Net worth should not be less than 75% of their
respective paid share capitals.
Net worth in combined manner shall be calculated as follows:
Net worth (combined )= (x1+x2+X3)/(y1+y2+y3) X 100, where x1,x2, x3 are individual net worth
which shall not be less than 75 % of the respective paid up share capitals and y1, y2, y3 are
individual paid up share capitals.
3) In case the bidder is not able to furnish its audited financial statements on stand-alone entity basis, the
unaudited unconsolidated financial statements of the bidder can be considered acceptable provided the
bidder further furnishes the following documents for substantiation of its qualification.
Copies of the unaudited unconsolidated financial statements of the bidder along with copies of the
Audited consolidated financial statements of its Holding Company.
A Certificate from the CEO/CFO of the Holding Company, stating that the unaudited unconsolidated
financial statements form part of the Consolidated Annual Report of the company.
EW- 283 PUR-F-006 RFQ-
4) In cases where audited results for the last preceding financial year as on the date of techno-commercial
bid opening are not available, the financial results certified by a practicing Chartered Accountant shall be
considered acceptable. In case, Bidder is not able to submit the Certificate from practicing Chartered
Accountant certifying its financial parameters, the audited results of three consecutive financial years
preceding the last financial year shall be considered for evaluating the financial parameters. Further, a
Certificate would be required from the CEO/CFO, stating that the Financial results of the Company are
under audit as on the date of Techno-commercial bid opening and the Certificate from the practicing
Chartered Accountant certifying the financial parameters is not available.
5) The bidder must submit Average Annual Turnover and Net worth Certificate in support of Financial QR,
duly certified and verified for authenticity from Independent Statutory Auditor of their company /
Practicing Charted Accountant/ C.A. Firms / TPIA (Third-Party Inspection Agency ) empaneled approved
by GSECL, along with copy of Annual Audited Accounts of last three years.
Note for point No.1, 2, 3&4:
i. Other income shall not be considered for arriving at annual turnover.
ii. “Holding Company" and “Subsidiary Company” shall have the meaning ascribed to them as per
Companies Act of India, in vogue.
Net worth means the sum total of the paid up share capital and free reserves. Free reserve means all reserves
credited out of the profits and share premium account but does not include reserves credited out of the
revaluation of the assets, write back of depreciation provision and amalgamation. Further, any debit balance of
Profit and Loss account and miscellaneous expenses to the extent not adjusted or written off, if any, shall be
reduced from reserves and surplus.
3. To pay EMD in form of DD OR in form of B.G. given by bank as described in the Annexure – I. All the
bidders will be required to pay Tender Fees plus 18% GST and EMD as mentioned in the Tender Document
either in Demand Draft, Pay Order or Bank Guarantee (only for EMD) in favour of Gujarat State Electricity
Corporation Limited payable at Gandhinagar, Gujarat.
4. Tender Fee: The tender fee shall be accompanied in the form of DD.
5. The Last three-year Audited Annual Accounts, Positive Net worth certificate, and Average Annual Turnover
certificate certified by charted accountant as Per Qualification Requirement.
6. Separate employee’s provident fund code number towards registration of firm with
Regional P.F. Commissioner.
7. Attested copy of relevant document duly signed and sealed on each and every page shall be
submitted.
8. Declaration form in original duly notarized on stamp paper of Rs. 300/- (As referred in Tender
9. Attach copy of GST Registration.
10. Bidder shall have to submit the PAN card No for Income Tax with documentary proof.
11. Details of the partnership deed.
12. Details of Tools, tackles, equipment and personals available with firm relevant to the
job/subject matter.
13. Copy of the updated valid labor contract license from the appropriate authorities and updated
workman group insurance policy covering labor engaged.
14. The tenderer shall have to produce the document of last three years annual account, i.e.
profit & loss account and balance sheet, if the estimated cost of tender is more than 50 lakhs
along with technical bid.
15. Details of skilled/semi-skilled persons presently employed by the contractor having sufficient
knowledge of similar jobs.
16. TPI should be mandatory to submit as per cl no.6 of Section B (i.e General Instruction to
the bidders).
The above documents will be analyzed and after satisfaction, the price bid will be opened.
GSECL may verify the documents, experience certificates from authority who have issued such
certificates / details.
On opening of Technical Bid, if any required attested documents are missing in technical bid
EW- 283 PUR-F-006 RFQ-
documents sufficient competition is not possible, in that case to have fair competition, the
to submit the missing required documents within stipulated time limit and failing
which bidder/bidders will be declared technically disqualified for not submitting the
required documents along with technical bids without any further notice. However,
document will be considered valid only if it is for the period of last day of month previous to the
one in which tenders are invited.
Chief Engineer (Gen)
Signature Of Contractor GSECL: GTPS
EW- 283 PUR-F-006 RFQ-
GENERAL INSTRUCTIONS TO THE BIDDERS
1. SUBMISSIOIN OF TENDER
The tender should be uploaded/ submitted online on n-procure process.
Technical bid cover:- This cover shall contain all relevant attested qualifying documents as
prescribed in tender notice along with tender fee & EMD. Bidder shall have submit Tender Fee and
EMD cover only, All other require document to be upload on online (n)procure process only
Note: - If attested copies of qualifying documents stated as prescribed in tender notice are
not found in on-line Technical bid, but same should be submitted by mail during scrutiny
will be treated as final to consider the bid for pre-qualification. Any missing documents, if
required will be asked from the bidder as mentioned in this tender elsewhere. If party has
not submitted tender in online is liable to be ignored.
Technical Bid
“Please note that the Notarized / self-attested copies of original required documents
should be invariably uploaded in n-procure portal before due date and time in pdf form
(Scanned copy). This is mandatory. No physical documents are required to be submitted
except tender fee and EMD.
Price bid:-
The price bid shall have to be submitted online only. The percentage rates and price shall be written
both in words, and figures and the units in words. In case of any ambiguity or mistakes, the unit rates
and prices written in words shall be considered as final.
Offered rate shall include cost of all Materials, wastage of material , Labours for all leads and lifts,
Supervision, setting out works, Machinery and equipment with its mobilization / demobilization,
transportation charges, Clearing of the site both prior to commencement and after completion of work.
Consumables such as, but not limited to petrol, oil, diesel, lubricants, drill bits, pipes, ropes etc.
Construction facilities such as scaffolding, tarpaulins, wind break, etc., Overheads / profits of
Contractor for due performance of the work under this contract.
Applicability of goods and service tax:-
1) The tenders shall be evaluated on firm price and cost with GST and cess as applicable unless
otherwise mentioned in the tender documents.
2) IF the supplier/contractor have opted for the composition scheme of GST, the same must be clearly
specified with valid declaration and certificate from department. In the event of withdrawal/ cessation
of the supplier from composition scheme during the tenure of the contract, the rate(i. e. price)
mentioned in the price bid shall be final and any additional GST will have to be borne by the tenderer
himself, In no case additional amount towards GST or otherwise will be paid/reimbursed to
supplier/contractor.
3) The bidder shall have to inform their GST no. of the registered place(s) where from the bidder intends
to supply the goods/services, meaning there by the bidder has to supply the goods/services from the
relevant declared/ registered place(s) of supply only.
4) The bidder shall not include GST in their quoted rates; but the bidder has to separately indicate the
GST rate, amount in the price bid schedule.
5) In-case Govt notification comes for change in GST , the same will be applicable.
6) Bidder should indicate GST no.( copy of GST registration to be enclosed) and PAN NO. (copy of PAN to
be enclosed) Tenders submitted without GSTIN No by the firms, the offer will be rejected without
entering into further correspondence.
Further information required, if any, can be had from the office of the Chief Engineer, GSECL, GTPS.
But it must be clearly noted that the tenders must be received complete in every respect by the
due date and time.
i. The bidder must clearly quote rates in figure as well as in words. In case of any discrepancy,
EW- 283 PUR-F-006 RFQ-
whatever written in words shall prevail.
ii. No deviation in terms & conditions, Schedule-B and technical specifications will be entertained. Any
ignorance for this shall not relieve the contractor from his contractual liability arising as per tender
documents and conditions contained in it.
iii. The bidders are required to quote only firm prices. No variation will be accepted on price/ raw
materials/ finished products or on any other cause.
iv. The bidders should note that the completion of above mentioned works in all respect in accordance
with the time limit given is very important and should be strictly adhered to. The work is to be
completed in time limit from the date of issue of written order to commence the work by the Chief
Engineer (Gen.), GSECL, Gandhinagar TPS.
v. The bids should be valid for a minimum period of 180 Days from the date of opening of technical
bid. During this period tenderer shall not be allowed to withdraw their tender and if withdrawn, the
Earnest Money Deposit submitted with the tender will be forfeited.
vi. The works covered under these specification shall be carried-out and governed by “Tender and
contract for Works” booklet appended herewith except where conditions specified in this
specifications.
vii. The successful bidder shall have to enter in to an agreement for contract as per G.S.E.C.L rules on a
stamp paper of Rs.300/- and necessary stamp duty charge shall be borne by the
contractor/consultant.
viii. The complete specification comprises of the following.
Bill of Quantities (Schedule-B), instructions to the bidders, Tender specifications and scope of work,
Tender and contract for Works booklet, General Conditions, Instructions to bidder & Technical
specifications. All these sections are complimentary to each other. The particulars and requirements
contained herein shall cover the execution of the works covered under these specifications.
ix. The tenderer must visit the site of works and see for him self the site conditions regarding availability
of approach road during all seasons and other matters affecting the above works before submitting
the tender.
x. The submission of tender by a contractor implies that he has read these instructions the conditions of
contract etc. and has himself aware of the scope and specifications of the work to be done and of
conditions and local conditions and other factors bearings on the execution of the works. GSECL will
not therefore after acceptance of contractor's rate pay any extra charge for any other reason; in case
the contractor is found later on to have misjudged the site condition.
xi. GSECL’s authorized officers who accepts tender, shall have the right of rejecting all or any of the
tenders and will not be bound to accept the lowest offer nor to assign any reason whatsoever for the
rejection of any tender or all tenders.
xii. Bidders shall provide evidence of their continued eligibility to the satisfaction of the owner.
xiii. Bidders shall not be listed under a declaration of ineligibility for corrupt or fraudulent Practices
issued by the Govt., the list of black listed Contractors announced by GSECL (erstwhile GEB) Govt. of
Gujarat or its Public Sector undertakings or the contractors who are under stop dealing in GUVNL and
/or their any subsidiary company viz. GETCO/MGVCL/UGVCL/PGVCL/DGVCL.
xiv.The bid, and in case of a successful bid, the Form of Contract Agreement, shall be signed with the
name of Firm / company which will be legally binding on all partners / parties.
xv.If the application is made by an individual, it shall be signed by the individual above his full typed
written name and current address.
xvi.If the application is made by a proprietary firm. It shall be signed by the proprietor above his full
typed written name and the full name of his firm with its current address.
xvii.If the application is made by a partnership firm, it shall be signed by all the partners of the firm
above their full type written names and current addresses or alternatively by partner holding
power of attorney for the firm in which case a certified copy of the power of attorney shall
accompany the application. A certified copy of the partnership deed, full names and current
addresses of all the partners of the firm shall also accompany the application.
xviii. If the application is made by a limited company or a Corporation, it shall be signed by the
authorized person holding power of attorney for signing application in which case a certified copy of
the power of attorney shall accompany the application. Such Limited company or Corporation
EW- 283 PUR-F-006 RFQ-
may be required to furnish satisfactory evidence of its existence before the pre-qualification
evaluation. They should also furnish Articles of Memorandum of Association. If the application is
made by group of companies, it shall be signed by the authorized person. The authority letter shall be
accompanied with the application.
2. SECURITY DEPOSIT
It should be mandatory to submit security deposit as per cl no.7 of Section C (i.e General
condition of contract).
3. MAINTENANCE: i] The contractor shall be responsible to make good and remedy at his own
expense any defect which may develop or may be noticed before the period mentioned hereunder
from the certified date of completion. The same shall be attended within 15 days of receipt of the
notice. In the case of failure on the part of the contractor, the Engineer-in-charge may rectify or
remove or re-execute the work at the risk & cost of the contractor. The Engineer-in-charge shall
be entitled to appropriate the whole or any part of the amount of security deposit towards the
expenses, if any, incurred by him in rectification, removal or re-execution. The defects liability
period shall be as under,
For all works costing more than Rs. 50,000 and up to Rs. 1 crore (Work Order amount), the period shall
be 06 months from the certified date of completion OR one monsoon, whichever is later.
4. TIME LIMIT FOR WORK:
The scheduled time limit for the completion of work shall be 04 (Four Months) calendar months
from the date of issue of letter to commence the work. However extension in time limit will be
granted by GSECL for the genuine reasons only as per terms of the contracts.
5. TERMS OF PAYMENTS:
Contractor shall be paid RA bill after observing GSECL’s general procedure and submission of bill by the
agency. Also, 75% payment shall be made immediately within a week period on receipt of recorded bill
by Account Section without checking of detail bill and compliance of queries & statutory requirement.
However, remaining balance 25% amount shall be released only after through checking of detail bill
and compliance of various quarries, statutory compliance etc. The above payment term is applicable to
all the bills of general civil works & ARC/BRC works, provided the bills are recorded regularly and
submitted to Account Section within Ninety [90] days. If the contractor fails to submit the bills regularly
in such a way so that the same cannot be recorded and submitted to account section within Sixty [60]
days, ad-hoc payment as stated above, may not be released and payment will be released as per
GSECL’s general procedure. The period of Sixty [60] days shall be considered from the date of receipt
of last R.A. Bill by Account Section.
6. METHOD OF PAYMENT:
a. The payment for the work done will be made by running bills every month after taking
joint measurement within 30 days.
b. Final bill will be paid within reasonable time after settlement of material account by
you and after recording of joint measurement.
7. All bidders shall submit the details/documents in support of Technical Qualification Requirements
duly certified and verified for authenticity from Specified Third-Party Inspection Agency
(TPIA) or Statutory Auditor of their Company or Practicing CA/CA Firm along with a certificate
regarding verification of authenticity of documents as per the format placed at Appendix 1. All
the documents submitted by the bidder in support of meeting Technical QR shall be digitally
signed by the Specified Third-Party Inspection Agency (TPIA) or Statutory Auditor of their
Company or Practicing CA/CA Firm. In case documents are certified & verified for authenticity
through TPIA, the verification and certification of authenticity of documents is acceptable from
EW- 283 PUR-F-006 RFQ-
any of the following TPI As:
1. M/s Competent Inspectorate and Consultants Pvt. Ltd, Hyderabad, India.
2. M/s Gulf Lloyds Industrial Service India Pvt. Ltd.-Ahmedabad.
3. M/s International Certifications Services.
4. M/s Intertek India Pvt. Ltd.
5. M/s SGS India Pvt. Ltd.
6. M/s Moody International (India) Pvt. Ltd.
7. M/s TUV SUD South Asia (P) Ltd.
8. M/s TUV Rheinland (India) Pvt Ltd.
9. M/s Bureau Veritas (india) Pvt. Ltd.
10. Hertz Inspection & services Pvt. Ltd.
11. IRCLASS Systems and Solutions Pvt. Ltd.
Verification for authenticity shall not be applicable in following cases.
1. Bidders having proven track record or regular suppliers/contractors (i.e.
OEM/OES/PSUS)
2. Past order copies of GSECL as these documents can be verified internally.
Bidders shall be responsible for getting their documents/ credentials verified &
certified by the Specified Third-Party Inspection Agency (TPIA) or Statutory Auditor
of their Company or Practicing CA/CA Firm in support of Technical QR. All the
costs pertaining to third party verification and certification (including those by
statutory auditors) shall be borne by the Bidder. GSECL shall have no liability
(financial or Otherwise) towards the same and shall not be liable for any claim/
dispute between the bidder and the Specified Third-Party inspection Agency (TPIA)
or Statutory Auditor of their Company or Practicing CA/CA Firm
Annexure-1
Undertaking from Third Party inspection Agency/Statutory Auditor or Practicing
CA/CA Firm
(On letter head digitally signed by a person duly authorized to Sign on behalf of the firm)
Ref: Date:
Power Station ……………….
Subject: Authentication of veracity of documents submitted by M/s ........ in support of
Meeting the Qualifying Requirements
Ref: Tender no. …………………..
Name of the Package/ Tender: ………………………………………
M/s. ……………… (hereinafter called Bidder) having Registered office at …………………… intend
to participate in above referred tender of GSECL.
The tender condition stipulates that the bidder shall submit supporting Documents
pertaining to Qualifying Requirement duly verified and certified by Third-Party Inspection
EW- 283 PUR-F-006 RFQ-
Agency (TPIA) or Statutory Auditor of their Company or Practicing CA/CA Firm as per the
list mentioned in the bidding documents.
In this regard, it is hereby confirmed that we have examined the following documents,
which are also attached with this letter. The same has been verified from the Original
Documents and / or Client for authenticity.
We hereby confirm that the following documents are found to be genuine and authentic.
1. Doc ref. no. ……….. Dated …….. (Name of Documents)
2. Doc ref. no. ……….. Dated …….. (Name of Documents)
All the aforesaid documents have been digitally signed by us as a certificate of
authenticity.
We further confirm that we neither have any vested interest in aforesaid tender nor have
any conflict of interest in respect of above tender.
This certificate is issued at the request of M/s ………………. (Bidder) for the purpose of
participating in the subject tender/s
Thanking you,
8. ASSIGNMENT:
The rights and liabilities of the contractor shall not be assigned or transferred by them without the
consent in writing of the GSECL to any other person, firm or organization.
9. The successful Bidder, on receipt of letter of intent will submit within a week's time his planning
/ programme of works, for scrutiny of the GSECL in a Bar Chart format, clearly indicating GSECL's
inputs also. Contractor will plan his works such that simultaneous work should progress in such a way
that entire job is completed in scheduled time limit on all the fronts released by GSECL.
10. The successful bidder will have to depute his authorized representative to attend progress
review meetings to be held at GSECL, Gandhinagar TPS without any extra cost.
11. The Contractor will be responsible for complying with all rules and regulations and labour laws
applicable to him and the GSECL will not be responsible for any lapses committed by them. If there is
any claim from any Government authority pertaining to the contract, the same amount will be
deducted from the Contractor's bill.
12. The time limit for completion of work is stipulated as in the tender will be adhered to.
13. The Contractor's rates should be firm and no variation clause is to be quoted by the Contractor
and GSECL will not accept the same, during contractual period including extended time limit if any.
14. BIDDER TO STUDY, ANALYSE & CONSIDER:
a) The information given in this specification is in good faith and meant to serve as a guide
to the Bidder. It is, therefore, imperative that Bidder shall obtain and examine for himself all the data,
information and particulars required for the satisfactory execution of the work under this tender. The
submission of a bid by Bidder implies that he has fully read the specifications, bid drawings,
instruction to the bidder along with Contract Document and Conditions of Contract, applicable labour
laws, safety norms etc., and has made himself aware of the scope and the specifications for the work
to be performed and local conditions and other features which have a bearing on the cost and
execution of the work. This specification is intended as a general description of quality envisaged for
materials and workmanship and of the finished work. It is not intended to cover minute details. The
work shall be executed in accordance with the best modern practice and to the complete satisfaction
EW- 283 PUR-F-006 RFQ-
of the Purchaser. Special techniques approved by the Purchaser shall be used if and where found
necessary. This specification shall have precedence if anything contrary to this is stated elsewhere in
the contract documents. The Purchaser’s decision shall be final and binding on the contractor on any
issue arising out of such discrepancies.
b) Inspection of site by bidder:
Before submission of his bid, Bidder shall inspect the site, examine and obtain all information
required and satisfy himself regarding matters such as:
weather characteristics,
Location of site and access, right of way, means of communication & mode of Transport to site,
The type and number of equipment and facilities required
The quantity of various items of the work.
The availability and rates of material.
Labours condition.
Local working conditions, obstructions and hindrances that may arise etc.
Power house, which is under running conditions.
Required GSECL’s security checks.
All materials brought to site only after making entries in security register at Control gate
c) These factors are likely to affect the satisfactory completion of work and or cost thereof. The
submission of a bid by the Bidder will be construed as evidence that such an examination was
made and any later claims/ disputes in regard to rates quoted shall not be entertained or
considered by the GSECL.
d) The site visit shall be done by the bidder on his own responsibility and all liabilities including
cash, arising out of the site visit shall be at the bidder’s account.
e) Contractor’s scope of work shall also include making all necessary arrangements for access to
work sites, stores and site offices etc. from the nearest approach road to facilitate
transportation of man power, machinery and equipment duly considering the existing site
conditions. No extra claims / costs will be entertained by GSECL.
f) The bidder shall carefully study the work to be carried out & consider all the factors & shall take
into account &consider all the factors such as lead, lift haulage of materials, sequence of
construction, etc. & shall allow for all such information / data in the rates quoted.
g) The GSECL will not pay any extra charges or rate for any reason in case the contractor claims,
after acceptance of contract to have misjudged the site condition. Ignorance of the intents and
contents of the specification document and site conditions shall not be accepted by the Owner
as basis for any claims for compensation.
h) BIDDER shall inspect the site, examine and obtain all information required and satisfy himself
regarding matters such as sub-surface conditions, water records, access to site, communication,
transport, right of way, the type and number of equipment and facilities required for the
satisfactory completion of work, the quantity of various items of the work, the availability and
rates of material, local working conditions, uncertainties of weather, obstructions and
hindrances that may arise etc. which may affect the work or cost thereof, before submission of
his bid. Ignorance of site conditions shall not be accepted by the ENGINEER IN CHARGE as
basis for any claim for compensation.
i) The rates quoted by BIDDER shall be based on his own knowledge and judgment of the
conditions and hazards involved and shall not be based on any representations of the Engineer
in Charge. No claim on this account shall be admitted by the GSECL.
j) The bidders shall submit on online in n-procure with their offer without any deviations in
general terms and conditions of the contract or in technical specifications.
k) Tenders received after the time and date specified in the tender notice will not be accepted.
Once the offer is submitted by bidder before due date of submission, the bidder shall not be
allowed to submit revised/ additional/ modified offer even before due date and time of
submission of tender. However, if the date of issue and/or submission of tender are extended
by the Corporation due to any reason, the bidder may submit if their wishes the
revised/additional/modified offer before extended due date and time of submission.
EW- 283 PUR-F-006 RFQ-
l) The Corporation reserves the right to accept any tender irrespective of whether it is lowest or
not or to reject all the tenders without assigning any reasons thereof. Tenders deferring from
the technical specifications or the method of bidding in a radical manner may also be rejected.
m) The bidder shall be presumed to have carefully examined the drawings, conditions &
specifications of work & to have fully acquainted themselves with all details of the site
conditions, locations, materials, geological & weather characteristics, labour conditions & in
general all the necessary information and data etc. pertaining to and need for the work.
n) This specification is intended as a general description of quality envisaged for materials and
workmanship and of the finished work. It is not intended to cover minute details. The work shall
be executed in accordance with the best modern practice and to the complete satisfaction of
the Purchaser. Special techniques approved by the Purchaser shall be used if and where found
necessary. This specification shall have precedence if anything contrary to this is stated
elsewhere in the contract documents. The Purchaser’s decision shall be final and binding on the
contractor on any issue arising out of such discrepancies.
o) Each bidder shall also submit a 'Declaration' to the effect that the tenderer is an engineering
construction firm or an association of firm or firm which has successfully carried out large works
of this nature and has adequate organization and experienced personnel to handle this type and
magnitude of work. Information should also be given regarding the constitution of the firm; it’s
authorized, subscribed & paid up capital, the date & place of registration, the place of business,
the names of the directors and other relevant information.
p) It is the intent of the ENGINEER IN CHARGE to incorporate these specification documents in the
final ‘Contract’. BIDDERS are required to review these documents and clearly state in their
proposals their acceptance of the same.
q) Each page of the bid document including the bid drawings shall be signed, stamped and dated
in ink by the BIDDER as a token of having examined the same. Any correction in price and the
rates entered in the Schedule of Price shall also be signed and dated by the BIDDER in ink,
before submitting the bid. Non-compliance with this condition will make the bid liable for
rejection.
r) All safety measures as required to be adopted as per the Statutory Regulations and the Safety
Rules of the Plant shall be strictly followed by the Contractor during the execution of the
Contract. The Contractor shall set up a suitable safety organization of his own in this regard.
s) In connection with the execution of the Contract, the Contractor shall comply with all applicable
statutory Rules & Regulations including employment of labours at site.
t) The Contractor shall carry out any and all such works, as may be required, for civil work to be
completed in all respect as per the Contract Specification.
u) If the GSECL Engineer-in-Charge is not satisfied with the progress of work at site, he shall direct
the Contractor to depute more numbers of supervisory personnel/workers to meet the
completion schedules as per the Contract. Upon receiving such direction, Contractor shall
deploy additional personnel within 7 days without any extra cost.
v) The GSECL may during the progress of work, order the removal of part or whole of the work
executed, found not in accordance with the specifications/ instructions. No extra claims shall be
entertained for re-executing or altering of such work.
15. SAFETY MEASURES:
The contractor shall ensure the safety of workers, material and structure including existing
structures during execution of the contract. Safety measures shall be followed during operations
of equipments/machinery being used. No separate payment shall be made for the safety
measures and the quoted rates shall include the cost for all safety measures.
16. COMPLETENESS:
Any technical services as set forth here in above and which might not have been specifically
mentioned in this Contract relating to the work or in the specifications and which are not
expressly excluded therefore but which are necessary for the performance in accordance with
the specifications as an integral part of the painting and misc. Civil works shall be rendered by
the Contractor without any extra cost.
17. TOTAL RESPONSIBILITY
The Contractor shall be solely responsible for the entire technical works / services irrespective
EW- 283 PUR-F-006 RFQ-
of works / services have been made /rendered by him.
18. PAYMENT TO THE LABOURES:
(a) Contractor has to pay the CPF as well as salary to his skilled/unskilled manpower by cheque
A/c payee only, as per minimum wages & prevailing applicable rules on or before 7th day of
next month.
(b) Contractor has to produce challan of PF with list of employees.
(c) Contractor shall have to make payment to his labours in presence of Personal Officer (Estt.)
GSECL, Gandhinagar TPS.
19. CONTRACT AGGREMENT ON ACCEPTANCE:
The successful contractor will have to sign an agreement as per the Gujarat State Electricity
Corporation Ltd.'s rules on stamped paper and the necessary stamp duty charges shall be
borne by the contractor.
On acceptance of the tender the name (s) of the accredited representative (s) of the tenderer
who would be responsible for taking instructions from the Engineers of the GSECL shall be
communicated to Chief Engineer (Gen.) Gandhinagar Power Station, Gujarat State Electricity
Corporation Limited.
20. Unsatisfactory progress of the work:
If the work is found not progressing as per the requirement or found not satisfactory then
GSECL will take such action to get the work done through the other agency at agency’s risk
and cost with 15% supervision charges and same will be recovered from agency.
21. The EMD will be returned promptly to the unsuccessful bidder except that of L1, L2 & L3 till
the successful contractor pays the Security Deposit as mentioned in tender document or after
the expiry of the validity of the offer, whichever is earlier.
The EMD will be returned to the successful tenderer after he furnishes the Security Deposit for
the tender work. If he fails to furnish the SD, his EMD shall be forfeited and the tenderer will
not be allowed to participate in the tenders invited by this office for a period of ONE Year in
respective Power Station.
The EMD in form of Bank Guarantee shall be valid for Ten Months from the date of
submission of the tender.
22. Effect and validity of Bid: The submission of bid with these documents and specification shall
constitute an agreement that bidder shall have no cause of action or claim against the GSECL
for rejection of his bid. The GSECL shall always be at liberty to reject or accept, split any bid or
bids at its sole discretion and any action will not be called into question and the bidder shall
have no claim in that regards against the GSECL.
23.Stop Deal / Banned for business dealing / Blacklisting :-
Has submitted fake, false or forged documents/certificates
Has revised/ withdrawn price bid after opening of Techno-commercial bid, until and unless it
is sought for,
Has tempered with the stipulated tendering procedure.
Has refused to accept Letter of Acceptance / Purchase order / Work Order after the same is
issued by the company within the validity period and as per agreed terms and conditions,
Has committed breach of contract or has failed to perform a contract or has abandoned the
Has failed to provide suitable expertise for the work as per pre-scheduled program.
Has failed to submit all the necessary tests reports / documents within time scheduled / as
per company’s time limit, as mentioned in the LOA, if the Letter of Acceptance (LOA) is placed
subject to submission of type reports / documents to the firm.
Has indulged in construction and erection of defective works.
Has supplied inferior quality / defective materials and refused to replace with stipulated time
frame, as specified by the company,
Has substituted materials in lieu of materials supplied by the company or has not returned or
has short returned or has unauthorisely disposed of materials / documents / drawings / tools
EW- 283 PUR-F-006 RFQ-
or plants or equipment supplied by the Company,
Has involved in malpractices such as bribery, corruption, fraud, canvassing and pilferage,
Has unauthorisely obtained official company information or copies of documents, in relation to
the Tender / Contract.
Has failed to follow the stipulated mode of communication, if specified by the tendering
authority / Purchaser.
Has parted with, leaked or provided confidential / proprietary information of the company
given to the firm only for its use (in discharge of its obligations against an order) to any third
party without prior consent of the Company,
Any other ground for which in the opinion of the Company makes it undesirable to deal with
In case the state Government directs the Company to place a firm in stop dealing / banned
for business dealing / blacklisting.
24. Conflict of Interest among Bidders / Agents
A bidder shall not have conflict of interest with other bidders for particular quoted item.
Such conflict of interest can lead to anti-competitive practices to the detriment of Procuring
Entity's interests. The bidder found to have a conflict of interest shall be disqualified. A
bidder may be considered to have a conflict of interest with one or more parties in this
bidding process for particular quoted item, if:
a) They have proprietor/partner(s)/Director(s)in common; or
b) They receive or have received any direct or indirect subsidy/financial
stake from any of them; or
c) They have the same legal representative/agent for purposes of this bid; or
d) they have relationship with each other, directly or through common third parties,
that puts them in a position to have access to information about or influence on the
bid of another bidder, or
e) bidder participates in more than one bid in this bidding process. Participation by a
bidder in more than one Bid will result in the disqualification of all bids in which the
parties are involved. However, this does not limit the inclusion of the components/
sub-assembly/ assemblies from one bidding manufacturer in more than one bid.
f) In cases of agents quoting in offshore procurements, on behalf of their principal
manufacturers, one agent cannot represent two manufacturers or quote on their
behalf in a particular tender enquiry. One manufacturer can also authorise only one
agent/ dealer. There can be only one bid from the following:
1. The principal manufacturer directly or through one Indian agent on his behalf;
2. Indian/foreign agent on behalf of onIy one principal.
g) A Bidder or any of its affiliates participated as a consultant in the preparation of the
design or technical specifications of the contract that is the subject of the Bid;
h) in case of a holding company having more than one independently manufacturing
units, or more than one unit having common business ownership/ management,
only one unit should quote. Similar restrictions would apply to closely related sister
EW- 283 PUR-F-006 RFQ-
companies. Bidders must proactively declare such sister/common business/
management units in same/ similar line of business.
i) Bidder shall not act in contravention/violation to the provisions of competition act,
as amended from time to time.
Every bidder should, at the time of submission of bid, give a declaration, that bidder
shall not have conflict of interest with other bidders for particular quoted item, as
CHIEF ENGINEER (Gen)
GSECL: GTPS
SIGNATURE OF CONTRACTOR
EW- 283 PUR-F-006 RFQ-
SECTION-C:
GENERAL CONDITIONS OF CONTRACT
EW- 283 PUR-F-006 RFQ-
GENERAL CONDITIONS OF CONTRACT
1. DEFINITIONS :
(a) The Contract means the documents forming the tender and acceptance thereof, together
with the documents referred to therein or individual work order in the case of term contract,
including these conditions, schedules and/or additional conditions attached to the form of
tender or individual works, order, rate schedule, the specifications and the drawings and all
these documents, as applicable, taken together shall be deemed to form the contract.
(b) The “Tender Document” means the form of tender, the applicable schedules and/or
additional conditions and the specifications and/or drawing as issued to the contractors for
the purpose of preparing tender.
(c) The expression “Works” or “Work” when used in the condition of contract shall, unless there
be something in the subject or context repugnant to such construction means, the works or
the work contracted to be executed under or in virtue of the contract whether original or
(d) The “Contractor” means the individual or firm or Corporation, whether incorporated or not,
undertaking the words and shall include his or its legal personal representatives, successors
and permitted assignees.
(e) “Corporation” means The Gujarat State Electricity Corporation Ltd. and the “Accepting
Officer” means the Officer who is authorized to sign and signs the contract on behalf of the
“Corporation”.
(f) The letter “EE” means Executive Engineer who in the case of measurement and lump sum
contract, direct the contract and the letters “SE” means Superintending Engineer and “GM”
means General Manager who administers and in the case of the term contracts, directs the
(g) The “Engineer-in-charge” means all officers of the Corporation appointed by the General
Manager to supervise the works or part of the works.
(h) “Approved” and “Directed” means the approval or direction of the Chief Engineer (Gen),
Gandhinagar TPS to Superintending Engineer or the person deputed by him for the particular
(i) “BS.” means “British Standards” as issued by the British Standards Institution. “A.S.” means
the “American Standards” as issued by the American Standards Institution, and “I.S.” means
the “Indian Standards” as issued by the Indian Standards Institution. Wherever the above-
mentioned abbreviations are referred to, in the specifications and/or work orders, they mean
the addition with all amendments current at the date of issue of tender document of work
(j) In the case of measurement and terms of contract “Specifications” mean those contained in
Gujarat State Electricity Corporation Ltd. scheduled together with any amendments etc.
embodied in the tender documents. “Drawing” refers to those incorporating the tender
documents and/or any work orders referred therein.
(k) The “Contract Sum” means the sum accepted or the sum calculated in accordance with the
prices accepted in the tender and/or the contract rate as payable to the contractor for the
full and entire executing and completion of works.
(l) “The date for completion” is the date or dates of completion of the work or any part of the
works set out or ascertained in accordance with the individual work orders and the tender
documents or any subsequent agreed amendments thereto.
2. CONTRACTOR TO INFORM HIMSELF FULLY:
A. Notwithstanding anything contained to the contrary in the specifications or tenders in
subsequent exchange of correspondence, the conditions of contract shall be binding on the
Contractor and any change or variation expressed or implied, however made in the said
conditions, shall not be valid or operative unless expressly sanctioned by the Corporation.
EW- 283 PUR-F-006 RFQ-
The Contractor shall be deemed to have fully informed himself and to have special
knowledge of the provisions of the conditions of the Contract herein contained.
B. The contractor shall be deemed to have carefully examined the work and site conditions, the
general conditions, the special conditions, specifications, schedules and drawing and shall
be deemed to have visited the site of the works and to have fully informed himself
regarding the local conditions.
C. If there shall have any doubt as to the meaning of any portion of these general conditions
or special conditions of the scope of work of the specifications or any other matter
concerning the contract, he shall in good time before submitting his tender, send for the
particulars thereof and submit them to the Engineer-in-charge in writing in order that such
doubt may be removed.
3. CONTRACT DRAWING AND SPECIFICATIONS:
The contractor will be entitled to receive one set of agreement along with one certified copy
of accepted tender.
The drawings which form part of these specifications show the work to be done in as much
detail as is possible at the present stage. They will be supplemented by such additional
detailed drawings as may be necessary as the work progresses. The contractor shall perform
the work on these features and in accordance with these additional or revised drawings as
the case may be and at the applicable rates as per the contract.
The contractor shall check all drawings carefully and shall bring to the notice to the Engineer-
in-charge immediately of any errors or omissions discovered. The contractor shall not take
advantages of errors or omissions of any kind in the drawings supplied.
4. INPUTS BY GSECL:
The electric power supply and connection for construction / work purpose shall be given at one
mutually agreed point at work site free of cost by the GSECL. Further extension for
construction site as well as bore well site for using construction water will have to be carried
out by the contractor as per requirement at their cost. The necessary electric charges will be
paid by the contractor as per rates prevailing from time to time in the respective DISCOM.
1. If there are any surplus quarters available after meeting the requirement of GSECL's staff,
then GSECL will consider allotment of quarters on rent as per GSECL's rule.
2. The contractor will have to make their own arrangement of water for construction work
as well as for their labourers at his own cost. If possible, water for construction
purpose only at one point as decided by EIC and recovery for water charges shall be
affected at the 2 % of the item of which water is used or by quantity measured by
meter reading of water meter installed by contractor, rate of water supply will be
charged at prevailing purchase rates of GSECL, for water supplied by GSECL is used as
certified by EIC. In case of agency is installing bore well and pumps at his cost, after
completion of work agency will hand over the bore well in good condition with pumps
to the GSECL.
5. DATA TO BE FURNISHED BY CONTRACTOR:
The contractor shall submit to the Executive Engineer for approval within one week of the
date of contract, a layout plan of construction plant and equipment for the execution
of work which the contractor proposes to adopt at site.
Prior to commencement of work, the contractor shall submit to the Executive Engineer for
approval, plans in triplicate showing the location of Major plant shop and storage
buildings, storage yards, offices, contractor's power house including its services and
housing facilities which he proposes to put up at site and also indicate the programme of the
The successful bidder on receipt of letter of intent will submit within a week's time his
planning/programme of works for scrutiny of GSECL in a PERT/Bar chart format, clearly
indicating GSECL inputs also.
Contractor will plan his works such that on all the fronts released by GSECL, simultaneous
work should progress in such a way that entire job is completed in scheduled time limit.
EW- 283 PUR-F-006 RFQ-
No change in the approved layout shall be carried out without specific written approval of the
Executive Engineer.
6. ERRORS, OMISSIONS AND DISCREPANCIES:
In all cases of errors, omissions, doubts or discrepancies in the dimensions, or
discrepancies in the drawings and items of work in specification, reference shall be made to
the Executive Engineer whose elucidation and elaboration shall be considered as
authoritative. The contractor shall be held responsible for any error that may occur in the
work thorough lack of such reference and precautions.
7. SECURITY DEPOSIT: In tender process for L1 bidder (lowest bidder)
security deposit will be charged as per table below:
Category of the Unit Security Deposit
Works up to Rs. 5 Works More than
Lakh Rs. 5 Lakh
Enterprise or Organization Exempted 3% of Order Value
which are exempted from
paying Tender Fee & EMD
For all other Enterprises 5% of Order Value 5% of Order Value
Note: Security Deposit will be collected from the successful tenderer at the rates mentioned
above. This may be recovered by deduction through running bills of the contractors and / or
by treating the Earnest Money Deposit (Bid Security) paid at the time of submission of the
After issue of Work order and Date of commencement, if successful bidder failed to start
the work then, RPAD notice will be issued to the successful bidder mentioning that on
failing to start the work within next 07 days from the date of issue of RPAD Notice the EMD
will be forfeited and he will not be allowed to participate in the tenders invited from
Gandhinagar TPS office for the period of One year.
The security deposit of the contract value shall be released on finalization of final bill /
successful completion of maintenance period / work.
All damages, costs, charges, expenses and other sums which may be or may become due
or payable by the contractor to the Corporation under the terms of the contract, may be
deducted from the cash in the proceeds of sale of the securities/bank guarantee so
deposited (which the officer or person to whom the same may be endorsed as aforesaid is
hereby authorized to sell/to encase for that purpose) or from the interest of any such
securities or from any sums due or which may become due to the contractor by the
Corporation or from the whole or the balance unpaid as aforesaid of the encase securities
so deposited being repaid or transferred and returned as the case may be, to the
contractor on finalization of final bill OR after 06 (six) months of successful completion of
the work, whichever later OR on furnishing of the Performance Bond amounting to 5% of
contract value against the defect liability period as mentioned in this document elsewhere.
If entire security deposit is paid in approved form of Bank Guarantee should be remain
valid during the contractual period and such bank Guarantee should not be reduced on the
basis of the work actually done.
8. USE OF LAND:
The land required for office, godowns and for labour camp if not available with GSECL,
then the contractor has to arrange the same at his cost. GSECL will give the land only if the
spare land is available with the following conditions.
The contractor shall be permitted to use for the bonafide purpose of execution of this
EW- 283 PUR-F-006 RFQ-
contract free of cost. The contractor shall be permitted to use for the bonafide purpose of
execution of this contract free of cost.
1. Site required for the construction of the work.
2. Required approach road. The contractor shall make their own arrangements for the
necessary approach, road, for transport of their materials and be responsible for the
compensation on account of damage to crop etc. and shall till completion of work.
3. He will be charged the rent at the annual rate of rupees one hundred per every acre or
part thereof, for the construction of temporary hutments and his store yard. However
area required for such purpose may be clearly indicated in this offer.
All areas of operation, including those for his staff and labour colonies handed over to the
contractor shall be cleared and handed over back in good condition to the Engineer
except areas under works as per this contract or those for which specific approval has
been obtained from the Engineer. The contractor shall make good to the satisfaction of
the Engineer any damage or alternation made to areas which he has to hand over back
or to other property land handed over to him for purpose of this work.
Temporary structures may be erected by the contractor for storage sheds, offices,
residence etc. for noncommercial use on the land, handed over to him at his own
expense and with the permission of the Engineer. These structures shall comply with the
regulation that may be in force and/or specified by the Engineer with regard, thereto. In
any circumstances for constructing temporary structures for contractor's use, GSECL's
free supply materials shall not be used. If it is found that GSECL's free supply materials
are used for other than approved project drawings work, same will be recovered at
penalized rate.
The contractor shall preserve all existing vegetation such as trees on or adjacent to the
sites which do not interfere with the construction as determined by the Engineer.
The contractors shall take all possible precautions in felling trees authorized for removal
to avoid any unnecessary damage to vegetation and trees not to be felled and to
structures under construction, or to workmen, and shall be responsible for any damage if
it occurs in such operations
All produce from cutting of trees; grass etc. shall be the property of GSECL and shall be
stocked at the place specified by the Engineer. No claim shall be made for such cutting
and stacking of trees or grass etc. by the contractor
The contractors shall not unnecessarily or for use as fuel, cut any trees brush wood,
grass or other vegetation nor shall set fire there to without the written permission of the
Engineer. When such permission is given, the contractor shall take necessary measures
to prevent damage or to prevent fire spreading to surrounding property, and shall be
responsible for any such damage, if cause.
The land shall as herein before mentioned be handed back to Engineer in Charge
immediately after the completion of the work under this contract. Also no land shall be
held by the contractor longer than the Engineer shall deem necessary and the contractor
shall, on due notice by the Engineer, vacate and return the land which the Engineer may
certify as no longer required by the contractor for purpose of the work.
9. START OF WORK:
The contractor shall not enter upon or commence any portion of work except with the
written authority or instructions of the Executive Engineer or his subordinate in charge of
the work, failing such the contractor shall have no claim to ask for measurement or
payment for work and shall be responsible for any claims or damages that may arise due to
such unauthorized commencement or entry.
10. COMPENSATION FOR THE DELAY:
The time allowed for carrying out the work as entered in the tender shall be strictly
observed by the contractor and shall be reckoned from the date on which the order to
commence work is given to the contractor. The work shall throughout the stipulated period
of contract be proceeded with all due diligence (time being deemed to be the essence of
contract) and for delay, the contractor shall pay compensation, an amount equal to ½
(half) percent per one week for the contract amount or part thereof, including taxes &
duties ( i.e. End cost of contract amount including taxes & duties) and maximum up to
% of the order value, including taxes & duties ( i.e. End cost of contract amount including
EW- 283 PUR-F-006 RFQ-
taxes & duties) or such smaller amount as per the decision of the Competent Authority of
the GSECL The penalty will be invariably deducted from the bills of the contractor and no
refund will be given unless the competent authority approves the reduction. The reasons
for delay, attributable to GSECL as well as to party will be brought out clearly while putting
the proposal for waiver/reduction in penalty.
11. ACTION WHEN WHOLE OF SECURITY DEPOSIT IS FORFEITED:
In any case in which under any clause or clauses of this contract the contractor shall have
tendered himself to pay compensation amounting to the whole of his security deposit
(whether paid one sum) or in the case of abandonment for the work owing to serious
illness or death of the contractor or any other cause, the Executive Engineer on behalf of
the Corporation, shall have powers to adopt (a) below and any of the following courses
under (b) and (c) as he may deem best suited to the interest of the Corporation.
(a) To rescind the contract (for which rescission notice of 10 days) in writing to the contractor
under the hand of the Executive Engineer shall be conclusive evidence and in that case the
security deposit of the contractor shall stand forfeited and absolutely at the disposal of the
Corporation. To employ labour paid by the Corporation, to supply materials, to carry out the
works or any part of the work debiting the contractor with the cost of the labour and the
price of the materials (as to the correctness of which cost and price, the certificate of the
Executive Engineer shall be final and conclusive against the contractor) and crediting him
with value of the work done in all respects in the same manner and at the same rates as if
it had been carried out by the Contractor under the terms of this contract and in that case
the certificate of the Executive Engineer as to the value of the work shall be final and
conclusive against the contractor.
(b) To order that the work of the contractor be measured up and to take such part thereof, as
shall be unexecuted, out of his hands and to give it to another contractor to complete, in
which case, any expenses, which may be incurred in excess of the sum, which would have
been paid to the original contractor, if the whole work would have been executed by him
(as to the amount of which excess expenses, the certificate in writing of the Engineer-in-
charge shall be final, conclusive and shall be borne and shall be paid by the original
contractors and shall be deducted from any money due to him by the Corporation under the
contract or otherwise from his security deposit of his proceeds sale thereof or a sufficient
part thereof.
(c) In the event of the above courses being adopted by the Executive Engineer, the contractor
shall have no claim to compensation for any loss sustained by him by reason of his having
purchased or procured any materials or entered into any engagements or made any
advances on account of or with a view to the execution of the work or the performance of
the contract. And in case the contract shall be rescinded under the provision aforesaid, the
contractor shall not be entitled to recovery or be paid any sum for any works thereof
actually performed by him under this contract unless and until the Executive Engineer shall
have certified in writing the performance of such work and the amount payable to him in
respect thereof and he only be entitled to be paid the amount so certified.
12. NOTICE UNDER UNSATISFACTORY PROGRESS:
If the progress of a particular portion of the work is unsatisfactory, and also if as per the
opinion/observation of the Executive Engineer (whose decision shall be final) in charge that
the general progress of work is not satisfactory, then Executive Engineer in charge shall be
entitled to take action under clause 11 (c) after giving the contractor ten days’ notice in
writing and the contractor will have no claim for compensation for any loss sustained by
him owing to such action.
13. ACTION IN THE CASE OF DEFAULT BY THE CONTRACTOR :
In any case in which any of the powers conferred upon the Executive Engineer by Clauses
11 and 12 hereof shall have exercisable and the same shall not have been exercised, the
non-exercised thereof shall not constitute a waiver of any of the conditions hereof and such
powers shall not withstanding be exercisable in any further case of default by the
contractor of which, by any clauses hereof, he is declared liable to pay compensation
EW- 283 PUR-F-006 RFQ-
amounting to the whole of his security deposit and liability of the contractor for past and
future compensation shall remain unaffected in the event of the Executive Engineer taking
action under sub-clause (a) or (c) of Clause 11, he may if he so desires, take possession of
all or any tools, plants, materials, and stores in so upon the work or the site thereof
belonging to the contractor, or procured by him and intended to be used for the execution
of the work of any part thereof paying for allowing for the same in account at the contract
rates, or in the case of a contract rates not being applicable of current market rates to be
certified by the Executive Engineer whose certificate thereof shall be final. In the
alternative, the Executive Engineer may by notice in writing to contractor or his clerk of
works, foreman or other authorized agent, require him to remove such tools, plant,
materials or stores from the premises within a time to be specified in such requisition, the
decision to the contractor failing to comply with any such requisition, the decision of the
Executive Engineer as to the expense of any such removal and the amount of the proceed
and expense of any such sale, be final and conclusive against the contractor
14. EXTENSION OF TIME LIMIT
If the contractor shall desire an extension of the time limit for completion of the work on
the ground of his having been unavoidably hindered in its execution or on any other
ground, he shall apply in writing to the Executive Engineer and the Executive Engineer
may, if in his opinion there are reasonable grounds for granting extension, recommend
such extension as he may think necessary or proper. The decision of the competent
authority in this regard shall be final, and binding to the contractor. Any delay attributed to
Corporation, shall be thus compensated only by way of extending the limit.
15. COMPLETION CERTIFICATE
On completion of the work, the Contractor shall be furnished with Completion Certificate by
the Executive Engineer. No such certificate shall be given nor shall be the work considered
to be completed until works are taken over and/or duly tested and put to operation as the
case may be, nor until the work shall have been measured by the Engineer-in-Charge or
where the measurement have been taken by his subordinates until they have received the
approval of the Executive Engineer the said measurement being binding and conclusive
against the contractor.
16. EFFECT OF THE CERTIFICATE :
No payment shall be made for any work estimated to cost less than Rs.1,000 till after the
whole of said work shall have been completed and a certificate of completion given. But in
the case of works estimated to cost more than Rs.1,000, contractor shall on submitting a
monthly bill thereof, be entitled to receive payments. Proportionate to the part of the work
then approved and passed by the Engineer-in-Charge, whose certificate of such approval
and a passing of the sum so payable shall be final and conclusive against the contract. All
such intermediate payment shall be regarded as payment by way of advance against the
final payment only and not as payments for work actually done or completed and shall not
preclude the Engineer-in-charge from requiring bad, unsound, imperfect or unskillful work
to be removed and taken away and reconstructed or re-erected nor shall any such payment
be considered as admission of the due performance of the contract or any part thereof in
any respect of the occurring of the claim nor shall conclude, determine or effect in any way
the powers of the Engineer-in-Charge as to the final settlement and adjustment of the
accounts otherwise or in any other way, vary or affect the contract. The final bill shall be
submitted by the contractor within one month of the date fixed for completion of work;
otherwise the certificate of the Engineer-in-charge of the measurement and of total amount
otherwise the certificate of the Engineer-in-charge of the measurement and of total amount
payable for the work shall be final and binding on all parties.
17. PAYMENT TO CONTRACTORS :
The rates for several items of works estimated to cost more than Rs.1, 000 agreed to
within shall be valid only when the item concerned is accepted, having been completed full,
in accordance with the sanctioned specification. In case, where the items of the work, are
not accepted, as so completed, the Engineer-in-charge, may make payment on account of
EW- 283 PUR-F-006 RFQ-
such items at such reduced rates, as he may consider reasonable in the preparation of final
or running accounts bills and it will be binding to the contractor.
18. BILLS :
The Bill Shall be submitted by the contactor each month on or before the date fixed by the
Engineer-in-charge, for all works, executed in the previous month and the Engineer-in-
charge shall take or cause to be taken the requisite measurement for the purpose or having
the same verified and the claim so far as it is admissible, shall be adjusted, if possible,
within Fifteen days from the presentation of the bills. If the contractor does not submit the
bill, within the time fixed, as aforesaid, the Engineer-in-charge may depute a subordinate to
measure up the said work in the presence of the contractor or his duly authorized agent,
whose counter signature in the measurement shall be sufficient warrant and the Engineer-
in-charge may prepare a bill from such list which shall be binding on the contractor in all
respects. In case if contractor/ representative does not remain present on specified date for
taking measurement than EIC may take the measurement one sided and the same shall be
binding to the contractor irrespective whether he has signed or not.
19. SUPPLY OF MATERIALS TO CONTRACTOR [APPLICABLE ONLY WHERE MATERIAL
IS TO BE SUPPLIED BY CORPORATION AS MENTIONED IN SCHEDULE A ]
If the specification of the estimated work provides for use of any special description of
material to be supplied from the Corporation’s stores or if it is required that the contractor
shall use certain stores to be provided by the Engineer-in-charge, (such material and stores
and the prices to be charged thereof as hereinafter mentioned being so far as practicable
for the convenience of contractor but not so as in any way to control, the meaning or effect
of this contract specified in the schedule or memorandum hereto annexed). The contractors
shall be supplied with such materials and stores as may be required from time to time be
used by him for the purpose of the contract only and the value of the full quantity of
materials and stores so supplied shall be set off or deducted from any sum due or
thereafter to become due to the contractor, under the contract or otherwise or from the
security deposit or the proceeds of sale thereof if the deposit is held in government
securities the same or a sufficient portion thereof, shall be sold for the purpose. All
materials supplied to the contractor shall remain the absolute property of the Corporation
and shall on account be removed from the site of work and shall at all times be open to
inspection by the Engineer-in-charge. Any such materials unused and in perfectly good
condition at time of completion or determination of the contract shall be returned to the
Corporation’s store if the Engineer-in-charge so requires by notice in writing given under his
hand but the contractor shall not be entitled to return any such materials except with such
consent and he shall have no claim for compensation on account of any such materials
supplied to him as aforesaid but remaining unused by him or for any wastage in or
damaged thereto. The contractor shall be responsible for the loss, destruction or
deterioration of the materials, stores or articles supplied to him by the Corporation even if
such loss, destruction or deterioration has occurred under any circumstances whatsoever
beyond his control as if the materials, stores or articles so supplied were his property.
20. WORKS TO BE EXECUTED IN ACCORDANCE WITH SPECIFICATIONS, DRAWING,
ORDERS ETC.
The contractor shall execute the whole and every part of work in the most substantial and
workman like manner and both as regarding materials and in every other respect in strict
accordance with the specification. The contractor shall also confirm exactly, fully and
faithfully to the designs, drawings and instructions in writing relating to the work signed by
the Engineer-in-charge and lodged in his office and to which the contractor shall be entitled
to have access for the purpose of inspection at such office, or on the site of the work
during office hours and the contractor shall, if he so requires, be entitled at his own
expense to make or cause to be made copies of the specification and of all such designs,
drawings and instructions as aforesaid.
21. ALTERATIONS IN SPECIFICATIONS AND DESIGNS NOT TO INVALIDATE
EW- 283 PUR-F-006 RFQ-
The Executive Engineer shall have powers to make any alterations, or additions to the
original specification, designs and instructions that may appear to him to be necessary or
advisable during the progress of the work and the contractor shall be bound to carry out
the work in accordance with any instruction in this connection which may be given to him
in writing, signed by the Engineer-in-charge and such alterations shall not invalidate the
contract. Any additional work which the contractor may be directed to do in the manner
above specified as part of the work shall be carried out by the contractor on same
conditions in all respect on which he agreed to do the main works and at the same rates as
are specified in the tender for the main work.
Where, however, the work is to be executed according to the designs, drawings and the
specifications recommended by the contractor and accepted by the competent authority,
the alteration above referred to shall be within the scope of such designs, drawings and
specifications appended to the tender.
22. RATES FOR WORKS NOT ENTERED IN ESTIMATE OR SCHEDULE OF RATE OF THE
CORPORATION
If the additional and altered work includes any class of work for which no rate is specified
in this contract, then such class of work shall be carried out at the rates entered in the
Schedule of Rates of the Corporation or at the rate mutually agreed upon between the
Executive Engineer and the Contractor, whichever are lower. If the additional or altered
work for which no rate is entered in the Schedule of Rates of the Division is ordered to be
carried out before the rates agreed upon then the contractor within seven days of date of
receipt by him of the order to carry out the work should inform the Executive Engineer for
the rate which it is his intention to charge for such class of work and if the Executive
Engineer does not agree to this rate, he shall be noticed in writing, be at liberty to cancel
his order to carry out such class of work and arrange to carry it out in such manner as he
may consider advisable provided always that if the rates shall have been determined as
lastly herein before mentioned then in such case he shall only be entitled to be paid in
respect of the work carried out or expenditure incurred by him prior to the date of the
determination of the rate as aforesaid according to such rate or rates as shall be fixed by
the Executive Engineer in the event of disputes, the decision of the General Manager of the
Corporation will be final.
23. EXTENSION OF TIME LIMIT IN CONSEQUENCE OF ADDITION OR ALTERATION
The time limit for the work shall be extended in the proportion that the increase in its cost
occasioned by alterations or additions bears to the cost of the original contract work and
the certificate of the Engineer-in-charge as to such proportions shall be conclusive.
24. NO COMPENSATION FOR ALTERATION IN OR RESTRICTION OF WORK TO BE
CARRIED OUT
If at any time, after the execution of the contract documents, the Engineer-in-charge shall,
for any reason whatsoever, requires the whole or any part of the work, as specified in the
tender, to be stopped for any period or shall not require the whole or part of the work to
be carried out at all or to be carried out by the contractor, he shall give notice in writing of
the fact to the contractor who shall thereupon suspend or stop the work totally or partially
as the case may be in any such case, except as provided here under. The contractor shall
have no claim to any payment or compensation whatsoever on account of any loss in profit
or advantage which he might have derived from the execution, of the work in full but which
he did not so derive in consequence of the full amount of work not having been carried out
or on account of any loss that he may be put to on account of materials purchased or
agree to be purchased or for unemployment of labour recruited by him. He shall not also
have any claim for compensation by reason of any alterations having been made in the
original specification, drawings, designs and instructions which may involve any curtailment
of the work as originally contemplated. Where, however, materials have already been
purchased or agreed to be purchased by the contractor before receipt by him of said
notice, the Executive Engineer provided they are not in excess or requirement and are of
approved quality and/or shall be compensated for the loss, if any, that he may put to in
EW- 283 PUR-F-006 RFQ-
respect of materials agreed to be purchased by him. The amount of such compensation to
be determined by the Executive Engineer, whose decision shall be final. If the contractor
suffers any loss on account of his having to pay, his labour charges during the period,
during which the stoppage of work has been ordered under this clause the contractor shall
on application be entitled to such compensation on account of labour charges as the
Executive Engineer whose decision shall be final, may consider reasonable provided that
the contractor shall not be entitled to any compensation on account of labour charges if, in
the opinion of the Executive Engineer, the labour could have been employed by the
contractor elsewhere for the whole or part of the period during which the stoppage of the
work has been ordered as aforesaid.
25. NO CLAIM FOR COMPENSATION ON ACCOUNT OF LOSS DUE TO DELAY IN
SUPPLY OF MATERIALS BY CORPORATION
The contractor shall not be entitled to claim any compensation from Corporation for the
loss suffered by him on account of delay by Corporation in the supply of materials entered
in Schedule A where such delay is caused by:
Difficulties relating to supply of railway wagons.
Force Majeure
Act of God
Any other reasonable cause beyond the control of Corporation, including shortage of
materials to be supplied by the Corporation and difficulties in time by reaching at the site of
any materials equipment.
In the case of such delay in the supply of materials, Corporation shall grant such extension
of time for the completion of the works as shall appear to the Executive Engineer to be
reasonable in accordance with the circumstances of the case. The decision of the Executive
Engineer as to the extension of time shall be accepted as final by the contractor.
26. TIME LIMIT FOR COMPENSATION CLAIMS
Under no circumstances, whatsoever, shall the contractor be entitled to any compensation
from Corporation on any account unless the contractor has claimed in writing to the
Executive Engineer within one month of the cause thereof.
27. ACTION AND COMPENSATION PAYABLE IN CASE OF BAD WORK
If at any time, before the security deposit is refunded to the contractor, it shall appear to
the Executive Engineer or his subordinate in charge of the work that any work has been
executed with unsound, imperfect or unskillful workmanship or with materials of inferior
quality or that any materials or articles provided by him for the execution of the work are
unsound or of inferior quality to that contract for or are otherwise not in accordance with
the contract, it shall be lawful for Engineer-in-charge to intimate this fact in writing to the
contractor and then notwithstanding the fact that the work, materials, or articles
complained of, may have been inadvertently passed, certified and paid for, the contractor
shall be bound forthwith to rectify or remove and reconstruct the work so specified in
whole or any part, as the case may require or if so required shall remove the materials or
articles so specified and provided other suitable materials or articles at his own charge and
cost, and in the event of his failing to do so within a period to be specified by the Engineer-
in-charge in the written intimation aforesaid the contractor shall be liable to pay
compensation at the rate of one percent on the amount of the estimate for every day not
exceeding ten days during which the failure so continues and in the event of any such
failure as aforesaid, the Engineer-in-charge may rectify or remove or re-execute the work
or remove and replace the materials or articles complained of, as the case may be, at the
risk and expense in all respects of contractor should the Engineer-in-charge consider that
any such inferior work or materials as described above may be accepted, or made use of, it
shall be within his discretion to accept the same as such reduced rates as he may fix
Provided that in the case of any work of which visible check is not possible if the Engineer-
in-charge or his subordinate in charge of the work feels that such work has been executed
with unsound, imperfect or unskillful workmanship or with materials of inferior quality, he
EW- 283 PUR-F-006 RFQ-
shall take sample tests at random, cost of which shall have to be borne by the contractor
and if after taking such test part of such work is found to be defective in any respect or to
have been executed with materials of inferior quality then the contractor shall pay for the
whole work such amount as may be fixed by the office of the Engineer-in-charge on the
basis of the lowest quality of work found by him in such sample tests.
28. WORK TO BE OPENED TO INSPECTION, CONTRACTOR OR RESPONSIBLE AGENT
TO BE PRESENT.
All works under execution or in pursuance of the contract shall at all times be open to the
inspection and supervision of the Executive Engineer and his subordinate and contractor
shall at all times, during the usual working hours and at all other times at which reasonable
notice of the intention of the Executive Engineer or his subordinate to visit the works shall
have been given to the contractor, during which period either he should be present to
receive order and instruction, or have a responsible agent duly authorized agent shall be
considered to have the same force and effect as if they had been given to the contractor
29. NOTICE TO BE GIVEN BEFORE WORK IS COVERED UP
The contractor shall give not less than five days’ notice in writing to the Executive Engineer
or his subordinate in charge of the work, before covering up or otherwise placing beyond
the reach of measurement of any work, in order that the same may be measured and
correct dimensions thereof, taken before the same is so covered up or placed beyond the
reach of measurement and shall not be covered up or placed beyond the reach of
measurement and work without the consent in writing of Executive Engineer or his
Subordinate in charge of work. If any work shall be covered up or placed beyond the reach
without such notice having been given or consent obtained, the same shall be uncovered at
the contractor’s expense and in default thereof no payment or allowance shall be made for
such work or for the materials with which the same was executed.
30. CONTRACTOR’S LIABILITIES
The contractor shall supply, at his own cost, all materials (except such special materials, if
any as may be supplied from the Corporation stored in accordance with the contract).
Plant, tools, appliances, implements, ladders, cordage, tackle, scaffolding and any
temporary works which may be required for the proper execution of the work, in the
original, altered or substituted form and whether included in the specification and other
document forming part of the contract or referred to in these conditions or not and which
may be necessary for the purpose of satisfying and complying with the requirements of the
Engineer-in-charge as to any matter on which under these conditions, he is entitled to be
satisfied or which he is entitled to require together with carriage thereof to and from the
work. The contractor shall also supply without any charge the requisite number of persons
of setting out works and counting, weighting and assisting in the measurement of
examination at the time and from time to time of the work or materials, failing this the
same may be provided by the Engineer-in-charge at the expenses of the contractor and the
expenses may be deducted from any money due to the contractor under the contract or
from his security deposit or the proceeds of sale thereof or of a sufficient portion thereof,
the contractor shall provide all necessary fencing and light required to protect the public
from accident and shall also be bound to bear expenses of defense of every suit, action or
other legal proceedings of law that may be brought by any person for injury sustained.
Owing to neglecting of the above precautions and to pay any damage and cost which may
be awarded in such suit, action or proceedings to any such person or which may with the
consent of the contractor be paid in comprising any claim by any such person.
31. CONTRACTOR LIABLE FOR ALL DAMAGE
Compensation for all damage done intentionally or unintentionally by contractor’s laborer,
whether in or beyond the limit of Corporation’s property, shall be estimated by the Executive
Engineer or such other office as he may appoint and the estimates of the Executive
Engineer, subject to the decision of the Superintending Engineer, on appeal, shall be final
and the contractor shall be bound to pay the amount of the assessed compensation demand,
EW- 283 PUR-F-006 RFQ-
failing which, the same will be recovered from the contractor as damages or deducted by the
Engineer-in-charge from any sums that may be due to or become due from Corporation to
the contractor under this contract or otherwise.
The contactor shall bear the expenses of defending any action or other legal proceeding that
may be brought by any person for injury sustained by him owing to negligence of
precautions for prevent the spread of fire and he shall also pay any damage and cost that
may be awarded by the court, if in consequence
32. RESCISSION OF CONTRACT AND FORFEITURE OF DEPOSIT
The contractor shall not assign or sublet, without the written approval of the Engineer-in-
charge and if the contractor assign, or sublet his contract, or attempt to do so or become
insolvent or commence any proceedings to be adjudicated as insolvent or make any
composition with creditors, attempt to do so, the Engineer-in-charge may, by notice in
writing rescind the contract. Also, if any bribe, gratuity, gift, loan, perquisite, reward or
advantage pecuniary or otherwise shall either directly or indirectly be given, promised or
offered by the contractor or any of his servants, or agents, or any person to the employee of
the Corporation in any way relating to his office or indirectly interested in the contract, the
Executive Engineer may, by ten days’ notice in writing, rescind the contract. In the event of
a contract being rescinded the security deposit of the contractor shall there upon stand
forfeited and be absolutely at the disposal of the Corporation and the same consequences
shall ensure as if the contract has been rescinded under Clause 11 thereof and in addition
the contractor shall not be entitled to recover or be paid for any work thereof actually
performed under the contract.
33. COMPENSATION
All sums payable by a contractor by way of compensation under any of these conditions shall
be considered as a reasonable compensation to be applied to the use of Corporation without
reference to the actual loss or damage sustained and whether any damage has not been
sustained.
34. CHANGE IN THE CONSTITUTION OF FIRM TO BE NOTIFIED
In case of tender by partners of a Firm, any change in constitution of firm shall be forthwith
notified by the contractor to the Executive Engineer for his information.
35. WORKS UNDER DIRECTION OF SUPERINTENDING ENGINEER
All works to be executed under the contract shall be executed under the direction and
subject to the approval of Superintending Engineer /Engineer-in-charge for the time being
who shall be entitled to direct at what point or points and in what manner they are to be
commenced and from time to time to be carried on.
36. DECISION OF SUPERINTENDING ENGINEER TO BE FINAL
Except where otherwise specified in contract and subject to the power delegated to him by
Corporation under the Corporation’s rules, then in force, the decision of the Superintending
Engineer/EIC for the time being shall be final, conclusive and binding on all the
specifications, designs, drawings and instructions herein before mentioned and as to the
quality of workmanship or material used on or as to any other question, claim, right matter
or thing whatsoever in any way arising out of or relating to the contract, designs, drawings,
specifications, estimates, instructions, orders or these conditions or otherwise concerning,
the works or the execution or failure to execute the same, whether arising during the
progress of the work or after the completion or abandonment thereof.
37. Dispute Resolution Mechanism: For works contracts and composite Contracts, the
arbitration mechanism shall be governed by the Gujarat Public Works Contracts Disputes
Arbitration Tribunal Act, 1992 as per below details.
sub clause 37(1) Amicable Settlement : Any dispute, difference, controversy or claim
between the Parties arising out of or relating to this contract with reference to the
construction, interpretation, breach, termination or validity thereof (hereinafter referred as
"the Dispute") shall, upon the written request of either Party be referred to the authorized
representatives of the Disputing Parties for resolution. The authorized representatives shall
EW- 283 PUR-F-006 RFQ-
promptly meet and attempt to negotiate in good faith a resolution of the Dispute within
thirty days of the service of the request.
sub clause 37(2) Arbitration : If the Parties fail to amicably resolve the disputes or
differences or contrary claims as indicated herewith in sub clause (1) of Clause 37 arising
under or in connection with the present works contracts, whether pertaining to works
contracts alone or works and procurement both, the same shall be referred to arbitration
under the Gujarat Public Works Contracts Disputes Arbitration Tribunal Act, 1992."
38. STORES TO BE OBTAINED FROM CORPORATION [APPLICABLE ONLY WHERE
MATERIAL IS TO BE SUPPLIED BY CORPORATION AS MENTIONED IN SCHEDULE
The contractor shall obtain from the Corporation stores, such articles as are mentioned in
schedule “A” which may be required for the work or any part of the work or in making up
any articles required therefore or in connection therewith, unless he has obtained
permission in writing from the Executive Engineer or obtained such stores and articles from
elsewhere. The value of such stores and articles as may be supplied to the contractor by
the Engineer-in-charge will be debited to the contractor in his account at the rate shown in
the schedule “A” attached to the contract and if they are not entered in said Schedule, they
shall be debited to him at cost price which for the purpose of this contract shall include cost
of carriage and all other expenses whatsoever which may have to be incurred in obtaining
delivery of the same at the stores aforesaid and further overhead charges 15%.
The Contractor shall be responsible for the loss, destruction or deterioration of the
materials, stores or articles supplied to him by the Corporation, even if such loss,
destruction or deterioration has occurred under any circumstances whatsoever beyond his
control as if the materials, stores or articles so supplied were his property. The contractor
shall be responsible for returning the residual materials after completion of the contract and
it fails to return, the balance materials supplied to him by the Corporation, the cost of the
residual materials will be recovered from the contractor at the market rate or stock issue
rate whichever be higher at the time of materials account plus 15%.
39. LUMP SUMS IN ESTIMATE
When the estimate on which tender is made, includes lump sums in respect of parts of the
works the contractor shall be entitled to payment in respect of the items of works involved
or the part of the work in question at the same rates as are payable under this contract or
such items or if the part of work in question is not in the opinion of the Engineer-in-charge
capable of measurement the Engineer-in-charge may at his discretion pay the lump sum
amount entered in the estimate and the certificate in writing of the Engineer shall be final
and conclusive against the contractor with regard to any sum or sums payable to him under
the provision of this clause.
40. LUMP SUM TENDERS
Whenever lump sum tenders have been invited for buildings or other structures of the
same type, design, the contractor shall submit his bill stated in Clause No. 18 and the
Engineer-in-charge not below the rank of work, Executive Engineer shall certify by general
measurement or by other method considered suitable to him, the value of work done and
the contractor shall be paid monthly a sum equal to 90% of the total value the work so
certified, since the last payment, after deducting a part or whole of the secured advance if
not already paid for the materials utilized on the works. An additional secured advance for
any fresh materials utilized on the works. An additional secured advance for any fresh
materials brought on site will also be paid if certified by the officer not below the rank of
Executive Engineer. After the work is completed final bill would be paid on the certification
of officer not below the rank of Executive Engineer, that the work, is done according to
drawing and specifications attached to the tender. If any additions and alterations have
been carried out, detailed measurement in respect thereof shall be recorded and extra
payment or deductions are regulated as per item rates quoted by the contractor while
submitting the tender and if there are any items in the additions and alterations for which
the contractor has not quoted a rate, the payment shall be as per Clause 39 above
EW- 283 PUR-F-006 RFQ-
41. ACTION WHERE NO SPECIFICATION
In the case of any class of work for which there is no such specification as is mentioned,
such work shall be carried out in accordance with the PWD and in the event of there being
no PWD specification, the work shall be carried out in all respects in accordance with the
instructions and requirements of the Engineer-in-charge of the Corporation etc.
42. NO CLAIM FOR VARIATION IN QUANTITIES OR WORK
Quantities shown in the tender are approximate and no claim shall be entertained for
quantities of work actually executed, being either more or less up to any extent than those
entered in the tender or less than those entered in the tender or estimate.
43. NO CLAIM FOR COMPENSATION FOR DELAY IN STARTING WORK
No compensation shall be allowed for any delay caused into starting of work on account of
acquisition of land and in the case of clearance for works or any delay in according sanction
to estimates.
44. NO CLAIM FOR COMPENSATION FOR DELAY IN EXECUTION OF WORK
No compensation shall be allowed for any delays in execution of the work on account of
water standing in borrow pits or compartment. The rates are inclusive for hard or cracked
soil, excavation in mud, sub-soil water or water standing in borrow pits and no claim for
any extra rate shall be entertained unless otherwise expressly specified and mentioned in
the tender.
45. EMPLOYMENT OF TECHNICAL PERSONS:
The contractor shall keep one full time qualified Civil Engineer at the site, who shall be fully
authorized to receive and comply with such instructions, as given by the Executive
Engineer. The contractor shall intimate the name of such Engineer with his qualifications
and experience. The Executive Engineer shall have the right to demand the removal of any
technical personnel, skilled or unskilled workmen, who in his opinion are considered to
cause bad workmanship in the execution of works or to cause indiscipline.
46. INDUSTRIAL LABOUR LAWS
LABOUR LAWS TERMS AND CONDITIONS
1) The contractor should not be allowed to engage 50 or more contract labourers without
valid labour license under The Contract Labour (Regulation & Abolition) Act, 1970 & The
Contract Labour (R & R)(Gujarat) Rules 1972 from the Assistant Commissioner of Labour
Gandhinagar (the said number i.e. 50 or more includes Supervisor and other staff)
2) The contractors shall have to obtain group insurance policy under Employee Compensation
Act, 2010 before starting the work.
3) All Contractors shall have to make the payment of wages to the Contract Labours engaged
by them, on or before expiry of 7th of every month through either by A/c Payee Cheque or
by crediting the wages in their bank accounts. The Contractor shall supply copy of Bank
Statement duly stamped by the Concerned Bank as a token of proof towards payment of
Wages to HR Department. Contractor shall intimate the Date & Mode of Payment in
advance to LWO / IRO. Contractor are also required to get the wage register of respective
month certified from LWO / IRO as per the provision laid down under the Contract Labour
(R&A) Act, 1970. Any default will result in cancellation of contract forthwith or else the
contractor shall be punishable to the extent of Rs. 100/- per day by way of fine.
4) Apart from payment of wages through bank, contractors should also make all other
payments like advances, bonus, leave encashment etc. to their labours through Banks.
5) The contractor shall give his telephone number, address, emails to the GSECL authority, so
that in case of labour unrest etc. the contractor can be contacted.
6) Maternity benefits and leave as per the provision of the Maternity Benefits Act.
7) If any workman engage by contractor meet with fatal or non-fatal accident while on duty,
then contractor shall be liable to pay compensation to legal heir or to the workman as case
may be as per Employees compensation act,2010.
8) The attendance of all contract labours of ARC / BRC contracts is to be monitored through
Bio-metric punching system only.It shall be the duty of the Contractor or his Supervisor to
ensure the supply of specified number of manpower and to ensure their Bio-Metric
EW- 283 PUR-F-006 RFQ-
punching and reporting at the location of work. Non-reporting or non-availability at the
location of work shall be considered as non-punching and suitable actions can be taken by
User department, including levy of penalty.
9) The contractors shall comply with the provisions of E.S.I. Act wherever applicable as per
the prevailing provisions of the Act and as amended from time to time.
10) The contractor shall be responsible and liable to pay difference in wages, if any, and /or
observe the revised service conditions that may be awarded by the Honorable court
effective from the date directed in the award to concerned Protected workmen.
11) The contractor shall require to maintain regular Labour record/ documents/ registers and
shall pay all benefits to Labour force as per applicable statutory laws and contractor shall
require to obtain clearance certificates to this effect from HR Officer of GSECL.
12) The contractor will make arrangements at his own cost to insure all men, materials and
equipment employed for this work. The GSECL will not be responsible for any loss or
damage either to the contractor’s personnel or his equipment.
13) Dispute, if any, taking place between the contractor and laborers must be intimated to
LWO/IRO/DGM, GTPS immediately.
14) Any casualty will also have to be borne by the contractor for the period the contract
continues.
15) The Contractor shall also indemnify GSECL for injury or damage to third party other than
employees of the GSECL, contractor or sub – contractor.
16) Contractor / Agency shall have to issue the contractual appointment letter for a specific
period to their Labour engaged during the contract period each and every instance &
should narrated clear out terms & conditions for the liabilities of the concerned employees.
17) Contractor shall produce certified copy of appointment letter of each worker deployed at
GSECL, GTPS.
18) Gate pass shall not be issued without Employee insurance for work inside or outside of
factory. Engineer in charge has to ensure employee compensation insurance before
commencement of work.
19) Wages rates for contract laborers are applicable as per The Minimum Wages Act, 1948 &
The Minimum Wages (Gujarat) Rules 1961 The contractor shall have to pay wages to
workers as notified by Government of Gujarat., from time to time.
20) It should be ensured that all the labours engaged by contractor are covered under the
Employees' Provident Funds & Miscellaneous Provisions Act, 1952 and their contributions
are remitted regularly to the concerned RPFC. The Xerox copies of challan along with ECR
and remittance slip in this regards should be submitted regularly in G.S.E.C.L. office.
21) In case the contractor having more than one contract in the same Power station, the
contractor shall have to submit contract wise separate list of the workmen & maintain
relevant registers and records accordingly and submit the same to the Concerned Section &
HR department as per applicable labour laws.
22) The Interstate Migrant Workers Act, 1979 & The Inter state Migrant Workers (Gujarat)
Rules 1981 shall be complied by contractor in case 05 or more outstate worker/ employees
is required to engaged at GSECL GTPS TPS.
23) Person below the age of 18 years and above 60 years should not be employed for the
24) No female worker shall be employed in the night shift between 7.00 P.M. to
25) The contractor shall maintain a valid labour license under the contract labour (Regulation
and Abolition) Act for employing necessary man power to be required by contractor. In the
absence of such license the contract shall be liable to be terminated without assigning any
EW- 283 PUR-F-006 RFQ-
reasons thereof.
26) The contractor shall at his own expense comply with all labour laws and keep the
G.S.E.C.L. Indemnified in respect thereof.
27) Contractor shall obtain valid Identity cards for their workmen as prescribed under the
Factories Act 1948 and Gujarat Factories Rules, 1963 from Factory Manager or Authorized
representative of Company in prescribed form by submitting required documents before
commencement of work.
28) Payment of retrenchment compensation, Notice pay and other liabilities as per The
Industrial Disputes Act, 1947 & Gujarat Rules 1966. Any payment to the contractor's
labours arising out of any claim or disputes under the Industrial Dispute Act 1947 or any
other labour laws.
29) Payment of compensation in case of accidental injury shall be made by contractor as per
the Employee Compensation Act,
30) If the female workmen are more than 30 numbers engaged then provision of crèches and
Maternity leave as per the provision of the Maternity benefit Act, 1961shall be complied.
31) Contractor shall comply the Provision laid down under the payment of Bonus Act, 1965 for
their workmen engaged at GTPS and submit the relevant records to GSECL office.
32) The contractor must possess separate P.F. code for the above subject work.
33) Provisions of The Building and other Construction Workers (Regulation of Employment and
Conditions of Service) Act, 1996 and Gujarat Building and Other Construction Workers
(Regulation of Employment and Condition of Service) Rules, 2003 shall be complied by
contractor if contract is awarded outside the factory premises i.e. colony area & other than
factory premises before execution of work compliance shall be submitted if 10 or more
workers are engaged .Necessary documents such as registration certificate under BOCW
Act etc shall be submitted by contractor. Contractor shall obtain Gate passes for the work
of carried out in Colony area & other than factory premises from Security Section after
following due procedure from GSECL Office.
34) Paid leave facility at the rate of one day for every 20 days worked by the contract labour
shall be provided by the contractor to his workers as per factory act. ,1948. It shall be duly
verified and approved/certified by the authorized officer of the GSECL.
35) The contractor shall employ adequate number of experienced staff at site for daily
supervision and for maintaining of various registers and records required under the law
and contracts. No payment for such supervision shall be admissible.
36) If any Agency found having involved in any kind of malpractices such as less payment to its
employees, irregularity in computation of duty hours, less deduction of Provident Fund &
default in other statutory compliances or in maintaining required manpower as per Contract
terms or failure in legal compliances the Company will have the right to terminate the
contract of such Agency immediately without giving any notice. In such circumstances
security deposit shall be forfeited.
37) If any complaints related to legal /statutory compliances received against contractor from
its workmen or otherwise, contractor shall be responsible to resolve the same immediately,
non-resolving the same company shall withheld his pending dues until the complaints is
38) In case the contractor’s work is found unsatisfactory or contractor abandons, stops, or
creates hurdle during the contract period, the GSECL will be entitled to terminate the
contract. In case of default the work will be got done through other agencies at the risk
and cost of contractor and GSECL shall be entitled to recover such expenses from
defaulting contractor by such methods as deemed fit. The contractor shall not however, be
entitled to terminate the contract or stop works undertaken by him before expiry of the
contract period due to any reason whatsoever.
39) Under the contract, the contractor shall either himself be present on site or should
nominate persons in writing, who must be available at site and who should be authorized
to take decision about the works and mutual consultation from time to time. In the
EW- 283 PUR-F-006 RFQ-
absence of any responsible man of contractor at the time of any emergency adhoc decision
of Engineer-in-charge will be binding to the contractor
40) CONTRACTOR TO INDEMNIFY THE GSECL
The contractor shall indemnify and keep indemnified the GSECL, and every member,
officer and employees of the GSECL, also Engineer-in-charge and his staff against all
actions, proceedings, claims, demands, costs and expenses whatsoever arising out of or in
connection with the matter referred in above clauses and elsewhere and against all
actions, claims demands, cost and expenses which may be made against the GSECL by
any workman/ employees of contractor or any sub contractor and or from any liability any
wise to any workman/employees of the contractor or sub-contractor under any laws, rules
or regulation having in force of law including but not limited to claims against the owner
under workmen compensation Act, 1923. The Employee’s Provident Fund Act.1952, and/or
the contract labour (Abolition and Regulation)Act, 1970 & various labour laws applicable.
The GSECL shall not be liable for or in respect of or in consequence of any accident or
injury to any workmen or other person in the employment of the contractor or his sub-
contractor, and the contractor shall indemnify and keep indemnified the GSECL against all
such damage and compensation and against all claims, demands proceedings costs,
charges and expenses whatsoever in respect of or in relation thereto.
41) EMPLOYEE'S COMPENSATION & EMPLOYER'S LIABILITY INSURANCE
The contractor has to take Employee Insurance under the Employee
Compensation Act, 2010 for all workmen engaged by him for GSECL work contract
(Location & Order wise) and copy of the same shall be produced to GSECL prior to start
work. Insurance shall be affected for all the contractor’s employees engaged in the
execution of these contracts. If any of the work is sublet, the contractor shall required the
sub-contractor to provide Employee's compensation and Employer's liability insurance for
the latter’s employees unless such employees are covered under the contractor’s
insurance. It shall be liability of contractor for employees of his sub-contractor.
42) Any other rules and regulation, conditions, Circulars etc., that are in force at present and
that may be framed by the GSECL From time to time in connection with contracts will be
binding and acceptable to contractor.
43) All relevant records i.e. registers, forms, valid licenses etc shall be maintained up to date as
per applicable all labour laws and kept ready at GSECL site office for inspection at any time
or submitted in-time to the concerned authorities as per applicable various labour laws by
contractor.
44) It is the responsibility of the contractor to ensure that contractor’s employees maintain
strict discipline as regards security, methods of safe working etc, and not to cause any
hindrance to smooth running of power station or in execution of duties by GSECL staff. Any
lapse in this regard will be viewed seriously and contract is liable to be terminated. If any
of contractor’s staff is found unsuitable or not behaving properly, the contractor shall have
to remove him from the work-site on demand by GSECL. To keep harmonious industrial
relations amongst contract labours is the sole responsibility of the contractor. Any breach
of the same will be viewed seriously.
45) Before starting the work, the contractor should contact Industrial Relation Officer/ Labour
Welfare Officer for fulfilling Labour Laws Compliances and obtaining the gate passes of all
contract labourers as per procedure laid down.
46) The contractor shall deposit 15 days salary at the rate of last drawn salary for every
completed year of services for each worker for the liabilities of the gratuity. (* applicable to
ARC/BRC works contract only).
The above instructions should be followed scrupulously to avoid undue litigation for non
Compliance of Labour Law.
Follow the following procedure at each milestone for the execution of works contract.
(A) On Commencement of Contractual Work:
(1) The Contractors shall have to obtain Photo-Gate-Pass as per Factory Act, 1948 before the
commencement of contractual work awarded. Contractor shall have to apply for the gate
EW- 283 PUR-F-006 RFQ-
passes in triplicate in a prescribed application form which is to be available with user
Section for the entry of workmen in the premises of GSECL including Colony premises.
(2) Such application shall have to be proceed for the approval of Factory Manager. After
obtaining approval of Factory Manager, contractor shall have to prepare the Gate Passes
and obtain the signature of Factory Manager / Authorized representative of company as
per factory Act,1948.
(3) If Labours are required to be engaged in Emergency during Public Holiday or any other
day, Contractors Can apply for Temporary Gate-Pass for the maximum period of only three
days with recommendation of respective EE/SE and the same shall have to be regularized
after following the procedure of Gate Pass applications by Chief Engineer. It is to note that
No Temporary Gate-Pass shall be issued for the work other than acute emergency to carry
out the work in power station premises. Emergency work is to be justified by concerned
user section and same shall be approved by Chief Engineer.
(4) The Contractor shall have to obtain the Group Insurance Policy under the Employee
Compensation Act, 1923 prior to commencement of work. No pass whether temporary or
Valid shall be issued without insurance policy under Employee compensation Act,2010
(5) The Contractor who intend to engaged 50 or more labours to carry out the awarded
contractual work then necessary - Form No. V under the Contract Labour (R& A) Act,
/ Form No. VI under the Interstate Migrant worker (employment regulation) rule 1979 as
applicable is to be obtained from HR Department for the purpose of obtaining Labour
License from the Licensing Authority.
(6) Contractor shall submit Registration certificate under The Building and other Construction
Workers (Regulation of Employment and Conditions of Service) Act, 1996 and Gujarat
Building and Other Construction Workers (Regulation of Employment and Condition of
Service) Rules, 2003 if contract is awarded outside the factory premises i.e. colony area &
other than factory premises before execution of work if 10 or more workers are engaged.
(B) During Contractual Work under the progress:
(1) Bill Recording Officer/Engineer of User department shall have to ensure as to whether
contractor has engaged minimum number of contract workmen per day as per the terms
of work order.
(2) All Contractors shall have to make the payment of wages to the Contract Labours engaged
by them on or before expiry of 7th of every month through either by A/c Payee Cheque or
by crediting the wages in their bank accounts preferably situated in the premises of
GSECL. The Contractor shall supply copy of Bank Statement duly stamped by the
Concerned Bank as a token of proof towards payment of Wages to HR Department.
(3) Contractors has to comply & maintain All statutory documents / registers at site under the
provision of labour laws such as CLRA Act, EPF & MP Act,1952, Minimum wages Act,
Payment of wages Act, Bonus Act, Gratuity Act, Factory Act, etc & other applicable labour
(C) Submission of Statutory documents to ensure the compliances:
1) The Contractor shall have to submit following statutory documents, work order wise,
under the labour laws with invoice to the recording officer of user department for ensuring
the compliances of provision of labour laws for the respective execution of contract period
and same is required to be forwarded to HR Department in Office note .(Copy attached).
List of documents are given below:
site (duly signed & stamp by Contractor and sub- contractor) - Form XVI.
2. Copy of Wage Payment Sheet – with signature of workmen, (duly signed & stamped by
Contractor sub-contractor)- Form XVII.
3. Copy of Bank Statement of Wage Payment for the proof of wage payment (Duly signed &
Stamp by Concern Bank and contractor and sub contractor
4. Copy of PF Challan along with ECR Statement of respective period. (High light n
employees in ECR )
EW- 283 PUR-F-006 RFQ-
5. EPF Remittance Slip
6. Bonus register with payment details ( If Applicable)
7. Leave Encashment Register with payment details (If applicable )
8. Undertaking for labour law compliances on non- judicial stamp paper of Rs.300/- to be
submitted with notarized at the time of processing the final bill.
Muster Roll- Form No. XVI & Wage Register – Form No XVII as Prescribed under the
Contract Labour (R&A) Act, 1970 & rules thereof.
2) The Recording Officer/ Engineer of User department shall furnish the details and statutory
documents in the form of prescribed Office Note as enclosed in Annexure ‘’A’’ and the
same should be submitted to LWO / IRO/PO /DGM for onward action. (Copy Enclosed) .
3) In case of running contracts, if the contractor does not fulfill the requirement of
documents (PF Challan, Wage Registers etc), RA Bill shall not be processed until the
documents are submitted.
4) On submission of relevant documents to LWO /IRO/PO/DGM by Office Note. The same will
be intimated to Accounts Section for Compliances of Labour Laws.
5) If contractor failed to submit above documents in that case his payment of Bill shall be
withheld by GSECL, GTPS and on submission of the required documents the said bill shall
be released by GSECL GTPS.
6) Original copies of above mentioned documents and other legal documents as per
requirement shall be produced before Dy. G.M. (HR) / IRO / LWO / In-charge of H.R.
Department as and when demanded.
7) The GSECL will be entitled to deduct directly from the bill to be paid to the contractor, any
sum or sums payable by the contractor and which sum/sumsthe GSECL is required to pay
as a principal employer on account contractor’s default in respect of all liabilities referred
to in above clauses.
8) GSECL shall entitled to fulfill statutory liabilities under applicable laws being a principal
employer if contractor, its Sub Contractor fails to comply statutory compliance towards his
workmen. The amount of the same can be recovered from pending dues of contractor
with appropriate penalty and administrative charges / Service charges.
9) Office correspondence will be carried out in English / Gujarati. The English version will be
the correct one and the same only will held good for legal matters.
10) Any other rules and regulation, conditions, etc., that are in force at present and that may
be framed by the GSECL From time to time in connection with contracts will be binding
and acceptable to contractor.
11) Contractor have to follow gate pass procedure in view of guideline issued by GSECL
Corporate Office vide letter No. GSECL/CEG/Corporate Safety/Gate Pass Procedure/1029
Dtd. 30.05.2019 (Performa of Gate Pass is attached herewith).
12) In view of GSECL Corporate Office Circular No. GSECL / CEG / G.I / Circular / Works/815
Dtd. 02.05.2019 Contractor have to follow all the terms and condition / guideline related
to contract labour management system such as Biometric punching, compliance to various
labour laws, regular submission of statutory documents etc. for obtaining no objection
certificate from HR.
13) As per tender terms and conditions. In case of contractor or OEM/ OES are permitted to
perform the works portion through sub-contractor, It would be necessary for such OEM/
OES to submit Declaration cum Indemnity Bond in specified format on Rs.300/ Non judicial
stamp paper and Bills submitted by the OEM/ OES on behalf of subcontractor shall be
processed only by complying statutory provision under applicable acts.
14) If any problem may arise for payment of wages through bank, same may inform to Chief
Engineer (Gen.) and after approval only , the payment shall be disbursed in presence of
the GSECL representative i.e. HR officer during the working hours in the factory premises
and the contractor shall get the entries certified in the register of wages by the
representative of the GSECL
EW- 283 PUR-F-006 RFQ-
15) During the tenure of work order, if by order of Court any workman engaged by
them declared as protected workman or during the pendency of proceedings at
court, then concerned contractor shall be binding to maintain status-quo until
further order of court.
16) Nothing in the contract document stated shall anywise construe any work
man/employees of the contractor or sub-contractors as or to be workman
employee of the Owner or place obligatory liability in respect of any such
workman/employees upon GSECL.
On Non-Judicial Stamp Paper of Rs.
To be submitted with NOTORIZED at the time of final bill
UNDERTAKING FOR LABOUR LAW COMPLIANCES
I, Proprietor / Owner / Partner / Authorized
Agent of M/s. do hereby declare and undertake as
1. That in capacity of independent contractor for M/s.
(Sub-Contractor of M/s. ) worked as
Contractor at GSECL, GTPS Thermal Power Station for the nature of work of
against Work Order
No. Dt. ., I have
complied with the provisions of all laws as applicable. I have paid the wages for the month/s
of my contractual period which is/are not less than the minimum rates as applicable, to all
my employee/s and no other dues are payable to my employee/s.
2. That I have covered all the eligible employee/s under the Employees’ Provident Funds and
Miscellaneous Provisions Act, 1952 and deposited the contributions under my P.F. Code No.
Place: for the month/s of my contractual
period and as such no amount towards contributions whatever is payable.
3. I further declare and undertake that in case any liability pertaining to any of my worker,
labour, employee/s is/are to be discharged by the Principal Employer i.e. Gujarat State
Electricity Corporation Limited, GTPS due to my lapse, I undertake to reimburse the same or
the Principal Employer is authorized to deduct the same from my dues as payable.
4. I further declare and undertake the legal consequences which may arise in future under the
said work awarded, and I bound myself to resolve the same at the risk and cost of M/s.
EW- 283 PUR-F-006 RFQ-
EW- 283 PUR-F-006 RFQ-
EW- 283 PUR-F-006 RFQ-
EW- 283 PUR-F-006 RFQ-
EW- 283 PUR-F-006 RFQ-
47. MATTERS RELATED TO EXECUTION OF WORK:
a) Work shall commence from the date given in letter to commence the work by EIC at
site. The Contractor shall make all necessary arrangements at site to mobilize labour,
operators, divers and materials and maintain necessary number of machinery and
equipment, barge, pontoons etc., to guarantee the agreed rate of progress of work as per
b) A detailed work schedule showing how he proposes to carry out the work, specifically
mentioning time periods as well as date of commencement and completion of each activity
and such approved schedules must be strictly adhered to by the CONTRACTOR. After the
owner has agreed with the schedule, the Contractor shall prepare detailed program of
each work front/activity breaking it down giving daily quantifiable/measure of progress.
The schedules are to be reviewed periodically with the OWNER / ENGINEER to ensure that
the completion date will be met or to institute corrective steps (at no extra cost to the
ENGINEER) to adhere to the completion dates. The OWNER reserves the right to revise
the schedule at his discretion in order to keep up to the completion date and to suit the
project requirement and such alterations shall not entitle the CONTRACTOR to any extra
c) A work schedule with PERT / Bar Chart for carrying out the work in prescribed time
limit mentioning date of commencement, activity to be carried with its time period,
starting & finishing event for each activity, completion of total project in critical path etc,
shall be jointly fixed and approved by the GSECL. Such approved schedules must be
strictly adhered by the Contractor.
d) After the GSECL has agreed with the schedule, the Contractor shall prepare detailed
program of each work front / activity breaking it down to daily quantifiable measure of
progress. The schedules are to be reviewed periodically with the Owner / E.I.C to ensure
that the completion date will be met or to institute corrective steps (at no extra cost to the
GSECL) to adhere to the completion dates. The Owner reserves the right to revise the
schedule at his discretion in order to keep up to the completion date and to suit the
project requirement and such alterations shall not entitle the Contractor to any extra
e) The GSECL reserves the right to delete any item of schedule-B for which contractor shall
not have any right to claim on this account.
f) One permanent reference bench mark and a reference base line shall be given for lay out
of work, which shall be maintained without disturbance by the CONTRACTOR during the
tenure of the contract. CONTRACTOR shall establish local bench marks as directed by the
ENGINEER IN CHARGE.
g) The contract or any part thereof shall not be subject to change without the written
permission of the Chief Engineer (Gen.) GSECL, GANDHINAGAR TPS or his authorized
representatives.
h) During the execution of the work if it is found that the work is not progressing as per the
scheduled program approved by the GSECL & planned by the contractor, due to the
reasons attributable to the contractor, suitable action shall be taken as per Clauses in this
tender elsewhere & other relevant clauses appearing in the section of “Terms & condition
of tender & works contract, Legal conditions of works contract” of tender document. And
the GSECL may also take such action as it may deem fit to ensure that the work is
completed in time at Risk and Cost of the contractor.
i) Contractor shall attend meetings at EIC's office at site or any other place as fixed by the
EIC, as and when required for review, discussion, coordination etc. Attending these
meetings shall be obligatory on the part of the Contractor, at no cost to the GSECL.
j) The Contractor shall take all requisite & necessary care to observe that no damage is
caused to the existing, pumps, existing works, service road, or any other structure etc. For
any damage to the existing structures of the GSECL, the Contractor shall be held
responsible and he will have to rectify the damage immediately up to the satisfaction of
Engineer in Charge, at his own cost.
k) The work shall be completed within the period stipulated in the contract. & site clearance
arranged according to the progress of work at site. Therefore, the contractor has to
organize & coordinate the work to suit these circumstantial conditions. In the event of any
delay due to the above or due to any other reason not attributable to the contractor,
reasonable extension in completing the work may be given at the discretion and as
decided by the GSECL but no compensation or idle charges will be payable to the
EW- 283 PUR-F-006 RFQ-
contractor on this account or any site conditions under any circumstances.
l) No idle charges shall be entertained by GSECL for any site condition or any circumstances.
The corporation will not pay any type of advances including mobilization advance
48. RECOVERIES:
a) In case of any damage to equipment / machinery or structure / building of GSECL or any
public property due to negligence of contractor or any other reasons attributed to
contractor, the decision of E.I.C. regarding the amount of recovery shall be final.
b) If the contractor fails to execute the work as per direction of E.I.C. within the time frame
given, the GSECL shall get the work done through any other contractor at the risk and
cost of the contractor and the cost of execution of such work along with 15% overhead
charges shall be deducted from contractor’s monthly bill over and above recovery as per
c) Recoveries due from the contractor, up to the end of the month previous to the one in
which the bill is prepared shall be made from bills approved for payment every month or
at other periods when the bills are prepared, for the various items in the following
order of priorities and extents.
d) Deduction on account of security deposit in full together with shortage, if any, to be made
e) Penalty in full, if levied.
f) Expenditure, if any, incurred by the Corporation on Contractor’s behalf in labour or
materials in full.
g) Charges for services such as water and power supply etc. in full.
h) Charge on account of supply of materials like cement and steel in case of shortages found
in balance or excess consumption than specified.
i) Hire charges for Corporation or Government machinery if any.
j) Recoveries of advance and secured payment or payments for preliminary work in full or
the installment due if and as the same as may have been allowed.
k) Rent recovery on account of allotting quarters on rent as per Corporation’s rules.
l) Income tax and sales tax in full as per Government rules.
m) Outstanding recoveries in respect of other contracts awarded by the Corporation if any.
n) Other recoveries. (If any)
49. WORK TO BE EXECUTED TO THE SATISFACTION OF THE ENGINEER -IN-
The contractor shall proceed with the work with diligence and expedition and the
whole of the work herein specified as well as the mode of execution shall be under
the supervision and direction and shall be carried on to the entire satisfaction of the
Engineer-in-charge, who shall have full power to order the contractor to alter, enlarge
or diminish the form, dimensions, positions, or quantities of any of the work or to make
use of material and workman-ship of different descriptions and qualities from this
herein specified.
The whole of the works, together with any temporary works, associated therewith, shall
be carried on in the most substantial proper and mannered workman like manner, with
the best materials and workmanship and to the entire satisfaction of the Engineer-in-
charge and in such order of time as he may direct. The contractor shall attend to and
execute without delay all orders and instruction which may from time to time be issued by
the Engineer-in-charge.
50. MATERIALS WORKMANSHIP etc.:
The work shall be executed in thoroughly substantial manner with material and
workmanship of best quality and strictly in accordance with the specifications and with
the drawings, or with such other drawings or written instruction as may from time to time
be furnished to the contractor, in accordance with terms of this contract and shall be
completed in every respect with all materials and workmanship implied and necessary
according to the fair interpretation and meaning of the same and should there be any
discrepancy between the drawings and specifications or any difference or disputes as to
the dimensions to be worked to or the quality of the materials to be used, or the mode of
doing periodical quantity of the work to be executed or with respect to any subject arising
out of this contract, the decision of the Engineer-in-charge shall be final and binding on all
parties. Rejected material shall be so disposed off as to obviate any possibility of their use
on works. The place, method and period of disposal shall be as directed by the Engineer-
in-charge.
51. SAMPLES OF DESCRIPTIVE DATE:
Samples of descriptive date, requiring approval, shall be submitted by contractor to the
EW- 283 PUR-F-006 RFQ-
Engineer-in-charge in good time before the use of such material for inspection and
permission of testing if required. The samples shall be properly marked to show the
name of the material, manufacture, place of origin, and place where to be used etc.
Failure of any sample to pass specified tests will be sufficient cause for the refusal to
consider any further sample from the same source.
52. FENCING AND LIGHTING AND VENTILATION
Except as herein after provided, the contractor shall unless otherwise specified, be
responsible for the proper fencing, guarding, lighting and taking of the necessary safety
measures for all works comprised in the contract and or the proper provision of
temporary roadway, footways, guards fences, caution notices etc. as far as the same
may be rendered necessary by reasons for the work for the accommodation and
protection of workman foot passenger or other traffic and of the owners and occupiers
of adjacent property and of the public and shall remain responsible for any
accidents that may occur on account of his failure to take proper and timely
precautions.
All the arrangements made for fencing, lighting and ventilation shall be maintained by
the contractor throughout the tendency of the contract till physical taking over of the
work by the department.
53. LIABILITY FOR DAMAGE TO WORKS OR PLANTS
The contractor shall during, the progress of the work, properly cover up and protect
the work, and plant, and materials placed at his disposal or acquired for him by
the Corporation, from injury by exposure to the weather, or any cause what so ever and
shall take every reasonable proper timely and useful precaution against accident or injury
to the same from any cause and shall be and remain answerable and liable for all
accidents, or injuries thereto which until the same be or be deemed to be, taken over by
the Corporation, may arise or be occasioned by the acts or omissions of the contractor or
his workmen of sub-contractors, and all losses and damages to the works or such
plant or material arising from such accidents or injuries as aforesaid shall be made good in
the most complete and substantial manner by and at the sole cost of the contractor and to
the reasonable satisfaction of the Engineer-in-charge. If the contractor fails to make
good such losses & damages within the time given by the Engineer-in-charge, the
Corporation shall be at liberty to recover the amount fixed by the Engineer-in-charge for
such losses or damages or any part thereof by deducting it from any sum due by the
Corporation to the contractor under this contract or otherwise.
Further the contractor shall, at all time, protect and preserve all materials, plant and
equipment that he may himself have procured for the execution of the work. All reasonable
requests of the Engineer-in-charge to enclose or especially protect any of the above shall be
expeditiously compiled with.
If the Engineer-in-charge considers that the work or materials or plant is not sufficiently
protected by the contractor, he shall be entitled to arrange for such protection at his
unfettered discretion and recover the cost thereof from the contractor.
Until the work shall be or be deemed to be taken, over as aforesaid, the contractor shall
also be liable for and shall be deemed to have indemnified the Corporation in respect of all
damage or injury to any person or any property of the Corporation or of others, occasioned
by the negligence of the contractor or his workmen, or his sub-contractor, or by
defective design, work or materials.
54. EXPLOSIVE PROCUREMENT AND STORAGE (IF APPLICABLE)
i) Explosives, petrol, oils, fuels and other inflammable materials shall be stored strictly in
accordance with the rule of the Explosive Department.
ii) The contractor shall at his own expense construct and maintain, proper magazines which
are required for the storage of explosive and arrange for proper storage facilities for oils,
fuels etc. for use in connection with the work.
iii) The contractor shall at his own expense obtain such license or licenses as may be
necessary for strong and using explosives, oils, fuels etc. The department shall not take any
responsibility whatsoever in connection with the storage or use of explosives on the site, or
any accident or occurrence whatsoever in connection therewith. All operation of the
contractor in which or for which Explosives are employed shall be at risk of contractor and
upon his own responsibility.
EW- 283 PUR-F-006 RFQ-
55. MATERIALS TOOLS AND PLANT BROUGHT ON THE SITE OF WORK
All materials, tools and tackle of the contractor brought to and delivered upon the site for
the purpose of the work shall from the time of their being so brought shall be deemed to
be the property of the Corporation in its possession to be used for the purpose of the
work and for that purpose only and shall not on any account be removed or taken away
by the contractor or any other person without the written permission of the Engineer-in-
charge but the contractor shall nevertheless be solely liable and responsible for and
loss destruction thereof or damage thereto. The Corporation shall have a lien on such
materials, tools and tackle for any sum of sums which may at any time prior to the
completion of the works be due or owing to the Corporation by the contractor, under in
respect of and dispose of any such materials, tools and tackle in such manner as the
Corporation may think fit and to apply the proceeding in or towards the satisfaction of
such sum or sums so due or owing as aforesaid but subject to such lien and power of
sale and disposal such surplus materials, tools and tackle shall belong to the contractor
and may be removed and disposed off by him as he may think fit.
56. ACCESS TO SITE AND WORK ON SITE
The Engineer-in-charge or his authorized representative may if he consider fit from time
to time enter upon any lands which may be in the possession of the contractor under
this contract, for the purpose of executing any work not included in this contract and
may execute such work not included in this contract by agents, or by other contractors
at his option and the contractor shall in accordance with the requirements of the
Engineer-in-charge, afford all reasonable facilities for execution of the works including
occupation of lands by structure or otherwise for any other contractor employed by the
Corporation and his workmen or for the workmen of the Corporation who may be
employed in the execution on or near the site of the work not included in the
contractor’s any contract in connection with or ancillary to the works and in default, the
contractor shall be liable to the Corporation for any delay or expense incurred by
reason of such default. Provided always that if the exercise of those power shall cause
any damage to the contractor he may within fifteen days of such damage arising make a
statement of the same to the Engineer-in-charge who shall from time to time assess the
value in his Judgment of such damage and the Corporation shall from time to time shall
pay to the contractor the amounts (if any accepted as justified) by the Engineer-in-
charge. The contractor shall not however, on account of any such modified, new or extra
work executed by or for the same of the Corporation be entitled to claim relief from the
obligation to execute other works.
57. INSPECTION OF WORKS
The Engineer-in-charge or his duly authorized agent shall have at all time full power to
inspect the works, wherever in progress, either on the site, on the contractor's premises
or at the premises wherever situated, of any firm or Corporation where work in
connection with this contract may be in hand.
Further, the contractor shall not allow, without written authorization permit entry on site
of work, any person except authorized agents of the Corporation of the Engineer-in-
charge or the contractor's staff and labour directly engaged on and in connection with the
The contractor shall, during working hours, maintain supervisors having sufficient training
and experience to supervise the various items and operations of the work and the said
supervisors shall remain present during the inspections of the Engineer-in-charge. All
orders and directions given to such supervisors or other staff of the contractor shall be
deemed to have been given to contractor. Further the Engineer-in-charge may be due
notice, desire a higher ranking members of the supervisory staff of the contractor to be
present on any specified inspection and the contractor shall comply with such direction.
58. CLEANING UP
The contractor shall at all times keep the construction area and his power house and
storage areas free from accumulation of waste, or rejected materials.
Prior to the completion of the work the contractor shall remove all rubbish from and about
the premises, and all tools, scaffolding, equipment and materials which are not part of
EW- 283 PUR-F-006 RFQ-
permanent structure. The premise will be left in a manner fully satisfactory to the Engineer-
in-charge, thereafter only the completion certificate will be issued.
59. CONTRACTOR TO KEEP INVENTORY OF MATERIALS etc.
The contractor shall prepare and maintain an inventory of all materials temporary rolling
stock, plant purchased or hired for use of employment or for any of the purposed for this
contract and such inventory or a copy thereof shall at all times be available for inspection
by the Engineer-in-charge. A complete and up to date copy of the inventory shall be
submitted to the Engineer-in-charge in the beginning and once a year; thereafter changes
in the interim period, if any shall be communicated on every three months.
60. CONTRACTOR TO RESTORE PLANT
Upon completion of the work, the contractor shall deliver to the Corporation, all
appliances, materials, and plants which may have been loaned or hired to him by the
Corporation and make good all damages which may have occurred to them, except
such as shall be caused by fair wear and tear in execution of the works.
61. PROGRESS SCHEDULE
i) The contractor shall furnish, within one week unless extended by the Engineer of the
order to start the work, a progress schedule in quadruplicate indicating the date of start
the weekly progress expected to be achieved and the anticipated completion date of each
major items of work to be done by him, also indicating dates of procurement and setting
up of materials, plant and machinery. The schedule should be such as is practicable of
achievement towards completion of the whole work in the time limit and of the particular
items on due dates specified in the contract and shall have the approval of the Engineer.
Further, the dates for the progress as in this schedule shall be kept up-to-date. In case it
is subsequently found necessary to alter this schedule, the contractor shall submit in good
time a revised schedule incorporating necessary modifications proposed and get the same
approved by the Engineer. No revised schedule shall be operative within such acceptance
in writing.
Detailed schedules for each week showing the progress proposed to achieve shall be
submitted to the Engineer and got approved. The Engineer is further empowered to ask
for more detailed schedule or schedules any week by week, for any items or items, and
the contractor shall supply the same as and when asked for.
ii) The Engineer shall have, at all times the right without in any way vitiating this
contract, or forming grounds for any claim to alter the order of the works or any part
thereof and the contractor shall after receiving such direction proceed in the order
directed. The contractors shall also revise the progress schedule accordingly and submit
four copies of the revised schedule to the Engineer within seven days of the Engineer's
direction to alter the order of works.
iii)The contractor shall furnish sufficient plant equipment and labour and shall work such
hours and shifts as may be necessary to maintain the progress on the work as per the
approved progress schedule. The working and shift hours shall comply with all GSECL's
regulations in force and shall be such as may be approved by the Engineer. They shall not
be varied without the prior approval of the Engineer.
iv)The contractor shall from time to time as may be required by the Engineer, furnish the
Engineer, with a statement in writing of the arrangement he proposes to adopt for the
execution of this contract and the Engineer may if he considers, necessary at any time
advise alteration in the same, which the contractor shall adopt on notice thereof.
v) The progress schedules shall be in the form of progress charts, forms, statement
and/or reports as may be approved by the Engineer. Further, the contractor shall submit
four copies showing the progress of work in forms and charts etc. at periodicals intervals
as may be specified by the Engineer.
62. DATE OF COMPLETION
The contractor shall supply, erect, equip and construct the whole of the works and
hand over them to the Corporation on or before the date specified in the tender
document including "Special Conditions" and save as herein provided, in no
circumstances whatever shall extend or alter the date for the completion of works.
Provided always that if in the opinion of the Engineer-in-charge the completion of the
EW- 283 PUR-F-006 RFQ-
works shall be delayed by any change of original design or by the order of the
Engineer-in-charge, of any altered, modified substituted or additional works or materials
omitted or by strikes, lock outs or stoppages of labour, or revolution, riots, civil or
political disturbance or by causes directly due to war or by the contractor not being
given possession of the site or any part there-of or by the Corporation taking possession
of and using the site or any part thereof or the works or any part thereof, whether any
nonperformance of work under the powers herein contained or otherwise or by any
nonperformance of work or non-supply of materials to be performed or supplied by the
Corporation or by the contractor not receiving any orders, drawings, instructions or
directions in time or by the suspensions of the works or by fire, flood exceptionally
bad weather tempest, storm, or by from unforeseen circumstances (and whether the
same shall be due to any act or omission of the Corporation or its agents or those in
their respective service or not) the Engineer-in-charge may, if in his unfettered
discretion, he thinks fit either forthwith or at any later time and from time to time not
withstanding that the prescribed or extended time for completion has expired or that
the work have been completed, by writing under his hand, extend the time for the
completion of the works to such date as he shall appoint. Provided always that unless
the contractor makes a written application to the Engineer-in-charge within one month
of the cause of delay and unless the time is extended by the Engineer-in-charge, the
prescribed time shall not be extended notwithstanding delays from the aforesaid
foregoing or any other causes of whatsoever kind.
63. SUBLETTING OF CONTRACT
There will be generally no objection on the component parts for the work, being given
over to responsible sub-contractors but Corporation shall under no
circumstances recognize these sub-contractors and the responsibility of executing the
work in the accordance with the conditions of contract will entirely rest on the main
contracts. The main contractors will therefore always have the very responsible
member, preferably a technical hand present on the works with power to sign all work
orders issued on the site of work and to take requisite actions in the interest of very
efficient execution of work. However, the subletting of the contract can be made only
with the prior approval of the competent authority of the Corporation.
64. OTHERCONTRACTS FOR THE WORK SUSPENSION STOPPAGEOR
CURTAILMENTS OF WORK
If during the tendency of the contract the Engineer-in-charge shall for any reasons
(which shall be unquestioned) whatsoever require the whole or any part of the work
as specified in the contract to be suspended for any period or shall not require the
whole or any part of the work as specified in the contract to be carried out at all by the
contractor, he shall give notice in writing of the fact to the contractor who shall
thereupon suspend or stop the work totally or partially as the case may be. In any,
case, except as provided hereunder, the contractor shall have no claim to any payment
or compensation whatsoever on account of any profit or advantage which he might have
derived from the execution of the work in full but which he did not so derive in
consequence of the full amount of the work not having being carried out, or on
account of any loss that he may be put to on account of materials purchased or agreed
to be purchased or for unemployment of labour recruited by him. He shall not also have
any claim for compensation by reason of any alterations having been made in the original
specifications, drawings, designs and instruction which may involve any curtailment of the
work as originally contemplated. Where, however, materials have already been
purchased or agreed to be purchased by the contractor, before receipt by him of the
aforesaid notice, the contractor shall be paid for such materials at the rate
determined by the Engineer-in-charge, provided they would have been useful for the
work curtailed or stopped are not in excess of requirements, are of approved quality
and cannot be used on other contract works or otherwise by the contractor and/or shall
be compensated for the loss if any, that he may be put to, in respect of materials
agreed to be purchased by him, the amount of such compensation to be determined by
the Engineer-in-charge, whose decision shall be final.
EW- 283 PUR-F-006 RFQ-
The Engineer-in-charge may grant extension of time for the execution of any item or
items of work affected by such suspension of work. The decision for the Engineer-in-
charge, regarding the granting of extension and the period thereof shall be final. The
Engineer-in-charge may order the contractor to suspend any work on account of bad
weather; rain or storm and such other adverse climate conditions and the contractor shall
comply with the same.
The contractor shall not be entitled to an compensation for such suspension of work,
concrete lining at the junctions of the different works under different contract shall be
done with particular care regarding forms, construction joints, interconnecting
reinforcement etc. If any and the joint planning of such work shall be with prior
approval of the Engineer-in-charge.
65. OTHER CONTRACTORS
Apart from this work, the other works connected with the power house will be
simultaneous going on either departmentally or through agencies inside or outside the
power house. Each contractor or agency shall co-operate with others to the fullest
extent and shall allow to each other every facility and co-ordination for execution of
their works simultaneously and satisfactorily, during their action of machinery or
execution of any other co-ordination works of the power house, the contractor will have
to work only at places as directed by the Engineer-in-charge. He will have some time
to suspend his work partially or totally in the interest of the work at large.
In such cases and at such time, he will be informed from time to time and directed by the
Engineer-in-charge where to work. He may also be required to remove the scaffolding or
to erect the scaffolding and shuttering in such a manner as to be of little obstruction and
inconvenience for erection of machinery. In such cases he shall not be given any
compensation on account of reduction or stoppage or labour force or removal and
reinstatement of scaffolding shuttering etc. It will be seen that contractor is not put to
unnecessary inconvenience.
In the matter of dumps, haul, roads, drainage, diversion and the like, each contractor
shall take into consideration the needs and requirements of the other constructors, if any
working in the vicinity. Further no contractor shall take or cause to be taken any
stops or action that may cause disruption, discontent or disturbance to the work, labour
of arrangements etc. or other contractors in the neighboring project localities.
Any action, by any contractor, which the Engineer-in-charge in his unquestioned
discretion may consider as infringement of the above code, would be considered as a
breach of the contract conditions and the Engineer-in-charge may take such action as he
may deem fit against the contractor and the action taken shall be considered as final
and binding.
66. SPEED OF WORK
The contractor shall at all times maintain the speed of work to confirm to the latest
operative progress schedule but the Engineer-in-charge may at any time with sufficient
notice in writing direct the contractor to slow down any part or the whole of the work
for any reason (which shall not be question whatsoever, and the contractor shall comply
with such orders of the Engineer-in-charge. The compliance of such orders shall not
entitle the contractor to any claim or compensation.
67. CONTRACT DOCUMENT AND MATTERS TO BE TREATED AS CONFIDENTIAL
All documents, correspondence, decisions and other matter concerning the contract shall
be considered as of confident and restricted nature by the contractor and he shall not
divulge or allow access there to any unauthorized persons of any kind.
68. ACCESS TO THE CONTRACTOR'S BOOK
Whenever it is considered necessary by the Engineer-in-charge to ascertain the actual
cost for execution of any particular item of work of supply of plant or material shall
direct the contractor to produce the relevant documents such as pay rolls records of
personnel, invoices of materials and any other data relevant to the item or necessary to
determine its cost etc. and the contractor to the aforesaid items in the mode and
manner that may be specified.
69. INTEREST ON MONEY DUE TO THE CONTRACTOR
EW- 283 PUR-F-006 RFQ-
The contractors shall not be entitled to get interest on any amount either of their bills or
arrears whatsoever because of delay in payment by the Corporation. Similarly they shall
not be entitled for any interest on amount of bank guarantees given by them. Non-
payment of interest by the Corporation therefore, shall not cause breach of contract.
70. MEASUREMENTS TO BE PROVISIONAL AND SUBJECT TO CORRECTION
Every measurements for running payment on account of work, done or supplies made,
shall be subject to adjustment or final measurements. In case of disagreement between
such intermediate and final measurements, the latter shall prevail. All works shall be
measured, met by standard measure and according to rules and custom and usual in the
use in Gujarat State Electricity Corporation Ltd., and no proposal to adopt alternative
method will be accepted, the Executive Engineer’s decision as to what is “the usual
method in use in the Gujarat State Electricity Corporation Ltd.” shall be final.
71. BREACH ON PART OF CORPORATION NOT TO ANNUAL CONTRACT
No breach or non-observance on the part of the Corporation of any of the agreements
contained herein, shall annul this contract or discharge the contractor from the
observance and performance thereof, or of any part thereof, but on application by the
contractor and in the unfettered discretion of the Engineer-in-charge an extension of
time may be given to the contractor in respect of such breach or non-observance by
the Corporation.
72. PROFORMA RETURNS
The contractor shall maintain Performa, charts and details regarding machinery
equipment materials, labour personnel and other matters as may be specified by the
Engineer-in-charge. He shall further, submit returns of Performa and details as may
be specified by the Engineer-in-charge from time to time.
73. LOCAL LAWS
All local laws in force at the time of entering into the contract and those enacted
thereafter shall be binding on the contractor and he shall abide by the same.
All import duties, sales tax and other local taxes shall be borne by the contractor and
they shall be deemed to have been covered by this quoted tender rate
74. WORKS IN SHIFT DUTY
Works shall be planned in shift duties, if possible in three shifts, depending on emergency
of the work with prior approval of Eng. - in- charge. 0n Sunday or any other holidays
work shall be continued in order to maintain progress with prior permission of Eng.-in -
charge. Such works shall not form any grounds for complaint, compensation or extension
of time limit.
If on the other hand, the Engineer-in-charge directs that the work shall be proceeded
with on days and during hours which are not permissible under this contract, the
contractor shall proceed with the work as directed without in any way vitiating this
contract or forming any grounds for compensation of claim.
The contractor shall in his dealing with labour, atall times, during the period of this
contract, have due regard to local festivals and religious and other customs.
A working day shall consist of two shifts each of eight hours, a working day shall
constitute any day on which in the opinion of the Engineer-in-charge, work can be carried
out in one or more shifts.
Final payment to the contractor shall not be made until the contractor shall deliver to the
purchaser or receipts in full in lieu thereof, and in either case, an affidavit that so far he
has knowledge or information the releases and receipts include all the labour and material
for which in lien could be filed. If any lien remains unsatisfied after all payments are
made, the contractor shall refund to the purchaser all moneys that the latter may be
compelled to pay in discharging such a lien, including all costs and a reasonable
attorney's.
76. MISCELLANEOUS:
1. In case of conflict / discrepancies among clauses of different specifications given in
this document, the stringent specification shall be followed and under such
circumstances, the decision of the EIC shall be final and binding to the Contractor
2. The Notice inviting tender, general instruction to bidders and all other documents of this
EW- 283 PUR-F-006 RFQ-
tender shall form part of the contract
3. No receipt for any payment alleged to have been made by a Contractor in regard to any
matter relating to tender of the contract shall be valid and binding on the Corporation
unless it is signed by the Engineer-in-Charge.
4. As per provisions of Income Tax Act, Corporation shall deduct Income Tax at the
applicable rate.
5. Agency has to note that the extension of Time limit/excess saving in the works if required
to approve, than it shall be processed as per the provision of DoP and will take time for
process the same.
6. The contract is inclusive of the cost of materials required to complete the work in totality.
7. It will be absolutely incumbent on the contractors to have on the site of work only such
of the materials as have been duly passed by the Engineer-in-charge. Materials that have
been rejected must on no account be allowed to remain on the site, and in spite of
written order to do so, any such rejected materials is on the site beyond a period of
hours’ notice, the Engineer-in-charge shall have the right to remove it, at the risk and
cost of the contractors and even to destroy it.
8. It must be distinctly understood that conditions of contract and of claims in respect of
extra work, will not be allowed unless the works to which they relate is clearly without
the spirit and meaning of the specifications or unless such works are ordered in writing
by the Engineer-in-charge and claimed for in specified manner.
9. Contractor will be asked to present the sample of materials, and the approved samples
will be preserved at the site of work, and no change in the approved sample will be
allowed, without the written permission of the Engineer-in-charge.
10. The department reserves the right to make any change in the design and the plans of the
works. The contractor shall be bound to carry them out at the rates tendered. No claim
or compensation will be allowed on this account.
11. The contractor shall keep instruction book on site, for taking site instructions from time to
time. This book shall be made available on site whenever asked for.
12. Above construction equipment brought to site shall be allowed to be taken out only after
the work for which it has been brought is over. The equipment shall be taken out only
with the specific permission in writing from the E.I.C. Only the equipment required for the
work and in fit condition shall be brought to the site. The Contractor shall ensure that
proper documentation is followed at entry gate of GSECL's premises for such items which
shall be carried back by Contractor after completion of work.
13. The Contractor shall provide all temporary ladders, scaffolding materials, platforms,
supports and other necessary facilities required for trimming & cutting of trees. The
Contractor shall provide sufficient, strong and safe staging so as to ensure safety of the
14. The Contractor shall provide sufficient fencing, notice Corporations and lights to protect
and warn others as may be considered necessary by the GSECL and safety authority.
15. The GSECL may during the progress of work, order the removal of part or whole of the
work executed, found not in accordance with the approved drawings, specifications/
instructions. No extra claims shall be entertained for re-executing or altering of such
16. On completion of the work, the site shall be left in good order and the excess materials,
scraps, debris, if any shall be removed and dumped by the Contractor at place/places as
designated by the GSECL. The Contractor shall also dismantle and remove the staging
and other temporary facilities like stores, offices, labor camp etc. on completion of work.
17. Contractor is required to maintain proper records at site of work in addition to normal
routine requirement of own office. The records to be maintained shall include but not
limited to the following:
(a) Daily Progress Record.
(b) Work Site Order Book.
(c) Instruction by GSECL's Officers.
(d) Test Registers of other materials/fittings, fixtures, equipment as stipulated in the
(e) Register for Working Details.
(f) Log Book of Defects.
(g) Hindrance Register giving details of commencement and removal of each
hindrance.
(h) Supply and consumption registers of all materials shall be maintained.
EW- 283 PUR-F-006 RFQ-
(i) Day to day Record of used/received materials shall be entered in the register and
signed by the Site Engineer of the GSECL as well as contractors' representative at
(j) Measurement Book.
77. SALES TAX ON WORK CONTRACT
The Gujarat Government by its amendment to the Gujarat sales tax act has also made
works contract subject to Sales Tax. However works contract tax shall be liability of the
contractor and shall be born by the contractor. More ever you shall also have to submit
form No 702 as prescribed by Gujarat Sales Tax act while submitting invoice.
More ever the purchaser will not pay any composite tax/turnover tax/works contract tax
which contractor has to pay as per act. Hence the incidence of sales tax or such type of
taxes shall not be payable by the purchaser in any case even if such taxes are levied on
the party/contractor at a future date.
Chief Engineer (Gen)
GSECL: GTPS
Signature Of Contractor
EW- 283 PUR-F-006 RFQ-
TERMS AND CONTRACT FOR WORKS
GENERAL SAFETY RULES
LIST OF SAFETY TOOLS
EW- 283 PUR-F-006 RFQ-
TENDER & CONTRACT FOR WORKS
I/We hereby tender for the Gujarat State Electricity Corporation Ltd. (herein Referred as
“Corporation”) of the work specified in the underwritten memorandum within the time specified in
Schedule B (memorandum showing items of work to be carried out) and in accordance, in all
respect, with the specifications, design, drawings and instructions in writing and as per annexed
conditions of contract and agree that when the materials for works are provided by the Corporation,
such materials and rates to be paid for them shall be as provided in Schedule A hereto.
MEMORANDUM
(a) General description of work : “Construction of Kitchen & renovation of GF toilet at KH
bungalow at GSECL, Gandhinagar TPS.”
(b) Estimated cost : Rs. 1577234.89/-
(c) Earnest money (3%) : Rs. 47318.00/-
(d) Security deposit : As per cl no.7 of Section C (i.e General condition of contract).
(e) Time allowed for the completion of work from date of written order to commence.:
(Four) Months
Should this tender be accepted, I/We hereby agree to abide by and fulfill all the terms and provision
of the conditions of contract annexed hereto as applicable and in default thereof forfeit and pay to
the Corporation, the sums of money mentioned in the said conditions.
Receipt No. Date from the Gujarat State Electricity Corporation Ltd. in respect of the sum of
Rs____________________________________. (The amount to be specified in figures and
words) is herewith forwarded representing the earnest money (the full value of which is to be
absolutely forfeited to the Corporation, should I / we do not execute / commence the work after
issuance of date of commencement by GSECL.
Signature of the Contractor:
Address of the Contractor:
Dated__________________ day of _______________year
Signature of Witness:
Address of the Witness:
Occupation:
Dated__________________ day of _______________year
The above tender is hereby accepted by me on behalf of the Gujarat State Electricity Corporation Ltd.
For & On behalf of GSECL
Chief Engineer (Gen)
GSECL GANDHINAGAR TPS
his duly authorized Assistant
EW- 283 PUR-F-006 RFQ-
General Safety Rules & List of Safety Tools.
“GENERAL SAFETY RULES / NORMS” TO BE OBSERVED BY THE CONTRACTORS
All the contractors working in Gujarat State Electricity Corporation Limited Factory like
Coal/Lignite/Gas/Hydro/Pumping Station shall have to strictly observe the following Safety
Rules. Concern principle contractors are responsible for informing & observance of these rules by
their supervisors/contract workers as well as the owner/supervisors/ workers of sub-Contractors
engaged, if any, by them for the work contract awarded to them. Prior to commencement of the
work, Contractor shall have to submit a written assurance on their letterhead to the concerned
Sectional Head / Engineer-in-charge that they have thoroughly gone through these Rules, have
educated their employees / workers of their sub contractor and will strictly observe the said Rules
while execution of work under work contract awarded to them. They will have to indemnify the
company for any loss or damage / accident / injury to the company’s property / employee or
employee of their own in default of non - observing these rules.
(01) Contractor should issue photo gate pass for their workers from GSECL Factory
Manager as per Gujarat F actories rules, 1963 & details shall be filled up in
GSECL gate pass f ormat as per Aadhar c ard /Election card id proof & to follow
the gate pass issue procedure through concern department EE & SE, Security Officer,
LWO/IRO/DGM, Factory Medical Officer, Safety Officer/Dy. Safety Officer & Factory Manager.
(02) In case of emergency, temporary photo gate pass shall be issued by Security Officer only for
three days with prior permission of Factory Manager only. More than three days, Permanent
photo gate pass procedure shall be completed by contract agency for their contract workers.
(03) Certificate of Fitness of employment in hazardous process & operations in form no.33 of Gujarat
Factories rules, 1963 shall be issued by GSECL Factory Medical Officer for all contractor workers
before commencement of work & examination responsibility shall be taken by contractor as well
as concerned Head of Department .Pre-employment & Periodical medical examination of
contractor workers shall be carried out in form no.32 from GSECL Factory Medical Officer after
every six (06) months of contractor with their contractor workers. Contractor shall be fulfilled all
health requirements before commencement of work. After completion of medical examination in
form no.32/33, GSECL Factory Medical Officer shall be signed in contract worker gate pass
procedure format.
(04) Contract worker gate pass will issue after completion of safety induction 3D animation movie &
Training record is to be maintained in IMS/OHSAS training format by TK Office/LWO.
(05) As per Gate pass format of GSECL, Safety Officer/Dy. Safety Officer shall be checked the issue
PPE to contract workers as per nature of job, Form no.10 of lifting tools and tackles, Driving
license, Electrical contractor license, Electrical trade qualifications, Safety induction training,
SOP, supervisor qualifications etc. After fulfillment of all Safety compliances, Safety Officer/Dy.
Safety Officer shall be signed in Contract worker Gate pass procedure format.
(06) Work Contract shall be completed by principle contractor/agency/person who is awarded the
work order. Subletting of contract shall be allowed only if prior approval of Power station chief
before execution of work. Contractor/agency shall be submitted the entire subletting contract
documents with gate pass application through concern department EE & SE, LWO/DGM, Safety
Officer/Dy.Safety Officer & Factory Manager.
(07) Under The Conditions Framed Under Rule-45 Of The Indian Electricity Rules,
Valid Electrical contractor License shall be submitted to concern electrical department
EE/SE/Electrical Safety Officer/ Safety Officer/Factory Manager at the time of apply gate pass by
agency/party with latest renewal from Chief Electrical Inspector, Gandhinagar- Gujarat. Electrical
License photocopy shall be checked by Concerned HOD of Electrical Department/Electrical Safety
Officer/Dy.Safety Officer/ Safety Officer/Factory Manager.
(08) As per nature of job/work, qualified supervisor (Diploma (Electrical/ Mechanical/Civil/C&I)
+ 3 years experiences or ITI + 10 years) shall be engaged by contract agency & qualification
certificate with experience certificate shall be submitted to concern EE/SE/LWO/IRO/DGM/
Dy.Safety Officer /Safety Officer/Factory Manager at the time of apply gate pass.
(09) As per rule 3 of CEA regulation ,2010: Designating person(s) to operate and carry out the
work on electrical lines and Apparatus, Contract person/worker possesses a certificate of
EW- 283 PUR-F-006 RFQ-
competency or electrical work permit, issued by the Appropriate Government. That means,
Electrical trade Qualification of contract worker/person like ITI-wireman/ Electrician, Diploma
(Elect), BE/B. TECH (Elect), ME/ M. TECH (Elect) shall be submitted to concern
EE/SE/LWO/IRO/DGM, Dy.Safety Officer/ Safety Officer/Factory Manager at the time of apply for
photo gate pass procedure.
(10) As per nature of job/work & during capital overhauling work /Annual overhauling work /24X7
round the clock work/major shut down work, Qualified Safety Officer/Manager/Supervisor
(BE/Diploma (Elect/Mech/Civil) + PDIS-Post Diploma in Industrial Safety) shall be engaged by
contractor during dangerous operations/dangerous works as well as day to day dangerous
activities, safety supervision, tool box talk, Safety awareness programme, SOP preparation with
hazards & its control measures with each step , checking of lifting tools & tackles, hydra mobile
crane, Safety precautions, coordination with Safety Department etc.
(11) License of driver shall be submitted with gate pass issue application as per nature of vehicles &
to follow the Motor vehicle Act,1988, the Central Motor Vehicles (Amendment) Rules,2016 as
well as Gujarat Motor Vehicles rules,1989 & driver license shall be checked every day by
security shift in charge before entry in the Factory premises.
(12) SOP with JSA (Job Safety Analysis) shall be prepared by contractor through competent person as
per GFR, 1963 or Qualified Safety Officer as per GFR, 1963 with 05 years experiences. SOP will
review & approve by concern JE/DE/EE/SE/Elect. Safety Officer/Dy. Safety Officer /Safety
Officer/Factory Manager before execution of work.
(13) It is compulsory to use standard make Personal Protective Equipments (P.P.Es.) as per the job
requirement. Do not work without use of required P.P.Es. Contractor is responsible to provide
standard make (ISI/DGMS/CE/EN/ANSI approved) & to checked standard/make in PPE issue
format by concern JE/DE/EE/SE/Safety Officer/Factory Manager. Personal Protective Equipments
/ Safety Gadgets suitable to give sufficient protection against hazards involved in their work / job
to their staff, as per the job requirement and insist / enforce their workers to put on the same
while at works.
The ongoing work is liable to be stopped at any time if your contract workers/staffs found
working without P.P.Es. Following is the list of various P.P.Es (as per ISI/DGMS/CE/ EN/ ANSI
approved only) to be used for various works / worksites.
In any work, Contractor shall be issued the minimum 05 nos. of PPEs like Safety Shoes, Safety
Helmet, Safety goggles, Mask & Reusable Ear plug to their workers/supervisor compulsory & it
will check by concern section HOD & Dy.Safety Officer /Safety Officer at the time of gate pass
procedure.
Industrial Safety Helmet For protection of head against falling objects or during fall of
person from height. Yellow Colour helmet is used for
contract worker with agency logo.
Safety Goggles/welding For protection of eyes against flying particles / dust, chemical
goggles/chemical splash splash, welding spark, arc, flashover etc.
Full Face shield For protection of face against flying particles / dust, chemical
splash, spark, arc, flashover etc.
Reusable Earplug / Ear muffs. For ear / hearing system protection while working in high
noise level area.
Chemical suit/Gas tight suit For body protection against chemicals, oils, sharp edged
/Fire proximity suit/FR Boiler objects, heat, hot objects etc.
Safety Hand Gloves For protection of hands against chemicals, oils, sharp edged
objects, heat, hot metals/objects, electricity etc.
Safety shoes/ Gum Boots with For protection of leg/feet against falling objects, sharp edged
Oil/Chemical/water/heat/ objects, heat, hot metals/objects, electricity etc..
Electrical resistance etc.
Safety Belt(full body hardness For fall prevention while working at heights or in depth,
with double lanyard & shock working in vessel or in confined space.
absorber) / Rope / Life line /
Fall arrestor etc.
EW- 283 PUR-F-006 RFQ-
Dust Mask/Respirator with Protection of respiratory system against dust.
valve(FFP2)
Chemical Cartridge Respirator Protection against toxic chemical fumes / gases/vapors/dust
with full face mask type etc.
Trolley mounted Air line Working in oxygen deficient zone or confine space area
respirators with full face mask
Portable Single gas detector like Working in hazardous storage/process area
Chlorine, Ammonia, Hydrogen,
Portable Multi gas Detector Working in oxygen deficient zone & use in entry of confine
( LEL,O2,CO,H2S,SO2, etc) space & Major fire
Automatic voltage detector To check the present voltage or induction voltage of electrical
equipments/ bus/switch gears from 01 (one) feet distance
before starting the any electrical work .
Auto darkening welding helmet The new auto darkening welding helmet combines legendary
(EN 379 & EN 175 Level-B) with Speed glass quality and auto darkening technology with an
PAPR as per EN 12941:1998, innovative wide-view grinding visor to give welders an all-in-
class TH2 and AS/NZS 1716 one solution for more flexibility, precision, and efficiency.
Respiratory System is a combined face and breathing
protection device, for increased comfort and safety in
welding. The unit is equipped with a particle filter which
removes particles from the air. The unit provides a constant
airflow independent of filter combinations and clogging. The
unit can also be equipped with a gas filter (for example
A1B1E1). The unit supplies air to the head top via the
connecting breathing tube. The airflow creates a slight
positive pressure which together with the sealing to the face
prevents particles and other contaminants from entering the
(14) All PPEs (as per ISI/DGMS/CE/EN/ANSI approved only) Should issued by
party/agency/contractor to their contractor workers as per nature of job and allotment of PPE
list shall be submitted to Safety Officer, Dhuvaran on his letter head as per below mentioned
format by Contractor before commencement of work through concerned JE,DE,EE/SE .
Sub: Issue of PEE to Contractor workers
Sub of work Order:
Work order no.
Name of Agency:
Date of Commencement:
Time limit for work order:
Sr. Name Design Name of Name of PPE IS Make Qty Uni Date Receivin
no. of ation Section :Code of t of g
worker under work no. of PPE issue signature
s execution PPE
Safety Helmet No
Safety goggles No
Reusable Ear Pai
Dust Mask No
Safety Shoes Pai
EW- 283 PUR-F-006 RFQ-
(15) Shift Security Inspector/Security Officer shall be checked Safety Shoes & Safety Helmet of all
contractor workers at entry gate of Factory Premises & shall entered contractor workers with
Safety Shoes & Safety Helmet with photo ID Gate Pass.
(16) Shift Security Inspector/Security Officer shall be checked validity of Gate pass of all contractor
workers on daily basis.
(17) During the work execution, one trained & competent supervisor of agency should always remain
present at work site. Concern JE/DE of GSECL shall be supervised the contract work as per SOP .
(18) Approved NABL laboratory calibration certificates of electrical/mechanical/Civil/C&I/Environment
survey/Chemical etc measuring /testing equipments/instruments which are used during contract
work shall be submitted before starting the work & shall be checked by concern JE/DE/EE before
starting work & it’s record shall be maintained in concern section.
(19) The contractor shall take all the required safety measures prior to commencement of work on
dangerous substances, machineries or area at which cautionary notice is displayed and obtain
“Line Clear” or “Work Permit” through the concern Department / Section JE/DE and shall be
informed to concern section JE/DE for closed/ returned after completion of work.
(20) Safety talk/Safety work instructions shall be given to contractor workers by concern JE/DE
regarding hazards of specific work, risk & it’s control measure (mentioned in HIRA) before
starting the job work and records shall be maintained for each & every job works.
(21) Display Safety instructions shall be strictly followed by all workers who are working in factory
(22) Material Safety Data Sheet (MSDS) of each chemical shall be available with Chief
Chemist/Control room & work related Chemical information shall be taken by contractor &
contractor workers from Concern EE/Chief Chemist before starting of chemical handling work.
(23) The contractor shall be checked & securely covered or securely fenced any opened fixed vessel,
sump, tank, pit or opening in ground or in floor which, by reason of its depth, situation,
construction or contents ,is or may be a source of danger before starting the work each & every
days or after interval/recess. Contractor supervisor shall be informed to concerned HOD
regarding any unsafe conditions.
(24) Prohibition of smoking, fires, lights, spontaneous ignition substance, matches; fuses, mobile
phone etc are to be strictly followed by all workers who are working in factory premises.
(25) Prior to carrying out welding, gas cutting, furnace heating or any other hot work job, remove all
the inflammable material lying at or nearby worksite or cover it properly by suitable protective
covering. Also, special care shall be taken before carrying out such job & see that all possible
contributing factors to set fire shall be removed / vanished prior to commencement of the work.
Advance intimation shall be given to concerned section / fire section to commence the work in
fire prone areas. They should also keep ready all the First Aid Fire Extinguishers / equipments &
fire extinguishing media / material like sand / water buckets or other appropriate equipment at
such place.
(26) While carrying out work in confined space or inside vessel, obtain necessary “Confined Space
/ Vessel Entry Permit” from concerned department prior to commencement of the work.
For lighting in such areas, only 24-volt (ISI certified & with proper guard) hand lamp shall be
used. For taking care of the persons working inside the confined space / vessel, a supervisor /
person capable to keep continuous watch on person(s) working inside, assist them in case of
emergency or arrange to get immediate outside help, shall remain present at entry point. Use
full body safety belt without failed.
While working inside sewage, trench or in-depth, a person to warn outsiders / entrants / passers
etc shall remain available near entry point or the entry point shall be cordoned by a barricaded
tape with a cautionary notice. After completion of the works, all the lids / covers / grills / grits
opened, shall be re-fixed / re-placed in the original position as it were prior to commencement of
the work and leave the work place in safe condition in all respect, so as to prevent accident to
fellow workers.
(27) The contractor shall see that he / his persons do not work on or block (by stacking material,
spare parts, tools-tackles, equipments etc), any passages / walkways / gangways / aisles /
staircases / ladders / lifts or any other approaches / roads leading to plans or its auxiliaries, on
which there is traffic movements or possible traffic movements in case of emergency. Such
passages are meant for safe escape in the event of emergency. If it is utmost necessary to carry
EW- 283 PUR-F-006 RFQ-
out work in such area with blocking of passage, prior permission of Competent Authority or the
Engineer-In-Charge shall be obtained. To demarcate / declare the area as “UNSAFE”, cordon it
using barricading tape & display suitable caution notice or keep a person to restrict / divert the
traffic on this route through other safe passage.
(28) The contractor shall see that he / his persons do not work on or block (by stacking material,
spare parts, tools-tackles, equipments etc), any passages / walkways / gangways / aisles /
staircases / ladders / lifts or any other approaches / roads leading to plans or its auxiliaries, on
which there is traffic movements or possible traffic movements in case of emergency. Such
passages are meant for safe escape in the event of emergency. If it is utmost necessary to carry
out work in such area with blocking of passage, prior permission of Competent Authority or the
Engineer-In-Charge shall be obtained. To demarcate / declare the area as “UNSAFE”, cordon it
using barricading tape & display suitable caution notice or keep a person to restrict / divert the
traffic on this route through other safe passage.
(29) Prior to use power / electrically operated hand tools / equipments / machines / gadgets like
welding machine, hand grinder, hand drill etc, ensure for its safe operation & use it only if it is
found safe to use. Do not use defective, unsafe or improperly maintained equipments.
The electrical power supply required to run such equipments shall not be taken directly at their
own but shall be obtained through concerned Electrical Maintenance Departments or their
authorized persons or under their observations / guidance only. The Electrical Section shall
provide temporary electrical connection up to contractor’s Mains Board on which it is compulsory
to install mains switch, ELCB & fuses of adequate capacity. All such equipments shall invariably
be earthed adequately to prevent electrical shock, sparking, short circuit etc. Power cord to be
used shall be of adequate capacity, without any joint & shall consist of earth wire also. Hence, it
is necessary to use adequate capacity 3-wire power cord for single & 5-wire power cord for three
phase power connections. The plugs, receptacles, pins, holders etc shall be of adequate capacity
& safe to use.
All electrical & mechanical equipments / tools-tackles viz. welding machine, cutting machine,
Grinder, Drill, Chain Pulley Blocks, Hook chooks etc required to be used during work execution
shall be of standard make & bear ISI certification mark on it. The consumables like welding
electrodes, grinding wheels / discs etc which has specific prescribed life span shall not be used in
any case if its expiry date is over.
(30) Non-Sparking Non-Magnetic electrical hand tools and tool kits shall be used by Electrical
contractor for safe use in areas where hazardous, flammable, or combustible vapors, liquids,
dusts, or residues may be present in Gas Based power plant and list of tools and tackles shall be
submitted with technical bid. Non-Sparking Non-Magnetic electrical hand tools and tool kits shall
be checked by JE/DE before commencement of Electrical work.
(31) Before using lifting machines / tackles (like C.P.Bs., Hook chooks, winch, forklift, mobile crane,
EOT crane etc) & its attachments (like D-shackles, slings, U-clamps, Eye bolts or any fixtures), it
shall be checked and used only if found safe to use. Also, ensure that these are tested,
examined & certified in form no.10 by Competent Person as per the Factory act-1948 & Gujarat
Factories Rules and its validity do not expire. Further, it shall be fixed properly and firmly prior to
lifting the weight. Valid Test certificate of all Lifting machines used by Contractor to be
submitted to Dy.Safety Officer/ Safety Officer before commencement of work through
concerned EE/SE.
(32) Metal Scaffoldings to be used for working at height shall be of adequate size & capacity. Obtain
the work permit when working at height. While climbing on such scaffolding or working on any
structure at height, use of full body safety belt /full body hardness with double lanyard & Fall
arrestor & Helmet is compulsory. It is also necessary to fasten chinstraps of the helmet.
(33) Contractor or their employee shall not interfere in day-to-day routine plant activities / works
except the work assigned to them, shall not loiter in the areas other than their work jurisdiction,
as well as shall not temper / operate / touch the machineries/equipments/auxiliaries with which
they are not concerned. Also, the contractor shall strictly instruct their staff for not to sit or take
rest at/near/below running plants, auxiliaries, systems or any place which is risky, hazardous &
prone to accident.
(34) The cylinders containing poisonous / toxic or inflammable / explosive gas like Oxygen, Acetylene,
LPG, Hydrogen, Ammonia, Chlorine, CO2 etc shall be handled safely taking due care. To handle /
EW- 283 PUR-F-006 RFQ-
shift such cylinders a special trolley /cage meant for it must be used but in no case it should be
(35) In Gas Based Power station/Hydrogen storage area /Hydro carbon fumes-vapour generated
area, Spark arrestor (as per approved manufacturer of CCOE, Nagpur) shall be provided on each
vehicle by party/agency and it will check by shift security in charge before entry of vehicles in
the factory premises.
(36) No women or young person shall be employed or permitted to work in Lead-compound area like
battery room etc. as per schedule VI of GFR
(37) No women or young person shall be allowed to clean, lubricate or adjust any part of a prime
mover or of any transmission machinery while the prime mover or transmission machinery is in
motion. Examination or operation of motion machinery shall be made or carried out only by a
specially trained adult male worker wearing tight fitting clothing as per section 22 of factories act
(38) In all risky job, before start the work, contractor should obtain General Safety Work Permit
through concerned section from Shift –in-charge well in advance.
(39) In case of noticing smoke or fire during their work execution, they shall make immediate efforts
to extinguish / control it and simultaneously inform the Fire Station Mobile No as well as Station
Fire Officer or Emergency Control room no which is displayed at prominent place of factory like
Main Security Gate, All unit control room, Canteen area, Safe Assembly points, Fire Station, All
security gates, Occupational Health Centre.
(40) In case of any injury / accident while working, it shall immediately be reported to Safety
Department through concerned Sectional Head / Engineer. The prescribed Form No. 21 &
ANNEXURE may be obtained from concerned section or Dy.Safety Officer/Safety Officer.
In case of any electrical accident, it shall immediately be reported to Electrical Safety Officer
through concern Sectional Head / Engineer. The prescribed Electrical accident form no. A as
per electricity act-2003 & Form No. 21 & ANNEXURE as per Gujarat Factories rules
shall be filled up by concern department JE/DE with written consent of contractor. The Form
may be obtained from concerned Electrical section or Electrical Safety Officer. Electrical accident
investigation shall be carried out by Electrical Safety Officer with Factory Manager.
After any reportable accident, Contract agency shall be submitted the fitness certificate of
injured person with endorsement of GSECL factory Medical Officer to LWO/Dy.Safety
Officer/Safety Officer/Electrical Safety Officer then after injured person may allow for work.
(41) For any incident occurred but have no injury to any persons should also reported as per GSECL
format and informed to Dy.Safety Officer/Safety Officer as Near Miss Incident.
(42) Safety penalty shall be imposed against violation by contract workers: if any contract worker
worked in a factory contravenes any provision of factories act or any rules or orders made there
under. Imposing any duty or liability on workers, contractors/agency shall be punishable with
fine which mentioned as under.
Sr. Description of penalty Amount
(i) Work without PPEs Rs.300/- per person
(ii) Work without work Safety permit like working at height, Rs.1000/- per day
confine space entry, hot work etc.
(iii) License of driver as per type of vehicles not registered. Rs.750/- per person
(iv) Welding work without flashback arrestor/double gauge Rs.1000/- per set
regulator set
(v) Operate Portable power tool without ELCB Rs.1000/-per
(vi) Work without qualified Supervisor as per nature of job like Rs.1000/-per day
mechanical, electrical, civil, C&I, chemical etc.
(vii) Work without SOP & JSA Rs.2000/-per day
(viii) Work without test report of lifting machines / tackles (like Rs.2000/- per
C.P.Bs., Hook chooks, winch, forklift, mobile crane, EOT crane equipment
etc) & its attachments (like D-shackles, slings, U-clamps, Eye
bolts or any fixtures) in Form No.10 of Gujarat Factories
Rules,1963
EW- 283 PUR-F-006 RFQ-
(ix) Work without Double lynyer Safety belt during working at Rs.3000/-per person
Height work, work without anchoring in hook/line line
(x) Work without 24 Volt supply in Confine space area Rs.3000/-per person
(xi) (a) Grinding machine used without safety guard/ machine Rs. 500/- per
guard equipment/ per set
(b) Unsafe welding machine like open body. Knob without
insulation. Connection without plug
(c) Damaged welding cables/gas pipelines
(d) Welding work doing without welding blanket.
(e) Electrical supply without 3 pin plug/industrial plug.
(f) Use of damaged electrical wire for lighting/equipments.
(g) Use of lighting lamp without cage.
(h) Use of open halogen tube.
(i) Use of damaged PPEs/use of non standard PPEs
(j) Unsafe lifting and handling of gas cylinders
(k) Cylinder handling without safety cap
(l) Temporary connection without ELCB. etc
During plants visit/supervision of concern JE/DE/EE,SE. Safety officer/Dy. safety officer. Electrical
safety officer , factory manager, if they will observed any safety violations as per CO
circular/statutory requirements then they must imposed safety penalty through office note
directly against contract workers/contract agency and Office Note process through proper
channel to concern sectional head and Account head for recovery purpose. Photograph/CCTV
Footage is to be put a with penalty note by imposing officer.
(43) Party will damage any fire equipments or property or machinery in factory during execution of
work, total damage cost will be recovered from party RA bill and recovery Office note put up by
concern HOD.
(44) All the relevant labour and industrial laws shall also be followed compulsorily.
(45) After completion of work, cotton waste, grease, oil, unused material, welding rod pieces, scrap
etc. are to be removed by contractor and scrap shall be deposited to scrap yard of Main Store.
(46) For performance evaluation of contractor, safety factors of work accident, fire incident & near
miss accident will be considered. Steps can be taken to review the job assignment up to
cancellation for negligence.
(47) Over & above these, contractor shall have to follow all the safety requirements /rules &
regulations / norms and legal provisions laid down in various statutes. Particularly the provisions
of The Factories Act-1948 & the Gujarat State Factories Rules-1963 (Amended up to date), The
Electricity Act-2003 & rules, BOCW Act/Rules shall be followed strictly. The contractor shall also
obey the rules / regulations / instructions of the local Competent Authority for safety & health
requirements.
(48) The above rules shall be scrupulously followed and where required, Contractor /contractor
workers may contact to the Dy.Safety Officer/Safety Officer/Electrical Safety Officer in case of
any ambiguity or needs further guidance in this regard.
Chief Engineer (Gen)
GSECL: GTPS
Signature Of Contractor
EW- 283 PUR-F-006 RFQ-
PERFORMA FOR BANK GUARANTEE
INTEGRITY PACT
CERTIFICATE – A
ANNEXURE - I
EW- 283 PUR-F-006 RFQ-
ON STAMP PAPER OF Rs.300/-
FORM OF BANKER’S UNERTAKING
(For Security Deposit for work period as per Terms and Conditions of Tender)
We, Bank of ______________________________________________ hereby agree unequivocally
and unconditionally to pay immediately on demand in writing from the Gujarat State Electricity
Corporation Limited, or any Officer authorized by it in this behalf any amount up to and not
exceeding Rs.__________ (in words) Rupees
to the said Gujarat State Electricity Corporation Limited on behalf of
M/s.___________________________________________________ who have entered into a contract
for the supply / works specified below :
L.O.I. No. _____________________________________________________ dated ______________.
This agreement shall be valid and binding on this Bank up to and inclusive of________________ and
shall not be terminable by notice or by change in the constitution of the Bank or the firm of
Contractors / Suppliers or by any other reason whatsoever and our liability hereunder shall not be
impaired or discharged by any extension of time or variations or alterations made, given conceded or
agreed, with or without our knowledge or consent, by or between parties to the said within written
Notwithstanding anything contrary contained in any law for the time being in force or banking
practice this Guarantee shall not be assignable, transferable by the beneficiary (i.e. GSECL or
Subsidiaries). Notice or invocation by any person such as assignee, transferee or agent of beneficiary
shall not be entertained by the Bank. Any invocation of the Guarantee can be made only by the
beneficiary directly
“NOT WITHSTANDING” anything contained herein before, our liability under this guarantee is
restricted to Rs._______________ (Rupees
_______________________________________________________ only). Our guarantee shall
remain in force until _______________ (date of validity of the Guarantee). [Unless demands or
claims under this Bank Guarantee are made to us in writing on or before _____________ (date of
validity of the Guarantee), all rights of Beneficiary under this Bank Guarantee shall be forfeited and
we shall be released and discharged from all liabilities there under]:
Please Mention here Complete Postal Signature of
Address of the Bank with Branch Code, Bank’s Authorized Signatory
Telephone and Fax Nos. with Official Round Seal
EW- 283 PUR-F-006 RFQ-
ANNEXURE- I
Financial Department, GR.No. FD/MSM/e-file/04/2025/2712/DMO Dtd.
[ To be revised as per GoG notification issued from time to time.]
List of Banks Notified by GSECL
(A) Guarantees issued by following banks will be accepted as SD/EMD on permanent
All Nationalized Banks.
(B) Guarantees issued by following Banks will be accepted as SD/EMD for period up to
March 31, 2027. The validity cut-off date in the GR is with respect to date of issue
of Bank Guarantee irrespective of date of termination of Bank Guarantee.
Name of Banks Name of Banks
1 AXIS Bank 23 A U Small Finance Bank
2 Bandhan Bank 24 City Union Bank
3 CSB Bank 25 DBS Bank India Limited
4 DCB Bank 26 Dhanlaxmi Bank
5 Equitas Small Finance
Federal Bank
6 HDFC Bank 28 HSBC Bank
7 ICICI Bank 29 IDBI Bank
8 IDFC First Bank 30 Induslnd Bank
9 Jammu and Kashmir
Jana Small Finance Bank
10 Karnataka Bank 32 Karur Vysya Bank
11 Kotak Mahindra Bank 33 RBL Bank
12 South Indian Bank 34 Standard Charter Bank
13 Tamilnadu Mercantile
Ujjivan Small Finance Bank
14 36 Ahmedabad Mercantile Co-
Operative Bank
15 Nutan Nagrik Sahakari 37 Rajkot Nagrik Sahakari Bank
Bank Ltd. Limited.
16 Sarswat Co-Operative
SBPP Co-operative Bank Ltd.
17 SVC Co-Operative Bank
The Cosmos Co-op Bank Ltd.
18 The Gujarat State Co- 40 The Surat District Co-operative
Operative Bank Bank
19 The Surat Peoples Co- 41 The Baroda Central Co-operative
operative Bank Ltd. Bank
20 The Panchmahal District 42 The Kalupur Commercial Co-
Co-operative Bank operative Bank
21 The Rajkot Commercial 43 The Banaskantha Mercantile Co-
Co-operative Bank Limited Operative Bank Ltd.
22 Gujarat Gramin Bank
EW- 283 PUR-F-006 RFQ-
EMD BANK GUARANTEE FORMAT
FOR TENDER /ENQ. NO. ___________________________________
(BANK GUARANTEE ON NON-JUDICIAL STAMP PAPER OF Rs.300)
WHERE AS M/s. _______________________________________________________________
(Name and Address of the Firm) having their registered Office at
_________________________________________________(Address of the Firm’s registered Office)
(hereinafter called the Tenderer) wish to participate in the Tender
No.__________________________ for______________________________________ of (supply /
Erection / Supply & Erection / Work) of __________________________________ (Name of the
material / equipment / work) for _________________________ Gujarat State Electricity Corporation
Limited and WHEREAS a Bank Guarantee for (hereinafter called the “Beneficiary”) Rs.
_____________ (Amount of EMD) valid till ____________ (mention here date of validity of this
Guarantee which will be 4 (FOUR) months beyond initial validity of Tender’s offer) which is required
to be submitted by the Tenderer along with the Tender.
(Name of the Bank and address of the Branch giving the Bank Guarantee) having our registered
Office at _____________________ (Address of Bank’s registered Office) hereby give this Bank
Guarantee No. _________________dated ____________ and hereby agree unequivocally and
unconditionally to pay immediately on demand in writing from the Gujarat State Electricity
Corporation Limited or any Officer authorized by it in this behalf any amount not exceeding
Rs.____________ (amount of EMD) (Rupees
______________________________________________________) (in words) to the said Gujarat
State Electricity Corporation Limited on behalf of the Tenderer.
We, ____________________________________________ (Name of the Bank) also agree that
withdrawal of the tender or part thereof by the Tenderer within its validity or non-submission of
Security Deposit by the Tenderer within one month from the date of tender or a part thereof has
been accepted by the Gujarat State Electricity Corporation Limited would constitute a default on the
part of the Tenderer and that this Bank Guarantee is liable to be invoked and encased within its
validity by the Beneficiary in case of any occurrence of a default on the part of the Tenderer and that
the encased amount is liable to be forfeited by the Beneficiary.
This agreement shall be valid and binding on this Bank up to and inclusive of____________________
(mention here the date of validity of Bank Guarantee) and shall not be terminated by notice or by
Guarantor change in the constitution of the Bank or the Firm of Tenderer or by any reason
EW- 283 PUR-F-006 RFQ-
whatsoever and our liability hereunder shall not be impaired or discharged by any extension of time
or variations or alterations made, given, conceded with or without our knowledge or consent by or
between the Tenderer and the Gujarat State Electricity Corporation Limited.
Notwithstanding anything contrary contained in any law for the time being in force or banking
practice this Guarantee shall not be assignable, transferable by the beneficiary (i.e. GSECL or
Subsidiaries). Notice or invocation by any person such as assignee, transferee or agent of beneficiary
shall not be entertained by the Bank. Any invocation of the Guarantee can be made only by the
beneficiary directly.
NOTWITHSTANDING anything contained hereinbefore our liability under this Guarantee is restricted
to Rs. ________ (amount of EMD) (Rupees ________________________________________ (in
words). Our Guarantee shall remain in force till _____________ (date of validity of the Guarantee).
Unless demands or claims under this Bank Guarantee are made to us in writing on or before
___________ (date of validity of the Guarantee), all rights of Beneficiary under this Bank Guarantee
shall be forfeited and we shall be released and discharged from all liabilities there under.
Please mention here complete Postal Signature of the
Address of the Bank with Branch Code, Bank’s authorized
Telephone and Fax Nos. Signatory with Official Seal.
EW- 283 PUR-F-006 RFQ-
GUJARAT STATE ELECTRICITY CORPORATION LIMITED- GTPS
INTEGRITY PACT
OUR ENDEAVOUR
To create an environment where Business Confidence is built through Best Business Practices and is
fostered in an atmosphere of trust and respect between providers of goods and services and their
users for the ultimate benefit of society and the nation.
GSECL’S COMMITMENT PARTY’S COMMITMENT
To maintain the highest ethical Not to bring pressure recommendations
standards in business and professions. from outside GSECL to influence its
decision..
Ensure maximum transparency to the Not to use intimidation, threat, inducement
satisfaction of stakeholders. or pressure of any kind on GSECL OR ANY
OF it’s employees under any circumstances.
To ensure to fulfill the terms of To be prompt and reasonable in fulfilling
agreement/contract and to consider the contract, agreement, legal obligations.
objectively the view point.
To ensure regular and timely release of To provide goods and / or services timely
payments on due dates for work done. as per agreed quality and specifications at
minimum cost to GSECL.
To ensure that no improper demand is To abide by the general discipline to be
made by employees or by anyone on maintained in our dealings.
our behalf.
To give maximum possible assistance to To be true and honest in furnishing
all the Vendors/Suppliers/Service information.
Provider and other to enable them to
complete the contract in time
To provide all information to Not to divulge any information, business
suppliers/contractors relating to details available during the course of
contract / job which facilitate him to business relationship to others without the
complete the contract / job successfully written consent to GSECL.
To ensure minimum hurdles to vendors Not to enter into carter / syndicate
/ suppliers / contractors in completion /understanding whether formal / non
of agreement / contract / work order. formal so as to influence the price.
Seal & Signature Seal & Signature
(GSECL’s Authorized Signatory) (Party’s Authorized Person)
Name : Name:
Designation:
Name : Name:
Designation:
EW- 283 PUR-F-006 RFQ-
On Firm’s Letter Head
CERTIFICATE - A
I / We ________________________________________________ authorized signatory of
M/s._________________________________________________here by Certify that
M/s. _____________________________________________ is not related with other firms who have
submitted tenders for the same items under this inquiry / Tender.
Signature of the Tenderer
With Designation
Seal of the Firm
EW- 283 PUR-F-006 RFQ-
GENERAL GUIDELINES RELEVANT TO I.S.
SPECIAL CONDITIONS FOR USE OF CEMENT
APPROVED NAME OF MANUFACTURERS OF
STEEL / CEMENT
EW- 283 PUR-F-006 RFQ-
GENERAL GUIDELINES RELEVANT TO IS
Please refer latest edition of relevant Indian Standard Specification of Code i.e. B.I.S.
General relevant I.S. of B.I.S. shall prevail for all items including materials,
measurements etc.
The Item wise detailed specifications are intended for full description of items covered
by Schedule “B”. The specifications are not however intended to cover every detail and
the works shall be executed according to the spirit of the specifications below and the
best prevailing P.W.D. practice. The clarification to any clause in detailed specifications
shall be sought from the latest edition of relevant I.S. specification and codes. Where
these specifications are at variance with the specification laid down in the I.S. Books
stated above, the former will be applicable. As regarded matters not covered by any of
the above specification, the decision of the Engineer-in-charge shall be treated as final
and shall be binding upon the contractor. The contractor is expected to get clarified any
doubt about specification, etc. before tendering by discussing with Engineer-in-charge.
For detail technical specification, the item wise description along with above general
specifications shall hold good.
Chief Engineer (Gen)
GSECL: GTPS
Signature Of Contractor
EW- 283 PUR-F-006 RFQ-
SPECIAL CONDITIONS FOR USE OF CEMENT IN WORK
1 The rates in Schedule – ‘B’ is inclusive of cement cost. Contractor has to purchase
fresh 43 grade cement confirming to as per IS 8112 Or PPC IS 1489 (Part-I) or as per
tender condition.
2 Contractor has to construct pucca Go down at site of work so that cement bags can be
properly preserved to avoid damage due to any kind of water/Humidity.
3 Contractor has to bring sufficient quantities of cement bags to maintain progress of
work. The work should not suffer for want of cement.
4 Cement should be used to achieve required strength in cement concrete or as per item
proportion.
5 To bring sufficient & timely cement at site is full responsibility of contractor. Nothing
extra will be paid on account of any reason to maintain progress of work and to
complete the work in schedule time.
6 Contractor has to submit material A/c. For consumption of cement used with every bills.
In case of not submitting the same, bill will not be passed. Party has to submit the copy
of cement purchased bill and Challan/invoice along with each RA Bill/Final Bill.
7 No negative variation will be allowed for consumption in cement less then prescribed as
per R & B SoR OR Corporation/mix design and nothing will be paid extra for over
consumption.
8 Contractor is fully responsible for safety of cement at site; nothing will be paid extra on
account of safety.
9 If Corporation’s authorized representative wants to check cement stock at site,
contractor has to allow for the same at any time.
10 Contractor has to maintain day to day cement consumption / balance account at site.
11 As far as possible, contractor has to maintain supply of cement of only one brand &
grade throughout the work and on account of closer/shortage of approved brand,
cement of other brand in accordance of condition No. (1) Will be allowed by Engineer –
in – Charge.
12 Minimum cement consumption considered for cement concrete having grade of M–15 /
M – 20 / M – 25 is 320 Kgs. / 375 Kgs / 400 Kgs. respectively. Contractor has to use
minimum cement as above. Contractor should not use less than the prescribed
quantities of cement even in the case of mix design recommends lower quantity. For
other items cement consumption shall be as per provisions of SoR without any negative
variation. Nothing will be paid extra for over consumption.
13 Contractor will be allowed to carry out work only after physical verification of cement
brought at site.
14 Full cement bags brought by contractor shall be entered at IN GATE of respective
security cabin / gateat Gandhinagar, TPS.
Chief Engineer (Gen)
GSECL: GTPS
Signature Of Contractor
EW- 283 PUR-F-006 RFQ-
Approved Name of Firms of Manufactures of Civil Items Allowed to use being
supplied by contractors in civil works
Sr. Name of approved Vendor List of Company & their Brand Name in Market
01 A.C.C. Cement A.C.C
02 Ambuja Cement Ambuja
03 Binani Cement Binani
04 Birla Cement Birla A-1
05 Gujarat Sidhee Cement Sidhee
06 J.K. Cement J.K.
07 J.K. Laxmi Cement J.K.Laxmi
08 Sanghi Cement Sanghi
09 Saurastra Cement Hathi
10 Shree Digvijay Cement (SDCC) Kamal
11 India Cement Corromandal King
12 Ultratech Cement (L&T) Ultra-tech
13 HI-BOND Cement Hi-Bond
14 Shree Cement Limited Shree/Bangur/Rock
Strong/Roofon/Bangur Power
15 Midland Concrete Pvt. Ltd., Rajkot S O L ID
CONSTRUCTION CHEMICALS
01 RedWop Chemicals Rajkot
02 Samrock Chemicals Ahmedabad
Water Proofing &Wrapping Coating
01 Bitumag Industries Vadodara
02 A.R. Industries Vadodara
03 Tiki Tar Danosa (India) Pvt. Ltd. Halol
04 STP Ltd., Ankleshwar
Flooring Tiles
01 Asian Granito Sabarkantha
02 Somany Kaloal
03 Simpolo Morbi
04 Varmora Morbi
05 Sunheart Morbi
06 Emcer Morbi
07 Cengres Ahmedabad
Pipes & Fittings
01 Astral Limited, Ahmedabad ASTRAL
EW- 283 PUR-F-006 RFQ-
01 Tata Iron & Steel Co. Ltd TATA
02 Jindal Jindal
03 Lloyds Llyods
04 Essar Steel Ltd. Essar
05 Steel Authority of India. SAIL
06 Parmeshwar Steel Pvt ltd. God TMT
07 Gallant Ispat Ltd. Gallant TMX
08 Aditya Ultra Steel Pvt. Ltd. KAMDHENU NXT & Kay 2 TMT
09 Mono steel India Ltd. MONO TMT
10 Aashiana Rolling Mills Ltd. Friends Steel
11 Electro Therm (I) Ltd. ET TMT
12 H.K. Ispat .Pvt. Ltd. Kothi
13 SRJ peety steel Pvt. Ltd. SHREE OM TMT/SRJ TMT/KAPILA
PURE STEEL
14 NilkanthConcast Private Limited Nilkanth
15 Shreeyam Power & Steel Industries Limited National
16 Utkarsh Bars Private Limited Utkarsh
17 Bhagyalaxmi Rolling Mill Pvt. Ltd Polad
18 ShriKhatuShyam Alloys Pvt. Ltd., Khatu TMT
19 Steefo Steels LLP, Ahmedabad STEEFO TMT
20 Haq Steel &MetaliksLtd.,Kutch GERMAN TMX
21 K.B. Ispat Private Ltd., Bhavnagar KB TMT
22 VMS TMT Private Ltd., Ahmedabad KAMDHENU NXT & Kay 2 TMT
23 Briskon Multimetals LLP
24 Kalika Steel Alloys Pvt. Ltd., Jalna KALIKA 500 TMT
25 Anjar TMT Steel Pvt.Ltd.,Anjar Welspun Shield
26 Shri Bajrang Power &Ispat Ltd. Goel TMT & Pipes
27 Rajuri Steels &TMT Bars Pvt. Ltd. Rajuri Steel
28 SMW Steel Sangam
29 Rathi Steel & Metal Pvt. Ltd. Icon Steel
30 Metarolls Ispat Pvt. Ltd. Metarolls TMT
31 Sai Bandhan Infinium Pvt. Ltd., BANDHAN TMX
32 Gajkesari Steels & Alloys Pvt. Ltd GAJKESARI TMX
33 Rudra Global Infra Product Ltd., RUDRA TMX
34 Varrsana Ispat Ltd.,Gandhidham VARRSANA TMT
35 N.N. Ispat Pvt. Ltd., West Bengal U L T R AMAX TMT
36 Jay Bharat Steel Corporation, Kutch JAY BHARAT TMX & KUTCH TMX
37 Jaideep Ispat & Alloys Pvt Ltd, Indore MOIRA CRS &TMT
38 R S VIRLA Pvt Ltd, Rajkot R S VIRLA TMT & R STMT
39 Bindra Steel Pvt Ltd. Jalna Roopam TMT
40 Rashmi Metaliks Ltd., Kolkata W.B. Rashmi TMT
In addition to the above Approved Vendor List of GSECL, the approved vendor list of GUVNL and its
subsidiary company i.e. GSECL/GETCO/MGVCL /PGVCL/DGVCL & UGVCL which are available on
their website- in tender head including above mention various manufacturers are also to be treated as
Approved Vendors.
EW- 283 PUR-F-006 RFQ-
Chief Engineer (Gen)
Signature Of Contractor GSECL: GTPS
GUJARAT STATE ELECTRICITY CORPORATION LTD
GANDHINAGAR THERMAL POWER STATION
GANDHINAGAR-388239
bungalow at GSECL, Gandhinagar TPS.”
DEVIATION FROM BIDDER (IF ANY)
1. GSECL does not bind to accept the deviation offered by bidder for evaluation of tender.
2. If there is any deviation from bidder, it should be clearly mentioned on this page.
3. Deviation mentioned on other page should not be considered and order will be placed according to
the tender documents.
4. If there is no any deviation from bidder, than it must be clearly mentioned in this page “NO
DEVIATION OFFERRED”
Signature of the Contractor
EW- 283 PUR-F-006 RFQ-
GUJARAT STATE ELECTRICITY CORPORATION LTD
WANAKBORI THERMAL POWER STATION
PO :THERMAL, TA:GALTESHWAR,
DI:KHEDA-388239
bungalow at GSECL, Gandhinagar TPS.”
ANNEXURE -
(UNDERTAKING IN REGARD TO STOP DEAL / BLACK
LIST THEREOF)
All Bidders will have to furnish the following Undertaking duly filled in, signed and stamped for
each quoted item of the Tender along with the Technical Bid.
Sub:- Undertaking in regard to Stop Seal / Banned for Business Dealing / Black List Thereof.
Ref:- Tender No:
Authorized signatory of M/s. _________________________________ _____________
Hereby certify that M/s.____________________________________________________
And their proprietor / any partner / any directors of the firm is not stop deal and/or banned for
business dealing and/or black listed by GUVNL and/or their any subsidiary company viz.
GSECL / GETCO / DGVCL / MGVCL / UGVCL / PGVCL”.
Seal of the Firm.
Signature of the Tenderer.
EW- 283 PUR-F-006 RFQ-
GENERAL SPECIFICATIONS
TECHNICAL SPECIFICATION
DETAILED TECHNICAL SPECIFICATION.
EW- 283 PUR-F-006 RFQ-
GENERAL SPECIFICATIONS
01. In the specifications, “as directed”/”Approved” shall be taken to mean “as
directed”/”approved” by the Engineer-in-charge.
02. Wherever a reference to any Indian Standard appears in the specifications, it shall be taken to
mean as a reference to the latest edition of the same in force on the date of agreement.
03. In “Mode of Measurement” in the specification wherever a dispute arises in the absence of
specific mention of a particular point or aspect, the provisions on these particular points or
aspects in the relevant Indian Standards shall be referred to.
04. All measurements and computations, unless otherwise specified, shall be carried out as per
Latest IS:
05. The distance which constitutes lead shall be determined along the shortest practical route and
not necessarily the route actually taken. The decision of the Engineer-in-charge in this regard
shall be taken as final.
06. Where no lead is specified, it shall mean “all leads”.
07. Lift shall be measured from plinth level.
08. Up to “floor two levels” means actual height of floor up to 6.5 Mt. Above plinth level.
09. Definite particulars covered in the items of work, though not mentioned or elucidated in it,
specification shall be deemed to be included therein.
10. Reference to specifications of materials as made in the detailed specification of the items of
work is in the form of a designation containing the number of the specification of the material
and prefix ‘M’ e.g. ‘M-5’.
11. Approval to the samples of various materials given by the Engineer-in-charge shall not absolve
the contractor from the responsibility of replacing defective material brought on site or
materials used in the work found defective at a later date. The contractor shall have no claim
to any payment or compensation whatsoever on account of any such materials being rejected
by the Engineer-in-charge.
12. The contract rate of the item of work shall be for the work completed in all respects.
13. No collection of materials shall be made before it is got approved from the Engineer-in-
14. Collection of approved materials shall be done at site of work in a systematic manner.
Materials shall be stored in such a manner as to prevent damage, deterioration or intrusion of
foreign matter and to ensure the preservation of their quality and fitness for the work.
15. Cement, reinforcements bars & all other materials to be used shall be got approved from EIC
before starting of work. The cement, reinforcement steel & other materials to be brought at
site shall be entered at GANDHINAGAR, TPS main entry gate.
16. Materials, if and when rejected by the Engineer-in-charge, shall be immediately removed from
the site of work.
17. No materials shall be stored prior to, during and after execution of a structure in such a way
as to cause or lead to damage or overloading of the various components of the structure.
18. All works shall be carried out in a workmanlike manner as per the best techniques for the
particular item.
19. All tools, templates, machinery and equipment for correct execution of the work as well as for
checking lines, levels, alignment of the works during execution shall be kept in sufficient
numbers and in good working condition on the site of the work.
20. The mode, procedure and manner of execution shall be such that it does not cause damage
or over loading of the various components of the structure during execution or after
completion of the structure.
21. Special modes of construction not adopted in general Engineering practice, if proposed to be
adopted by the Contractor, shall be considered only if the contractor provides satisfactory
evidence that such special mode of construction is safe, sound and helps in speedy
construction and completion of work to the required strength and quality. Acceptance of the
same by the Engineer-in-charge shall not, however, absolve the contractor of the
responsibility of any adverse effects and consequences of adopting the same in the course of
execution of completion of the work.
EW- 283 PUR-F-006 RFQ-
22. All installations pertaining to water supply and fixtures thereof as well as drainage lines and
sanitary fittings shall be deemed to be completed only after giving satisfactory tests by the
Contractor.
23. The contractor shall be responsible for observing the rules and regulations imposed under
‘Minor Minerals Act’ and such other laws and rules prescribed by Government from time to
24. All necessary safety measures and precaution [including those laid down in the various
relevant Indian Standards shall be taken to ensure the safety of men, materials and
machinery on the works as also of the work itself.
25. The testing charge of all materials shall be borne by the Contractor unless recovery at one
percent towards using charges is separately made.
26. Approval to any of the executed items for the work does not in any way relieves the
contractor of his responsibility for the correctness, soundness and strength of the structure as
the drawings and specification.
Chief Engineer (Gen)
Signature Of Contractor GSECL: GTPS
EW- 283 PUR-F-006 RFQ-
TECHNICAL SPECIFICATIONS
GSECL, Gandhinagar TPS.”
01. In the specifications, “as directed”/”Approved” shall be taken to mean “as directed”/”approved” by the
Engineer-in-charge.
02. In “Mode of Measurement” in the specification wherever a dispute arises in the absence of specific mention
of a particular point or aspect, the provisions on these particular points, or aspects - the relevant Indian
Standards shall be referred to.
03. All measurements and computations, unless otherwise specified, shall be carried out nearest to the
following limits:
a. Length, width and depth (height) -----------0.01 Meter.
b. Areas-------------------------------------------- 0.01 sq Mt.
c. Cubic Contents-------------------------------- 0.01 Cu. Mt.
04. The distance which constitutes lead shall be determined along the shortest practical route and
not necessarily the route actually taken. The decision of the Engineer-in-charge in this regard shall
be taken as final.
05. Where no lead is specified, it shall mean “all leads”.
06. Lift shall be measured from plinth level.
07. Reference to specifications of materials as made in the detailed specification of the items of work is in the
form of a designation containing the number of the specification of the material and prefix ‘M’ e.g. ‘M5’.
08. Approval to the samples of various materials given by the Engineer-in-charge shall not absolve the
contractor from the responsibility of replacing defective material brought on site or materials used in the work
found defective at a later date. The contractor shall have no claim to any payment or compensation whatsoever
on account of any such materials being rejected by the Engineer-in-charge.
09. The contract rate of the item of work shall be for the work completed in all respects.
10. No collection of materials shall be made before it is got approved from the Engineer-in-charge.
11. Collection of approved materials shall be done at site of work in a systematic & sequantial manner.
Materials shall be stored in such a manner as to prevent damage, deterioration or intrusion of foreign matter
and to ensure the preservation of their quality and fitness for the work.
12. Materials, if and when rejected by the Engineer-in-charge, shall be immediately removed from the site of
13. All tools, templates, machinery and equipment for correct execution of the work as well as for checking
lines, levels, alignment of the works during execution shall be kept in sufficient numbers and in good working
condition on the site of the work.
14. Special modes of construction not adopted in general Engineering practice, if proposed to be adopted by
the Contractor, shall be considered only if the contractor provides satisfactory evidence that such special mode
of construction is safe, sound and helps in speedy construction and completion of work to the required strength
and quality. Acceptance of the same by the Engineer-in-charge shall not, however, absolve the contractor of
the responsibility of any adverse effects and consequences of adopting the same in the course of execution of
completion of the work.
15. All installations pertaining to water supply and fixtures thereof as well as drainage lines and sanitary
fittings shall be deemed to be completed only after giving satisfactory tests by the Contractor.
16. The contractor shall be responsible for observing the rules and regulations imposed under ‘Minor Minerals
Act’ and such other laws and rules prescribed by Government from time to time.
17. The testing charge of all materials shall be borne by the Contractor & reports of authorize laboratory shall
be submitted timely.
18. Approval to any of the executed items for the work does not in any way relieves the contractor of his
responsibility for the correctness, soundness and strength of the structure as per the drawings and
specification.
19. Due care at all the items shall be taken to see that no damage is caused to the existing setup of GSECL. In
case of any such damage is caused, it shall be restored by the agency at his own cost.
EW- 283 PUR-F-006 RFQ-
DETAILED TECHNICAL SPECIFICATION
NOTE: BOOKLET FOR “GENERAL TECHNICAL SPECIFICATIONS FOR BUILDING WORKS” OF R. & B.
DEPARTMENT, GOG, GUJARAT AND BOOKLET OF “GENERAL SPECIFICATION FOR CIVIL WORKS” OF
GSECL WILL BE AVAILABLE IN CIVIL OFFICE AT GANDHINAGAR TPS FOR REFERNCE OF RELEVANT
DETAIL SPECIFICATIONS OF ITEMS. SHALL BE CONSIDERED & ADOPTED IN WORK.
GSECL, Gandhinagar TPS.”
GENERAL SPECIFICATIONS
27. In the specifications, “as directed”/”Approved” shall be taken to mean “as directed”/”approved” by
the Engineer-in-charge.
28. Wherever a reference to any Indian Standard appears in the specifications, it shall be taken to mean
as a reference to the latest edition of the same in force on the date of agreement.
29. In “Mode of Measurement” in the specification wherever a dispute arises in the absence of specific
mention of a particular point or aspect, the provisions on these particular points or aspects in the
relevant Indian Standards shall be referred to.
30. All measurements and computations, unless otherwise specified, shall be carried out as per Latest
31. The distance which constitutes lead shall be determined along the shortest practical route and not
necessarily the route actually taken. The decision of the Engineer-in-charge in this regard shall be
taken as final.
32. Where no lead is specified, it shall mean “all leads”.
33. Lift shall be measured from plinth level.
34. Up to “floor two levels” means actual height of floor up to 11.0 Mt. Above plinth level.
35. Definite particulars covered in the items of work, though not mentioned or elucidated in it,
specification shall be deemed to be included therein.
36. Reference to specifications of materials as made in the detailed specification of the items of work is
in the form of a designation containing the number of the specification of the material and prefix ‘M’
37. Approval to the samples of various materials given by the Engineer-in-charge shall not absolve the
contractor from the responsibility of replacing defective material brought on site or materials used in
the work found defective at a later date. The contractor shall have no claim to any payment or
compensation whatsoever on account of any such materials being rejected by the Engineer-in-
38. The contract rate of the item of work shall be for the work completed in all respects.
39. No collection of materials shall be made before it is got approved from the Engineer-in-charge.
40. Collection of approved materials shall be done at site of work in a systematic manner. Materials shall
be stored in such a manner as to prevent damage, deterioration or intrusion of foreign matter and
to ensure the preservation of their quality and fitness for the work.
41. Cement, reinforcements bars & all other materials to be used shall be got approved from EIC before
starting of work. The cement, reinforcement steel & other materials to be brought at site shall be
entered at Gandhinagar TPS main entry gate.
42. Materials, if and when rejected by the Engineer-in-charge, shall be immediately removed from the
site of work.
43. No materials shall be stored prior to, during and after execution of a structure in such a way as to
cause or lead to damage or overloading of the various components of the structure.
44. All works shall be carried out in a workmanlike manner as per the best techniques for the particular
45. All tools, templates, machinery and equipment for correct execution of the work as well as for
checking lines, levels, alignment of the works during execution shall be kept in sufficient numbers
and in good working condition on the site of the work.
46. The mode, procedure and manner of execution shall be such that it does not cause damage or over
loading of the various components of the structure during execution or after completion of the
structure.
47. Special modes of construction not adopted in general Engineering practice, if proposed to be
adopted by the Contractor, shall be considered only if the contractor provides satisfactory evidence
EW- 283 PUR-F-006 RFQ-
that such special mode of construction is safe, sound and helps in speedy construction and
completion of work to the required strength and quality. Acceptance of the same by the Engineer-
in-charge shall not, however, absolve the contractor of the responsibility of any adverse effects and
consequences of adopting the same in the course of execution of completion of the work.
48. All installations pertaining to water supply and fixtures thereof as well as drainage lines and sanitary
fittings shall be deemed to be completed only after giving satisfactory tests by the Contractor.
49. The contractor shall be responsible for observing the rules and regulations imposed under ‘Minor
Minerals Act’ and such other laws and rules prescribed by Government from time to time.
50. All necessary safety measures and precaution [including those laid down in the various relevant
Indian Standards shall be taken to ensure the safety of men, materials and machinery on the works
as also of the work itself.
51. The testing charge of all materials shall be borne by the Contractor unless recovery at one percent
towards using charges is separately made.
52. Approval to any of the executed items for the work does not in any way relieves the contractor of
his responsibility for the correctness, soundness and strength of the structure as the drawings and
specification.
SPECIFICATIONS OF MATERIALS
M-1 Water:
1.1 Water shall not be salty or brackish and shall be clean, reasonably clear and free from
objectionable quantities of silt and traces of oil and injurious alkalis, salts, organic matter and other
deleterious material which will either weaken the mortar or concrete or cause efflorescence or attack
the steel in R.C.C Container for transport, storage and handling of water shall be clean. Water shall
conform to the standards specified I.S 456-1978.
1.2 If required by Engineer-in-charge it shall be tested by comparison with distilled water.
Comparison shall be made by means of standard cement tests for soundness, time of setting and
mortar strength as specified in I.S.269-1976. Any indication of unsoundness, change in time of
setting by 30 minutes or more or decrease of more than 10 per cent in strength of mortar prepared
with water sample when compared with the results obtained with mortar prepared with distilled
water shall be sufficient cause for rejection of water under test.
1.3 Water for curing mortar, concrete or masonry should not be too acidic or too alkaline. It shall be
free of elements which significantly affect the hydration reaction or otherwise interfere with the
hardening of concrete during curing or those which produce objectionable stains or other unsightly
deposits on concrete or mortar surfaces.
1.4 Hard and bitter water shall not be used for curing.
Potable water will be generally found suitable for curing mortar or concrete.
M-3 Cement:
Cement shall be ordinary Portland slag cement as per I.S. 269-1976 or Portland slag cement as per
6.1 Sand shall be natural sand, clean, well graded, hard strong durable and gritty particle free from
injurious amounts of dust clay, kankar nodules, soft or flaky particles shale, alkali, salts organic
matter, loam, mica or other deleterious substance and shall be got approved from the Engineer-in-
charge. The sand shall not contain more that 8 percent of silt as determined by field test. If
necessary the sand shall be washed to make it clean.
6.2 Coarse Sand: The fineness modulus of coarse sand shall not be less than 2.5 and shall not
exceed 3.0.
The sieve analysis or coarse shall be as under:
I.S. Sieve Percentage by I.S. Sieve Percentage by
Designation weight Designation weight
Passing sieve Passing sieve
4.75 mm. 100 600 Micron 30-100
2.36 mm. 90 to 100 300 Micron 5-70
1.18 mm. 70-100 150 Micron 0-50
6.3 Fine Sand: The fineness modulus shall not exceed 1.0. The sieve analysis of fine sand shall be
EW- 283 PUR-F-006 RFQ-
I.S. Sieve Percentage by I.S. Sieve Percentage by
Designation weight Designation weight
Passing through Passing through
4.75 mm. 100 600 Micron 40-85
2.36 mm. 100 300 Micron 5-50
1.18 mm. 70-100 150 Micron 0-10
M-8 Stone Grit:
8.1 Grit shall consist of crushed or broken stone and be hard strong, dense, durable, clean, of proper
gradation and free from skin or coating likely to prevent adhesion of mortar Grit shall generally be
cubical in shape and as far as possible flaky elongated pieces shall be avoided. It shall generally
comply with the provisions of I.S. 383-1970. Unless special stone of particular quarries is mentioned,
grit shall be obtained from the best black trap or equivalent hard stone as approved by the Engineer-
in-charge. The grit shall have no deleterious reaction with cement.
8.2 The grit shall conform to the following gradation as per sieve analysis :
I.S. Sieve Percentage I.S. Sieve Percentage
Designation Passing Designation Passing
Through sieve Through sieve
8.3 The crushing strength of grit will be such as to allow the concrete in which it is used to built up
the specified strength of concrete.
8.4 The necessary tests for grit shall carried out as per the requirements of I.S.2386 (Parts I to VII)
1963, as per instructions of the Engineer-in-charge. The necessity of test will be decided by the
Engineer-in-charge.
M-11. Cement Mortar:
11.1 Water shall conform to specification M-1. Cement :Cement shall conform to specification M-3.
Sand :Sand shall conform to M-6.
11.2 Proportion of Mix : 11.2.1 Cement and sand shall be mixed to specified proportion, sand
being measured by measuring boxes. The proportion of cement will be by volume on the basis of
Kg./Bag of cement being equal to 0.0342 Cu. M. The mortar may be hand mixed or machine mixed
as directed.
11.3 Preparation of Mortar: 11.3.1 In hand mixed mortar cement and sand in the specified
proportions shall be thoroughly mixed dry on a clean impervious platform by turning over at least
times or more till a homogenous mixture of uniform color is obtained. Mixing platform shall be so
arranged that no deleterious extraneous material shall get mixed with mortar or mortar shall flow
out. While mixing, the water shall be gradually added and thoroughly mixed to form a stiff plastic
mass of uniform color so that each particle of sand shall be completely covered with a film of wet
cement. The water cement ratio shall be adopted as directed.
11.3.1 The mortar so prepared shall be used within 30 minutes of adding water. Only such quantity
of mortar shall be prepared as can be used within 30 minutes.
M-12 Stone Coarse Aggregate for Nominal Mix Concrete:
12.1 Coarse aggregate shall be machine crushed stone of black trap or equivalent and be hard,
strong, dense, durable, clean and free from skin and coating likely to prevent proper adhesion of
12.2 The aggregate shall generally be cubical in shape. Unless special stones of particular quarries
are mentioned aggregates shall be machine crushed from the best black trap or equivalent hard
stone as approved. Aggregate shall have no deleterious reaction with cement. The size of the coarse
aggregate for plain cement concrete and ordinary reinforced cement concrete shall generally be as
per the table given below, However in case of reinforced cement concrete the maximum limit may be
EW- 283 PUR-F-006 RFQ-
restricted to 6 mm. Less than the minimum lateral clear distance between bars or 6 mm. Less than
the cover, whichever is smaller.
I.S. Sieve Percentage passing for I.S. Sieve Percentage passing for
Designation single sized aggregates of Designation single sized aggregates of
nominal size Nominal size
Note: This percentage may be varied somewhat by Engineer-in-charge when considered necessary
for obtaining better density and strength of concrete.
The grading test shall be taken in the beginning and at the change of source of materials. The
necessary test indicated in I. S. 383-1970 and I.S. 456-1978 shall have to be carried out to be
carried out to ensure the acceptability. The aggregates shall be stored separately and handled in such
a manner as to prevent the intermixing of different aggregates. If the aggregates are covered with
dust, they shall be washed with water to make them clean.
M-13.Blak Trap or Equivalent Hard Stone Coares.
13.1. Aggregate For Design Mix Concrete : Coarse aggregate shall be of machine crushed stone of
black trap or
equivalent hard stone and be hard strong dense, durable clean and free from skin and coating likely
to prevent proper adhesion of mortar.
13.2. The aggregates shall generally be cubical in shape. Unless special stones of particular quarries
are mentioned, aggregate shall be machine crushed from4he best, black trap or equivalent hard
stones as approved. Aggregate shall have no deleterious reaction with cement.
13.3. The necessary tests indicated in I.S. 383-1970 and I.S. 456-1978 shall have to the carried oat
to. ensure the acceptability of the material.
12.3 13.4. If aggregate is covered with dust it shall be washed with water to make it clean..
M-15 Bricks :
15.1 The bricks shall be hand or machine molded and made from suitable Flyash and klin-burnt.
They shall be free from crack and nodules of free lime. They shall have smooth rectangular faces
with sharp corners and shall be of uniform color.
The bricks shall be molded with a frog of 100 mm. X 40 mm. And 10 mm. To 20 mm. Deep on one of
its flat sides. The bricks shall not break when thrown on the ground from a height of 600 mm.
15.2 The size of modular bricks shall be 190 mm. X 90 mm. X 90 mm.
15.3 The size of the conventional bricks shall be as under :
15.4 Only bricks of one standard size shall be used on one work. The following tolerances shall be
permitted in the conventional size adopted in a particular work.
Length : 1.8(3.0 mm.) Width : 1/6” (1.51 mm.) Height : 1/6” (1.50 mm.)
15.5 The crushing strength of the bricks shall not be less than 35 Kg./Sq. Cm. The average water
absorption shall not be more than 20 percent by weight. Necessary tests for crushing strength and
water absorption etc. Shall be carried out as per I. S. 3495 (Part-I to IV)
M-18. Mild Steel Bars
18.1 Mild steel bars reinforcement for R.C.C. work shall conform to I.S, 432 (Part-II) 1966 and §hail
be of tested quality.It shall also comply with relevant part of I.S. 456-
18.2 All the reinforcement shall be clean and free from dirt, paint, grease, mill scale or loose or thick
rust at the time ofplacing.
18.3 For the purpose of payment, the bar shall be measured correct upto 100 mm. length and weight
payable worked outat the rate specified below :
EW- 283 PUR-F-006 RFQ-
1. .6 mm. 0,22 Kg./Rmt. 8 20 mm. 2.47 Kg./Rmt.
2. 8 mm. 0.39 Kg./Rmt. 9. 22. mm. 2.98 Kg./Rmt.
3. 10mm. 0.62 Kg./Rmt. 10. 25 mm. 3.85 Kg./Rmt.
4. 12 mm. 0.89 Kg./Rmt. 11. 28 mm. 4,83 Kg./Rmt.
5. 14 mm. 1.21 Kg./Rmt. 12. 32 mm. 6.3.1 Kg./Rmt.
6. 16mm. 1 .58 Kg./Rmt, 13. 36 mm. 7.99 Kg./Rmt.
7. 18 mm. 2.00 Kg./Rmt. 14. 40 mm. 9.86 Kg/Rmt.
M-19. High Yield Strength Steel Deformed Bars
19.1. High yield strength steel deformed bars be either cold twisted or hot/rolled, shall conform to
I.S. 1739-1966 andI.S.1139-1966 respectively.
19.2. Other provision and requirements shall conform to specification No. M-18.for Mild steel bars.
M-21 Mild Steel Binding Wire:
21.1 The mild steel wire shall be of 1.63 mm. Or 1.22 mm. (16 or 18 gauge) diameter and shall
conform to I. S. 280-1972.
21.2 The use of black wire will be permitted for binding reinforcement bars. It shall be free from
rust, oil paint, grease, loose mill scale or any other undesirable coating which may prevent adhesion
of cement mortar.
M-22 Structural Steel :
22.1 All structural steel shall conform to I. S. 226-1965. The steel shall be free from the defects
mentioned in I. S. 226-1975 and shall have a smooth finish. The materials shall be free from loose
mill scale, rust pits or other defects affecting the strength and durability. Rivet bars shall conform to
22.2 When the steel is supplied by the Contractor test certificates of the manufactures shall be
obtained according to I. S. 226-1975 and other relevant Indian Standards.
This part of the specification deals with requirements for repair & retrofitting of various quarters in
GSECL Colony GTPS.
Applicable Codes
The provisions of relevant IS specifications for materials, respective items, published by BIS shall be
followed for all purposes shall be followed.
The Engineer will furnish indicative drawings wherever in his opinion such drawings are required to
show the areas to be repaired, sequence of priorities etc. The contractor shall follow such drawings
The specifications to be followed for this work are the specification for repairing of RCC structures
published by the BIS for relevant Items. This specification shall be supplemented by the technical
specification as given here under in this document and also the provision in the relevant IRC & IS
In case of any discrepancy or contradiction if any in the provision of above specification the order of
the precedence shall be followed.
2. IRC Provisions
3. IS Provisions
4. Technical Specification in this Volume
5. Sound Engineering Practice
6. Manufacture specification for special items
All work shall be carried out in confirmation with the above specifications. These specifications
broadly cover all major aspects of the work involved. Minor details may not be specified here
however if these are necessary for completion of work the contractor shall execute such minor items
without any additions to the costs.
All work shall be executed in accordance with good engineering practices. The Contractor shall
remain responsible for workmen’s compensation if any, when such case occurs.
The Contractor shall have to give site clean of all rubbish on completion of work and handover the
EW- 283 PUR-F-006 RFQ-
structure with final finishing as directed. All the rejected materials shall be removed from site by
Contractor at his risk and cost.
GENERAL DETAILS
All work shall be carried out in confirmation with these specifications. In general, provisions of Indian
Standard, Indian Road Congress codes and other national standards shall be followed unless
otherwise specified. These specifications are not intended to cover the minor details. The work shall
be executed in accordance with best modern practices & all latest codes and standards referred to in
these specifications shall be read in conjunction with the various other documents forming the
contract, tender specifications, BOQ, contract drawings and other related documents.
Measurement and payments
a) Mode of measurements:
The methods of measurement and payment shall be as described under various items and in Price
Bid. Where specific definitions are not given, the methods described in IS code will be followed?
b) Unacceptable work:
All defective works are liable to be demolished, rebuilt and defective materials replaced by the
contractor at his own cost. In the event of such works being accepted by carrying out repairs etc. as
specified by the engineer in charge, the cost of repairs will be borne by the contractor
Safety and Control
The Contractor shall take all necessary measures for the safety during construction / repair activities
and provide, erect and maintain such barricades, including signs, markings, flags, lights etc. as may
be required by the Engineer for the information and protection of persons approaching or passing
through the section of the plant under repair.
Scaffolding
Scaffolding shall consist of double legged steel scaffolding with necessary bracing and planks. All
members before installations shall be checked for their strength and stiffness and other requirements
as per below described safe erection of scaffolding.
a) Erect metallic scaffolding including supply of all scaffolding material like pipes, planks, clamps,
pins, ladders etc.
b) In case of difficulties and to suit the site conditions, scaffolding may be modified as per instruction
of engineer in charge.
c) In case of site restrictions contractor have to carry out necessary improvements / alterations in
scaffolding wherever required keeping in mind the site conditions and safety requirements both.
d) All scaffolding shall be subjected to inspection and approval of engineer in charge after its
Before taking up any construction /repair activities, an agreed phased program shall be drawn up in
consultation with the Engineer to facilitate smooth operation of the plant.
DETAILED SPECIFICATIONS
Item no.
Dismantling tiled of stone floors laid in mortar including stacking of serviceable materials
and disposal of unserviceable materials with all lead and lift.
1.1 The tiles or kotah stone flooring shall be removed carefully so as to have minimum damage to
tiles or kotah stones. Removed usable tiles or kotah stones shall be stacked separately as directed.
The base concrete of the flooring shall be removed completely and disposed of at the places shown.
The usable materials are to be credited to deptt. store.
The payment shall be made on the actual floor area removed in square meter. Rates quoted shall be
inclusive of all tools, tackles, labour, transportation etc.
1.2. The demolition shall always be planned before hand and shall be done in reverse order of the
one in which the structure was constructed. This scheme shall be got approved from the Engineer-
in-charge before starting the work. This however will not absolve the contractor from the
EW- 283 PUR-F-006 RFQ-
responsibility of proper and safe demolition.
1.3. Necessary dropping, shoring and under pinning shall be provided for the safety of the adjoining
work or property, which is to be left intact, before dismantling and demolishing is taken up and the
work shall be carried out in such a way that no damages is caused to the adjoining property.
1.4. Wherever required, temporary enclosures or partitions shall also be provided. Necessary
precautions shall be taken to keep the dust nuisance down as and where necessary.
1.5. Dismantling shall be commenced in a systematic manner. All materials which are likely to be
damaged by dropping from a height or demolishing, masonry etc. shall be carefully dismantled first.
The dismantled articles shall be properly stacked as directed.
1.6. All materials obtained from demolition shall be the property of Government unless otherwise
specified and shall be kept in safe custody until handed over to the Engineer-in-charge.
1.7. Any serviceable material, obtained during dismantling or demolition shall be separated out and
stacked properly as directed, with all lead and loft. All unserviceable materials, rubbish etc. shall be
stacked as directed by the Engineer-in-charge.
1.8. On completion of work, the site shall be cleared of all debris rubbish and cleaned as directed.
2.0. Mode of measurements & payment :
2.1. Measurements of all work except hidden work shall be taken before demolition or no allowance
for increase in bulk shall be allowed. The demolition of lime concrete shall be measured under this
item. Specification for deduction for voids, openings etc. shall be on same basis as that employed for
construction of work.
2.2. All work shall be measured in decimal system as fixed in its place subject to the following limits,
unless otherwise stated hereinafter: (a) Dimensions shall be measured to the nearest 0.01 mt. (b)
Area shall be worked out to the nearest 0.01 sq. mt
(c) Cubical connection shall be worked out to the nearest 0.01 Cu. M.
2.3. The rate shall include cost of all labour involved and tools used in demolishing and dismantling in
including scaffolding. The rate shall also include the charges for separating out and stacking the
serviceable materials properly and disposing the unserviceable materials with all lead and lift. The
rate also includes for temporary storing for the safety of the portion not required to be pulled down
or of adjoining properly and providing temporary enclosures or partitions where considered.
2.0. Mode of measurements & payment :
The rate shall be for a unit of one square meter.
Item no.
Demolition of Brick work and stone masonry including stacking of serviceable materials
and disposal of unserviceable materials with all lead and lift. (i) Cement Mortar.
1. Workmanship:
1.1. The demolition shall consist of demolition of one or more parts of the building as specified or
shown in the drawings. Demolition implies taking up or down or breaking up. This shall
consist of demolishing whole or part of work including all relevant items as specified or
shown in the drawings.
1.2. The demolition work. shall always be planned before hand and shall be done in reverse order
of the one in which the structure was constructed. This scheme shall be got approved from
the Engineer-in-charge before starting the work. This however will not absolve the
contractor from the responsibility of proper and safe demolition.
1.3. Necessary dropping, shoring and under pinning shall be provided for the safety of the
adjoining work or property, which is to be left intact, before dismantling and demolishing is
taken up and the work shall be carried out in such a way that no damages is caused to the
adjoining property.
1.4. Wherever required, temporary enclosures or partitions shall also be provided. Necessary
precautions shall be taken to keep the dust nuisance down as and where necessary.
1.5. Dismantling shall be commenced in a systematic manner. All materials which are likely to be
damaged by dropping from a height or demolishing, Shall be carefully dismantled first. The
dismantled articles shall be properly stacked as directed.
1.6. All materials obtained from demolition shall be the property of Government unless otherwise
specified and shall be kept in safe custody until handed over to the Engineer-in-charge.
1.7. Any serviceable material, obtained during dismantling or demolition of sheet roofing including
EW- 283 PUR-F-006 RFQ-
ridges, hips, valleys, gutters shall be separated out and stacked properly as directed, with all
lead and loft. All unserviceable materials, rubbish etc shall be stacked as directed by the
Engineer-in-charge.
1.8. On completion of work, the site shall be cleared of all debris rubbish and cleaned as directed.
1.9. Dismantling implies carefully, taking up or down or these are fixed by nail, screws, bolts etc.
These shall be taken out with proper tools
2. Mode of measurements & payment :
2.1. Measurements of all work except hidden work shall be taken before demolition or no
allowance for increase in bulk shall be allowed. The demolition of brick or stone masonry in
cement mortar shall be measured under this item. Specification for deduction for voids,
openings etc. shall be on same basis as that employed for construction of work.
2.2. All work shall be measured in decimal system as fixed in its place subject to the following
limits, unless otherwise stated hereinafter: (a) Dimensions shall be measured to the nearest
0.01 mt. (b) Area shall be worked out to the nearest 0.01 sq. mt (c) Cubical connection shall
be worked out to the nearest 0.01 Cu. M.
2.3. The rate shall include cost of all labour involved and tools used in demolishing and
dismantling in including scaffolding. The rate shall also include the charges for separating out
and stacking the serviceable materials properly and disposing the unserviceable materials
with all lead and lift. The rate also includes for temporary storing for the safety of the
portion not required to be pulled down or of adjoining properly and providing temporary
enclosures or partitions where considered necessary.
2.4. The unserviceable materials shall be stacked as directed by Engineer-in-charge with all leads
and lifts.
2.5. The rate shall be for a unit of one Cubic. Metre.
Item no.
Demolition including stacking of serviceable materials and disposal of unserviceable
materials with all lead and lift. (i) R.C.C. work.
1. Workmanship:
1.1. The demolition shall consist of demolition of one or more parts of the building as specified or
shown in the drawings. Demolition implies taking up or down or breaking up. This shall
consist of demolishing whole or part of work including all relevant items as specified or
shown in the drawings.
1.2. The RCC work includes slab, Parapet, Chhajja. Lintel, gutters etc. shall always be planned
before hand and shall be done in reverse order of the one in which the structure was
constructed. This scheme shall be got approved from the Engineer-in-charge before starting
the work. This however will not absolve the contractor from the responsibility of proper and
safe demolition.
1.3. Necessary dropping, shoring and under pinning shall be provided for the safety of the
adjoining work or property, which is to be left intact, before dismantling and demolishing is
taken up and the work shall be carried out in such a way that no damages is caused to the
adjoining property.
1.4. Wherever required, temporary enclosures or partitions shall also be provided. Necessary
precautions shall be taken to keep the dust nuisance down as and where necessary.
1.5. Dismantling shall be commenced in a systematic manner. All materials which are likely to be
damaged by dropping from a height or demolishing, Shall be carefully dismantled first. The
dismantled articles shall be properly stacked as directed.
1.6. All materials obtained from demolition shall be the property of Government unless otherwise
specified and shall be kept in safe custody until handed over to the Engineer-in-charge.
1.7. Any serviceable material, obtained during dismantling or demolition of sheet roofing including
ridges, hips, valleys, gutters shall be separated out and stacked properly as directed, with all
lead and loft. All unserviceable materials, rubbish etc shall be stacked as directed by the
Engineer-in-charge.
1.8. On completion of work, the site shall be cleared of all debris rubbish and cleaned as directed.
1.9. Dismantling implies carefully, taking up or down or these are fixed by nail, screws, bolts etc.
These shall be taken out with proper tools
EW- 283 PUR-F-006 RFQ-
2. Mode of measurements & payment :
2.1. The area of demolished RCC work shall be measured in Cubic meter.
2.2. The unserviceable materials shall be disposed of at all leads and lifts. The rate excludes
scraping straightening of reinforcement but includes cutting of reinforcement.
2.3. The rate shall be for a unit of one Cubic meter.
Item no.
Dismantling of sheet roofing including ridges, Hips, Valleys, Gutters etc. stacking of
serviceable materials and disposal of unserviceable materials with all lead and lift.(i) G.I.
sheet roofing.
Workmanship :
The demolition shall consist of demolition of roof sheet as specified or shown in the drawings
up to any height. This shall consist of demolishing whole or part of work including all relevant
item as specified or shown in the drawings.
The demolition shall always be planned before hand and shall be done in reverse order of the
one in which the structure was constructed. This scheme shall be got approved from the
Engineer-in-charge before starting the work. This however will not absolve the contractor
from the responsibility of proper and safe demolition.
Necessary dropping, shoring and under pinning shall be provided for the safety of the
adjoining work or property, which is to be left intact, before dismantling and demolishing is
taken up and the work shall be carried out in such a way that no damages is caused to the
adjoining property.
Wherever required, temporary enclosures or partitions shall also be provided. Necessary
precautions shall be taken to keep the dust nuisance down as and where necessary.
Dismantling shall be commenced in a systematic manner. All materials which are likely to be
damaged by dropping from a height or demolishing, masonry etc shall be carefully dismantled
first. The dismantled articles shall be properly stacked as directed.
All materials obtained from demolition shall be the property of Government unless otherwise
specified and shall be kept in safe custody until handed over to the Engineer-in-charge.
Any serviceable material, obtained during dismantling or demolition shall be separated out and
stacked properly as directed, with all lead and lift. All unserviceable materials, rubbish etc
Shall be stacked as directed by the Engineer-in-charge.
The entire work area will be barricaded with barricading tape and “MEN AT WORK” signboard
will be erected in all entry point to work area.
Safety belts shall be used by labourers while working at higher level to prevent falling from
the structure. Wherever, possible mechanized working platform shall be used.
On completion of work, the site shall be cleared of all debris rubbish and cleaned as directed.
The AC sheet should be dismantled proper method that it should not be damaged and it
should be utilized in future. Dismantled AC sheet shall be stacked in proper method at location
shown by EIC.
Mode of measurements & payment :
The flat area of AC sheet roofing shall be measured in sq. metre for dismantling the sheet.
Ridge, hips and valley shall be girthed and included with roof area. Corrugated and semi-
corrugated surfaces shall be measured flat and not girthed.
Supporting member such as rafters, purlins, beams, joints, trusses etc shall be measured
separately.
The rate shall be including disposal of unserviceable materials with all leads and lifts and
stacking the serviceable materials as directed.
The rate shall be for a unit of one sq. Meter for removing the sheet up to any height and credited to
store or as directed by EIC.
Item no.
Dismantling doors, windows, ventilators etc. (wood, Aluminum, PVC or steel) shutters
including chowkhats architraves, holdfasts and other attachment etc. complete and
EW- 283 PUR-F-006 RFQ-
stacking them within all lead and lift.(i) Not exceeding 3 Sq.M. in area.
Workmanship: 1. Workmanship: (up to any height)
1.1 The demolition shall consist of demolition of one or more parts of the building as specified or
shown in the drawings. Demolition implies taking up or down or breaking up. This shall consist of
demolishing whole or part of work including all relevant items as specified or shown in the drawings.
1.2 The demolition shall always be planned before hand and shall be done in reverse order of the one
in which the structure was constructed. This scheme shall be got approved from the Engineer
incharge before starting the work. This however will not absolve the contractor from the responsibility
of proper and safe demolition.
1.3 Necessary dropping, shoring and under pinning shall be provided for the safety of the adjoining
work or property, which is to be left intact, before dismantling and demolishing is taken up and the
work shall be carried out in such a way that no damages is caused to the adjoining property.
1.4 Wherever required, temporary enclosures or partitions shall also be provided. Necessary
precautions shall be taken to keep the dust nuisance down as and where necessary.
1.5 Dismantling shall be commenced in a systematic manner. All materials which are likely to be
damaged by dropping from a height or demolishing, masonry etc. shall be carefully dismantled first.
The dismantled articles shall be properly stacked as directed.
1.6 All materials obtained from demolition shall be the property of Government unless otherwise
specified and shall be kept in safe custody until handed over to the Engineer-in-charge.
1.7 Any serviceable material, obtained during dismantling or demolition shall be separated out and
stacked properly as directed, with all lead and loft. All unserviceable materials, rubbish etc. shall be
stacked as directed by the Engineer-in-charge.
1.8 On completion of work, the site shall be cleared of all debris rubbish and cleaned as directed.
2. Mode of measurements & payment:
2.1 Measurements of all work except hidden work shall be taken before demolition or no allowance
for increase in bulk shall be allowed. The demolition of lime concrete shall be measured under this
Specification for deduction for voids, openings etc. shall be on same basis as that employed for
construction of work.
2.2 All work shall be measured in decimal system as fixed in its place subject to the following limits,
unless otherwise stated hereinafter: (a) Dimensions shall be measured to the nearest 0.01 mt. (b)
Area shall be worked out to the nearest 0.01 sq. Mt. (c) Cubical connection shall be worked out to
the nearest 0.01 Cu. M.
2.3 The rate shall include cost of all labour involved and tools used in demolishing and dismantling in
including scaffolding. The rate shall also include the charges for separating out and stacking the
serviceable materials properly and disposing the unserviceable materials with all lead and lift. The
rate also includes for temporary storing for the safety of the portion not required to be pulled down
or of adjoining properly and providing temporary enclosures or partitions where considered
necessary.
2.4 The rate shall be for a unit of Nos.
Mode of measurements & payment :
The doors, windows, ventilators etc. Not exceeding 3 sq. Mt. In area (each) including shutters and
chowkhats Architraves, hold fasts and other attachments to grames etc. Will be dismantled and
measured under this item.
The rate includes stacking serviceable materials as and where directed with all leads and lifts.
The rate shall be for a unit of one number.
The rate includes stacking serviceable materials as and where directed with all leads and lifts.
The rate shall be for a unit of one number.
Item no.
Dismantling steel work including distempering and stacking the materials with all lead
Workmanship :
The demolition shall consist of demolition of one or more parts of the building as specified or
shown in the drawings. Demolition implies taking up or down or breaking up. This shall
consist of demolishing whole or part of work including all relevant item as specified or shown
EW- 283 PUR-F-006 RFQ-
in the drawings upto any height.
The Item includes demolition of structural steel members like I-beam, channels, angles,
purlins, cable trays, cleats, girders, railway track lines, nut-bolts etc.
The demolition shall always be planned before hand and shall be done in reverse order of the
one in which the structure was constructed. This scheme shall be got approved from the
Engineer-in-charge before starting the work. This however will not absolve the contractor
from the responsibility of proper and safe demolition.
Necessary dropping, shoring and under pinning shall be provided for the safety of the
adjoining work or property, which is to be left intact, before dismantling and demolishing is
taken up and the work shall be carried out in such a way that no damages is caused to the
adjoining property.
Wherever required, temporary enclosures or partitions shall also be provided. Necessary
precautions shall be taken to keep the dust nuisance down as and where necessary.
Dismantling shall be commenced in a systematic manner. All materials which are likely to be
damaged by dropping from a height or demolishing, masonry etc shall be carefully dismantled
first. The dismantled articles shall be properly stacked as directed.
Safety belts shall be used by labourers while working at higher level to prevent falling from
the structure. Wherever, possible mechanized working platform shall be used.
All materials obtained from demolition shall be the property of Government unless otherwise
specified and shall be kept in safe custody until handed over to the Engineer-in-charge.
Any serviceable material, obtained during dismantling or demolition shall be
separated out and stacked properly as directed, with all lead and lift. Serviceable
structural steel shall be stacked within plant premises at main store or at the
location shown by EIC properly. Record for the same shall be maintained and
submitted to civil section regularly. All unserviceable materials, rubbish etc shall be
stacked as directed by the Engineer-in-charge.
On completion of work, the site shall be cleared of all debris rubbish and cleaned as directed.
The weight of the member shall be computed from standard tables unless the actual weight
can be readily determined.
Riveted works where rivets are required to be cut, the same shall be carried out under this
item and nothing extra shall be paid, if any.
Existing steel Structure fabricated using nut-bolts, the same shall be dismantled by removing
the same in systematic manners so the same will be utilized for other purpose.
In framed steel gate, the weight of any covering materials or filling such as iron sheets and
expanded metal shall be added to the weight of the main articles if such covering is not
ordered to be taken out separately.
The entire work area will be barricaded with barricading tape and “MEN AT WORK” signboard
will be erected in all entry point to work area.
The rate includes stacking the materials as and where directed with all leads and lifts and upto
any height.
The dismantled material shall be credited to Main store.
The structure should be dismantled by proper method and to make piece of each members of
structure for utilization in future and credited to main store.
Mode of measurements & payment :
The weight of the member shall be computed from standard tables unless the actual weight
can be readily determined.
The rate includes stacking the materials at location shown by EIC with all machineries like gas
cutter, gas bottle, hydra/crane, man power etc including transportation.
The rate shall be for a unit of one kg.
Item no.
Excavation for foundation upto 1.5 m depth including sorting out and stacking of useful
materials and disposing off the excavated stuff upto 50 Meter lead. (A) Loose or soft soil.
General: Any soil which generally yields to the application of pickaxes and shovels, phawaras, rakes
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
GTPS_Tender _ EW-283_11_05_2026.pdf
GTPS_Tender _ EW-283_11_05_2026.pdf
CORRIGENDUM
Download all tender documents and submit your bid