Loading…
Loading…
Tender Value
Refer Docs
EMD Value
₹9.3 L
Closing Date
2 Nov 2026, 6:00 pm
Chief General Manager (P), Gujarat Water Infrastructure Limited
Comprehensive Operation, Maintenance and Repair of Civil & Electromechanical assets such as Sump, Pump house, Intake Channel, Approach Road, Security Cabin, Staff quarters, Compound Wall, Bulk transmission pipeline, Valves, Pumping machinery & electrical equipment etc. for the Maliya to Bhachau – NC-09 Project, execution of required civil and electro-mechanical scheme strengthening works, including proper supply of water as per demand and maintaining complete and accurate records of all operation and maintenance activities, for a total period of 60 months, Dist.: Kutch.
350865
21/2026
Open
Civil Works - Water Works
Works
Gandhinagar
3 documents required · 3 mandatory
₹12,000
Chief General Manager (P), Gujarat Water Infrastructure Limited
₹9.3 L
1 Oct 2026
1 Oct 2026
1 Oct 2026
2 Nov 2026
1 Oct 2026
Estimated Cost: Rs.
TECHNICAL SPECIFICATION CIVIL
Chief General Manager (Project)
Gujarat Water Infrastructure Limited
1st floor Block – 1, Jivraj Mehta Bhavan, Sector-10 Gandhinagar,
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
Comprehensive Operation, Maintenance and Repair of Civil & Electromechanical
assets such as Sump, Pump house, Intake Channel, Approach Road, Security
Cabin, Staff quarters, Compound Wall, Bulk transmission pipeline, Valves,
Pumping machinery & electrical equipment etc. for the Maliya to Bhachau – NC-09
Project, execution of required civil and electro-mechanical scheme strengthening
works, including proper supply of water as per demand and maintaining complete
and accurate records of all operation and maintenance activities, for a total
period of 60 months, Dist.: Kutch.
TECHNICAL SPECIFICATION
SECTION:2 SURVEY & GEOTECHNICAL INVESTIGATION FOR DESIGN ...................
SECTION – 5 STRUCTURAL STEEL WORK ....................................................
SECTION -6 WATER SUPPLY AND SANITARY WORKS ......................................
SECTION 8 : ITEMWISE SPECIFICATIONS ................................................
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
SECTION: 1 GENERAL AND MATERIAL
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
GENERAL AND MATERIAL
1.0 Employer’s Drawings:
The drawings listed in the Tender document are the Employer’s conceptual drawings
and are to be got approved prior to start of the works with actual site conditions & level
in consultation with EIC.
2.0 Drawing Sheet Format:
All drawings provided by the Contractor shall be on standard size sheets, prepared on
computer with AutoCAD and shall show the following particulars in a title block
located in the lower right hand corner, in addition to the name of Contractor and
equipment manufacturer, date, scale, drawing number, revision number (R0 for
drawings submitted initially, R1, R2, etc. for drawings submitted subsequently) and
Senior Manager ……,GWIL
Project name: -
A blank space of 90 mm x 100 mm shall be provided for the Engineer’s approval stamp
and provision shall be made for details of revisions to be recorded.
All drawings submitted by the Tenderer/Contractor shall use the English language and
SI units. All drawings shall be clearly and fully cross-referenced to the other drawings
3.0 Tender / Contract Drawings:
Drawings submitted by the Tenderer shall show all the essential items of the Plant
offered together with sufficient details to enable the general arrangement of the Plant
to be determined.
The drawings and documents to be provided by the Tenderer / Contractor shall be as
per the schedules of price but shall not be limited to those listed:
4.0 Submissions and Approval of Drawings:
The following shall be the procedure for submission and approval of drawings:
The Contractor shall submit minimum 6 copies of the drawings to the Employer. All the
drawings are to be signed by the Contractor or his authorized representatives.
The Engineer’s Representative will review the drawings and, if found fit for approval,
the Employer will return 2 copies to the Contractor duly approved.
In case the drawings/documents are not fit for approval but worth for review, the
Engineer’s Representative will mark the comments on the drawings and return 2 copies
to the Contractor. In such case, the Contractor shall resubmit the revised drawings
within two weeks as per above and the same shall be repeated till the drawings are
finally approved as per sub-clause above.
If the submitted drawings/documents are not worth for review, the Contractor will be
informed accordingly.
On receipt of the approved drawings as per sub-clause above, the Contractor shall
submit CD/Pen-Drive, Soft Copy and documents to the employer as and when
After tests on completion, the Contractor shall submit, within 15 days of the conclusion
of the tests, CDs/Pen-Drive, Soft Copy, Hard Copy of the “As Built Drawings” to the
When the drawings are received by the Engineer’s Representative after revision by the
Contractor, he will only review the revision made and hence the Contractor shall
carefully identify all the revised details / dimensions and also describe the revisions in
the revision block.
No drawings, with corrections made after taking the prints, will be accepted.
Approval of drawings by the Engineer shall not relieve the Contractor of his
responsibility in terms of the Contract.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
5.0 Delivery, Unloading and Storing at Site:
The Contractor shall be responsible for checking all materials delivered to Site and
shall keep the Engineer’s Representative fully informed of the state of deliveries. The
Contractor shall carry out, at his cost, all instructions of Engineer or his
Representative for proper unloading, preservation, maintenance, storage and security
of materials delivered to Site until he fulfills all his obligations under the Contract.
The Contractor shall erect and maintain on the Site any temporary storage facility as
required and approved by the Engineer.
Multiple handling and movement of materials during storage and retrieval shall be
6.0 Spare Parts:
Spare Parts required after the taking over the Plant shall be filled up by the bidder in
Spares during pre-commissioning trials, commissioning tests/maintenance, guarantee
etc. shall be provided by the Contractor. The necessary spares shall be brought by the
Contractor prior to the pre-commissioning test so as to avoid the downtime of
equipment due to non-availability of them. All these spares have to be provided as
required, by Contractor free of cost.
All spare parts shall be new, unused and strictly interchangeable with the parts for
which they are intended to be replacements and shall be treated and packed for long
storage under the climatic conditions prevailing at the site. Each spare part shall be
clearly marked or labeled on the outside of its packing with its description, number
and purpose. When more than one spare is packed in a single case or other container,
a general description of its contents shall be shown on the outside of such case or
container and a detailed list enclosed. All cases, containers and other packages shall
be marked and numbered in an approved manner for the purpose of identification.
Spares shall be delivered to Site after the completion of erection but before start of
commissioning of Plant along with technical leaflets and details. Spare parts shall be
indicated in the assembly drawing showing clearly the part numbers.
All cases, containers or other packages are liable to be opened for such examination as
the Engineer’s Representative may require and packing shall be designed to facilitate
opening and thereafter re-packing. In the event of some specific spares offered in the
Contract being withdrawn from manufacture owing to changes in design of equipment
or similar reasons viz., model being obsolete etc., the Contractor shall inform the
Employer before such withdrawal so that the Employer can take timely alternative
Tools shall be delivered to site just prior to Tests on Completion.
The specified tools shall not be used for the erection of the Plant being supplied and
except that the Engineer may call upon the Contractor to demonstrate their use or
effectiveness, they must be handed over to the Employer in a completely new and
unused condition. Should the Contractor require any such tools at site for erection, he
shall provide his own.
The test equipment shall include special purpose items essential to the testing or re-
calibration of related items of Facilities.
MATERIALS AND WORKMANSHIP:
1.0 Introduction:
This part of the Specification sets out the general standards of materials to be supplied
and the workmanship required to be ensured by the Contractor. All component parts of
the works shall, unless otherwise specified, comply with the provisions of employer’s
requirement or be subject to the approval of the Employer.
Particular attention shall be paid to a neat, orderly and well-arranged installation carried
out in a methodical competent manner.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
2.0 Reference Specifications and Standards:
Where reference is made in the Specification to a British Standard Specification
(hereinafter abbreviated to `B.S’) issued by the British Standards Institution of 2, Park
street, London W.I., or to an Indian Standard Specification (I.S.) issued by the Bureau of
Indian Standards, (earlier known as Indian Standard Institution), Manak Bhavan,
Bahadur shah Zafar Marg, New Delhi 110 002, or American Society for Testing and
materials (ASTM) issued by ASTM 1916 Race Street, Philadelphia, P.A., 19103, U.S.A. or
American national Standards Institute (ANSI) issued by ANSI 1430, Broadway, New York,
N.Y., 10018, U.S.A. or Japanese Industrial Standards (JIS) issued by Japanese Standards
Association, 4-1-24, Alaska, Minato-Ku, Tokyo 107, Japan or to any other equivalent
Standard it shall be to the latest revision of that Standard on the Tender opening date.
The Contractor may propose at no extra cost to the Employer, the use of any relevant
authoritative internationally recognized Reference Standard.
All details, materials and utensils supplied and workmanship performed shall comply
with the specified Standards. If Tenderer offers equipment to other Standards, the
equipment/material should be equal or superior to those specified and full details of the
difference shall be supplied.
In the event of conflict between this Specification and the Codes for equipment,
provisions of this Specification shall govern. Certain specifications issued by national or
other widely recognized bodies are referred to in this Specification. In referring to the
Standard Specifications the following abbreviations are used:
IS: Indian Standard
ANSI: American National Standards Institute
API: American Petroleum Institute
ASME: American Society of Mechanical Engineers
ASTM: American Society of Testing and Materials
AWS: American Welding Society
AWWA: American Water Works Association
ISO: International Organization for Standardization
DIN: Deutsches Institute fur Normung
BS: British Standard
IEC: International Electro technical Commission
IEE: Institution of Electrical Engineers
IEEE: Institute of Electrical and Electronic Engineers
NEMA: National Electrical Manufacturers Association
AGMA: American Gear Manufacturer’s Association
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
3.0 Materials – General:
All materials incorporated in the Works shall be the most suitable for the duty
concerned and shall be new and of reputed make/approved quality, free from
imperfections and selected for long life and minimum maintenance. Non-destructive
tests, if called for in the specification, shall be carried out. All submerged moving parts
of the Plant, or shafts and spindles or faces etc. in contact with them shall be of
corrosion resistant materials. All parts in direct contact with various chemicals, shall be
completely resistant to corrosion, or abrasion by these chemicals, and shall maintain
their properties without aging due to the passages of time, exposure to light or any
4.0 Workmanship – General:
Workmanship and general finish shall be of first-class quality and in accordance with
best workshop practice.
All similar items of the Plant and their component parts shall be completely
interchangeable. Spare parts shall be manufactured from the same materials as the
originals and shall fit all similar items.
All parts, which can be worn or damaged by dust, shall be totally enclosed in dust
proof housings. All materials incorporated in the Works shall be the most suitable for
the duty concerned, free from imperfections and selected for long life and minimum
maintenance. All necessary accessories required for satisfactory and safe operation of
the Plant shall be supplied by the Contractor unless it is specifically excluded from his
scope. Suitable provision by means of eyebolts or other means are to be provided to
facilitate handling of all items that are too heavy or bulky for lifting and carrying by
Welding shall comply with the latest revision of the BS 5135 Code.
Welders shall be qualified in accordance with the requirement of the appropriate
section of BS 4871. The Engineer shall have the right to call for further qualification
from time to time from any welder who in the opinion of the Engineer does not produce
weld in accordance with the qualification. Each welder shall be assigned a number and
letter. Each welding elements shall clearly be identified as to its welder marking the
welder’s Code adjacent to the welds. A record chart shall be maintained for each
welder showing the procedures, for which he has qualified, the date of such
qualification, the type of defects produced and their frequency. The Engineer shall
disqualify the welder whose Work requires a disproportionate amount of repairs. All
procedures where required shall be qualified as per BS EN 283-3.
Inspection and quality of surveillance shall not be limited to the examination of finished
welds. The techniques employed shall be based on methods which are known to produce
good results and which have been verified at Site by actual demonstration.
Haphazard striking of the electrodes for establishing an arc shall not be permitted. The
arc shall be struck either on the joint or on a starting tag. The starting tag shall be of
the same material or a material compatible with the base metal being welded. In case
of any inadvertent strike on place other than the welding, the area affected shall be
ground flushed and examined by liquid penetration method.
Generally, a stringer bead technique shall be used with a slight oscillation of necessary
to avoid slag and to minimize the number of beads needed to fill exceed 3 times the
wire diameter. Vertical welds shall be made in upward direction. For all pipes above
300 mm dia., welding shall be done whenever possible, by 2 welders working
simultaneously along both sides of the pipe.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
The root pass shall have less than 1.5 mm internal reinforcement. Defects like icicles,
burn through and excessive “such back”, etc. shall be cause for rejection of welds.
Final welds shall be suitable for appropriate fabrication of the non-destructive
examination of the weld. If grinding is necessary, the weld shall be blended into the
parent metal without gouging or thinning of the parent metal in any way. Uneven and
excessive grinding may be a cause for rejection. Fillet weld shall preferably be convex
and free from undercutting and overlap at the toe of weld. Convexity and concavity
shall not exceed 1.5 mm. The leg lengths shall not exceed the specified size by more
All attachments such as lugs, brackets and other non-pressure parts shall also be done
by qualified welders in accordance with the design details and materials specifications.
Temporary attachments shall be removed in a manner that will not damage the parent
metal. Areas of temporary attachments shall be dressed smooth and examined by
ultrasonic or liquid penetration methods.
All tack welds shall be made using qualified procedure and welders, the number of sizes
of tack welds shall be kept as small as to consist of adequate strength and joint
alignments. All tack welds shall be examined visually for defects and if found defective
shall be completely removed. As welding proceeds, tack welds shall be either removed
completely or shall be properly prepared by grinding or filling their starting ends so that
they may be satisfactorily incorporated in the welds. Unacceptable defects shall be
removed by grinding machine or chipping or gouge. Flame gouging may be permitted
provided gouged surfaces are ground at least by 1.0 mm below the deepest indentation.
All weld repairs shall be carried out using the approved welding procedures and
welders. Re-welded areas shall be re-examined by the methods specified for the original
welds and the Engineer’s Representative shall duly qualify repair procedures.
6.0 Pre-heating and Post-Heating Treatment:
Pre-heating and post heating treatment shall conform to the relevant application
Codes. Pre-heating not exceeding 121 deg. C for all carbon steel construction above
mm thickness would be mandatory. Such pre-heating would be maintained during
flame cutting, flame or arc gouging, welding and repairs and may be done by gas
heating by gas torches/gas rings with neutral flame. The temperature shall be checked
by temperature indicating crayons. However, such pre-heating will not be necessary
for welds less than 6 mm size. In large diameter pipe fabricated out of plate materials,
production control test plates in accordance with the BS 4870-part 1 Table 6 to
represent 30% of the long seams and each welder’s performance would be mandatory.
7.0 Electrodes:
All electrodes shall be stored in their original sealed containers under dry conditions.
Electrodes shall remain identified until consumed. All electrodes shall be dried before
use. Drying ovens shall be provided in Work areas for drying purposes. Electrodes
withdrawn from oven shall be promptly used and excess unused electrodes shall be
promptly returned to oven.
8.0 Examination/NDT/Radiography
The various stages of examination and types shall be as stipulated in the respective
fabrication Codes. Radiographic examination shall be carried out as per provisions of
BS 2600 or BS 2910; Ultrasonic tests where called for shall be carried out as per
provisions of BS 3926; magnetic particle tests shall be carried out as per BS
Liquid penetration tests shall be carried out as per BS
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
9.0 Stainless Steel Welding:
All welding consumable such as electrodes, filler weirs, argon gas for shielding and
purging shall be of high quality and the proposed brand shall be furnished for approval
of the Engineer. Weld deposits shall have similar or higher physical properties and
similar chemical composition to the members joined.
All electrodes shall be purchased in sealed containers only and stored in their packing
intact. The packets opened shall be consumed as early as possible. The electrodes
removed from the containers shall be kept in holding ovens at temperatures
recommended by electrode manufacturer. Special care shall be taken in avoiding
mixing of electrodes in the oven. The electrodes and filling wires shall be free from
rust, oil, grease, earth and other foreign matter.
Argon gas with purity 99.5% shall be used for shielding and purging. The purity of gas
shall be certified by the gas manufacturers.
Non-destructive examination of the welds shall be carried out to ensure quality of
The electric current for welding shall be direct current, straight polarity (electrode
negative). The welding current shall be kept minimum possible to ensure minimum
heat affected zone in the parent material. Other side of the weld joint shall be
periodically flushed with argon gas.
Cast iron shall be of standard grey close-grained quality. The structure of the castings
shall be homogeneous and free from non-metallic inclusions and other injurious
defects. All surfaces of castings, which are not machined, shall be smooth and shall be
carefully fettled to remove all foundry irregularities.
Minor defects in depth not exceeding 12.5 percent of total metal thickness and which
will not ultimately affect the strength and serviceability of the casting may be
repaired by approved welding techniques. The Engineer shall be notified of large
defects and no repair welding of such defects shall be carried out without prior
approval of the Engineer. If the removal of metal for repair should reduce the stress
resisting cross section of the casting by more than 25 percent, or to such an extent
that the computed stress in the remaining metal exceeds the allowable stress by more
than 25 percent, then casting shall be rejected. Test coupons cast simultaneously with
the main castings shall be identified to check physical, chemical analysis of casting.
Major defects on casting are not acceptable. Castings repaired by welding for minor
defects shall be stress-relieved after such welding. Non-destructive tests as directed
by the Engineer will be required for any casting containing defects whose extent
cannot otherwise be judged, or to determine where repair welds have been properly
All major stress-bearing forging shall be made to a Standard Specification. Forging
shall be subjected to magnetic particle testing or dye penetration test at the areas of
fillets and change in section. The testing shall be conducted after rough machining (10
microns). Any defect, which will not machine out during the final machining, will be
gouged out fully, inspected by dye penetration or magnetic particle inspection to
ensure that the defect is fully removed and repaired using an approved repair
procedure. Any indication, which proves to penetrate deeper than 2.5% of the finished
thickness of the component, shall be reported to the Engineer giving the details like
location, length, width and depth. For the magnetic particle inspection, the choice of
wet or dry particles shall be at the Contractor’s discretion.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
All forging shall be demagnetized after test and shall be heat-treated for the relief of
residual stresses.
12.0 Design Life:
The Works as a whole shall be new, of sound workmanship, robustly designed for a
long reliable operating life and shall be capable of 24 hours per day continuous
operation for prolonged period in the climatic and working conditions prevailing at the
site, and with the minimum of maintenance. Particular attention shall be given to
temperature changes, the stability of paint finish for high temperatures, the rating of
engines, electrical machinery, thermal overload services, cooling systems and the
choice of lubricants for possible high and prolonged operating temperatures. The
Contractor shall be called upon to demonstrate this for any component part either by
service records, or evidence of similar equipment already installed elsewhere or
relevant type tests. Routine maintenance and repair shall as far as possible not
requires the services of highly skilled personnel.
The Plant shall be designed to provide easy access to and replacement of component
parts, which are subject to wear, without the need to replace whole units. No parts in
contact with water shall have a life from new to replacement or repair of less than
Design features shall include the protection of Plant against damage caused by vermin,
dirt, dust and dampness and to reduce risk of fire. Plant shall operate without undue
vibration, and parts shall be designed to withstand the maximum stresses under the
most severe condition of normal service. Materials shall have a high resistance to
change in their properties due to the passage of time, exposure to light, temperature
and any other cause, which may have a detrimental effect upon the performance or
life of the Works.
Plant located outside lockable areas/building shall have additional features to prevent
un-authorized operation.
Design shall be carried out as per following:
RCC footings: Limit state method of design
RCC columns: Limit state method of design
RCC beams and slabs: Limit state method of design
Retaining wall: Limit state method of design with limiting crack width of 0.2mm as per
Also provide the seismic design calculation of RCC Water retaining structures as per
IS:1893 (Part – II, Draft Code).
Steel Structures: Limit state/Working Stress method of design.
RCC water retaining structure shall be designed as per Working Stress Method as per IS :
Seismic Zone for Civil Structures as per IS 1893 :
RCC structures shall be designed as per IS 456 and reinforcement details shall be done as
per IS : 13920 (Ductile detailing).
Foundation shall be designed to carry all the loads from equipment or super structure,
which they support in accordance with the relevant codes.
Net safe bearing capacity of soil & Ground water table: As per geo-technical report
Type of foundation.
For buildings and structures: As per geo-technical report
Allowable increase in soil bearing capacity in event of storm(wind) 25%, Earthquake
25%,factor of safety as per IS 1904 against overturning 1.5, Sliding 1.5, and buoyancy
As a general rule following features will be adopted, unless decided otherwise in a
specific or exceptional case:
Top of footing will be horizontal and flat/Trapezoidal as case.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
Minimum depth of foundation is considered as per latest geotechnical report for
locations of the proposed structure.
Foundation plinth for structural columns and equipment supports shall extend not less
than 5 mm from the edge of base plate.
The clear distance between a standard mild-steel anchor bolt or anchor sleeve and the
face of the foundation shall be not less than 75 mm.
Minimum thickness of lean concrete layer shall be 100 mm for building and 150 mm for
retaining structure, also extend 75 mm beyond the foundation edge.
For heavier loads and restricted settlements pile foundation may be considered as an
alternative as per IS
Wherever columns are very near pedestals of footing are considered combined to take
unbalance loading. Sufficient reinforcement is provided to take care of unbalancing
Centre of footing and combined loading is match to nullify eccentricity in load.
Where stresses due to wind (or seismic) and temperature are combined with those due
to other loads, the allowable stresses in concrete and reinforcement steel shall be
increased by 33.33% in case of working stress design. However steels having definite
yield stress, stress limited to yield stress, for steels without definite yield point, the
stress will be limited to 80 percentage of ultimate strength or 0.2 percent proof stress
whichever is smaller.
All building shall have a minimum 1.0 m wide, 100 mm thick plinth protection paving
grade concrete or stone slabs/tiles. All plinth protection shall be supported on well
compacted strata.
HFL of nearby dam & NGL shall be checked before finalizing the uplift pressure.
Contractor shall take HFL data from concerned authority & FGL shall be considered as
1.0 mt. above HFL.
If the compound wall is in contact with HFL/ FSL/ permanent water logged area than
RCC compound wall shall be designed as Retaining wall.
All underground or partly underground liquid containing structures shall be designed
for the following conditions:
Liquid depth to be considered up to full height of wall and no relief due to soil pressure
from the other side to be considered.
i. RCC water retaining structures like storage tanks shall be leak proof and designed by
working stress method. (Stress in steel limited to 130 N/mm2) or limit state method
with limiting crack width 0.1 mm.
ii. Structure empty condition (i.e., empty of liquid, any material, etc.) : full earth
with saturation and surcharge pressure wherever applicable, to be considered.
iii. Partition wall between dry sump and wet sump: to be designed for full liquid depth
full height of wall.
iv. Partition wall between two compartments: to be designed as one compartment
and the other full for both the directions.
v. Structures shall be designed for uplift in empty conditions with no live load with the
water table as per Geotechnical report or high flood level or rock level, whichever is
maximum. If uplift pressure is more than 2000 Kg/m2, use of pressure relief valves to
reduce uplift pressure due to ground water table shall be allowed. In this case
minimum thickness of raft shall with provision of under drainage arrangement (as per IS
4558) be kept as per below para viii.
vi. Walls shall be designed under operating conditions to resist earthquake forces from
earth pressure mobilization and dynamic water loads.
vii. Underground or partially underground structures shall also be checked against
stresses developed due to any combination of full and empty compartments with
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
appropriate ground/uplift pressures from below to base slab. A minimum factor of
shall be ensured against uplift or floatation and due to other loads shall be 1.5.
The minimum clear cover to reinforcement in all R.C.C structures shall be as per IS:
456/IS: 3370 (Part –II), except as mentioned for following:
1. The following minimum clear cover shall be provided for RCC (non-Water retaining)
2. Face in contact with earth 50 mm
3. Free face 50 mm
id retaining structures
4. Face in contact with liquid 50 mm
5. Away from liquid but in contact with earth 50 mm
6. Sides and top 50 mm
7. Bottom 60 mm
13.0 Name Plate:
Each item of the Plant shall have permanently attached to it in a conspicuous position,
a nameplate and rating plate. Upon these shall be engraved or stamped, the
manufacturer’s name, type and serial number of Plant, details of the loading and duty
at which the item of Plant has been designed to operate, and such diagrams as may be
required by the Engineer. All indicating and operating devices shall have securely
attached to them or marked upon them designations as to their function and proper
Nameplates, rating plates and labels shall be of a non-flame propagating material,
either non-hygroscopic or transparent plastic with engraved lettering of a contrasting
colour. Fixing shall be by means of non-corrosive screws; drive rivets or adhesives shall
Warning labels shall be provided where necessary to warn of dangerous circumstances
or substances. Inscriptions or graphic symbols shall be black on a yellow background
circumstances or substances. Inscriptions or graphic symbols shall be black on a yellow
Instruction labels shall be provided where safety procedures such as wearing of
protective clothing are essential to protect personnel from hazardous or potentially
hazardous conditions. These labels shall have inscriptions or graphic symbols in white
on a blue background.
14.0 Nuts, Bolts, Studs and Washers:
Nuts, bolts, studs and washers for incorporation in the Plant shall conform to the
requirements of the appropriate standard. Nuts and bolts shall be of the best quality
of specified grade, machined on the shank and under the head and nut.
Fitted bolts shall be a light driving fit in the reamed holes they occupy, shall have the
screwed portion of such a diameter that it will not be damaged in driving and shall be
marked in a conspicuous position to ensure correct assembly at Site.
Washers, locking devices and anti-vibration arrangements shall be provided where
necessary Jointing hardware for the entire Plant shall be provided with sufficient
spares to cater for site losses.
Where bolts pass through structural members taper washers shall be fitted, where
necessary, to ensure that no bending stress is caused in the bolt. Where there is a risk
of corrosion, bolts, nuts and studs shall be designed so that the maximum stress does
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
not exceed half the yield stress of the material under any conditions. All bolts, nuts
and washers that are subject to frequent adjustment or removal in the course of
maintenance and repair shall be made of nickel-bearing stainless steel.
The Contractor shall supply all holding down, alignment and leveling bolts complete
with anchorages, nuts, washers and packing required to attach the Plant to its
foundations, and all bed plates, frames and other structural parts necessary to spread
the loads transmitted by the Plant to concrete foundations without exceeding the
design stresses.
15.0 Allowances for Wastage:
The Contractor shall supply reasonable excess quantities to cover wastage of those
consumable, which will be normally subject to waste during erection, commissioning
and setting to Work.
16.0 Painting – General:
The Contractor shall be responsible for the cleaning, preparation for painting, and
priming or otherwise protecting, as specified, all parts of the Plant at the place of
manufacture prior to packing.
Parts may be cleaned but surface defects may not be filled in before testing at the
manufacturer’s works. Parts subject to hydraulic test shall be tested before any
surface treatment. After test, all surfaces shall be thoroughly cleaned and dried out, if
necessary by washing with an approved de-watering fluid prior to surface treatment.
Except where the specification provides to the contrary all painting materials shall be
applied in strict accordance with the paint manufacturer’s instructions.
All protective coatings shall be suitable for use in warm humid climates. All primers,
under coats and finishes shall be applied by brush or airless spray, except where
otherwise specified. Consecutive coats shall be in distinct but appropriate shades. All
paints shall be supplied from the store to the painters, ready for application, and
addition of thinners or any other material shall be prohibited.
17.0 Painting at Place of Manufacture:
Steel and cast-iron parts shall be sand blasted to near white cleaning before painting.
Edges, sharp covers etc. shall be ground to a curve before sand blasting. A primer coat
of a zinc rich epoxy resin-based coating with at least 75 microns’ dry film thickness is
to be provided. In addition, the parts are to be provided with adequate number of
coats of coal tar epoxy polyamine coating to a dry film thickness of 175 microns
including primer coating.
18.0 Painting at Site:
Immediately on arrival at the site, all items of Plant shall be examined for damage to
the paint coat applied at the manufacturer’s works, and any damaged portions shall be
cleaned down to the bare metal, all rust removed, and the paint coat made good with
After erection, such items, which are not finish painted, shall be done so and, items
that have been finish painted at the manufacturer’s works shall be touched up for any
damaged paintwork. For finish painting, two coats of synthetic enamel conforming to
IS: 2932 shall be applied. Dry film thickness of each coat shall be at least 25 microns.
The dry paint film thickness shall be measured by Electrometer or other instruments
approved by the Employer. In order to obtain the dry film thickness specified the
Contractor should ensure that the coverage rate given by the paint manufacturer
would enable this thickness to be obtained. Strength of adhesion shall be measured
with an adhesion tester and this value shall not be less than 10 kg/cm2. Painted
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
fabricated steel work which is to be stored prior to erection shall be kept clear of the
ground and shall be laid out or stacked in an orderly manner that will ensure that no
water or dirt can accumulate on the surface. Suitable packing shall be laid between
the stacked materials. Where cover is provided, it shall be ventilated.
19.0 Galvanizing:
Wherever galvanizing has been specified the hot dip process shall be used. The
galvanized coating shall be of uniform thickness. Weight of zinc coatings for various
applications shall not be less than those indicated below:
a) Fabricated steel :
Thickness less than 2 mm but not less than 1.2 mm - 340 gms/sq.m
Thickness 2 mm and above - 460 gms/sq.m
Up to nominal size M10 - 270 gms/sq.m
Over M10 - 300 gms/sq.m
Galvanizing shall be carried out after all drilling; punching, cutting, bending and
welding operations have been carried out. Burrs shall be removed before galvanizing.
Any Site modification of galvanized parts should be covered well by zinc rich primer
and aluminum paint.
20.0 Support for Pipe work & Valves:
All necessary supports, saddles, sling, fixing bolts & foundation bolts shall be supplied
to support the pipe work. Valve and other facilities mounted in the pipe work shall be
supported independent of the pipes to which they connect.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
INSPECTION AND TESTING AT MANUFACTURER’S PREMISES
1.0 Inspection and Tests:
1.1.1 During testing there shall be no visible evidence of structural damage to any of the
valve component.
1.1.2 Motorized valves shall be tested with their actuators, with a differential head
equivalent to their maximum working pressure, to prove that the actuators are
capable of opening and closing the valves under maximum unbalanced head condition
within the specified opening or closing period.
1.1.3 The following test shall be carried out for sluice valves:
a) Seat leakage test at rated pressure
b) Hydrostatic test at 1.5 times the rated pressure
c) Valve operation
1.1.4 The following test shall be carried out for non-return valves:
a) Seat leakage test at rated pressure
b) Body hydrostatic test at 1.5 times rated pressure
1.2.1 Testing of pipes and fitting shall be carried out in accordance with relevant Indian
Standard and internationally approved standard. Pipes, fittings and expansion
bellows shall be hydrostatically tested for 1.5 times the rated pressure.
1.4 Equipment/material for testing:
Equipment required for testing of all construction materials such as sieve analysis,
cone for slump, concrete cubes casting and testing machine shall be available on
site. All construction materials like sand, cement, aggregate etc. have to be tested
on site in representative of engineer in-charge.
Testing of steel bars are to be installed at site or shall be tested in
Government/NABL approved laboratory or as directed by engineer in-charge.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
SECTION:2 SURVEY & GEOTECHNICAL INVESTIGATION FOR
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
Specifications for Minimum Investigations required for Project:
1.0 Survey and Soil Exploration:
To plan out and obtain pre-approval and subsequently carry out Topographic and level
Survey, preparing cross sections, Longitudinal sections, Soil exploration to obtain
foundation design data at various locations for all the components listed in preamble on
previous page, complete all as per general pre-approved plan and as per detailed
description and specifications and including submitting survey, soil exploration and
analysis reports in six copies along with two soft copies and getting the same approved
by the engineer in charge.
Work consists of providing all equipment, materials, labour etc. to carry out survey, to
provide permanent markers of various points for later use, to create permanent bench
mark of approved design and approved location on the site, to carry out soil exploration
to obtain information for foundation design as well as collecting data to determine
various design parameters, to collect all data, prepare interim and final reports for
submission and approval of the Engineer in-charge, all as per detailed description,
specifications and as directed by the Engineer in-charge.
It must be clearly understood that the data furnished with the tender and suggested
procedure for survey and soil exploration are purely for general guidance of the bidders
for selecting the best design criteria. The contractor is expected to carry out additional
work if it becomes necessary in the process of selecting appropriate criteria. In any case
responsibility of assuring the guaranteed water supply will fully rests with him.
2.0 Work Description:
Work under this item involves survey, soil exploration and investigation as described
below. Survey maps and all interim as well as final reports of soil investigation, other
tests as well as the reporting of final tests shall be submitted in six paper copies as well
as two soft copies and these will form part of a permanent record of the project for use
during construction, operation, and maintenance stages as well as for future use. All
below mentioned work shall be all inclusive and will be carried out as per detailed
specifications and as directed by the Engineer in-charge.
Survey and soil investigation shall be completed within one & half month. In case after
delay of 15 calendar days the department will get completed the work from
departmental agency at the risk and cost of the contractor which shall be binding to the
3.0 Survey work shall consist of the following:
To carry out Block level survey based on GTS benchmark, prepare longitudinal section
along alignment of all types of pipeline and prepare contour survey of the allotted plot
of land and the river bed of the width of 100m – 50m on either side - of the suggested
center line of the alignment, and prepare contour maps to a scale of 1:500 or larger.
Survey in the river may be carried out with help of sounding technique or long metallic
rod inserted in water from the boat. All the levels/ distance may be measured with help
of total station or DGPS.
Selecting most appropriate location (on the basis of survey) to determine various
geotechnical parameters for carrying out design of various components shall be
responsibility of the contractors and it shall be carried out by laboratory approved by
GOG acceptable to GWIL.
Above survey shall be carried out in stages as and when required, using the latest
equipment like TOTAL STATION or DGPS with high accuracy. In case dumpy level/ auto
level is used, then fly back as well as closing error must be performed without which
survey will be considered as NOT completed. All levels will be based on GTS, and the
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
work shall include transferring level from a reliable established GTS benchmark in the
vicinity of the site of work and establishing a permanent bench mark on site at a
suitable location as per approved design and location. Above survey will be carried out
jointly with the representative of the owner, as per his convenience during day time.
Detailed Longitudinal Section for each pipe shall be prepared and HGL marked on it for
approval of GWSSB. After marking of such data only, execution of pipeline shall be
Detailed contour plan of the headwork/ sub headwork etc. prepared with interval of
m so as to determine position of various units.
Soil exploration work for intake, RCC and framed structures, underground sumps, Pump
Houses (positive/ negative suction) shall consist of the following:
150 mm bores or more diameters (Minimum one no per unit/ structure) will be made to
collect information for the foundation design of the intake well, approach bridge
supports, underground sump, Pump House, other structures. Minimum depth of bores
from the existing level at the location of proposed sump 12 m depth, and pump house
m depth, or more as per requirement of structural design. Disturbed and undisturbed
soil samples will be collected, and grain size analysis by dry sieving/Wet analysis,
determination of liquid/plastic limit and other necessary tests like C value, N value, Ø
value and important parameters to carry out structural design and facilitate execution
of structures shall be carried out. All levels including ground level of the bore point,
levels of various strata and water levels etc. will be noted in reference to GTS.
4.0 Specification for drilling, investigation, furnishing details of bore logs, laboratory testing
The investigation bores shall be made by percussion method and not by rotary method.
No bentonite slurry or drilling mud shall be used. The bores shall be cased when it is to
be done in sandy and silty strata.
The quantity of boring mentioned in work description is approximate and likely to vary
materially if investigating alternative location of Infiltration Well becomes necessary.
Any change in the quantity of boring work shall not entitle the contractor for any claim
or compensation. His rates shall be deemed to cover such an eventuality.
The disturbed samples shall be collected at every 1.5 Mt. Depth or at the points where
the strata changes whichever is less.
The samples so collected shall be preserved in systematic manner in core boxes, when
the bore is in progress. After the bore is completed, each of the samples shall be
packed in two separate poly thin bags with contents of approx. 0.5 Kg and properly
numbered giving other details so as to identify the position to which the samples
represent. All other details such as the bores Sr. Nos., the depth from which the
samples are taken etc. should be clearly given with the samples.
Out of the two sets of samples collected for every bore one set of samples with all
requisite details shall be sent to the laboratory for testing and the second set of
samples together with requisite details shall be supplied to the clients in their office for
record. The casing pipes shall be removed after above compliance and with the
approval of the Engineer in-charge. The recovered samples shall be tested in the
laboratory for grain size analysis and Atterberg’s limits to identify the samples in
accordance with the provision in IS.1498, 1971. The testing of samples shall have to be
done at the recognized laboratory approved by the engineer-in charge.
The drilling shall be terminated at approx. 2.0 Mts. below the impervious (e.g. clay)
strata, when bores are being made primarily to find the level of impervious strata. And
if the samples collected indicate the soil being predominantly clayey further drilling
shall be discontinued. In sandy strata including sand with gravels and small size
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
boulders, Bores shall be extended at least up to 15 Mts. below bed level or low water
level whichever is lower, however if required by Client /Consultants, the bores may
have to be carried further.
Where bores are required to be done in water channel in river/ nallah bed, necessary
island/islands shall be prepared in sand or sand filled gunny bags. The cost of which
shall be covered within the rates quoted.
The rates quoted shall be inclusive for drilling in all kinds of strata including boulders,
soft or hard rock.
For every bore water level encountered shall be recorded together with variation in
water level if during the period of boring.
All levels shall be with reference to the GTS Bench Hark. For this purpose, a pucca GTS
Bench mark shall be established in the region of proposed survey and investigation area.
The readings are to be recorded and observations are to be submitted with the reports
in the format as per prosoma 1 and 2 shown below. The Contractor shall prepare bore
charts for each and every bore in the approved manner and Performa as required by
The disturbed samples are to be analyzed as per relevant clause of I.S. 2720 Part I to IV.
The water samples of water pumped out during pump test shall be collected and
analyzed covering requirements of I.S. 10500 to establish its portability and the results
of the chemical and other tests submitted in the format shown in Performa
A Technical report covering the observations and tests is to be submitted to the client
with the contractor’s recommendations for selecting the most suitable site for the
Radial well which could give the desired yield. The site for location of the pumping test
shall be finalized in consultation with the clients before the work of pumping test
including necessary boring work for the same is taken up.
5.0 Specification for preparing and submitting the full technical report:
The survey work shall be carried out with proper accuracy and permanent Bench Marks
shall be established at points which are approved by the Engineer in-charge. Also,
sufficient number of permanent identification marks shall be established on the bank to
enable establishment of base lines and the survey map to be included in the report shall
contain sufficient details with respect to these permanent marks to enable the
contractor to relocate the soil investigation bores as well as pump well and piezometric
bores positions.
Based on the soil investigation carried out, a contour map of the area investigated
showing the soil strata shall be prepared and included in the technical report.
The soil investigation work shall be carried out as per specifications and information
will be recorded in the format given in attached Performa 1 and
The short chemical analysis of water samples shall be carried out as per I.S. 10500 and
results reported in format given in attached Performa
The Performa included in the tender are only for guidance and by no means are they to
be considered as the only ones required for reporting the investigation. Additional
information which is considered necessary shall be collected and recorded
systematically in proper format to arrive at the relevant conclusions.
Using these parameters discharge shall be calculated for different water levels of the
river, and the report shall make definite recommendations as regards to the number of
radials, their levels, and their lengths required to obtain the desired yield.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
Bore hole no. Date of start Date of comp. GTS value Revision no.
Penetration test
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
Bore Date of Date of Termination depth Revision no.
hole no. start comp.
Depth of Grain size analysis
% Gravel % sand Hydrometer LL% PL% PI%
PERFORMA 3: CHEMICAL ANALYSIS OF WATER
Date of arrival Location Village:
Sr. Characteristics Permissible value as per IS
Desirable Relaxation in absence Analytical value
of alternate source
4 Dissolved solids
6 Total hardness as CaCO3
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
SECTION:3 CONCRETE
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
SECTION -3: CONCRETE
1.0 Applicable Codes with latest revisions.
IS.269 Specification for 33 grade ordinary Portland cement.
IS.455 Specification for Portland slag cement.
IS.1489 Specification for Portland- Pozzolana cement (Part 1&2).
IS:8112 Specification for 43 grade ordinary Portland cement.
IS:12269 Specification for 53 grade ordinary Portland cement.
IS:12330 Specification for sulphate resisting Portland cement.
IS:383 Specification for coarse and fine aggregates from natural sources for
IS:432 Specification for mild steel and medium (tensile steel bars and hard-drawn
steel) wires for concrete reinforcement. (Part 1 and 2)
IS:1786 Specification for high strength deformed steel bars and wires for Concrete
IS:1566 Specification for hard-drawn steel wire fabric for concrete Reinforcement.
IS:9103 Specification for admixtures for concrete.
IS:2645 Specification for integral cement water- proofing compounds.
IS:4990 Specification for plywood for concrete shuttering work.
2.0 Material Testing:
IS.4031 Methods of physical tests for hydraulic cement (Parts 1 to 15)
IS:4032 Method chemical analysis of hydraulic cement.
IS:650 Specification for standard sand for testing of cement.
IS:2430 Methods for sampling of aggregates for concrete.
IS: 2386 Methods of test for aggregates for concrete (Parts 1 to 8)
IS:3025 Methods of sampling and test (physical and chemical) for water used in industry.
IS:6925 Methods of test for determination of water-soluble chlorides in Concrete
3.0 Material Storage:
IS:4082 Recommendations on stacking and storing of construction Materials at site.
4.0 Concrete Mix Design:
IS:10262 Recommended guidelines for concrete mix design.
SP:23 (S&T) Handbook on Concrete Mixes
5.0 Concrete Testing:
IS.1199 Method of sampling and analysis of concrete.
IS:516 Method of test for strength of concrete.
IS:9013 Method of making, curing and determining compressive strength of accelerated
cured concrete test specimens.
IS:8142 Method of test for determining setting time of concrete by Penetration
IS:9284 Method of test for abrasion resistance of concrete.
IS:2770 Methods of testing bond in reinforced concrete.
IS:1791 Specification for batch type concrete mixers.
IS:2438 Specification for roller pan mixer.
IS:4925 Specification for concrete batching and mixing plant.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
IS:5892 Specification for concrete transit mixer and agitator.
IS:7242 Specification for concrete spreaders.
IS:2505 General Requirements for concrete vibrators: Immersion type.
IS:2506 General Requirements for screed board concrete vibrators.
IS:2514 Specification for concrete vibrating tables.
IS:3366 Specification for pan vibrators.
IS:4656 Specification for form vibrators for concrete.
IS:11993 Code of practice for use of screed board concrete vibrators.
IS:7251 Specification for concrete finishers.
IS:2722 Specification for portable swing weigh batchers for concrete (Single and double
IS:2750 Specification for steel scaffoldings.
7.0 Codes of Practice:
IS:456 Code of practice for plain and reinforced concrete.
IS:457 Code of practice for general construction of plain and reinforced Concrete for
dams and other massive structures.
IS:3370 Code of practice for concrete structure for storage of liquids (Part 1 to 4).
IS:3935 Code of practice for composite construction.
IS:2204 Code of practice for construction of reinforced concrete shell roof.
IS:2210 Criteria for the design of reinforced concrete shell structures and Folded Plates.
IS:2502 Code of practice for bending and fixing of bars for concrete Reinforcement.
IS:5525 Recommendation for detailing of reinforcement in reinforced Concrete works.
IS:2751 Code of practice for welding of mild steel plain and deformed bars used for
reinforced concrete construction.
IS:9417 Specification for welding cold worked bars for reinforced concrete construction.
IS:3558 Code of practice for use of immersion vibrators for consolidating concrete.
IS:3414 Code of practice for design and installation of joints in buildings.
IS:4326 Code of practice for earthquake resistant design and construction of building.
IS:4014 Code of practice for steel tubular scaffolding (Parts 1 & 2)
IS:2571 Code of practice for laying in situ cement concrete flooring.
IS:7861 Code of practice for extreme weather concreting: Part 1 Recommended practice
for hot weather concreting.
8.0 Construction Safety:
IS: 3696 Safety code for scaffolds and ladders.
IS:7969 Safety code for handling and storage of building materials.
IS:8989 Safety code for erection of concrete framed structures.
The Engineer in charge shall have the right at all times to inspect all operations
including the sources of materials, procurement, layout and storage of materials, the
concrete batching and mixing equipment and the quality control system. Such an
inspection shall be arranged and the Engineer in charge’s approval obtained, prior to
starting of concrete work. This shall however, not relieve the Contractor from any of his
responsibilities. All materials which do not conform to the Specifications shall be
Materials should be selected so that they can satisfy the design requirements of
strength, serviceability, safety, durability and finish with due regards to the functional
requirements and the environmental conditions to which the structure will be
subjected. Materials complying with codes/standards shall generally be used. Other
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
materials may be used after approval of the Engineer in charge and after establishing
their performance suitability based on previous data, experience or tests.
10.0 Materials:
Unless otherwise called for by the Engineer in charge, cement shall be ordinary Portland
cement/Sulphate resistant cement (As per instruction of engineer in-charge) conforming
to IS: 12269. However, in any case, cement grade shall not be lower than 53 grades.
Fresh quality cement shall be procured only from approved manufacturer /Supplier and
shall be subject to prior approval of the Engineer-in-charge.
All cement used for the work shall ordinary Portland cement of 53 grade only. Ordinary
Portland Cement shall comply with the requirements of the latest version of IS:
Only one type of cement shall be used in a particular unit. The source of supply, type or
brand of cement within the same structure or portion thereof shall not be changed
without approval from the Engineer in charge.
Cement which is not used within 90 days from its date of manufacture shall be tested at
a laboratory approved by the Engineer in charge and until the results of such tests are
found satisfactory, it shall not be used in any work.
The white cement shall conform to I.S. 8042-1978.
Aggregates (General):
Aggregates shall consist of naturally occurring stones (crushed or uncrushed), gravel and
sand. They shall be chemically inert, strong, hard, clean, durable against weathering, of
limited porosity, free from dust/silt/ organic impurities/deleterious materials and
conform to IS:383. Aggregates such as slag, crushed over burnt bricks, bloated clay ash,
sintered fly ash and tiles shall not be used.
Aggregates shall be washed and screened before use where necessary or if directed by
the Engineer in charge.
Aggregates containing reactive materials shall be used only after tests conclusively
prove that there will be no adverse effect on strength, durability and finish, including
long term effects, on the concrete.
The fineness modulus of sand shall neither be less than 2.2 nor more than 3.2.
The maximum size of coarse aggregate shall be as stated on the drawings but in no case
greater than 1/4 of the minimum thickness of the member.
Plums 160 mm and above of a reasonable size may be used in mass concrete where
directed. Plums shall not constitute more than 20% by volume of the concrete.
Grit shall be consist of machined crushed stone and shall be hard, strong, tough, dense,
durable, clean, of proper gradation and free from skin or coating likely to prevent
proper adhesion of mortar. Grit shall generally be cubical in shape and as far as possible
flaky elongated pieces shall be avoided. It shall generally comply with the provisions of
I.S. 383-2016. Grit shall be obtained from the best black trap. The grit shall have no
deleterious reaction with cement.
The grit shall conform to the following gradation as per sieve analysis:
I.S. Sieve % by weight passing I.S. Sieve % by weight passing
Designation sieve Designation sieve
Sand shall consist of natural sand, crushed stone sand or crushed gravel sand or
combination of any of these. The sand shall be clean, well graded, strong, durable and
gritty particles free from injurious amounts of dust, clay, kankar nodules, soft or flaky
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
particles, shale, alkali, salts, organic matter, loam, mica or other deleterious substances
and shall be got approved from the Engineer-in-charge. The sand shall not contain more
than 3% of silt as determined by field tests. If necessary the sand shall be washed to
FM of sand used for different work:
Sr. No. Type of Work IS Code FM Range
1 For Cement concrete IS 383 zone-I & II 2.11 to
2 For Masonry IS 2116, Table:1 1.15 to
3 For plaster IS 1542 1.20 to
4 For sand bedding below pipe IS 383 zone-I & II 2.11 to
Water to be used for both mixing and curing shall conform to IS:456. Potable water is
generally satisfactory. Water containing any excess of acid, alkali, sugar or salt shall not
Water shall not be salty or brackish and shall be clean, reasonably clear and free from
objectionable quantities of silt and traces of oil and injurious alkalis, salts, organic
matter and other deleterious material, which will either weaken the mortar or concrete
or cause efflorescence or attack the steel in R.C.C. Container for transport, storage and
handling of water shall be clean.
Water for curing mortar, concrete or masonry should not be too acidic or too alkaline. It
shall be free of elements, which significantly affect the hydration reaction or otherwise
interfere with the hardening of mortar or concrete during curing or those which produce
objectionable stains or other unsightly deposits on concrete or mortar surfaces.
Hard and bitter water shall not be used for curing.
Potable water shall generally be found suitable for curing mortar or concrete.
Permissible Limit for Solids
Tested as per Permissible Limit Max.
Organic IS: 456 200 mg/lit
Inorganic IS: 456 3000 mg/lit
Sulphate (as SO3) IS: 456 400 mg/lit
Chlorides (as CI) IS: 456 2000 mg/lit for PCC and
500 mg/lit for RCC
Suspended Matter IS: 456 2000 mg/lit
All reinforcement steel shall be CRS-FE-500 steel conforming to relevant I.S. for all RCC
structure with conforming to IS-1786.
All reinforcement shall be clean, free from pitting, oil, grease, paint, loose mill scales,
rust, dirt, dust, or any other substance that will destroy or reduce bond.
All Grade of reinforcement steel shall be as per Price bid & Data-sheet.
Accelerating, retarding, water-reducing and air entraining admixtures shall conform to
IS: 9103 and integral water proofing admixtures to IS:
Admixtures may be used in concrete as per manufacturer's instructions only with the
approval of the Engineer in charge. An admixture's suitability and effectiveness shall be
verified by trial mixes with the other materials used in the works. If two or more
admixtures are to be used simultaneously in the same concrete mix, their interaction
shall be checked and trial mixes done to ensure their compatibility. There should also
be no increase in risk of corrosion of the reinforcement or other embedment.
Calcium chloride shall not be used for accelerating set of the cement for any concrete
containing reinforcement or embedded steel parts. When calcium chloride is permitted
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
such as in mass concrete works, it shall be dissolved in water and added to the mixing
water by an amount not exceeding 1.5 percent of the weight of the cement in each
batch of concrete. The designed concrete mix shall be corrected accordingly.
Wastage allowance for cement and steel shall be considered in the item rate and no
extra payment shall be paid to the Contractor on any account.
Samples and Tests:
All materials used for the works shall be tested before use.
Manufacturer's test certificate shall be furnished for each batch of cement/steel and
when directed by the Engineer in charge samples shall also be got tested by the
Contractor in a laboratory approved by the Engineer in charge at no extra cost. Engineer
in charge may appoint separate third-party inspection for the material testing to ensure
the quality of the work. The Contractor shall replace the defective material as an
outcome of these tests.
Sampling and testing shall be as per IS:2386 under the supervision of the Engineer in
Water to be used shall be tested to comply with requirements of IS:456.
The Contractor shall furnish manufacturer's test certificates and technical literature for
the admixture proposed to be used. If directed, the admixture shall be got tested at an
approved laboratory at no extra cost.
Storing of Materials:
All materials shall be stored in a manner so as to prevent its deterioration and
contamination which would preclude its use in the works. Requirements of IS:4082 shall
be complied with.
The Contractor will have to make his own arrangements for the storage of adequate
quantity of cement. If such cement is not stored properly and has deteriorated, the
material shall be rejected. Cement bags shall be stored in dry weatherproof shed with a
raised floor, well away from the outer walls and insulated from the floor to avoid
moisture from ground. Not more than 15 bags shall be stacked in any tier. Storage
arrangement shall be approved by the Engineer in charge. Storage under tarpaulins shall
not be permitted. Each consignment of cement shall be stored separately and consumed
in its order of receipt.
Each size of coarse and fine aggregates shall be stacked separately and shall be
protected from leaves and contamination with foreign material. The stacks shall be on
hard, clean, free draining bases, draining away from the concrete mixing area.
The Contractor shall make his own arrangements for storing water at site in tanks to
prevent contamination.
The reinforcement shall be stacked on top of timber sleepers to avoid contact with
ground/water. Each type and size shall be stacked separately.
Concrete grade shall be as designated on drawings. In concrete grade M15, M20 etc. the
number represents the specified characteristic compressive strength of 150X150X150
mm cube at 28 days, expressed in N/mm2 as per IS:456. Concrete in the works shall be
"DESIGN MIX CONCRETE" or "NOMINAL MIX CONCRETE". All concrete works of grade M5,
M7.5 and M10 shall be NOMINAL MIX CONCRETE whereas all other grades, M15 and
above, shall be DESIGN MIX CONCRETE. Concrete grade shall not be lower than M-25 for
building and M-30 for water retaining structures (all units of STP including distribution
chambers, sludge chambers, inlet/ outlet chambers adjacent to PST/ AT/ SST, sump).
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
12.0 Design Mix Concrete:
Mix Design & Testing
For Design Mix Concrete, the mix shall be designed according to IS:10262 and SP:23 to
provide the grade of concrete having the required workability and characteristic
strength not less than appropriate values given in IS:456. The design mix shall be
cohesive and does not segregate and should result in a dense and durable concrete and
also capable of giving the finish as specified. For liquid retaining structures, the mix
shall also result in water tight concrete. The Contractor shall exercise great care while
designing the concrete mix and executing the works to achieve the desired result.
The minimum cement content for Design Mix Concrete shall be as per Appendix-A of
IS:456 or as given below, whichever is higher.
Minimum Cement Content in Kg/m 3 of
Grade of Concrete
The minimum cement content stipulated above shall be adopted irrespective of whether
the Contractor achieves the desired strength with less quantity of cement. The
CONTRACTOR's quoted rates for concrete shall provide for the above eventuality and
nothing extra shall be paid to the CONTRACTOR on this account. Even in the case where
the quantity of cement required is higher than that specified above to achieve desired
strength based on an approved mix design, nothing extra shall become payable to the
It shall be the Contractor's sole responsibility to carry out the mix designs at his own
cost. He shall furnish to the EMPLOYER at least 30 days before concreting operations, a
statement of proportions proposed to be used for the various concrete mixes and the
strength results obtained. The strength requirements of the concrete mixes ascertained
on 150 mm cubes as per IS:516 shall comply with the requirements of IS:456.
Grade of Minimum Compressive Specified Characteristic Compressive
Concrete Strength N/sq.mm at 7 days Strength N/sq.mm at 28 days
A range of slumps which shall generally be used for various types of construction unless
otherwise instructed by the Engineer in charge is given below:
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
Slump in millimeters
Structure/Member
Maximum Minimum
Reinforced foundation walls and 75
Plain footings, caissons and 100
Slabs, Beams and reinforced walls 75
Pump & miscellaneous Equipment
Building columns 50
Heavy mass construction 50
Characteristic Compressive Strength Compliance Requirement (Table 11: IS 456).
13.0 Batching & Mixing of Concrete:
Proportions of aggregates and cement, as decided by the concrete mix design, shall be
by weight. These proportions shall be maintained during subsequent concrete batching
by means of weigh batchers capable of controlling the weights within one percent of the
Amount of water added shall be such as to produce dense concrete of required
consistency, specified strength and satisfactory workability and shall be so adjusted to
account for moisture content in the aggregates. Water- cement ratio specified for use
by the Engineer in charge shall be maintained. Each time when the work stops, the
mixer shall be cleaned out, and while recommencing, the first batch shall have 10%
additional cement to allow for sticking in the drum.
Arrangement should be made by the Contractor at his own cost to have the cubes tested
in an Government/NABL approved laboratory as per IS 10262-2009 or in field with prior
consent of the Engineer in charge. Prior to start the work as per approved Mix Design,
the cubes shall be casted at site and it shall be sent to “GERI” for testing, confirmation
and to compare the test results for 7 and 28 days with the approved Mix Design.
Concrete work can be started after approval of testing results from GERI for 7 and
days. At least 10% of tests shall be carried out in Government engineering college or in
the GERI. Sampling and testing of strength and workability of concrete shall be as per
IS:1199, IS:516 and IS:456, IS
14.0 Nominal Mix Concrete
Mix Design & Testing
Mix design and preliminary tests are not necessary for Nominal Mix Concrete.
However, works tests shall be carried out as per IS:456. Proportions for Nominal Mix
Concrete and Water Cement Ratio may be adopted as per Table 3 of IS:456. However, it
will be the Contractor's sole responsibility to adopt appropriate nominal mix proportions
to yield the specified strength.
15.0 Batching & Mixing of Concrete:
Based on the adopted nominal mixes, aggregates shall be measured by volume.
However, cement shall be by weight only.
Formwork shall be all inclusive and shall consist of shoring, bracings, sides of footings,
walls, beams and columns, bottom of slabs etc. including ties, anchors, hangers, inserts,
false work, wedges etc.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
The design and engineering of the formwork as well as its construction shall be the
responsibility of the Contractor. However, if so desired by the Engineer in charge,
The drawings and calculations for the design of the formwork shall be submitted to the
Engineer in charge for approval.
Formwork shall be designed to fulfill the following requirements:
Sufficiently rigid and tight to prevent loss of grout/ slurry or mortar from the concrete
at all stages and appropriate to the methods of placing and compacting.
Formwork shall be made of suitable materials as directed by engineer in-charge.
Capable of providing concrete of the correct shape and surface finish within the
specified tolerance limits.
Capable of withstanding without deflection the worst combination of self-weight,
reinforcement and concrete weight, all loads and dynamic effects arising from
construction and compacting activities, earthquake, wind and weather forces.
Capable of easy striking out without shock, disturbance or damage to the concrete.
Soffit forms capable of imparting a camber if required.
Soffit forms and supports capable of being left in position if required.
Capable of being cleaned and/or coated if necessary immediately prior to casting the
concrete; design temporary openings where necessary for these purposes and to
facilitate the preparation of construction joints.
The formwork may be of timber, plywood, steel, plastic or concrete depending upon the
type of finish specified. Sliding forms and slip form may be used with the approval of
the Engineer in charge. Timber for formwork shall be well seasoned, free from sap,
shakes, loose knots, worm holes, warps and other surface defects. Joints between
formwork and between formwork and structures shall be sufficiently tight to prevent
loss of slurry from concrete, using seals if necessary.
The faces of formwork coming in contact with concrete shall be cleaned and two coats
of approved mould oil applied before fixing reinforcement. All rubbish, particularly
chippings, shavings, sawdust, wire pieces dust etc. shall be removed from the interior of
the forms before the concrete is placed. Where directed, cleaning of forms shall be
done by blasting with a jet of compressed air at no extra cost.
Forms intended for reuse shall be treated with care. Forms that have deteriorated shall
not be used. Before reuse, all forms shall be thoroughly scraped, cleaned, nails
removed, holes suitably plugged, joints repaired and warped lumber replaced to the
satisfaction of the Engineer in charge. The Contractor shall equip himself with enough
shuttering to allow for wastage so as to complete the job in time.
Permanent formwork shall be checked for its durability and compatibility with adjoining
concrete before it is used in the structure. It shall be properly anchored to the
Wire ties passing through beams, columns and walls shall not be allowed. In their place
bolts passing through sleeves shall be used. Formwork spacers left in situ shall not
impair the desired appearance or durability of the structure by causing spilling, rust
staining or allowing the passage of moisture.
For liquid retaining structures, sleeves shall not be provided for through bolts nor shall
through bolts be removed if provided. The bolts, in the latter case, shall be cut at
mm depth from the surface and the hole made good by cement mortar of the same
proportion as the concrete just after striking the formwork.
Where specified all corners and angles exposed in the finished structure shall have
chamfers or fillets of 20 mm x 20 mm size.
Forms for substructure may be omitted when, in the opinion of the Engineer in charge,
the open excavation is firm enough (in hard non-porous soils) to act as a form. Such
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
excavations shall be larger, as approved by the Engineer in charge, than that required
as per drawing to compensate for irregularities in excavation.
The Contractor shall provide adequate props carried down to a firm bearing without
overloading any of the structures.
The shuttering for beams and slabs shall be so erected that the side shuttering of beams
can be removed without disturbing the bottom shuttering. If the shuttering for a column
is erected for the full height of the column, one side shall be built up in sections as
placing of concrete proceeds or windows left for placing concrete from the side to limit
the drop of concrete to 1.0m or as approved by the Engineer in charge. The Contractor
shall temporarily and securely fix items to be casted (embedment / inserts) in a manner
that will not hinder the striking of forms or permit loss of grout.
Formwork showing excessive distortion, during any stage of construction, shall be
repositioned and strengthened. Placed concrete affected by faulty formwork, shall be
entirely removed and formwork corrected prior to placement of new concrete at
Contractor's cost.
The striking time for formwork shall be determined based on the following requirements:
Development of adequate concrete strength.
Permissible deflection at time of striking form work.
Curing procedure employed - its efficiency and effectiveness.
Subsequent surface treatment to be done;
Prevention of thermal cracking at re-entrant angles;
Ambient temperatures; and
Aggressiveness of the environment (unless immediate adequate steps are taken to
prevent damage to the concrete).
Under normal circumstances (generally where temperatures are above 20oC) forms may
be struck after expiry of the time period given in IS:456 unless approved otherwise by
the Engineer in charge. For Portland Pozzolana/slag cement the stripping time shall be
suitably modified as approved by the Engineer in charge. It is the Contractor's
responsibility to ensure that forms are not struck until the concrete has developed
sufficient strength to support itself, does not undergo excessive deformation and resist
surface damage and any stresses arising during the construction period.
17.0 Reinforcement Workmanship
Reinforcing bars supplied bent or in coils shall be straightened cold without damage. No
bending shall be done when ambient temperature is below 5°C. Local warming may be
permitted if steel is kept below 10° C. All bars shall be accurately cut and bent
gradually and according to the sizes and shapes shown on the drawings/ schedules or as
directed by Engineer in charge. Re-bending or straightening incorrectly bent bars shall
not be done without the approval of the Engineer in charge.
Reinforcement shall be accurately fixed and maintained firmly in the correct position by
the use of blocks, spacers, chairs, binding wire etc. to prevent displacement during
placing and compaction of concrete. The tied in place reinforcement shall be approved
by the Engineer in charge prior to concrete placement. Spacers shall be of such
materials and designs as will be durable, not lead to corrosion of the reinforcement and
not cause spilling of the concrete cover. Binding wire shall be 16-gauge soft annealed
wires. Ends of the binding wire shall be bent away from the concrete surface and in no
case encroach into the concrete cover.
Substitution of reinforcement, laps/splices not shown on drawing shall be subject to
Engineer in charge’s approval.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
18.0 Tolerances:
Tolerance for formwork and concrete dimensions shall be as per IS:456 unless specified
Tolerances specified for horizontal or vertical building lines or footings shall not be
construed to permit encroachment beyond the legal boundaries.
The formwork shall be designed and constructed to the shapes, lines and dimensions
shown on the drawings within the tolerances given below:
Deviation from specified dimensions
of cross section of columns and beams
Deviations from dimensions of footings
(Tolerances apply to concrete
dimensions only, not to positioning of
vertical reinforcing steel or dowels
1) Dimension in plan - 12 mm+ 50 mm
0.02 times the width of the
footing in the direction of
2) Eccentricity
deviation but not more than
± 0.05 times the specified
19.0 Preparation Prior to Concrete Placement:
Before concrete is actually placed in position, the inside of the formwork shall be
cleaned and mould oil applied, inserts and reinforcement shall be correctly positioned
and securely held, necessary openings, pockets, etc. provided.
All arrangements-formwork, equipment and proposed procedure, shall be approved by
the Engineer in charge. Contractor shall maintain separate Pour Card for each pour as
per the format enclosed.
20.0 Transporting, Placing and Compacting Concrete:
Concrete shall be transported from the mixing plant to the formwork with minimum
time lapse by methods that shall maintain the required workability and will prevent
segregation, loss of any ingredients or ingress of foreign matter or water.
In all cases concrete shall be deposited as nearly as practicable directly in its final
position. To avoid segregation, concrete shall not be re handled or caused to flow. For
locations where, direct placement is not possible and in narrow forms the Contractor
shall provide suitable drops and "Elephant Trunks". Concrete shall not be dropped from a
height of more than 1.0m.
Concrete shall not be placed in flowing water. Under water, concrete shall be placed in
position by tremie or by pipeline from the mixer and shall never be allowed to fall
freely through the water.
While placing concrete the Contractor shall proceed as specified below and also
ensure the following:
Continuously between construction joints and pre-determined abutments.
Without disturbance to forms or reinforcement.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
Without disturbance to pipes, ducts, fixings and the like to be cast in; ensure that such
items are securely fixed. Ensure that concrete cannot enter open ends of pipes and
Without dropping in a manner that could cause segregation or shock.
In deep pours only when the concrete and formwork designed for this purpose and by
using suitable chutes or pipes.
Do not place if the workability is such that full compaction cannot be achieved.
Without disturbing the unsupported sides of excavations; prevent contamination of
concrete with earth. Provide sheeting if necessary. In supported excavations, withdraw
the linings progressively as concrete is placed.
If placed directly onto hardcore or any other porous material, dampen the surface to
reduce loss of water from the concrete.
Ensure that there is no damage or displacement to sheet membranes.
Record the time and location of placing structural concrete.
Concrete shall normally be compacted in its final position within thirty minutes of
leaving the mixer. Concrete shall be compacted during placing with approved vibrating
equipment without causing segregation until it forms a solid mass free from voids
thoroughly worked around reinforcement and embedded fixtures and into all corners of
the formwork. Immersion vibrators shall be inserted vertically at points not more than
450 mm apart and withdrawn slowly till air bubbles cease to come to the surface,
leaving no voids. When placing concrete in layers advancing horizontally, care shall be
taken to ensure adequate vibration, blending and melding of the concrete between
successive layers. Vibrators shall not be allowed to come in contact with reinforcement,
formwork and finished surfaces after start of initial set. Over-vibration shall be avoided.
Concrete may be conveyed and placed by mechanically operated equipment after
getting the complete procedure approved by the Engineer in charge. The slump shall be
held to the minimum necessary for conveying concrete by this method. When concrete
is to be pumped, the concrete mix shall be specially designed to suit pumping. Care
shall be taken to avoid stoppages in work once pumping has started.
Except when placing with slip forms, each placement of concrete in multiple lift work
shall be allowed to set for at least 24 hours after the final set of concrete before the
start of subsequent placement. Placing shall stop when concrete reaches the top of the
opening in walls or bottom surface of slab, in slab and beam construction, and it shall
be resumed before concrete takes initial set but not until it has had time to settle as
approved by the Engineer in charge. Concrete shall be protected against damage until
final acceptance.
21.0 Mass Concrete Works:
Sequence of pouring for mass concrete works shall be as approved by the Engineer in
charge. The Contractor shall exercise great care to prevent shrinkage cracks and shall
monitor the temperature of the placed concrete if directed.
At the time of placing concrete, thickness of layer shall not be more than 450 mm for
vibrated concrete per layer and limiting height of concrete shall be applicable as per IS
457, clause 4.10.7 for particular component.
Curing and protection shall start immediately after the compaction of the concrete
to protect it from:
Premature drying out, particularly by solar radiation and wind;
Leaching out by rain and flowing water;
Rapid cooling during the first few days after placing;
High internal thermal gradients;
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
Low temperature or frost;
Vibration and impact which may disrupt the concrete and interfere with its bond to the
All concrete, unless approved otherwise by the Engineer in charge, shall be cured by use
of continuous sprays or ponded water or continuously saturated coverings of sacking,
canvas or other absorbent material for the period of complete hydration with a
minimum of 7 days. The quality of curing water shall be the same as that used for
Where a curing membrane is approved to be used by the Engineer in charge, the same
shall be of a non-wax base and shall not impair the concrete finish in any manner. The
curing compound to be used shall be approved by the EMPLOYER before use and shall be
applied with spraying equipment capable of a smooth, even textured coat.
Curing may also be done by covering the surface with an impermeable material such as
polyethylene, which shall be well sealed and fastened.
23.0 Construction Joints and Keys:
Construction joints will be as shown in the drawing or as approved by the EMPLOYER.
Concrete shall be placed without interruption until completion of work between
construction joints. If stopping of concreting becomes unavoidable anywhere, a properly
formed construction joint shall be made with the approval of the Engineer in charge.
Dowels for concrete work, not likely to be taken up in the near future, shall be coated
with cement slurry and encased in lean concrete as indicated on the drawings or as
approved by the Engineer in charge.
Before resuming concreting on a surface which has hardened all laitance and loose stone
shall be thoroughly removed by wire brushing/hacking and surface washed with high
pressure water jet and treated with thin layer of cement slurry for vertical joints and
horizontal layers.
When concreting is to be resumed on a surface which has not fully hardened, all
laitance shall be removed by wire brushing, the surface wetted, free water removed
and a coat of cement slurry applied. On this, a layer of concrete not exceeding
thickness shall be placed and well rammed against the old work. Thereafter work shall
proceed in the normal way.
24.0 Foundation Bedding:
All earth surfaces upon which or against which concrete is to be placed, shall be well
compacted and free from standing water, mud or debris. Soft or spongy areas shall be
cleaned out and back filled with either soil-cement mixture, lean concrete or clean
sand compacted as approved by the Engineer in charge. The surfaces of absorptive soils
shall be moistened.
Concrete shall not be deposited on large sloping rock surfaces. The rock shall be cut to
form rough steps or benches by picking, barring or wedging. The rock surface shall be
kept wet for 2 to 4 hours before concreting.
The formwork for concrete works shall be such as to give the finish as specified. The
Contractor shall make good any unavoidable defects as approved consistent with the
type of concrete and finish as specified. Defects due to bad workmanship (e.g. damaged
or misaligned forms, defective or poorly compacted concrete) will not be accepted. The
Contractor shall construct the formwork using the correct materials and to meet the
requirements of the design and to produce finished concrete to required dimensions,
plumbs, planes and finishes.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
Surface Finish Type F1:
The main requirement is that of dense, well-compacted concrete. No treatment is
required except repair of defective areas, filling all form tie holes and cleaning up of
loose or adhering debris. For surfaces below grade, which will receive waterproofing
treatment, the concrete shall be free of surface irregularities, which would interfere
with proper and effective application of waterproofing material specified for use.
Surface Finish Type F2:
The appearance shall be that of a smooth dense, well-compacted concrete showing the
slight marks of well fitted shuttering joints. The Contractor shall make good any
Surface Finish Type F3:
This finish shall give an appearance of smooth, dense, well-compacted concrete with no
shutter marks, stain free and with no discoloration, blemishes, arises, air holes etc.
Only lined or coated plywood with very tight joints shall be used to achieve this finish.
The panel size shall be uniform and as large as practicable. Any minor blemishes that
might occur shall be made good by the Contractor.
Integral Cement Finish on Concrete Floor:
In all cases where integral cement finish on a concrete floor has been specified, the top
layer of concrete shall be screened off to proper level and tamped with tamper having
conical projections so that the aggregate shall be forced below the surface. The surface
shall be finished with a wooden float and a trowel with pressure. The finish shall be
continued till the concrete reaches its initial set. No cement or cement mortar finish
shall be provided on the surface. Where specified, a floor hardener as approved by the
Engineer-In-Charge shall be supplied and used as recommended by the manufacturer.
The formwork for concrete works shall be such as to give the finish as specified. The
Contractor shall make good any unavoidable defects as approved consistent with the
type of concrete and finish specified; defects due to bad workmanship (e.g. damaged or
misaligned forms, defective or poorly compacted concrete) will not be accepted. The
Contractor shall construct the formwork using the correct materials and to meet the
requirements of the design and to produce finished concrete to required dimensions,
plumbs, planes and finishes.
26.0 Repair and Replacement of Unsatisfactory Concrete:
Immediately after the shuttering is removed, all the defective areas such as honey-
combed surfaces, rough patches, holes left by form bolts etc. shall be inspected by the
Engineer in charge who may permit patching of the defective areas or reject the
All through holes for shuttering shall be filled for full depth and neatly plugged flush
Rejected concrete shall be removed and replaced by the Contractor at no additional
cost to the Employer.
For patching of defective areas all loose materials shall be removed and the surface
shall be prepared as approved by the Engineer in charge.
Bonding between hardened and fresh concrete shall be done either by placing cement
mortar or by applying epoxy. The decision of the Engineer in charge as to the method of
repairs to be adopted shall be final and binding on the Contractor. The surface shall be
saturated with water for 24 hours before patching is done with 1:5 cement sand mortar.
The use of epoxy for bonding fresh concrete shall be carried out as approved by the
Engineer in charge.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
27.0 Vacuum Dewatering of Slabs:
Where specified floor slabs, either grade or suspended, shall be finished by vacuum
dewatering including all operations such as poker vibration, surface vibration, vacuum
processing, floating and toweling as per equipment manufacturers recommendation.
The equipment to be used shall be subject to the Engineer in charge's approval.
28.0 Hot Weather Requirements:
Concreting during hot weather shall be carried out as per IS:7861 (Part I).
Adequate provisions shall be made to lower concrete temperatures which shall not
exceed 40º C at the time of placement of fresh concrete.
Where directed by the Engineer in charge, the Contractor shall spray non-wax based
curing compound on unformed concrete surfaces at no extra costs.
29.0 Cold Weather Requirements.
Concreting during cold weather shall be carried out as per IS: 7861 (Part II).
The ambient temperature during placement and up to final set shall not fall below 5º C.
Approved antifreeze/accelerating additives shall be used where directed.
For major and large-scale concreting works the temperature of concrete at times of
mixing and placing, the thermal conductivity of the formwork and its insulation and
stripping period shall be closely monitored.
30.0 Liquid Retaining Structures:
The Contractor shall take special care for concrete for liquid retaining structures,
underground structures and those others specifically called for to guarantee the finish
and water tightness.
The minimum level of surface finish for liquid retaining structures shall be as defined
elsewhere. All such structures shall be hydro-tested.
The Contractor shall make all arrangements for hydro-testing of structure, all
arrangements for testing such as temporary bulk heads, pressure gauges, pumps, pipe
The Contractor shall also make all temporary arrangements that may have to be made
to ensure stability of the structures during construction.
Any leakage that may occur during the hydro-test or subsequently during the defects
liability period or the period for which the structure is guaranteed shall be effectively
stopped either by cement/epoxy pressure grouting, guiniting or such other methods as
may be approved by the Engineer in charge. All such rectification shall be done by the
Contractor to the entire satisfaction of the Engineer in charge at no extra cost.
Placing Concrete Underwater:
Under all ordinary conditions all foundations shall be completely dewatered and
concrete placed in the dry. However, when concrete placement under water is
necessary, all work shall conform to IS:456 and the procedure shall be as described in
the following paragraphs:
Concrete shall be deposited underwater by means of tremies, or drop bottom buckets of
All work requiring placement of concrete underwater shall be designed, directed and
inspected with due regard to local circumstances and purposes. All underwater concrete
shall be placed according to the plans or Specifications and as directed and approved by
Engineer In-charge.
31.0 Testing Concrete Structures for Leakage:
Hydro-static test for water tightness shall be done at full storage level or soffit of
cover slab, as may be directed by the Engineer in charge, as described below:
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
In case of structures whose external faces are exposed, such as elevated tanks, the
requirements of the test shall be deemed to be satisfied if the external faces show no
sign of leakage or sweating and remain completely dry during the period of observation
of seven days after allowing a seven-day period for absorption after filling with water.
In the case of structures whose external faces are buried and are not accessible for
inspection, such as underground tanks, the structures shall be filled with water and
after the expiry of seven days after the filling; the level of the surface of the water
shall be recorded. The level of water shall be recorded again at subsequent intervals of
24 hrs. Over a period of seven days. Backfilling shall be withheld till the tanks are
tested. The total drop in surface level over a period for seven days shall be taken as an
indication of the water tightness of the structure. The Engineer in charge shall decide
on the actual permissible nature of this drop in the surface level, considering whether
the structures are open or closed and the corresponding effect it has on evaporation
Unless specified otherwise, a structure whose top is covered shall be deemed to be
water tight if the total drop in the surface level over a period of seven days does not
Each compartment/segment of the structure shall be tested individually and then all
For structures such as pipes, tunnels etc. the hydrostatic test shall be carried out by
filling with water, after curing as specified, and subjecting to the specified test
pressure for specified period. If during this period the loss of water does not exceed the
equivalent of the specified rate, the structure shall be considered to have successfully
passed the test.
Optional Tests:
If the Employer feels that the materials i.e. cement, sand, coarse aggregates,
reinforcement and water are not in accordance with the Specifications or if specified
concrete strengths are not obtained, he may order tests to be carried out on these
materials in laboratory, to be approved by the Engineer in charge, as per relevant IS
Codes. Contractor shall have to pay for these tests.
In the event of any work being suspected of faulty material or workmanship requiring its
removal or if the works cubes do not give the stipulated strengths, the Engineer in
charge reserves the right to order the Contractor to take out cores and conduct tests on
them or do ultrasonic testing or load testing of structure, etc. The Engineer in charge
also reserves the right to ask the Contractor to dismantle and re-do such unacceptable
work, at no cost to the Engineer in charge. Alternately Engineer in charge also reserves
the right to ask the CONTRACTOR to dismantle and re-do such unacceptable work at the
cost of CONTRACTOR.
Standard Grout:
Grout shall be provided as specified on the drawings.
The proportion of Standard Grout shall be such as to produce a flow able mixture
consistent with minimum water content and shrinkage. Surfaces to be grouted shall be
thoroughly roughened and cleaned. All structural steel elements to be grouted shall be
cleaned of oil, grease, dirt etc. The use of hot, strong caustic solution for this purpose
will be permitted. Prior to grouting, the hardened concrete shall be saturated with
water and just before grouting, water in all pockets shall be removed. Grouting once
started shall be done quickly and continuously. Variation in grout mixes and procedures
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
shall be permitted if approved by the Engineer in charge. The grout proportions shall be
limited as follows:
Use Grout Thickness Mix Proportions
Cement Ratio (max)
One-part Portland Cement
1. Fluid mix Under 25mm
to one-part sand
25mm and over but One-part Portland Cement
less than 50mm to 2 parts of sand
One-part Portland Cement
c) Stiff mix 50mm and over
to 3 parts of sand
Non-Shrink Grout:
Non-shrink grout where required shall be provided in strict accordance with the
manufacturer's instructions / specifications on the drawing.
All materials, workmanship and finished construction shall be subject to continuous
inspection and approval of Engineer in charge. Materials rejected by Engineer in charge
shall be expressly removed from site and shall be replaced by Contractor immediately.
Upon the completion of concrete work, all forms, equipment, construction tools,
protective coverings and any debris, scraps of wood, etc. resulting from the work shall
be removed and the premises left clean.
Acceptance Criteria:
Any concrete work shall satisfy the requirements given below individually and
collectively for it to be acceptable.
Properties of constituent materials;
Characteristic compressive strength;
Specified mix proportions;
Minimum cement content;
Maximum free-water/cement ratio;
Temperature of fresh concrete;
Density of fully compacted concrete;
Cover to embedded steel;
Tolerances in dimensions;
Tolerances in levels;
Surface finishes;
Special requirements such as;
Water tightness
Resistance to aggressive chemicals
Resistance to freezing and thawing
Very high strength
Improved fire resistance
Wear resistance
Resistance to early thermal cracking
The Engineer in charge's decision as to the acceptability or otherwise of any concrete
work shall be final and binding on the Contractor. For work not accepted, the Engineer
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
in charge may review and decide whether remedial measures are feasible so as to
render the work acceptable. The Engineer in charge shall in that case direct the
Contractor to undertake and execute the remedial measures. These shall be
expeditiously and effectively implemented by the Contractor. Nothing extra shall
become payable to the Contractor by the Employer for executing the remedial
33.0 Water stops:
The material for the PVC water stops shall be a plastic compound with the basic resin of
polyvinyl chloride and additional resins, plasticizers, inhibitors, which satisfies the
performance characteristics specified below as per IS:12200. Testing shall be in
accordance with IS:8543.
a) Tensile strength : 3.6 N/mm2 minimum
c) Ultimate elongation : 300 % minimum
d) Tear resistance : 4.9 N/mm2 minimum
e) Stiffness in flexure : 2.46 N/mm2 minimum
f) Accelerated extraction
g) Tensile strength : 10.50 N/mm2 minimum
h) Ultimate elongation : 250% minimum
i) Effect of Alkali : 7 days
j) Weight increase : 0.10% maximum
k) Weight decrease : 0.10% maximum
l) Hardness change : ± 5 points
m) Effect of Alkali : 28 days
n) Weight increase : 0.40% maximum
o) Weight decrease : 0.30% maximum
p) Dimension change : ±1%
PVC water stops shall be either of the bar type, serrated with center bulb and end grips
for use within the concrete elements or of the surface (kicker) type for external use.
PVC water stops shall be of approved manufacture. Samples and the test certificate
shall be got approved by the Engineer in charge before procurement for incorporation in
the works. Alternatively, G.I. sheet of 18 gage (1.3mm) thick and 200mm wide can be
used by the contractor as construction joints.
Alternatively, contractors can use G.I sheet 200mm wide and 18 gauge thick as
constructions joints.
34.0 Workmanship:
Water stops shall be cleaned before placing them in position. Oil or grease shall be
removed thoroughly using water and suitable detergents.
Water stops shall be procured in long lengths as manufactured to avoid joints as far as
possible. Standard L or T type of intersection pieces shall be procured for use depending
on their requirement. Any non-standard junctions shall be made by cutting the pieces
to profile for jointing. Lapping of water stops shall not be permitted. All jointing shall
be of fusion welded type as per manufacturer’s instructions.
Water stops shall be placed at the correct location/level and suitably supported at
intervals with the reinforcement to ensure that it does not deviate from its intended
position during concreting and vibrating. Care shall also be taken to ensure that no
honey-combing occurs because of the serrations/end grips, by placing concrete with
smaller size aggregates in this region. Projecting portions of the water stops embedded
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
in concrete shall be thoroughly cleaned of all mortar/ concrete coating before resuming
further concreting operations. The projecting water stop shall also be suitably
supported at intervals with the reinforcement to maintain its intended position during
concreting so as to ensure that it does not bend leading to formation of pockets. In
addition, smaller size aggregates shall be used for concreting in this region also.
35.0 Preformed Fillers and Joint Sealing Compound:
Preformed filler for expansion/isolation joints shall be non-extruding and resilient type
of bitumen impregnated fibers conforming to IS:1838 (Part I).
Bitumen coat to concrete/masonry surfaces for fixing the preformed bitumen filler strip
shall conform to IS:702. Bitumen primer shall conform to IS:3384.
Sealing compound for filling the joints above the preformed bitumen filler shall conform
to Grade 'A' as per IS:1834.
The thickness of the preformed bitumen filler shall be 25mm for expansion joints and
50mm for isolation joints around foundation supporting rotatory equipment's. Contractor
shall procure the strips of the desired thickness and width in lengths as manufactured.
Assembly of small pieces/thicknesses of strips to make up the specified size shall not be
The concrete/masonry surface shall be cleaned free from dust and any loose particles.
When the surface is dry, one coat of industrial blown type bitumen of grade 85/25
conforming to IS:702 shall be applied hot by brushing at the rate of 1.20 kg/m2. When
the bitumen is still hot the preformed bitumen filler shall be pressed and held in
position till it completely adheres. The surface of the filler against which further
concreting/masonry work is to be done shall similarly be applied with one coat of hot
bitumen at the rate of 1.20 kg/m2.
Sealing compound shall be heated to a pouring consistency for enabling it to run molten
in a uniform manner into the joint. Before pouring the sealing compound, the vertical
faces of the concrete joint shall be applied hot with a coat of bitumen primer
conforming to IS: 3384 in order to improve the adhesive quality of the sealing
Expansion joints between beams/slabs shall be provided with 100mm wide x 4mm thick
mild steel plate at the soffit of RCC beams/slabs to support and prevent the preformed
joint filler from dislodging. This plate shall be welded to an edge angle of ISA 50 x 50 x
6mm provided at the bottom corner, adjacent to the expansion joint of one of the
beams/slabs, by intermittent fillet welding. Steel surfaces shall be provided with
coats of red oxide zinc chrome primer and 3 coats of synthetic enamel paint finish.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
CONCRETE POUR CARD
POUR NO.: DATE:
DRG. NO.: STRUCTURE:
CONCRETE GRADE/QUANTITY/: MAX. AGGREGATE SIZE /
SLUMP: START / COMPLETION TIME:
BEFORE CENTRELINES
CONCRETING CHECKED
STAGING CHECKED
STRENGTH & FINISH
4 REINFORCEMENT YES/NO
5 CERTIFICATE FOR YES/NO
6 MATERIALS / YES/NO
EQUIPMENT FOR POUR
EMBEDDED CIVIL YES/NO
PARTS MECH. YES/NO
PLUMB) ELEC. YES/NO
SOFFIT(S) & POUR TOP(T) LEVELS T(B)
8 CHECKED BEFORE (B) & AFTER (A)
CONSTRUCTION JOINTS LOCATION &
EXPANSION JOINTS – LOCATION AND
10 CEMENT CONSUMPTION IN KGS.
REINFORCEMENT CONSUMPTION
NUMBER OF CUBES AND
IDENTIFICATION MARKS
TEST CUBE RESULTS (7 DAYS /
CONCRETE CONDITION ON FORM V.GOOD/GOOD/FAIR/
Contractor's Representative Engineer- in-charge's Representative
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
EACH POUR TO HAVE SEPARATE CARDS, IN TRIPLICATE ONE EACH FOR CLIENT,
CONTRACTOR & SITE OFFICE.
UNDER REMARKS, INDICATE DEVIATIONS FROM DWGS. & SPECIFICATIONS, CONGESTION IN
REINFORCEMENT IF ANY, UNUSUAL OCCURRENCES SUCH AS FAILURE OF EQUIPMENTS,
SINKING OF SUPPORTS / PROPS. HEAVY RAINS AFFECTING CONCRETING, POOR
COMPACTION, IMPROPER CURING, OTHER DEFICIENCIES, OBSERVATIONS ETC.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
SECTION -4 BUILDING ITEMS
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
BUILDING ITEMS.
Applicable Codes and Specifications
The following codes and standards are included in this section, as part of these
specifications. However, respective IS codes for the works not mentioned here shall also be
applicable for those particular items of work.
IS:110 - Ready mixed paint, brushing, gray filler, for Enamels for use over primers
IS:269 - Specification for 33 grade ordinary Portland cement
IS:280 - Specification for mild steel wire for general Engineering purposes
IS:287 - Recommendations for maximum permissible Moisture content of timber used for
different purposes
IS:383 - Specif. for coarse &fine aggregates from natural sources for concrete
IS:412 - Expanded metal steel sheets for general purposes
IS:419 - Specification for putty for use on window frames
IS:428 - Distemper, oil emulsion, color as required
IS:459 - Specification for unreinforced corrugated and semi-corrugated asbestos cement
IS:702 - Specification for industrial bitumen
IS:710 - Specification for marine plywood
IS:712 - Specification for building limes
IS:730 - Specification for hook bolts for corrugated sheet Roofing
IS:733 - Wrought aluminum and aluminum alloys, bars, Rods and sections for general
engineering purposes
IS:777 - Specification for glazed earthenware tiles
IS:1003 - Specification for timber paneled and glazed shutters (Parts 1 & 2)
IS:1038 - Specification for steel doors, windows and ventilators
IS:1077 - Specification for common burnt clay building bricks
IS:1081 - Code of practice for fixing and glazing of metal (steel &aluminum) doors,
windows and ventilators.
IS:1124 - Method of test for determination of water absorption, apparent specific
gravity and porosity of natural building stones
IS:1237 - Specification for cement concrete flooring tiles
IS:1322 - Bitumen felts for water proofing and damp proofing
IS:1346 - Code of practice for water proofing of roofs with bitumen felts
IS:1361 - Specification for steel windows for industrial buildings
IS:1443 - Code of practice for laying and finishing of cement concrete flooring tiles
IS:1477 - Code of practice for painting of ferrous metals in buildings (Parts 1 & 2)
IS:1542 - Specification for sand for plaster
IS:1580- Specification for bituminous compounds for water-proofing and caulking purposes.
IS:1597- Code of practice for construction of stone masonry: Part 1 Rubble stone masonry
IS:1661 - Code of practice for application of cement and cement-lime plaster finishes
IS:1834 - Specification for hot applied sealing compound for joint in concrete
IS:1838- Specification for preformed fillers for expansion joint in concrete Pavements and
structures (none extruding and resilient type): Part 1 Bitumen impregnated fiber.
IS:1948 - Specification for aluminum doors, windows and ventilators
IS:1949 - Specification for aluminum windows for industrial buildings
IS:2074 - Ready mixed paint, air drying, red oxide- zinc chrome, priming
IS:2114 - Code of practice for laying in-situ terrazzo floor finish
IS:2116 - Specification for sand for masonry mortars
IS:2185 - Specification for concrete masonry units (Parts 1,2& 3)
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
IS:2202 - Specification for wooden flush door shutters (Solid core type): Parts 1&2
IS:2212 - Code of practice for brickwork
IS:2250 - Code of practice for preparation and use of masonry mortars
IS:2338 - Code of practice for finishing of wood and wood-based materials (Parts 1 & 2)
IS: 2395- Code of practice for painting concrete, masonry and plaster surfaces (Parts 1 & 2)
IS:2402 - Code of practice for external rendered finishes
IS:2571 - Code of practice for laying in-situ cement concrete flooring
IS:2572 - Code of practice for construction of hollow concrete block masonry
IS:2645 - Specification of integral cement waterproofing compounds
IS:2690 - Specification for burnt clay flat terracing tiles: Part 1 Machine made
IS:2691 - Specification for burnt clay facing bricks
IS:2750 - Specification for steel scaffoldings
IS:2835 - Flat transparent sheet glass
IS:2932 - Specification for enamel, synthetic, exterior type (a) undercoating,(b) finishing
IS:3007- Code of practice for laying of asbestos cement sheets - corrugated and
(Part 1 & 2) semi-corrugated sheets
IS:3067 - Code of practice of general design details and preparatory work for
Damp-proofing and water- proofing of buildings
IS:3068- Specification for broken brick (burnt clay) coarse aggregates for use in Lime
IS:3384 - Specification for bitumen primer for use in water-proofing and damp-proofing
IS:3462 - Specification for unbaked flexible PVC flooring
IS:3495 - Method of test for burnt clay building bricks: Part 1 to
IS:3536 - Specification for ready mixed paint, brushing, and wood primer, pink
IS:3696 - Safety code of scaffolds and ladders (Parts 1 & 2)
IS:4020 - Methods of test for wooden flush door: Type test
IS:4021 - Specification for timber door, window and ventilator frames
IS:4351 - Specification for steel door frames
IS:4443 - Code of practice for use of resin type chemical resistant mortars
IS:4457 - Specification for ceramic unglazed vitreous acid resisting tile
IS:4631 - Code of practice for laying epoxy resin floor toppings
IS:4832 - Specification for chemical resistant mortars (Part II)
IS:4860 - Specification for acid resistant bricks
IS:4948 - Specification for welded steel wire fabric for general use
IS:5318 - Code of practice for laying of flexible PVC sheet and tile flooring
IS:5410 - Cement paint, color as required
IS:5411 - Specification for plastic emulsion paint (Parts 1 & 2)
IS:5437 - Wired and figured glass
IS:5491 - Code of practice for laying of in-situ granolithic concrete floor topping
IS:6042 - Code of practice for construction of light weight concrete block masonry
IS:6248 - Specification for metal rolling shutters and rolling grilles
IS:7193 - Specification for glass fiber base coal tar pitch and bitumen felts
IS:7452 - Specification for hot rolled steel sections for doors, windows and Ventilators
IS:8042 - Specification for white Portland cement
IS:9197- Specification for epoxy resin, hardeners and epoxy resin composites for floor
IS:9862 Specification for ready mixed paint, brushing, bituminous, black, lead-free, acid,
alkali, water and chlorine resisting
IS:12200- Code of practice for provision of water stops at transverse contraction
joints in masonry and concrete dams
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
Bricks used in the works shall conform to the requirements laid down in IS: 1077. The class
of the bricks shall be as specifically indicated in the respective items of work.
The nominal size of the modular brick shall be 200 mm x 100 mm x 100 mm with the
permissible tolerances over the actual size of 190mm x90 mm x 90 mm as per IS: 1077. The
nominal thickness of one brick and half brick walls using modular bricks shall be considered
as 200 mm and 100 mm respectively. In the event of use of traditional bricks of nominal size
230 mmx115mmx75mm with tolerance up to ±3 mm in each dimension, one brick and half
brick walls shall be considered as 230 mm and 115 mm respectively.
Bricks shall be sound, hard, and homogenous in texture, well burnt in kiln without being
vitrified, hand/machine mounded, deep red, cherry or copper colored, of regular shape and
size & shall have sharp and square edges with smooth rectangular faces. The bricks shall be
tested from approved laboratory and free from pores, cracks, flaws and nodules of free
lime. Hand moulded bricks shall be moulded with a frog and those made by extrusion
process may not be provided with a frog. Bricks shall give a clear ringing sound when struck
and shall have a minimum crushing strength of 3N/sq.mm unless otherwise specified in the
Items of work prepared by the Contractor.
The average water absorption shall not be more than 20 percent by weight up to class
and 15 percent by weight for higher classes. Bricks which do not conform to this
requirement shall be rejected. Over or under burnt bricks are not acceptable for use in the
works. Sample bricks shall be submitted to the GWIL for approval and bricks supplied shall
conform to approved samples. If demanded by GWIL, brick samples shall be got tested as
per IS: 3495 by Contractor. Bricks rejected by GWIL shall be removed from the site of works
within 24 hours.
Mortar for brick masonry shall consist of cement and sand and shall be prepared as per IS:
2250. Mix shall be in the proportion of 1:5 for brickwork of thickness one brick or above and
1:4 for brickwork of thickness half brick or below, unless otherwise specified in the
respective items of work prepared by the Contractor. Sand for masonry mortar shall conform
to IS:218. The sand shall be free from clay, shale, loam, alkali and organic matter and shall
be of sound, hard, clean and durable particles. Sand shall be approved by GWIL. If so
directed by the GWIL, sand shall be screened and washed till it satisfies the limits of
deleterious materials.
For preparing cement mortar, the ingredients shall first be mixed thoroughly in dry
condition. Water shall then be added and mixing continued to give a uniform mix of required
consistency. Mixing shall be done thoroughly in a mechanical mixer, unless hand mixing is
specifically permitted by the GWIL. The mortar thus mixed shall be used as soon as possible,
preferably within 30 minutes from the time water is added to cement. In case, the mortar
has stiffened due to evaporation of water, this may be re-tempered by adding water as
required to restore consistency, but this will be permitted only up to 30 minutes from the
time of initial mixing of water to cement. Any mortar which is partially set shall be rejected
and shall be removed from the site. Droppings of mortar shall not be re-used under any
circumstances. The Contractor shall arrange for test on mortar samples if so directed by the
Workmanship of brick work shall conform to IS: 2212. All bricks shall be thoroughly soaked in
clean water for at least one hour immediately before being laid. The cement mortar for
brick masonry work shall be as specified in the respective item of work prepared by the
Contractor. Brick work 200mm/230mm thick and over shall be laid in English Bond unless
otherwise specified. 100mm/115mm thick brickwork shall be laid with stretchers. For laying
bricks, a layer of mortar shall be spread over the full width of suitable length of the lower
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
course. Each brick shall be slightly pressed into the mortar and shoved into final position so
as to embed the brick fully in mortar. Only full-size bricks shall be used for the works and
cut bricks utilized only as closers to make up required wall length or for bonding. Bricks
shall be laid with frogs on top.
All brickwork shall be plumb, square and true to dimensions shown. Vertical joints in
alternate courses shall come directly one over the other and be in line. Horizontal courses
shall be leveled. The thickness of brick courses shall be kept uniform. In case of one brick
thick or half brick thick wall, at least one face should be kept smooth and plane, even if the
other is slightly rough due to variation in size of bricks. For walls of thickness greater than
one brick both faces shall be kept smooth and plane. All interconnected brickwork shall be
carried out at nearly one level so that there is uniform distribution of pressure on the
supporting structure and no portion of the work shall be left more than one course lower
than the adjacent work. Where this is not possible, the work shall be raked back according
to bond (and not saw toothed) at an angle not exceeding 45 deg. But in no case the level
difference between adjoining walls shall exceed one meter. Brickwork shall not be raised
more than one meter per day.
Bricks shall be so laid that all joints are well filled with mortar. The thickness of joints shall
not be less than 6 mm and not more than 10 mm. The face joints shall be raked to a
minimum depth of 10mm/15mm by raking tools during the progress of work when the mortar
is still green, so as to provide a proper key for the plastering/ pointing respectively to be
done later. When plastering or pointing is not required to be done, the joints shall be
uniform in thickness and be struck flush and finished at the time of laying. The face of
brickwork shall be cleaned daily and all mortar droppings removed. The surface of each
course shall be thoroughly cleaned of all dirt before another course is laid on top. During
inclement weather conditions, newly built brick masonry works shall be protected by
tarpaulin or other suitable covering to prevent mortar being washed away by rain.
Brickwork shall be kept constantly moist on all the faces for at least seven days after 24 hrs
of laying. The arrangement for curing shall be got approved from the E.I.C.
Double scaffolding having two sets of vertical supports shall be provided to facilitate
execution of the masonry works. The scaffolding shall be designed adequately considering
all the dead, live and possible impact loads to ensure safety of the workmen, in accordance
with the requirements stipulated in IS:2750 and IS:3696(Part I).
Scaffolding shall be properly maintained during the entire period of construction. Single
scaffolding shall not be used on important works and will be permitted only in certain cases
as decided by the GWIL. Where single scaffolding is adopted, only minimum number of
holes, by omitting a header shall be left in the masonry for supporting horizontal scaffolding
poles. All holes in the masonry shall be carefully made good before plastering/pointing.
In the event of usage of traditional bricks of size 230 mm x115mm x75mm, the courses at
the top of the plinth and sills as well as at the top of the wall just below the roof/floor slabs
and at the top of the parapet shall be laid with bricks on edge. All brickwork shall be built
tightly against columns, floor slabs or other structural members.
To overcome the possibility of development of cracks in the brick masonry following
measures shall be adopted. For resting RCC slabs, the bearing surface of masonry wall shall
be finished on top with 12 mm thick cement mortar 1:3 and provided with 2 layers of Kraft
paper Grade 1 as per IS:1397 or 2 layers of 50-micron thick polyethylene sheets.
RCC/ steel beams resting on masonry wall shall be provided with reinforced concrete bed
blocks of 50 mm thickness, projecting 50mm on either side of the beam, duly finished on top
with 2 layers of Kraft paper Grade 1 as per IS:1397 or 2 layers of 50-micron thick
polyethylene sheets.
Steel wire fabric shall be provided at the junction of brick masonry and concrete before
taking up plastering work. Bricks for partition walls shall be stacked adjacent to the
structural member to pre-deflect the structural member before the wall is taken up for
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
execution. Further, the top most course of half or full brick walls abutting against either a
de-shuttered slab or beam shall be built only after any proposed masonry wall above the
structural member is executed to cater for the deflection of the structural element.
Reinforced cement concrete transoms and mullions of dimensions as indicated in the
construction Drawings to be prepared by the Contractor are generally required to be
provided in the half brick partition walls.
Where the drawings prepared by the Contractor indicate that structural steel sections are to
be encased in brickwork, the brickwork masonry shall be built closely against the steel
section, ensuring a minimum of 20mm thick cement-sand mortar 1:4 over all the steel
surfaces. Steel sections partly embedded in brickwork shall be provided with bituminous
protective coating to the surfaces at the point of entry into the brick masonry.
Facing bricks of the type specified conforming to IS: 2691 shall be laid in the positions
indicated on the Drawings prepared by the Contractor and all facing brickwork shall be well
bonded to the backing bricks/RCC surfaces. The level of execution of the facing brickwork
shall at any time be lower by at least 600 mm below the level of the backing brickwork.
Facing bricks shall be laid over 10 mm thick backing of cement mortar. The mortar mix,
thickness of joint and the type of pointing to be carried out shall be as specified in the item
of works prepared by the Contractor. The pattern of laying the bricks shall be as specifically
indicated in the Drawings prepared by the Contractor. For facing brickwork, double
scaffolding shall be used. Faced works shall be kept clean and free from damage,
discoloration etc., at all times.
Uncoursed Random Rubble Masonry, in Foundation, Plinth and Superstructure.
Stones for the works shall be of the specified variety, which are hard, durable, fine grained
and uniform in color (for superstructure work) free from veins, flaws and other defects.
Quality and work shall conform to the requirements specified in IS: 1597 (Part-I). The
percentage of water absorption shall not exceed 5 percent as per test conducted in
accordance with IS: 1124. The Contractor shall supply sample stones to the GWIL for
approval. Stones shall be laid with its grains horizontal so that the load transmitted is always
perpendicular to the natural bed.
Cement-sand mortar for stone masonry works shall be in the proportion of 1:6.
Materials and preparation of mortar shall be as specified above.
For All Works below ground level the masonry shall be random rubble uncoursed with
ordinary quarry dressed stones for the hearting and selected quarry dressed stones for the
For all works above ground level and in superstructure the masonry shall be random rubble
uncoursed, well bonded, faced with hammer dressed stones with squared quoins at corners.
The bushings on the face shall not be more than 40 mm on an exposed face and on the face
to be plastered it shall not project by more than 12 mm nor shall it have depressions more
than 10 mm from the average wall surface.
Face stones shall extend back sufficiently and bond well with the masonry. The depth of
stone from the face of the wall inwards shall not be less than the height or breadth at the
face. The length of the stone shall not exceed three times the height and the breadth on
base shall not be greater than three-fourths the thickness of wall nor less than 150 mm.
The height of stone may be up to a maximum of 300 mm. Face stones or hearting stones
shall not be less than 150 mm in any direction. Chips and spalls shall be used wherever
necessary to avoid thick mortar joints and to ensure that no hollow spaces are left in the
masonry. The use of chips and spalls in the hearting shall not exceed 20 percent of the
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
quantity of stone masonry. Spalls and chips shall not be used on the face of the wall and
below hearting stones to bring them to the level of face stones.
The maximum thickness of joints shall not exceed 20 mm. All joints shall be completely
filled with mortar. When plastering or pointing is not required to be done, the joints shall
be struck flush and finished as the work proceeds. Otherwise, the joints shall be raked to a
minimum depth of 20 mm by a raking tool during the progress of the work while the mortar
is still green.
Through or bond stones shall be provided in walls up to 600 mm thick and in case of walls
above 600 mm thickness, a set of two or more bond stones overlapping each other by at
least 150 mm shall be provided in a line from face to back. In case of highly absorbent
types of stones (porous lime stone and sand stone, etc.) the bond stone shall extend about
two-thirds into the wall and a set of two or more bond stones overlapping each other by at
least 150 mm shall be provided. Each bond stone or a set of bond stones shall be provided
for every 0.5 sq.m of wall surface.
All stones shall be sufficiently wetted before laying to prevent absorption of water from
the mortar. All connected walls in a structure shall be normally raised uniformly and
regularly. However, if any part of the masonry is required to be left behind, the wall shall
be raked back (and not saw toothed) at an angle not exceeding 45deg. Masonry work shall
not be raised by more than one meter per day. Green work shall be protected from rain by
suitable covering. Masonry work shall be kept constantly moist on all the faces for a
minimum period of seven days for proper curing of the joints.
Coursed Rubble Masonry (First Sort) for Superstructure:
The Material specification for the work shall be as specified above.
All Courses shall be laid truly horizontal and shall be of the same height in any course. The
height of course shall not be less than 150 mm and not more than 300 mm. The width of
stone shall not be less than its height.
Face stones shall tail into the work for not less than their height and at least 1/3rd the
number of stones shall tail into the work for a length not less than twice their height but
not more than three-fourths the thickness of the wall whichever is smaller. These should
be laid as headers and stretchers alternately to break joints by at least 75 mm.
The face stones shall be squared on all joints and beds; the bed joints being hammer or
chisel dressed true and square for at least 80 mm back from the face and the side joints
for at least 40 mm. The face of the stone shall be hammer dressed so that the bushing
shall not be more than 40 mm on an exposed face and 10 mm on a face to be plastered. No
portion of the dressed surface shall show a depth of gap more than 6 mm from a straight
edge placed on it. The remaining unexposed portion of the stone shall not project beyond
the surface of bed and side joints. No spalls or pinning shall be allowed on the face.
All bed joints shall be horizontal and side joints shall be vertical and no joints shall be
more than 10 mm in thickness. When plastering or pointing is not required to be done, the
joints shall be struck flush and finished as the work proceeds. Otherwise, the joints shall
be raked to a minimum depth of 20 mm by a raking tool, during the progress of the work
while the mortar is still green.
Hearting shall consist of flat bedded stones carefully laid on their proper beds and solidly
bedded in mortar. The use of chips shall be restricted to the filling of interstices between
the adjacent stones in hearting and these shall not exceed 10 percent of the quantity of
the stone masonry. Care shall be taken so that no hollow spaces are left anywhere in the
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
The requirement regarding through or bond stones shall be as specified in clause 7.3.2 with
the further stipulation that these shall be provided at 1.5 m to 1.8m apart clear in every
course but staggered at alternate courses.
The quoins which shall be of the same height as the course, in which they occur, shall not
be less than 450 mm in any direction. Quoin stones shall be laid as stretchers and headers
alternately. They shall be laid square on their beds, which shall be rough chisel dressed to
a depth of at least 100 mm from the face. These stones shall have a minimum uniform
chisel draft of 25mm width at four edges, all the edges being in the same plane.
Concrete Block Masonry:
Masonry units of hollow and solid concrete blocks shall conform to the requirements of IS:
2185 (Part I). Masonry units of hollow and solid light-weight concrete blocks shall conform
to the requirements of IS: 2185 (Part 3). Masonry units of autoclaved cellular concrete
blocks shall conform to the requirements of IS:2185 (Part 3). The height of the concrete
masonry units shall not exceed either its length or six times its width.
The nominal dimensions of concrete block shall be as under.
Length 400, 500 or 600 mm
Height 100 or 200 mm
Width 100 to 300 mm in 50 mm increments
Half blocks shall be in lengths of 200, 250 or 300mm to correspond to the full-length
blocks. Actual dimensions shall be 10mm short of the nominal dimensions.
The maximum variation in the length of the units shall not be more than ±5 mm and
maximum variation in height or width of the units shall not be more than ± 3mm.
Concrete blocks shall be either hollow blocks with open or closed cavities or solid blocks.
Concrete blocks shall be sound, free of cracks, chipping or other defects which impair the
strength or performance of the construction. Surface texture shall as specify. The faces of
the units shall be flat and rectangular, opposite faces shall be parallel and all arises shall
The bedding surfaces shall be at right angles to the faces of the block.
The concrete mix for the hollow and solid concrete blocks/light weight concrete blocks
shall not be richer than one part of cement to six parts of combined aggregates by volume.
Concrete blocks shall be of approved manufacture, which satisfy the limitations in the
values of water absorption, drying shrinkage and moisture movement, as specified for the
type of block as per relevant IS code. Contractor shall furnish the test certificates and also
supply the samples for the approval of GWIL.
The type of the concrete block, thickness and grade based on the compressive strength for
use in load bearing and/or non-load bearing walls shall be as specified. The minimum
nominal thickness of non-load bearing internal walls shall be 100mm. The minimum
nominal thickness of external panel walls in framed construction shall be 200 mm.
The workmanship shall generally conform to the requirements of IS:2572 for concrete block
masonry, IS:6042 for light weight concrete block masonry and IS:6041 for autoclaved
cellular concrete block masonry works.
From considerations of durability, generally concrete block masonry shall be used in
superstructure works above the damp-proof course level.
Concrete blocks shall be embedded with a mortar which is relatively weaker than the mix
of the blocks in order to avoid the formation of cracks. Cement mortar of proportion 1:6
shall be used for the works. Preparation of mortar shall be as specified above.
Thickness of both horizontal and vertical joints shall be 10mm. The first course shall be
laid with greater care, ensuring that it is properly aligned, leveled and plumb since this
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
will facilitate in laying succeeding courses to obtain a straight and truly vertical wall. For
the horizontal (bedding) joint, mortar shall be spread over the entire top surface of the
block including front and rear shells as well as the webs to a uniform layer of 10mm. For
vertical joints, the mortar shall be applied on the vertical edges of the front and rear
shells of the blocks. The mortar may be applied either to the unit already placed on the
wall or on the edges of the succeeding unit when it is standing vertically and then placing
it horizontally, well pressed against the previously laid unit to produce a compacted
vertical joint. In case of two cell blocks with slight depression on the vertical sides these
shall also be filled up with mortar to secure greater lateral rigidity. To assure satisfactory
bond, mortar shall not be spread too far ahead of actual laying of the block as the mortar
will stiffen and lose its plasticity Mortar while hardening shrinks slightly and thus pulls
away from the edges of the block. The mortar shall be pressed against the units with a
jointing tool after it has stiffened to effect intimate contact between the mortar and the
unit to obtain a weather tight joint. The mortar shall be raked to a depth of 10mm as each
course is laid to ensure good bond for the plaster.
Dimensional stability of hollow concrete blocks is greatly affected by variations of moisture
content in the units. Only well dried blocks should be used for the construction. Blocks
with moisture content more than 25% of maximum water absorption permissible shall not
be used. The blocks should not be wetted before or during laying in the walls. Blocks
should be laid dry except slightly moistening their surfaces on which mortar is to be
applied to obviate absorption of water from the mortar.
As per the design requirements and to effectively control cracks in the masonry, RCC
bound beams/studs, joint reinforcement shall be provided at suitable locations. Joint
reinforcement shall be fabricated either from mild steel wires conforming to IS:280 or
welded wire fabric/high strength deformed basis.
For jambs of doors, windows and openings, should concrete blocks shall be provided. If
hollow units are used, the hollows shall be filled with concrete of mix 1:3:6. Hold fasts of
doors/windows should be arranged so that they occur at block course level.
At intersection of walls, the courses shall be laid up at the same time with a true masonry
bond between at least 50% of the concrete blocks. The sequence for construction of
partition walls and treatment at the top of load bearing walls for the RCC slab shall be as
for the brick work. Curing of the mortar joints shall be carried out for at least 7 days. The
walls should only be lightly moistened and shall not be allowed to become excessively wet.
Double scaffolding as per clause shall be adopted for execution of block masonry work.
Cutting of the units shall be restricted to a minimum. All horizontal and vertical
dimensions shall be in respectively, adopting modular co-ordination for walls, opening
locations for doors, windows etc.
Concrete blocks shall be stored at site suitably to avoid any contact with moisture from the
ground and covered to protect against wetting.
Damp - Proof Course:
Materials and Workmanship:
Where Specified, all the walls in a building shall be provided with damp-proof course cover
at plinth to prevent water from rising up the wall. The damp-proof course shall run without
a break throughout the length of the wall, even under the door or other openings. Damp-
proof course shall consist of 50 mm thick cement concrete of 1:2:4 nominal mix with
approved water-proofing compound admixture conforming to IS: 2645 in proportion as
directed by the manufacturer. Concrete shall be with 10 mm downgraded coarse
The surface of brick work/stone masonry work shall be leveled and prepared before laying
the cement concrete. Side shuttering shall be properly fixed to ensure that slurry does not
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
leak through and is also not disturbed during compaction. The upper and side surface shall
be made rough to afford key to the masonry above and to the plaster.
Damp-proof course shall be cured properly for at least seven days after which it shall be
allowed to dry for taking up further work.
Miscellaneous Inserts, Bolts etc.
All the miscellaneous inserts such as bolts, pipes, plate embedment etc., shall be
accurately installed in the building works at the correct location and levels, all as detailed
in the construction Drawings to be prepared by the Contractor. Contractor shall prepare
and use templates for this purpose, if so directed by the GWSSB. In the event, of any of
the inserts are improperly installed, Contractor shall make necessary arrangements to
remove and reinstall at the correct locations/levels, all as directed by the GWSSB.
Wood Work for Doors, Windows, Ventilators & Partitions
Timber to be used shall be first class Teak wood as per IS:4021. Timber shall be of the best
quality and well seasoned by a suitable process before being planed to the required sizes.
The maximum permissible moisture content shall be from 10 to 16 percent for timber
50mm and above in thickness and 8 to 14 percent of timber less than 50mm in thickness for
different regions of the country as stipulated in IS:287. Timber shall be close grained, of
uniform color and free from decay, fungal growth, boxed heart, pitch pockets or streaks on
the exposed edges, borer holes, splits and cracks.
Flush door shutters of the solid core type with plywood face panels shall conform to
IS:2202 (Part 1) and with particle board/hard board face panels shall conform to IS:2202
Transparent sheet glass shall conform to the requirements of IS:2835. Wired and figured
glass shall be as per IS:5437.
Builder’s hardware for fittings and fixtures shall be of the best quality from approved
The workmanship and finish of wood work in doors, windows, ventilators and partitions
shall be of a very high order. Contractor shall ensure that work is executed in a
professional manner by skilled carpenters for good appearance, efficient and smooth
operation of the shutters.
All works shall be executed as per the detailed Drawings prepared by the Contractor
and/or as directed by the GWIL.
All members of the door, window, and ventilator shall be straight without any warp or bow
and shall have smooth well-planned faces. The right angle shall be checked from the inside
surfaces of the respective members of the frame. Frames shall have mortise and tenon
joints which shall be treated with an approved adhesive and provided with metal or wood
pins. The vertical members of the door frame shall project 50 mm below the finished floor
level. The finished dimension of frames shall be rebated on the solid for keying with the
plaster and for receiving the shutters. The depth of rebate for housing the shutter shall be
15 mm. The size of the frames shall be as specified in the respective items of work
prepared by the Contractor. The workmanship shall generally conform to the requirements
specified in IS:4021.
The face of the frames abutting the masonry or concrete shall be provided with a coat of
Three hold fasts using 25 mm x 6 mm mild steel flats 225 mm long with split ends shall be
fixed on each side of door and window frames, one at the center and the other two at
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
mm from the top and bottom of the frame. For window and ventilator frames less than 1 m
in height, two hold fasts on each side shall be fixed at quarter points.
Timber paneled shutters for doors, windows and ventilators shall be constructed in the
form of framework of stiles and rails with panel insertion. The panels shall be fixed by
either providing grooves in the stiles and rails or by beading. Glazing bars shall be as
detailed in the Drawings prepared by the Contractor. The stiles and rails shall be joined by
mortise and tenon joints at right angles. All members of the shutter shall be straight
without any warp or bow and shall have smooth, well planed faces at right angles to each
other. The right angle for the shutter shall be checked by measuring the diagonals and the
difference shall not be more than ±3 mm. Timber panels made from more than one piece
shall be jointed with a continuous tongued and grooved joint, glued together and
reinforced with metal dowels.
The workmanship shall generally conform to the requirements specified in IS: 1003 (Parts
& 2). The thickness of the shutter, width/thickness of the stiles/rails/panel type shall be
as specified. Marine plywood panels conforming to IS:710 shall be used for doors where
Details of the wooden flush door shutters, solid core type with specific requirement of the
thickness, core, face panels, viewing glazed panel, Venetian louver opening, teak wood
lapping etc. shall be as specified. Panels of shutter shall be of marine plywood conforming
to IS:710. Flush door shutters shall be from reputed manufacturers and Contractor shall
submit test results as per IS:4020, if so desired by the GWIL.
Glazing of door, window, ventilator and partitions shall be with either flat transparent
sheet glass, wired or figured glass. Transparent sheet glass shall be of 'B' quality as per IS:
2835.The thickness and type of glazing to be provided shall be as specified.
The material of the fittings and fixtures either of chromium plated steel, cast brass,
copper oxidized or anodized aluminum shall be as specified. The number, size and type of
the fittings and fixtures shall be as specified.
Woodwork shall not be provided with the finishes of painting/varnishing etc. unless it has
been approved by the GWIL. The type of finish and the number of coats shall be as
stipulated in the respective items of work prepared by the Contractor. Preparation of the
wood surfaces and application of the finishes shall be in accordance with clause 7.32.
Wooden hand railing and architraves shall be of the size and shape with the fixing
arrangement as indicated in the Drawings prepared by the Contractor.
The framework of the partitions with mullions and transoms shall be with the sections of
dimensions as specified. Panels of double/single glazing/plywood shall be fixed as per
details specified. Partitions shall be fixed rigidly between the floor and structural
columns/beams including provision of necessary shims for wedging etc. Finished work shall
be of rigid construction, erected truly plumb to the lines and levels, at locations as per the
construction Drawings prepared by the Contractor.
Any carpentry work which shows defects due to inadequate seasoning of the timber or bad
workmanship shall be removed and replaced by Contractor with work as per Specifications.
Steel Doors, Windows and Ventilators:
Hot rolled steel sections for the fabrication of steel doors, windows and ventilators shall
conform to IS: 7452, which are suitable for, single glazing.
Pressed steel door frames for steel flush doors shall be out of 1.25mm thick mild steel
sheets of profiles as per IS:
Transparent sheet glass shall conform to the requirements of IS:
Wired and figured glass shall be as per IS:
Builder’s hardware of fittings and fixtures shall be of the best quality from the approved
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
All steel doors, windows and ventilators shall be of the type as specified in the respective
items of work prepared by the Contractor and of sizes as indicated in the Drawings
prepared by the Contractor prepared by the Contractor. Steel doors, windows and
ventilators shall conform to the requirements as stipulated in IS: 1038. Steel windows shall
conform to IS: 1361, if so specified.
Doors, windows and ventilators shall be of an approved manufacture. Fabrication of the
unit shall be with rolled section, cut to correct lengths and metered. Corners shall be
welded to form a solid fused welded joint conforming to the requirements of IS:
Tolerance in overall dimensions shall be within ±1.5mm. The frames and shutters shall be
free from wrap or buckle and shall be square and truly plain. All welds shall be dressed
flush on exposed and contact surfaces. Punching of holes, slots and other provisions to
install fittings and fixtures later shall be made at the correct locations as per the
requirements. Samples of the units shall be got approved by the GWIL before further
manufacture/purchase by the Contractor.
Type and details of shutters, hinges, glazing bar requirement, couplings, locking
arrangement, fittings and fixtures shall be as described in the respective items of work and
/ or as shown in the Drawings prepared by the Contractor for single or composite units.
For windows with fly proof mesh as per the item of work prepared by the Contractor, rotor
operator arrangement, for the operation of the glazed shutters from the inside shall be
Pressed steel door frames shall be provided with fixing lugs at each jamb, hinges, lock-
strike plate, mortar guards, angle threshold, shock-absorbers of rubber or similar material
as per the requirements of IS: 4351. Pressed steel doorframes shall be fixed as `built-in’ as
the masonry work proceeds. After placing it plumb at the specified location, masonry walls
shall be built up solid on either side or each course grouted with mortar to ensure solid
contact with the doorframe, without leaving any voids. Temporary struts across the width
shall be fixed, during erection to prevent bow/sag of the frame. Door shutters of flush
welded construction shall be 45 mm thick, fabricated with two outer skills of 1.25mm thick
steel sheets, 1mm thick steel sheet stiffeners and steel channels on all four edges. Double
shutters shall have meeting stile edge beveled or rebated. Provision of glazed viewing
panel, louvers shall be made as per the items of works and/or Drawings prepared by the
Contractor. Shutters shall be suitably reinforced for lock and other surface hardware and
to prevent sagging/twisting. Single sheet steel door shutters shall be fabricated out of
1.25mm thick steel sheets, mild steel angles and stiffeners as per the Drawings prepared
by the Contractor.
Doors, windows and ventilators shall be fixed into the prepared openings. They shall not be
‘built-in’ as the masonry work proceeds, to avoid distortion and damage of the units. The
dimensions of the masonry opening shall have 10mm clearance around the overall
dimensions of the frame for this purpose. Any support of scaffolding members on the
frames/glazing bars is prohibited.
Glazing of the units shall be either with flat transparent glass or wired / figured glass of
the thickness as specified in the items of works prepared by the Contractor. All glass
panels shall have properly squared corner and straight edges. Glazing shall be provided on
the outside of the frames.
Fixing of the glazing shall be either with spring glazing clips and putty conforming to IS:419
or with metal beads. Pre-formed PVC or rubber gaskets shall be provided for fixing the
beads with the concealed screws. The type of fixing the glazing shall be as indicated in the
items of work and/or in Drawings prepared by the Contractor.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
Steel doors, windows and ventilators shall be provided with finish of either painting as
specified or shall be hot dip galvanized with thickness of the zinc coating as stipulated all
as described in the respective items of works prepared by the Contractor.
The material of the Builders hardware of fittings and fixtures of chromium plated steel,
cast brass, brass copper oxidized or anodized aluminum shall be as specified in the items
of works prepared by the Contractor. The number, size and type of fittings and fixtures
shall be as in the Drawings /items of works prepared by the Contractor.
Installation of the units with fixing lugs, screws, mastic caulking compound at the specified
locations shall generally conform to the requirements of IS:1081. Necessary holes etc
required for fixing shall be made by the Contractor and made good after installation.
Workmanship expected is of a high order for efficient and smooth operation of the units.
Aluminum Doors, Windows, Ventilators & Partitions:
Aluminum alloy used in the manufacture of extruded sections for the fabrication of doors,
windows, ventilators shall conform to designation HE9-WP of IS:733.
Transparent sheet glass shall conform to the requirements of IS:2835. Wired and figured
glass shall be as per IS:5437.
Builder's hardware of fittings & fixtures shall be of the best quality from approved
All aluminum doors, windows, ventilators and partitions shall be of the type and size as
specified. The doors, windows, ventilators shall conform to the requirements of IS:1948.
Aluminum windows shall conform to IS:1949, if so specified.
All aluminum units shall be supplied with anodized finish. The minimum anodic film
thickness shall be 0.015 mm. Doors, windows and ventilators shall be of an approved
manufacture. Fabrication of the units shall be with the extruded sections, cut to correct
lengths, mitered and welded at the corners to a true right angle conforming to the
requirements of IS:1948. Tolerance in overall dimensions shall be within ± 1.5mm. The
frames and shutters shall be free from warp or buckle and shall be square and truly plane.
Punching of holes, slots and other provisions to install fittings or fixtures later shall be
made at the correct locations, as per the requirements. Aluminum swing type doors,
aluminum sliding windows, partitions shall be as specified.
IS:1948 and IS:1949 referred to incorporates the sizes, shapes, thicknesses and weight per
running meter of extruded sections for the various components of the units. However, new
sizes, shapes, thicknesses with modifications to suit snap-fit glazing clips etc. are being
continuously being added by various leading manufacturers of extruded sections, which are
available in the market. As such, the sections of the various components of the unit
proposed by the Contractor will be reviewed by the GWIL and will be accepted only if they
are equal to or marginally more than that given in the codes/as specified.
The framework of the partitions with mullions and transom shall be with anodized
aluminum box sections. Anodized aluminum box sections shall be in-filled with timber of
class 3 (silver oak or any other equivalent) as per IS:4021. Panels of double/single
glazing/plywood shall be fixed as per details indicated in the Drawings to be prepared by
the Contractor. Partitions shall be fixed rigidly between the floor and the structural
columns/beams including provision of necessary shims for wedging etc. Finished work shall
be of rigid construction, erected truly plumb to the lines and levels, at locations as per the
construction Drawings to be prepared by the Contractor.
Specific provisions as stipulated for steel doors, windows, ventilators under clause 7.9.2
shall also be applicable for this item work. Glazing beads shall be of the snap-fit type
suitable for the thickness of glazing proposed as indicated in the items of works prepared
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
by the Contractor. A layer of clear transparent lacquer shall be applied on aluminum
sections to protect them from damage during installation. This lacquer coating shall be
removed after the installation is completed.
Steel Rolling Shutters:
Materials and Workmanship:
Rolling shutters shall be of an approved manufacture, conforming to the requirements
specified in IS:6248.
The type of rolling shutter shall be self-coiling type (manual) for clear areas up to 12 m2,
gear operated type (mechanical) for clear areas up to 35 m2 and electrically operated type
for areas up to 50 sq.m. Mechanical type of rolling shutters shall be suitable for operation
from both inside and outside with the crank handle or chain gear operating mechanism
duly considering the size of wall/column. Electrical type of rolling shutter shall also be
provided with a facility for emergency mechanical operation.
Rolling shutters shall be supplied duly considering the type, specified clear width/height of
the opening and the location of fixing as indicated in the Drawings prepared by the
Contractor. Shutters shall be built up of interlocking laths 75 mm width between rolling
centers formed from cold rolled steel strips. The thickness of the steel strip shall not be
less than 0.90 mm for shutters up to 3.50m width and not less than 1.20 mm for shutters
above 3.50 m width. Each lath section shall be continuous single piece without any welded
joint. The guide channels out of mild steel sheets of thickness not less than 3.15 mm shall
be of either rolled, pressed or built up construction. The channel shall be of size as
stipulated in IS:6248 for various clear widths of the shutters.
Hood covers shall be of mild steel sheets not less than 0.90 mm thick and of approved
shape. Rolling shutters shall be provided with a central hasp and staple safety device in
addition to one pair of lever locks and sliding locks at the ends.
All component parts of the steel rolling shutter (excepting springs and insides of guide
channels) shall be provided with one coat of zinc chrome primer conformity to IS:2074 at
the shop before supply. These surfaces shall be given an additional coat of primer after
erection at the site along with the number of coats and type of finish paint as specified in
the respective items of works prepared by the Contractor. Painting shall be carried out as
specified in specifications or as per engineer in charge direction.
In case of galvanized rolling shutter, the lath sections, guides, lock plate, bracket plates,
suspension shaft and the hood cover shall be hot dip galvanized with a zinc coating
containing not less than 97.5 percent pure zinc. The weight of the zinc coating shall be at
least 610gms/m2.
Guide channels shall be installed truly plumb at the specified location. Bracket plate shall
be rigidly fixed with necessary bolts and holdfasts. Workmanship of erection shall ensure
strength and rigidity of rolling shutter for trouble free and smooth operation.
Rubble Sub-Base:
Stones used for rubble packing under floors on grade, foundations etc., shall be clean,
hard, durable rock free from veins, flaws, laminations, weathering and other defects.
Stones shall generally conform to the requirements stipulated in IS: 1597 (Part I).
Stones shall be as regular as can be obtained from quarries. Stones shall be of height equal
to the thickness of the packing proposed with a tolerance of 10 mm. Stones shall not
have a base area less than 250 sq cm nor more than 500 sq.cm, and the smallest dimension
of any stone shall not be less than half the largest dimension. The quality and size of
stones shall be subject to the approval of the GWSSB.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
Stones shall be hand packed carefully and laid with their largest base downwards resting
flat on the prepared sub-grade and with their height equal to the thickness of the packing.
Stones shall be laid breaking joints and in close contact with each other. All interstices
between the stones shall be wedged-in by small stones of suitable size, well driven in by
crow bars and hammers to ensure tight packing and complete filling-in of the interstices.
The wedging shall be carried out simultaneously with the placing in position of rubble
packing and shall not lag behind. After this, any interstices between the smaller wedged
stones shall be unfilled with clean hard sand by brooming so as to fill the joints
The laid rubble packing shall be sprinkled with water and compacted by using suitable
The thickness and grade of concrete and reinforcement shall be as specified in items of
works prepared by the contractor.
Before placing the blinding concrete, the sub-base of rubble packing shall be properly
wetted and rammed. Concrete for the base shall then be deposited between the forms,
thoroughly tamped and the surface finished level with the top edges of the forms. Two or
three hours after the concrete has been laid in position, the surface shall be roughened
using steel wire brush to remove any scum or laitance and swept clean so that the coarse
aggregates are exposed. The surface of the base concrete shall be left rough to provide
adequate bond for the floor finish to be provided later.
Terrazzo and Plain Cement Tiling Work:
Terrazzo tiles and cement tiles shall generally conform in all respects to standards
stipulated in IS:1237. Tiles shall be of the best quality manufactured adopting hydraulic
pressure of not less than 14N/mm2.
The type, quality, size, thickness color etc, of the tiles for flooring/dado/skirting shall be
The aggregates for terrazzo topping shall consist of marble chips which are hard, sound
and dense. Cement to be used shall be either ordinary Portland cement or white cement
with or without coloring pigment. The binder mix shall be with 3 parts of cement to 1 part
of marble powder by weight. The proportion of cement shall be inclusive of any pigments.
For every one part of cement-marble powder binder mix, the proportion of aggregates
shall be 1.75 parts by volume, if the chips are between 1mm to 6mm and 1.50 parts by
volume if the chips are between 6mm to 25mm.
The minimum thickness of wearing layer of terrazzo tiles shall be 5mm for tiles with chips
of size varying from 1mm up to 6mm or from 1mm up to 12mm. This shall be 6mm for tiles
with chips varying from 1mm up to 25mm. The minimum thickness of wearing layer of
cement/colored cement tiles shall be 5mm. This shall be 6mm for heavy duty tiles.
Pigment used in the wearing layer shall not exceed 10 percent of the weight of cement
used in the mix.
Laying and finishing of tiles shall conform to the requirements of workmanship stipulated
Tiling work shall be commenced only after the door and window frames are fixed and
plastering of the walls/ ceiling is completed. Wall plastering shall not be carried out up to
about 50 mm above the level of proposed skirting/dado.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
The base concrete shall be finished to a reasonably plane surface about 40 to 45mm below
the level of finished floor. Before the tiling work is taken up, the base concrete or
structural slab shall be cleaned of all loose materials, mortar droppings, dirt, laitance etc.
using steel wire brush and well wetted without allowing any water pools on the surface. A
layer of 25mm average thickness of cement mortar consisting of one part of cement to
parts of sand shall be provided as bedding for the tiles over the base concrete.
The thickness of bedding mortar shall not be less than 10mm at any place. The quantity of
water to be added for the mortar shall be just adequate to obtain the workability for
laying. Sand for the mortar shall conform to IS:2116 and shall have minimum fineness
modulus of 1.5. The surface shall be left rough to provide a good bond for the tiles.
The bedding shall be allowed to harden for a day before laying of the tiles. Neat cement
slurry using 4.4 kg of cement per m2of floor area shall be spread over the hardened mortar
bedding over such an area at a time as would accommodate about 20 tiles.
Tiles shall be fixed in this slurry one after the other, each tile being gently tapped with a
wooden mallet till it is properly bedded and in level with the adjoining tiles. The joints
shall be in straight lines and shall normally be 1.5mm wide.
On completion of laying of the tiles in a room, all the joints shall be cleaned and washed
fairly deep with a stiff broom/wire brush to a minimum depth of 5mm. The day after the
tiles have been laid, the joints shall be filled with cement grout of the same shade as the
color of the matrix of the tile. For this purpose, white cement or grey cement with or
without pigments shall be used.
The flooring should be kept moist and left undisturbed for 7 days for the bedding/joints to
set properly. Heavy traffic shall not be allowed on the floor for at least 14 days after fixing
About a week after laying the tiles, each and every tile shall be lightly tapped with a small
wooden mallet to find out if it gives a hollow sound; if it does, such tiles along with any
other cracked or broken tiles shall be removed and replaced with new tiles to proper line
The same procedure shall be followed again after grinding the tiles and all damaged tiles
replaced, properly jointed and finished to match. For the purpose of ensuring that such
replaced tiles match with those laid earlier, it is necessary that the Contractor shall
procure sufficient quantity of extra tiles to meet this contingency.
Wherever a full tile cannot be provided, tiles shall be cut to size and fixed. Floor tiles
adjoining the wall shall go about 10mm under the plaster, skirting or dado.
Tile skirting and dado work shall be executed only after laying tiles on the floor. For dado
and skirting work, the vertical wall surface shall be thoroughly cleaned and wetted.
Thereafter it shall be evenly and uniformly covered with 10mm thick backing of 1:4
cement sand mortar.
For this work the tiles as obtained from the factory shall be of the size required and
practically full polished. The back of each tile to be fixed shall be covered with a thin
layer of neat cement paste and the tile shall then be gently tapped against the wall with a
wooden mallet. Fixing shall be done from the bottom of the wall upwards. The joints shall
be in straight lines and shall normally be 1.5mm wide. Any difference in the thickness of
the tiles shall be evened out in the backing mortar or cement paste so that the tile faces
are in conformity & truly plumb. Tiles for use at the corners shall be suitably cut with
beveled edges to obtain a neat and true joint. After the work has set, hand polishing with
carbonado stones shall be done so that the surface matches with the floor finish.
Wall plastering of the strip left out above the level of skirting/dado shall be taken up after
the tiles are fixed.
Chequered terrazzo tiles for flooring and for stair treads shall be delivered to site after the
first machine grinding.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
Machine grinding and polishing shall be commenced only after a lapse of 14 days of laying.
The sequence and three numbers of machine grinding operations, usage of the type of
carborundum stones, filling up of pin holes, watering etc. shall be carried out all as
specified in IS:1443.
Tiles shall be laid to the levels specified. Where large areas are to be tiled the level of the
central portion shall be kept 10mm higher than that at the walls to overcome optical
illusion of a depression in the central portion. Localized deviation of ±3mm in any 3m
length is acceptable in a nominally flat floor.
In-Situ Terrazzo Work:
The requirements of marble aggregates for terrazzo topping shall be as mentioned above.
Cement shall first be mixed with the marble powder in dry state. The mix thus obtained
shall be mixed with the aggregates in the specified proportions. Care shall be taken not to
get the materials into a heap which results in the coarsest chips falling to the edges and
cement working to the center at the bottom.
Materials shall be kept, as far as possible, in an even layer during mixing. After the
materials have been thoroughly mixed in the dry state, water shall be added, just
adequate to obtain plastic consistency for the desired workability for laying. The mix shall
be used in the works within 30 minutes of the addition of water to the cement.
The thickness, type, quality, size and color of chips etc. for the in-situ terrazzo finish for
flooring/dado/ skirting shall be as specified in the respective items of works prepared by
the Contractor. Laying and finishing of in-situ work shall conform to the requirements of
workmanship stipulated in IS:
In-situ terrazzo finish shall be laid over hardened concrete base. The finish layer consists
of an under layer and terrazzo topping. The under layer shall be of cement concrete of mix
1:2:4 using 10mm downgraded coarse aggregates. The combined thickness of under layer
and topping shall not be less than 30 mm for flooring and 20mm for dado/skirting work.
The minimum thickness of topping shall be 6mm if chips used are between 1mm to 4mm,
9mm if chips are between 4mm to 7mm and 12mm if chips are between 7mm to 10mm. If
chips larger than 10mm size are used, the minimum thickness shall be one and one third
the maximum size of chips.
Both the under layer and later the topping shall be divided into panels not exceeding
m2for laying so as to reduce the possibility of development of cracks. The longer dimension
of any panel shall not exceed 2m. Dividing strips shall be used to separate the panels.
When the dividing strips are not provided, the bays shall be laid alternately, allowing an
interval of at least 24 hours between laying adjacent bays.
Dividing strips shall be either of aluminum, brass or other material as indicated in the
items of works prepared by the Contractor. Aluminum strips should have a protective
coating of bitumen. The thickness of the strips shall not be less than 1.5mm and width not
less than 25mm for flooring work.
Concrete base shall be finished to a reasonably plane surface to a level below the finished
floor elevation equal to the specified thickness of terrazzo finish. Before spreading the
under layer, the base concrete surface shall be cleaned of all loose materials, mortar
droppings, dirt, laitance etc. and well wetted without allowing any water pools on the
surface. Dividing strips or screed strips, if dividing strips are not provided shall be fixed on
the base and leveled to the correct height to suit the thickness of the finish.
Just before spreading the under layer the surface shall be smeared with cement slurry at
2.75 Kg/m2. Over this slurry, the under layer shall be spread and leveled with a screening
board. The top surface shall be left rough to provide a good bond for the terrazzo topping.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
Terrazzo topping shall be laid while the under layer is still plastic and normally between
to 24 hours after the under layer is laid. Cement slurry of the same color as the topping
shall be brushed on the surface immediately before laying is commenced.
The terrazzo mix shall be laid to a uniform thickness and compacted thoroughly by tamping
and with a minimum of toweling. Straight edge and steel floats shall be used to bring the
surface true to the required level in such a manner that the maximum amount of marble
chips come up and spread uniformly all over the surface.
The surface shall be left dry for air-curing for a period of 12 to 18 hours. Thereafter it shall
be cured by allowing water to stand in pools for a period of not less than 4 days.
Machine grinding and polishing shall be commenced only after a lapse of 7 days from the
time of completion of laying. The sequence and four numbers of machine grinding
operations, usage of the type of carborundum stones, filling up of pinholes, wet curing,
watering etc. shall be carried out all as specified in IS:
Shahabad / Tandur/ Kota Stone Slab work:
The slabs shall be of approved selected quality, hard, sound, dense and homogenous in
texture, free from cracks, decay, weathering and flaws. The percentage of water
absorption shall not exceed 5 percent as per test conducted in accordance with IS:
The slabs shall be hand or machine cut to the required thickness. Tolerance in thickness
for dimensions of tile more than 100mm shall be ±5mm. This shall be ±2mm on dimensions
less than 100mm. Slabs shall be supplied to the specified size with machine cut edges or
fine chisel dressed to the full depth. All angles and edges of the slabs shall be true and
square, free from any chipping giving a plane surface. Slabs shall have the top surface
machine polished (first grinding) before being brought to site. The slabs shall be washed
clean before laying.
The type, size, thickness and color/shade etc. of the slabs for flooring/dado/skirting shall
be as specified in the respective items of works prepared by the Contractor.
Preparation of the concrete base, laying and curing shall be as mentioned above.
Dado / skirting work shall be as per mentioned above. The thickness of the slabs for
dado/skirting work shall not be more than 25mm. Slabs shall be so placed that the back
surface is at a distance of 12mm. If necessary, slabs shall be held in position temporarily
by suitable method. After checking for verticality, the gap shall be filled and packed with
cement sand mortar of proportion 1:3. After the mortar has acquired sufficient strength,
the temporary arrangement holding the slab shall be removed.
Grinding and polishing shall be as per mentioned above, except that first grinding with
coarse grade carborundum shall not be done and cement slurry with or without pigment
shall not applied before polishing.
Carborundum Tile Finish:
Carborundum tiles shall generally conform in all respects to the standards stipulated in
IS:1237 for heavy duty tiles. Tiles shall be of the best quality manufactured adopting
hydraulic pressure of not less than 14 N/mm2.
The topping shall be uniform and of thickness not less than 6mm. The quantity of
Carborundum grit shall be not less than 1.35 kg/sq.m used with cement with or without
pigment. The Carborundum grit shall pass through 1.18mm mesh and shall be retained on
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
Requirements as detailed for terrazzo/cement tile finish as mentioned above shall be
applicable for Carborundum tile flooring.
Glazed Tile Finish:
Glazed earthenware tiles shall conform to the requirements of IS: 777. Tiles shall be of the
best quality from an approved manufacturer. The tiles shall be flat, true to shape and free
from flaws such as crazing, blisters, pinholes, specks or welts. Edges and underside of the
tiles shall be free from glaze and shall have ribs or indentations for a better anchorage
with the bedding mortar. Dimensional tolerances shall be as specified in IS:
The total thickness of glazed tile finish including the bedding mortar shall be 20 mm in
flooring/dado/skirting. The minimum thickness of bedding mortar shall be 12mm for
flooring and 10mm for dado/skirting work.
The bedding mortar shall consist of 1 part of cement to 3 parts of sand mixed with just
sufficient water to obtain proper consistency for laying. Sand for the mortar shall conform
to IS: 2116 and shall have minimum fineness modulus of 1.5.
Tiles shall be soaked in water for about 10 minutes just before laying. Where full size tiles
cannot be fixed, tiles shall be cut to the required size using special cutting device and the
edges rubbed smooth to ensure straight and true joints.
Colored tiles with or without designs shall be uniform and shall be preferably procured
from the same batch of manufacture to avoid any differences in the shade.
Tiles for the flooring shall be laid over hardened concrete base. The surface of the
concrete base shall be cleaned of all loose materials, mortar droppings etc well wetted
without allowing any water pools on the surface. The bedding mortar shall then be laid
evenly over the surface, tamped to the desired level and allowed to harden for a day. The
top surface shall be left rough to provide a good bond for the tiles. For skirting and dado
work, the backing mortar shall be roughened using a wire brush.
Neat cement slurry using 3.3 kg cement per m2of floor area shall be spread over the
hardened mortar bed over such an area as would accommodate about 20 tiles. Tiles shall
be fixed in this slurry one after the other, each tile being gently tapped with a wooden
mallet till it is properly bedded and in level with the adjoining tiles. For skirting and dado
work, the back of the tiles shall be smeared with cement slurry for setting on the backing
mortar. Fixing of tiles shall be done from the bottom of the wall upwards.
The joints shall be in perfect straight lines and as thin as possible but shall not be more
than 1mm wide. The surface shall be checked frequently to ensure correct level/required
slope. Floor tiles near the walls shall enter skirting/dado to a minimum depth of 10mm.
Tiles shall not sound hollow when tapped. All the joints shall be cleaned of grey cement
with wire brush to a depth of at least 3mm and all dust, loose mortar etc. shall be
White cement with or without pigment shall then be used for flush pointing the joints.
Curing shall then be carried out for a minimum period of 7 days for the bedding and joints
to set properly. The surface shall then be cleaned using a suitable detergent, fully washed
Specials consisting of coves, internal and external angles, cornices, beads and their corner
pieces shall be of thickness not less than the tiles with which they are used.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
In-Situ Cement Concrete Floor Topping:
The mix proportion for the in-situ concrete floor topping shall be 1:2.5:3.5 (one-part
cement: two and half parts sand: three and half parts coarse aggregates) by volume unless
otherwise specified.
The aggregates shall conform for the requirements of IS:383.
Coarse aggregates shall have high hardness surface texture and shall consist of crushed
rock of granite, basalt, trap or quartzite. The aggregate crushing valve shall not exceed
percent. The grading of the aggregates of size 12.5mm and below shall be as per IS:2571.
Grading of the sand shall be within the limits indicated in IS:2571.
The thickness of the floor topping shall be as specified in the items of work prepared by
the Contractor. The minimum thickness of the floor topping shall be 25mm.
Preparation of base concrete/structural slab before laying the topping shall be as
mentioned above. The surface shall be rough to provide adequate bond for the topping.
Mixing of concrete shall be done thoroughly in a mechanical mixer unless hand mixing is
specifically permitted by the GWIL. The concrete shall be as stiff as possible and the
amount of water added shall be the minimum necessary to give just sufficient plasticity for
laying and compacting. The mix shall be used in the work within 30 minutes of the addition
of water for its preparation.
Floor finish shall be laid in suitable panels to reduce the risk of cracking. No dimension of a
panel shall exceed 2 meters and the length of a panel shall not exceed one and a half
times its breadth. Topping shall be laid in alternate panels, the intermediate panels being
cast after a gap of at least one day. Construction joints shall be plain vertical butt joints.
Screed strips shall be fixed dividing the area into suitable panels. Immediately before
depositing the concrete topping, neat cement slurry at 2.75 kg/m2of area shall be
thoroughly brushed into the prepared surface. Topping shall then be laid, very thoroughly
tamped, struck off level and floated with wooden float. The surface shall then be tested
with a straight edge and mason's spirit level to detect any inequalities and these shall be
made good immediately.
Finishing of the surface by Trowelling shall be spread over a period of one to six hours
depending upon the temperature and atmospheric conditions. The surface shall be
trowelled 3 times at intervals so as to produce a smooth uniform and hard surface.
Immediately after laying, the first Trowelling just sufficient to give a level surface shall be
carried out avoiding excessive Troweling at this stage.
The surface shall be re- trowelled after sometime to close any pores and to scrap off
excess water or laitance, which shall not be trowelled back into the topping. Final
Trowelling shall be done well before the concrete has become too hard but at a time when
considerable pressure is required to make any impression on the surface. Sprinkling of dry
cement or cement-sand mixture for absorbing moisture shall not be permitted.
Immediately after the surface is finished, it shall be protected suitably from rapid drying
due to wind/ sunlight. After the surface has hardened sufficiently to prevent any damage
to it, the topping shall be kept continuously moist for a minimum period of 10 days.
It is preferable to lay the topping on hardened base concrete, as against being laid
monolithically with a lesser thickness, since proper levels and slopes with close surface
tolerances is achievable in practice, owing to its greater thickness. Further, as this would
be laid after all other building operations are over, there will be no risk of any damages or
discolorations to the floor finish which are difficult to repair satisfactorily.
In-Situ Granolithic Concrete Floor Topping:
Materials and Workmanship:
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
The Requirements of materials and workmanship shall be all as mentioned above for in-situ
cement concrete floor topping except that the mix proportion of the concrete shall be
1:1:2 (cement: sand: coarse aggregates) by volume.
The minimum thickness of granolithic floor topping on hardened concrete base shall be
Floor Hardener Topping:
Materials & Workmanship:
Floor Hardener topping shall be provided either as integrally finished over the structural
slab/grade slab or lay monolithically with the concrete/granolithic floor finish on top of
hardened concrete base.
Floor hardener of the metallic or non-metallic type suitable for the performance of normal
/ medium/ heavy duty function of the floor, the quantum of ingredients and the thickness
of topping shall be as specified in the respective items of work prepared by the Contractor.
For monolithic application with the floor finish/slab the thickness of the layer shall be
15mm. The topping shall be laid within 2 to 3 hours after concrete is laid when it is still
plastic but stiffened enough for the workmen to tread over it by placing planks.
The surface of the concrete layer shall be kept rough for providing adequate bond for the
topping. Laitance shall be removed before placing the topping. The topping shall be
screened and thoroughly compacted to the finished level. Trowelling to a smooth finish
shall be carried out. After the surface has hardened sufficiently, it shall be kept
continuously moist for at least 10 days. The procedure for mixing the floor hardener
topping shall be as per manufacturer's instructions.
Surface shall be prevented from any damages due to subsequent building operations by
covering with 75 mm thick layer of sand.
PVC Sheet/Tile Flooring:
PVC floor covering shall be of either unbaked homogeneous flexible type in the form of
sheets/tiles conforming to IS:3462 or homogeneous PVC asbestos tiles conforming to
IS:3461. Surface of the sheets/tiles shall be free from any physical defects such as pores,
blisters, cracks etc. which affects the appearance and serviceability. Tiles/ sheets shall
meet with the tolerance limits in dimensions specified in the IS. Contractor shall submit
the test certificates, if so desired by the GWIL.
Each tile/sheet shall be legibly and indelibly marked with the name of the manufacturer or
his trade mark, IS certificate mark, and batch number.
The adhesive to be used for laying the PVC flooring shall be rubber based and of the make
as recommended and approved by the manufacturer of PVC sheets/tiles.
The type, size, colour, plain or mottled and the pattern shall be as specified in the
respective items of work prepared by the Contractor.
PVC Floor covering shall be provided over an under bed of cement concrete floor finish
over the base concrete or structural slab. It is essential that the sub-floor and the under
bed are perfectly dry before laying the PVC flooring. This shall be ensured by methods of
testing as stipulated in Appendix-A of IS:5318.
The surface of the underbed shall have trowelled finish without any irregularities, which
creates poor adhesion. Surface shall be free of oil or grease and thoroughly cleaned of all
dust, dirt and wiped with a dry cloth.
PVC sheets/tiles shall be brought to the temperature of the area in which they are to be
laid by stacking in a suitable manner within or near the laying area for a period of about
hours. Where air-conditioning is installed, the flooring shall not be laid on the underbed
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
until the A/C units have been in operation for at least 7 days. During this period, the
temperature range shall be between 20deg.C and 30deg.C and this shall be maintained
during the laying operations and also for 48 hours thereafter.
Layout of the PVC flooring shall be marked with guidelines on the underbed and PVC
tiles/sheets shall be first laid for trial, without using the adhesive, according to the layout.
The adhesive shall be applied by using a notched trowel to the surface of the underbed and
to the backside of PVC sheets/tiles. When the adhesive has set sufficiently for laying, it
will be tacky to the touch, which generally takes about 30 minutes. The time period need
be carefully monitored since a longer interval will affect the adhesive properties. Adhesive
shall be uniformly spread over only as much surface area at one time which can be covered
with PVC flooring within the stipulated time.
PVC sheet shall be carefully taken and placed in position from one end onwards slowly so
that the air will be completely squeezed out between the sheet and the background
surface and no air pockets are formed. It shall then be pressed with a suitable roller to
develop proper contact. The next sheet shall be laid edge to edge with the sheet already
laid, so that there is minimum gap between joints. The alignment shall be checked after
each row of sheet is completed and trimmed if considered necessary.
Tiles shall be laid in the same manner as sheets and preferably, commencing from the
center of the area. Tiles should be lowered in position and pressed firmly on to the
adhesive with minimum gap between the joints. Tiles shall not be slide on the surface.
Tiles shall be rolled with a light wooden roller of about 5kg to ensure full contact with the
underlay. Work should be constantly checked to ensure that all four edges of adjacent tiles
meet accurately.
Any excess adhesive which may squeeze up between sheets/tiles shall be wiped off
immediately with a wet cloth. Suitable solvents shall be used to remove hardened
A minimum period of 24 hours shall be given after laying for the development of proper
bond of the adhesive. When the flooring is thus completed, it shall be cleaned with a wet
cloth soaked in warm soap solution.
Metallic edge strips shall be used to protect the edges of PVC sheets/tiles which are
exposed as in doorways/ stair treads.
Hot sealing of joints between adjacent PVC sheet flooring to prevent creeping of water
through the joints shall be carried out, using special equipment as per manufacturer's
Acid Resisting Brick/Tiling Work:
The ceramic unglazed vitreous acid resisting tiles shall conform to the requirements of
IS:4457. Acid resistant bricks shall conform to the requirements of IS:4860.
The finished tile/brick when fractured shall appear fine grained in texture, dense and
homogeneous. Tile/brick shall be sound, true to shape, flat, free from flaws and any
manufacturing defects affecting their utility. Tolerance in dimensions shall be within the
limits specified in the respective IS.
The tiles/bricks shall be bedded and jointed using chemical resistant mortar of the resin
type conforming to IS:4832 (Part II). Method of usage shall generally be as per the
requirements of IS:4443.
The resin shall have viscosity for readily mixing with the filler by manual methods.
The filler shall have graded particles which permit joint thickness of 1.5 mm.
The base concrete surface shall be free from dirt and thoroughly dried. The surface shall
be applied with a coat of bitumen primer conforming to IS:3384. The primed surface shall
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
then be applied with a uniform coat of bitumen conforming to IS:1580. Tiles or bricks shall
be laid directly without the application of bitumen, if epoxy or polyester resin is used for
the mortar. Just adequate quantity of mortar which can be applied within the pot life as
specified by the manufacturer shall be prepared at one time for bedding and jointing. Rigid
PVC/Stainless steel/chromium plated tools shall be used for mixing and laying. For laying
the floor 6 to 8 mm thick mortar shall be spread on the back of the tile/brick. Two
adjacent sides of the tile/brick shall be smeared with 4 to 6 mm thick mortar. Tile/brick
shall be pressed into the bed and pushed against the floor and with the adjacent tile/
brick, until the joint in each case is 2 to 3 mm thick. Excess mortar shall then be trimmed
off and allowed to harden fully. Similar procedure shall be adopted for the work on walls
by pressing the tile/brick against the prepared wall surfaces and only one course shall be
laid at a time until the initial setting period.
The mortar joints shall be cured for a minimum period of 72 hours with 20 to 25%
hydrochloric acid or 30 to 40% sulphuric acid. After acid curing, the joints shall be washed
with water and allowed to thoroughly dry. The joints shall then be filled with mortar to
make them smooth and plane. Acid curing is not required to be carried out if epoxy or
polyester resin is used for the mortar.
Resin mortars are normally self-curing. The area tiled shall not be put to use before
hours in case epoxy, polyester and furan type of resin is used for the mortar. If phenolic or
cashew nut shell liquid resin is used for the mortar, the area tiled shall not be put to use
for 7 to 28 days respectively, without heat treatment. This period shall be 2 to 6 days
respectively, if heat treatment is given with infrared lamp.
Epoxy Lining Work:
The epoxy resin and hardener formulation for laying of joint less lining work in floors and
walls of concrete tanks/trenches etc shall be as per the requirements of IS:9197.
The epoxy composition shall have the chemical resistance to withstand the following
conditions of exposure:
Hydrochloric acid up to 30% concentration
Sodium hydroxide up to 50% concentration
Liquid temperature up to 60deg.C
Ultraviolet radiation
Alternate wetting and drying
Sand shall conform to grading zone III or IV of IS:383.
The hardener shall be of the liquid type such as Aliphatic Amine or an Aliphatic/Aromatic
Amine Adduct for the epoxy resin. The hardener shall react with epoxy resin at normal
ambient temperature.
Contractor shall furnish test certificates for satisfying the requirements of the epoxy
formulation if so directed by the GWIL.
The minimum thickness of epoxy lining shall be 4 mm. It is essential that the concrete
elements are adequately designed to ensure that water is excluded to permeate to the
surface, over which the epoxy lining is proposed. The epoxy lining shall be of the trowel
type to facilitate execution of the required thickness for satisfactory performance.
The concrete surfaces over which epoxy lining is to be provided shall be thoroughly
cleaned of oil or grease by suitable solvents, wire brushed to remove any dirt/dust and
laitance. The surfaces shall then be washed with dilute hydrochloric acid and rinsed
thoroughly with plenty of water or dilute ammonia solution. The surfaces shall then be
allowed to dry. It is essential to ensure that the surfaces are perfectly dry before the
commencement of epoxy application. Just adequate quantity of epoxy resin which can be
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
applied within the pot life as specified by the manufacturer shall be prepared at one time
for laying and jointing. Rigid PVC/stainless steel/chromium plated tools shall be used for
laying. Trowelling shall be carried out to obtain uniformly the specified thickness of lining.
Lining shall be allowed to set without disturbance for a minimum period of 24 hours. The
facility shall be put to use only after a minimum period of 7 days of laying of the lining.
Water-Proofing:
The work shall include waterproofing for the building roofs, terraces, toilets, floor slabs,
walls, planters, chhajjas, sills and any other areas and at any other locations and situations
as directed by the Employers Representative.
The waterproofing treatment shall be carried out on top of lime concrete (brick bat coba)
laid to slope on roof surfaces. The brick bat-coba shall be covered as specified below.
The work shall be carried out by an experienced specialist Sub-Contractor who shall be
appointed only after prior approval of the GWIL.
Modified Bituminous Membrane:
Modified Bituminous Membrane shall be “SUPER THERMOLAY” 4 mm thick weighing
Kg/sq.m, manufactured using APP Polymer modified bitumen with a central core of non-
woven polyester reinforcement (200 gms/sqm) and with top and bottom layers of thermo
fusible film (top layer could also be sand finished) made by STP Limited in collaboration
with Bitumen Company Limited. “PLYFLEX” of Bitumen Company Limited, Saudi Arabia
supplied by STP Limited shall also be acceptable or other equivalent specification.
Waterproofing of Roofs with Lime Concrete:
Broken brick coarse aggregates prepared from well/over burnt bricks shall be well graded
having a maximum size of 25mm and shall generally conform to IS:3068.
Lime shall be class C lime (fat lime) or factory-made hydrated lime conforming to IS:712.
Lime concrete shall be prepared by thoroughly mixing the brick aggregates inclusive of
brick dust obtained during breaking with the slaked lime in the proportions of 2 1/2 (two
and a half) parts of brick aggregates to 1 part of slaked lime by volume. Water shall be
added just adequate to obtain the desired workability for laying. Washing soap and alum
shall be dissolved in the water to be used. The quantity of these materials required per
cum of lime concrete shall be 12kg of washing soap and 4kg of alum. Brick aggregates shall
be soaked thoroughly in water for a period of not less than six hours before use in the
concrete mix. Lime concrete shall be used in the works within 24 hours after mixing.
The roof surface over which the water-proof treatment is to be carried out shall be
cleaned of all foreign matter by wire brushing, dusting and made thoroughly dry.
Preparation of surfaces shall be as stipulated in IS:3067.
The slope of the finished waterproofing treatment shall be not less than 1 in 60 for
efficient drainage. This shall be achieved either wholly in the lime concrete layer.
The average thickness of lime concrete, slope and the finish on top of machine-made burnt
clay flat terracing tiles conforming to IS:2690 (part I) shall be as specified in the items of
work to be prepared by the Contractor. Cement concrete flooring tiles in lieu of clay
terracing tiles shall be provided if so specified in the items of work prepared by the
Contractor, duly considering the traffic the terrace will be subjected to.
The minimum compacted thickness of lime concrete layer shall be 75mm and average
thickness shall not be less than 100mm. In case, the thickness is more than 100mm, it shall
be laid in layers not exceeding 100mm to 125mm. Laying of lime concrete shall be
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
commenced from a corner of the roof and proceeded diagonally towards center and other
sides duly considering the slopes specified for effectively draining the rain-water towards
the downtake points. Lime concrete fillet for a minimum height of 150mm shall be
provided all along the junction of the roof surface with the brick masonry
wall/parapet/column projections. These shall then be finished on top with provision of
clay terracing tiles/cement concrete tiles.
After the lime concrete is laid it shall be initially rammed with a rammer weighing not
more than 2 Kg and the finish brought to the required evenness and slope. Alternatively,
bamboo strips may be used for the initial ramming. Further consolidation shall be done
using wooden THAPIES with rounded edges. The beating will normally have to be carried on
for at least seven days until the THAPI makes no impression on the surface and rebounds
readily from it when struck. Special care shall be taken to properly compact the lime
concrete at its junction with parapet walls or column projections. During compaction by
hand-beating, the surface shall be sprinkled liberally with lime water (1 part of lime putty
and 3 to 4 parts of water) and a small proportion of sugar solution for obtaining improved
water-proofing quality of the lime concrete.
On completion of beating, the mortar that comes on the top shall be smoothened with a
trowel or float, if necessary, with the addition of sugar solution and lime putty.
The sugar solution may be prepared in any one of the following ways as directed by the
By mixing about 3 Kg of Jaggery and 1.5 Kg of BAEL fruit to 100 liters of water.
By mixing about 600 gm of KADUKAI (the dry nuts shall be broken to small pieces and
allowed to soak in water), 200 gm of jaggery and 40 liters of water for 10 sq.m of work.
This solution shall be brewed for about 12 to 24 hours and the resulting liquor decanted
and used for the work.
The lime concrete after compaction shall be cured for a minimum period of seven days or
until it hardens by covering with a thin layer of straw or hessian which shall be kept wet
continuously. Machine made flat terracing tiles shall be of the size and thickness as
specified. Tiles shall be soaked in water for at least one hour before laying. Bedding for
the tiles shall be 12mm thick in cement mortar 1:3. Tiles shall be laid, open jointed with
to 6 mm wide joints, flat on the mortar and lightly pressed and set to plane surface true to
slope, using a trowel and wooden straight edge. They shall be laid with their longitudinal
lines of joints truly parallel and generally at right angles to the direction of run-off
gradient. Transverse joints in alternate rows shall come directly in line with each other.
Transverse joints in adjacent courses shall break joints by at least 50 mm. The joints shall
be completely filled and flush pointed with cement mortar 1:2 mixed with water proofing
compound as per manufacturer's instructions. Curing shall be carried out for a minimum
period of seven days. Finishing on top with cement concrete tiles or in-situ cement
concrete floor topping shall be carried out in similar fashion as described for clay tiles in
above paragraph. Tiles to be used shall be supplied after the first machine grinding of the
Waterproofing of Roofs/Terraces etc.:
(A) Water proofing of Horizontal Surfaces:
The waterproofing shall be applied as follows:
A coat of Blown Bitumen 85/25 shall be applied at the rate of 1.45 kg/sq.km
A roll of Modified Bituminous Membrane shall be unrolled over the primed surface and
completely bonded to the substrate by pressing down evenly for the full width of the roll
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
using a wooden roller. Torching shall be done, where recommended by the manufacturer
and where directed by the GWIL, as the unrolling progresses.
The side overlaps shall be minimum 100 mm whereas the end overlaps shall be minimum
150 mm; both shall be bonded and sealed by flame torching. Care shall be taken that the
membrane is lapped with the treatment along the vertical surface and roof gutter
treatment for at least 500 mm. The membrane shall be properly overlapped/terminated at
all openings, rainwater down takes etc. to ensure that such junctions do not become
sources of leakage.
Top of membrane finally shall be painted with anti-glare reflective paint.
(B) Waterproofing of Vertical Surfaces at Roof Level and Gutters:
The Water proofing shall be applied as described in (a) above.
Modified Bituminous membrane shall be unrolled and bonded to the substrate after
applying a coat of bitumen and by pressing down evenly for the full width of the roll. Light
torching shall be done to ensure complete bonding.
The membrane shall be overlapped with treatment for the horizontal surface by at least
The membrane shall be taken up to a pre-cut chase anchored and sealed.
Khurras and Rainwater down Pipes:
Down pipes shall be isolated from RCC work with 6 mm polyethylene foam fixed with
adhesive (Araldite) and sealed with silicone sealant prior to laying membrane. A water
proofing flashing composed of one layer of Hessian based self-finished felt Type 3 Grade
and two layers of aluminum foil of 0.075 mm thickness shall be provided. This flashing shall
be carried into the down take pipes for at least 150 mm and sealed with hot bitumen. The
Contractor shall closely coordinate the work with the agency providing and fixing the
rainwater down take pipes.
The treated area (flat and horizontal only) shall be tested by allowed water to stand on
the treated areas to a depth of 150 mm for a minimum period of 72 hours.
The treated area (flat and horizontal) shall have continuous slope towards the rainwater
outlets and no water shall pond anywhere on the surface.
Cement Plastering Work:
The proportions of the cement mortar for plastering shall be 1:3 (one part of cement to
three parts of sand). Cement and sand shall be mixed thoroughly in dry condition and then
just enough water added to obtain a workable consistency. The quality of water and
cement shall be as per relevant IS standards. The quality and grading of sand for plastering
shall conform to IS:1542. The mixing shall be done thoroughly in a mechanical mixer unless
hand mixing is specifically permitted by the GWIL. If so desired by the GWIL sand shall be
screened and washed to meet the Specifications. The mortar thus mixed shall be used as
soon as possible preferably within 30 minutes from the time water is added to cement. In
case the mortar has stiffened due to evaporation of water this may be re- tempered by
adding water as required to restore consistency but this will be permitted only up to
minutes from the time of initial mixing of water to cement. Any mortar which is partially
set shall be rejected and removed forthwith from the site. Droppings of plaster shall not
be re-used under any circumstances.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
Preparation of surfaces and application of plaster finishes shall generally conform to the
requirements specified in IS:1661 and IS:2402.
Plastering operations shall not be commenced until installation of all fittings and fixtures
such as door/window panels, pipes, conduits etc. are completed.
All joints in masonry shall be raked as the work proceeds to a depth of 10mm/20mm for
brick/stone masonry respectively with a tool made for the purpose when the mortar is still
green. The masonry surface to be rendered shall be washed with clean water to remove all
dirt, loose materials, etc., Concrete surfaces to be rendered shall be roughened suitably by
hacking or bush hammering for proper adhesion of plaster and the surface shall be evenly
wetted to provide the correct suction. The masonry surfaces should not be too wet but
only damp at the time of plastering. The dampness shall be uniform to get uniform bond
between the plaster and the masonry surface.
Interior plain faced plaster - This plaster shall be laid in a single coat of 13mm thickness.
The mortar shall be dashed against the prepared surface with a trowel. The dashing of the
coat shall be done using a strong whipping motion at right angles to the face of the wall or
it may be applied with a plaster machine. The coat shall be trowelled hard and tight
forcing it to surface depressions to obtain a permanent bond and finished to smooth
surface. Interior plaster shall be carried out on jambs, lintel and sill faces etc. as shown in
the drawing and as directed by the GWIL.
Plain Faced Ceiling plaster - This plaster shall be applied in a single coat of 6mm
thickness. Application of mortar shall be as stipulated in above paragraph.
Exterior plain faced plaster - This plaster shall be applied in 2 coats. The first coat or the
rendering coat shall be approximately 14mm thick. The rendering coat shall be applied as
stipulated above except finishing it to a true and even surface and then lightly roughened
by cross scratch lines to provide bond for the finishing coat. The rendering coat shall be
cured for at least two days and then allowed to dry. The second coat or finishing coat shall
be 6 mm thick. Before application of the second coat, the rendering coat shall be evenly
damped. The second coat shall be applied from top to bottom in one operation without
joints and shall be finished leaving an even and uniform surface. The mortar proportions
for the coats shall be as specified in the respective item of work. The finished plastering
work shall be cured for at least 7 days.
Interior plain faced plaster 20mm thick if specified for uneven faces of brick walls or for
random/coursed rubble masonry walls shall be executed in 2 coats similar to the procedure
stipulated in above paragraph.
Exterior Sand Faced Plaster - This plaster shall be applied in 2 coats. The first coat shall
be approximately 14mm thick and the second coat shall be 6mm thick. These coats shall be
applied as stipulated above. However, only approved quality white sand shall be used for
the second coat and for the finishing work. Sand for the finishing work shall be coarse and
of even size and shall be dashed against the surface and sponged. The mortar proportions
for the first and second coats shall be as specified in the respective items of work.
Wherever more than 20mm thick plaster has been specified, which is intended for purposes
of providing beading, bands, etc. this work shall be carried out in two or three coats as
directed by the GWIL duly satisfying the requirements of curing each coat
(rendering/floating) for a minimum period of 2 days and curing the finished work for at
In the case of pebble faced finish plaster, pebbles of approved size and quality shall be
dashed against the final coat while it is still green to obtain as far as possible a uniform
pattern all as directed by the GWIL.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
Where specified in the Drawings to be prepared by the Contractor prepared by the
Contractor, rectangular grooves of the dimensions indicated shall be provided in external
plaster by means of timber battens when the plaster is still in green condition. Battens
shall be carefully removed after the initial set of plaster and the broken edges and corners
made good. All grooves shall be uniform in width and depth and shall be true to the lines
and levels as per the Drawings to be prepared by the Contractor prepared by the
Curing of plaster shall be started as soon as the applied plaster has hardened sufficiently so
as not to be damaged when watered. Curing shall be done by continuously applying water
in a fine spray and shall be carried out for at least 7 days.
For waterproofing plaster, the Contractor shall provide the water-proofing admixture as
specified in manufacturer’s instruction while preparing the cement mortar.
For external plaster, the plastering operations shall be commenced from the top floor and
carried downwards. For internal plaster, the plastering operations for the walls shall
commence at the top and carried downwards. Plastering shall be carried out to the full
length of the wall or to natural breaking points like doors/windows etc. Ceiling plaster
shall be completed first before commencing wall plastering.
Double scaffolding to be used shall be as specified.
The finished plaster surface shall not show any deviation more than 4mm when checked
with a straight edge of 2m length placed against the surface.
To overcome the possibility of development of cracks in the plastering work following
measures shall be adopted.
Plastering work shall be deferred as much as possible so that fairly complete drying
shrinkage in concrete and masonry works takes place.
Steel wire fabric shall be provided at the junction of brick masonry and concrete to
overcome reasonably the differential drying shrinkage/thermal movement.
Ceiling plaster shall be done, with a trowel cut at its junction with wall plaster. Similarly
trowel cut shall be adopted between adjacent surfaces where discontinuity of the
background exists.
Cement Pointing:
The cement mortar for pointing shall be in the proportion of 1:3 (one part of cement to
three parts of fine sand). Sand shall conform to IS: 1542 and shall be free from clay, shale,
loam, alkali and organic matter and shall be of sound, hard, clean and durable particles.
Sand shall be approved by GWIL and if so directed it shall be washed/screened to meet
specification requirements.
Where pointing of joints in masonry work is specified, the joints shall be raked at least
15mm/20mm deep in brick/stone masonry respectively as the work proceeds when the
mortar is still green.
Any dust/dirt in the raked joints shall be brushed out clean and the joints shall be washed
with water. The joints shall be damp at the time of pointing. Mortar shall be filled into
joints and well pressed with special steel trowels. The joints shall not be disturbed after it
has once begun to set. The joints of the pointed work shall be neat. The lines shall be
regular and uniform in breadth and the joints shall be raised, flat, sunk or 'V' as may be
specified in the respective items of work. No false joints shall be allowed.
The work shall be kept moist for at least 7 days after the pointing is completed. Whenever
colored pointing has to be done, the coloring pigment of the color required shall be added
to cement in such proportions as recommended by the manufacturer and as approved by
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
Water-Proofing Admixtures;
Water-proofing admixture shall conform to the requirements of IS:2645 and shall be of
approved manufacture. The admixture shall not contain calcium chloride. The quantity of
the admixture to be used for the works and method of mixing etc. shall be as per
manufacturer's instructions and as directed by the GWIL.
Painting of Concrete, Masonry & Plastered Surfaces:
Oil bound distemper shall conform to IS:428. The primer shall be alkali resistant primer of
the same manufacture as that of the distemper.
Cement paint shall conform to IS:5410. The primer shall be a thinned coat of cement paint.
Lead free acid, alkali and chlorine resisting paint shall conform to IS:9862.
Color wash shall be made by addition of a suitable quantity of mineral pigment, not
affected by lime, to the prepared white wash to obtain the shade/tint as approved by the
All the materials shall be of the best quality from an approved manufacturer. Contractor
shall obtain prior approval of the GWIL for the brand of manufacture and the color/shade.
All materials shall be brought to the site of works in sealed containers.
Contractor shall obtain the approval of the GWIL regarding the readiness of the surfaces to
receive the specified finish, before commencing the work on painting. Painting of new
surfaces shall be deferred as much as possible to allow for thorough drying of the sub-
The surfaces to be treated shall be prepared by thoroughly brushing them free from dirt,
mortar droppings and any loose foreign materials. Surfaces shall be free from oil, grease
and efflorescence. Efflorescence shall be removed only by dry brushing of the growth.
Cracks shall be filled with Gypsum. Workmanship of painting shall generally conform to
IS:2395. Surfaces of doors, windows etc. shall be protected suitably to prevent paint
finishes from splashing on them.
The prepared surfaces shall be wetted and the finish applied by brushing. The operation
for each coat shall consist of a stroke of the brush first given horizontally from the right
and the other from the left and similarly, the subsequent stroke from bottom upwards and
the other from top downwards, before the first coat dries. Each coat shall be allowed to
dry before the next coat is applied. Minimum of 2 coats shall be applied unless otherwise
specified. The dry surface shall present a uniform finish without any brush marks.
Color wash shall be applied in the same way as for white wash. A minimum of 2 coats shall
be applied unless otherwise specified. The surface shall present a smooth and uniform
finish without any streaks. The finished dry surface shall not show any signs of
peeling/powdery and come off readily on the hand when rubbed.
The prepared surfaces shall be wetted to control surface suction and to provide moisture
to aid in proper curing of the paint. Cement paint shall be applied with a brush with stiff
bristles. The primer coat shall be a thinned coat of cement paint. The quantity of thinner
shall be as per manufacturer's instructions. The coats shall be vigorously scrubbed to work
the paint into any voids for providing a continuous paint film free from pinholes for
effective water proofing in addition to decoration. Cement paint shall be brushed in
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
uniform thickness and the covering capacity for two coats on plastered surfaces shall be
to 4 kg/m2. A minimum of 2 coats of the same color shall be applied. At least 24 hours
shall be left after the first coat to become sufficiently hard before the second coat is
applied. The painted surfaces shall be thoroughly cured by sprinkling with water using a
fog spray at least 2 to 3 times a day. Curing shall commence after about 12 hours when the
paint hardens. Curing shall be continued for at least 2 days after the application of final
coat. The operations for brushing each coat shall be as detailed above.
Oil bound Distemper:
The prepared surfaces shall be dry and provided with one coat of alkali resistant primer by
brushing. The surface shall be finished uniformly without leaving any brush marks and
allowed to dry for at least 48 hours.
A minimum of two coats of oil bound distemper shall be applied, unless otherwise
specified. The first coat shall be of a lighter tint. At least 24 hours shall be left after the
first coat to become completely dry before the application of the second coat. Broad, stiff,
double bristled distemper brushes shall be used for the work. The operations for brushing
each coat shall be as detailed above.
Acid, Alkali Resisting Paint:
A minimum of 2 coats of acid/alkali resisting paint shall be applied over the prepared dry
surfaces by brushing. Primer coat shall be as per manufacturer's instructions.
Plastic Emulsion Paint:
The prepared surface shall be dry and provided with one coat of primer which shall be a
thinned coat of emulsion paint. The quantity of thinner shall be as per manufacturer's
instructions. The paint shall be laid on evenly and smoothly by means of crossing and laying
off. The crossing and laying off consists of covering the area with paint, brushing the
surface hard for the first time over and then brushing alternately in opposite directions
two or three times and then finally brushing lightly in a direction at right angles. In this
process, no brush marks shall be left after the laying off is finished. The full process of
crossing and laying off constitutes one coat. The next coat shall be applied only after the
first coat has dried and sufficiently become hard which normally takes about 2 to 3 hours.
A minimum of 2 finishing coats of the same color shall be applied unless otherwise
specified. Paint may also be applied using rollers. The surface on finishing shall present a
flat velvety smooth finish and uniform in shade without any patches.
Acrylic Emulsion Paint:
Acrylic emulsion paint shall be applied in the same way as for plastic emulsion paint. A
minimum of 2 finishing coats over one coat of primer shall be provided unless otherwise
Painting & Polishing of Wood Work:
Wood primer shall conform to IS:3536.
Filler shall conform to IS:110.
Varnish shall conform to IS:337.
French polish shall conform to IS:348.
Synthetic enamel paint shall conform to IS:2932.
All the materials shall be of the best quality from an approved manufacturer. Contractor
shall obtain prior approval of the GWIL for the brand of manufacture and the color/shade.
All materials shall be brought to the site of works in sealed containers.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
The type of finish to be provided for woodwork of painting or polishing, the number of
coats, etc. shall be as specified in the respective items of work to be prepared by the
Contractor. Primer and finish paint shall be compatible with each other to avoid cracking
and wrinkling. Primer and finish paint shall be from the same manufacturer. Painting shall
be either by brushing or spraying. Contractor shall procure the appropriate quality of paint
for this purpose as recommended by the manufacturer.
The workmanship shall generally conform to the requirements of IS:2338 (Part I). All the
wood surfaces to be painted shall be thoroughly dry and free from any foreign matter.
Surfaces shall be smoothened with abrasive paper using it across the grains and dusted off.
Wood primer coat shall then be applied uniformly by brushing. The number of primer coats
shall be as specified in the item of work to be prepared by the Contractor. Any slight
irregularities of the surface shall then be made- up by applying an optimum coat of filler
conforming to IS:110 and rubbed down with an abrasive paper for obtaining a smooth
surface for the undercoat of synthetic enamel paint conforming to IS:2932. Paint shall be
applied by brushing evenly and smoothly by means of crossing and laying off in the
direction of the grain of wood. After drying, the coat shall be carefully rubbed down using
very fine grade of sand paper and wiped clean before the next coat is applied. At least
hours shall elapse between the applications of successive coats. Each coat shall vary
slightly in shade and this shall be got approved by the GWIL. The number of coats of paint
to be applied shall be as specified in the item of work to be prepared by the Contractor.
All the wood surfaces to be provided with clear finishes shall be thoroughly dry and free
from any foreign matter. Surfaces shall be smoothened with abrasive paper using it in the
direction of the grains and dusted off. Any slight irregularities of the surface shall be made
up by applying an optimum coat of transparent liquid filler and rubbed down with an
abrasive paper for obtaining a smooth surface. All dust and dirt shall be thoroughly
removed. Over this prepared surface, varnish conforming to IS:337 shall be applied by
brushing. Varnish should not be retouched once it has begun to set. Staining if required
shall be provided as directed by the GWIL. When two coats of varnish are specified, the
first coat should be a hard-drying undercoat or flatting varnish which shall be allowed to
dry hard before applying the finishing coat. The number of coats to be applied shall be as
specified. For works where clear finish of French polish is specified the prepared surfaces
of wood shall be applied with the polish using a pad of woolen cloth covered by a fine
cloth. The pad shall be moistened with polish and rubbed hard on the surface in a series of
overlapping circles to give an even finish over the entire area. The surface shall be allowed
to dry before applying the next coat. Finishing shall be carried out using a fresh clean cloth
over the pad, slight dampening with methylated spirit and rubbing lightly and quickly in
circular motions. The finished surface shall have a uniform texture and high gloss. The
number of coats to be applied shall be as specified.
Painting of Steel Work:
Red-oxide – zinc chrome primer shall conform to IS:2074.
Synthetic enamel paint shall conform to IS:
Aluminum paint shall conform to IS:2339.
All the materials shall be of the best quality from an approved manufacturer. Contractor
shall obtain prior approval of the GWIL for the brand of manufacture and the color/shade.
All the materials shall be brought to the site in sealed containers.
Painting work shall be carried out only on thoroughly dry surfaces. Painting shall be applied
either by brushing or by spraying. Contractor shall procure the appropriate quality of paint
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
for this purpose as recommended by the manufacturer. The workmanship shall generally
conform to the requirement of IS:1477 (Part 2).
The type of paint, number of costs etc. shall be as specified in the respective items of
work. Primer and finish paint shall be compatible with each other to avoid cracking and
wrinkling. Primer and finish paint shall be from the same manufacturer. All the surfaces
shall be thoroughly cleaned of oil, grease, dirt, rust and scale. The methods to be adopted
using solvents, wire brushing, power tool cleaning etc., shall be as per IS:1477 (Part – I)
and as indicated in the item of work. It is essential to ensure that immediately after
preparation of the surfaces; the first coat of red oxide-zinc chrome primer shall be applied
by brushing and working it well to ensure a continuous film without holidays. After the first
coat becomes hard dry, a second coat of primer shall be applied by brushing to obtain a
film free from `holidays. After the second coat of primer is hard dry, the entire surface
shall be wet rubbed cutting down to a smooth uniform surface. When the surface becomes
dry, the undercoat of synthetic enamel paint of optimum thickness shall be applied by
brushing with minimum of brush marks. The coat shall be allowed to hard-dry. The under
coat shall then be wet rubbed cutting down to a smooth finish, taking adequate care to
ensure that at no place the undercoat is completely removed. The surface shall then be
allowed to dry. The first finishing coat of paint shall be applied by brushing and allowed to
hard-dry. The gloss from the entire surface shall then be gently removed and the surface
dusted off. The second finishing coat shall then be applied by brushing. At least 24 hours
shall elapse between the applications of successive coats. Each coat shall vary slightly in
shade and this shall be got approved by the GWIL.
Anodized Aluminum sheets shall be 1.00mm thick with anodic film thickness of 0.025 mm.
Galvanized mild steel sheets shall be 1.00mm thick with zinc coating of 800 gms/sq.m.
Bitumen felt shall be either Hessian base self finished bitumen felt Type-3 Grade I
conforming to IS:1322 or glass fiber base self finished felt Type-2 Grade 1 conforming to
The type of the flashing and method of fixing shall be as specified.
Flashing shall be of the correct shape and size as indicated in the construction Drawings to
be prepared by the Contractor and they shall be properly fixed to ensure their
Flashing shall be of long lengths so as to provide minimum number of joints. The minimum
overlap at joints shall be 100mm.
Fixing of the flashing shall be either by bolting with bitumen washers or by tucking into the
groove 75 mm wide x 65 mm deep in masonry/concrete along with cement mortar 1:4
filleting as indicated in the Drawings to be prepared by the Contractor. Curing of the
mortar shall be carried out for a minimum period of 4 days.
Bitumen felt flashing of the type as specified shall be provided with 2 coats of bituminous
paint at the rate of 0.10 liter/m2after the installation.
Thermal Insulation for Ceiling
Thermal insulation shall be “Thermocole” TF type or similar approved or Resin bonded
fiber glass boards.
“Thermocole” Boards:
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
Soffit of RCC Slab shall be thoroughly cleaned with wire brush and 85/25 industrial grade
hot bitumen conforming to IS:702 shall be applied uniformly over the surface at the rate of
Thermocole boards (T.F. variety) of 50mm thickness shall be stuck by means of the same
grade of hot bitumen. The boards shall be further secured with screws, washers and plugs.
The joints of the boards shall be sealed with bitumen.
Fiber Glass Boards:
Timber pegs 50mm x 50mm x 50mm shall be fixed to the slab at 600mm centers with 6mm
x 65mm long wood screws. 20-gauge G.I. lacing wire shall be tied to the pegs `Crown’
fiberglass boards 50mm thick shall be stuck to the pegs with CPRX compound or any other
suitable adhesive and be held in position by the 20-gauge G.I. lacing wires. The insulation
boards shall be covered with 20mm – 24-gauge hexagonal G.I. chicken wire mesh, nailed to
the timber pegs and 30-gauge aluminum sheets shall be fixed over the chicken wire mesh
with 50mm overlap and secured to the timer pegs by screws. If the insulation is specified
to rest on top of the false ceiling, it shall be properly installed and anchored to the
framework. In case additional battens are required for proper installation, Contractor shall
include its cost in the rate for insulation.
Plaster of Paris Board for False Ceiling:
Plaster of Paris Boards:
The plaster of Paris boards to be used in the false ceiling shall be of an approved
manufacture or manufactured at site by methods and materials approved by GWIL.
The plaster of Paris shall be of the calcium-sulphate hemi-hydrate variety and shall contain
not less than 35 percent Sulphur trioxide and other requirements as per IS:2547 (Part I)
However, its fineness shall be such that the residue, after drying, and sieving on I.S. sieve
designation 3.35mm for 5 minutes shall not be more than 1 percent by weight. Initial
setting time shall not be less than 13 minutes. The average compressive strength of plaster
determined by testing 5 cm cubes 24 hours after removal from moulds and drying in an
oven at 40 Deg. C till the weight of the cubes is constant, shall not be less than 84 Kg per
The plaster of Paris boards reinforced with hessian cloth or coir shall be prepared in
suitable sizes as shown on the drawings or as directed by GWSSB. Wooden forms of height
equal to the thickness of boards shall be placed on truly level and smooth surface such as a
glass sheet. The edges of the boards shall be truly square. The glass sheet or surface on
which form is kept and the form sides shall be given a thin coat of non-staining oil to
facilitate the easy removal of the board. Plaster of Paris shall be evenly spread into the
form up to about half the depth and hessian cloth or coir shall be pressed over the plaster
of Paris layer. The weight of hessian cloth or coir in the board shall be 250 gm per sq.m.
The ends of the hessian/coir reinforcement shall be turned over at all edges to form a
double layer for a width of 50mm. The hessian cloth shall be of an open web texture so as
to allow the plaster below and above to intermix with each other and form an integral
board. The form shall then be filled with plaster of Paris which shall be uniform pressed
and then wire cut to an even and smooth surface. The board shall then be allowed to set
initially for an hour or so and then removed from the form and allowed to dry and harden
for about a week. The board after drying and hardening shall give a ringing sound when
struck. The boards shall be true and exact to shape and size and the exposed face shall be
truly plane and smooth.
The size of boards shall generally be 600mm x 600 mm x 12 mm thick. Boards shall be kept
dry in transit and stored flat in a clean dry place and shall not be exposed to moisture. The
boards shall always be carried on edges.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
Timber Frame Work:
Timber for frame work of false ceiling grid and hangers shall be of good quality and well
seasoned. It shall have uniform color, reasonably straight and close grains and shall be free
from knots, cracks and sapwood. It shall be treated with approved anti-termite
preservative as directed by the GWIL. Extreme care shall be taken so that the preservative
treatment does not stain the ceiling boards. In case metal hangers are used, these shall be
M.S. flats or bars, having two coats of red oxide zinc chromate paint primer, as shown on
drawings or as approved by GWIL.
Metal Framework:
The metal frame work may be made of sections of light metal, such as anodized aluminum,
mild steel or as shown on the drawings. The shape of cross-section shall be such as to
facilitate proper suspension and proper fixing of the ceiling boards covering them and shall
be structurally sound and rigid.
The false ceiling grid work shall be carried out as per the approved drawings or as directed
by GWIL. In case of timber grid work, the grid work shall consist of teak wood runners of
minimum size 60mm deep x 40mm wide along one direction at 1.2m centre to centre and
secondary runners of size 50mm deep x 40 mm wide at 60mm centre to centre
perpendicular to the main runners.
The timber grid work shall be suspended with the help of wooden hangers or metal hangers
at 1.2m centre to centre in both the directions. Wooden hangers shall be adopted for flat
R.C. roof slab structures whereas metal hangers for flat R.C. roof or structural steel floors
/ tresses. Metal hangers shall be fabricated from mild steel / galvanized flats of 35mm x
6mm size or bars of 10mm dia. Threaded at the lower end and anchored securely in the
roof concrete or welded to inserts provided on the underside of slabs, beams etc. All M.S.
hangers shall be given two coats of red oxide zinc chromate paint primer. In case the roof
work is of A.C. sheeting supported on purlins and trusses, hangers shall be suspended from
roof steel work. The arrangement of metal hangers shall be such that the level of false
ceiling can be adjusted during fixing of the ceiling frame work. The ceiling frame work
shall be secured to hangers by means of washers and nuts. The ends of main runners shall
preferably be embedded into the masonry work.
The metal frame work when it is anodized aluminum false ceiling grid system shall consist
of aluminum main member of special T-Profile of 38mm x 38mm x 1.5mm thick,
interlocking with each other to form frames of various sizes, 600mm x 600 mm or as shown
on the drawing. The main members shall be suspended from the roof structures by means
of steel hangers as described for timber frame work and supported at the walls by means
of anodized aluminum wall angles.
In the case of timber frame work, all the edges of the plaster of Paris board shall be fixed
to frame members by means of counter sunk and rust less screws of 2.74 mm size, 40mm
long at a spacing of 100mm to 150 mm c/c and 12mm from the edge of the board. Holes
for screws shall be drilled and screws slightly countersunk into the boards. The boards shall
be fixed to wooden framework with a joint clearance of about 3mm. The joints shall
always be in perfect line and plane.
In case of aluminum grid system, boards shall be just placed into the frames formed by the
main `T’ members and the cross members fitted with the clips for locking boards.
Contractor shall take utmost care so as not to force the boards in position and a slight gap
shall be provided so as not to make a tight joint. The boards shall be cut with a saw, if
required, to any shape and size.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
As the work of false ceiling may be inter-connected with the work of air-conditioning ducts
and lighting, Contractor shall fully co-operate with the other agencies entrusted with the
above work, who may be working simultaneously. Contractor shall provide necessary
openings in the false ceiling work for air-conditioning, lighting and other fixtures.
Additional framing, if required, for the above opening shall also be provided at no extra
cost to Employer. Removable or hinged type inspection or access trap doors shall be
provided at locations specified by GWIL.
It is essential that false ceiling work should be firm and in perfect line and level and all
boards free from distortion, bulge, and other defects. All defective boards and other
material shall be removed from site immediately and replaced, and ceiling restored to
original finish to the satisfaction of GWIL. The workmanship shall be of highest order and
all joinery work for timber work shall be in the best workmanship manner. The joints for
aluminum frame work shall be of inter-locking type so that when the cross member is in
place, it cannot be lifted out. The countersunk heads of screws and all joints shall be filled
with plaster of Paris and finished smooth. After filling the joints, a thick skin of the
finishing material shall be spread about 50mm wide on either side of the joint and on to it
shall be trowelled dry a reinforcing scrim cloth about 10mm wide. If metal scrim is used, a
stiffer plaster will be necessary to enable the Troweling the scrim down to the board.
In case of fire protective ceilings, fire resisting barriers at suitable intervals shall be
provided. These shall completely close the gap between the false ceiling and soffit of the
structural slab. The material of the barrier shall be as indicated by GWSSB (Reference may
be made to the British Standards Institutions CP 290: Code of Practice for suspended
ceiling and lining of dry construction using metal fixing system, `for guidance).
False or Cavity Floor;
The false floor shall consist of a framework of suitable structural member designed to carry
the loads specified. This frame work shall be supported on suitably designed stools placed
at 600mm centre to centre in both directions. The stools shall consist of a mild steel base
plate with a mild steel stud having adjustable lock nut and coupling at the centre and
another mild steel plate at top serving as a prop head.
The above framework shall be suitably designed to accommodate 35mm thick, 600mm
square panels. The base plate shall be fixed to the reinforced concrete floor with an
approved adhesive compound or with 4 Nos. 6mm dia. Anchor fasteners. Bedding of 1:2 or
richer cement sand mortar shall be provided locally under the base plates of stools to
provide a level surface.
The prop head shall be provided with mild steel lugs welded on top and each placed
perpendicular to the other for proper positioning and supporting the main and cross
members. The stools shall be capable of adjustment to accommodate concrete floor level
irregularities up to plus or minus 15mm. The framing members shall be completely
removable and shall remain in position without screwing or bolting to the prop heads. All
steel framework including steel stools shall be given a coat of zinc chromate primer and
two coats of enamel paint of approved color and shade.
The floor panels shall be made of 600mm x 600mm x 35 mm thick medium density
unvinegared/ non-prelaminated teak wood particle boards having a density of not more
than 800 kg/cu.m bonded with boiling water proof phenol formaldehyde synthetic resin
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
and shall be of fire resistant, termite resistant and moisture proof quality, generally
conforming to IS:3087-specification for wood particle boards (Medium Density) for general
The thermal conductivity of the boards shall not exceed 0.12 kCal/hr./sq.m/deg./C/m.
The panel size given above may be suitably modified near electrical panel/equipment and
also to suit room dimensions with panel size not more than 600mm under any
circumstances. Exposed 2mm thick vinyl edging shall be provided on all edges of individual
panels. Each panel shall be given a coat or primer and two coats of approved fire-resistant
paint from underside. The particle boards shall be faced with 600mm x 600 mm x 2mm
thick approved make flooring tiles conforming to IS:3462 – “Specification for unbaked
flexible PVC flooring” and of approved color and shade. The completed panel shall be
completely removable and shall remain in position without screwing or bolting to the on
the inner side with stickers for easy identification and reassembly whenever required.
Suitable backing material shall be provided on the underside of the particle board to
prevent warping and / or to cater to specified loading. Suitable removable covers shall be
provided to serve as outlets for the cables.
Imposed Loading:
The finished floor shall be capable of supporting uniformly distributed loads of 500 to
Kg. per m2of floor area as specified in data sheet. A point load of 450 Kg on 600 sq.mm on
any part of the panel or a line load of 725 Kg on 100mm strip across the panel length shall
not result in a deflection greater than 2.5mm.
The finished floor shall be true to lines and levels and present a neat flush surface.
Vendor Drawing:
Vendor shall prepare and submit a layout drawing for false floor giving all details including
supporting system for approval. If so called for, vendor shall also submit his calculations
for the supporting system with all relevant data assumed, to the GWIL for his approval.
Work shall be carried out on approved drawings only.
Fire Proof Doors:
Material and Workmanship:
The design of fire proof doors and the materials to be used in their fabrication have to be
such that they shall be capable of providing the effective barrier to the spread of fire. The
materials, fabrication and erection of fire proof doors shall confirm to IS:3614 (Part – I).
The fire proof doors shall be obtained from an approved manufacturer. Specific approval
for such purchase shall be obtained beforehand. Sample approval shall also be obtained
from testing authority as per the standard IS: 3614 (Part – 2) for the specified degree of
fire rating in hours. All fire proof doors shall have specified sizes and confirm to the
description in the respective items of work.
Fire proof door shutters shall be of zinc coated weldable steel (confirming to BS:6687) or
stainless steel (conforming to IS:304) sheet (18G minimum) fixed in a frame work of rolled
channel. The shutter shall consist of an insulating material like mineral wool in required
thickness to satisfy the specified fire rating. Normally the thickness of door shutter shall
not be less than 35mm for two-hour fire rating and 46mm for four-hour fire rating. The
shutter with the required insulating material shall be mounted on angle iron frame or the
special made frame from zinc coated (16G minimum) weldable steel sheet. The shutter
shall be fixed to frame by means of suitable hinges and shall have a three-way latching
system. All the doors shall be provided with a coat of primer and one coat of synthetic
enamel paint to attain the specified fire rating. All other accessories like hinges, door lock,
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
hold fasts, etc. shall be provided as approved by TAC (Tariff Advisory Committee). All
these accessories shall be compatible with the material used for door and shutter.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
SECTION – 5 STRUCTURAL STEEL WORK
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
STRUCTURAL STEEL WORK
Applicable Codes and Specifications:
The supply, fabrication, erection and painting of structural steel works shall comply with
the following specifications, standards and codes unless otherwise specified herein. All
standards, specifications and codes of practices referred to herein shall be the latest
editions including all applicable official amendments and revisions.
IS: 808 Dimensions for Hot Rolled Steel sections
Covered Electrodes for Manual Metal Arc Welding of Carbon and Carbon
Manganese Steel
IS: 800 Code of Practice for General Construction in Steel
Code of Practice for Use of Cold Formed Light Gauge Steel Structural
Members in General Building Construction
IS: 806 Code of Practice for Use of Steel Tubes in General Building Construction
IS: 7205 Safety Code for Erection of Structural Steel Work
IS: 7215 Tolerances for Fabrication of Steel Structures
IS: 4000 High Strength Bolts in Steel Structure – Code of Practice
AISC Specifications for Design, Fabrication and Erection of Buildings
IS: 1161 Steel Tubes for structural purposes
Ready Mixed paint, Brushing, Red Lead, Non-setting, Priming.
IS:110 Ready Mixed paint, brushing, grey filler for enamels for use over primers.
Ready Mixed paint, Brushing, Finishing, and Exterior Semigloss for general
purposes, to Indian Standard colors.
Ready Mixed paint, Brushing, Bituminous, Black, Lead free, Acid, Alkali and
heat resisting.
Ready Mixed paint, Brushing, Acid resisting for protection against acid fumes,
color as required.
IS:341 Black Japan, Types A, B and C
IS:2339 Aluminum paint for general purposes, in Dual container
Specification for enamel, synthetic, exterior, type 1, (a) Undercoating, (b)
IS:2933 Specification for enamel, exterior, type 2, (a) Undercoating, (b) finishing.
IS:5905 Sprayed aluminum and zinc coatings on Iron and Steel.
IS:6005 Code of practice for phosphating of Iron and Steel.
Specification for ready mixed paint, brushing, bituminous, black, lead free,
acid, alkali, water & chlorine resisting.
IS:13183 Aluminum paint, Heat resistant.
SIS-05-5900 (Swedish Standard)
Mild steel tubes, tubulars and other Wrought steel fittings
IS: 1239 Part 1 – Mild steel tubes
Part 2 – Mild steel tubulars and other wrought steel pipe fittings
IS: 1363 (Parts Hexagon Head Bolts, Screws and Nuts of product Grade C (Size range M5 to
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
Technical Supply Conditions for Threaded Fasteners
IS: 1852 Rolling and Cutting Tolerances for Hot Rolled Steel Products
IS: 1977 Structural Steel (Ordinary Quality)
IS: 2062 Steel for General Structural Purposes
IS: 2074 Ready Mixed Paint, Air drying, Red Oxide Zinc Chrome and Priming
IS: 3502 Steel Chequered Plate
IS: 3757 High Strength Structural Bolts
IS: 5369 General Requirements for Plain Washers and Lock Washers
IS: 5372 Taper Washers for Channels
IS: 5374 Taper Washer for 1 Beams
IS: 6610 Heavy Washers for Steel Structures
IS: 8500 Structural Steel-micro alloyed (medium and high strength qualities)
Code of practice for design, fabrication and erection of vertical mild steel
cylindrical welded storage tanks
Code of Practice for use of Metal Arc Welding for General construction in
IS: 822 Code of Procedure for Inspection of Welds
Recommended Practice for Radiographic examination of Fusion – Welded Butt
Joints in Steel Plates
IS: 1200 Method of Measurement in Building Civil Works
IS: 1477 Code of Practice for Painting of (Parts 1&2) Ferrous Metals in Buildings
IS: 2595 Code of Practice for Radiographic Testing
IS: 3658 Code of Practice for Liquid Penetrate Flaw Detection
IS: 5334 Code of Practice for Magnetic Particle Flaw Detection of Welds
Recommendations for Metal Arc Welding of Carbon and Carbon Manganese
Steel Materials:
All materials used shall be new, unused and free from defects.
Steel conforming to IS: 1977 shall be used only for the following:
Fe310-0 For general purposes such as door/window frames, grills, steel
handrails, fence posts, tee bars and other non-structural use.
Fe410-0 For structures not subjected to dynamic loading other than wind loads such
(St 42-0) as: Platform roofs, foot over bridges, building, factory sheds etc.
Fe510-0 Grade steel shall not be used
a) If welding is to be employed for fabrication
b) If site is in severe earthquake zone
c) If plastic theory of design is used
Drawings prepared by the VENDOR/CONTRACTOR:
The VENDOR/CONTRACTOR shall prepare all fabrication and erection drawings for the
entire work. All the drawings for the entire work shall be prepared in metric units. The
drawings shall preferably be of one standard size and the details shown there in shall
be clear and legible.
All fabrication drawings shall be submitted to the Engineer-In-Charge for approval.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
No fabrication drawings will be accepted for Engineer In charge’s approval unless
checked and approved by the VENDOR/Contractor’s qualified structural engineer and
accompanied by an erection plan showing the location of all pieces detailed. The
VENDOR/CONTRACTOR shall ensure that connections are detailed to obtain ease in
erection of structures and in making field connections.
Fabrication shall be started by the VENDOR/CONTRACTOR only after Engineer In
charge’s approval of fabrication drawings. Approval by the Engineer-In-Charge of any
of the drawings shall not relieve the VENDOR/CONTRACTOR from the responsibility for
correctness of engineering and design of connections, workmanship, fit of parts,
details, material, errors or omissions or any and all work shown thereon. The Engineer
In charge’s approval shall constitute approval of the size of members, dimensions and
general arrangement but shall not constitute approval of the connections between
members and other details.
The drawings prepared by the VENDOR/CONTRACTOR and all subsequent revisions etc.
shall be at the cost of the VENDOR/CONTRACTOR for which no separate payment will
All workmanship and finish shall be of the best quality and shall conform to the best-
approved method of fabrication. All materials shall be finished straight and shall be
machined/ground smooth true and square where so specified. All holes and edges shall
be free of burrs. Shearing and chipping shall be neatly and accurately done and all
portions of work exposed to view shall be neatly finished. Unless otherwise approved
by the Engineer-In-Charge, reference may be made to relevant IS codes for providing
standard fabrication tolerance. Material at the shops shall be kept clean and protected
Shop/field connections shall be as per approved fabrication drawings. In case of bolted
connections, taper washers or flat washers or spring washers shall be used with bolts
as necessary. In case of high strength friction grip bolts, hardened washers to be used
under the nuts or the bolt heads whichever are turned to tighten the bolts. The length
of the bolt shall be such that at least one thread of the bolt projects beyond the nut,
except in case of high strength friction grip bolts where this projection shall be at
least three times the pitch of the thread.
In all cases where bearing is critical, the unthreaded portion of bolt shall bear on the
members assembled. A washer of adequate thickness may be provided to exclude the
threads from the bearing thickness, if a longer grip bolt has to be used for this
All connections and splices shall be designed for full strength of members or loads.
Column splices shall be designed for the full tensile strength of the minimum cross
section at the splice.
All bolts, nuts, washers, electrodes, screws etc., shall be supplied/brought to site 10%
in excess of the requirement in each category and size. Rates shall cover the cost of
this extra quantity.
All members likely to collect rainwater shall have drain holes provided.
All materials shall be straight and, if necessary, before being worked shall be
straightened and/or flattened by pressure and shall be free from twists. Heating or
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
forging shall not be resorted to without the prior approval of the Engineer-In-Charge in
Rolling and Forming:
Plates, channels, R.S.J. etc., for circular bins, bunkers, hoppers, gantry girders, etc.,
shall be accurately laid off and rolled or formed to required profile/shape as called for
on the drawings. Adjacent sections shall be match-marked to facilitate accurate
assembly, welding and erection in the field.
High Strength Friction Grip Bolting:
Inspection after tightening of bolts shall be carried out as stipulated in the appropriate
standards depending upon the method of tightening and the type of bolt used.
Welding procedure shall be submitted to the Engineer-In-Charge for approval. Welding
shall be entrusted to qualified and experienced welders who shall be tested
periodically and graded as per IS 817, IS: 7310 (Part 1) and IS: 7318 (Part 1).
While fabricating plated beams and built up members, all shop splices in each
component part shall be made before such component part is welded to other parts of
the members. Wherever weld reinforcement interferes with proper fit-up between
components to be assembled off welding, these welds shall be ground flush prior to
Approval of the welding procedure by the Engineer-In-Charge shall not relieve the
Contractor of his responsibility for correct and sound welding without undue distortion
in the finished structure.
No welding shall be done when the surface of the members is wet nor during periods of
Each layer of a multiple layer weld except root and surfaces runs may be moderately
penned with light blows from a blunt tool. Care shall be exercised to prevent scaling
or flaking of weld and base metal from overweening.
No welding shall be done on base metal at a temperature below –50 C. Base metal
shall be preheated to the temperature as per relevant IS codes.
Electrodes other than low-hydrogen electrodes shall not be permitted for thickness of
32 mm and above.
All welds shall be inspected for flaws by any of the methods described under Sub-
clause 4.6.3. The choice of the method adopted shall be agreed with the Engineer-In-
The correction of defective welds shall be carried out in a manner approved by the
Engineer-In-Charge without damaging the parent metal. When a crack in the weld is
removed, magnetic particle inspection or any other equally positive means approved
by the Engineer-In-Charge shall be used to ensure that the whole of the crack and
material up to 25 mm beyond each end of the crack has been removed. The cost of all
such tests and operations incidental to correction shall be borne by the Contractor.
The dimensional and weight tolerances for rolled shapes shall be in accordance with
ARE: 1852 for indigenous steel and equivalent applicable codes for imported steel. The
tolerances for fabrication of structural steel shall be as per ARE:
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
Cutting, punching, drilling, welding and fabrication tolerances shall be generally as per
relevant IS codes.
Where compression joints are specified to be designed for bearing, the bearing
surfaces shall be milled true and square to ensure proper bearing and alignment.
The Contractor shall give due notice to the Engineer-In-Charge in advance of the works
being made ready for inspection. All rejected material shall be promptly removed
from the shop and replaced with new material for the Engineer In charge’s inspection.
The fact that certain material has been accepted at the Contractor’s shop shall not
invalidate final rejection at site by the Engineer-In-Charge if it fails to conform to the
requirements of these specifications, to be in proper condition or has fabrication
inaccuracies which prevent proper assembly nor shall it invalidate any claim which the
Employer may make because of defective or unsatisfactory materials and/or
No materials shall be painted or dispatched to site without inspection and approval by
the ENGINEER INCHARGE unless such inspection is waived in writing by the ENGINEER-
The Contractor shall provide all the testing and inspection services and facilities for
shop work except where otherwise specified.
For fabrication work carried out in the field the same standard of supervision and
quality control shall be maintained as in shop fabricated work. Inspection and testing
shall be conducted in a manner satisfactory to the Engineer-In-Charge.
Inspection and tests on structural steel members shall be as set forth below.
Material Testing:
If mill test reports are not available for any steel materials the same shall be tested by
the Contractor to the Employer’s Representative’s satisfaction to demonstrate
conformity with the relevant specification.
Tests on Welds:
(a) Magnetic Particle Test:
Where welds are examined by magnetic particle testing, such testing shall be carried
out in accordance with relevant IS codes. If heat treatment is performed, the
completed weld shall be examined after the heat treatment. All defects shall be
repaired and retested. Magnetic particle tests shall be carried out using alternating
current. Direct current may be used with the permission of the Engineer-In-Charge.
(b) Liquid Penetrate Inspection:
In the case of welds examined by Liquid Penetrate Inspection, such tests shall be
carried out in accordance with relevant IS Code. All defects shown shall be repaired
(c) Radiographic Inspection:
All full-strength butt welds shall be radio graphed in accordance with the
recommended practice for radiographic testing as per relevant IS code.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
Dimensions, Workmanship & Cleanliness:
Members shall be inspected at all stages of fabrication and assembly to verify that
dimensions, tolerances, alignment, surface finish and painting are in accordance with
the requirements shown in the Contractor’s approved fabrication drawings.
In the event of failure of any member to satisfy inspection or test requirement, the
Contractor shall notify the Engineer-In-Charge. The Contractor must obtain permission
from the Engineer-In-Charge before any repair `is undertaken. The quality control
procedures to be followed to ensure satisfactory repair shall be subject to approval by
the Engineer-In-Charge.
The Engineer-In-Charge has the right to specify additional testing as he deems
necessary, and the additional cost of such testing shall be borne by the Employer, only
in case of successful testing.
The Contractor shall maintain records of all inspection and testing which shall be made
available to the Engineer-In-Charge.
For structures like bunkers, tanks, etc. Shop assembly is essential. For other steel
work, such as columns along with the tie beams/bracings may have to be shop
assembled to ensure satisfactory fabrication, obtaining of adequate bearing areas etc.,
if so desired by the Engineer-In-Charge. All these shop assemblies shall be carried out
by the Contractor.
Drilling Holes for other works:
As a part of this Contract, holes in members required for installing equipment or steel
furnished by other manufacturers or other contractors shall be drilled by the
VENDOR/CONTRACTOR at no extra cost of the EMPLOYER. The information for such
extra holes will be supplied by the EMPLOYER/ENGINEER-IN-CHARGE.
Marking of Members:
After checking and inspection, all members shall be marked for identification during
erection. This mark shall correspond to distinguishing marks on approved erection
drawings and shall be legibly painted and stamped on it. The erection mark shall be
stamped with a metal dye with figures at least 20 mm high and to such optimum depth
as to be clearly visible.
All erection marks shall be on the outer surface of all sections and near one end, but
clear of bolt holes. The marking shall be so stamped that they are easily discernible
when sorting out members. The stamped marking shall be encircled boldly by a
distinguishable paint to facilitate easy location.
Erection marks on like pieces shall be in identical locations. Members having lengths of
7.0 m or more shall have the erection mark at both ends.
Any error in shop fabrication which prevents proper assembling and fitting up of parts
in the field by moderate use of drift pins or moderate amount of reaming will be
classified by the Engineer-In-Charge as defective workmanship. Where the Engineer-In-
Charge rejects such material or defective workmanship, the same shall be replaced by
materials and workmanship conforming to the Specifications by the Contractor, at no
cost to the Employer.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
Painting of Steel Work:
All fabricated steel material, except those galvanized shall receive protective paint
coating as specified in specification, which is described below.
Red-oxide – zinc chrome primer shall conform to IS:
Synthetic enamel paint shall conform to IS:
Aluminum paint shall conform to IS:
All the materials shall be of the best quality from an approved manufacturer.
Contractor shall obtain prior approval of the Engineer-In-Charge for the brand of
manufacture and the color/shade. All the materials shall be brought to the site in
sealed containers.
Painting work shall be carried out only on thoroughly dry surfaces. Painting shall be
applied either by brushing or by spraying. Contractor shall procure the appropriate
quality of paint for this purpose as recommended by the manufacturer. The
workmanship shall generally conform to the requirement of IS: 1477 (Part 2).
The type of paint, number of costs etc. shall be as specified in the respective items of
work. Primer and finish paint shall be compatible with each other to avoid cracking
and wrinkling. Primer and finish paint shall be from the same manufacturer. All the
surfaces shall be thoroughly cleaned of oil, grease, dirt, rust and scale. The methods
to be adopted using solvents, wire brushing, power tool cleaning etc., shall be as per
IS: 1477 (Part – I) and as indicated in the item of work. It is essential to ensure that
immediately after preparation of the surfaces; the first coat of red oxide-zinc chrome
primer shall be applied by brushing and working it well to ensure a continuous film
without holidays. After the first coat becomes hard dry, a second coat of primer shall
be applied by brushing to obtain a film free from `holidays.
After the second coat of primer is hard dry, the entire surface shall be wet rubbed
cutting down to a smooth uniform surface. When the surface becomes dry, the
undercoat of synthetic enamel paint of optimum thickness shall be applied by brushing
with minimum of brush marks. The coat shall be allowed to hard dry. The under coat
shall then be wet rubbed cutting down to a smooth finish, taking adequate care to
ensure that at no place the undercoat is completely removed. The surface shall then
be allowed to dry.
The first finishing coat of paint shall be applied by brushing and allowed to hard dry.
The gloss from the entire surface shall then be gently removed and the surface dusted
off. The second finishing coat shall then be applied by brushing.
At least 24 hours shall elapse between the applications of successive coats. Each coat
shall vary slightly in shade and this shall be got approved by the Engineer-In-Charge.
Acceptance of Steel, its Handling & Storage:
The Contractor shall carefully check the steel to be erected at the time of
acceptance. Any fabrication defects observed should be brought to the notice of the
Engineer-In-Charge.
No dragging of steel shall be permitted. All steel shall be stored 300mm above ground
on suitable packing to avoid damage. It shall be stored in the order required for
erection, with erection marks visible. All storage areas shall be prepared and
maintained by the Contractor. Steel shall not be stored in the vicinity of areas where
excavation or grading will be done and, if so stored temporarily, this shall be removed
by the Contractor well before such excavation and/or grading commences to a safe
distance to avoid burial under debris. Scratched or abraded steel shall be given a coat
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
of primer in accordance with the Specifications for protection after unloading and
handling prior to erection. All milled and machined surfaces shall be properly
protected from rust/corrosion by suit able coating and also from damage.
Anchor Bolts & Foundations:
The Contractor shall carefully check the location and layout of anchor bolts embedded
in foundations constructed, to ensure that the structures can be properly erected as
shown on the drawings. Any discrepancy in the anchor bolts/foundation shall be
reported to the Engineer-In-Charge.
Leveling of column bases to the required elevation may be done either by providing
shims or three nuts on the upper threaded portion of the anchor bolt. All shim stock
required for keeping the specified thickness of grout and in connection with erection
of structures on foundations, crane brackets or at any other locations shall be of good
M.S. plates and shall be supplied by the Contractor at his cost.
A certain amount of cleaning of foundations and preparing the area is considered
normal and shall be carried out by the Contractor at no extra cost. Here beams bear in
pockets or on walls; bearing plates shall be set and leveled as part of the work. All
grouting under column base plates or beam bearing plates will be carried out by the
Assembly & connections:
Field connections may be affected by riveting, bolting, welding or by use of high
strength friction grip bolts as shown on the design and erection drawings.
All field connection work shall be carried as per the drawings. All bolts, nuts, washers,
rivets, electrodes required for field connections shall be supplied by the Contractor
free of cost. All assembling shall be carried on a level platform. Drifts shall be used
only for drawing the work to proper position and must not be used to such an extent as
to damage the holes. Size of drifts larger than the normal diameter of hole shall not
be used. Any damaged holes or burrs must be rectified to the satisfaction of the
Engineer-In-Charge.
Corrections of minor misfits and reasonable amount of reaming and cutting of excess
stock from rivets shall be considered as a part of erection. Any error in the shop,
which prevents proper fit on a moderate amount of reaming and slight chipping or
cutting, shall be immediately reported to the Engineer-In-Charge.
All structural steel shall be erected as shown on the drawings prepared by the
Contractor. Proper size steel cable slings, etc., shall be used for hoisting. Guys shall
not be anchored to existing structures, foundations, etc., unless so permitted by the
Engineer-In-Charge in writing. Care shall be taken to see that ropes in use are always
in good condition.
Steel columns in the basement, if any, are to be lowered and erected carefully with
the help of a crane and/or derrick without damaging the basement walls or floor.
Structural steel frames shall be erected plumb and true. Frames shall be lifted at
points such that they are not liable to buckle and deform. Trusses shall be lifted only
at node points. In the case of trusses, roof girders, all of the purlins and wind bracing
shall be placed simultaneously and the columns shall be erected truly plumb on screed
bars over the pedestals. All steel columns and beams shall be checked for plumb and
level individually before and after connections are made. Temporary bracings shall be
introduced wherever necessary to take care of all loads to which the structure may be
subjected, including erection equipment and the operation thereof. Such bracings
shall be left in place as long as may be required for safety and stability.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
Chequered plates shall be fixed to supporting members by tack welding or by
countersunk bolts as shown/specified in relevant drawings and/or as approved by the
Engineer-In-Charge. The edges shall be made smooth and no burrs or jagged ends shall
be left. While splicing, care should be taken so that there is continuity in pattern
between the two portions. Care should also be taken to avoid distortion of the plate
The erection of chequered plates shall include:
Welding of stiffening angles/vertical stiffening ribs Cutting to size and making holes to
required shape wherever necessary to allow service piping and/or cables to pass
through Splicing as shown in relevant drawings.
Smoothening of edges
Fixing of chequered plates by tack welding or by countersunk bolts
Providing lifting hooks for ease of lifting.
As erection progresses, the work shall be securely bolted to take care of all dead load,
wind, seismic and erection stresses. No riveting or welding or final bolting shall be done
until the structure has been properly aligned and approved by the Engineer-In-Charge. No
cutting, heating or enlarging of the holes shall be carried out without the prior written
approval of the Engineer-In-Charge. The Contractor shall furnish test certificates.
The Engineer-In-Charge shall have free access to all parts of the job during erection
and all erection shall be subjected to his approval. In case of faulty erection, all
dismantling and re-erecting required will be at the Contractor’s cost. No paint shall be
applied to rivet heads or field welds or bolts until these have been approved by the
Engineer-In-Charge.
Tolerances mentioned below shall be achieved after the entire structure or part
thereof is in line, level and plumb.
Deviation of column axes at foundation top level with respect to true axes:
(a) In longitudinal direction ±5 mm
(b) In lateral direction ±5 mm
Deviation in the level of bearing surface of columns at foundation top with respect to true
Out of plumb ness (verticality) of column axis from true vertical axis, as measured at
(a) For columns up to and including 15 meters ±1/1000 of column height in mm
or ±15 mm whichever is less
(b) For columns exceeding ±1/1000 of column height in mm
or ±20 mm whichever is less
Deviation in straightness in longitudinal transverse ±1/1000 of column height in mm
planes of column at any height or ±10 mm whichever is less
Point along the height
Difference in erected position of adjacent Pairs of ±10 mm
columns along length or across width of building prior to
connecting trusses/beams with respect to true distance
Width of building prior to connecting trusses/beams with ±10 mm
respect to true distance
Deviation in any bearing or seating level with respect to ±5 mm
Deviation in differences in bearing level of a member on ±10 mm
adjacent pair of columns both across and along the
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
Trusses and Beams:
Shift at the center of span of top chord member with ±1/250 of height of truss in mm
respect to the vertical plane passing through the center or ±15 mm whichever is less
of bottom chord.
Lateral shift of top chord of truss at the center of span ±1/1500 of height of truss in mm
from the vertical plane passing through the center of or ±15 mm whichever is less
supports of the truss
Lateral shift in location of truss from its true vertical ±10 mm
Lateral shift in location of purlin true position ±5 mm
Deviation in difference of bearing levels of trusses or 1. ±20 mm for trusses
beams from 2. For beams: the true
Depth < 1800mm: ±6mm
Depth > 1800mm: ±10mm
Deviation in sag in chords and diagonals of truss between 1/1500 of length in mm or 10mm
node points whichever is smaller
Deviation in sweep of trusses, beams etc. horizontal plan 1/1000 of span in mm subject to
a maximum of 10 mm
Crane Girders & Rails
Shift in the center line of crane rail respect to center line ±5 mm
of web of with crane girder
Shift in plan of alignment of crane rail with respect to ±1 mm
true axis of crane rail at any point
Difference in alignment of crane rail in plan measured ±1 mm
between any two points 2 meters apart
Deviation in crane track with respect to true gauge
For track gauges up to and Including 15 meters ±5 mm
For track gauges more than 15 meters ± [5 + 0.25 (S-15)] where S in
meters are true gauge
Deviation in the crane real level at any point from true ±1/1200 of the gauge distance
level or±10mm whichever is less
Difference in the crane rail actual levels between any ±2 mm
two points 2 meters apart along the rail length
Difference in levels between crane track Rails at
(a) Supports of crane girders ±15 mm
(b) Mid span of crane girders ± 20 mm
Relative shift of crane rail surfaces at a joint in plane 2 mm
and elevation surfaces for smooth transition
Relative shift in the location of crane stops (end buffer 1/1000 of track gauge subject to
along the crane tracks with track gauge S maximum of 20 mm S in
After steel has been erected, all bare and abraded spots, rivet heads, field welds, bolt
heads and nuts shall be spot painted with primer. Before paint is applied, the surface shall
be dry and free from dust, dirt, scale and grease. All surfaces inaccessible after erection
shall receive two coats of the approved paint before erection.
Clean up of Work site:
During erection, the Contractor shall at all times keep the working and storage areas
used by him free from accumulation of waste materials or rubbish. Before completion of
erection, he shall remove or dispose of in a satisfactory manner all temporary structures,
waste and debris and leave the premises in a condition satisfactory to the Engineer-In-
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
SECTION -6 WATER SUPPLY AND SANITARY WORKS
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
WATER SUPPLY AND SANITARY WORKS
Applicable Codes:
The following standards and codes are made a part of this Employer’s Requirement. All
standards, codes of practice referred to herein shall be the latest editions including all
official amendments and revisions.
IS: 210 : Specification for grey iron castings
IS: 269 : Specification for ordinary and low heat Portland cement
IS: 383 : Specification for coarse and fine aggregates from natural sources for concrete
IS: 432 : Specification for mild steel and medium tensile steel bars and hard drawn steel
wire for concrete reinforcement
IS: 456 : Code of Practice for plain and reinforced concrete
IS: 458 : Concrete Pipes (with and without reinforcement).
IS: 516 : Methods of tests for strength of concrete
IS: 554 :Dimensions for pipe threads where pressure tight joints are required on the
IS: 651 : Salt glazed stoneware pipes and fittings.
IS: 774 : Flushing Cisterns for water closets and urinals (valueless siphonic type)
IS: 775 : Cast iron brackets and supports for wash basins and sinks.
IS: 781 : Sand-cast brass screw-down bib taps and stop taps for water services.
IS: 783 : Code of practice for lying of concrete pipes.
IS: 1068 : Electroplated coatings of nickel and chromium of iron and steel.
IS: 1077 : Specification for common burnt clay building bricks
IS: 1786 : Specification for high strength deformed steel bars and wires for concrete
IS: 1239 : Mild steel tubes (Part I) and mild steel tubular and other wrought steel pipe
fittings (Part II)
IS: 1536 : Centrifugally cast (spun) iron pressure pipes for water, gas and sewage.
IS: 1626 : Asbestos cement building pipes, gutters and fittings (spigot and socket types).
IS: 1703 : Copper Alloy float valves (horizontal plunger type) for water supply purposes.
IS: 1726 : Cast iron manhole covers and frames.
IS: 1729 : Sand cast iron spigot and socket soil, waste and ventilating pipes, fittings and
IS: 1742 : Code of practice for buildings drainage
IS: 2116 : Specification for sand for masonry mortars
IS: 2212 : Code of practice for brickwork
IS: 2250 : Code of practice for preparation and use of masonry mortars
IS: 2326 : Automatic flushing cisterns for urinals
IS: 2470 : Code of practice for design and construction of septic tanks (Parts I & II)
IS: 2556 : Vitreous sanitary appliances (Part I to Part XV)
IS: 2963 : Specification for copper alloy waste fittings for wash basins and sinks
IS: 3006 : Specification for chemically resistant glazed stoneware pipes and fittings
IS: 3311 : Waste plug and its accessories for sinks and wash basins
IS: 5455 : Specification for cast iron steps for manholes
IS: 4127 : Code of Practice for laying of glazed stoneware pipes
IS: 3495 : Methods of tests of burnt clay building bricks
IS: 4111 : Code of practice for ancillary structures in sewerage system manholes
IS: 5382 : Specification for rubber sealing rings for gas mains, water mains and sewers
IS: 5329 : Code of practice for sanitary pipe work above ground for buildings
IS: 5434 : Non-ferrous alloy bottle traps for marine use
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
Sanitary Installation:
The work shall be carried out complying in all respects with any specific requirements of
the local body in whose jurisdiction the work is situated, and as approved by the
Employer’s Representative.
Any damage caused to the building, or to installations therein, either due to negligence
on the part of the Contractor, or due to actual requirements of the work, shall be made
good and the building or the installation shall be restored to its original condition by the
All sanitary and plumbing work shall be carried out by licensed plumbers.
All sanitary appliances including sanitary fittings, fixtures, and toilet requisites shall be of
size, and design as approved by the Employer’s Representative. All white glazed
porcelain fixtures, such as wash basin, sink drain board, water closet pan, urinal, `P' trap
etc. shall have hard durable white glazed finish. They shall be free from cracks and other
glazing defects. No chipped porcelain fixtures shall be used. Joints between iron and
earthenware pipes shall be made perfectly air and water tight by caulking with neat
A) Indian Type Water Closet:
This shall be the long pan pattern with separate footrests made of white glazed
earthenware; white glazed vitreous china or of white glazed fire clay. The general
requirements shall conform to IS:2556 (Parts III and X). Each pan shall have an integral
flushing rim of suitable type. It shall also have an inlet or supply horn for connecting the
flush type. The flushing rim and inlet shall be of the self draining type. It shall have a
weep hole at the flushing inlet to the pan. The flushing inlet shall be in the front, unless
otherwise approved by the Employer’s Representative. The inside of the bottom of pan
shall have sufficient slope from the front towards the outlet and the surface shall be
uniform and smooth enable easy and quick disposal while flushing. The exterior surface
shall be unglazed and sufficiently rough or grooved at right angles to the axis of the
outlet. Pans shall be provided with a trap `P' or `S' type with a minimum 50 mm water
seal and 50 mm dia. vent horn. Pan shall be laid at the correct location and level over a
bed of lime concrete using brick aggregates (1-part lime mortar to 2 parts brick bats with
lime mortar to 2 parts of sand) or cement-sand admixture as specified in the drawings.
B) European Type Water Closet:
Water closets shall be either of white glazed earthenware, white grazed vitreous china or
white glazed fire clay as specified and shall be of "Symphonic Wash down type"
conforming to IS.2556 (Part VIII). The closets shall be of one-piece construction with
approved plastic/Bakelite seat and cover. Each water closet shall have 4 fixing holes
having a minimum diameter of 6.5 mm for fixing to floor and shall have an integral
flushing rim of suitable type. It shall also have an inlet of supply horn for connecting the
flush pipe. The flushing rim and inlet shall be of the self-draining type. The water closet
shall have a weep hole at the flushing inlet. Each water closet shall have an integral trap
with either "S" or "P" outlet with at least 50 mm water seal. The water closets shall have
an ant siphonage 50 mm dia. vent horn on the outlet side of the trap. The inside of water
closets and traps shall be uniform and smooth in order to ensure in efficient flush. The
serrated part of the outlet shall not be glazed externally. The water closet when sealed
at the bottom of the trap in line with the back plate shall be capable of holding not less
than 10 liters of water between the normal water level and the highest possible water
level of the water closet installed.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
Urinals shall be of the bowl pattern, either flat back or angle back type lipped in front.
They shall be of white glazed earthenware, white glazed vitreous china or white glazed
fire clay, and of size as specified conforming to IS:2556 (Part VI). The urinals shall be of
one-piece construction. Each urinal shall be provided with not less than two fixings holes
of a minimum dia. of 6.5 mm on each side. Each urinal shall have an integral flushing box
rim of suitable type and inlet or supply horn for connecting the flush pipe. The flushing
rim and inlet shall be of the self-draining type. It shall have a weep hole at the flushing
inlet of the urinal. At the bottom of the urinal, an outlet horn for connecting to an outlet
pipe shall be provided. The exterior of the outlet horn shall not be glazed and the surface
shall be provided with grooves at right angles to the axis of the outlet to facilitate fixing
to the uniform and smooth throughout to ensure efficient flushing. The bottom of pan
shall have sufficient slope from the front, towards the outlet such that there is efficient
draining of the urinal. The waste fittings shall be chromium plated.
Wash basins shall be of white glazed earthenware, white glazed vitreous china or white
glazed fire clay as approved by the Employer’s Representative and conforming to IS.2556
Flat Back 630 x 450 mm
Flat Back 550 x 400 mm
Wash basins shall be of one-piece construction, including a combined overflow. All
internal angles shall be designed so as to facilitate cleaning. Each shall have a rim sloping
inside towards the bowl on all sides except skirting at the back. Basins shall be provided
with single or double tap holes as approved. The tap holes shall be square. A suitable tap
hole button shall be supplied if one tap hole is not required in installation. Each basin
shall have a circular waste hole to which the interior of basin shall drain. The waste hole
shall be either rebated or beveled internally with diameter of 65 mm at top and a depth
of 10 mm to suit a waste plug having 64 mm diameter. Each basin shall be provided with
non-ferrous 32 mm waste fittings. Stud slots to receive the brackets on the underside of
the wash basins shall be suitable for a bracket with stud not exceeding 13 mm diameter,
5 mm high and 305 mm from the back of basin to the center of the stud. The stud slots
shall be of depth sufficient to take 5 mm stud. Every basin shall have an integral soap
holder recess or recesses which shall fully drain into the bowl. The position of the chain
stay-hole shall not be lower than the overflow slot. A slot type of overflow having an area
of not less than 5 cm2. shall be provided and shall be so designed as to facilitate cleaning
of the overflow. The Employer’s Requirements for waste plug, chain and stay shall be the
same as given for sinks.
All the waste fittings shall be chromium plated. Bottle trap shall conform to IS. 5434. The
chromium plating shall be of service grade No. 2 conforming to IS.1068.
The sinks shall be of white glazed earthenware, white glazed vitreous china or white
glazed fire clay as approved by the Employer’s Representative conforming to IS.2556
(Part V) and shall be of the following sizes:
They shall be of one-piece construction, including a combined overflow. The floor of the
sink shall gently slope towards the outlet. The outlet shall in all cases be suitable for
waste fittings having flange of 64 mm diameter and the waste hole shall have a minimum
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
diameter of 65 mm at the bottom to suit the waste fittings. The waste hole shall be
either rebated or beveled having a depth of 10 mm. Each sink shall be provided with a
non-ferrous 40 mm dia. waste fitting. The sink shall have overflow of the weir type and
the inverts shall be 30 mm below the top edge. Each sink shall be provided with a waste
plug, of suitable dia. chain and stay. The plug shall be of rubber or other equally suitable
material and shall be water tight when fitted. Plug chains shall be of brass wire chromium
plated. It shall have an overall length from the collar to the stay of not less than 300 mm.
There shall be a triangular or D shackle at each end, one of which shall be brazed to the
plug and the other securely fixed to the stay. The 150 mm long shank of the waste shall
be threaded conforming to the requirements of IS: 2556 for sinks only. The waste fittings
and plug fittings shall be chromium plated. The chromium plating shall be of service
grade No.2 conforming to IS:
Flushing Cisterns:
The flushing cisterns shall be automatic or manually operated high level or low level, as
approved by the Employer’s Representative. For water closets and urinals high level
cistern is intended to operate with minimum height of 125 cm and a low-level cistern a
maximum height of 30 cm between the top of the pan and the underside of the cistern.
They shall be of cast iron, glazed earthenware, or pressed steel complying iron, glazed
requirement of IS: 774. Automatic flushing cistern for urinals shall conform to IS:
Cast Iron Soil Waste and Vent Pipes and Fittings:
All cast iron pipes and fittings shall be of uniform thickness with strong and deep sockets,
free from flaws, air holes, cracks, sand holes and other defects and conform to IS:
The diameter approved shall be internal diameter of pipe. The pipes and fittings shall be
true to shape, smooth and cylindrical and shall ring clearly when struck over with a light
hand hammer. All pipes and fittings shall be properly cleaned of all foreign material
before being fixed.
All plug bends of drainage pipes shall be provided with inspection and cleaning caps,
covers, which shall be fixed with nuts and screws. Pipes shall be fixed to the wall by W.I.
or M.S. holder bat clamps, unless projecting ears with fixing holes are provided at socket
end of pipe. The pipes shall be installed, truly vertical or to the lines and slopes as
indicated. The clamps shall be fixed to the walls by embedding their hooks in cement
concrete blocks (1:2:4) 10 cm x 10 cm making necessary holes in the walls at proper
places. All holes and breakages shall be made good. The clamps shall be kept 25 mm
clear of the finished face of the walls to facilitate cleaning and painting of pipes.
The annular space between the socket and spigot shall be filled with a gasket of hemp or
spun yarn soaked in neat cement slurry. The joint shall then be filled with stiff cement
mortar 1:2 (1 cement: 2 fine sand) well pressed with caulking tool and finished smooth on
top at an angle of 45°. The joint shall be kept wet for not less than 7 days by tying a
piece of gunny bag kept moist. Joints shall be perfectly air tight as well as water tight.
C.I. pipes and fittings which are exposed shall be first cleaned and then painted with a
coat of red lead primer. Two coats of zinc paint with white base and mixed with pigment
of required color to get the approved shade shall be given over the base primer coat.
The thickness of fittings and their socket and spigot dimensions shall conform to the
thickness and dimensions approved for the corresponding sizes of straight pipes.
The connection between the main pipe and branch pipes shall be made by using branches
and bends with access for cleaning. Floor traps shall be provided with 25 mm dia. puff
pipe where the length of the waste is more than 1800 mm or the floor trap is connected
to a waste stack through bends.
All cast iron pipes and fittings including joints shall be tested by a smoke test to the
satisfaction of the Employer’s Representative and left in working condition after
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
The smoke test shall be carried out as stated under:
Smoke shall be pumped into the pipe at the lowest and from a smoke machine which
consists of a bellow and a burner. The material usually burnt is greasy cotton waste which
gives out a clear pungent smoke which is easily detectable by sight as well as by smell if
there is a leak at any point of the pipeline. Water test and air test shall be conducted as
stipulated in IS:
Galvanized Mild Steel (G.I.) Pipe:
The pipes shall be galvanized mild steel welded pipes and seamless screwed and sockets
tubes conforming to the requirements of IS: 1239, for medium grade. They shall be of the
diameter (nominal bore) approved. The sockets shall be designated by the respective
nominal bores of the pipes for which they are intended. The pipes and sockets shall be
finished neatly, well galvanized on both inner and outer surfaces, and shall be free from
cracks, surface flaws, laminations and other defects. All screws, threads shall be clean
and well cut. The ends shall be cut cleanly and square with the axis of the tube.
All screwed tubes and sockets shall have pipe threads conforming to the requirements of
IS.554. Screwed tubes shall have taper threads while the sockets shall have parallel
The fittings shall be of malleable cast iron or mild steel tubes complying with all the
appropriate requirements as approved for pipes. The fittings shall be designated by the
respective nominal bores of the pipes for which they are intended. The fittings shall have
screw threads at the ends conforming to the requirements of IS: 554. Female threads on
fittings shall be parallel and male threads (except on running nipples and collars of
unions) shall be tapered.
The pipes and fittings shall be inspected at site before use to ascertain that they conform
to the specification. The defective pipes shall be rejected. Where the pipes have to be
cut or rethreaded, the ends shall be carefully filled out so that no obstruction to bore is
offered. The ends of the pipes shall then be threaded conforming to the requirements of
IS.554 with pipe dies and taps carefully in such a manner as will not result in slackness of
joints when the two pieces are screwed together. The taps and dies shall be used only for
straightening bent and damaged screw threads and shall not be used for turning of the
threads so as the make them slack, water tight joint. The screw- thread of pipes and
fittings shall be protected from damage until they are fitted. The pipes shall be cleaned
and cleared of all foreign matter before being laid. In jointing the pipes, the inside of the
socket and the screwed end of the pipes shall be oiled and rubbed over with white lead
and a few turns of spun yarn wrapped around the screwed end of the pipe. The end shall
then be screwed in the socket, tee, etc., with the pipe wrench. Care should be taken
that all pipes and fittings are properly jointed so as to make the joints completely water
tight and pipes are kept at all times free from dust and dirt during fixing. Burrs from the
joint shall be removed after screwing. After laying, the open ends of the pipes shall be
temporarily plugged to prevent access of soil or any other foreign matter. Any threads
exposed after jointing shall be painted or in the case of underground piping thickly
coated with approved anticorrosive paint to prevent corrosion.
For internal work the galvanized iron pipes and fittings shall run on the surface of the
walls or ceiling (not in chase) unless otherwise specified. The fixing shall be done by
means of standard pattern holder bat clamps, keeping the pipes about 1.5 cm clear of the
wall. Pipes and fittings shall be fixed truly vertical/horizontal. When it is found necessary
to conceal the pipes, chasing may be adopted or pipes fixed in the ducts of recesses etc.
provided there is sufficient space to work on the pipes with the usual tools. The pipes
shall not ordinarily be buried in walls or solid floors. Where unavoidable, pipes may be
buried for short distances provided adequate protection is given against damage, but the
joints in pipes shall not be buried. M.S. pipe sleeve shall be fixed at a place where a pipe
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
is passing through a wall or floor for reception of the pipe and to allow freedom for
expansion/contraction and other movements/maintenance. In case the pipe is embedded
in walls or floors it should be painted with anti-corrosive bitumastic paint of approved
quality. The pipe should not come in contract with lime mortar or lime concrete as the
pipe is affected by lime. Under the floors the pipes shall be laid in layer of sand filling or
as approved by the Employer’s Representative.
G.I. pipes with socket and spigot ends shall be provided with lead caulked joints
wherever specified and the joints shall conform to the requirements of IS.3114.
The work of excavation and backfilling shall be done true to line and gradient in
accordance with General Employer’s Requirements for earthworks in trenches for pipes
laid underground.
The pipes shall be laid on a layer of 10.0 cm sand and filled up to 15 cm above the pipes.
A sand cushion of 15cm on either side of the pipe shall also be provided. The remaining
portion of the trench shall then be filled with excavated earth. The surplus earth shall be
got rid of as directed. When excavation is done in rock the bottom shall be cut deep
enough to permit the pipes to be laid on a cushion of sand 75 mm minimum.
The pipes and fittings after they are laid and jointed shall be subjected to hydrostatic
pressure test as approved by the Employer’s Representative and shall satisfactorily pass
the test. Pipe line system shall be tested in sections as the work proceeds, keeping the
joints exposed for inspection. Pipes shall be slowly and carefully charged with water
allowing all air to escape. All draw off taps shall then be closed and water pressure
gradually raised to test pressure. Care shall be taken to ensure that pressure gauge is
accurate and preferably should have been recalibrated before the test. Pump used having
been stopped; the section of the pipeline shall maintain the test pressure for at least half
an hour. Any joints or pipes found leaking shall be removed and replaced by the
The G.I. pipe line shall be cut to the required length at the position where the meter and
stop cock are required to be fixed. The ends of the pipes shall be threaded. The meter
and stop cock shall be fixed in position by means of connecting pipe, G.I. nuts, sockets,
etc. The stop cock shall be fixed near the inlet of the water meter. The paper disc
inserted in the ripples of the meter shall be removed and meter installed exactly
horizontally or vertically and with the arrow cast on the body of the meter pointing in the
direction of flow. Care shall be taken that the factory seal of the meter is not disturbed.
Whenever the meter is to be fixed to a newly fitted pipe line, the pipe line will have to
be completely washed before fixing the meter. For this purpose, a connecting piece of
pipe equal to the length of the meter is to be fixed on the new pipe line. The water shall
be allowed to flow completely to wash the pipe line and then the meter installed as
described above by replacing the connecting piece.
Stoneware pipes and fittings:
All pipes with spigot and socket ends shall conform to IS: 651/3006 and shall be of grade
`A'. These shall be sound, free from visible defects such as fine cracks or hair cracks. The
glaze of the pipes shall be free from crazing. The pipes shall give a sharp clear note when
struck with a light hammer.
The following information shall be clearly marked on each pipe and fitting:
(a) Internal diameter;
(c) Date of manufacture;
(d) Name of manufacturer or his registered trade-mark or both.
All pipes and fittings shall have ISI mark.
Jointing of GSW pipes and fittings shall be done as per the requirements of the following
Employer’s Requirements and the relevant IS. After jointing, extraneous material if any
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
shall be removed from the inside of the pipes and fittings and the newly made joints shall
be thoroughly cured. In case, rubber sealing rings are used for jointing, these shall
Spigot and Socket Joint (Cement Joint):
The spigot of each pipe shall be slipped home well into the socket of the pipe previously
laid and adjusted in the correct position. In each joint, spun yarn soaked in neat cement
slurry or tarred gasket shall be passed around the joint and inserted in it by means of a
caulking tool. More skeins of yarn or gasket shall be added if necessary and shall be well
caulked. Yarn or gasket so rammed shall not occupy more than one- fourth of the depth
or socket. Cement mortar (1:1) shall be slightly moistened and carefully inserted by hand
into the remaining space of the joint after caulking of yarn or gasket. The mortar shall
than be caulked into the joint with a caulking tool. More cement mortar shall be added
until the space of joint has been completely filled with tightly caulked mortar. The joint
shall then be finished of neatly outside the socket at an angle of 45 degrees. The cement
mortar joints shall be cured at least for seven days before testing.
The approximate quantity of cement required for each joint for certain common sizes of
pipes are given below for guidance:
Nominal diameter of pipe (mm) Cement (kg)
Spigot and Socket Joint (Bituminous Joint):
The general requirements for this type of joint shall be as specified in the material for
jointing shall consist of composition of asphalt and sand in the ratio of 1:7. Asphalt and
sand shall be boiled together and filled into the socket in a molten state with the aid of
special moulds.
Spigot and Socket Joint (Rubber Ring Joint):
The pipe with the rubber ring accurately positioned on the spigot shall be pushed well
home into the socket of the previously laid pipe by means of uniformly applied pressure
with the aid of a jack or similar appliance. The rubber rings conforming to IS: 5382 shall
be used, and the manufacturer's instructions shall be deemed to form a part of this
Employer’s Requirements. The rubber rings shall be lubricated before making the joint
and the lubricant shall be soft soap water or an approved lubricant supplied by the
Cleaning of Pipes:
As soon as a stretch of GSW pipes has been laid complete from manhole to manhole or for
a length as approved by the Employer’s Representative, the Contractor shall run through
the pipes both backward and forward a double disc or solid or closed cylinder 50 mm less
in diameter than the internal diameter of pipes. The open end of an incomplete stretch
of pipeline shall be securely closed as approved by the Employer’s Representative to
prevent entry of mud or silt etc. If as a result of the removal of any obstruction the
Employer’s Representative considers that damages may have been caused to the pipe
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
lines, he shall be entitled to order the length to be tested immediately. Should such test
prove unsatisfactory the Contractor shall repair the pipeline and carry out such further
tests as are required by the Employer’s Representative.
It shall also be ascertained by the Contractor that each length from manhole to manhole
or the length as approved by the Employer’s Representative is absolutely clear and
without any obstruction by means of visual examination of the interior of the pipeline
suitably illuminated by projected sunlight or otherwise.
After laying and jointing of GSW pipes is completed the pipe line shall be tested as per
the following Employer’s Requirements and as approved by the Employer’s
Representative. All equipment for testing at work site shall be supplied and erected by
the Contractor. Water for testing of pipeline shall be arranged by him. Damage during
testing shall be the Contractor's responsibility and shall be rectified by him to the full
satisfaction of the Employer’s Representative. Water used for test shall be removed from
pipes and not released to the excavated trenches. After the joints have thoroughly set
and have been checked by the Employer’s Representative and before backfilling the
trenches, the entire section of the sewer or storm water drain shall be proved by the
Contractor to be water tight. Before commencing the hydraulic test, the pipelines shall
be filled with water and maintained full for 24 hours by adding water, if necessary, under
a head of 0.6 m of water. The test shall be carried out by suitably plugging the low end of
the drain and the ends of connections, if any, and filling the system with water. A
knuckle bend shall be temporarily jointed at the top end and a sufficient length of
vertical pipe jointed to it so as to provide the required test head; or the top end may be
plugged with a connection to a hose ending in a funnel which could be raised or lowered
till the required head is obtained and fixed suitably for observation. The pipeline shall be
subjected to a test pressure of at least 2.5 m head of water at the highest point of the
section under test. The tolerance of two liters per centimeter of diameter per kilometer
may be allowed during a period of 10 minutes. Any leakage including excessive sweating
which causes a drop in the test water level will be visible and the defective part of the
work should be removed and made good. If any damage is caused to the pipeline during
the execution of work or while cleaning/testing the pipeline as specified. The Contractor
shall be held responsible for the same and shall replace the damaged pipeline and re-test
the same to the full satisfaction of the Employer’s Representative.
Water for testing of pipeline shall be arranged by the Contractor.
Stop Cock and Bib Cock:
A bibcock (bib tap) is a draw off tap with a horizontal inlet and free outlet and stopcock
(stop tap) is a valve with a suitable means of connections for insertion in a pipe line for
controlling or stopping the flow. They shall be of specified size and shall be of the screw
down type. The closing device should work by means of a disc carrying a renewable non-
metallic washer, which shuts against water pressure on a seating at right angles to the
axis of the threaded spindle which operates it. The handle shall be either crutch or
butterfly type securely fixed to the spindle. The cocks shall open in anti-clockwise
direction. When the bib cocks and stop cocks are required to be chromium plated, the
chromium plating shall be of service Grade No. 2 conforming to IS.1068. in finish and
appearance, the plated articles shall be free from plating defects such as blisters, pits,
roughness and shall not be stained or discolored.
These fittings shall be of brass heavy class; chromium plated (C.P) and of approved
manufacture and pattern with screwed of flanged ends as specified. The fittings shall in
all respects comply with the requirements of IS.781. The standard size of brass fittings
shall be designated by the nominal bore of the pipe to which the fittings are attached. A
sample of each kind of fitting shall be approved by the Employer’s Representative and all
supplies made according to the approved samples.
VOLUME IIB Technical Specifications Civil NC-09 (Maliya to Bhachau)
All cast fittings shall be sound and free from laps, blow holes and fittings, both internal
and external surfaces shall be clean, smooth and free from sand etc. Burning, plugging
stopping or patching of the casting shall not be permitted. The bodies, bonnets, spindles
and other parts shall be truly machined and when assembled the parts shall be axial,
parallel and cylindrical with surfaces smoothly finished. The area of the waterway of the
fittings shall not be less than the area of the nominal bore.
The fittings shall be fully examined and cleared of all foreign matter before being fixed.
The fittings shall be fitted in the pipe line in a workman like manner. The joints between
fittings and pipes shall be made leak- proof. The joints and fittings shall be leak proof
when subjected to a pressure test approved by the Employer’s Representative and the
defective fittings and joints shall be replaced or redone.
Soak pit shall be constructed at the location specified by the Employer’s Representative.
Earthwork excavation shall be carried out to the exact dimensions. Brick masonry lining
with open joints shall be constructed in the pit up to 150 mm below the outlet pipeline.
Brick masonry in cement mortar 1:6 shall be constructed above this level up to ground.
Well burnt brick aggregates of nominal size 40 mm to 80 mm and coarse sand shall be
filled within the chamber. Construction of pit lining and filling of the brick ballast shall
progress simultaneously.
Manholes shall be constructed at places approved by the Employer’s Representative.
Excavation, shoring, dewatering etc. for the pits of manholes, laying of pipes and
fittings/specials shall be done in accordance with Employer’s Requirements described
elsewhere in the document.
The bed concrete for manholes shall be done in accordance with Employer’s
Requirements described elsewhere in the document.
Precast reinforced concrete slab shall be casted on top of chambers in pieces as directed.
Bricks to be used for construction of manholes shall conform to the relevant Indian
Standards. They shall be sound, hard, and homogeneous in texture, well burnt in kiln
without being vitrified, table moulded, deep red, cherry or copper colored, of regular
shape and size and shall have sharp and square and parallel faces. The bricks shall be
free from pores, chips, flaws or humps of any kind. Bricks containing ungrounded
particles and/or which absorb water more than 1/6th of their weight when soaked in
water for twenty-four hours shall be rejected. Over burnt or under burnt bricks shall be
liable to rejection. The bricks shall give a clear ringing sound when struck and shall have
a minimum crushing strength of 50 kg/sq.cm. Unless otherwise noted in drawings. The
class and quality requirements of bricks shall be as laid down in IS:
The size of the brick shall be 23.0 x 11.5 x 7.5 cm. unless otherwise specified; but
tolerance up to full-size brick shall be
used for masonry work. Brick bats shall be used only with the permission of Employer’s
Representative to make up required wall length or for bonding. Sample bricks shall be
submitted to the Employer’s Representative for approval and bricks supplied shall
conform to approved samples. If required by the Employer’s Representative, brick sample
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
1. VOL 1A Tech Bid NC-09.pdf
2. VOL -1B _GCC_NC-09.pdf
3. VOL 1B PART - 2 NC-09.pdf
4. VOL 1B PART -3 NC-09.pdf
5. VOL 1B PART-4 EMD GR DMO 2941 01-Apr-2026 744.pdf
6. VOL 1B PART-5 GST circular.pdf
7. VOL II A Extent of work and Tech Specification NC-09.pdf
8. VOL IIB Civil Tech. Spec Sch-C NC-09.pdf
9. VOL II C Technical Specification Electromechanical works NC-09.pdf
10. Volume III Price Bid -NC-09.pdf
11. O and M Colour work related.pdf
12. VOL IV General Condition of OnM Contract NC-09.pdf
13. Indicative Drawing.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .