Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Tender Value
₹33.3 L
EMD Value
₹99,872
Closing Date
27 Jan 2026, 6:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
CHIEF ENGINEER (G)
Miscellaneous civil works for maintenance of plant in PH area at Gandhinagar TPS
245503
EW-257
Open
Miscellaneous Works
Works
Gandhinagar
2 documents required · 2 mandatory
₹2,950
Gujarat State Electricity Corporation Limited Payable at Gandhinagar
₹99,872
8 Dec 2025
8 Dec 2025
8 Dec 2025
27 Jan 2026
8 Dec 2025
Name of Work: Miscellaneous civil works for maintenance of plant
in PH area at Gandhinagar TPS
AT GSECL Gandhinagar TPS
EW- 257 PUR-F-006 RFQ-74075
NAME OF WORK: Miscellaneous civil works for maintenance of plant in PH
area at Gandhinagar TPS
DESCRIPTION PAGE NO.
ACKNOWLEDGEMENT OF TENDER FEE /EMD. 3 To
TENDER NOTICE.
DECLARATION FORM CUM UNDER TAKING TO BE
SIGNED BY BIDDER
RTGS DETAILS OF BIDDER
PROJECT SYNOPSIS
SCOPE OF WORK AND SITE CONDITION
SPECIAL NOTE FOR PRE-QUALIFICATION
GENERAL INSTRUCTION TO THE TENDERER
GENERAL CONDITIONS OF CONTRACT
TERMS AND CONTRACT FOR WORKS 62 To
GENERAL SAFETY RULES & LIST OF SAFETY TOOLS
PERFORMA FOR BANK GUARANTEE
INTEGRITY PACT
CERTIFICATE – A
ANNEXURE – I (DETAILS OF BANK FOR SOLVEANCY &
SPECIAL CONDITIONS FOR USE OF CEMENT
APPROVED NAME OF MANUFACTURERS OF 78 To
GENERAL GUIDELINES RELEVANT TO I.S.
GENERAL SPECIFICATIONS
TECHNICAL SPECIFICATION
DETAIL SPECIFICATION
SCHEDULE-B 122 To
Safe Maintenance Procedure
EW- 257 PUR-F-006 RFQ-74075
ACKNOWLEDGEMENT OF TENDER FEE /EMD
TENDER NOTICE
EW- 257 PUR-F-006 RFQ-74075
GUJARAT STATE ELECTRICITY CORPORATION LIMITED
Gandhinagar Thermal Power Station, Gandhinagar, India–382041.
[email protected] Website: www.gsecl.in
CIN:U40100GJ1993SGCO19988
E- Tender for the
Miscellaneous civil works for maintenance of plant in PH area at Gandhinagar TPS
TENDER FEE PAID VIDE DEMAND DRAFT NO. _________________________________
EARNEST MONEY DEPOSIT PAID VIDE D.D. NO. _______________________________
1. The undersigned reserves the right to reject any or all tenders without
assigning any reasons thereof.
2. The Tender fee will be accepted in form of Demand Draft and Earnest Money Deposit
will be accepted in form of Demand Draft or Bank Guarantee of any bank as prescribe in
ANNEXURE- I drawn in favour of “GUJARAT STATE ELECTRICITY CORPORATION
LTD.” payable at Gandhinagar TPS
For & On behalf of GSECL
CHIEF ENGINEER (Gen)
SIGNATURE OF CONTRACTOR GSECL: GTPS
EW- 257 PUR-F-006 RFQ-74075
GUJARAT STATE ELECTRICITY CORPORATION LIMITED
Gandhinagar Thermal Power Station, Gandhinagar, India–382041.
[email protected] Website: www.gsecl.in
CIN:U40100GJ1993SGCO19988
Tender Notice No: GSECL/___/ __/ For Civil works
CE [Generation], Gandhinagar, TPS invites “On-line Tenders” (e-tendering) for the work of Miscellaneous
civil works for maintenance of plant in PH area at Gandhinagar TPS. Tender Papers & Specifications may be
down loaded from Web site https://gsecl.nprocure.com(For view, down load and on line
submission) and GUVNL / GSECL web sites www.gsecl.in (For view only).All tender documents are to
be upload (Notarized / self-attested copies of original – as specified in tender document) through online
only (mandatory) on (n) procure portal excluding Tender fee and EMD Tender fee and EMD are to be
submitted physically by Registered Post A.D. or Speed Post addressed to: CHIEF ENGINEER
(GENERATION), GUJARAT STATE ELECTRICITY CORPORATION LTD, THERMAL POWER
STATION, GANDHINAGAR-382041, GUJARAT. “NO COURIER SERVICE OR HAND DELIVERY” will be
Tender Estimated E.M.D.
Name of Work Time Limit Fee Rs.+
No. Cost Rs. Rs.
EW-257 Miscellaneous Rs. 12 Rs. 2500+ Rs.
civil works for 3329080.76 (Twelve) 450 = Rs.
maintenance of Months 2950/-(Two (Ninety Nine
plant in PH area from the Thousand Thousand
at Gandhinagar date of Nine Eight
TPS written hundred Hundred
order to Fifty only Seventy Two
commence (Non Only)
the work. Refundable)
180 Days [From the opening of
1 Validity of Tender
Technical Bid].
Last Date for Online tender / offer submission through
2 As per Tender Notice
(n)Procure only up to 18:00 Hrs(This is Mandatory)
Last Date for physical receipt of cover for DD / Bank Guarantee
3 / Online payment reference for Tender Fee and EMD only up to As per Tender Notice
15:00 Hrs Through RPAD or Speed Post Only
Date of opening of online Technical Bid, all relevant documents
submitted through online process, Cover for Tender fee and
4 As per Tender Notice
EMD at 15:30 Hrs (Online technical bid will be opened for
Bidders who have submitted Cover for Tender Fee and EMD)
Tentative date of on-line opening of price bid (if possible) at Party has to be in touch with
15.30 hrs. website www.nprocure.com and
also with e-mail sent by above
For & On behalf of GSECL
CHIEF ENGINEER (Gen)
SIGNATURE OF CONTRACTOR GSECL: GTPS
EW- 257 PUR-F-006 RFQ-74075
1) Only following listed documents must be upload in n-process online only. No physical documents are to be
submitted except tender fee and EMD cover. Price Bid shall not be submitted in Hard copy.
1. Demand Draft for Tender Fee and EMD (Original) cover only to submit through RPAD/Speed post only.
2. The bidder shall have a separate Provident Fund Code of RPFC in the name of company. The bidder, who
does not possess such separate P.F. code, shall not be considered for acceptance of tender. The contractor
has to submit attested copy of such certificate showing P.F. code along with the tender.
3. Attested copy of PAN No.
4. Attested copy of work experience certificate for the similar works executed.
5. List of work in progress.
6. Attested copy of firm registration [Applicable only to the firms registered under Company Law]
7. Attested copy of partnership deed. [Applicable only to the partnership firms.]
8. Attested copy of power of attorney, if any, for signing the bid document.
9. Attested copy of balance sheet of profit & Loss account duly audited by Chartered Accountant of at least
financial years, if work estimate is more than Rs. 50 Lacks.
10. Attested copy of latest solvency certificate not older than 12 months issued by any nationalized bank OR
Banks as per Annexure – I.
11. Details of equipment, tools and plants immediately available with the tenderer for use of this work.
12. Details of technical personnel.
13. Undertaking duly Notarized as per attached Declaration Form
14. Any other documents required to verify technical, financial capability of the bidders & other Credentials
15. Attached The Copy Of GST Registration.
All such documents should be strictly uploaded in N-procure only expect Tender Fee and EMD details cover.
Otherwise the offer will not be considered and no any further communication in the matter will be
2) In case any deviation is found in Data / Details / Documents uploaded on N-procure online offer (e-tendering)
documents then such tender will not be considered and no any further communication in the matter will be
entertained. Tenders must be un-conditional. Conditional Tenders will be rejected.
3) Further bidders are requested to submit Technical Bid documents and price – bid i.e. Schedule-B on line only
and not to submit the Technical bid and price bid in physical form expect Tender Fee and EMD details cover.
This is mandatory. If Technical bid document and price bid is submitted in physical form expect Tender Fee
and EMD details cover, same will not be opened and only on-line Uploaded/submitted Technical bid document
and price will be considered for evaluation. The bidder is requested not to upload/submit the by
online (n)procure while bid submission on in (n)procure tender document, condition of the
contract, specification & other relevant documents, except documents as stated here above.
Instead of the same, the bidder shall upload on (n) procure scan copy of the duly Notarized Undertaking as
stated below declaration form on the stamp paper of Rs. 300/-. However, bidder may download tender
document & preserve with them in Hard Copy for their future reference. Later on, L1 bidder shall
be asked to collect the tender documents from the tender inviting authorities for the purpose of
contract agreement execution and place their signature with seal of the company.
4) It is mandatory for all the bidders to submit their tender documents viz. on-line (e-tendering) and uploading
on (n) procure in scheduled time. Tender documents submitted in physical form will not be accepted and
considered expect Tender Fee and EMD details cover. Also, all bidders shall submit required Physical
documents as stated in Tender Notice
5) GSECL reserves the rights to reject any OR all tenders without assigning any reasons thereof.
6) Tender Notice Number & name of the work shall be clearly written on the covers of containing the Tender Fee
7) Technical / Price Bids will be opened on the day and time indicated in the tender notice by an Officer nominated
by the Purchaser in the presence of such of the bidders who wish to be present. Any technical questions,
information and clarifications that may be required pertaining to this tender should be referred to the CHIEF
ENGINEER (GEN.) Gandhinagar TPS. Also during pre-bid meeting (if arranged) the same may please be
The exemption in payment of Tender Fee & EMD shall be given to the,
1. Micro & small-scale enterprises which participate directly in tendering process
for the product which they are manufacturing / service which they are
providing and have Udyam registration for items / service under procurement.
2. Startups which participate directly in tendering process for the product which
they are manufacturing / service which they are providing and recognised by
DPIIT under the Start-up India Program and has obtained Udyam registration.
EW- 257 PUR-F-006 RFQ-74075
3. Organization which has registration certificate for the manufacturing product of
the tender, from Gujarat Khadi Gramodyog Board or Khadi and Village
Industries Commission(K.V.I.C)or Commissioner of Cottage Industries.
4. Board/Corporations/PSUs of the Central/State Government for their own
manufactured items.
5. State Government recognized organizations like(i) organizations for blinds,
dumb and deaf, disabled, mentally disabled persons;(ii)women's self-help group
recognized by Gujarat Livelihood Promotion Company; which participate
directly in tendering process for the product which they are manufacturing /
service which /they are providing.
For & On behalf of GSECL
CHIEF ENGINEER (Gen)
SIGNATURE OF CONTRACTOR GSECL: GTPS
EW- 257 PUR-F-006 RFQ-74075
DECLARATION FORM CUM UNDER TAKING TO
BE SIGNED BY BIDDER
RTGS DETAILS OF BIDDER
PROJECT SYNOPSIS
SCOPE OF WORK AND SITE CONDITION
SPECIAL NOTE FOR PRE-QUALIFICATION
GENERAL INSTRUCTION TO THE BIDDER
EW- 257 PUR-F-006 RFQ-74075
(To be uploaded on (n) procure online process duly notarized on Rs. 300/- Non –
Judicial Stamp Paper)
DECLARATION FORM
Name of Work: Miscellaneous civil works for maintenance of plant in PH area at Gandhinagar
Tender No/ RFQ No:
1. I/We hereby declare that I/We have carefully studied the entire tender placed on the
WEB site and conditions of contract, specifications and other documents of this work
mentioned in the tender and abide by the same. Also, I/We hereby agree to execute the
same accordingly.
2. I/We hereby abide to execute the contract agreement by downloading the copies of the
conditions of contract, specifications and other documents of this work of otherwise I/we
will get copy of the same from the office of the tender inviting authority and the same
will be acceptable to me/us.
3. I/We hereby accept and confirm that any dispute on this regard shall not be entertained
by the tender inviting authority.
4. I/We hereby declare that I/We have visited the work site and fully acquainted
myself/ourselves with the local situations regarding materials, labour and other factors
pertaining to the work before submitting the tender.
5. I/We hereby confirm that our offer is Un-conditional and without any technical &
commercial deviations.
6. Should this tender be accepted, I /We hereby agree to abide by to fulfill all the terms-
conditions and provision of the Tender and Contract for Works as applicable and default
thereof, to forfeit and to pay to the Gujarat State Electricity Corporation Limited the
sums of money due.
EW- 257 PUR-F-006 RFQ-74075
7. The full value of the “Earnest Money Deposit” paid herewith should be absolutely
forfeited to the Corporation, should I/ we do not execute / commence the work after
issuance of date of commencement by GSECL.
8. If, I fail to submit all required documents with application or tender copy ( in each
tender ) then my tender will be cancelled, which is binding to me.
9. If, full or part work will be given to me, it will be accepted to me with same terms, rate
10. I, ______ proprietor / owner / partner / Authorized Agent of M/s. ______ do hereby also
declare and undertake as under:
a) That in capacity of independent contractor for M/s. ______ (Sub-Contractor of
M/s. ______ ) worked as contractor at GSECL, ___________Thermal Power Station for
the nature of work of ______ against work Order No. ______ Dt. ______., I have
complied with the provisions of all laws as applicable. I have paid the wages for the
month/s of my contractual period which is / are not less than the minimum rates as
applicable, to all my employee/s and no other dues are payable to my employee/s.
b) That I have covered all the eligible employee/s under the Employees’ Provident
Funds and Miscellaneous Provisions Act, 1952 and deposited the contributions under my
PF Code No. ______, place: ______ for the month/s of my contractual period and as
such no amount towards contribution whatever is payable.
c) I further declare and undertake that in case any liability pertaining to any of my
worker, labour, employee/s is/are to be discharged by the principle employer i.e.
Gujarat State Electricity corporation Limited, ___________Thermal Power Station due
to my lapse, I undertake to reimburse the same or the principle employer is authorized
to deduct the same from my dues as payable.
d) I further declare and undertake the legal consequences which may arise in future
under the said work order awarded, and I bond myself to resolve the same at the risk
and cost of M/s. ______.
authorized signatory of M/s ______________________________________________
and their proprietor / any partner / any directors of the firm is not stop deal and / or
banned for business dealing and / or black listed by GUVNL and / or their any
subsidiary company viz. GSECL / GETCO / DGVCL / MGVCL / UGVCL / PGVCL as well as
Government and / or Semi Government company / department.
Seal & Signature of the Bidder
Phone / Mobile/ Fax No. & Company’s Seal
EW- 257 PUR-F-006 RFQ-74075
E- Tender for the work of Miscellaneous civil works for maintenance of plant in PH area at
Gandhinagar TPS
RTGS DETAIL OF BIDDER
Following RTGS details shall be submitted by agency along with the tender for direct deposit of
payment to the beneficiary account. Bidder has to submit the details as under:
1 Name of Bidder :-
2 Address for correspondence :-
4 Phone / Mobile No. :-
5 Name of Beneficiary :-
6 Bank Account Number of :-
7 Name of Bank of beneficiary :-
8 Name of Bank, branch & address :-
9 Type of account :-
10 Bank Code :-
11 RTGS Code :-
12 IFSC Code :-
EW- 257 PUR-F-006 RFQ-74075
Project Synopsis and Data
1) Location :- Gandhinagar Thermal power station
2) Purchaser :- GUJARAT STATE ELECTRICITY CORPORATION
3) Engineer :- Chief Engineer(Gen)
4) Site of Project :- Gandhinagar,Gujarat State
5) Nearest town :- Gandhinagar
6) Nearest Railway Station :- Gandhinagar Capital(Ahmedabad is situated at a
distance of about 30.00Km)
7) Nearest Port :-
8) Nearest Air Port :- Ahmedabad-20Km(Approx)
9) Access Road :-
10) Site Elevation from MSL :- RL 81.5 M(floor level)
11) Meteorological Data
Ambient Air temperature
1] Highest monthly mean of daily Max. :- 350 C
Temperature ( In 0C)
2] Maximum dry bulb :- 450 C
Temperature ( In 0C)
3] Minimum dry bulb :- 8.60 C
Temperature ( In 0C)
1] Average annual rainfall (In :- 1000 to 1200mm
2] For 01 hour ( In mm) :- 75 to 100mm
3] For 24 hour ( In mm) :- 250mm
Wind velocity
1] Maximum wind velocity (In :-
2] Wind direction – N,NE & SW :-
3] For 24 hour ( In mm) :-
Relative Humidity
1] Annual mean humidity ( In %) :- 50 to 60%
2] Maximum humidity (In %) :- 98%
3] Minimum humidity (In %) :- 2%
4] Type of Atmosphere :- Dry
12) DESIGN DATA
Seismic Data :-
Zone :- Zone-III as per IS 1893-1975
Ambient temperature :-
Other Data :-
EW- 257 PUR-F-006 RFQ-74075
SCOPE OF WORK AND SITE CONDITIONS
The main scope of the work is to carryout miscellaneous civil works for maintenance of plant as
and when requirement of running plants, maintenance sections of Gandhinagar power station whole
power station inside area (Anywhere and at any height).
Under the scope of this tender the agency has to carry out the subject work, various works as per
all items of Schedule B and as per detail technical specifications items. The quantities taken under
individual items are very tentative. However, the agency has to carry out the works as per the
Company’s requirements (Anywhere in PH Area).
The agency has to carry out the works as per item & specifications of the tender by providing all
materials of best quality and of standard manufactures as the samples approved by EIC and
providing best workmanship through expert manpower.
The agency has to carry out the works as per the priority & schedule given by EIC time to time
even in on or off working hours of the office. The agency will take complete care and will not
damage any other structure in premises of company.
The agency has to carry out all the works by taking all due cares of safety, security norms, with all
risks including scaffolding, strutting, shoring, etc up to any height irrespective of quantum of the
work. Anywhere in Power house premises or as directed by EIC/ as per GSECL requirement.
Contractor has to make arrangement for workable site condition with the cooperation of
departments of company and agencies, all necessary arrangement to get work permit is to be
made by contractor. Day to day cleaning is required after completion of job. The removed
materials and any other unwanted materials are to be transported and taken away as instructed
All safety measures shall be taken by the contractor with his own cost.
The scope of work to be carried out by the Contractor shall also include Clearance of the site,
Disposal of debris, excavated material etc,
The major works involvement generally mentioned as per schedule-B.
For & On behalf of GSECL
CHIEF ENGINEER (Gen)
SIGNATURE OF CONTRACTOR GSECL: GTPS
EW- 257 PUR-F-006 RFQ-74075
Registration in VMS System
Additional Note: Vendor gets to register in VMS System through vms.guvnl.com. For
registration following documents are required and mail to [email protected] and
[email protected]. After registration vendor have to upload the invoice in the VMS
system for smooth functioning of payment.
Documents required for Registration:
(2) GST Certificate Copy
(4) Full Name of Vendor
EW- 257 PUR-F-006 RFQ-74075
SPECIAL NOTE FOR PRE-QUALIFICATION
Name of work: Miscellaneous civil works for maintenance of plant in PH area at
Gandhinagar TPS
The tender documents are of two separate bids i.e. technical and price bids. Bidder is
requested to submit the technical bid with the following credentials for post-qualification.
1. Bidder should produce evidence of having experience of successfully completed similar
works as defined hereunder, carried out in Central & State Government / Semi-Government /
GSECL / GETCO / DGVCL / MGVCL / UGVCL/PGVCL during the last seven years ending last
day of the month previous to the one in which tender is invited. Bidder should submit self-
attested copies of documentary evidence, preferably photo copies of work completion
certificate, certificate regarding works on hand progressing satisfactorily along with
certificate of amount of work done, work order with Schedule-B, etc. from the respective
department. The amount of completed works should be either of the following:-
a. Three similar completed works each costing not less than the amount equal to 40% of
the estimated cost.
b. Two similar completed works each costing not less than the amount equal to 50% of the
c. One similar completed works each costing not less than the amount equal to 80% of the
2. Similar work means – General Civil Construction / Civil Maintenance works. The work
of housekeeping, horticulture, cleaning, anti-termite, fabrication will not be considered in
3. Experience certificate of work executed with private firm shall not be accepted. Experience
as a joint venture or sub-contractor is not allowed and price bid of such bidders will be
4. EMD: To pay EMD in form of DD OR in form of B.G. given by bank as described in
the Annexure – I.
5. Tender Fee: The tender fee shall be accompanied in the form of DD.
6. Separate employee’s Provident Fund code number towards registration of firm
with Regional P.F. Commissioner.
7. Financial qualification criteria:
1) The Average Annual Turnover of the bidder, shall not be less than 30% of estimated cost
during the preceding three (3) financial years as one date of Techno-Commercial bid
2) Net worth of bidder shall not be less than 100% of the bidder’s paid up share capital as on
the last day of the preceding financial year. In case the Bidder meets the requirement of
Net worth based on the strength of its Subsidiary (ies) and/or Holding company and/or
Subsidiaries of its Holding Companies wherever applicable, the Net worth of the Bidder
and its Subsidiary (ies) and/or Holding company and/or Subsidiary (ies) of the Holding
Company, in combined manner should not be less than 100% of their total paid up share
capital. However individually, their Net worth should not be less than 75% of their
EW- 257 PUR-F-006 RFQ-74075
respective paid share capitals.
Net worth in combined manner shall be calculated as follows:
Net worth (combined )= (x1+x2+X3)/(y1+y2+y3) X 100, where x1,x2, x3 are individual
net worth which shall not be less than 75 % of the respective paid up share capitals and
y1, y2, y3 are individual paid up share capitals.
3) In case the bidder is not able to furnish its audited financial statements on stand-alone
entity basis, the unaudited unconsolidated financial statements of the bidder can be
considered acceptable provided the bidder further furnishes the following documents
for substantiation of its qualification.
Copies of the unaudited unconsolidated financial statements of the bidder along with
copies of the Audited consolidated financial statements of its Holding Company.
A Certificate from the CEO/CFO of the Holding Company, stating that the unaudited
unconsolidated financial statements form part of the Consolidated Annual Report of the
4) In cases where audited results for the last preceding financial year as on the date of
techno-commercial bid opening are not available, the financial results certified by a
practicing Chartered Accountant shall be considered acceptable. In case, Bidder is not
able to submit the Certificate from practicing Chartered Accountant certifying its
financial parameters, the audited results of three consecutive financial years preceding
the last financial year shall be considered for evaluating the financial parameters.
Further, a Certificate would be required from the CEO/CFO, stating that the Financial
results of the Company are under audit as on the date of Techno-commercial bid
opening and the Certificate from the practicing Chartered Accountant certifying the
financial parameters is not available.
5) The bidder must submit Average Annual Turnover and Net worth Certificate in support
of Financial QR, duly certified and verified for authenticity from Independent Statutory
Auditor of their company / Practicing Charted Accountant/ C.A. Firms / TPIA (Third-
Party Inspection Agency ) empaneled approved by GSECL, along with copy of Annual
Audited Accounts of last three years.
8. Attested copy of relevant document duly signed and sealed on each and every page shall
9. Attach copy of GST Registration.
10. Details of orders for similar nature/jobs carried out along with documentary Evidence,
Performance Certificate and their organization set up for such work executed in past there
of indicating the Names of the organizations, order no and date.
11. Bidder shall have to submit the PAN card No for Income Tax with documentary proof.
12. Details of the partnership deed.
13. Details of Tools, tackles, equipments and personals available with firm relevant to the
job/subject matter.
14. Copy of the updated valid labor contract license from the appropriate authorities and
updated workman group insurance policy covering labor engaged.
EW- 257 PUR-F-006 RFQ-74075
15. The tenderer shall have to produce the document of last three years annual account, i.e.
profit & loss account and balance sheet, if the estimated cost of tender is more than
lakhs along with technical bid.
16. Details of skilled/semi-skilled persons presently employed by the contractor having
sufficient knowledge of similar jobs.
17.Declaration form in original duly notarized on stamp paper of Rs. 300/- (As referred in
The above documents will be analyzed and after satisfaction, the price bid will be opened.
GSECL may verify the documents, experience certificates from authority who have issued such
certificates / details.
On opening of Technical Bid, if any required attested documents are missing in technical bid
submitted by the bidder, and tender inviting authority is in the opinion that in absence of
these documents sufficient competition is not possible, in that case to have fair competition,
the tender inviting authority may inform only once by Registered post to bidder/bidders to
submit the missing required documents within stipulated time limit and failing which
bidder/bidders will be declared technically disqualified for not submitting the required
documents along with technical bids without any further notice. However, document will be
considered valid only if it is for the period of last day of month previous to the one in which
tenders are invited.
For & On behalf of GSECL
CHIEF ENGINEER (Gen)
SIGNATURE OF CONTRACTOR
EW- 257 PUR-F-006 RFQ-74075
GENERAL INSTRUCTIONS TO THE BIDDERS
1. SUBMISSIOIN OF TENDER
The tender should be uploaded/ submitted online on n-procure process.
Technical bid cover:- This cover shall contain all relevant attested qualifying documents as
prescribed in tender notice along with tender fee & EMD. Bidder shall have submit Tender Fee and
EMD cover only, All other require document to be upload on online (n)procure process only
Note: - If attested copies of qualifying documents stated as prescribed in tender notice are
not found in on-line Technical bid, but same should be submitted by mail during scrutiny
will be treated as final to consider the bid for pre-qualification. Any missing documents, if
required will be asked from the bidder as mentioned in this tender elsewhere. If party has
not submitted tender in online is liable to be ignored.
“Please note that the Notarized / self-attested copies of original required documents
should be invariably uploaded in n-procure portal before due date and time in pdf form
(Scanned copy). This is mandatory. No physical documents are required to be submitted
except tender fee and EMD.
The price bid shall have to be submitted online only. The percentage rates and price shall be written
both in words, and figures and the units in words. In case of any ambiguity or mistakes, the unit rates
and prices written in words shall be considered as final.
Offered rate shall include cost of all Materials, wastage of material , Labours for all leads and lifts,
Supervision, setting out works, Machinery and equipment with its mobilization / demobilization,
transportation charges, Clearing of the site both prior to commencement and after completion of work.
Consumables such as, but not limited to petrol, oil, diesel, lubricants, drill bits, pipes, ropes etc.
Construction facilities such as scaffolding, tarpaulins, wind break, etc., Overheads / profits of
Contractor for due performance of the work under this contract.
Applicability of goods and service tax:-
1) The tenders shall be evaluated on firm price and cost with GST and cess as applicable unless
otherwise mentioned in the tender documents.
2) IF the supplier/contractor have opted for the composition scheme of GST, the same must be clearly
specified with valid declaration and certificate from department. In the event of withdrawal/ cessation
of the supplier from composition scheme during the tenure of the contract, the rate(i. e. price)
mentioned in the price bid shall be final and any additional GST will have to be borne by the tenderer
himself, In no case additional amount towards GST or otherwise will be paid/reimbursed to
supplier/contractor.
3) The bidder shall have to inform their GST no. of the registered place(s) where from the bidder intends
to supply the goods/services, meaning there by the bidder has to supply the goods/services from the
relevant declared/ registered place(s) of supply only.
4) The bidder shall not include GST in their quoted rates; but the bidder has to separately indicate the
GST rate, amount in the price bid schedule.
5) In-case Govt notification comes for change in GST , the same will be applicable.
6) Bidder should indicate GST no.( copy of GST registration to be enclosed) and PAN NO. (copy of PAN to
be enclosed) Tenders submitted without GSTIN No by the firms, the offer will be rejected without
entering into further correspondence.
Further information required, if any, can be had from the office of the Chief Engineer, GSECL, GTPS.
But it must be clearly noted that the tenders must be received complete in every respect by the
due date and time.
i. The bidder must clearly quote rates in figure as well as in words. In case of any discrepancy,
EW- 257 PUR-F-006 RFQ-74075
whatever written in words shall prevail.
ii. No deviation in terms & conditions, Schedule-B and technical specifications will be entertained. Any
ignorance for this shall not relieve the contractor from his contractual liability arising as per tender
documents and conditions contained in it.
iii. The bidders are required to quote only firm prices. No variation will be accepted on price/ raw
materials/ finished products or on any other cause.
iv. The bidders should note that the completion of above mentioned works in all respect in accordance
with the time limit given is very important and should be strictly adhered to. The work is to be
completed in time limit from the date of issue of written order to commence the work by the Chief
Engineer (Gen.), GSECL, Gandhinagar TPS.
v. The bids should be valid for a minimum period of 180 Days from the date of opening of technical
bid. During this period tenderer shall not be allowed to withdraw their tender and if withdrawn, the
Earnest Money Deposit submitted with the tender will be forfeited.
vi. The works covered under these specification shall be carried-out and governed by “Tender and
contract for Works” booklet appended herewith except where conditions specified in this
specifications.
vii. The successful bidder shall have to enter in to an agreement for contract as per G.S.E.C.L rules on a
stamp paper of Rs.300/- and necessary stamp duty charge shall be borne by the
contractor/consultant.
viii. The complete specification comprises of the following.
Bill of Quantities (Schedule-B), instructions to the bidders, Tender specifications and scope of work,
Tender and contract for Works booklet, General Conditions, Instructions to bidder & Technical
specifications. All these sections are complimentary to each other. The particulars and requirements
contained herein shall cover the execution of the works covered under these specifications.
ix. The tenderer must visit the site of works and see for him self the site conditions regarding availability
of approach road during all seasons and other matters affecting the above works before submitting
x. The submission of tender by a contractor implies that he has read these instructions the conditions of
contract etc. and has himself aware of the scope and specifications of the work to be done and of
conditions and local conditions and other factors bearings on the execution of the works. GSECL will
not therefore after acceptance of contractor's rate pay any extra charge for any other reason; in case
the contractor is found later on to have misjudged the site condition.
xi. GSECL’s authorized officers who accepts tender, shall have the right of rejecting all or any of the
tenders and will not be bound to accept the lowest offer nor to assign any reason whatsoever for the
rejection of any tender or all tenders.
xii. Bidders shall provide evidence of their continued eligibility to the satisfaction of the owner.
xiii. Bidders shall not be listed under a declaration of ineligibility for corrupt or fraudulent Practices
issued by the Govt., the list of black listed Contractors announced by GSECL (erstwhile GEB) Govt. of
Gujarat or its Public Sector undertakings or the contractors who are under stop dealing in GUVNL and
/or their any subsidiary company viz. GETCO/MGVCL/UGVCL/PGVCL/DGVCL.
xiv.The bid, and in case of a successful bid, the Form of Contract Agreement, shall be signed with the
name of Firm / company which will be legally binding on all partners / parties.
xv.If the application is made by an individual, it shall be signed by the individual above his full typed
written name and current address.
xvi.If the application is made by a proprietary firm. It shall be signed by the proprietor above his full
typed written name and the full name of his firm with its current address.
xvii.If the application is made by a partnership firm, it shall be signed by all the partners of the firm
above their full type written names and current addresses or alternatively by partner holding
power of attorney for the firm in which case a certified copy of the power of attorney shall
accompany the application. A certified copy of the partnership deed, full names and current
addresses of all the partners of the firm shall also accompany the application.
xviii. If the application is made by a limited company or a Corporation, it shall be signed by the
authorized person holding power of attorney for signing application in which case a certified copy of
the power of attorney shall accompany the application. Such Limited company or Corporation
EW- 257 PUR-F-006 RFQ-74075
may be required to furnish satisfactory evidence of its existence before the pre-qualification
evaluation. They should also furnish Articles of Memorandum of Association. If the application is
made by group of companies, it shall be signed by the authorized person. The authority letter shall be
accompanied with the application.
1. SECURITY DEPOSIT
It should be mandatory to submit security deposit as per cl no.7 of Section C (i.e General
condition of contract).
2. MAINTENANCE: Not Applicable.
3. TIME LIMIT FOR WORK:
The scheduled time limit for the completion of work shall be 12 (Twelve) calendar months from the
date of issue of letter to commence the work. However extension in time limit will be granted by
GSECL for the genuine reasons only as per terms of the contracts.
4. TERMS OF PAYMENTS:
Contractor shall be paid RA bill after observing GSECL’s general procedure and submission of bill
by the agency. Also, 75% payment shall be made immediately within a week period on receipt of
recorded bill by Account Section without checking of detail bill and compliance of queries &
statutory requirement. However, remaining balance 25% amount shall be released only after
through checking of detail bill and compliance of various quarries, statutory compliance etc. The
above payment term is applicable to all the bills of general civil works & ARC/BRC works,
provided the bills are recorded regularly and submitted to Account Section within Ninety [90]
days. If the contractor fails to submit the bills regularly in such a way so that the same cannot be
recorded and submitted to account section within Sixty [60] days, ad-hoc payment as stated
above, may not be released and payment will be released as per GSECL’s general procedure. The
period of Sixty [60] days shall be considered from the date of receipt of last R.A. Bill by Account
5. METHOD OF PAYMENT:
a. The payment for the work done will be made by running bills every month after taking
joint measurement within 30 days.
b. Final bill will be paid within reasonable time after settlement of material account by
you and after recording of joint measurement.
6. (Applicable for Works tender having estimated cost above Rs 25 Lakhs
(without Tax)): “All bidders shall submit the details/documents in support of
Technical Qualification Requirements duly certified and verified for authenticity from
Specified Third-Party Inspection Agency (TPIA) or Statutory Auditor of their
Company or Practicing CA/CA Firm along with a certificate regarding verification of
authenticity of documents as per the format placed at Appendix 1. All the documents
submitted by the bidder in support of meeting Technical QR shall be digitally signed
by the Specified Third-Party Inspection Agency (TPIA) or Statutory Auditor of their
Company or Practicing CA/CA Firm. In case documents are certified & verified for
authenticity through TPIA, the verification and certification of authenticity of
documents is acceptable from any of the following TPI As:
1. M/s Competent Inspectorate and Consultants Pvt. Ltd, Hyderabad, India.
2. M/s Gulf Lloyds Industrial Service India Pvt. Ltd.-Ahmedabad.
3. M/s International Certifications Services.
4. M/s Intertek India Pvt. Ltd.
5. M/s SGS India Pvt. Ltd.
6. M/s Moody International (India) Pvt. Ltd.
7. M/s TUV SUD South Asia (P) Ltd.
8. M/s TUV Rheinland (India) Pvt Ltd.
9. M/s Bureau Veritas (india) Pvt. Ltd.
10. Hertz Inspection & services Pvt. Ltd.
11. IRCLASS Systems and Solutions Pvt. Ltd.
EW- 257 PUR-F-006 RFQ-74075
The Bidder shall be responsible to get their documents/ credentials verified &
certified by the Specified Third- Party Inspection Agency (TPIA) or Statutory Auditor
of their Company or Practicing CA/CA Firm in support of Technical QR. All the
costs pertaining to third party verification and certification (including those by
statutory auditors) shall be borne by the Bidder. GSECL shall have no liability
(financial or otherwise) towards the same and shall not be liable for any claim/
dispute between the bidder and the Specified Third-Party Inspection Agency (TPIA)
or Statutory Auditor of their Company or Practicing CA/CA Firm.”
Undertaking from Third Party Inspection Agency/Statutory Auditor or Practicing
(On letter head digitally signed by a person duly authorized to Sign on behalf of the firm)
Power Station ……………….
Subject: Authentication of veracity of documents submitted by M/s …… in support of
Meeting the Qualifying Requirements
Ref: Tender no. …………………..
Name of the Package/ Tender: ………………………………………
M/s. ……………… (here in after called Bidder) having Registered office at ……………………
intend to participate in above referred tender of GSECL.
The tender condition stipulates that the bidder shall submit supporting Documents
pertaining to Qualifying Requirement duly verified and certified by Third-Party Inspection
Agency (TPIA) or Statutory Auditor of their Company or Practicing CA/CA Firm as per the
list mentioned in the bidding documents.
In this regard, it is hereby confirmed that we have examined the following documents,
which are also attached with this letter. The same has been verified from the Original
Documents and / or Client for authenticity.
We hereby confirm that the following documents are found to be genuine and authentic.
1. Doc ref. no. ……….. Dated …….. (Name of Documents)
2. Doc ref. no. ……….. Dated …….. (Name of Documents)
All the aforesaid documents have been digitally signed by us as a certificate of
We further confirm that we neither have any vested interest in aforesaid tender nor have
any conflict of interest in respect of above tender.
EW- 257 PUR-F-006 RFQ-74075
This certificate is issued at the request of M/s ………………. (Bidder) for the purpose of
participating in the subject tender/s
Thanking you, ……………………
The rights and liabilities of the contractor shall not be assigned or transferred by them without the
consent in writing of the GSECL to any other person, firm or organization.
2. The successful Bidder, on receipt of letter of intent will submit within a week's time his planning
/ programme of works, for scrutiny of the GSECL in a Bar Chart format, clearly indicating GSECL's
inputs also. Contractor will plan his works such that simultaneous work should progress in such a way
that entire job is completed in scheduled time limit on all the fronts released by GSECL.
3. The successful bidder will have to depute his authorized representative to attend progress
review meetings to be held at GSECL, Gandhinagar TPS without any extra cost.
4. The Contractor will be responsible for complying with all rules and regulations and labour laws
applicable to him and the GSECL will not be responsible for any lapses committed by them. If there is
any claim from any Government authority pertaining to the contract, the same amount will be
deducted from the Contractor's bill.
5. The time limit for completion of work is stipulated as in the tender will be adhered to.
6. The Contractor's rates should be firm and no variation clause is to be quoted by the Contractor
and GSECL will not accept the same, during contractual period including extended time limit if any.
7. BIDDER TO STUDY, ANALYSE & CONSIDER:
a) The information given in this specification is in good faith and meant to serve as a guide
to the Bidder. It is, therefore, imperative that Bidder shall obtain and examine for himself all the data,
information and particulars required for the satisfactory execution of the work under this tender. The
submission of a bid by Bidder implies that he has fully read the specifications, bid drawings,
instruction to the bidder along with Contract Document and Conditions of Contract, applicable labour
laws, safety norms etc., and has made himself aware of the scope and the specifications for the work
to be performed and local conditions and other features which have a bearing on the cost and
execution of the work. This specification is intended as a general description of quality envisaged for
materials and workmanship and of the finished work. It is not intended to cover minute details. The
work shall be executed in accordance with the best modern practice and to the complete satisfaction
of the Purchaser. Special techniques approved by the Purchaser shall be used if and where found
necessary. This specification shall have precedence if anything contrary to this is stated elsewhere in
the contract documents. The Purchaser’s decision shall be final and binding on the contractor on any
issue arising out of such discrepancies.
b) Inspection of site by bidder:
Before submission of his bid, Bidder shall inspect the site, examine and obtain all information
required and satisfy himself regarding matters such as:
weather characteristics,
Location of site and access, right of way, means of communication & mode of Transport to site,
The type and number of equipment and facilities required
The quantity of various items of the work.
The availability and rates of material.
Labours condition.
Local working conditions, obstructions and hindrances that may arise etc.
Power house, which is under running conditions.
Required GSECL’s security checks.
All materials brought to site only after making entries in security register at Control gate
c) These factors are likely to affect the satisfactory completion of work and or cost thereof. The
submission of a bid by the Bidder will be construed as evidence that such an examination was
made and any later claims/ disputes in regard to rates quoted shall not be entertained or
considered by the GSECL.
d) The site visit shall be done by the bidder on his own responsibility and all liabilities including
EW- 257 PUR-F-006 RFQ-74075
cash, arising out of the site visit shall be at the bidder’s account.
e) Contractor’s scope of work shall also include making all necessary arrangements for access to
work sites, stores and site offices etc. from the nearest approach road to facilitate
transportation of man power, machinery and equipment duly considering the existing site
conditions. No extra claims / costs will be entertained by GSECL.
f) The bidder shall carefully study the work to be carried out & consider all the factors & shall take
into account &consider all the factors such as lead, lift haulage of materials, sequence of
construction, etc. & shall allow for all such information / data in the rates quoted.
g) The GSECL will not pay any extra charges or rate for any reason in case the contractor claims,
after acceptance of contract to have misjudged the site condition. Ignorance of the intents and
contents of the specification document and site conditions shall not be accepted by the Owner
as basis for any claims for compensation.
h) BIDDER shall inspect the site, examine and obtain all information required and satisfy himself
regarding matters such as sub-surface conditions, water records, access to site, communication,
transport, right of way, the type and number of equipment and facilities required for the
satisfactory completion of work, the quantity of various items of the work, the availability and
rates of material, local working conditions, uncertainties of weather, obstructions and
hindrances that may arise etc. which may affect the work or cost thereof, before submission of
his bid. Ignorance of site conditions shall not be accepted by the ENGINEER IN CHARGE as
basis for any claim for compensation.
i) The rates quoted by BIDDER shall be based on his own knowledge and judgment of the
conditions and hazards involved and shall not be based on any representations of the Engineer
in Charge. No claim on this account shall be admitted by the GSECL.
j) The bidders shall submit on online in n-procure with their offer without any deviations in
general terms and conditions of the contract or in technical specifications.
k) Tenders received after the time and date specified in the tender notice will not be accepted.
Once the offer is submitted by bidder before due date of submission, the bidder shall not be
allowed to submit revised/ additional/ modified offer even before due date and time of
submission of tender. However, if the date of issue and/or submission of tender are extended
by the Corporation due to any reason, the bidder may submit if their wishes the
revised/additional/modified offer before extended due date and time of submission.
l) The Corporation reserves the right to accept any tender irrespective of whether it is lowest or
not or to reject all the tenders without assigning any reasons thereof. Tenders deferring from
the technical specifications or the method of bidding in a radical manner may also be rejected.
m) The bidder shall be presumed to have carefully examined the drawings, conditions &
specifications of work & to have fully acquainted themselves with all details of the site
conditions, locations, materials, geological & weather characteristics, labour conditions & in
general all the necessary information and data etc. pertaining to and need for the work.
n) This specification is intended as a general description of quality envisaged for materials and
workmanship and of the finished work. It is not intended to cover minute details. The work shall
be executed in accordance with the best modern practice and to the complete satisfaction of
the Purchaser. Special techniques approved by the Purchaser shall be used if and where found
necessary. This specification shall have precedence if anything contrary to this is stated
elsewhere in the contract documents. The Purchaser’s decision shall be final and binding on the
contractor on any issue arising out of such discrepancies.
o) Each bidder shall also submit a 'Declaration' to the effect that the tenderer is an engineering
construction firm or an association of firm or firm which has successfully carried out large works
of this nature and has adequate organization and experienced personnel to handle this type and
magnitude of work. Information should also be given regarding the constitution of the firm; it’s
authorized, subscribed & paid up capital, the date & place of registration, the place of business,
the names of the directors and other relevant information.
p) It is the intent of the ENGINEER IN CHARGE to incorporate these specification documents in the
final ‘Contract’. BIDDERS are required to review these documents and clearly state in their
proposals their acceptance of the same.
EW- 257 PUR-F-006 RFQ-74075
q) Each page of the bid document including the bid drawings shall be signed, stamped and dated
in ink by the BIDDER as a token of having examined the same. Any correction in price and the
rates entered in the Schedule of Price shall also be signed and dated by the BIDDER in ink,
before submitting the bid. Non-compliance with this condition will make the bid liable for
r) All safety measures as required to be adopted as per the Statutory Regulations and the Safety
Rules of the Plant shall be strictly followed by the Contractor during the execution of the
Contract. The Contractor shall set up a suitable safety organization of his own in this regard.
s) In connection with the execution of the Contract, the Contractor shall comply with all applicable
statutory Rules & Regulations including employment of labours at site.
t) The Contractor shall carry out any and all such works, as may be required, for civil work to be
completed in all respect as per the Contract Specification.
u) If the GSECL Engineer-in-Charge is not satisfied with the progress of work at site, he shall direct
the Contractor to depute more numbers of supervisory personnel/workers to meet the
completion schedules as per the Contract. Upon receiving such direction, Contractor shall
deploy additional personnel within 7 days without any extra cost.
v) The GSECL may during the progress of work, order the removal of part or whole of the work
executed, found not in accordance with the specifications/ instructions. No extra claims shall be
entertained for re-executing or altering of such work.
8. SAFETY MEASURES:
The contractor shall ensure the safety of workers, material and structure including existing
structures during execution of the contract. Safety measures shall be followed during operations
of equipments/machinery being used. No separate payment shall be made for the safety
measures and the quoted rates shall include the cost for all safety measures.
9. COMPLETENESS:
Any technical services as set forth here in above and which might not have been specifically
mentioned in this Contract relating to the work or in the specifications and which are not
expressly excluded therefore but which are necessary for the performance in accordance with
the specifications as an integral part of the painting and misc. Civil works shall be rendered by
the Contractor without any extra cost.
10. TOTAL RESPONSIBILITY
The Contractor shall be solely responsible for the entire technical works / services irrespective
of works / services have been made /rendered by him.
11. PAYMENT TO THE LABOURES:
(a) Contractor has to pay the CPF as well as salary to his skilled/unskilled manpower by cheque
A/c payee only, as per minimum wages & prevailing applicable rules on or before 7th day of
(b) Contractor has to produce challan of PF with list of employees.
(c) Contractor shall have to make payment to his labours in presence of Personal Officer (Estt.)
GSECL, Gandhinagar TPS.
12. CONTRACT AGGREMENT ON ACCEPTANCE:
The successful contractor will have to sign an agreement as per the Gujarat State Electricity
Corporation Ltd.'s rules on stamped paper and the necessary stamp duty charges shall be
borne by the contractor.
On acceptance of the tender the name (s) of the accredited representative (s) of the tenderer
who would be responsible for taking instructions from the Engineers of the GSECL shall be
communicated to Chief Engineer (Gen.) Gandhinagar Power Station, Gujarat State Electricity
Corporation Limited.
13. Unsatisfactory progress of the work:
If the work is found not progressing as per the requirement or found not satisfactory then
GSECL will take such action to get the work done through the other agency at agency’s risk
and cost with 15% supervision charges and same will be recovered from agency.
EW- 257 PUR-F-006 RFQ-74075
14. The EMD will be returned promptly to the unsuccessful bidder except that of L1, L2 & L3 till
the successful contractor pays the Security Deposit as mentioned in tender document or after
the expiry of the validity of the offer, whichever is earlier.
The EMD will be returned to the successful tenderer after he furnishes the Security Deposit for
the tender work. If he fails to furnish the SD, his EMD shall be forfeited and the tenderer will
not be allowed to participate in the tenders invited by this office for a period of ONE Year in
respective Power Station.
The EMD in form of Bank Guarantee shall be valid for Ten Months from the date of
submission of the tender.
15. Effect and validity of Bid: The submission of bid with these documents and specification shall
constitute an agreement that bidder shall have no cause of action or claim against the GSECL for
rejection of his bid. The GSECL shall always be at liberty to reject or accept, split any bid or bids at
its sole discretion and any action will not be called into question and the bidder shall have no claim in
that regards against the GSECL.
16. Stop Deal / Banned for business dealing / Blacklisting :-
Has submitted fake, false or forged documents/certificates
Has revised/ withdrawn price bid after opening of Techno-commercial bid, until and unless it
Has tempered with the stipulated tendering procedure.
Has refused to accept Letter of Acceptance / Purchase order / Work Order after the same is
issued by the company within the validity period and as per agreed terms and conditions,
Has committed breach of contract or has failed to perform a contract or has abandoned the
Has failed to provide suitable expertise for the work as per pre-scheduled program.
Has failed to submit all the necessary tests reports / documents within time scheduled / as
per company’s time limit, as mentioned in the LOA, if the Letter of Acceptance (LOA) is placed
subject to submission of type reports / documents to the firm.
Has indulged in construction and erection of defective works.
Has supplied inferior quality / defective materials and refused to replace with stipulated time
frame, as specified by the company,
Has substituted materials in lieu of materials supplied by the company or has not returned or
has short returned or has unauthorisely disposed of materials / documents / drawings / tools
or plants or equipment supplied by the Company,
Has involved in malpractices such as bribery, corruption, fraud, canvassing and pilferage,
Has unauthorisely obtained official company information or copies of documents, in relation to
the Tender / Contract.
Has failed to follow the stipulated mode of communication, if specified by the tendering
authority / Purchaser.
Has parted with, leaked or provided confidential / proprietary information of the company
given to the firm only for its use (in discharge of its obligations against an order) to any third
party without prior consent of the Company,
Any other ground for which in the opinion of the Company makes it undesirable to deal with
In case the state Government directs the Company to place a firm in stop dealing / banned
for business dealing / blacklisting.
Conflict of Interest among Bidders / Agents
A bidder shall not have conflict of interest with other bidders for particular quoted item. Such
conflict of interest can lead to anti-competitive practices to the detriment of Procuring Entity's
interests. The bidder found to have a conflict of interest shall be disqualified. A bidder may be
considered to have a conflict of interest with one or more parties in this bidding process for
particular quoted item, if:
EW- 257 PUR-F-006 RFQ-74075
a) They have proprietor/partner(s)/Director(s)in common; or
b) They receive or have received any direct or indirect subsidy/financial
stake from any of them; or
c) They have the same legal representative/agent for purposes of this bid; or
d) they have relationship with each other, directly or through common third parties, that
puts them in a position to have access to information about or influence on the bid of
another bidder, or
e) bidder participates in more than one bid in this bidding process. Participation by a
bidder in more than one Bid will result in the disqualification of all bids in which the
parties are involved. However, this does not limit the inclusion of the components/
sub-assembly/ assemblies from one bidding manufacturer in more than one bid.
f) In cases of agents quoting in offshore procurements, on behalf of their principal
manufacturers, one agent cannot represent two manufacturers or quote on their behalf
in a particular tender enquiry. One manufacturer can also authorise only one agent/
dealer. There can be only one bid from the following:
1. The principal manufacturer directly or through one Indian agent on his behalf; and
2. Indian/foreign agent on behalf of onIy one principal.
g) A Bidder or any of its affiliates participated as a consultant in the preparation of the
design or technical specifications of the contract that is the subject of the Bid;
h) in case of a holding company having more than one independently manufacturing units,
or more than one unit having common business ownership/ management, only one
unit should quote. Similar restrictions would apply to closely related sister companies.
Bidders must proactively declare such sister/common business/ management units in
same/ similar line of business.
i) Bidder shall not act in contravention/violation to the provisions of competition act, as
amended from time to time.
Every bidder should, at the time of submission of bid, give a declaration, that bidder shall
not have conflict of interest with other bidders for particular quoted item, as above.
For & On behalf of GSECL
CHIEF ENGINEER (Gen)
SIGNATURE OF CONTRACTOR
EW- 257 PUR-F-006 RFQ-74075
GENERAL CONDITIONS OF CONTRACT
EW- 257 PUR-F-006 RFQ-74075
GENERAL CONDITIONS OF CONTRACT
1. DEFINITIONS :
(a) The Contract means the documents forming the tender and acceptance thereof, together
with the documents referred to therein or individual work order in the case of term contract,
including these conditions, schedules and/or additional conditions attached to the form of
tender or individual works, order, rate schedule, the specifications and the drawings and all
these documents, as applicable, taken together shall be deemed to form the contract.
(b) The “Tender Document” means the form of tender, the applicable schedules and/or
additional conditions and the specifications and/or drawing as issued to the contractors for
the purpose of preparing tender.
(c) The expression “Works” or “Work” when used in the condition of contract shall, unless there
be something in the subject or context repugnant to such construction means, the works or
the work contracted to be executed under or in virtue of the contract whether original or
(d) The “Contractor” means the individual or firm or Corporation, whether incorporated or not,
undertaking the words and shall include his or its legal personal representatives, successors
and permitted assignees.
(e) “Corporation” means The Gujarat State Electricity Corporation Ltd. and the “Accepting
Officer” means the Officer who is authorized to sign and signs the contract on behalf of the
(f) The letter “EE” means Executive Engineer who in the case of measurement and lump sum
contract, direct the contract and the letters “SE” means Superintending Engineer and “GM”
means General Manager who administers and in the case of the term contracts, directs the
(g) The “Engineer-in-charge” means all officers of the Corporation appointed by the General
Manager to supervise the works or part of the works.
(h) “Approved” and “Directed” means the approval or direction of the Chief Engineer (Gen),
Gandhinagar TPS to Superintending Engineer or the person deputed by him for the particular
(i) “BS.” means “British Standards” as issued by the British Standards Institution. “A.S.” means
the “American Standards” as issued by the American Standards Institution, and “I.S.” means
the “Indian Standards” as issued by the Indian Standards Institution. Wherever the above-
mentioned abbreviations are referred to, in the specifications and/or work orders, they mean
the addition with all amendments current at the date of issue of tender document of work
(j) In the case of measurement and terms of contract “Specifications” mean those contained in
Gujarat State Electricity Corporation Ltd. scheduled together with any amendments etc.
embodied in the tender documents. “Drawing” refers to those incorporating the tender
documents and/or any work orders referred therein.
(k) The “Contract Sum” means the sum accepted or the sum calculated in accordance with the
prices accepted in the tender and/or the contract rate as payable to the contractor for the
full and entire executing and completion of works.
(l) “The date for completion” is the date or dates of completion of the work or any part of the
works set out or ascertained in accordance with the individual work orders and the tender
documents or any subsequent agreed amendments thereto.
2. CONTRACTOR TO INFORM HIMSELF FULLY:
A. Notwithstanding anything contained to the contrary in the specifications or tenders in
subsequent exchange of correspondence, the conditions of contract shall be binding on the
Contractor and any change or variation expressed or implied, however made in the said
conditions, shall not be valid or operative unless expressly sanctioned by the Corporation.
EW- 257 PUR-F-006 RFQ-74075
The Contractor shall be deemed to have fully informed himself and to have special
knowledge of the provisions of the conditions of the Contract herein contained.
B. The contractor shall be deemed to have carefully examined the work and site conditions, the
general conditions, the special conditions, specifications, schedules and drawing and shall
be deemed to have visited the site of the works and to have fully informed himself
regarding the local conditions.
C. If there shall have any doubt as to the meaning of any portion of these general conditions
or special conditions of the scope of work of the specifications or any other matter
concerning the contract, he shall in good time before submitting his tender, send for the
particulars thereof and submit them to the Engineer-in-charge in writing in order that such
doubt may be removed.
3. CONTRACT DRAWING AND SPECIFICATIONS:
The contractor will be entitled to receive one set of agreement along with one certified copy
of accepted tender.
The drawings which form part of these specifications show the work to be done in as much
detail as is possible at the present stage. They will be supplemented by such additional
detailed drawings as may be necessary as the work progresses. The contractor shall perform
the work on these features and in accordance with these additional or revised drawings as
the case may be and at the applicable rates as per the contract.
The contractor shall check all drawings carefully and shall bring to the notice to the Engineer-
in-charge immediately of any errors or omissions discovered. The contractor shall not take
advantages of errors or omissions of any kind in the drawings supplied.
4. INPUTS BY GSECL:
The electric power supply and connection for construction / work purpose shall be given at one
mutually agreed point at work site free of cost by the GSECL. Further extension for
construction site as well as bore well site for using construction water will have to be carried
out by the contractor as per requirement at their cost. The necessary electric charges will be
paid by the contractor as per rates prevailing from time to time in the respective DISCOM.
1. If there are any surplus quarters available after meeting the requirement of GSECL's staff,
then GSECL will consider allotment of quarters on rent as per GSECL's rule.
2. The contractor will have to make their own arrangement of water for construction work
as well as for their labourers at his own cost. If possible, water for construction
purpose only at one point as decided by EIC and recovery for water charges shall be
affected at the 2 % of the item of which water is used or by quantity measured by
meter reading of water meter installed by contractor, rate of water supply will be
charged at prevailing purchase rates of GSECL, for water supplied by GSECL is used as
certified by EIC. In case of agency is installing bore well and pumps at his cost, after
completion of work agency will hand over the bore well in good condition with pumps
5. DATA TO BE FURNISHED BY CONTRACTOR:
The contractor shall submit to the Executive Engineer for approval within one week of the
date of contract, a layout plan of construction plant and equipment for the execution
of work which the contractor proposes to adopt at site.
Prior to commencement of work, the contractor shall submit to the Executive Engineer for
approval, plans in triplicate showing the location of Major plant shop and storage
buildings, storage yards, offices, contractor's power house including its services and
housing facilities which he proposes to put up at site and also indicate the programme of the
The successful bidder on receipt of letter of intent will submit within a week's time his
planning/programme of works for scrutiny of GSECL in a PERT/Bar chart format, clearly
indicating GSECL inputs also.
Contractor will plan his works such that on all the fronts released by GSECL, simultaneous
work should progress in such a way that entire job is completed in scheduled time limit.
EW- 257 PUR-F-006 RFQ-74075
No change in the approved layout shall be carried out without specific written approval of the
Executive Engineer.
6. ERRORS, OMISSIONS AND DISCREPANCIES:
In all cases of errors, omissions, doubts or discrepancies in the dimensions, or
discrepancies in the drawings and items of work in specification, reference shall be made to
the Executive Engineer whose elucidation and elaboration shall be considered as
authoritative. The contractor shall be held responsible for any error that may occur in the
work thorough lack of such reference and precautions.
7. SECURITY DEPOSIT:
SECURITY DEPOSIT: In tender process for L1 bidder (lowest bidder)
security deposit will be charged as per table below:
Category of the Security Deposit
Unit Works up to Rs. 5 Works More than Rs.
Enterprise or Exempted 3% of Order End Cost
Organization which
are exempted from
paying Tender Fee &
For all other 5% of Order End 5% of Order End Cost
Enterprises Cost
ELIGIBILITY FOR EXEMPTION:
1. Micro & small-scale enterprises which participate directly in tendering process
for the product which they are manufacturing / service which they are
providing and have Udyam registration for items / service under procurement.
2. Startups which participate directly in tendering process for the product which
they are manufacturing / service which they are providing and recognised by
DPIIT under the Start-up India Program and has obtained Udyam registration.
3. Organization which has registration certificate for the manufacturing product of
the tender, from Gujarat Khadi Gramodyog Board or Khadi and Village
Industries Commission(K.V.I.C)or Commissioner of Cottage Industries.
4. Board/Corporations/PSUs of the Central/State Government for their own
manufactured items.
5. State Government recognized organizations like(i) organizations for blinds,
dumb and deaf, disabled, mentally disabled persons;(ii)women's self-help group
recognized by Gujarat Livelihood Promotion Company; which participate
directly in tendering process for the product which they are manufacturing /
service which /they are providing
Note: Security Deposit will be collected from the successful tenderer at the rates
mentioned above. This may be recovered by deduction through running bills of the
contractors and / or by treating the Earnest Money Deposit (Bid Security) paid at
the time of submission of the tender.
After issue of Work order and Date of commencement, if successful bidder failed to start
the work then, RPAD notice will be issued to the successful bidder mentioning that on
failing to start the work within next 07 days from the date of issue of RPAD Notice the EMD
will be forfeited and he will not be allowed to participate in the tenders invited from
Gandhinagar TPS office for the period of One year.
The security deposit of the contract value shall be released on finalization of final bill /
EW- 257 PUR-F-006 RFQ-74075
successful completion of the work.
All damages, costs, charges, expenses and other sums which may be or may become due
or payable by the contractor to the Corporation under the terms of the contract, may be
deducted from the cash in the proceeds of sale of the securities/bank guarantee so
deposited (which the officer or person to whom the same may be endorsed as aforesaid is
hereby authorized to sell/to encase for that purpose) or from the interest of any such
securities or from any sums due or which may become due to the contractor by the
Corporation or from the whole or the balance unpaid as aforesaid of the encase securities
so deposited being repaid or transferred and returned as the case may be, to the
contractor on finalization of final bill OR after 06 (six) months of successful completion of
the work, whichever later OR on furnishing of the Performance Bond amounting to 5% of
contract value against the defect liability period as mentioned in this document elsewhere.
If entire security deposit is paid in approved form of Bank Guarantee should be remain
valid during the contractual period and such bank Guarantee should not be reduced on the
basis of the work actually done.
8. USE OF LAND:
The land required for office, godowns and for labour camp if not available with GSECL,
then the contractor has to arrange the same at his cost. GSECL will give the land only if the
spare land is available with the following conditions.
The contractor shall be permitted to use for the bonafide purpose of execution of this
contract free of cost. The contractor shall be permitted to use for the bonafide purpose of
execution of this contract free of cost.
1. Site required for the construction of the work.
2. Required approach road. The contractor shall make their own arrangements for the
necessary approach, road, for transport of their materials and be responsible for the
compensation on account of damage to crop etc. and shall till completion of work.
3. He will be charged the rent at the annual rate of rupees one hundred per every acre or
part thereof, for the construction of temporary hutments and his store yard. However
area required for such purpose may be clearly indicated in this offer.
All areas of operation, including those for his staff and labour colonies handed over to the
contractor shall be cleared and handed over back in good condition to the Engineer
except areas under works as per this contract or those for which specific approval has
been obtained from the Engineer. The contractor shall make good to the satisfaction of
the Engineer any damage or alternation made to areas which he has to hand over back
or to other property land handed over to him for purpose of this work.
Temporary structures may be erected by the contractor for storage sheds, offices,
residence etc. for noncommercial use on the land, handed over to him at his own
expense and with the permission of the Engineer. These structures shall comply with the
regulation that may be in force and/or specified by the Engineer with regard, thereto. In
any circumstances for constructing temporary structures for contractor's use, GSECL's
free supply materials shall not be used. If it is found that GSECL's free supply materials
are used for other than approved project drawings work, same will be recovered at
penalized rate.
The contractor shall preserve all existing vegetation such as trees on or adjacent to the
sites which do not interfere with the construction as determined by the Engineer.
The contractors shall take all possible precautions in felling trees authorized for removal
to avoid any unnecessary damage to vegetation and trees not to be felled and to
structures under construction, or to workmen, and shall be responsible for any damage if
it occurs in such operations
All produce from cutting of trees; grass etc. shall be the property of GSECL and shall be
stocked at the place specified by the Engineer. No claim shall be made for such cutting
and stacking of trees or grass etc. by the contractor
The contractors shall not unnecessarily or for use as fuel, cut any trees brush wood,
EW- 257 PUR-F-006 RFQ-74075
grass or other vegetation nor shall set fire there to without the written permission of the
Engineer. When such permission is given, the contractor shall take necessary measures
to prevent damage or to prevent fire spreading to surrounding property, and shall be
responsible for any such damage, if cause.
The land shall as herein before mentioned be handed back to Engineer in Charge
immediately after the completion of the work under this contract. Also no land shall be
held by the contractor longer than the Engineer shall deem necessary and the contractor
shall, on due notice by the Engineer, vacate and return the land which the Engineer may
certify as no longer required by the contractor for purpose of the work.
9. START OF WORK:
The contractor shall not enter upon or commence any portion of work except with the
written authority or instructions of the Executive Engineer or his subordinate in charge of
the work, failing such the contractor shall have no claim to ask for measurement or
payment for work and shall be responsible for any claims or damages that may arise due to
such unauthorized commencement or entry.
10. COMPENSATION FOR THE DELAY:
The time allowed for carrying out the work as entered in the tender shall be strictly
observed by the contractor and shall be reckoned from the date on which the order to
commence work is given to the contractor. The work shall throughout the stipulated period
of contract be proceeded with all due diligence (time being deemed to be the essence of
contract) and for delay, the contractor shall pay compensation, an amount equal to ½
(half) percent per one week for the contract amount or part thereof, including taxes &
duties ( i.e. End cost of contract amount including taxes & duties) and maximum up to
% of the order value, including taxes & duties ( i.e. End cost of contract amount including
taxes & duties) or such smaller amount as per the decision of the Competent Authority of
the GSECL The penalty will be invariably deducted from the bills of the contractor and no
refund will be given unless the competent authority approves the reduction. The reasons
for delay, attributable to GSECL as well as to party will be brought out clearly while putting
the proposal for waiver/reduction in penalty.
11. ACTION WHEN WHOLE OF SECURITY DEPOSIT IS FORFEITED:
In any case in which under any clause or clauses of this contract the contractor shall have
tendered himself to pay compensation amounting to the whole of his security deposit
(whether paid one sum) or in the case of abandonment for the work owing to serious
illness or death of the contractor or any other cause, the Executive Engineer on behalf of
the Corporation, shall have powers to adopt (a) below and any of the following courses
under (b) and (c) as he may deem best suited to the interest of the Corporation.
(a) To rescind the contract (for which rescission notice of 10 days) in writing to the contractor
under the hand of the Executive Engineer shall be conclusive evidence and in that case the
security deposit of the contractor shall stand forfeited and absolutely at the disposal of the
Corporation. To employ labour paid by the Corporation, to supply materials, to carry out the
works or any part of the work debiting the contractor with the cost of the labour and the
price of the materials (as to the correctness of which cost and price, the certificate of the
Executive Engineer shall be final and conclusive against the contractor) and crediting him
with value of the work done in all respects in the same manner and at the same rates as if
it had been carried out by the Contractor under the terms of this contract and in that case
the certificate of the Executive Engineer as to the value of the work shall be final and
conclusive against the contractor.
(b) To order that the work of the contractor be measured up and to take such part thereof, as
shall be unexecuted, out of his hands and to give it to another contractor to complete, in
which case, any expenses, which may be incurred in excess of the sum, which would have
been paid to the original contractor, if the whole work would have been executed by him
(as to the amount of which excess expenses, the certificate in writing of the Engineer-in-
charge shall be final, conclusive and shall be borne and shall be paid by the original
contractors and shall be deducted from any money due to him by the Corporation under the
EW- 257 PUR-F-006 RFQ-74075
contract or otherwise from his security deposit of his proceeds sale thereof or a sufficient
(c) In the event of the above courses being adopted by the Executive Engineer, the contractor
shall have no claim to compensation for any loss sustained by him by reason of his having
purchased or procured any materials or entered into any engagements or made any
advances on account of or with a view to the execution of the work or the performance of
the contract. And in case the contract shall be rescinded under the provision aforesaid, the
contractor shall not be entitled to recovery or be paid any sum for any works thereof
actually performed by him under this contract unless and until the Executive Engineer shall
have certified in writing the performance of such work and the amount payable to him in
respect thereof and he only be entitled to be paid the amount so certified.
12. NOTICE UNDER UNSATISFACTORY PROGRESS:
If the progress of a particular portion of the work is unsatisfactory, and also if as per the
opinion/observation of the Executive Engineer (whose decision shall be final) in charge that
the general progress of work is not satisfactory, then Executive Engineer in charge shall be
entitled to take action under clause 11 (c) after giving the contractor ten days’ notice in
writing and the contractor will have no claim for compensation for any loss sustained by
him owing to such action.
13. ACTION IN THE CASE OF DEFAULT BY THE CONTRACTOR :
In any case in which any of the powers conferred upon the Executive Engineer by Clauses
11 and 12 hereof shall have exercisable and the same shall not have been exercised, the
non-exercised thereof shall not constitute a waiver of any of the conditions hereof and such
powers shall not withstanding be exercisable in any further case of default by the
contractor of which, by any clauses hereof, he is declared liable to pay compensation
amounting to the whole of his security deposit and liability of the contractor for past and
future compensation shall remain unaffected in the event of the Executive Engineer taking
action under sub-clause (a) or (c) of Clause 11, he may if he so desires, take possession of
all or any tools, plants, materials, and stores in so upon the work or the site thereof
belonging to the contractor, or procured by him and intended to be used for the execution
of the work of any part thereof paying for allowing for the same in account at the contract
rates, or in the case of a contract rates not being applicable of current market rates to be
certified by the Executive Engineer whose certificate thereof shall be final. In the
alternative, the Executive Engineer may by notice in writing to contractor or his clerk of
works, foreman or other authorized agent, require him to remove such tools, plant,
materials or stores from the premises within a time to be specified in such requisition, the
decision to the contractor failing to comply with any such requisition, the decision of the
Executive Engineer as to the expense of any such removal and the amount of the proceed
and expense of any such sale, be final and conclusive against the contractor
14. EXTENSION OF TIME LIMIT
If the contractor shall desire an extension of the time limit for completion of the work on
the ground of his having been unavoidably hindered in its execution or on any other
ground, he shall apply in writing to the Executive Engineer and the Executive Engineer
may, if in his opinion there are reasonable grounds for granting extension, recommend
such extension as he may think necessary or proper. The decision of the competent
authority in this regard shall be final, and binding to the contractor. Any delay attributed to
Corporation, shall be thus compensated only by way of extending the limit.
15. COMPLETION CERTIFICATE
On completion of the work, the Contractor shall be furnished with Completion Certificate by
the Executive Engineer. No such certificate shall be given nor shall be the work considered
to be completed until works are taken over and/or duly tested and put to operation as the
case may be, nor until the work shall have been measured by the Engineer-in-Charge or
where the measurement have been taken by his subordinates until they have received the
EW- 257 PUR-F-006 RFQ-74075
approval of the Executive Engineer the said measurement being binding and conclusive
against the contractor.
16. EFFECT OF THE CERTIFICATE :
No payment shall be made for any work estimated to cost less than Rs.1,000 till after the
whole of said work shall have been completed and a certificate of completion given. But in
the case of works estimated to cost more than Rs.1,000, contractor shall on submitting a
monthly bill thereof, be entitled to receive payments. Proportionate to the part of the work
then approved and passed by the Engineer-in-Charge, whose certificate of such approval
and a passing of the sum so payable shall be final and conclusive against the contract. All
such intermediate payment shall be regarded as payment by way of advance against the
final payment only and not as payments for work actually done or completed and shall not
preclude the Engineer-in-charge from requiring bad, unsound, imperfect or unskillful work
to be removed and taken away and reconstructed or re-erected nor shall any such payment
be considered as admission of the due performance of the contract or any part thereof in
any respect of the occurring of the claim nor shall conclude, determine or effect in any way
the powers of the Engineer-in-Charge as to the final settlement and adjustment of the
accounts otherwise or in any other way, vary or affect the contract. The final bill shall be
submitted by the contractor within one month of the date fixed for completion of work;
otherwise the certificate of the Engineer-in-charge of the measurement and of total amount
otherwise the certificate of the Engineer-in-charge of the measurement and of total amount
payable for the work shall be final and binding on all parties.
17. PAYMENT TO CONTRACTORS :
The rates for several items of works estimated to cost more than Rs.1, 000 agreed to
within shall be valid only when the item concerned is accepted, having been completed full,
in accordance with the sanctioned specification. In case, where the items of the work, are
not accepted, as so completed, the Engineer-in-charge, may make payment on account of
such items at such reduced rates, as he may consider reasonable in the preparation of final
or running accounts bills and it will be binding to the contractor.
The Bill Shall be submitted by the contactor each month on or before the date fixed by the
Engineer-in-charge, for all works, executed in the previous month and the Engineer-in-
charge shall take or cause to be taken the requisite measurement for the purpose or having
the same verified and the claim so far as it is admissible, shall be adjusted, if possible,
within Fifteen days from the presentation of the bills. If the contractor does not submit the
bill, within the time fixed, as aforesaid, the Engineer-in-charge may depute a subordinate to
measure up the said work in the presence of the contractor or his duly authorized agent,
whose counter signature in the measurement shall be sufficient warrant and the Engineer-
in-charge may prepare a bill from such list which shall be binding on the contractor in all
respects. In case if contractor/ representative does not remain present on specified date for
taking measurement than EIC may take the measurement one sided and the same shall be
binding to the contractor irrespective whether he has signed or not.
19. SUPPLY OF MATERIALS TO CONTRACTOR [APPLICABLE ONLY WHERE MATERIAL
IS TO BE SUPPLIED BY CORPORATION AS MENTIONED IN SCHEDULE A ]
If the specification of the estimated work provides for use of any special description of
material to be supplied from the Corporation’s stores or if it is required that the contractor
shall use certain stores to be provided by the Engineer-in-charge, (such material and stores
and the prices to be charged thereof as hereinafter mentioned being so far as practicable
for the convenience of contractor but not so as in any way to control, the meaning or effect
of this contract specified in the schedule or memorandum hereto annexed). The contractors
shall be supplied with such materials and stores as may be required from time to time be
used by him for the purpose of the contract only and the value of the full quantity of
materials and stores so supplied shall be set off or deducted from any sum due or
thereafter to become due to the contractor, under the contract or otherwise or from the
security deposit or the proceeds of sale thereof if the deposit is held in government
EW- 257 PUR-F-006 RFQ-74075
securities the same or a sufficient portion thereof, shall be sold for the purpose. All
materials supplied to the contractor shall remain the absolute property of the Corporation
and shall on account be removed from the site of work and shall at all times be open to
inspection by the Engineer-in-charge. Any such materials unused and in perfectly good
condition at time of completion or determination of the contract shall be returned to the
Corporation’s store if the Engineer-in-charge so requires by notice in writing given under his
hand but the contractor shall not be entitled to return any such materials except with such
consent and he shall have no claim for compensation on account of any such materials
supplied to him as aforesaid but remaining unused by him or for any wastage in or
damaged thereto. The contractor shall be responsible for the loss, destruction or
deterioration of the materials, stores or articles supplied to him by the Corporation even if
such loss, destruction or deterioration has occurred under any circumstances whatsoever
beyond his control as if the materials, stores or articles so supplied were his property.
20. WORKS TO BE EXECUTED IN ACCORDANCE WITH SPECIFICATIONS, DRAWING,
The contractor shall execute the whole and every part of work in the most substantial and
workman like manner and both as regarding materials and in every other respect in strict
accordance with the specification. The contractor shall also confirm exactly, fully and
faithfully to the designs, drawings and instructions in writing relating to the work signed by
the Engineer-in-charge and lodged in his office and to which the contractor shall be entitled
to have access for the purpose of inspection at such office, or on the site of the work
during office hours and the contractor shall, if he so requires, be entitled at his own
expense to make or cause to be made copies of the specification and of all such designs,
drawings and instructions as aforesaid.
21. ALTERATIONS IN SPECIFICATIONS AND DESIGNS NOT TO INVALIDATE
The Executive Engineer shall have powers to make any alterations, or additions to the
original specification, designs and instructions that may appear to him to be necessary or
advisable during the progress of the work and the contractor shall be bound to carry out
the work in accordance with any instruction in this connection which may be given to him
in writing, signed by the Engineer-in-charge and such alterations shall not invalidate the
contract. Any additional work which the contractor may be directed to do in the manner
above specified as part of the work shall be carried out by the contractor on same
conditions in all respect on which he agreed to do the main works and at the same rates as
are specified in the tender for the main work.
Where, however, the work is to be executed according to the designs, drawings and the
specifications recommended by the contractor and accepted by the competent authority,
the alteration above referred to shall be within the scope of such designs, drawings and
specifications appended to the tender.
22. RATES FOR WORKS NOT ENTERED IN ESTIMATE OR SCHEDULE OF RATE OF THE
If the additional and altered work includes any class of work for which no rate is specified
in this contract, then such class of work shall be carried out at the rates entered in the
Schedule of Rates of the Corporation or at the rate mutually agreed upon between the
Executive Engineer and the Contractor, whichever are lower. If the additional or altered
work for which no rate is entered in the Schedule of Rates of the Division is ordered to be
carried out before the rates agreed upon then the contractor within seven days of date of
receipt by him of the order to carry out the work should inform the Executive Engineer for
the rate which it is his intention to charge for such class of work and if the Executive
Engineer does not agree to this rate, he shall be noticed in writing, be at liberty to cancel
his order to carry out such class of work and arrange to carry it out in such manner as he
may consider advisable provided always that if the rates shall have been determined as
EW- 257 PUR-F-006 RFQ-74075
lastly herein before mentioned then in such case he shall only be entitled to be paid in
respect of the work carried out or expenditure incurred by him prior to the date of the
determination of the rate as aforesaid according to such rate or rates as shall be fixed by
the Executive Engineer in the event of disputes, the decision of the General Manager of the
Corporation will be final.
23. EXTENSION OF TIME LIMIT IN CONSEQUENCE OF ADDITION OR ALTERATION
The time limit for the work shall be extended in the proportion that the increase in its cost
occasioned by alterations or additions bears to the cost of the original contract work and
the certificate of the Engineer-in-charge as to such proportions shall be conclusive.
24. NO COMPENSATION FOR ALTERATION IN OR RESTRICTION OF WORK TO BE
If at any time, after the execution of the contract documents, the Engineer-in-charge shall,
for any reason whatsoever, requires the whole or any part of the work, as specified in the
tender, to be stopped for any period or shall not require the whole or part of the work to
be carried out at all or to be carried out by the contractor, he shall give notice in writing of
the fact to the contractor who shall thereupon suspend or stop the work totally or partially
as the case may be in any such case, except as provided here under. The contractor shall
have no claim to any payment or compensation whatsoever on account of any loss in profit
or advantage which he might have derived from the execution, of the work in full but which
he did not so derive in consequence of the full amount of work not having been carried out
or on account of any loss that he may be put to on account of materials purchased or
agree to be purchased or for unemployment of labour recruited by him. He shall not also
have any claim for compensation by reason of any alterations having been made in the
original specification, drawings, designs and instructions which may involve any curtailment
of the work as originally contemplated. Where, however, materials have already been
purchased or agreed to be purchased by the contractor before receipt by him of said
notice, the Executive Engineer provided they are not in excess or requirement and are of
approved quality and/or shall be compensated for the loss, if any, that he may put to in
respect of materials agreed to be purchased by him. The amount of such compensation to
be determined by the Executive Engineer, whose decision shall be final. If the contractor
suffers any loss on account of his having to pay, his labour charges during the period,
during which the stoppage of work has been ordered under this clause the contractor shall
on application be entitled to such compensation on account of labour charges as the
Executive Engineer whose decision shall be final, may consider reasonable provided that
the contractor shall not be entitled to any compensation on account of labour charges if, in
the opinion of the Executive Engineer, the labour could have been employed by the
contractor elsewhere for the whole or part of the period during which the stoppage of the
work has been ordered as aforesaid.
25. NO CLAIM FOR COMPENSATION ON ACCOUNT OF LOSS DUE TO DELAY IN
SUPPLY OF MATERIALS BY CORPORATION
The contractor shall not be entitled to claim any compensation from Corporation for the
loss suffered by him on account of delay by Corporation in the supply of materials entered
in Schedule A where such delay is caused by:
Difficulties relating to supply of railway wagons.
Force Majeure
Any other reasonable cause beyond the control of Corporation, including shortage of
materials to be supplied by the Corporation and difficulties in time by reaching at the site of
any materials equipment.
In the case of such delay in the supply of materials, Corporation shall grant such extension
of time for the completion of the works as shall appear to the Executive Engineer to be
reasonable in accordance with the circumstances of the case. The decision of the Executive
Engineer as to the extension of time shall be accepted as final by the contractor.
EW- 257 PUR-F-006 RFQ-74075
26. TIME LIMIT FOR COMPENSATION CLAIMS
Under no circumstances, whatsoever, shall the contractor be entitled to any compensation
from Corporation on any account unless the contractor has claimed in writing to the
Executive Engineer within one month of the cause thereof.
27. ACTION AND COMPENSATION PAYABLE IN CASE OF BAD WORK
If at any time, before the security deposit is refunded to the contractor, it shall appear to
the Executive Engineer or his subordinate in charge of the work that any work has been
executed with unsound, imperfect or unskillful workmanship or with materials of inferior
quality or that any materials or articles provided by him for the execution of the work are
unsound or of inferior quality to that contract for or are otherwise not in accordance with
the contract, it shall be lawful for Engineer-in-charge to intimate this fact in writing to the
contractor and then notwithstanding the fact that the work, materials, or articles
complained of, may have been inadvertently passed, certified and paid for, the contractor
shall be bound forthwith to rectify or remove and reconstruct the work so specified in
whole or any part, as the case may require or if so required shall remove the materials or
articles so specified and provided other suitable materials or articles at his own charge and
cost, and in the event of his failing to do so within a period to be specified by the Engineer-
in-charge in the written intimation aforesaid the contractor shall be liable to pay
compensation at the rate of one percent on the amount of the estimate for every day not
exceeding ten days during which the failure so continues and in the event of any such
failure as aforesaid, the Engineer-in-charge may rectify or remove or re-execute the work
or remove and replace the materials or articles complained of, as the case may be, at the
risk and expense in all respects of contractor should the Engineer-in-charge consider that
any such inferior work or materials as described above may be accepted, or made use of, it
shall be within his discretion to accept the same as such reduced rates as he may fix
Provided that in the case of any work of which visible check is not possible if the Engineer-
in-charge or his subordinate in charge of the work feels that such work has been executed
with unsound, imperfect or unskillful workmanship or with materials of inferior quality, he
shall take sample tests at random, cost of which shall have to be borne by the contractor
and if after taking such test part of such work is found to be defective in any respect or to
have been executed with materials of inferior quality then the contractor shall pay for the
whole work such amount as may be fixed by the office of the Engineer-in-charge on the
basis of the lowest quality of work found by him in such sample tests.
28. WORK TO BE OPENED TO INSPECTION, CONTRACTOR OR RESPONSIBLE AGENT
All works under execution or in pursuance of the contract shall at all times be open to the
inspection and supervision of the Executive Engineer and his subordinate and contractor
shall at all times, during the usual working hours and at all other times at which reasonable
notice of the intention of the Executive Engineer or his subordinate to visit the works shall
have been given to the contractor, during which period either he should be present to
receive order and instruction, or have a responsible agent duly authorized agent shall be
considered to have the same force and effect as if they had been given to the contractor
29. NOTICE TO BE GIVEN BEFORE WORK IS COVERED UP
The contractor shall give not less than five days’ notice in writing to the Executive Engineer
or his subordinate in charge of the work, before covering up or otherwise placing beyond
the reach of measurement of any work, in order that the same may be measured and
correct dimensions thereof, taken before the same is so covered up or placed beyond the
reach of measurement and shall not be covered up or placed beyond the reach of
measurement and work without the consent in writing of Executive Engineer or his
Subordinate in charge of work. If any work shall be covered up or placed beyond the reach
EW- 257 PUR-F-006 RFQ-74075
without such notice having been given or consent obtained, the same shall be uncovered at
the contractor’s expense and in default thereof no payment or allowance shall be made for
such work or for the materials with which the same was executed.
30. CONTRACTOR’S LIABILITIES
The contractor shall supply, at his own cost, all materials (except such special materials, if
any as may be supplied from the Corporation stored in accordance with the contract).
Plant, tools, appliances, implements, ladders, cordage, tackle, scaffolding and any
temporary works which may be required for the proper execution of the work, in the
original, altered or substituted form and whether included in the specification and other
document forming part of the contract or referred to in these conditions or not and which
may be necessary for the purpose of satisfying and complying with the requirements of the
Engineer-in-charge as to any matter on which under these conditions, he is entitled to be
satisfied or which he is entitled to require together with carriage thereof to and from the
work. The contractor shall also supply without any charge the requisite number of persons
of setting out works and counting, weighting and assisting in the measurement of
examination at the time and from time to time of the work or materials, failing this the
same may be provided by the Engineer-in-charge at the expenses of the contractor and the
expenses may be deducted from any money due to the contractor under the contract or
from his security deposit or the proceeds of sale thereof or of a sufficient portion thereof,
the contractor shall provide all necessary fencing and light required to protect the public
from accident and shall also be bound to bear expenses of defense of every suit, action or
other legal proceedings of law that may be brought by any person for injury sustained.
Owing to neglecting of the above precautions and to pay any damage and cost which may
be awarded in such suit, action or proceedings to any such person or which may with the
consent of the contractor be paid in comprising any claim by any such person.
31. CONTRACTOR LIABLE FOR ALL DAMAGE
Compensation for all damage done intentionally or unintentionally by contractor’s laborer,
whether in or beyond the limit of Corporation’s property, shall be estimated by the Executive
Engineer or such other office as he may appoint and the estimates of the Executive
Engineer, subject to the decision of the Superintending Engineer, on appeal, shall be final
and the contractor shall be bound to pay the amount of the assessed compensation demand,
failing which, the same will be recovered from the contractor as damages or deducted by the
Engineer-in-charge from any sums that may be due to or become due from Corporation to
the contractor under this contract or otherwise.
The contactor shall bear the expenses of defending any action or other legal proceeding that
may be brought by any person for injury sustained by him owing to negligence of
precautions for prevent the spread of fire and he shall also pay any damage and cost that
may be awarded by the court, if in consequence
32. RESCISSION OF CONTRACT AND FORFEITURE OF DEPOSIT
The contractor shall not assign or sublet, without the written approval of the Engineer-in-
charge and if the contractor assign, or sublet his contract, or attempt to do so or become
insolvent or commence any proceedings to be adjudicated as insolvent or make any
composition with creditors, attempt to do so, the Engineer-in-charge may, by notice in
writing rescind the contract. Also, if any bribe, gratuity, gift, loan, perquisite, reward or
advantage pecuniary or otherwise shall either directly or indirectly be given, promised or
offered by the contractor or any of his servants, or agents, or any person to the employee of
the Corporation in any way relating to his office or indirectly interested in the contract, the
Executive Engineer may, by ten days’ notice in writing, rescind the contract. In the event of
a contract being rescinded the security deposit of the contractor shall there upon stand
forfeited and be absolutely at the disposal of the Corporation and the same consequences
shall ensure as if the contract has been rescinded under Clause 11 thereof and in addition
the contractor shall not be entitled to recover or be paid for any work thereof actually
performed under the contract.
EW- 257 PUR-F-006 RFQ-74075
33. COMPENSATION
All sums payable by a contractor by way of compensation under any of these conditions shall
be considered as a reasonable compensation to be applied to the use of Corporation without
reference to the actual loss or damage sustained and whether any damage has not been
34. CHANGE IN THE CONSTITUTION OF FIRM TO BE NOTIFIED
In case of tender by partners of a Firm, any change in constitution of firm shall be forthwith
notified by the contractor to the Executive Engineer for his information.
35. WORKS UNDER DIRECTION OF SUPERINTENDING ENGINEER
All works to be executed under the contract shall be executed under the direction and
subject to the approval of Superintending Engineer /Engineer-in-charge for the time being
who shall be entitled to direct at what point or points and in what manner they are to be
commenced and from time to time to be carried on.
36. DECISION OF SUPERINTENDING ENGINEER TO BE FINAL
Except where otherwise specified in contract and subject to the power delegated to him by
Corporation under the Corporation’s rules, then in force, the decision of the Superintending
Engineer/EIC for the time being shall be final, conclusive and binding on all the
specifications, designs, drawings and instructions herein before mentioned and as to the
quality of workmanship or material used on or as to any other question, claim, right matter
or thing whatsoever in any way arising out of or relating to the contract, designs, drawings,
specifications, estimates, instructions, orders or these conditions or otherwise concerning,
the works or the execution or failure to execute the same, whether arising during the
progress of the work or after the completion or abandonment thereof.
37. Dispute Resolution Mechanism: For works contracts and composite Contracts, the
arbitration mechanism shall be governed by the Gujarat Public Works Contracts Disputes
Arbitration Tribunal Act, 1992 as per below details.
sub clause 37(1) Amicable Settlement : Any dispute, difference, controversy or claim
between the Parties arising out of or relating to this contract with reference to the
construction, interpretation, breach, termination or validity thereof (hereinafter referred as
"the Dispute") shall, upon the written request of either Party be referred to the authorized
representatives of the Disputing Parties for resolution. The authorized representatives shall
promptly meet and attempt to negotiate in good faith a resolution of the Dispute within
thirty days of the service of the request.
sub clause 37(2) Arbitration : If the Parties fail to amicably resolve the disputes or
differences or contrary claims as indicated herewith in sub clause (1) of Clause 37 arising
under or in connection with the present works contracts, whether pertaining to works
contracts alone or works and procurement both, the same shall be referred to arbitration
under the Gujarat Public Works Contracts Disputes Arbitration Tribunal Act, 1992."
38. STORES TO BE OBTAINED FROM CORPORATION [APPLICABLE ONLY WHERE
MATERIAL IS TO BE SUPPLIED BY CORPORATION AS MENTIONED IN SCHEDULE
The contractor shall obtain from the Corporation stores, such articles as are mentioned in
schedule “A” which may be required for the work or any part of the work or in making up
any articles required therefore or in connection therewith, unless he has obtained
permission in writing from the Executive Engineer or obtained such stores and articles from
elsewhere. The value of such stores and articles as may be supplied to the contractor by
the Engineer-in-charge will be debited to the contractor in his account at the rate shown in
the schedule “A” attached to the contract and if they are not entered in said Schedule, they
shall be debited to him at cost price which for the purpose of this contract shall include cost
of carriage and all other expenses whatsoever which may have to be incurred in obtaining
delivery of the same at the stores aforesaid and further overhead charges 15%.
EW- 257 PUR-F-006 RFQ-74075
The Contractor shall be responsible for the loss, destruction or deterioration of the
materials, stores or articles supplied to him by the Corporation, even if such loss,
destruction or deterioration has occurred under any circumstances whatsoever beyond his
control as if the materials, stores or articles so supplied were his property. The contractor
shall be responsible for returning the residual materials after completion of the contract and
it fails to return, the balance materials supplied to him by the Corporation, the cost of the
residual materials will be recovered from the contractor at the market rate or stock issue
rate whichever be higher at the time of materials account plus 15%.
39. LUMP SUMS IN ESTIMATE
When the estimate on which tender is made, includes lump sums in respect of parts of the
works the contractor shall be entitled to payment in respect of the items of works involved
or the part of the work in question at the same rates as are payable under this contract or
such items or if the part of work in question is not in the opinion of the Engineer-in-charge
capable of measurement the Engineer-in-charge may at his discretion pay the lump sum
amount entered in the estimate and the certificate in writing of the Engineer shall be final
and conclusive against the contractor with regard to any sum or sums payable to him under
the provision of this clause.
40. LUMP SUM TENDERS
Whenever lump sum tenders have been invited for buildings or other structures of the
same type, design, the contractor shall submit his bill stated in Clause No. 18 and the
Engineer-in-charge not below the rank of work, Executive Engineer shall certify by general
measurement or by other method considered suitable to him, the value of work done and
the contractor shall be paid monthly a sum equal to 90% of the total value the work so
certified, since the last payment, after deducting a part or whole of the secured advance if
not already paid for the materials utilized on the works. An additional secured advance for
any fresh materials utilized on the works. An additional secured advance for any fresh
materials brought on site will also be paid if certified by the officer not below the rank of
Executive Engineer. After the work is completed final bill would be paid on the certification
of officer not below the rank of Executive Engineer, that the work, is done according to
drawing and specifications attached to the tender. If any additions and alterations have
been carried out, detailed measurement in respect thereof shall be recorded and extra
payment or deductions are regulated as per item rates quoted by the contractor while
submitting the tender and if there are any items in the additions and alterations for which
the contractor has not quoted a rate, the payment shall be as per Clause 39 above
41. ACTION WHERE NO SPECIFICATION
In the case of any class of work for which there is no such specification as is mentioned,
such work shall be carried out in accordance with the PWD and in the event of there being
no PWD specification, the work shall be carried out in all respects in accordance with the
instructions and requirements of the Engineer-in-charge of the Corporation etc.
42. NO CLAIM FOR VARIATION IN QUANTITIES OR WORK
Quantities shown in the tender are approximate and no claim shall be entertained for
quantities of work actually executed, being either more or less up to any extent than those
entered in the tender or less than those entered in the tender or estimate.
43. NO CLAIM FOR COMPENSATION FOR DELAY IN STARTING WORK
No compensation shall be allowed for any delay caused into starting of work on account of
acquisition of land and in the case of clearance for works or any delay in according sanction
44. NO CLAIM FOR COMPENSATION FOR DELAY IN EXECUTION OF WORK
No compensation shall be allowed for any delays in execution of the work on account of
water standing in borrow pits or compartment. The rates are inclusive for hard or cracked
soil, excavation in mud, sub-soil water or water standing in borrow pits and no claim for
any extra rate shall be entertained unless otherwise expressly specified and mentioned in
45. EMPLOYMENT OF TECHNICAL PERSONS:
EW- 257 PUR-F-006 RFQ-74075
The contractor shall keep one full time qualified Civil Engineer at the site, who shall be fully
authorized to receive and comply with such instructions, as given by the Executive
Engineer. The contractor shall intimate the name of such Engineer with his qualifications
and experience. The Executive Engineer shall have the right to demand the removal of any
technical personnel, skilled or unskilled workmen, who in his opinion are considered to
cause bad workmanship in the execution of works or to cause indiscipline.
46. INDUSTRIAL LABOUR LAWS
LABOUR LAWS TERMS AND CONDITIONS
1) The contractor should not be allowed to engage 50 or more contract labourers without
valid labour license under The Contract Labour (Regulation & Abolition) Act, 1970 & The
Contract Labour (R & R)(Gujarat) Rules 1972 from the Assistant Commissioner of Labour
Gandhinagar (the said number i.e. 50 or more includes Supervisor and other staff)
2) The contractors shall have to obtain group insurance policy under Employee Compensation
Act, 2010 before starting the work.
3) All Contractors shall have to make the payment of wages to the Contract Labours engaged
by them, on or before expiry of 7th of every month through either by A/c Payee Cheque or
by crediting the wages in their bank accounts. The Contractor shall supply copy of Bank
Statement duly stamped by the Concerned Bank as a token of proof towards payment of
Wages to HR Department. Contractor shall intimate the Date & Mode of Payment in
advance to LWO / IRO. Contractor are also required to get the wage register of respective
month certified from LWO / IRO as per the provision laid down under the Contract Labour
(R&A) Act, 1970. Any default will result in cancellation of contract forthwith or else the
contractor shall be punishable to the extent of Rs. 100/- per day by way of fine.
4) Apart from payment of wages through bank, contractors should also make all other
payments like advances, bonus, leave encashment etc. to their labours through Banks.
5) The contractor shall give his telephone number, address, emails to the GSECL authority, so
that in case of labour unrest etc. the contractor can be contacted.
6) Maternity benefits and leave as per the provision of the Maternity Benefits Act.
7) If any workman engage by contractor meet with fatal or non-fatal accident while on duty,
then contractor shall be liable to pay compensation to legal heir or to the workman as case
may be as per Employees compensation act,2010.
8) The attendance of all contract labours of ARC / BRC contracts is to be monitored through
Bio-metric punching system only.It shall be the duty of the Contractor or his Supervisor to
ensure the supply of specified number of manpower and to ensure their Bio-Metric
punching and reporting at the location of work. Non-reporting or non-availability at the
location of work shall be considered as non-punching and suitable actions can be taken by
User department, including levy of penalty.
9) The contractors shall comply with the provisions of E.S.I. Act wherever applicable as per
the prevailing provisions of the Act and as amended from time to time.
10) The contractor shall be responsible and liable to pay difference in wages, if any, and /or
observe the revised service conditions that may be awarded by the Honorable court
effective from the date directed in the award to concerned Protected workmen.
11) The contractor shall require to maintain regular Labour record/ documents/ registers and
shall pay all benefits to Labour force as per applicable statutory laws and contractor shall
require to obtain clearance certificates to this effect from HR Officer of GSECL.
12) The contractor will make arrangements at his own cost to insure all men, materials and
equipment employed for this work. The GSECL will not be responsible for any loss or
damage either to the contractor’s personnel or his equipment.
13) Dispute, if any, taking place between the contractor and laborers must be intimated to
LWO/IRO/DGM, GTPS immediately.
14) Any casualty will also have to be borne by the contractor for the period the contract
EW- 257 PUR-F-006 RFQ-74075
15) The Contractor shall also indemnify GSECL for injury or damage to third party other than
employees of the GSECL, contractor or sub – contractor.
16) Contractor / Agency shall have to issue the contractual appointment letter for a specific
period to their Labour engaged during the contract period each and every instance &
should narrated clear out terms & conditions for the liabilities of the concerned employees.
17) Contractor shall produce certified copy of appointment letter of each worker deployed at
18) Gate pass shall not be issued without Employee insurance for work inside or outside of
factory. Engineer in charge has to ensure employee compensation insurance before
commencement of work.
19) Wages rates for contract laborers are applicable as per The Minimum Wages Act, 1948 &
The Minimum Wages (Gujarat) Rules 1961 The contractor shall have to pay wages to
workers as notified by Government of Gujarat., from time to time.
20) It should be ensured that all the labours engaged by contractor are covered under the
Employees' Provident Funds & Miscellaneous Provisions Act, 1952 and their contributions
are remitted regularly to the concerned RPFC. The Xerox copies of challan along with ECR
and remittance slip in this regards should be submitted regularly in G.S.E.C.L. office.
21) In case the contractor having more than one contract in the same Power station, the
contractor shall have to submit contract wise separate list of the workmen & maintain
relevant registers and records accordingly and submit the same to the Concerned Section &
HR department as per applicable labour laws.
22) The Interstate Migrant Workers Act, 1979 & The Inter state Migrant Workers (Gujarat)
Rules 1981 shall be complied by contractor in case 05 or more outstate worker/ employees
is required to engaged at GSECL GTPS TPS.
23) Person below the age of 18 years and above 60 years should not be employed for the
24) No female worker shall be employed in the night shift between 7.00 P.M. to
25) The contractor shall maintain a valid labour license under the contract labour (Regulation
and Abolition) Act for employing necessary man power to be required by contractor. In the
absence of such license the contract shall be liable to be terminated without assigning any
reasons thereof.
26) The contractor shall at his own expense comply with all labour laws and keep the
G.S.E.C.L. Indemnified in respect thereof.
27) Contractor shall obtain valid Identity cards for their workmen as prescribed under the
Factories Act 1948 and Gujarat Factories Rules, 1963 from Factory Manager or Authorized
representative of Company in prescribed form by submitting required documents before
commencement of work.
28) Payment of retrenchment compensation, Notice pay and other liabilities as per The
Industrial Disputes Act, 1947 & Gujarat Rules 1966. Any payment to the contractor's
labours arising out of any claim or disputes under the Industrial Dispute Act 1947 or any
other labour laws.
29) Payment of compensation in case of accidental injury shall be made by contractor as per
the Employee Compensation Act,
30) If the female workmen are more than 30 numbers engaged then provision of crèches and
Maternity leave as per the provision of the Maternity benefit Act, 1961shall be complied.
31) Contractor shall comply the Provision laid down under the payment of Bonus Act, 1965 for
their workmen engaged at GTPS and submit the relevant records to GSECL office.
32) The contractor must possess separate P.F. code for the above subject work.
33) Provisions of The Building and other Construction Workers (Regulation of Employment and
Conditions of Service) Act, 1996 and Gujarat Building and Other Construction Workers
EW- 257 PUR-F-006 RFQ-74075
(Regulation of Employment and Condition of Service) Rules, 2003 shall be complied by
contractor if contract is awarded outside the factory premises i.e. colony area & other than
factory premises before execution of work compliance shall be submitted if 10 or more
workers are engaged .Necessary documents such as registration certificate under BOCW
Act etc shall be submitted by contractor. Contractor shall obtain Gate passes for the work
of carried out in Colony area & other than factory premises from Security Section after
following due procedure from GSECL Office.
34) Paid leave facility at the rate of one day for every 20 days worked by the contract labour
shall be provided by the contractor to his workers as per factory act. ,1948. It shall be duly
verified and approved/certified by the authorized officer of the GSECL.
35) The contractor shall employ adequate number of experienced staff at site for daily
supervision and for maintaining of various registers and records required under the law
and contracts. No payment for such supervision shall be admissible.
36) If any Agency found having involved in any kind of malpractices such as less payment to its
employees, irregularity in computation of duty hours, less deduction of Provident Fund &
default in other statutory compliances or in maintaining required manpower as per Contract
terms or failure in legal compliances the Company will have the right to terminate the
contract of such Agency immediately without giving any notice. In such circumstances
security deposit shall be forfeited.
37) If any complaints related to legal /statutory compliances received against contractor from
its workmen or otherwise, contractor shall be responsible to resolve the same immediately,
non-resolving the same company shall withheld his pending dues until the complaints is
38) In case the contractor’s work is found unsatisfactory or contractor abandons, stops, or
creates hurdle during the contract period, the GSECL will be entitled to terminate the
contract. In case of default the work will be got done through other agencies at the risk
and cost of contractor and GSECL shall be entitled to recover such expenses from
defaulting contractor by such methods as deemed fit. The contractor shall not however, be
entitled to terminate the contract or stop works undertaken by him before expiry of the
contract period due to any reason whatsoever.
39) Under the contract, the contractor shall either himself be present on site or should
nominate persons in writing, who must be available at site and who should be authorized
to take decision about the works and mutual consultation from time to time. In the
absence of any responsible man of contractor at the time of any emergency adhoc decision
of Engineer-in-charge will be binding to the contractor
40) CONTRACTOR TO INDEMNIFY THE GSECL
The contractor shall indemnify and keep indemnified the GSECL, and every member,
officer and employees of the GSECL, also Engineer-in-charge and his staff against all
actions, proceedings, claims, demands, costs and expenses whatsoever arising out of or in
connection with the matter referred in above clauses and elsewhere and against all
actions, claims demands, cost and expenses which may be made against the GSECL by
any workman/ employees of contractor or any sub contractor and or from any liability any
wise to any workman/employees of the contractor or sub-contractor under any laws, rules
or regulation having in force of law including but not limited to claims against the owner
under workmen compensation Act, 1923. The Employee’s Provident Fund Act.1952, and/or
the contract labour (Abolition and Regulation)Act, 1970 & various labour laws applicable.
The GSECL shall not be liable for or in respect of or in consequence of any accident or
injury to any workmen or other person in the employment of the contractor or his sub-
contractor, and the contractor shall indemnify and keep indemnified the GSECL against all
such damage and compensation and against all claims, demands proceedings costs,
charges and expenses whatsoever in respect of or in relation thereto.
41) EMPLOYEE'S COMPENSATION & EMPLOYER'S LIABILITY INSURANCE
EW- 257 PUR-F-006 RFQ-74075
The contractor has to take Employee Insurance under the Employee
Compensation Act, 2010 for all workmen engaged by him for GSECL work contract
(Location & Order wise) and copy of the same shall be produced to GSECL prior to start
work. Insurance shall be affected for all the contractor’s employees engaged in the
execution of these contracts. If any of the work is sublet, the contractor shall required the
sub-contractor to provide Employee's compensation and Employer's liability insurance for
the latter’s employees unless such employees are covered under the contractor’s
insurance. It shall be liability of contractor for employees of his sub-contractor.
42) Any other rules and regulation, conditions, Circulars etc., that are in force at present and
that may be framed by the GSECL From time to time in connection with contracts will be
binding and acceptable to contractor.
43) All relevant records i.e. registers, forms, valid licenses etc shall be maintained up to date as
per applicable all labour laws and kept ready at GSECL site office for inspection at any time
or submitted in-time to the concerned authorities as per applicable various labour laws by
44) It is the responsibility of the contractor to ensure that contractor’s employees maintain
strict discipline as regards security, methods of safe working etc, and not to cause any
hindrance to smooth running of power station or in execution of duties by GSECL staff. Any
lapse in this regard will be viewed seriously and contract is liable to be terminated. If any
of contractor’s staff is found unsuitable or not behaving properly, the contractor shall have
to remove him from the work-site on demand by GSECL. To keep harmonious industrial
relations amongst contract labours is the sole responsibility of the contractor. Any breach
of the same will be viewed seriously.
45) Before starting the work, the contractor should contact Industrial Relation Officer/ Labour
Welfare Officer for fulfilling Labour Laws Compliances and obtaining the gate passes of all
contract labourers as per procedure laid down.
46) The contractor shall deposit 15 days salary at the rate of last drawn salary for every
completed year of services for each worker for the liabilities of the gratuity. (* applicable to
ARC/BRC works contract only).
47) Dispute Resolution Mechanism: For works contracts and composite
Contracts, the arbitration mechanism shall be governed by the Gujarat
Public Works Contracts Disputes Arbitration Tribunal Act, 1992 as per
sub clause 48(1) Amicable Settlement : Any dispute, difference, controversy or
claim between the Parties arising out of or relating to this contract with
reference to the construction, interpretation, breach, termination or validity
thereof (hereinafter referred as "the Dispute") shall, upon the written request of
either Party be referred to the authorized representatives of the Disputing
Parties for resolution. The authorized representatives shall promptly meet and
attempt to negotiate in good faith a resolution of the Dispute within thirty days
of the service of the request. sub clause 48(2) Arbitration : If the Parties fail to
amicably resolve the disputes or differences or contrary claims as indicated
herewith in sub clause (1) of Clause 48 arising under or in connection with the
present works contracts, whether pertaining to works contracts alone or works
and procurement both, the same shall be referred to arbitration under the
Gujarat Public Works Contracts Disputes Arbitration Tribunal Act, 1992."
48) For procedure for health check-up accordingly bill shall be reimbursed once
during total contract period(for as & when and AOH/COH contract)
maximum up to Rs.1000 or actual cost per worker/ labour /person,
whichever is minimum after verification & recommendation by concern
doctor. In case any worker left the work in between than for replacement
Worker Company will not provide any reimbursement, however it is
compulsory to submit new report of replacement worker for fitness certificate
at contractor’s own expense.
EW- 257 PUR-F-006 RFQ-74075
49) For Periodic Medical examination, No reimbursement for periodic medical
examination to be given to contract employee for whom GSECL are
conducting Periodic Medical examination at company’s cost at GTPS. If a
contractor fails to undergo periodic medical examination, they have to
undergo prescribed investigation as per hazard analysis from outside, No
reimbursement to be given for these investigations.
The above instructions should be followed scrupulously to avoid undue litigation for non
Compliance of Labour Law.
Follow the following procedure at each milestone for the execution of works contract.
(A) On Commencement of Contractual Work:
(1) The Contractors shall have to obtain Photo-Gate-Pass as per Factory Act, 1948 before the
commencement of contractual work awarded. Contractor shall have to apply for the gate
passes in triplicate in a prescribed application form which is to be available with user
Section for the entry of workmen in the premises of GSECL including Colony premises.
(2) Such application shall have to be proceed for the approval of Factory Manager. After
obtaining approval of Factory Manager, contractor shall have to prepare the Gate Passes
and obtain the signature of Factory Manager / Authorized representative of company as
per factory Act,1948.
(3) If Labours are required to be engaged in Emergency during Public Holiday or any other
day, Contractors Can apply for Temporary Gate-Pass for the maximum period of only three
days with recommendation of respective EE/SE and the same shall have to be regularized
after following the procedure of Gate Pass applications by Chief Engineer. It is to note that
No Temporary Gate-Pass shall be issued for the work other than acute emergency to carry
out the work in power station premises. Emergency work is to be justified by concerned
user section and same shall be approved by Chief Engineer.
(4) The Contractor shall have to obtain the Group Insurance Policy under the Employee
Compensation Act, 1923 prior to commencement of work. No pass whether temporary or
Valid shall be issued without insurance policy under Employee compensation Act,2010
(5) The Contractor who intend to engaged 50 or more labours to carry out the awarded
contractual work then necessary - Form No. V under the Contract Labour (R& A) Act,
/ Form No. VI under the Interstate Migrant worker (employment regulation) rule 1979 as
applicable is to be obtained from HR Department for the purpose of obtaining Labour
License from the Licensing Authority.
(6) Contractor shall submit Registration certificate under The Building and other Construction
Workers (Regulation of Employment and Conditions of Service) Act, 1996 and Gujarat
Building and Other Construction Workers (Regulation of Employment and Condition of
Service) Rules, 2003 if contract is awarded outside the factory premises i.e. colony area &
other than factory premises before execution of work if 10 or more workers are engaged.
(B) During Contractual Work under the progress:
(1) Bill Recording Officer/Engineer of User department shall have to ensure as to whether
contractor has engaged minimum number of contract workmen per day as per the terms
(2) All Contractors shall have to make the payment of wages to the Contract Labours engaged
by them on or before expiry of 7th of every month through either by A/c Payee Cheque or
by crediting the wages in their bank accounts preferably situated in the premises of
GSECL. The Contractor shall supply copy of Bank Statement duly stamped by the
Concerned Bank as a token of proof towards payment of Wages to HR Department.
(3) Contractors has to comply & maintain All statutory documents / registers at site under the
provision of labour laws such as CLRA Act, EPF & MP Act,1952, Minimum wages Act,
Payment of wages Act, Bonus Act, Gratuity Act, Factory Act, etc & other applicable labour
(C) Submission of Statutory documents to ensure the compliances:
1) The Contractor shall have to submit following statutory documents, work order wise,
EW- 257 PUR-F-006 RFQ-74075
under the labour laws with invoice to the recording officer of user department for ensuring
the compliances of provision of labour laws for the respective execution of contract period
and same is required to be forwarded to HR Department in Office note .(Copy attached).
List of documents are given below:
1. Copy of Attendance register – with name & address of establishment, Name of work and
site (duly signed & stamp by Contractor and sub- contractor) - Form XVI.
2. Copy of Wage Payment Sheet – with signature of workmen, (duly signed & stamped by
Contractor sub-contractor)- Form XVII.
3. Copy of Bank Statement of Wage Payment for the proof of wage payment (Duly signed &
Stamp by Concern Bank and contractor and sub contractor
4. Copy of PF Challan along with ECR Statement of respective period. (High light n
employees in ECR )
5. EPF Remittance Slip
6. Bonus register with payment details ( If Applicable)
7. Leave Encashment Register with payment details (If applicable )
8. Undertaking for labour law compliances on non- judicial stamp paper of Rs.300/- to be
submitted with notarized at the time of processing the final bill.
Contractor shall specify the Name of Work, Place of Work and Work order number in
Muster Roll- Form No. XVI & Wage Register – Form No XVII as Prescribed under the
Contract Labour (R&A) Act, 1970 & rules thereof.
2) The Recording Officer/ Engineer of User department shall furnish the details and statutory
documents in the form of prescribed Office Note as enclosed in Annexure ‘’A’’ and the
same should be submitted to LWO / IRO/PO /DGM for onward action. (Copy Enclosed) .
3) In case of running contracts, if the contractor does not fulfill the requirement of
documents (PF Challan, Wage Registers etc), RA Bill shall not be processed until the
documents are submitted.
4) On submission of relevant documents to LWO /IRO/PO/DGM by Office Note. The same will
be intimated to Accounts Section for Compliances of Labour Laws.
5) If contractor failed to submit above documents in that case his payment of Bill shall be
withheld by GSECL, GTPS and on submission of the required documents the said bill shall
be released by GSECL GTPS.
6) Original copies of above mentioned documents and other legal documents as per
requirement shall be produced before Dy. G.M. (HR) / IRO / LWO / In-charge of H.R.
Department as and when demanded.
7) The GSECL will be entitled to deduct directly from the bill to be paid to the contractor, any
sum or sums payable by the contractor and which sum/sumsthe GSECL is required to pay
as a principal employer on account contractor’s default in respect of all liabilities referred
to in above clauses.
8) GSECL shall entitled to fulfill statutory liabilities under applicable laws being a principal
employer if contractor, its Sub Contractor fails to comply statutory compliance towards his
workmen. The amount of the same can be recovered from pending dues of contractor
with appropriate penalty and administrative charges / Service charges.
9) Office correspondence will be carried out in English / Gujarati. The English version will be
the correct one and the same only will held good for legal matters.
10) Any other rules and regulation, conditions, etc., that are in force at present and that may
be framed by the GSECL From time to time in connection with contracts will be binding
and acceptable to contractor.
11) Contractor have to follow gate pass procedure in view of guideline issued by GSECL
Corporate Office vide letter No. GSECL/CEG/Corporate Safety/Gate Pass Procedure/1029
Dtd. 30.05.2019 (Performa of Gate Pass is attached herewith).
12) In view of GSECL Corporate Office Circular No. GSECL / CEG / G.I / Circular / Works/815
Dtd. 02.05.2019 Contractor have to follow all the terms and condition / guideline related
EW- 257 PUR-F-006 RFQ-74075
to contract labour management system such as Biometric punching, compliance to various
labour laws, regular submission of statutory documents etc. for obtaining no objection
certificate from HR.
13) As per tender terms and conditions. In case of contractor or OEM/ OES are permitted to
perform the works portion through sub-contractor, It would be necessary for such OEM/
OES to submit Declaration cum Indemnity Bond in specified format on Rs.300/ Non judicial
stamp paper and Bills submitted by the OEM/ OES on behalf of subcontractor shall be
processed only by complying statutory provision under applicable acts.
14) If any problem may arise for payment of wages through bank, same may inform to Chief
Engineer (Gen.) and after approval only , the payment shall be disbursed in presence of
the GSECL representative i.e. HR officer during the working hours in the factory premises
and the contractor shall get the entries certified in the register of wages by the
representative of the GSECL
15) During the tenure of work order, if by order of Court any workman engaged by
them declared as protected workman or during the pendency of proceedings at
court, then concerned contractor shall be binding to maintain status-quo until
further order of court.
16) Nothing in the contract document stated shall anywise construe any work
man/employees of the contractor or sub-contractors as or to be workman
employee of the Owner or place obligatory liability in respect of any such
workman/employees upon GSECL.
On Non-Judicial Stamp Paper of Rs.
To be submitted with NOTORIZED at the time of final bill
UNDERTAKING FOR LABOUR LAW COMPLIANCES
I, Proprietor / Owner / Partner / Authorized
Agent of M/s. do hereby declare and undertake as
1. That in capacity of independent contractor for M/s.
(Sub-Contractor of M/s. ) worked as
Contractor at GSECL, GTPS Thermal Power Station for the nature of work of
against Work Order
No. Dt. ., I have
complied with the provisions of all laws as applicable. I have paid the wages for the month/s
of my contractual period which is/are not less than the minimum rates as applicable, to all
my employee/s and no other dues are payable to my employee/s.
2. That I have covered all the eligible employee/s under the Employees’ Provident Funds and
Miscellaneous Provisions Act, 1952 and deposited the contributions under my P.F. Code No.
Place: for the month/s of my contractual
period and as such no amount towards contributions whatever is payable.
3. I further declare and undertake that in case any liability pertaining to any of my worker,
labour, employee/s is/are to be discharged by the Principal Employer i.e. Gujarat State
Electricity Corporation Limited, GTPS due to my lapse, I undertake to reimburse the same or
the Principal Employer is authorized to deduct the same from my dues as payable.
4. I further declare and undertake the legal consequences which may arise in future under the
said work awarded, and I bound myself to resolve the same at the risk and cost of M/s.
EW- 257 PUR-F-006 RFQ-74075
EW- 257 PUR-F-006 RFQ-74075
EW- 257 PUR-F-006 RFQ-74075
EW- 257 PUR-F-006 RFQ-74075
EW- 257 PUR-F-006 RFQ-74075
47. MATTERS RELATED TO EXECUTION OF WORK:
a) Work shall commence from the date given in letter to commence the work by EIC at
site. The Contractor shall make all necessary arrangements at site to mobilize labour,
operators, divers and materials and maintain necessary number of machinery and
equipment, barge, pontoons etc., to guarantee the agreed rate of progress of work as per
b) A detailed work schedule showing how he proposes to carry out the work, specifically
mentioning time periods as well as date of commencement and completion of each
activity and such approved schedules must be strictly adhered to by the CONTRACTOR.
After the owner has agreed with the schedule, the Contractor shall prepare detailed
program of each work front/activity breaking it down giving daily quantifiable/measure
of progress. The schedules are to be reviewed periodically with the OWNER / ENGINEER
to ensure that the completion date will be met or to institute corrective steps (at no extra
cost to the ENGINEER) to adhere to the completion dates. The OWNER reserves the right
to revise the schedule at his discretion in order to keep up to the completion date and to
suit the project requirement and such alterations shall not entitle the CONTRACTOR to
any extra payment.
c) A work schedule with PERT / Bar Chart for carrying out the work in prescribed time
limit mentioning date of commencement, activity to be carried with its time period,
starting & finishing event for each activity, completion of total project in critical path etc,
shall be jointly fixed and approved by the GSECL. Such approved schedules must be
strictly adhered by the Contractor.
d) After the GSECL has agreed with the schedule, the Contractor shall prepare detailed
program of each work front / activity breaking it down to daily quantifiable measure of
progress. The schedules are to be reviewed periodically with the Owner / E.I.C to ensure
that the completion date will be met or to institute corrective steps (at no extra cost to
the GSECL) to adhere to the completion dates. The Owner reserves the right to revise the
schedule at his discretion in order to keep up to the completion date and to suit the
project requirement and such alterations shall not entitle the Contractor to any extra
e) The GSECL reserves the right to delete any item of schedule-B for which contractor shall
not have any right to claim on this account.
f) One permanent reference bench mark and a reference base line shall be given for lay out
of work, which shall be maintained without disturbance by the CONTRACTOR during the
tenure of the contract. CONTRACTOR shall establish local bench marks as directed by the
ENGINEER IN CHARGE.
g) The contract or any part thereof shall not be subject to change without the written
permission of the Chief Engineer (Gen.) GSECL, GANDHINAGAR TPS or his authorized
representatives.
h) During the execution of the work if it is found that the work is not progressing as per the
scheduled program approved by the GSECL & planned by the contractor, due to the
reasons attributable to the contractor, suitable action shall be taken as per Clauses in this
tender elsewhere & other relevant clauses appearing in the section of “Terms & condition
of tender & works contract, Legal conditions of works contract” of tender document. And
the GSECL may also take such action as it may deem fit to ensure that the work is
completed in time at Risk and Cost of the contractor.
i) Contractor shall attend meetings at EIC's office at site or any other place as fixed by the
EIC, as and when required for review, discussion, coordination etc. Attending these
meetings shall be obligatory on the part of the Contractor, at no cost to the GSECL.
j) The Contractor shall take all requisite & necessary care to observe that no damage is
caused to the existing, pumps, existing works, service road, or any other structure etc. For
any damage to the existing structures of the GSECL, the Contractor shall be held
responsible and he will have to rectify the damage immediately up to the satisfaction of
Engineer in Charge, at his own cost.
k) The work shall be completed within the period stipulated in the contract. & site
clearance arranged according to the progress of work at site. Therefore, the contractor
has to organize & coordinate the work to suit these circumstantial conditions. In the
event of any delay due to the above or due to any other reason not attributable to the
contractor, reasonable extension in completing the work may be given at the discretion
and as decided by the GSECL but no compensation or idle charges will be payable to the
contractor on this account or any site conditions under any circumstances.
l) No idle charges shall be entertained by GSECL for any site condition or any
EW- 257 PUR-F-006 RFQ-74075
circumstances. The corporation will not pay any type of advances including mobilization
48. RECOVERIES:
a) In case of any damage to equipment / machinery or structure / building of GSECL or any
public property due to negligence of contractor or any other reasons attributed to
contractor, the decision of E.I.C. regarding the amount of recovery shall be final.
b) If the contractor fails to execute the work as per direction of E.I.C. within the time frame
given, the GSECL shall get the work done through any other contractor at the risk and
cost of the contractor and the cost of execution of such work along with 15% overhead
charges shall be deducted from contractor’s monthly bill over and above recovery as per
c) Recoveries due from the contractor, up to the end of the month previous to the one in
which the bill is prepared shall be made from bills approved for payment every month
or at other periods when the bills are prepared, for the various items in the following
order of priorities and extents.
d) Deduction on account of security deposit in full together with shortage, if any, to be made
e) Penalty in full, if levied.
f) Expenditure, if any, incurred by the Corporation on Contractor’s behalf in labour or
materials in full.
g) Charges for services such as water and power supply etc. in full.
h) Charge on account of supply of materials like cement and steel in case of shortages found
in balance or excess consumption than specified.
i) Hire charges for Corporation or Government machinery if any.
j) Recoveries of advance and secured payment or payments for preliminary work in full or
the installment due if and as the same as may have been allowed.
k) Rent recovery on account of allotting quarters on rent as per Corporation’s rules.
l) Income tax and sales tax in full as per Government rules.
m) Outstanding recoveries in respect of other contracts awarded by the Corporation if any.
n) Other recoveries. (If any)
49. WORK TO BE EXECUTED TO THE SATISFACTION OF THE ENGINEER -IN-CHARGE:
The contractor shall proceed with the work with diligence and expedition and the
whole of the work herein specified as well as the mode of execution shall be under
the supervision and direction and shall be carried on to the entire satisfaction of the
Engineer-in-charge, who shall have full power to order the contractor to alter, enlarge
or diminish the form, dimensions, positions, or quantities of any of the work or to make
use of material and workman-ship of different descriptions and qualities from this
herein specified.
The whole of the works, together with any temporary works, associated therewith, shall
be carried on in the most substantial proper and mannered workman like manner, with
the best materials and workmanship and to the entire satisfaction of the Engineer-in-
charge and in such order of time as he may direct. The contractor shall attend to and
execute without delay all orders and instruction which may from time to time be issued
by the Engineer-in-charge.
50. MATERIALS WORKMANSHIP etc.:
The work shall be executed in thoroughly substantial manner with material and
workmanship of best quality and strictly in accordance with the specifications and with
the drawings, or with such other drawings or written instruction as may from time to
time be furnished to the contractor, in accordance with terms of this contract and shall
be completed in every respect with all materials and workmanship implied and
necessary according to the fair interpretation and meaning of the same and should there
be any discrepancy between the drawings and specifications or any difference or
disputes as to the dimensions to be worked to or the quality of the materials to be used,
or the mode of doing periodical quantity of the work to be executed or with respect to
any subject arising out of this contract, the decision of the Engineer-in-charge shall be
final and binding on all parties. Rejected material shall be so disposed off as to obviate
any possibility of their use on works. The place, method and period of disposal shall be as
directed by the Engineer-in-charge.
51. SAMPLES OF DESCRIPTIVE DATE:
Samples of descriptive date, requiring approval, shall be submitted by contractor to the
Engineer-in-charge in good time before the use of such material for inspection and
permission of testing if required. The samples shall be properly marked to show the
name of the material, manufacture, place of origin, and place where to be used etc.
EW- 257 PUR-F-006 RFQ-74075
Failure of any sample to pass specified tests will be sufficient cause for the refusal to
consider any further sample from the same source.
52. FENCING AND LIGHTING AND VENTILATION
Except as herein after provided, the contractor shall unless otherwise specified, be
responsible for the proper fencing, guarding, lighting and taking of the necessary safety
measures for all works comprised in the contract and or the proper provision of
temporary roadway, footways, guards fences, caution notices etc. as far as the same
may be rendered necessary by reasons for the work for the accommodation and
protection of workman foot passenger or other traffic and of the owners and occupiers
of adjacent property and of the public and shall remain responsible for any
accidents that may occur on account of his failure to take proper and timely
All the arrangements made for fencing, lighting and ventilation shall be maintained by
the contractor throughout the tendency of the contract till physical taking over of the
work by the department.
53. LIABILITY FOR DAMAGE TO WORKS OR PLANTS
The contractor shall during, the progress of the work, properly cover up and protect the
work, and plant, and materials placed at his disposal or acquired for him by the
Corporation, from injury by exposure to the weather, or any cause what so ever and shall
take every reasonable proper timely and useful precaution against accident or injury to
the same from any cause and shall be and remain answerable and liable for all accidents,
or injuries thereto which until the same be or be deemed to be, taken over by the
Corporation, may arise or be occasioned by the acts or omissions of the contractor or his
workmen of sub-contractors, and all losses and damages to the works or such plant or
material arising from such accidents or injuries as aforesaid shall be made good in the
most complete and substantial manner by and at the sole cost of the contractor and to the
reasonable satisfaction of the Engineer-in-charge. If the contractor fails to make good
such losses & damages within the time given by the Engineer-in-charge, the Corporation
shall be at liberty to recover the amount fixed by the Engineer-in-charge for such losses or
damages or any part thereof by deducting it from any sum due by the Corporation to the
contractor under this contract or otherwise.
Further the contractor shall, at all time, protect and preserve all materials, plant and
equipment that he may himself have procured for the execution of the work. All reasonable
requests of the Engineer-in-charge to enclose or especially protect any of the above shall be
expeditiously compiled with.
If the Engineer-in-charge considers that the work or materials or plant is not sufficiently
protected by the contractor, he shall be entitled to arrange for such protection at his
unfettered discretion and recover the cost thereof from the contractor.
Until the work shall be or be deemed to be taken, over as aforesaid, the contractor shall
also be liable for and shall be deemed to have indemnified the Corporation in respect of all
damage or injury to any person or any property of the Corporation or of others, occasioned
by the negligence of the contractor or his workmen, or his sub-contractor, or by
defective design, work or materials.
54. EXPLOSIVE PROCUREMENT AND STORAGE (IF APPLICABLE)
i) Explosives, petrol, oils, fuels and other inflammable materials shall be stored strictly in
accordance with the rule of the Explosive Department.
ii) The contractor shall at his own expense construct and maintain, proper magazines which
are required for the storage of explosive and arrange for proper storage facilities for oils,
fuels etc. for use in connection with the work.
iii) The contractor shall at his own expense obtain such license or licenses as may be
necessary for strong and using explosives, oils, fuels etc. The department shall not take any
responsibility whatsoever in connection with the storage or use of explosives on the site, or
any accident or occurrence whatsoever in connection therewith. All operation of the
contractor in which or for which Explosives are employed shall be at risk of contractor and
upon his own responsibility.
55. MATERIALS TOOLS AND PLANT BROUGHT ON THE SITE OF WORK
All materials, tools and tackle of the contractor brought to and delivered upon the site
for the purpose of the work shall from the time of their being so brought shall be
deemed to be the property of the Corporation in its possession to be used for the
purpose of the work and for that purpose only and shall not on any account be removed
EW- 257 PUR-F-006 RFQ-74075
or taken away by the contractor or any other person without the written permission of
the Engineer-in-charge but the contractor shall nevertheless be solely liable and
responsible for and loss destruction thereof or damage thereto. The Corporation shall
have a lien on such materials, tools and tackle for any sum of sums which may at any
time prior to the completion of the works be due or owing to the Corporation by the
contractor, under in respect of and dispose of any such materials, tools and tackle in such
manner as the Corporation may think fit and to apply the proceeding in or towards the
satisfaction of such sum or sums so due or owing as aforesaid but subject to such lien
and power of sale and disposal such surplus materials, tools and tackle shall belong to
the contractor and may be removed and disposed off by him as he may think fit.
56. ACCESS TO SITE AND WORK ON SITE
The Engineer-in-charge or his authorized representative may if he consider fit from time
to time enter upon any lands which may be in the possession of the contractor under
this contract, for the purpose of executing any work not included in this contract and
may execute such work not included in this contract by agents, or by other contractors
at his option and the contractor shall in accordance with the requirements of the
Engineer-in-charge, afford all reasonable facilities for execution of the works including
occupation of lands by structure or otherwise for any other contractor employed by
the Corporation and his workmen or for the workmen of the Corporation who may be
employed in the execution on or near the site of the work not included in the
contractor’s any contract in connection with or ancillary to the works and in default,
the contractor shall be liable to the Corporation for any delay or expense incurred by
reason of such default. Provided always that if the exercise of those power shall cause
any damage to the contractor he may within fifteen days of such damage arising make a
statement of the same to the Engineer-in-charge who shall from time to time assess the
value in his Judgment of such damage and the Corporation shall from time to time shall
pay to the contractor the amounts (if any accepted as justified) by the Engineer-in-
charge. The contractor shall not however, on account of any such modified, new or extra
work executed by or for the same of the Corporation be entitled to claim relief from the
obligation to execute other works.
57. INSPECTION OF WORKS
The Engineer-in-charge or his duly authorized agent shall have at all time full power to
inspect the works, wherever in progress, either on the site, on the contractor's premises
or at the premises wherever situated, of any firm or Corporation where work in
connection with this contract may be in hand.
Further, the contractor shall not allow, without written authorization permit entry on
site of work, any person except authorized agents of the Corporation of the Engineer-in-
charge or the contractor's staff and labour directly engaged on and in connection with
The contractor shall, during working hours, maintain supervisors having sufficient
training and experience to supervise the various items and operations of the work and
the said supervisors shall remain present during the inspections of the Engineer-in-
charge. All orders and directions given to such supervisors or other staff of the
contractor shall be deemed to have been given to contractor. Further the Engineer-in-
charge may be due notice, desire a higher ranking members of the supervisory staff of
the contractor to be present on any specified inspection and the contractor shall comply
with such direction.
58. CLEANING UP
The contractor shall at all times keep the construction area and his power house and
storage areas free from accumulation of waste, or rejected materials.
Prior to the completion of the work the contractor shall remove all rubbish from and about
the premises, and all tools, scaffolding, equipment and materials which are not part of
permanent structure. The premise will be left in a manner fully satisfactory to the
Engineer-in-charge, thereafter only the completion certificate will be issued.
59. CONTRACTOR TO KEEP INVENTORY OF MATERIALS etc.
The contractor shall prepare and maintain an inventory of all materials temporary
rolling stock, plant purchased or hired for use of employment or for any of the purposed
for this contract and such inventory or a copy thereof shall at all times be available for
inspection by the Engineer-in-charge. A complete and up to date copy of the inventory
EW- 257 PUR-F-006 RFQ-74075
shall be submitted to the Engineer-in-charge in the beginning and once a year; thereafter
changes in the interim period, if any shall be communicated on every three months.
60. CONTRACTOR TO RESTORE PLANT
Upon completion of the work, the contractor shall deliver to the Corporation, all
appliances, materials, and plants which may have been loaned or hired to him by the
Corporation and make good all damages which may have occurred to them, except such
as shall be caused by fair wear and tear in execution of the works.
61. PROGRESS SCHEDULE
i) The contractor shall furnish, within one week unless extended by the Engineer of the
order to start the work, a progress schedule in quadruplicate indicating the date of start
the weekly progress expected to be achieved and the anticipated completion date of each
major items of work to be done by him, also indicating dates of procurement and setting
up of materials, plant and machinery. The schedule should be such as is practicable of
achievement towards completion of the whole work in the time limit and of the particular
items on due dates specified in the contract and shall have the approval of the Engineer.
Further, the dates for the progress as in this schedule shall be kept up-to-date. In case it is
subsequently found necessary to alter this schedule, the contractor shall submit in good
time a revised schedule incorporating necessary modifications proposed and get the
same approved by the Engineer. No revised schedule shall be operative within such
acceptance in writing.
Detailed schedules for each week showing the progress proposed to achieve shall be
submitted to the Engineer and got approved. The Engineer is further empowered to ask
for more detailed schedule or schedules any week by week, for any items or items, and
the contractor shall supply the same as and when asked for.
ii) The Engineer shall have, at all times the right without in any way vitiating this
contract, or forming grounds for any claim to alter the order of the works or any part
thereof and the contractor shall after receiving such direction proceed in the order
directed. The contractors shall also revise the progress schedule accordingly and submit
four copies of the revised schedule to the Engineer within seven days of the Engineer's
direction to alter the order of works.
iii)The contractor shall furnish sufficient plant equipment and labour and shall work such
hours and shifts as may be necessary to maintain the progress on the work as per the
approved progress schedule. The working and shift hours shall comply with all GSECL's
regulations in force and shall be such as may be approved by the Engineer. They shall not
be varied without the prior approval of the Engineer.
iv)The contractor shall from time to time as may be required by the Engineer, furnish the
Engineer, with a statement in writing of the arrangement he proposes to adopt for the
execution of this contract and the Engineer may if he considers, necessary at any time
advise alteration in the same, which the contractor shall adopt on notice thereof.
v) The progress schedules shall be in the form of progress charts, forms, statement
and/or reports as may be approved by the Engineer. Further, the contractor shall submit
four copies showing the progress of work in forms and charts etc. at periodicals intervals
as may be specified by the Engineer.
62. DATE OF COMPLETION
The contractor shall supply, erect, equip and construct the whole of the works and
hand over them to the Corporation on or before the date specified in the tender
document including "Special Conditions" and save as herein provided, in no
circumstances whatever shall extend or alter the date for the completion of works.
Provided always that if in the opinion of the Engineer-in-charge the completion of the
works shall be delayed by any change of original design or by the order of the
Engineer-in-charge, of any altered, modified substituted or additional works or
materials omitted or by strikes, lock outs or stoppages of labour, or revolution, riots,
civil or political disturbance or by causes directly due to war or by the contractor not
being given possession of the site or any part there-of or by the Corporation taking
possession of and using the site or any part thereof or the works or any part thereof,
whether any nonperformance of work under the powers herein contained or otherwise
or by any nonperformance of work or non-supply of materials to be performed or
supplied by the Corporation or by the contractor not receiving any orders, drawings,
instructions or directions in time or by the suspensions of the works or by fire, flood
EW- 257 PUR-F-006 RFQ-74075
exceptionally bad weather tempest, storm, or by from unforeseen circumstances (and
whether the same shall be due to any act or omission of the Corporation or its agents
or those in their respective service or not) the Engineer-in-charge may, if in his
unfettered discretion, he thinks fit either forthwith or at any later time and from time
to time not withstanding that the prescribed or extended time for completion has
expired or that the work have been completed, by writing under his hand, extend the
time for the completion of the works to such date as he shall appoint. Provided always
that unless the contractor makes a written application to the Engineer-in-charge within
one month of the cause of delay and unless the time is extended by the Engineer-in-
charge, the prescribed time shall not be extended notwithstanding delays from the
aforesaid foregoing or any other causes of whatsoever kind.
63. SUBLETTING OF CONTRACT
There will be generally no objection on the component parts for the work, being given
over to responsible sub-contractors but Corporation shall under no
circumstances recognize these sub-contractors and the responsibility of executing the
work in the accordance with the conditions of contract will entirely rest on the main
contracts. The main contractors will therefore always have the very responsible
member, preferably a technical hand present on the works with power to sign all
work orders issued on the site of work and to take requisite actions in the interest of
very efficient execution of work. However, the subletting of the contract can be made
only with the prior approval of the competent authority of the Corporation.
64. OTHERCONTRACTS FOR THE WORK SUSPENSION STOPPAGEOR CURTAILMENTS OF
If during the tendency of the contract the Engineer-in-charge shall for any reasons
(which shall be unquestioned) whatsoever require the whole or any part of the work
as specified in the contract to be suspended for any period or shall not require the
whole or any part of the work as specified in the contract to be carried out at all by the
contractor, he shall give notice in writing of the fact to the contractor who shall
thereupon suspend or stop the work totally or partially as the case may be. In any,
case, except as provided hereunder, the contractor shall have no claim to any payment
or compensation whatsoever on account of any profit or advantage which he might have
derived from the execution of the work in full but which he did not so derive in
consequence of the full amount of the work not having being carried out, or on
account of any loss that he may be put to on account of materials purchased or agreed
to be purchased or for unemployment of labour recruited by him. He shall not also have
any claim for compensation by reason of any alterations having been made in the
original specifications, drawings, designs and instruction which may involve any
curtailment of the work as originally contemplated. Where, however, materials have
already been purchased or agreed to be purchased by the contractor, before receipt
by him of the aforesaid notice, the contractor shall be paid for such materials at the
rate determined by the Engineer-in-charge, provided they would have been useful for
the work curtailed or stopped are not in excess of requirements, are of approved
quality and cannot be used on other contract works or otherwise by the contractor
and/or shall be compensated for the loss if any, that he may be put to, in respect of
materials agreed to be purchased by him, the amount of such compensation to be
determined by the Engineer-in-charge, whose decision shall be final.
The Engineer-in-charge may grant extension of time for the execution of any item or
items of work affected by such suspension of work. The decision for the Engineer-in-
charge, regarding the granting of extension and the period thereof shall be final. The
Engineer-in-charge may order the contractor to suspend any work on account of bad
weather; rain or storm and such other adverse climate conditions and the contractor
shall comply with the same.
The contractor shall not be entitled to an compensation for such suspension of work,
concrete lining at the junctions of the different works under different contract shall be
done with particular care regarding forms, construction joints, interconnecting
reinforcement etc. If any and the joint planning of such work shall be with prior
approval of the Engineer-in-charge.
65. OTHER CONTRACTORS
EW- 257 PUR-F-006 RFQ-74075
Apart from this work, the other works connected with the power house will be
simultaneous going on either departmentally or through agencies inside or outside the
power house. Each contractor or agency shall co-operate with others to the fullest
extent and shall allow to each other every facility and co-ordination for execution of
their works simultaneously and satisfactorily, during their action of machinery or
execution of any other co-ordination works of the power house, the contractor will have
to work only at places as directed by the Engineer-in-charge. He will have some time
to suspend his work partially or totally in the interest of the work at large.
In such cases and at such time, he will be informed from time to time and directed by the
Engineer-in-charge where to work. He may also be required to remove the scaffolding or
to erect the scaffolding and shuttering in such a manner as to be of little obstruction and
inconvenience for erection of machinery. In such cases he shall not be given any
compensation on account of reduction or stoppage or labour force or removal and
reinstatement of scaffolding shuttering etc. It will be seen that contractor is not put to
unnecessary inconvenience.
In the matter of dumps, haul, roads, drainage, diversion and the like, each contractor
shall take into consideration the needs and requirements of the other constructors, if any
working in the vicinity. Further no contractor shall take or cause to be taken any
stops or action that may cause disruption, discontent or disturbance to the work,
labour of arrangements etc. or other contractors in the neighboring project localities.
Any action, by any contractor, which the Engineer-in-charge in his unquestioned
discretion may consider as infringement of the above code, would be considered as a
breach of the contract conditions and the Engineer-in-charge may take such action as he
may deem fit against the contractor and the action taken shall be considered as final
66. SPEED OF WORK
The contractor shall at all times maintain the speed of work to confirm to the latest
operative progress schedule but the Engineer-in-charge may at any time with sufficient
notice in writing direct the contractor to slow down any part or the whole of the work
for any reason (which shall not be question whatsoever, and the contractor shall comply
with such orders of the Engineer-in-charge. The compliance of such orders shall not
entitle the contractor to any claim or compensation.
67. CONTRACT DOCUMENT AND MATTERS TO BE TREATED AS CONFIDENTIAL
All documents, correspondence, decisions and other matter concerning the contract shall
be considered as of confident and restricted nature by the contractor and he shall not
divulge or allow access there to any unauthorized persons of any kind.
68. ACCESS TO THE CONTRACTOR'S BOOK
Whenever it is considered necessary by the Engineer-in-charge to ascertain the actual
cost for execution of any particular item of work of supply of plant or material shall
direct the contractor to produce the relevant documents such as pay rolls records of
personnel, invoices of materials and any other data relevant to the item or necessary to
determine its cost etc. and the contractor to the aforesaid items in the mode and
manner that may be specified.
69. INTEREST ON MONEY DUE TO THE CONTRACTOR
The contractors shall not be entitled to get interest on any amount either of their bills or
arrears whatsoever because of delay in payment by the Corporation. Similarly they shall
not be entitled for any interest on amount of bank guarantees given by them. Non-
payment of interest by the Corporation therefore, shall not cause breach of contract.
70. MEASUREMENTS TO BE PROVISIONAL AND SUBJECT TO CORRECTION
Every measurements for running payment on account of work, done or supplies made,
shall be subject to adjustment or final measurements. In case of disagreement between
such intermediate and final measurements, the latter shall prevail. All works shall be
measured, met by standard measure and according to rules and custom and usual in the
use in Gujarat State Electricity Corporation Ltd., and no proposal to adopt alternative
EW- 257 PUR-F-006 RFQ-74075
method will be accepted, the Executive Engineer’s decision as to what is “the usual
method in use in the Gujarat State Electricity Corporation Ltd.” shall be final.
71. BREACH ON PART OF CORPORATION NOT TO ANNUAL CONTRACT
No breach or non-observance on the part of the Corporation of any of the agreements
contained herein, shall annul this contract or discharge the contractor from the
observance and performance thereof, or of any part thereof, but on application by the
contractor and in the unfettered discretion of the Engineer-in-charge an extension of
time may be given to the contractor in respect of such breach or non-observance by
the Corporation.
72. PROFORMA RETURNS
The contractor shall maintain Performa, charts and details regarding machinery
equipment materials, labour personnel and other matters as may be specified by the
Engineer-in-charge. He shall further, submit returns of Performa and details as may
be specified by the Engineer-in-charge from time to time.
All local laws in force at the time of entering into the contract and those enacted
thereafter shall be binding on the contractor and he shall abide by the same.
All import duties, sales tax and other local taxes shall be borne by the contractor and
they shall be deemed to have been covered by this quoted tender rate
74. WORKS IN SHIFT DUTY
Works shall be planned in shift duties, if possible in three shifts, depending on
emergency of the work with prior approval of Eng. - in- charge. 0n Sunday or any other
holidays work shall be continued in order to maintain progress with prior permission of
Eng.-in -charge. Such works shall not form any grounds for complaint, compensation or
extension of time limit.
If on the other hand, the Engineer-in-charge directs that the work shall be proceeded
with on days and during hours which are not permissible under this contract, the
contractor shall proceed with the work as directed without in any way vitiating this
contract or forming any grounds for compensation of claim.
The contractor shall in his dealing with labour, atall times, during the period of this
contract, have due regard to local festivals and religious and other customs.
A working day shall consist of two shifts each of eight hours, a working day shall
constitute any day on which in the opinion of the Engineer-in-charge, work can be
carried out in one or more shifts.
Final payment to the contractor shall not be made until the contractor shall deliver to the
purchaser or receipts in full in lieu thereof, and in either case, an affidavit that so far he
has knowledge or information the releases and receipts include all the labour and
material for which in lien could be filed. If any lien remains unsatisfied after all payments
are made, the contractor shall refund to the purchaser all moneys that the latter may be
compelled to pay in discharging such a lien, including all costs and a reasonable
76. MISCELLANEOUS:
1. In case of conflict / discrepancies among clauses of different specifications given in
this document, the stringent specification shall be followed and under such
circumstances, the decision of the EIC shall be final and binding to the Contractor
2. The Notice inviting tender, general instruction to bidders and all other documents of this
tender shall form part of the contract
3. No receipt for any payment alleged to have been made by a Contractor in regard to any
matter relating to tender of the contract shall be valid and binding on the Corporation
unless it is signed by the Engineer-in-Charge.
4. As per provisions of Income Tax Act, Corporation shall deduct Income Tax at the
applicable rate.
EW- 257 PUR-F-006 RFQ-74075
5. Agency has to note that the extension of Time limit/excess saving in the works if
required to approve, than it shall be processed as per the provision of DoP and will take
time for process the same.
6. The contract is inclusive of the cost of materials required to complete the work in
7. It will be absolutely incumbent on the contractors to have on the site of work only such
of the materials as have been duly passed by the Engineer-in-charge. Materials that have
been rejected must on no account be allowed to remain on the site, and in spite of
written order to do so, any such rejected materials is on the site beyond a period of
hours’ notice, the Engineer-in-charge shall have the right to remove it, at the risk and
cost of the contractors and even to destroy it.
8. It must be distinctly understood that conditions of contract and of claims in respect of
extra work, will not be allowed unless the works to which they relate is clearly without
the spirit and meaning of the specifications or unless such works are ordered in writing
by the Engineer-in-charge and claimed for in specified manner.
9. Contractor will be asked to present the sample of materials, and the approved samples
will be preserved at the site of work, and no change in the approved sample will be
allowed, without the written permission of the Engineer-in-charge.
10. The department reserves the right to make any change in the design and the plans of the
works. The contractor shall be bound to carry them out at the rates tendered. No claim
or compensation will be allowed on this account.
11. The contractor shall keep instruction book on site, for taking site instructions from time
to time. This book shall be made available on site whenever asked for.
12. Above construction equipment brought to site shall be allowed to be taken out only after
the work for which it has been brought is over. The equipment shall be taken out only
with the specific permission in writing from the E.I.C. Only the equipment required for
the work and in fit condition shall be brought to the site. The Contractor shall ensure
that proper documentation is followed at entry gate of GSECL's premises for such items
which shall be carried back by Contractor after completion of work.
13. The Contractor shall provide all temporary ladders, scaffolding materials, platforms,
supports and other necessary facilities required for trimming & cutting of trees. The
Contractor shall provide sufficient, strong and safe staging so as to ensure safety of the
14. The Contractor shall provide sufficient fencing, notice Corporations and lights to protect
and warn others as may be considered necessary by the GSECL and safety authority.
15. The GSECL may during the progress of work, order the removal of part or whole of the
work executed, found not in accordance with the approved drawings, specifications/
instructions. No extra claims shall be entertained for re-executing or altering of such
16. On completion of the work, the site shall be left in good order and the excess materials,
scraps, debris, if any shall be removed and dumped by the Contractor at place/places as
designated by the GSECL. The Contractor shall also dismantle and remove the staging
and other temporary facilities like stores, offices, labor camp etc. on completion of work.
17. Contractor is required to maintain proper records at site of work in addition to normal
routine requirement of own office. The records to be maintained shall include but not
limited to the following:
(a) Daily Progress Record.
(b) Work Site Order Book.
(c) Instruction by GSECL's Officers.
(d) Test Registers of other materials/fittings, fixtures, equipment as stipulated in the
(e) Register for Working Details.
(f) Log Book of Defects.
(g) Hindrance Register giving details of commencement and removal of each
(h) Supply and consumption registers of all materials shall be maintained.
(i) Day to day Record of used/received materials shall be entered in the register and
signed by the Site Engineer of the GSECL as well as contractors' representative at
(j) Measurement Book.
EW- 257 PUR-F-006 RFQ-74075
77. SALES TAX ON WORK CONTRACT
The Gujarat Government by its amendment to the Gujarat sales tax act has also
made works contract subject to Sales Tax. However works contract tax shall be
liability of the contractor and shall be born by the contractor. More ever you shall
also have to submit form No 702 as prescribed by Gujarat Sales Tax act while
submitting invoice.
More ever the purchaser will not pay any composite tax/turnover tax/works
contract tax which contractor has to pay as per act. Hence the incidence of sales
tax or such type of taxes shall not be payable by the purchaser in any case even if
such taxes are levied on the party/contractor at a future date.
For & On behalf of GSECL
CHIEF ENGINEER (Gen)
SIGNATURE OF CONTRACTOR
EW- 257 PUR-F-006 RFQ-74075
TERMS AND CONTRACT FOR WORKS
GENERAL SAFETY RULES
LIST OF SAFETY TOOLS
EW- 257 PUR-F-006 RFQ-74075
TENDER & CONTRACT FOR WORKS
I/We hereby tender for the Gujarat State Electricity Corporation Ltd. (herein Referred as
“Corporation”) of the work specified in the underwritten memorandum within the time specified
in Schedule B (memorandum showing items of work to be carried out) and in accordance, in all
respect, with the specifications, design, drawings and instructions in writing and as per annexed
conditions of contract and agree that when the materials for works are provided by the
Corporation, such materials and rates to be paid for them shall be as provided in Schedule A
(a) General description of work : Miscellaneous civil works for maintenance of plant
in PH area at Gandhinagar TPS
(b) Estimated cost : Rs. 3329080.76/-
(c) Earnest money (3%) : Rs. 99872.00/-
(d) Security deposit : As per cl no.7 of Section C (i.e General condition of
(e) Time allowed for the completion of work from date of written order to commence.:
12 (Twelve) Months
Should this tender be accepted, I/We hereby agree to abide by and fulfill all the terms and
provision of the conditions of contract annexed hereto as applicable and in default thereof
forfeit and pay to the Corporation, the sums of money mentioned in the said conditions.
Receipt No. Date from the Gujarat State Electricity Corporation Ltd. in respect of the sum of
Rs____________________________________. (The amount to be specified in figures and
words) is herewith forwarded representing the earnest money (the full value of which is to be
absolutely forfeited to the Corporation, should I / we do not execute / commence the work
after issuance of date of commencement by GSECL.
Signature of the Contractor:
Address of the Contractor:
Signature of Witness:
Address of the Witness:
The above tender is hereby accepted by me on behalf of the Gujarat State Electricity Corporation
For & On behalf of GSECL
Chief Engineer (Gen)
GSECL GANDHINAGAR TPS
his duly authorized Assistant
EW- 257 PUR-F-006 RFQ-74075
General Safety Rules & List of Safety Tools.
“GENERAL SAFETY RULES / NORMS” TO BE OBSERVED BY THE CONTRACTORS
All the contractors working in Gujarat State Electricity Corporation Limited Factory like
Coal/Lignite/Gas/Hydro/Pumping Station shall have to strictly observe the following Safety
Rules. Concern principle contractors are responsible for informing & observance of these rules by
their supervisors/contract workers as well as the owner/supervisors/ workers of sub-Contractors
engaged, if any, by them for the work contract awarded to them. Prior to commencement of the work,
Contractor shall have to submit a written assurance on their letterhead to the concerned Sectional
Head / Engineer-in-charge that they have thoroughly gone through these Rules, have educated their
employees / workers of their sub contractor and will strictly observe the said Rules while execution
of work under work contract awarded to them. They will have to indemnify the company for any loss
or damage / accident / injury to the company’s property / employee or employee of their own in
default of non - observing these rules.
(01) Contractor s hould issue photo gat e pass f or their workers from GSECL F actory
Manager as per G uj arat Factories r ules, 1963 & details shall be fi lled up in
GSECL gate pass f orm at as per A adhar car d /Election card id proof & to follow
the gate pass issue procedur e throug h concern department EE & SE, Security Officer,
LWO/IRO/DGM, Factory Medical Officer, Safety Officer/Dy. Safety Officer & Factory Manager.
(02) In case of emergency, temporary photo gate pass shall be issued by Security Officer only for
three days with prior permission of Factory Manager only. More than three days, Permanent
photo gate pass procedure shall be completed by contract agency for their contract workers.
(03) Certificate of Fitness of employment in hazardous process & operations in form no.33 of Gujarat
Factories rules, 1963 shall be issued by GSECL Factory Medical Officer for all contractor
workers before commencement of work & examination responsibility shall be taken by
contractor as well as concerned Head of Department .Pre-employment & Periodical medical
examination of contractor workers shall be carried out in form no.32 from GSECL Factory
Medical Officer after every six (06) months of contractor with their contractor workers.
Contractor shall be fulfilled all health requirements before commencement of work. After
completion of medical examination in form no.32/33, GSECL Factory Medical Officer shall be
signed in contract worker gate pass procedure format.
(04) Contract worker gate pass will issue after completion of safety induction 3D animation movie &
Training record is to be maintained in IMS/OHSAS training format by TK Office/LWO.
(05) As per Gate pass format of GSECL, Safety Officer/Dy. Safety Officer shall be checked the issue
PPE to contract workers as per nature of job, Form no.10 of lifting tools and tackles, Driving
license, Electrical contractor license, Electrical trade qualifications, Safety induction training,
SOP, supervisor qualifications etc. After fulfillment of all Safety compliances, Safety Officer/Dy.
Safety Officer shall be signed in Contract worker Gate pass procedure format.
(06) Work Contract shall be completed by principle contractor/agency/person who is awarded the
work order. Subletting of contract shall be allowed only if prior approval of Power station chief
before execution of work. Contractor/agency shall be submitted the entire subletting contract
documents with gate pass application through concern department EE & SE, LWO/DGM, Safety
Officer/Dy.Safety Officer & Factory Manager.
(07) Under The Conditions Framed Under Rule-45 Of The Indian Electricity Rules, 1956, Valid
Electrical contractor License shall be submitted to concern electrical department
EE/SE/Electrical Safety Officer/ Safety Officer/Factory Manager at the time of apply gate pass
by agency/party with latest renewal from Chief Electrical Inspector, Gandhinagar- Gujarat.
Electrical License photocopy shall be checked by Concerned HOD of Electrical
Department/Electrical Safety Officer/Dy.Safety Officer/ Safety Officer/Factory Manager.
(08) As per nature of job/work, qualified supervisor (Diploma (Electrical/
Mechanical/Civil/C&I) + 3 years experiences or ITI + 10 years) shall be engaged by contract
agency & qualification certificate with experience certificate shall be submitted to concern
EE/SE/LWO/IRO/DGM/ Dy.Safety Officer /Safety Officer/Factory Manager at the time of apply
(09) As per rule 3 of CEA regulation ,2010: Designating person(s) to operate and carry out the
work on electrical lines and Apparatus, Contract person/worker possesses a certificate of
competency or electrical work permit, issued by the Appropriate Government. That means,
Electrical trade Qualification of contract worker/person like ITI-wireman/ Electrician, Diploma
EW- 257 PUR-F-006 RFQ-74075
(Elect), BE/B. TECH (Elect), ME/ M. TECH (Elect) shall be submitted to concern
EE/SE/LWO/IRO/DGM, Dy.Safety Officer/ Safety Officer/Factory Manager at the time of apply
for photo gate pass procedure.
(10) As per nature of job/work & during capital overhauling work /Annual overhauling work /24X7
round the clock work/major shut down work, Qualified Safety Officer/Manager/Supervisor
(BE/Diploma (Elect/Mech/Civil) + PDIS-Post Diploma in Industrial Safety) shall be engaged by
contractor during dangerous operations/dangerous works as well as day to day dangerous
activities, safety supervision, tool box talk, Safety awareness programme, SOP preparation with
hazards & its control measures with each step , checking of lifting tools & tackles, hydra mobile
crane, Safety precautions, coordination with Safety Department etc.
(11) License of driver shall be submitted with gate pass issue application as per nature of vehicles &
to follow the Motor vehicle Act,1988, the Central Motor Vehicles (Amendment) Rules,2016 as
well as Gujarat Motor Vehicles rules,1989 & driver license shall be checked every day by
security shift in charge before entry in the Factory premises.
(12) SOP with JSA (Job Safety Analysis) shall be prepared by contractor through competent person
as per GFR, 1963 or Qualified Safety Officer as per GFR, 1963 with 05 years experiences. SOP
will review & approve by concern JE/DE/EE/SE/Elect. Safety Officer/Dy. Safety Officer /Safety
Officer/Factory Manager before execution of work.
(13) It is compulsory to use standard make Personal Protective Equipments (P.P.Es.) as per the job
requirement. Do not work without use of required P.P.Es. Contractor is responsible to provide
standard make (ISI/DGMS/CE/EN/ANSI approved) & to checked standard/make in PPE issue
format by concern JE/DE/EE/SE/Safety Officer/Factory Manager. Personal Protective
Equipments / Safety Gadgets suitable to give sufficient protection against hazards involved in
their work / job to their staff, as per the job requirement and insist / enforce their workers to
put on the same while at works.
The ongoing work is liable to be stopped at any time if your contract workers/staffs found
working without P.P.Es. Following is the list of various P.P.Es (as per ISI/DGMS/CE/ EN/ ANSI
approved only) to be used for various works / worksites.
In any work, Contractor shall be issued the minimum 05 nos. of PPEs like Safety Shoes, Safety
Helmet, Safety goggles, Mask & Reusable Ear plug to their workers/supervisor compulsory & it
will check by concern section HOD & Dy.Safety Officer /Safety Officer at the time of gate pass
Industrial Safety Helmet For protection of head against falling objects or during fall of
person from height. Yellow Colour helmet is used for
contract worker with agency logo.
Safety Goggles/welding For protection of eyes against flying particles / dust,
goggles/chemical splash goggles chemical splash, welding spark, arc, flashover etc.
Full Face shield For protection of face against flying particles / dust,
chemical splash, spark, arc, flashover etc.
Reusable Earplug / Ear muffs. For ear / hearing system protection while working in high
noise level area.
Chemical suit/Gas tight suit For body protection against chemicals, oils, sharp edged
/Fire proximity suit/FR Boiler objects, heat, hot objects etc.
Safety Hand Gloves For protection of hands against chemicals, oils, sharp edged
objects, heat, hot metals/objects, electricity etc.
Safety shoes/ Gum Boots with For protection of leg/feet against falling objects, sharp
Oil/Chemical/water/heat/ edged objects, heat, hot metals/objects, electricity etc..
Electrical resistance etc.
Safety Belt(full body hardness For fall prevention while working at heights or in depth,
with double lanyard & shock working in vessel or in confined space.
absorber) / Rope / Life line /
Fall arrestor etc.
Dust Mask/Respirator with Protection of respiratory system against dust.
Chemical Cartridge Respirator Protection against toxic chemical fumes /
with full face mask type gases/vapors/dust etc.
EW- 257 PUR-F-006 RFQ-74075
Trolley mounted Air line Working in oxygen deficient zone or confine space area
respirators with full face mask
Portable Single gas detector like Working in hazardous storage/process area
Chlorine, Ammonia, Hydrogen,
Portable Multi gas Detector (
Working in oxygen deficient zone & use in entry of confine
LEL,O2,CO,H2S,SO2, etc) space & Major fire
Automatic voltage detector To check the present voltage or induction voltage of
electrical equipments/ bus/switch gears from 01 (one)
feet distance before starting the any electrical work .
Auto darkening welding helmet The new auto darkening welding helmet combines
(EN 379 & EN 175 Level-B) with legendary Speed glass quality and auto darkening
PAPR as per EN 12941:1998, technology with an innovative wide-view grinding visor to
class TH2 and AS/NZS 1716 give welders an all-in-one solution for more flexibility,
precision, and efficiency.
Respiratory System is a combined face and breathing
protection device, for increased comfort and safety in
welding. The unit is equipped with a particle filter which
removes particles from the air. The unit provides a constant
airflow independent of filter combinations and clogging. The
unit can also be equipped with a gas filter (for example
A1B1E1). The unit supplies air to the head top via the
connecting breathing tube. The airflow creates a slight
positive pressure which together with the sealing to the face
prevents particles and other contaminants from entering the
(14) All PPEs (as per ISI/DGMS/CE/EN/ANSI approved only) Should issued by
party/agency/contractor to their contractor workers as per nature of job and allotment of PPE
list shall be submitted to Safety Officer, Dhuvaran on his letter head as per below mentioned
format by Contractor before commencement of work through concerned JE,DE,EE/SE .
Sub: Issue of PEE to Contractor workers
Sub of work Order:
Name of Agency:
Date of Commencement:
Time limit for work order:
Sr. Name Design Name of Name of PPE IS Make Qty Uni Date Receivin
no. of ation Section :Code of t of g
worker under work no. of PPE issue signature
s execution PPE
01 Safety Helmet No
Safety goggles No
Reusable Ear Pai
Safety Shoes Pai
(15) Shift Security Inspector/Security Officer shall be checked Safety Shoes & Safety Helmet of all
contractor workers at entry gate of Factory Premises & shall entered contractor workers with
Safety Shoes & Safety Helmet with photo ID Gate Pass.
(16) Shift Security Inspector/Security Officer shall be checked validity of Gate pass of all contractor
workers on daily basis.
EW- 257 PUR-F-006 RFQ-74075
(17) During the work execution, one trained & competent supervisor of agency should always
remain present at work site. Concern JE/DE of GSECL shall be supervised the contract work as
(18) Approved NABL laboratory calibration certificates of
electrical/mechanical/Civil/C&I/Environment survey/Chemical etc measuring /testing
equipments/instruments which are used during contract work shall be submitted before
starting the work & shall be checked by concern JE/DE/EE before starting work & it’s record
shall be maintained in concern section.
(19) The contractor shall take all the required safety measures prior to commencement of work on
dangerous substances, machineries or area at which cautionary notice is displayed and obtain
“Line Clear” or “Work Permit” through the concern Department / Section JE/DE and shall be
informed to concern section JE/DE for closed/ returned after completion of work.
(20) Safety talk/Safety work instructions shall be given to contractor workers by concern JE/DE
regarding hazards of specific work, risk & it’s control measure (mentioned in HIRA) before
starting the job work and records shall be maintained for each & every job works.
(21) Display Safety instructions shall be strictly followed by all workers who are working in factory
(22) Material Safety Data Sheet (MSDS) of each chemical shall be available with Chief
Chemist/Control room & work related Chemical information shall be taken by contractor &
contractor workers from Concern EE/Chief Chemist before starting of chemical handling work.
(23) The contractor shall be checked & securely covered or securely fenced any opened fixed vessel,
sump, tank, pit or opening in ground or in floor which, by reason of its depth, situation,
construction or contents ,is or may be a source of danger before starting the work each & every
days or after interval/recess. Contractor supervisor shall be informed to concerned HOD
regarding any unsafe conditions.
(24) Prohibition of smoking, fires, lights, spontaneous ignition substance, matches; fuses, mobile
phone etc are to be strictly followed by all workers who are working in factory premises.
(25) Prior to carrying out welding, gas cutting, furnace heating or any other hot work job, remove all
the inflammable material lying at or nearby worksite or cover it properly by suitable protective
covering. Also, special care shall be taken before carrying out such job & see that all possible
contributing factors to set fire shall be removed / vanished prior to commencement of the work.
Advance intimation shall be given to concerned section / fire section to commence the work in
fire prone areas. They should also keep ready all the First Aid Fire Extinguishers / equipments
& fire extinguishing media / material like sand / water buckets or other appropriate equipment
(26) While carrying out work in confined space or inside vessel, obtain necessary “Confined Space /
Vessel Entry Permit” from concerned department prior to commencement of the work.
For lighting in such areas, only 24-volt (ISI certified & with proper guard) hand lamp shall be
used. For taking care of the persons working inside the confined space / vessel, a supervisor /
person capable to keep continuous watch on person(s) working inside, assist them in case of
emergency or arrange to get immediate outside help, shall remain present at entry point. Use
full body safety belt without failed.
While working inside sewage, trench or in-depth, a person to warn outsiders / entrants /
passers etc shall remain available near entry point or the entry point shall be cordoned by a
barricaded tape with a cautionary notice. After completion of the works, all the lids / covers /
grills / grits opened, shall be re-fixed / re-placed in the original position as it were prior to
commencement of the work and leave the work place in safe condition in all respect, so as to
prevent accident to fellow workers.
(27) The contractor shall see that he / his persons do not work on or block (by stacking material,
spare parts, tools-tackles, equipments etc), any passages / walkways / gangways / aisles /
staircases / ladders / lifts or any other approaches / roads leading to plans or its auxiliaries, on
which there is traffic movements or possible traffic movements in case of emergency. Such
passages are meant for safe escape in the event of emergency. If it is utmost necessary to carry
out work in such area with blocking of passage, prior permission of Competent Authority or the
Engineer-In-Charge shall be obtained. To demarcate / declare the area as “UNSAFE”, cordon it
using barricading tape & display suitable caution notice or keep a person to restrict / divert the
traffic on this route through other safe passage.
(28) The contractor shall see that he / his persons do not work on or block (by stacking material,
spare parts, tools-tackles, equipments etc), any passages / walkways / gangways / aisles /
EW- 257 PUR-F-006 RFQ-74075
staircases / ladders / lifts or any other approaches / roads leading to plans or its auxiliaries, on
which there is traffic movements or possible traffic movements in case of emergency. Such
passages are meant for safe escape in the event of emergency. If it is utmost necessary to carry
out work in such area with blocking of passage, prior permission of Competent Authority or the
Engineer-In-Charge shall be obtained. To demarcate / declare the area as “UNSAFE”, cordon it
using barricading tape & display suitable caution notice or keep a person to restrict / divert the
traffic on this route through other safe passage.
(29) Prior to use power / electrically operated hand tools / equipments / machines / gadgets like
welding machine, hand grinder, hand drill etc, ensure for its safe operation & use it only if it is
found safe to use. Do not use defective, unsafe or improperly maintained equipments.
The electrical power supply required to run such equipments shall not be taken directly at their
own but shall be obtained through concerned Electrical Maintenance Departments or their
authorized persons or under their observations / guidance only. The Electrical Section shall
provide temporary electrical connection up to contractor’s Mains Board on which it is
compulsory to install mains switch, ELCB & fuses of adequate capacity. All such equipments
shall invariably be earthed adequately to prevent electrical shock, sparking, short circuit etc.
Power cord to be used shall be of adequate capacity, without any joint & shall consist of earth
wire also. Hence, it is necessary to use adequate capacity 3-wire power cord for single & 5-wire
power cord for three phase power connections. The plugs, receptacles, pins, holders etc shall be
of adequate capacity & safe to use.
All electrical & mechanical equipments / tools-tackles viz. welding machine, cutting machine,
Grinder, Drill, Chain Pulley Blocks, Hook chooks etc required to be used during work execution
shall be of standard make & bear ISI certification mark on it. The consumables like welding
electrodes, grinding wheels / discs etc which has specific prescribed life span shall not be used
in any case if its expiry date is over.
(30) Non-Sparking Non-Magnetic electrical hand tools and tool kits shall be used by Electrical
contractor for safe use in areas where hazardous, flammable, or combustible vapors, liquids,
dusts, or residues may be present in Gas Based power plant and list of tools and tackles shall be
submitted with technical bid. Non-Sparking Non-Magnetic electrical hand tools and tool kits
shall be checked by JE/DE before commencement of Electrical work.
(31) Before using lifting machines / tackles (like C.P.Bs., Hook chooks, winch, forklift, mobile crane,
EOT crane etc) & its attachments (like D-shackles, slings, U-clamps, Eye bolts or any fixtures), it
shall be checked and used only if found safe to use. Also, ensure that these are tested, examined
& certified in form no.10 by Competent Person as per the Factory act-1948 & Gujarat Factories
Rules and its validity do not expire. Further, it shall be fixed properly and firmly prior to lifting
the weight. Valid Test certificate of all Lifting machines used by Contractor to be
submitted to Dy.Safety Officer/ Safety Officer before commencement of work through
concerned EE/SE.
(32) Metal Scaffoldings to be used for working at height shall be of adequate size & capacity. Obtain
the work permit when working at height. While climbing on such scaffolding or working on any
structure at height, use of full body safety belt /full body hardness with double lanyard & Fall
arrestor & Helmet is compulsory. It is also necessary to fasten chinstraps of the helmet.
(33) Contractor or their employee shall not interfere in day-to-day routine plant activities / works
except the work assigned to them, shall not loiter in the areas other than their work jurisdiction,
as well as shall not temper / operate / touch the machineries/equipments/auxiliaries with
which they are not concerned. Also, the contractor shall strictly instruct their staff for not to sit
or take rest at/near/below running plants, auxiliaries, systems or any place which is risky,
hazardous & prone to accident.
(34) The cylinders containing poisonous / toxic or inflammable / explosive gas like Oxygen,
Acetylene, LPG, Hydrogen, Ammonia, Chlorine, CO2 etc shall be handled safely taking due care.
To handle / shift such cylinders a special trolley /cage meant for it must be used but in no case
it should be rolled.
(35) In Gas Based Power station/Hydrogen storage area /Hydro carbon fumes-vapour generated
area, Spark arrestor (as per approved manufacturer of CCOE, Nagpur) shall be provided on each
vehicle by party/agency and it will check by shift security in charge before entry of vehicles in
the factory premises.
(36) No women or young person shall be employed or permitted to work in Lead-compound area
like battery room etc. as per schedule VI of GFR
EW- 257 PUR-F-006 RFQ-74075
(37) No women or young person shall be allowed to clean, lubricate or adjust any part of a prime
mover or of any transmission machinery while the prime mover or transmission machinery is in
motion. Examination or operation of motion machinery shall be made or carried out only by a
specially trained adult male worker wearing tight fitting clothing as per section 22 of factories
(38) In all risky job, before start the work, contractor should obtain General Safety Work Permit
through concerned section from Shift –in-charge well in advance.
(39) In case of noticing smoke or fire during their work execution, they shall make immediate efforts
to extinguish / control it and simultaneously inform the Fire Station Mobile No as well as
Station Fire Officer or Emergency Control room no which is displayed at prominent place of
factory like Main Security Gate, All unit control room, Canteen area, Safe Assembly points, Fire
Station, All security gates, Occupational Health Centre.
(40) In case of any injury / accident while working, it shall immediately be reported to Safety
Department through concerned Sectional Head / Engineer. The prescribed Form No. 21 &
ANNEXURE may be obtained from concerned section or Dy.Safety Officer/Safety Officer.
In case of any electrical accident, it shall immediately be reported to Electrical Safety Officer
through concern Sectional Head / Engineer. The prescribed Electrical accident form no. A as
per electricity act-2003 & Form No. 21 & ANNEXURE as per Gujarat Factories rules shall be
filled up by concern department JE/DE with written consent of contractor. The Form may be
obtained from concerned Electrical section or Electrical Safety Officer. Electrical accident
investigation shall be carried out by Electrical Safety Officer with Factory Manager.
After any reportable accident, Contract agency shall be submitted the fitness certificate of
injured person with endorsement of GSECL factory Medical Officer to LWO/Dy.Safety
Officer/Safety Officer/Electrical Safety Officer then after injured person may allow for work.
(41) For any incident occurred but have no injury to any persons should also reported as per GSECL
format and informed to Dy.Safety Officer/Safety Officer as Near Miss Incident.
(42) Safety penalty shall be imposed against violation by contract workers: if any contract worker
worked in a factory contravenes any provision of factories act or any rules or orders made there
under. Imposing any duty or liability on workers, contractors/agency shall be punishable with
fine which mentioned as under.
Sr. Description of penalty Amount
(i) Work without PPEs Rs.300/- per person
(ii) Work without work Safety permit like working at height, Rs.1000/- per day
confine space entry, hot work etc.
(iii) License of driver as per type of vehicles not registered. Rs.750/- per person
(iv) Welding work without flashback arrestor/double gauge Rs.1000/- per set
(v) Operate Portable power tool without ELCB Rs.1000/-per
(vi) Work without qualified Supervisor as per nature of job like Rs.1000/-per day
mechanical, electrical, civil, C&I, chemical etc.
(vii) Work without SOP & JSA Rs.2000/-per day
(viii) Work without test report of lifting machines / tackles (like Rs.2000/- per
C.P.Bs., Hook chooks, winch, forklift, mobile crane, EOT crane equipment
etc) & its attachments (like D-shackles, slings, U-clamps, Eye
bolts or any fixtures) in Form No.10 of Gujarat Factories
(ix) Work without Double lynyer Safety belt during working at Rs.3000/-per person
Height work, work without anchoring in hook/line line
(x) Work without 24 Volt supply in Confine space area Rs.3000/-per person
(xi) (a) Grinding machine used without safety guard/ machine Rs. 500/- per
guard equipment/ per set
(b) Unsafe welding machine like open body. Knob without
insulation. Connection without plug
(c) Damaged welding cables/gas pipelines
(d) Welding work doing without welding blanket.
(e) Electrical supply without 3 pin plug/industrial plug.
EW- 257 PUR-F-006 RFQ-74075
(f) Use of damaged electrical wire for lighting/equipments.
(g) Use of lighting lamp without cage.
(h) Use of open halogen tube.
(i) Use of damaged PPEs/use of non standard PPEs
(j) Unsafe lifting and handling of gas cylinders
(k) Cylinder handling without safety cap
(l) Temporary connection without ELCB. etc
During plants visit/supervision of concern JE/DE/EE,SE. Safety officer/Dy. safety officer.
Electrical safety officer , factory manager, if they will observed any safety violations as per CO
circular/statutory requirements then they must imposed safety penalty through office note
directly against contract workers/contract agency and Office Note process through proper
channel to concern sectional head and Account head for recovery purpose. Photograph/CCTV
Footage is to be put a with penalty note by imposing officer.
(43) Party will damage any fire equipments or property or machinery in factory during execution of
work, total damage cost will be recovered from party RA bill and recovery Office note put up by
(44) All the relevant labour and industrial laws shall also be followed compulsorily.
(45) After completion of work, cotton waste, grease, oil, unused material, welding rod pieces, scrap
etc. are to be removed by contractor and scrap shall be deposited to scrap yard of Main Store.
(46) For performance evaluation of contractor, safety factors of work accident, fire incident & near
miss accident will be considered. Steps can be taken to review the job assignment up to
cancellation for negligence.
(47) Over & above these, contractor shall have to follow all the safety requirements /rules &
regulations / norms and legal provisions laid down in various statutes. Particularly the
provisions of The Factories Act-1948 & the Gujarat State Factories Rules-1963 (Amended up to
date), The Electricity Act-2003 & rules, BOCW Act/Rules shall be followed strictly. The
contractor shall also obey the rules / regulations / instructions of the local Competent Authority
for safety & health requirements.
(48) The above rules shall be scrupulously followed and where required, Contractor /contractor
workers may contact to the Dy.Safety Officer/Safety Officer/Electrical Safety Officer in case of
any ambiguity or needs further guidance in this regard.
(49) As per C.O circular No. GSECL/Medical/PME/O1 DTD.16.07.2019 i.e for procedure for health
cheak-up accordingly bill shall be reimbursed once during total contract period (for as & when
and AOH/COH contract) maximum up to Rs.1000 or actual cost per worker/ labour /person,
whichever is minimum after verification & recommendation by concern doctor. In case any
worker left the work in between than for replacement Worker Company will not provide any
reimbursement, however it is compulsory to submit new report of replacement worker for
fitness certificate at contractor’s own expense.
Chief Engineer (Gen.)
GSECL,GandhinagarTPS
SIGNATURE OF CONTRACTOR
(With Rubber Stamp & Date)
EW- 257 PUR-F-006 RFQ-74075
PERFORMA FOR BANK GUARANTEE
INTEGRITY PACT
CERTIFICATE – A
EW- 257 PUR-F-006 RFQ-74075
ON STAMP PAPER OF Rs.300/-
FORM OF BANKER’S UNERTAKING
(For Security Deposit for work period as per Terms and Conditions of Tender)
unequivocally and unconditionally to pay immediately on demand in writing from the Gujarat
State Electricity Corporation Limited, or any Officer authorized by it in this behalf any amount up
to and not exceeding Rs.__________ (in words) Rupees
to the said Gujarat State Electricity Corporation Limited on behalf of
contract for the supply / works specified below :
This agreement shall be valid and binding on this Bank up to and inclusive of________________
and shall not be terminable by notice or by change in the constitution of the Bank or the firm of
Contractors / Suppliers or by any other reason whatsoever and our liability hereunder shall not
be impaired or discharged by any extension of time or variations or alterations made, given
conceded or agreed, with or without our knowledge or consent, by or between parties to the said
within written contract.
Notwithstanding anything contrary contained in any law for the time being in force or banking
practice this Guarantee shall not be assignable, transferable by the beneficiary (i.e. GSECL or
Subsidiaries). Notice or invocation by any person such as assignee, transferee or agent of
beneficiary shall not be entertained by the Bank. Any invocation of the Guarantee can be made
only by the beneficiary directly
“NOT WITHSTANDING” anything contained herein before, our liability under this guarantee is
restricted to Rs._______________ (Rupees
remain in force until _______________ (date of validity of the Guarantee). [Unless demands or
claims under this Bank Guarantee are made to us in writing on or before _____________ (date
of validity of the Guarantee), all rights of Beneficiary under this Bank Guarantee shall be forfeited
and we shall be released and discharged from all liabilities there under]:
Please Mention here Complete Postal Signature of
Address of the Bank with Branch Code, Bank’s Authorized Signatory
Telephone and Fax Nos. with Official Round Seal
EW- 257 PUR-F-006 RFQ-74075
NAME OF DESIGNATED BANKS: (Annexure – I.)
A Guarantees issued by following banks will be accepted as SD/EMD on
permanent basis.
1. All Nationalized Banks.
B Guarantees issued by following Banks will be accepted as SD/EMD for
period up to March 31, 2026. The validity cut-off date in the GR is with
respect to date of issue of Bank Guarantee irrespective of date of
termination of Bank Guarantee.
2. A U Small Finance Bank
3. Bandhan Bank
4. Barclays Bank
5. City Union Bank
7. DBS Bank India Limited
9. Equitas Small Finance Bank
10. ESAF Small Finance Bank
11. Federal Bank
16. IDFC First Bank
17. Jammu and Kashmir Bank
18. Jana Small Finance Bank
19. Karnataka Bank
20. Karur Vysya Bank
21. Kotak Mahindra Bank
22. South Indian Bank
23. Standard Chartered Bank
24. Tamilnadu Mercantile Bank
25. Utkarsh Small Finance Bank
27. Ahmedabad Mercantile Co-Operative Bank
28. Nutan Nagrik Sahakari Bank Ltd.
29. Rajkot Nagrik Sahakari Bank Limited.
30. Sarswat Co-Operative Bank Ltd.
31. SBPP Co-operative Bank LTD
32. SVC Co-Operative Bank Ltd.
33. The Cosmos Co-op Bank Ltd.
34. The Gujarat State Co-Operative Bank
35. The Mehsana Urban Co-Operative Bank Ltd.
36. The Surat District Co-operative Bank
37. The Surat Peoples Co-operative Bank Ltd.
38. The Kalupur Commercial Co-operative Bank
39. The Panchmahal District Co-operative Bank
40. The Baroda District Co-operative Bank
41. Baroda Gujarat Gramin Bank
42. Saurashtra Gramin Bank
EW- 257 PUR-F-006 RFQ-74075
EMD BANK GUARANTEE FORMAT
(BANK GUARANTEE ON NON-JUDICIAL STAMP PAPER OF Rs.300)
(Name and Address of the Firm) having their registered Office at
_________________________________________________(Address of the Firm’s registered
Office) (hereinafter called the Tenderer) wish to participate in the Tender
/ Erection / Supply & Erection / Work) of __________________________________ (Name of the
material / equipment / work) for _________________________ Gujarat State Electricity
Corporation Limited and WHEREAS a Bank Guarantee for (hereinafter called the “Beneficiary”)
Rs. _____________ (Amount of EMD) valid till ____________ (mention here date of validity of
this Guarantee which will be 4 (FOUR) months beyond initial validity of Tender’s offer) which is
required to be submitted by the Tenderer along with the Tender.
(Name of the Bank and address of the Branch giving the Bank Guarantee) having our registered
Office at _____________________ (Address of Bank’s registered Office) hereby give this Bank
Guarantee No. _________________dated ____________ and hereby agree unequivocally and
unconditionally to pay immediately on demand in writing from the Gujarat State Electricity
Corporation Limited or any Officer authorized by it in this behalf any amount not exceeding
Rs.____________ (amount of EMD) (Rupees
Gujarat State Electricity Corporation Limited on behalf of the Tenderer.
We, ____________________________________________ (Name of the Bank) also agree that
withdrawal of the tender or part thereof by the Tenderer within its validity or non-submission of
Security Deposit by the Tenderer within one month from the date of tender or a part thereof has
been accepted by the Gujarat State Electricity Corporation Limited would constitute a default on
the part of the Tenderer and that this Bank Guarantee is liable to be invoked and encased within
its validity by the Beneficiary in case of any occurrence of a default on the part of the Tenderer
and that the encased amount is liable to be forfeited by the Beneficiary.
This agreement shall be valid and binding on this Bank up to and inclusive
of____________________ (mention here the date of validity of Bank Guarantee) and shall not
be terminated by notice or by Guarantor change in the constitution of the Bank or the Firm of
Tenderer or by any reason whatsoever and our liability hereunder shall not be impaired or
EW- 257 PUR-F-006 RFQ-74075
discharged by any extension of time or variations or alterations made, given, conceded with or
without our knowledge or consent by or between the Tenderer and the Gujarat State Electricity
Corporation Limited.
Notwithstanding anything contrary contained in any law for the time being in force or banking
practice this Guarantee shall not be assignable, transferable by the beneficiary (i.e. GSECL or
Subsidiaries). Notice or invocation by any person such as assignee, transferee or agent of
beneficiary shall not be entertained by the Bank. Any invocation of the Guarantee can be made
only by the beneficiary directly.
NOTWITHSTANDING anything contained hereinbefore our liability under this Guarantee is
restricted to Rs. ________ (amount of EMD) (Rupees
________________________________________ (in words). Our Guarantee shall remain in
force till _____________ (date of validity of the Guarantee). Unless demands or claims under
this Bank Guarantee are made to us in writing on or before ___________ (date of validity of the
Guarantee), all rights of Beneficiary under this Bank Guarantee shall be forfeited and we shall be
released and discharged from all liabilities there under.
Please mention here complete Postal Signature of the
Address of the Bank with Branch Code, Bank’s authorized
Telephone and Fax Nos. Signatory with Official Seal.
EW- 257 PUR-F-006 RFQ-74075
GUJARAT STATE ELECTRICITY CORPORATION LIMITED- GTPS
To create an environment where Business Confidence is built through Best Business Practices
and is fostered in an atmosphere of trust and respect between providers of goods and services
and their users for the ultimate benefit of society and the nation.
GSECL’S COMMITMENT PARTY’S COMMITMENT
To maintain the highest ethical Not to bring pressure recommendations
standards in business and professions. from outside GSECL to influence its
Ensure maximum transparency to the Not to use intimidation, threat, inducement
satisfaction of stakeholders. or pressure of any kind on GSECL OR ANY
OF it’s employees under any circumstances.
To ensure to fulfill the terms of To be prompt and reasonable in fulfilling
agreement/contract and to consider the contract, agreement, legal obligations.
objectively the view point.
To ensure regular and timely release of To provide goods and / or services timely
payments on due dates for work done. as per agreed quality and specifications at
minimum cost to GSECL.
To ensure that no improper demand is To abide by the general discipline to be
made by employees or by anyone on maintained in our dealings.
To give maximum possible assistance to To be true and honest in furnishing
all the Vendors/Suppliers/Service information.
Provider and other to enable them to
complete the contract in time
To provide all information to Not to divulge any information, business
suppliers/contractors relating to details available during the course of
contract / job which facilitate him to business relationship to others without the
complete the contract / job successfully written consent to GSECL.
To ensure minimum hurdles to vendors Not to enter into carter / syndicate
/ suppliers / contractors in completion /understanding whether formal / non
of agreement / contract / work order. formal so as to influence the price.
Seal & Signature Seal & Signature
(GSECL’s Authorized Signatory) (Party’s Authorized Person)
EW- 257 PUR-F-006 RFQ-74075
On Firm’s Letter Head
CERTIFICATE - A
I / We ________________________________________________ authorized signatory of
M/s. _____________________________________________ is not related with other firms who
have submitted tenders for the same items under this inquiry / Tender.
Signature of the Tenderer
With Designation
Seal of the Firm
EW- 257 PUR-F-006 RFQ-74075
SPECIAL CONDITIONS FOR USE OF CEMENT
APPROVED NAME OF MANUFACTURERS OF
GENERAL GUIDELINES RELEVANT TO I.S.
EW- 257 PUR-F-006 RFQ-74075
SPECIAL CONDITIONS FOR USE OF CEMENT IN WORK
1 The rates in Schedule – ‘B’ is inclusive of cement cost. Contractor has to purchase fresh
grade cement confirming to as per IS 8112 Or PPC IS 1489 (Part-I) or as per tender
2 Contractor has to construct pucca Go down at site of work so that cement bags can be
properly preserved to avoid damage due to any kind of water/Humidity.
3 Contractor has to bring sufficient quantities of cement bags to maintain progress of work.
The work should not suffer for want of cement.
4 Cement should be used to achieve required strength in cement concrete or as per item
5 To bring sufficient & timely cement at site is full responsibility of contractor. Nothing extra will
be paid on account of any reason to maintain progress of work and to complete the work in
6 Contractor has to submit material A/c. For consumption of cement used with every bills. In
case of not submitting the same, bill will not be passed. Party has to submit the copy of
cement purchased bill and Challan/invoice along with each RA Bill/Final Bill.
7 No negative variation will be allowed for consumption in cement less then prescribed as per
R & B SoR OR Corporation/mix design and nothing will be paid extra for over consumption.
8 Contractor is fully responsible for safety of cement at site; nothing will be paid extra on
account of safety.
9 If Corporation’s authorized representative wants to check cement stock at site, contractor has
to allow for the same at any time.
10 Contractor has to maintain day to day cement consumption / balance account at site.
11 As far as possible, contractor has to maintain supply of cement of only one brand & grade
throughout the work and on account of closer/shortage of approved brand, cement of other
brand in accordance of condition No. (1) Will be allowed by Engineer – in – Charge.
12 Minimum cement consumption considered for cement concrete having grade of M–15 / M –
20 / M – 25 / is 290 Kgs. / 360 Kgs / 380 Kgs. Respectively as per R&B SOR. Contractor has
to use minimum cement as above. Contractor should not use less than the prescribed
quantities of cement even in the case of mix design recommends lower quality. For other
items cement consumption shall be as per provisions of SoR without any negative variation.
Nothing will be paid extra for over consumption.
13 Contractor will be allowed to carry out work only after physical verification of cement brought
14 Full cement bags brought by contractor shall be entered at IN GATE of GANDHINAGAR,
EW- 257 PUR-F-006 RFQ-74075
The list of adopting cement and steel of companies / suppliers /
manufacturers are shown below:
EW- 257 PUR-F-006 RFQ-74075
(Signature of Contractor)
Address &Seal: Chief Engineer (Gen)
EW- 257 PUR-F-006 RFQ-74075
GENERAL GUIDELINES RELEVANT TO IS
Please refer latest edition of relevant Indian Standard Specification of Code i.e.
B.I.S. General relevant I.S. of B.I.S. shall prevail for all items including materials,
measurements etc.
The Item wise detailed specifications are intended for full description of items
covered by Schedule “B”. The specifications are not however intended to cover
every detail and the works shall be executed according to the spirit of the
specifications below and the best prevailing P.W.D. practice. The clarification to any
clause in detailed specifications shall be sought from the latest edition of relevant
I.S. specification and codes. Where these specifications are at variance with the
specification laid down in the I.S. Books stated above, the former will be applicable.
As regarded matters not covered by any of the above specification, the decision of
the Engineer-in-charge shall be treated as final and shall be binding upon the
contractor. The contractor is expected to get clarified any doubt about specification,
etc. before tendering by discussing with Engineer-in-charge.
For detail technical specification, the item wise description along with above general
specifications shall hold good.
For & On behalf of GSECL
CHIEF ENGINEER (Gen)
SIGNATURE OF CONTRACTOR
EW- 257 PUR-F-006 RFQ-74075
GENERAL SPECIFICATIONS
TECHNICAL SPECIFICATION
EW- 257 PUR-F-006 RFQ-74075
GENERAL SPECIFICATIONS
01. In the specifications, “as directed”/”Approved” shall be taken to mean “as
directed”/”approved” by the Engineer-in-charge.
02. Wherever a reference to any Indian Standard appears in the specifications, it shall be
taken to mean as a reference to the latest edition of the same in force on the date of
03. In “Mode of Measurement” in the specification wherever a dispute arises in the absence
of specific mention of a particular point or aspect, the provisions on these particular
points or aspects in the relevant Indian Standards shall be referred to.
04. All measurements and computations, unless otherwise specified, shall be carried out as
05. The distance which constitutes lead shall be determined along the shortest practical route
and not necessarily the route actually taken. The decision of the Engineer-in-charge in
this regard shall be taken as final.
06. Where no lead is specified, it shall mean “all leads”.
07. Lift shall be measured from plinth level.
08. Up to “floor two levels” means actual height of floor up to 6.5 Mt. Above plinth level.
09. Definite particulars covered in the items of work, though not mentioned or elucidated in
it, specification shall be deemed to be included therein.
10. Reference to specifications of materials as made in the detailed specification of the items
of work is in the form of a designation containing the number of the specification of the
material and prefix ‘M’ e.g. ‘M-5’.
11. Approval to the samples of various materials given by the Engineer-in-charge shall not
absolve the contractor from the responsibility of replacing defective material brought on
site or materials used in the work found defective at a later date. The contractor shall
have no claim to any payment or compensation whatsoever on account of any such
materials being rejected by the Engineer-in-charge.
12. The contract rate of the item of work shall be for the work completed in all respects.
13. No collection of materials shall be made before it is got approved from the Engineer-in-
14. Collection of approved materials shall be done at site of work in a systematic manner.
Materials shall be stored in such a manner as to prevent damage, deterioration or
intrusion of foreign matter and to ensure the preservation of their quality and fitness for
15. Cement, reinforcements bars & all other materials to be used shall be got approved from
EIC before starting of work. The cement, reinforcement steel & other materials to be
brought at site shall be entered at GANDHINAGAR, TPS main entry gate.
16. Materials, if and when rejected by the Engineer-in-charge, shall be immediately removed
from the site of work.
17. No materials shall be stored prior to, during and after execution of a structure in such a
way as to cause or lead to damage or overloading of the various components of the
18. All works shall be carried out in a workmanlike manner as per the best techniques for the
particular item.
19. All tools, templates, machinery and equipment for correct execution of the work as well
as for checking lines, levels, alignment of the works during execution shall be kept in
sufficient numbers and in good working condition on the site of the work.
20. The mode, procedure and manner of execution shall be such that it does not cause
damage or over loading of the various components of the structure during execution or
after completion of the structure.
21. Special modes of construction not adopted in general Engineering practice, if proposed to
be adopted by the Contractor, shall be considered only if the contractor provides
satisfactory evidence that such special mode of construction is safe, sound and helps in
speedy construction and completion of work to the required strength and quality.
Acceptance of the same by the Engineer-in-charge shall not, however, absolve the
EW- 257 PUR-F-006 RFQ-74075
contractor of the responsibility of any adverse effects and consequences of adopting the
same in the course of execution of completion of the work.
22. All installations pertaining to water supply and fixtures thereof as well as drainage lines
and sanitary fittings shall be deemed to be completed only after giving satisfactory tests
by the Contractor.
23. The contractor shall be responsible for observing the rules and regulations imposed under
‘Minor Minerals Act’ and such other laws and rules prescribed by Government from time
24. All necessary safety measures and precaution [including those laid down in the various
relevant Indian Standards shall be taken to ensure the safety of men, materials and
machinery on the works as also of the work itself.
25. The testing charge of all materials shall be borne by the Contractor unless recovery at
one percent towards using charges is separately made.
26. Approval to any of the executed items for the work does not in any way relieves the
contractor of his responsibility for the correctness, soundness and strength of the
structure as the drawings and specification.
For & On behalf of GSECL
CHIEF ENGINEER (Gen)
SIGNATURE OF CONTRACTOR
EW- 257 PUR-F-006 RFQ-74075
SPECIFICATIONS OF MATERIALS
1.1 Water shall not be salty or brackish and shall be clean, reasonably clear and free from
objectionable quantities of silt and traces of oil and injurious alkalies, salts, organic matter
and other deleterious material which will either weaken the mortar or concrete or cause
efflorescence or attack the steel in R.C.C Container for transport, storage and handling of
water shall be clean. Water shall conform to the standards specified I.S 456-1978.
1.2 If required by Engineer-in-charge it shall be tested by comparison with distilled water.
Comparison shall be made by means of standard cement tests for soundness, time of setting
and mortar strength as specified in I.S.269-1976. Any indication of unsoundness, change in
time of setting by 30 minutes or more or decrease of more than 10 per cent in strength of
mortar prepared with water sample when compared with the results obtained with mortar
prepared with distilled water shall be sufficient cause for rejection of water under test.
1.3 Water for curing mortar, concrete or masonry should not be too acidic or too alkaline. It
shall be free of elements which significantly affect the hydration reaction or otherwise
interfere with the hardening of concrete during curing or those which produce objectionable
stains or other unsightly deposits on concrete or mortar surfaces.
1.4 Hard and bitter water shall not be used for curing.
1.5 Potable water will be generally found suitable for curing mortar or concrete.
M-3. Cement: Cement shall be fresh 43 grade ordinary Portland cement confirming to IS
8112 or PPC IS 1489 (Part-I) and as per special conditions for use of cement in section-D.
6.1 Sand shall be natural sand, clean, well graded, hard strong durable and gritty particle free
from injurious amounts of dust clay, kankar nodules, soft or flaky particles shale, alkali, salts
organic matter, loam, mica or other deleterious substance and shall be got approved from
the Engineer-in-charge. The sand shall not contain more that 8 percent of silt as determined
by field test. If necessary the sand shall be washed to make it clean.
6.2 Coarse Sand: The fineness modulus of coarse sand shall not be less than 2.5 and shall not
The sieve analysis or coarse shall be as under:
I.S. Sieve Percentage by weight I.S. Sieve Percentage by weight
Designation Passing sieve Designation Passing sieve
6.3 Fine Sand : The fineness modulus shall not exceed 1.0. The sieve analysis of fine sand
shall be as under :
I.S. Sieve Percentage by weight I.S. Sieve Percentage by weight
Designation Passing through Designation Passing through
Grit shall consist of crushed or broken stone and be hard strong, dense, durable, clean,
of proper gradation and free from skin or coating likely to prevent adhesion of mortar Grit
shall generally be cubical in shape and as far as possible flaky elongated pieces shall be
avoided. It shall generality comply with the provisions of I.S. 383-1970. Unless special
stone of particular quarries is mentioned, grit shall be obtained from the best black trap or
equivalent hard stone as approved by the Engineer-in-charge. The grit shall have no
deleterious reaction with cement.
EW- 257 PUR-F-006 RFQ-74075
The grit shall conform to the following gradation as per sieve analysis :
I.S SievePercentage byPassing I.S. Sieve Designation
Percentage by Weight
Designation weight Passing through
The crushing strength of grit will be such as to allow the concrete in which it is used to
built up the specified strength of concrete.
The necessary tests for grit-shall carried out as per the requirements of I.S. 2386 (Parts I to
VII) 1963, as per instructions of the Engineer-in-charge. The necessity of test will be decided
by the Engineer-in-charge.
M-11. Cement Mortar:
11.1 Water shall conform to specification M-1. Cement: Cement shall conform to
specification M-3.
Sand: Sand shall conform to M-6.
11.2 Proportion of Mix: Cement and sand shall be mixed to specified proportion, sand
being measured by measuring boxes. The proportion of cement will be by volume on the
basis of 50 Kg./Bag of cement being equal to 0.0342 Cu. m. The mortar may be hand mixed
or machine mixed as directed.
11.3 Preparation of Mortar: 11.3.1 In hand mixed mortar cement and sand in the
specified proportions shall be thoroughly mixed dry on a clean impervious platform by
turning over at least 3 times or more till a homogenous mixture of uniform color is obtained.
Mixing platform shall be so arranged that no deleterious extraneous material shall get mixed
with mortar or mortar shall flow out. While mixing, the water shall be gradually added and
thoroughly mixed to form a stiff plastic mass of uniform color so that each particle of sand
shall be completely covered with a film of wet cement. The water cement ratio shall be
adopted as directed.
i. The mortar so prepared shall be used within 30 minutes of adding water. Only such
quantity of mortar shall be prepared as can be used within 30 minutes.
M-12 Stone Coarse Aggregate for Nominal Mix Concrete:
12.1 Coarse aggregate shall be machine crushed stone of black trap or equivalent and be
hard, strong, dense, durable, clean and free from skin and coating likely to prevent proper
adhesion of mortar.
12.2 The aggregate shall generally be cubical in shape. Unless special stones of particular
quarries are mentioned aggregates shall be machine crushed from the best black trap or
equivalent hard stone as approved. Aggregate shall have no deleterious reaction with
cement. The size of the coarse aggregate for plain cement concrete and ordinary reinforced
cement concrete shall generally be as per the table given below, However in case of
reinforced cement concrete the maximum limit may be restricted to 6 mm. less than the
minimum lateral clear distance between bars or 6 mm. less than the cover, whichever is
I.S. Sieve Percentage passing for I.S. Sieve Percentage passing for
Designation single sized aggregates of Designation single sized aggregates of
nominal size Nominal size
EW- 257 PUR-F-006 RFQ-74075
Note: This percentage may be varied somewhat by Engineer-in-charge when considered
necessary for obtaining better density and strength of concrete.
12.3 The grading test shall be taken in the beginning and at the change of source of
materials. The necessary test indicated in I. S. 383-1970 and I.S. 456-1978 shall have to be
carried out to be carried out to ensure the acceptability. The aggregates shall be stored
separately and handled in such a manner as to prevent the intermixing of different
aggregates. If the aggregates are covered with dust, they shall be washed with water to make
M-13 Black Trap or Equivalent Hard Stone Coarse:
13.1 Aggregate for Design mix Concrete: Coarse aggregate shall be of machine crushed stone
of black trap or equivalent hard stone and be hard strong dense, durable clean and free from
skin and coating likely to prevent proper adhesion of mortar.
13.2 The aggregates shall generally be cubical in shape. Unless special stones of particular
quarries are mentioned, aggregates shall be machine crushed from the best, black trap or
equivalent hard stones as approved. Aggregate shall have no deleterious reaction with
13.3 The necessary tests indicated in I.S. 383-1970 and I.S. 456-1978 shall have to be
carried out to ensure the acceptability of the material. If aggregate is covered with dust it
shall be washed with water to make it clean
15.1. The bricks shall be hand or machine molded and made from suitable soils and kiln-
burnt. They shall be free Iron crack and nodules of free lime. They shall have smooth
rectangular faces with sharp corners and shall be of uniform colour. The bricks shall be
molded with a frog of 100mm. X 40 mm. and 10mm. to 20 mm. deep on one of its flat sides.
The bricks shall not break when thrown oft the ground from a height of 600 mm.
15.2. The size of modular bricks shall be 190 mm. x 90 mm. x 90 mm.
15.3. The size of the conventional bricks shall be as under : (9” x 4 3/8 “ X2 3/4 “) 225 x
15.4. Only bricks of one standard size shall be used on one work. The following n-.rrances
shall be Permitted in the conventional size adopted in a particular work. Length + 1/8 “(3.0
15.5. The crushing strength of the bricks shall not be less than 50 Kg./Sq.Cm. The average
water Absorption shall not be more than 20 percent by weight. Necessary tests for crushing
strength and water absorption etc. shall be carried. Out as per I.S. 3495 (Part-I to IV)
M-18. Mild Steel Bars
18.1 Mild steel bars reinforcement for R.C.C. work shall conform to I.S, 432 (Part-II)
and §hail be of tested quality. It shall also comply with relevant part of I.S. 456-
18.2 All the reinforcement shall be clean and free from dirt, paint, grease, mill scale or loose
at the time of placing.
18.3 For the purpose of payment, the bar shall be measured correct upto 100 mm. length
and weight payable worked out at the rate specified below :
1. .6 mm. 0,22 Kg./Rmt. 8 20 mm. 2.47 Kg./Rmt.
EW- 257 PUR-F-006 RFQ-74075
M-19. High Yield Strength Steel Deformed Bars
19.1. High yield strength steel deformed bars be either cold twisted or hot/rolled, shall
conform to I.S. 1739-
1966 and I.S.1139-1966 respectively.
19.2. Other provision and requirements shall conform to specification No. M-18. for Mild
M-22 Structural Steel:
22.1 All structural steel shall conform to I. S. 226-1965. The steel shall be free from the
defects mentioned in I. S. 226-1975 and shall have a smooth finish. The materials shall be
free from loose mill scale, rust pits or other defects affecting the strength and durability.
Rivet bars shall conform to I. S. 1148-1973.
22.2 When the steel is supplied by the Contractor test certificates of the manufactures shall
be obtained according to I. S. 226-1975 and other relevant Indian Standards.
EW- 257 PUR-F-006 RFQ-74075
DETAILED TECHNICAL SPECIFICATIONS
NOTE: BOOKLET FOR “GENERAL TECHNICAL SPECIFICATIONS FOR BUILDING WORKS” OF R.
& B. DEPARTMENT, GOG, GUJARAT AND BOOKLET OF “GENERAL SPECIFICATION FOR CIVIL
WORKS” OF GSECL WILL BE AVAILABLE IN CIVIL OFFICE AT GANDHINAGAR TPS FOR
REFERNCE OF RELEVANT DETAIL SPECIFICATIONS OF ITEMS. SHALL BE CONSIDERED &
ADOPTED IN WORK.
Item No.1: Demolition of Brick work and stone masonry including stacking of
serviceable materials and disposal of unserviceable materials with all lead and lift. (ii)
In Cement Mortar.
1.0. Workmanship: The relevant specifications of item No. (3) shall be followed except
demolition of brick or stone masonry in cement mortar is to be done.
2.0. Mode of measurements & payment : The relevant specification of item No.3 shall be
followed. The unserviceable materials shall be stacked as directed by Engineer-in-charge
with all leads and lifts
The rate shall be for a unit of one cubic metre.
Item No.2: Demolition including stacking of serviceable materilas and disposal of
unserviceable materials with all lead and lift. (i) R.C.C. Work
1.0. Workmanship: The relevant specifications of item No.(3) shall be followed except that
demolition of R.C.C. work is to be done.
2.0. Mode of measurements & payment:
2.1. The relevant specification of item No.3 shall be followed except that the demolition of
reinforced concrete structure. The unserviceable materials shall be disposed of at all leads
and lifts. The rate excludes scraping straightening of reinforcement but includes cutting of
2.2. The rate shall be for a unit of one cubic metre.
Item No.3: Demolition and disposal of unserviceable materials with all lead and lifts.
(i) Unreinforced cement concrete
1.0. Workmanship :
1.1. The demolition shall consist of demolition of one or more parts of the building as
specified or shown in the drawings. Demolition implies taking up or down or breaking up.
This shall consist of demolishing whole or part of work including all relevant item as
specified or shown in the drawings.
1.2. The demolition shall always be planned before hand and shall be done in reverse order
of the one in which the structure was constructed. This scheme shall be got approved from
the Engineer-in-charge before starting the work. This however will not absolve the
contractor from the responsibility of proper and safe demolition.
1.3. Necessary dropping, shoring and under pinning shall be provided for the safety of the
adjoining work or property, which is to be left intact, before dismantling and demolishing is
taken up and the work shall be carried out in such a way that no damages is caused to the
adjoining property.
1.4. Wherever required, temporary enclosures or partitions shall also be provided.
Necessary precautions shall be taken to keep the dust nuisance down as and where
1.5. Dismantling shall be commenced in a systematic manner. All materials which are likely
to be damaged by dropping from a height or demolishing, masonry etc. Shall be carefully
dismantled first. The dismantled articles shall be properly stacked as directed.
EW- 257 PUR-F-006 RFQ-74075
1.6. All materials obtained from demolition shall be the property of Government unless
otherwise specified and shall be kept in safe custody until handed over to the Engineer-in-
1.7. Any serviceable material, obtained during dismantling or demolition shall be separated
out and stacked properly as directed, with all lead and loft. All unserviceable materials,
rubbish etc. Shall be stacked as directed by the Engineer-in-charge.
1.8. On completion of work, the site shall be cleared of all debris rubbish and cleaned as
Mode of measurements & payment:
Measurements of all work except hidden work shall be taken before demolition or no
allowance for increase in bulk shall be allowed. The demolition of lime concrete shall be
measured under this item. Specification for deduction for voids, openings etc. Shall be on
same basis as that employed for construction of work.
The unserviceable materials shall be disposed of at all leads and lifts. The rate excludes
scraping straightening of reinforcement but includes cutting of reinforcement.
The rate shall be for a unit of one cubic meter actual work done.
Item No. 4: Removing and scraping of old deteriorated plaster of any thickness from
wall / R.C.C member including stacking of serviceable material and disposal of
unserviceable from site of work with all lead and lift.
1.0. Workmanship: The relevant specifications of item No. (3) shall be followed except that
removing or scrapping of old plaster is to be done.
2.0. Mode of measurements & payment:
2.1. The relevant specification of item No.3 shall be followed except that the removing or
scrapping of old plaster. The unserviceable materials shall be disposed of at all leads and
2.2. The rate shall be for a unit of one Square meter.
Item No. 5: Dismantling of sheet roofing including ridges, hips, vallies, gutters etc
stacking of serviceable materials and disposal of unserviceable materials with all lead
and lift (II) A.C.sheet roofing.
Disposal shall be as directed including lead & lift.
Workmanship: The demolition shall consist of demolition of one or more parts of the
building as specified or shown in the drawings. Demolition implies taking up or down or
breaking up. This shall consist of demolishing whole or part of work including all relevant
item as specified or shown in the drawings.
1.2. The demolition shall always be planned before hand and shall be done in reverse order
of the one in which the structure was constructed. This scheme shall be got approved from
the Engineer-in-charge before starting the work. This however will not absolve the
contractor from the responsibility of proper and safe demolition.
1.3. Necessary dropping, shoring and under pinning shall be provided for the safety of the
adjoining work or property, which is to be left intact, before dismantling and demolishing is
taken up and the work shall be carried out in such a way that no damages is caused to the
adjoining property.
1.4. Wherever required, temporary enclosures or partitions shall also be provided.
Necessary precautions shall be taken to keep the dust nuisance down as and where
EW- 257 PUR-F-006 RFQ-74075
1.5. Dismantling shall be commenced in a systematic manner. All materials which are likely
to be damaged by dropping from a height or demolishing, masonry etc. Shall be carefully
dismantled first. The dismantled articles shall be properly stacked as directed.
1.6. All materials obtained from demolition shall be the property of Government unless
otherwise specified and shall be kept in safe custody until handed over to the Engineer-in-
1.7. Any serviceable material, obtained during dismantling or demolition shall be separated
out and stacked properly as directed, with all lead and lift. All unserviceable materials,
rubbish etc. shall be stacked as directed by the Engineer-in-charge.
1.8. On completion of work, the site shall be cleared of all debris rubbish and cleaned as
2.0. Mode of measurements & payment :
The rate shall be for a unit of one sq. Metre.
Item No.6: Dismentling of sheet roofing including ridges, hips, vallies, gutters etc
stacking of serviceable materials and disposal of unserviceable materials with all lead
and lift (I) G.I. sheet roofing.
Workmanship: The relevant specifications of item No. (5) shall be followed except that
dismantling of G.I sheet roofing is to be done.
Mode of measurements & payment:
The rate shall be for a unit of one sq. Metre.
Item No.7: Labour charges for fixing AC/GI plain or corrugated sheets roofing
including transportation & fixing the same by means of 6mm & 'J'bolt and nuts,
bitumen washer including 150mm overlap all sides completed as directed by EIC
(Payment shall be made for flat slopping area without overlapping area as per
specifications. Only AC/GI sheet shall be supplied by the GSECL free of cost)
1.0 Materials: AC/GI sheet shall be supplied by the GSECL free of cost at civil store.
2.0 Workmanship:
2.1 Laying of sheets :
2.3.1 The sheets shall be laid in purlins to a true plane with the line of corrugations truly
parallel or normal to the sides of area to be covered. The sheets shall not generally be built
into gables and parapets. They shall be bent up along their side edges close to the wall and
the junction shall be protected by suitable flushing or by projecting drip course..
2.3.2 The sheets shall be but to the dimensions of the shape of the roof either along their
lengths or their width or in slant across the line of corrugations at hips and valleys. The
sheets shall be cut carefully with a straight edge and chisel to give straight finish. The sheets
shall be laid such that the laps are turned away from the usual direction of local heavy rain.
2.3.3 Fixing of Sheets :
2.3.4.1 Sheets shall be fixed to the purlins or other roof members such as hips of
valley rafter etc. With ‘J’ or ‘L’ galvanized hook bolts and galvanised nuts 6 mm. Dia with
bitumen impact washers and G. I. Washers. Length of hook bolt shall be varied to suit the site
requirement. Bolts shall be sufficiently long so that after fixing the project above the top of
their nuts by not less than 12 mm. The grip of ‘J’ or ‘L’ hook bolts on the side of purlins shall
not be less than 25 mm. There shall be minimum of three hooks bolts placed at the ridge of
corrugations in each sheets in every purlin Coach screw shall not be used for fixing the
sheets to purlins.
2.3.4 Holes for all bolts shall be drilled and not punched in the ridges of the corrugations
from the under side while the sheets are on the ground. The holes in the sheets shall be at
least 50 mm. From the edge. Sheets drilled wrongly shall be rejected. The holes in the
EW- 257 PUR-F-006 RFQ-74075
washers shall be of the exact diameter of hook, bolts or the seam bolts. The nuts shall be
tightened from above to give a leak-proof roof.
2.3.5 The roof when complete shall be true to lines and slopes and shall be lead-proof.
3.0 Mode of measurements & payment:
3.1 The measurements of the C.G.I. sheet roof shall be taken for finished work in superficial
area in general plane (not girthed on the roof). The lapse between the C.G.I. sheets both at
their ends and along the side edges shall not be measured. The overlaps of C.G.I. sheets over
the valley piece and their under lap under the ridge, hip and flashing piece shall be included
in the measurements.
3.2 No deductions in measurements shall be made for openings for chimney stacks, sky
light etc. Of area upto 0.40 sq. Mt.nor extra be paid for extra labor in cutting and for extra
labor in cutting and for wastage etc. In forming such openings.
3.3 The rate of roof shall include the cost of labour involved in all operations described
above. The rate also includes the cost of provision, erection and removal of the scaffolding,
benching, ladders, templates and tools required for the proper erection and completion of
the work. The rate includes the cost of purloins, rafters and trusses.
3.4 The rate shall be for a unit of one sq. Meter.
Item No. 8: Providing corrugated G.I. Sheet of class-3 roofing fixed with glavanished
iron J or L Hook, Bolts and nuts 8mm diameter with bitumen and G.I. Limpet washer
or G.I. Limpet washer. Filled with white lead complete excluding the cost of purlins,
Rafters and Trusses (1) 0.80 mm thick sheet.
1.0 Materials: Corrugated G. I. Sheets shall conform to M-23 and as per manufacturer’s
specification. Providing and fixing TATA /JINDAL/ ESSAR make corrugated G.I Sheet of class-
3 as per item specification. 2.0 Workmanship : 2.1 Spacing of purlines : One purlin shall be
provided at the ridge and one at the caves. The spacing of other purlines for 0.8 mm. Thick G. I.
Sheet shall not exceed 1.80 meter. The purlin shall coincide with the center line of the end lap.
The ridge purlins shall be placed in such a way that the ridges can be fixed properly. The portion
overhanding the wall support shall not be more than one fourth of the spacing of purlins. 2.2 The
top surface of the purlins shall be painted before the sheets are fixed over them. Embedded
portions of purlins shall be finished with two coats of coal-tar. 46 | P a g e 2.3 Laying of sheets :
2.3.1 The sheets shall be laid in purlins to a true plane with the line of corrugations truly parallel
or normal to the sides of area to be covered. The sheets shall not generally be built into gables and
parapets. They shall be bent up along their side edges clost to the wall and the junction shall be
protected by suitable flushing or by projecting drip course. 2.3.2 The laps at end shall be provided
150 mm. Minimum for roof slopes 1 in 2 (1 vertical : 2 horizontal) and steeper but 200 mm. Shall
be provided for flatter slopes than those above. The side lap shall be provided two ridges of
corrugations at each side. 2.3.3 The sheets shall be but to the dimensions of the shape of the roof
either along their lengths or their width or in slant across the line of corrugations at hips and
valleys. The sheets shall be cut carefully with a straight edge and chisel to give straight finish. The
sheets shall be laid such that the laps are turned away from the usual direction of local heavy rain.
2.3.4 Fixing of Sheets : 2.3.4.1 Sheets shall be fixed to the purlins or other roof members such as
hips of valley rafter etc. With ‘J’ or ‘L’ galvanized hook bolts and galvanised nuts 8 mm. Dia with
bitumen impact washers and G. I. Washers. Limpet washers with white lead shall be used. Length
of hook bolt shall be varied to suit the site requirement. Bolts shall be sufficiently long so that
after fixing the project above the top of their nuts by not less than 12 mm. The grip of ‘J’ or ‘L’
hook bolts on the side of purlins shall not be less than 25 mm. There shall be minimum of three
hooks bolts placed at the ridge of corrugations in each sheets in every purlin and their spacing
shall not exceed 300 mm. Coach screw shall not be used for fixing the sheets to purlins. Where the
slopes of roof are not less than 2½ horizontal). (1 vertical : 2½ horizontal). Sheets shall be jointed
together at the side laps by galvanished iron bolts and nuts 25 mm. X 6 mm. Size each bolt with a
bitumen and G. I. Limper washer filled with white lead. Where the overlaps at the sides extend to
two corrugations these bolts shall be placed zigzag over the two over lapping corrugations so that
the ends of the overlapping sheets are drawn tightly towards each other. The spacing of same bolts
EW- 257 PUR-F-006 RFQ-74075
shall not exceed 600 mm. Along each of the staggered rows. 2.3.5 Holes for all bolts shall be
drilled and not punched in the ridges of the corrugations from the under side while the sheets are
on the ground. The holes in the sheets shall be at least 50 mm. From the edge. Sheets drilled
wrongly shall be rejected. The holes in the washers shall be of the exact diameter of hook, bolts or
the seam bolts. The nuts shall be tightened from above to give a leak-proof roof. 2.3.6 The roof
when complete shall be true to lines and slopes and shall be lead-proof. 3.0 Mode of
measurements & payment : 3.1 The measurements of the C.G.I. sheet roof shall be taken for
finished work in superficial area in general plane (not girthed on the roof). The lapse between the
C.G.I. sheets both at their ends and along the side edges shall not be measured. The overlaps of
C.G.I. sheets over the valley piece and their under lap under the ridge, hip and flashing piece shall
be included in the measurements. 3.2 No deductions in measurements shall be made for openings
for chimney stacks, sky light etc. Of area upto 0.40 sq. Mt.nor extra be paid for extra labor in
cutting and for extra labor in cutting and for wastage etc. In forming such openings. 3.3 The rate
of roof shall include the cost of all materials and labor involved in all operations described above.
The rate also includes the cost of provision, erection and removal of the scaffolding, benching,
ladders, templates and tools required for the proper erection and completion of the work. The rate
includes the cost of purloins, rafters and trusses. The rate shall be for a unit of one sq. Meter
Item No. 9: Excavation for foundation up to 1.5m depth including sorting out and
stacking of useful materials and disposing excavated stuff up to 500 mt. lead. (A)
Loose or soft soil.
1.1 Any soil which generally yields to the application of pickaxes and shovels, phawaras,
rakes or any such ordinary excavating implement or organic soil, gravel, silt, sand turf loam,
clay, peat etc. Fall under this category.
2.0 Clearing the site:
2.1 The site on which the structure is to be built shall be cleared and all obstructions, loose
stone, materials and rubbish of all kind, bush, wood and trees shall be removed as directed.
The materials so obtained shall be properly of the Government and be conveyed and stacked
as directed within 50 M. Lead. The roots of the trees coming in the sides shall be cut and
Coated with a hot asphalt.
2.2 The rate of site clearance is deemed to be included in the rate of earth work for which no
extra will be paid.
3.0 Setting out :
After clearing the site, the centerlines will be given by the Engineer-in-charge. The
contractor shall assume full responsibility for alignment Elevation and dimension of each
and all parts of the work. Contractor shall supply laborers, materials, etc. Required for
setting out the Reference marks and bench marks and shall maintain them as long as
required and directed.
4.0 Excavation:
The excavation in foundation shall be carried out in true line and level and shall have the
width and depth as shown in the drawings or as directed. The contractor shall do the
necessary shoring and shutting or providing necessary slopes to a safe angle, at his own cost.
The payment for such precautionary measures shall be paid separately if not specified. The
bottom of the excavated area shall be leveled both longitudinally and transversely as
directed by removing and watering as required. No earth filling will be allowed for bringing
it to level, if by mistake or any other reason excavation is made deeper or wider that shown
on the plan or directed. The extra depth or width shall be made up with concrete of same
proportion as specified for the foundation concrete at the cost of the contractor. The
excavation up to 1.5m Depth shall be measured under this item.
5.0 Disposal of the excavated stuff:
5.1 The excavated stuff of the selected type shall be used in filling the trenches and plinth or
leveling the ground in layers including ramming and watering etc. The balance of the
excavated quantity shall be removed by the contractor from the site of work to a place as
EW- 257 PUR-F-006 RFQ-74075
directed with lead up to 500 M and all lift.
Mode of measurement and payment:
The measurement of excavation in trenches for foundation shall be made according to the
sections of trenches shown on the drawing or as per sections given by the Engineer-in-
charge. No payment shall be made for surplus excavation made in excess of above
requirements or due to slopping back as found necessary on account of conditions of soil
and requirements of safety.
The rate shall be for a unit of one cubic meter.
Item NO.10: Excavation for foundation upto 1.5 m depth including sorting out and
stacking of useful materials and disposing off the excavated stuff upto 50 Meter
lead.(A) Loose or soft soil (B) Manual Labour
The detailed item specification is the same as per item no. 9, except that the excavation shall
be carried out manually.
The rate shall be for a unit of one cubic meter.
Item NO.11: Providing and laying cement concrete 1:3:6 (1 cement: 3 coarse sand:
hand broken stone aggregates 40mm nominal size ) & curing complete excluding cost
of form work in (A) foundation & plinth.
1.1 Water shall conform to M-1. Cement shall conform to M-3. Sand shall conform to M-6.
Stone aggregate 40 mm. Nominal size shall conform to M-12.
2.1 General: before starting concrete bed of foundation trenches shall be cleared of all loose
materials, leveled, watered and rammed as directed.
2.2 Proportion of Mix: The Proportion of cement, sand and coarse aggregate shall be 1 part
of cement, 4 parts of sand, 8 parts of stone aggregates and shall so measured by volume.
2.3 Mixing: The concrete shall be mixed in a mechanical mixer at the site of work. Hand
mixing may however be allowed for smaller quantity of work if approved by the Engineer-in-
charge. When hand mixing is permitted by the Engineer-in-charge in case of break-down of
machineries and in the interest of the work, it shall be carried out on a water tight platform
and care shall be taken to ensure that mixing is continued until the mass in uniform in color
and consistency. However in such cases 10% more cement than otherwise required shall
have to be used without any extra cost. The mixing in mechanical mixer shall be done for a
period 1 to 2 minutes. The quantity of water shall be sufficient to produce a dense concrete
of required workability for the purpose.
2.4 Transporting & placing the concrete:
2.4.1 The concrete shall be handled from the place of mixing to the final position in not
more than 15 minutes by the method as Directed and shall be placed into its final position,
compacted and finished within 30 minutes of mixing with water i.e. before the setting
commences. The concrete shall be laid in layers of 15 cms. to 20 cms.
2.5 Compacting:
2.5.1 The concrete shall be rammed with heavy iron rammers and rapidly to get the required
compaction and to allow all the interstices to be filled with mortar.
2.6 Curing: 2.6.1 after the final set, the concrete shall be kept continuously wet, if
required by pounding for a period of not less than 7 days from the date of placement.
2.7 Mode of measurement and payment:
The concrete shall be measured for its length, breadth and depth, limiting dimensions to
those specified on plans or directed.
The rate shall be for a unit of one cubic meter.
EW- 257 PUR-F-006 RFQ-74075
Item NO.12: Providing and laying cement concrete work 1:2:4 (1- Cement : 2- Coarse
sand : 4- graded stone aggregates 20 mm nominal size) and curing complete excluding
cost of formwork and reinforcement for reinforced concrete work in (A) Foundations,
footings, Base or columns and Mass concrete
1.0 Materials: Water shall conform to M-1. Cement shall conform to M-3. Sand shall
conform to M-6. Graded stone aggregate 20 mm. Nominal size shall conform to M-12.
2.2 The concrete mix is not required to be designed by preliminary tests. The proportion of
the concrete mix shall be 1 : 2 : 4 (1 cement : 2 coarse sand : 4 graded stone aggregate
mm. Nominal size) by volume. Concrete work shall have exposed concrete surface or as
specified in the item.
2.3 The designation ordinary M-100, M-150, M-200, M-250 specified as per I. S.
Corresponding approximately to 1 : 3 : 6, 1 : 2 : 4, 1 ½ : 3 and 1 : 1 : 2 nominal mix of
ordinary concrete by volume respectively.
2.4 The ingredients required for ordinary concrete containing one beg of cement of 50 Kg.
By weight (0.0342 Cu. M.) For different proportions of mix shall be as under :
Grade of concrete Total quantity of Proportion of fine Quantity of water per
dry aggregate by aggregate to coarse 50 Kgs. Of cement
volume per 50 kgs. aggregate maximum
Of cement to be
taken as the sum of
individual of fine
1 aggregates, 3
M-100 (1 : 3 : 6) 300 Liters Generally 1 : 2 for 34 liters
fine aggregate to
coarse aggregate
upper limit of 1:1
1/2 and lower limit
The water cement ratio shall not more than those specified in the above table. The cement
content of the mix specified in the Table shall be increased if the quantity of water in a mix
has to be increased to overcome the difficulties of placement and compaction so that the
water-cement-ratio specified in the Table is not exceeded.
2.5 Workability of the concrete shall be controlled by maintaining a water-cement-ratio
that is bound to give a concrete mix which is just sufficiently wet to be placed and compacted
without difficulty with the means available.
2.6 The maximum size of coarse aggregate shall be as large as possible within the limits
specified but in no case greater than one fourth of the minimum thickness of the member,
provided that the concrete can be placed without difficulty so as to surround all
reinforcement thoroughly and to fill the corners of the form.
2.7 For reinforced concrete work, coarse aggregates having a nominal size of 20 mm. Are
generally considered satisfactory.
EW- 257 PUR-F-006 RFQ-74075
2.8 For heavily reinforced concrete members as in the case of ribs of main beams, the
nominal maximum size of coarse aggregate should usually be restricted to 5 mm. Less than
the minimum clear distance between the main bars, or 5 mm. Less than the minimum cover
to the reinforcement whichever is smaller.
Where the reinforcement is widely spaced as in solid slabs, limitations of size of the
aggregate may not be important and the nominal maximum size may sometimes be as great
as or greater than the minimum cover.
2.9 Admixture may be used in concrete only with approval of Engineer-in-charge upon
the evidence that with the passage of time, neither the compressive strength of concrete is
reduced nor are other requisite qualities of concrete and steel impaired by the use of such
3.0 Workmanship:
3.1 Proportioning: proportioning shall be done by volume, except cement which shall be
measured in terms of bags of 50 Kg. Weight. The volume of one such bag being taken as
0.0342 Cu. Meter Boxes of suitable sizes shall be used for measuring sand aggregate. The size
of the boxes (internal) shall be 35 cms. X 25 cms. and 40 cms. Deep. While measuring the
aggregate and sand, the box shall be filled without shaking ramming or hammering. The
proportioning of sand shall be on the basis of its dry volume and in case of damp sand,
allowances for bulk age shall be made.
3.2.1 For all work. Concrete shall be mixed in a mechanical mixer which along with other
accessories shall be kept in first class working condition and so maintained throughout the
construction. Measured quantity of aggregate, sand, cement required for each batch shall be
poured into the drum of the mechanical mixer while it is continuously running. After about
half a minute of dry mixing, measured quantity of water required for each batch of concrete
mix shall be added gradually and mixing continued for another one and a half minute. Mixing
shall be continued till materials are uniformly distributed and uniform color of the entire
mass is obtained and each individual particle of the coarse aggregate shows complete
coating of mortar containing its proportionate amount of cement. In no case shall the mixing
be done for less than 2 minutes after all ingredients have been put into the mixer.
3.2.2 When hand mixing is permitted by the Engineer-in-charge for small jobs or for certain
other reasons, it shall be done on the smooth watertight platform large enough to allow
efficient turning over the ingredients of concrete before and after adding water. Mixing
platform shall be so arranged that no foreign materials gets mixed with concrete nor does
the mixing water flow out. Cement in required number of bags shall be placed in a uniform
layer on top of the measured quantity of fine and coarse aggregate, which shall also be
spread in a layer of uniform thickness on the mixing platform. Dru coarse and fine aggregate
and cement shall then be mixed thoroughly by turning over to get a mixture to uniform
color. Specified quantity of water shall then be added gradually through a rose-can and the
mass turned over till a mix of required consistency is obtained. In hand mixing, quantity of
cement shall be increased by 10 percent above that specified.
3.2.3 Mixers which have been out of use for more than 30 minutes shall be thoroughly
cleaned before putting in a new batch. Unless otherwise agreed to by the Engineer-in-charge
the first batch of concrete from the mixture shall contain only two thirds of normal quantity
of coarse aggregate. Mixing plant shall be thoroughly cleaned before changing from one type
of cement to another.
3.3 Consistency: 3.3.1 The degree of consistency which shall depend upon the nature of
the work and methods of vibration of concrete, shall be determined by regular slumps tests
in accordance with I. S. 1199-1959. The slumps of 10 mm. To 25 mm. Shall be adopted when
vibrators are used and 80 mm. When vibrators are not used.
3.4 Inspection :
3.4.1 Contractor shall give the Engineer-in-charge due notice before placing any concrete in
the forms to permit him to inspect and accept the false work and forms as to their strength,
alignment, and general fitness but such inspection shall not relive the contractor of his
EW- 257 PUR-F-006 RFQ-74075
responsibility for the safety of men, machinery, materials and for results obtained.
Immediately before concreting, all forms shall be thoroughly cleaned.
3.4.2 Centering design and its erection shall be got approved from the Engineer-in-charge.
One carpenter with helper shall invariably be kept present throughout the period of
concreting. Movement of labor and other persons shall be totally prohibited for
reinforcement laid in position. For access to different parts, suitable mobile platforms shall
be provided so that steel reinforcement in position is not disturbed for ensuring proper
cover, mortar blocks of suitable size shall be cast and tied to the reinforcement. Timber,
kapachi or metal pieces shall not be used for this purpose.
3.5 Transporting and laying:
3.5.1 The method of transporting and placing concrete shall be as approved. Concrete shall
be so transported and placed that no contamination, segregation or loss of its constituent
material takes place.
All formwork shall be cleaned and made free from standing water, dust show or ice
immediately before placing of concrete.
No concrete shall be placed in any part of the structure until the approval of the
Engineer-in-charge has been obtained.
3.5.2 Concerting shall proceed continuously over the area between construction joints.
Fresh concrete shall not be placed against concrete which has been in position for more than
30 minutes unless a proper construction joints is formed. Concrete shall be compacted in its
final position within 30 minutes of its discharge from the mixer. Except where otherwise
agreed to by the Engineer-in-charge concrete shall be deposited shall be deposited in
horizontal layers to a compacted depth of not more than 0.45 meter when internal vibrators
are used and not exceeding 0.30 meter in all other cases.
3.5.3 Unless otherwise agreed to by the Engineer-in-charge, concrete shall not be dropped
into place from a height exceeding 2 meters. When trucking or chutes are used they shall be
kept close and used in such a way as to avoid segregation. When concreting has to be
resumed on a surface which has hardened, it shall be roughened, swept clean, thoroughly
wetted and covered with a 13 mm. Thick layer of mortar composed of cement and sand in
the same ratio as in the concrete mix itself. This 13 mm. Layer of mortar shall be freshly
mixed and placed immediately before placing of new concrete. Where concrete has not fully
hardened, all laitance shall be removed by scrubbing the wet surface with wire or bristle
brushes, care being taken to avoid dislodgement of any particles of coarse aggregate. The
surface shall then be thoroughly wetted all free water removed and then coated with neat
cement grout. The first layer of concrete to be placed on his surface shall not exceed
mm. In thickness and shall be well rammed against old work, particular attention being
given to corners and close spots.
3.5.4 All concrete shall be compacted to produce a dense homogeneous mass with the
assistance of vibrators, unless otherwise permitted by the Engineer-in-charge for
exceptional cases, such as concreting under water, where vibrators cannot be used.
Sufficient vibrators in serviceable condition shall be kept at site so that spare equipment is
always available in the event of breakdowns.
Concrete shall be judged to be compacted when the mortar fills the spaces between the
coarse aggregate and begins to cream up to form an even surface. Compaction shall be
completed before the initial setting starts i.e. Within 30 minutes of addition of water to dry
mixture. During compaction, it shall be observed that needle vibrators are not applied on
reinforcement which is likely to destroy the bond between concrete and reinforcement.
3.6 Curing: Immediately after compaction, concrete shall be protected from weather,
including rain, running water, shocks, vibration, traffic, rapid temperature changes, frost and
drying out process. It shall be covered with wet sacking, hassain or other similar absorbant
material approved soon after the initial set and shall be kept continuously wet for a period of
not less than 14 days from the date of placement. Masonry work over foundation concrete
may be started after 48 hours of its laying but curing of concrete shall be continued for a
minimum period of 14 days.
EW- 257 PUR-F-006 RFQ-74075
3.7 Sampling and Testing of concrete:
3.7.1 Samples from fresh concrete shall be taken as per I. S. 1199-1959 and cubes shall be
made,cured and tested at 7 days or 28 days as per requirements in accordance with I. S. 516-
1959. A random sampling procedure shall be adopted to ensure that each concrete batch
shall have a reasonable chance of being tested i.e. The sampling should be spread over the
entire period of concreting and cover all mixing units. The minimum frequency of sampling
of concrete of each grade shall be in accordance with following :
Quantity of No. Of samples Quantity of No. Of samples
concrete in the concrete in the
51 and above + one additional for each additional 50 M. Or part thereof.
NOTE : At least one sample shall be taken from each shift. Ten test specimens shall be
made from each sample, five for testing at 7 days and the remaining five at 28 days. The
samples of concrete shall be taken on each day of the concreting as per above frequency. The
number of specimens may be suitably increased as deemed necessary by the Engineer-in-
charge when procedure of tests given above revels a poor quality of concrete and in other
3.7.2 The average strength of the group of cubes case for each day shall not be less than the
specified cube strength of 150 kg/Cm2 at 28 days. 20% of the cubes cast for each day may
have value less than the specified strength provided the lowest value is not less than 85% of
the specified strength. If the concrete made in accordance with the proportions given for a
particular grade, does not yield the specified strength, such concrete shall be classified as
belonging to the appropriate lower grade. Concrete made in accordance with the
proportions given for a particular grade shall not however, be placed in a higher grade on
the ground that the test strength are higher than the minimum specified.
3.8 Stripping :
3.8.1 The Engineer-in-charge shall be informed in advanced by the contractor of his
intention to strike the form work. While fixing the time for removal of form work due
consideration shall be given to local conditions, character of the structure the weather and
other condition that influence the setting of concrete and of the materials used in the mix in
normal circumstances (generally where temperatures are above 20ºc) and where ordinary
concrete is used forms may be struck after expiry of periods specified in item No. 9.1 (A) for
respective item of form work.
3.8.2 All formwork shall be removed without causing any shock or vibration as would
damage the concrete. Before the soffits and struts are removed the concrete surface shall be
exposed where necessary in order to ascertain that the concrete has sufficiently hardened.
Centering shall be gradually and uniformly lowered in such manner as to permit the
concrete to take stresses due to its own weight uniformly and gradually. Where internal
metal ties are permitted they or their removable parts shall be extracted without causing
any damage to the concrete and remaining holes filled with mortar. No permanently
embedded metal part shall have less than 25 mm. Cover to the finished concrete surface.
Where it is intended to re-use the formwork, it shall be cleaned and made good to the
satisfaction of the Engineer-in-charge. After removable of form work and shuttering the
Executive Engineer shall inspect the work and satisfy by random checks that concrete
produced is of good quality.
3.8.3 Immediately after the removal of forms all exposed bolts etc., passing through the
cement concrete member and use for shuttering or any other purpose shall be cut inside the
cement concrete members to a depth of at least 25 mm. Below the surface of the concrete
and the resulting holes be filled by cement mortar. All fine caused by form joints, all cavities
produced by the removal of forms ties and all other holes and depressions honeycomb spots
broken edges or corners and other defects shall be thoroughly cleaned, saturated with water
EW- 257 PUR-F-006 RFQ-74075
and carefully pointed and rendered true with mortar of cement and fine aggregate mixed in
the proportion used in the grade of concrete that is being finished and of as dry consistency
as is possible to use. Considerable pressure shall be applied in filling and pointing to ensure
through filling in all voids. Surfaces which are pointed shall be kept moist for a period of
If rock pockets honeycombs in the opinion of the Engineer-in-charge are of such an extent or
character as to affect the strength of the structure materially or to endanger the life of the
steel reinforcement he may declare the concrete defective and require the removal and
replacement of the portions of the structure affected.
4.0 Mode of measurement and payment:
4.1 The consolidated cubical contents of concrete work as specified in item shall be
measured the concrete laid in excess of section shown on drawings or as directed shall not
be measured. No deduction shall be made for
(a) Ends of dis-similar materials such as joints, beams, posts, girders, rafters, purling
trusses, corbels and steps etc. Up to 500 Sq. Cm. In section.
(b) Opening up to 0.1 Sq. M.
4.2 The rate includes cost of all materials, labor, tools and plant required for mixing, placing
in position, vibrating and compacting, finishing as directed curing and all other incidental
expenses for producing concrete of specified strength. The rate excludes the cost of form
4.3 The rate shall be for a unit of one cubic meter
Providing and laying cement concrete work 1:2:4 (1- Cement : 2- Coarse sand : 4-
graded stone aggregates 20 mm nominal size) and curing complete excluding cost of
formwork and reinforcement for reinforced concrete work in (B) Slabs, landing,
shelves, Balconis , Lintels, Beams, Girders and Cantilever upto floor two level.
All the relevant specifications for item no. 12 shall be followed.
The rate shall be for a unit of one cubic meter
Providing and laying cement concrete flooring 1:2:4 (1- cement : 2-coarse sand : 4-
graded stone aggregate 20mm nominal size) laid in one layer and finished with a
floating coat of neat cement. (B) 50mm thick.
1.0 Materials :
Water shall conform to M-1 cement shall conform to M-3. Sand shall conform to M-6. Stone
aggregate 20 mm. Normal size shall conform to M-12.Cement concrete 1 : 2 : 4 proportion
measured by volume shall conform to relevant specification or ordinary grade 1 : 2 :
2.0 Workmanship :
2.1 The relevant concrete flooring of 50 mm thick (Average) is to be laid as per the site
condition. The concrete shall be mixed in a mechanical mixer at the work. Hand mixed may
however be allowed for smaller quantities of work and in case of failure of machines or as
permitted by the Engineer-in-charge. It shall carried out on a water platform and care shall
be taken to ensure that mixing is continued until the mass is uniform in color and
consistency. However, in such cases 10 % more cement than otherwise required shall have
to be used without any extra cost. The quantity of water shall be just sufficient of produce a
dense concrete of required workability for the purpose. Flooring of specified thickness shall
be laid in accordance with approved pattern or as directed. Finishing operation shall start
shortly after the cessation of beating and shall be spread over a period one to six hours
depending upon the temperature and atmosphere conditions. The surface shall be left for
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
GTPS_Tender _ EW-257_08_11_2025.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .