Tender Value
₹2.0 Cr
EMD Value
₹2.5 L
Closing Date
18 Dec 2025, 3:00 pmClosed
Transportation of P Way materials by road from different places for track renewal works in Adra Division of S.E.Railway for two years.
E-DRM-Engg-ADRA-99-25~SER
E-DRM-Engg-ADRA-99-25
Open
Works - General
24 Months
Purulia, West Bengal
₹0
₹2.5 L
18 Dec 2025
24 Nov 2025
4 Dec 2025
A-Execution of work pertaining to loading and unloading of rail,
B-Execution of works pertaining to loading and unloading of
C-Execution of works pertaining to leading and transportation of
D-Execution of works pertaining to leading and transportation of
Execution of work pertaining to loading and unloading of rail, SEJ and Glued Joint etc.and all other
items of under IR Unified Standard Schedule of Rates - 2021 except item No.172014, 172024,
S No. Item Description of Item Unit Qty Rate Amount
Loading of rails of any section and length up to
13 metres in Wagons / Truck / trailer including
lead up to 50 metres and lift up to 5 metres.
possible and traffic block is not required or in
Loading of tongue rail, stock rail, switch
assembly and crossings of any section and
length, SEJ, Glued joint etc. with / without P.Way
fittings and fastenings, in Wagon / Truck / trailer
including lead up to 250 metre and lift up to 5
possible and traffic block is not required or in
Unloading of rails of any section and length up
to 13 metre, in neat manner for Railway usage
from departmental material train (DMT) or
contractor's / Railway's Truck/trailer including
lead up to 50 metre, lift up to 5 metre and
stacking in prescribed manner.
3 171053 From Wagon where mechanical handling is MT 670.00 88.97 59609.90
possible and traffic block is not required or in
Truck / trailer.
Unloading of Switches / Crossings / SEJ Rails /
Glued Joints of any rail section and length with
or without P.Way fittings & fastenings in neat
manner for Railway usage from departmental
material train (DMT) or contractor's / Railway's
Truck/Trailer with lead up to 250 metre & lift up
Schedule B-Execution of works pertaining to loading and unloading of sleeper vide item No.
172014, 172024, 172063 and 172073 under IR Unified Standard Schedule of Rates - 2021
Execution of works pertaining to loading and unloading of sleeper vide item No. 172014, 172024,
172063 and 172073 under IR Unified Standard Schedule of Rates - 2021
ADRA DIVISION-ENGG/SOUTH EASTERN RLY
S No. Item Description of Item Unit Qty Rate Amount
Loading of 52kg / 60kg PSC normal line and
special sleepers up to 2.75 metre length in
Depot / Station / Mid-section between stations in
a neat manner to departmental material train
(DMT) or contractor's / Railway's Truck/Trailer
with crane or any other means including
crossing of one track with free lead up to 250
metre and lift up to 5 metre, if required with
contractor's labour, tools & plants, machinery,
consumables etc. Note: In case of any damage
to sleeper during loading, penalty @ 50% of the
all inclusive cost of sleeper shall be levied.
1 172014 I n Wagon where mechanical handling is MT 22110.00 92.36 2042079.60
possible and traffic block is not required or in
Truck / trailer
Loading of 52kg / 60kg PSC line and special
sleepers beyond 2.75 metre length including
existing fittings and fastenings in Depot /
Station / Mid-section between stations in a neat
manner to departmental material train (DMT) or
contractor's / Railway's Truck/trailer with crane
or any other means including crossing of one
track with free lead up to 250 metre and lift up
to 5 metre, if required with contractor's labour,
tools & plants, machinery, consumables etc.
Note: In case of any damage to sleeper during
loading, penalty @ 50% of the all inclusive cost
of sleeper shall be levied.
2 172024 I n Wagon/Truck / trailer where mechanical MT 2680.00 118.45 317446.00
handling is possible a n d traffic block is not
Unloading of 52kg / 60kg PSC line and special
sleepers up to 2.75 metre length in Depot /
Station / Mid-section between stations in neat
manner for Railway usage from departmental
material train (DMT) or contractor's / Railway's
Truck/Trailer with crane or any other means
including crossing of one track and lead up to
250 metre & lift up to 5 metre with contractor's
labour, tools & plants, machinery, consumables
etc . Note: In case of any damage to sleeper
during loading, penalty @ 50% of the all
inclusive cost of sleeper shall be levied.
Unloading of 52kg / 60kg PSC special sleepers
beyond 2.75 metre length in Depot / Station /
Mid-section between stations in neat manner
for Railway usage from departmental material
train (DMT) or contractor's / Railway's
Truck/Trailer with crane or any other means
including crossing of one track and lead up to
50 metre & lift up to 5 metre with contractor's
labour, tools & plants, machinery, consumables
etc. Note: In case of any damage to sleeper
during loading, penalty @ 50% of the all
inclusive cost of sleeper shall be levied.
Schedule C-Execution of works pertaining to leading and transportation of all P Way material upto
IR Unified Standard Schedule of Rates - 2021
Execution of works pertaining to leading and transportation of all P Way material upto 150km vide
Standard Schedule of Rates - 2021
S No. Item Description of Item Unit Qty Rate Amount
ADRA DIVISION-ENGG/SOUTH EASTERN RLY
Loading, leading and unloading of all types of
P.Way fittings and all other miscellaneous
m a t e r i a l except Rails, sleepers, switches,
crossings, SEJs and Glued Joints by road
vehicles for different leads. Note: Lead shall be
the shortest motorable road length between the
points of loading and unloading.
Transportation of Rails, sleepers, switches,
crossings, SEJs and Glued Joints by road
vehicles for different leads. Note: 1 . Lead shall
be the shortest motorable road length between
the points of loading and unloading. 2. Loading
and unloading shall be paid extra under
relevant items.
Schedule D-Execution of works pertaining to leading and transportation of all P Way materials
Schedule beyond 150km vide item No. 172048 and 172058 under IR Unified Standard Schedule of Rates -
Execution of works pertaining to leading and transportation of all P Way materials beyond 150km
vide item No. 172048 and 172058 under IR Unified Standard Schedule of Rates - 2021
S No. Item Description of Item Unit Qty Rate Amount
Loading, leading and unloading of all types of
P.Way fittings and all other miscellaneous
m a t e r i a l except Rails, sleepers, switches,
crossings, SEJs and Glued Joints by road
vehicles for different leads. Note: Lead shall be
the shortest motorable road length between the
points of loading and unloading.
1 172048 Extra for every Km per MT beyond 150 Km over MT-Km 53600.00 3.30 176880.00
item no. 172047
Transportation of Rails, sleepers, switches,
crossings, SEJs and Glued Joints by road
vehicles for different leads. Note: 1 . Lead shall
be the shortest motorable road length between
the points of loading and unloading. 2. Loading
and unloading shall be paid extra under
relevant items.
2 172058 Extra for every Km per MT beyond 150 Km over MT-Km 871000.00 3.30 2874300.00
item no. 172057
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
Bidsecruitydocument.pdf
ATTACHMENT
Letterofcreditboardletter.pdf
ATTACHMENT
Updationlabourdatashramikkalyan.pdf
ATTACHMENT
JPOcabledamage.pdf
ATTACHMENT
GCC_April-2022.pdf
ATTACHMENT
ANNEXUREVIAforBIDSECURITY.pdf
ATTACHMENT
GCCACS-1.pdf
ATTACHMENT
ACS2GCC-2022.pdf
ATTACHMENT
ACS-03OFGCC2022.pdf
ATTACHMENT
2023_10_20RBCE_CE-I-CTIndianRailwaysStandardGeneralConditionsofContractApril-2022AdvanceCorrectionSlipNo_5ACS-53.pdf
ATTACHMENT
CorrectionSlipNo_6ACS-61.pdf
ATTACHMENT
correctionslip07.pdf
ATTACHMENT
CorrectionSlip08.pdf
ATTACHMENT
correctionslip-09.pdf
ATTACHMENT
Correctionslip10.pdf
ATTACHMENT
annexureVIBwithUDIN1.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .