Tender Value
₹10 L
EMD Value
₹20,000
Closing Date
18 Jul 2026, 6:00 pmDue today
EO Nagar Palika, Sangod
EO Nagar Palika, Sangod
Construction work of Community Building near Harizan Basi, Kundanpur Road in Sangod City.
2026_DLB_574008_1
No. 1983
Open Tender
Civil Works
Percentage
180 days
Kota
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,000
EO Nagar Palika, Sangod
₹20,000
Yes
9 Jul 2026
9 Jul 2026
20 Jul 2026
9 Jul 2026
18 Jul 2026
9 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. upto two stories excluding cost of centering, shuttering, finishing and reinforcement : including Providing /mixing of synthetic fibers compulsorily complying with IS 16481:2022 of 06 mm/12 mm length to be mixed @ 0.25% by weight of Cement i.e. 125 gms per 50 kg Cement up to 900 gms per cum of Concrete/ mortar. 1:1½:3 (1 cement : 1½ coarse sand : 3 graded stone aggregate 20 mm nominal size) | 21.65 | Cum | 7,380 | ₹1,59,777 |
| 2 | Centering and shuttering with plywood or steel sheet upto two stories (each story of height upto 3.5 metre from floor level) including strutting, propping etc. and removal of form for : Suspended floors, roofs, landings, balconies and access platform | 93.08 | Sqm | 456 | ₹42,444.48 |
| 3 | Lintels, beams, plinth beams, girders, bressumers and cantilevers. | 50.7 | Sqm | 426 | ₹21,598.2 |
| 4 | Columns, Pillars, Piers, Abutments, Posts and Struts | 31.19 | Sqm | 375 | ₹11,696.25 |
| 5 | Reinforcement for R.C.C. work at all levels including straightening, cutting, bending, placing in position and binding all complete. Thermo-Mechanically Treated bars. | 2,300 | Kg | 83.3 | ₹1,91,590 |
| 6 | Random rubble dry stone Kharanja (soling) under floor. | 13.1 | Cum | 2,270 | ₹29,737 |
| 7 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work upto plinth level : 1:3:6 (1 Cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size). | 6.41 | Cum | 5,000 | ₹32,050 |
| 8 | Kota stone slab flooring 25mm thick over 20 mm (average) thick base laid over and jointed with grey cement slurry mixed with pigment to match the shade of the slab including rubbing and polishing complete with base of cement mortar 1 : 4 (1 cement : 4 coarse sand) : Area of each slab 900 to 2000 sqcm | 66.75 | Sqm | 1,365 | ₹91,113.75 |
| 9 | Brick masonry work with First class FPS bricks (min. 10.5 Mpa) in cement mortar with mechanical mixer in substructure/ super structure at all levels complete as per clause 1300 and 2200 of MoRT&H specification including all material, labour, scaffolding etc but excluding pointing and plastering. In cement mortar 1:4 (1 cement : 4 coarse sand) | 24.49 | Cum | 6,060 | ₹1,48,409.4 |
| 10 | Cement plastering including T&P, scaffolding, material and complete labour, including cost of water, curing, racking of joints etc. with 20 mm cement plaster of mix : including Providing /mixing of synthetic fibers compulsorily complying with IS 16481:2022 of 06 mm/12 mm length to be mixed @ 0.25% by weight of Cement i.e. 125 gms per 50 kg Cement up to 900 gms per cum of Concrete/ mortar. 1:6 (1 cement : 6 fine/ coarse sand) | 398.25 | Sqm | 294.5 | ₹1,17,284.63 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.70 MB
BOQ_1021055.xls
BOQ • 0.25 MB
Download all tender documents and submit your bid