Tender Value
₹46.6 Cr
EMD Value
₹46.6 L
Closing Date
3 Oct 2026, 6:00 pm6d left
Executive Engineer, Salinity Control Division, Porbandar
Integrated Irrigation, Drainage and Water Infrastructure Modernization Project in Sorthi Ghed Area Phase-2 , Package-2:- Deepening and Desilting of Rivers and Drains, Sub Package-2:- Excavation and Re-Sectioning of Various Rivers/Drains Including Construction of Various New Canals in Sorthi Ghed Porbandar District.
341350
06 of 2026-27
Open
Civil Works - Others
Works
Porbandar
16 documents required · 15 mandatory · 1 optional
₹18,000
Executive Engineer, Salinity Control Division, Porbandar
₹46.6 L
3 Sept 2026
3 Sept 2026
3 Sept 2026
3 Oct 2026
3 Sept 2026
BILL OF QUANTITIES
1. The bill of Quantities shall be read in conjunction with the Instructions to Bidder,
Conditions of Contract, Technical Specifications and Drawings.
2. The quantities given in the Bill of Quantities are estimated and provisional, and
are given to provide a common basis for bidding. The basis of payment will be
the actual quantities of work ordered and carried out, as measured by the
Contractor and verified by the Engineer and valued at the rates and prices
tendered in the priced Bill of Quantities, where applicable, and otherwise at such
rates and prices as the Engineer may fix within the terms of the Contract.
3. The rates and prices tendered in the priced Bill of Quantities shall, except in so
far as it is otherwise provided under the Contract, include all constructional
plant, layout, supervision, materials, erection, maintenance, insurance, profit,
taxes and duties, together with all general risks, liabilities and obligations set out
or implied in the Contract.
4. The rates and prices shall be quoted entirely in Indian Currency.
5. A rate or prices shall be entered against each item in the Bill Quantities, whether
quantities are stated or not. The cost of Items against which Contractor has failed
to enter a rate or price shall be deemed to be covered by other rates and prices
entered in the Bill of Quantities (in case of Item rate contract).
6. The whole cost of complying with the provisions of the Contract shall be
included in the items provided in the priced Bill of Quantities, and where no
Items are provided the cost shall be deemed to be distributed among the rates
and prices entered for the related items of Work.
7. General direction and descriptions of work and materials are not necessarily
repeated or summarized in the Bill of Quantities. References to the relevant
sections of the contract documentation shall be made before entering rates or
prices against each item in the Bill of Quantities.
8. The method of completed work of payment shall be in accordance with the
specification for this work. For building works specifications for building are to
9. Errors will be corrected by the Employer for any arithmetic errors pursuant to
Clause 29 of the Instructions to Bidder.
10. Item of excavation in Hard rock is to be operated as per tender item and hard
rock received shall be issued to contractor at the SOR rate Rs. 224.08 per Cum
as per operated quantity. The royalty if any shall be paid by contractor on such
quantity of hard rock to relevant department the stuff of hard rock irrespective
of void or quarry spalls shall be taken by contractor. The excavated hard rock
fully on USR to contractor.
BILL OF QUANTITIES
(A) Percentage Rate Tender (Up to INR 50 Cr.)
Item Description of Item (with brief
No. specification and reference to Rate In
book of specifications) Quantity Unit figures Amount
1 Jungle clearance of specified 1235400.00 Sqmt. 5.90
category and bushes for canal/dam
work as directed with depositing
material etc complete. (Excluding
tree of grith above 0.5 mt) B) More
than 2 year old (c) For Heavy dence
2 Excavation in all sort of strata and 1054420.00 Cum. 126.57
formations incl. depositing the
unuseful excavated stuff as and
where directed incl. sorting and
stacking useful materials in
measurable conditions as directed
upto 1.2 Km lead and all lifts etc.
complete incl. dewatering.
(A) IN OVER BURDEN INCL. HARD
3 Excavation of HARD ROCK by using 410240.00 Cum. 792.12
rock breaker only and without
using any type of explosive and
removal of material by means of
wedging and chiseling including
depositing the excavated stuff as
and where directed with 1.2 Km
lead and all lift including sorting
and stacking of useful materials as
directed etc complete.
(Forty-Six Crores Fifty-Seven Lacs Six Thousand One Hundred Eight Rupees and Twenty
I/We am/are willing to carry out the work at….......................% above/below percent (Should
be written in figures and words) of the estimated rate mentioned above. Amount of my /our
tender works out as under.
Estimated amount put to tender Estimated amount put to tender
Deduct………% below Add………% Above
In words In words
(B) For Item Rate Tender (For Above INR 50 Cr. )
Item Description of Item (with brief Quantity Unit Rate In Amount
No. specification and reference to figures
book of specifications)
(A) Total Tendered Amount
(B) Rebate on above tendered amount (if any) % (in figure) ………………………………
(C)Net Tendered Amount (A-B) (in figure) ………………………………
1 The Contractor shall exhibit a board with detailed specification and details of work as
directed by the Engineer-In-Charge for which no extra payment shall be made.
2 The labour cess will be deducted as per prevailing rules i.e. 1% of the work done.
3 GST and Income tax TDS will be deducted at a source while making payments of bills
4 In all R.C.C. Items in Rate Analys`is Standard Cement Consumption has been taken as
per Govt. G.R.: No. MIS 102010/17/K1, dtd. 30/07/2018 as stated in S.O.R. therefore in
R.C.C. items where there is a change as per actual mix design the cost of difference of
cement consumption have been deducted from the rate of original item at the rate of
input rate mentioned in all the tender.
Signature of Contractor Executive Engineer
Salinity Control Division
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
Bid Security (Bank Gurantee Blank Form).pdf
Tender Notice No. 06 of 2026-27.pdf
SBD Phase-2 Sorthi phase.-2 package-2 sub pkg-2 online upload.pdf
BOQ sorathi ghed phase 2 package 2 sub package 2 46.57 crore.pdf
Corrigendum-1 Sorthi phase-2 pack-2 sub pack-2 (1).pdf
CORRIGENDUM
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .