Loading…
Loading…
Tender Value
₹3.3 Cr
EMD Value
₹3.3 L
Closing Date
5 Aug 2026, 6:00 pmClosed
PRAVINBHAI HADIYAL
Renovation work of Narol Crematorium in Lambha Ward of South Zone
328873
tender notice no.03/2026-27, tender no.195
Open
Civil - All
Works
Ahmedabad
₹6,000
MUNICIPAL COMMISSIONER, AHMEDABAD
₹3.3 L
29 Jul 2026
29 Jul 2026
29 Jul 2026
5 Aug 2026
29 Jul 2026
9. Definite particulars covered in the items of work, through not mentioned or elucidated in it,
specifications shall be deemed to be included there in.
10. Reference to specifications of materials as made in the detailed specification of the items of
work is in the form of a designation containing the number of the specification of the material
and prefix 'M' e.g. 'M-5'.
11. Approval to the samples of various materials given by the Engineer-in-charge shall not
absolve the contractor from the responsibility of replacing defective material brought on site
or materials used in the work found defective at a later date.
12. The contract rate of the item of work shall be for the work completed in all respects.
13. No collection of materials shall be made before it is got approved from the Engineer-in-
14. Collection of approved materials shall be done at site of work in a systematic manner.
Materials shall be done at site of work in a systematic manner. Materials shall be stored in
such a manner as to prevent damage, deterioration or intrusion of foreign matter and to-
ensure the preservation of their quality and fitness for the work.
15. Materials, if and when rejected by the Engineer-in-charge, shall be immediately removed from
the site of work.
16. NO materials shall be stored prior to, during and after execution shall be kept in sufficient
numbers and in good working condition on the site of the work.
17. All works shall be carried out in a workmanlike manners per the best techniques for the
particular item.
18. All tools, templates, machinery and equipment for correct execution of the work as well as for
checking lines, levels, alignment of the works during execution shall be kept in sufficient
numbers and in good working condition on the site of the work.
19. The mode, procedure and manner of execution shall be such that it does not cause damage or
over loading of the various components of the structure during execution or after completion
of the structure.
20. Special modes of construction not adopted in general Engineering practice, if proposed to be
adopted by the Contractor, shall be considered only if the contractor provides satisfactory
evidence that such special mode of construction is safe, sound and helps in speedy
construction and completion of work to the required strength and quality. Acceptance of the
same by the Engineer-in-Charge shall not, however, absolve the contractor of the
responsibility of any adverse effects and consequences of adopting the same in the course of
execution of completion of the work.
21. All installations pertaining to water supply and fixtures thereof as well as drainage lines and
sanitary fittings shall be deemed to be completed only after giving satisfactory tests by the
22. The contractor shall be responsible for observing the rules and regulations imposed under
"Minor Minerals Act", and such other laws and rules prescribed by Government from time to
23. All necessary safety measures and precaution (including those laid down in the various
relevant Indian Standards) shall be taken to ensure the safety of men, materials and machinery
on the works as also of the work itself.
24. The testing charges of all materials shall be borne by the Contractor unless recovery at one
percent towards testing charges is separately made.
25. Approval to any of the executed items for the work does not in any way relieve the contractor
of his responsibility for the correctness, soundness and strength of the structure as per the
drawings and specification.
SPECIFICATIONS OF MATERIALS
1.1. Water shall not be salty or brackish and shall be clean, reasonably clear and free objectionable
quantities of silt and traces of oil and injurious alkalis, salts, organic matter and other
deleterious material which will either weaken the mortar or concrete or cause efflorescence or
attack the steel in R.C.C Container for transport, storage and handling of water shall be clean.
Water shall conform to the standards specified in I.S.456-1978.
1.2. If required by the Engineer-in-charge it shall be tested by comparison with distilled water.
Comparison shall be made by means of standard cement tests for soundness, time of setting
and mortar strength as specified in I.S.269-1976. Any indication of unsoundness, change in
time of setting by 30 minutes or more or decrease of more than 10 per cent in strength of
mortar prepared with water sample when compared with the results obtained with mortar
prepared with distilled water shall be sufficient cause for rejection of water under test.
1.3. Water for curing mortar, concrete or masonry should not be too acidic or too alkaline. It shall
be free of elements which significantly affect the hydration reaction or otherwise interfere
with the hardening of concrete during curing or those which produce objectionable stains or
other unsightly deposits on concrete or mortar surfaces.
1.4. Hard and bitter water shall not be used for curing.
1.5. Portable water will be generally found suitable for curing mortar or concrete.
2.1. Lime shall be hydraulic lime as per I.S. 712-1973. Necessary test shall be carried out as per
I.S. 6932 (Parts I to X),
2.2. The following field tests for limes are to be carried out:
(1) A very rough idea can be formed about the type of lime by its visual examination i.e. fat lime
bears pure white colour, lime in form of porous lumps of dirty while colour indicates quick
lime, and solid lumps are the unburnt lime stone.
(2) Acid tests for determining the carbonate content in lime, Excessive amount of impurities and
rough determination of class of lime.
2.3. Storage shall comply with I.S. 712-1973. The slaked lime, if stored, shall be kept in a weather
proof and damp-proof shed with impervious floor and sides to protect it against rain, moisture,
weather and extraneous materials mixing with it. All lime that has been damaged in any way
shall be rejected and all rejected materials shall be removed from site of work.
2.4. Field testing shall be done according to I.S. 1624-1974 to show the acceptability of materials.
3.1 Cement shall be ordinary Portland slag cement as per I.S. 269-1976 or Portland slag cement as
M-4. White Cement :
4.1 The white cement shall conform to I.S. 80412-E
M-5. Coloured Cement:
5.1 Coloured cement shall be with white or gray Portland cement as specified in the item of the
5.2 The pigments used for coloured cement shall be of approved quality and shall not exceed 10%
of cement used in the Mix. The mixture of pigment shall be properly grounded to have a
uniform colour and shade. The pigments shall have such properties to provide for durability
under exposure to sunlight and weather.
5.3 The pigment shall have the property such that it is neither by the cement nor detrimental to it.
6.1. Sand shall be natural sand, clean, well graded, hard strong durable and gritty particle free from
injurious amounts of dust clay, kankar nodules, soft or flaky particles shale, alkali, salts
organic matter, loam, mica or another deleterious substance and shall be got approved from
the Engineer-in-charge. The sand shall not contain more than 8 percent of silt as determined
by field test. If necessary the sand shall be washed to make it clean.
6.2. Coarse Sand : The fineness modulus of coarse sand shall not be less than 2.5 and shall not
The sieve analysis of coarse shall be as under:
I.S.Sieve Percentage by I.S.Sieve Percentage by
Designation Passing Sieve Designation Passing Sieve
6.3 Fine Sand:The fineness modulus shall not exceed 1.0. The sieve analysis of fine sand shall be
I.S.Sieve Percentage by I.S.Sieve Percentage by
Designation Passing Sieve Designation Passing Sieve
M-7. Stone Dust :
7.1. This shall be obtained from crushing hard black trap or equivalent. It shall not contain more
than 8% of silt as determined by field test with measuring cylinder. The method of
determining silt contents by field test is given as under :
7.2. A sample of stone dust to be tested shall be placed without drying in 200 mm. measuring
cylinder. The quantity of the sample shall be such that it fills the cylinder upto100 mm. mark.
The clean water shall be added upto 150 mm. mark. The mixture shall be stiffed vigorously
and the content allowed to settle for 3 hours.
7.3. The height of silt visible as settled layer above the stone dust shall be expressed as percentage
of the height of the stone dust below. The stone dust containing more than 8% silt shall be
washed so as lowering the silt content within the allowable limit.
7.4. The fineness modulus of stone dust shall not be less than 1.80.
M-8. Stone Grit:
8.1. Grit shall consist of crushed or broken stone and be hard strong, dense, durable, clean, of
proper gradation and free from skin or coating likely to prevent adhesion of mortar Grit shall
generally be cubical in shape and as far as possible flaky elongated pieces shall be avoided. It
shall generally comply with the provisions of I.S. 383-1970. Unless special stone of particular
quarries is mentioned, grit shall be obtained from the best black trap or equivalent hard stone
as approved by the Engineer-in-charge. The grit shall have no deleterious reaction with
8.2. The grit shall conform to the following gradation as per sieve analysis:
I.S.Sieve Percentage by I.S.Sieve Percentage by
Designation through Sieve Designation through Sieve
8.3. The crushing strength of grit will be such as to allow the concrete in which it is used to used
to built up the specified strength of concrete.
8.4. The necessary tests for grit shall carried out as per the requirements of I.S.2386(Parts I to VII)
1963, as per instructions of the Engineer-in-charge. The necessity of test will be decided by
the Engineer-in-charge. The necessity of test will be decided by the Engineer-in-charge.
9.1 Cinder is well burnt furnace residue, which has been fused or sintered into lumps of varying
9.2 Cinder aggregates shall be well burnt furnace residue obtained from furnace using coal fuel
only. it shall be sound clean free from clay, dirt ash or other deleterious matter.
9.3 The average grading for cinder aggregates shall be as mentioned below :
I.S.Sieve Percentage I.S.Sieve Percentage
Designation passing Designation passing
M-10. Lime Mortar :
10.1. Lime shall confirm to specification M-2 Water shall conform to specification M-1.
Sand: Sand Shall conform to specification M-6.
10.2. Proportion of Mix : 10.2.1. Mortar shall consist of such proportions of slaked lime and sand
as may be specified in the item. The slaked lime and sand be measured by volume.
10.3. Preparation of Mortar :
10.3.1. Lime mortar shall be prepared by wet process as per I.S. 1625-1971. Power driven mill shall
be used for preparation of lime mortar. The slaked lime shall be placed in the mill in an even
layer and ground for the 180 revolutions with a sufficient water. Water shall be added as
required during grinding (care being taken not to add more water) that will bring the mixed
material to a consistency of stiff paste. Thoroughly wetted sand shall then be added evenly
and the mixture ground for another 180 revolutions.
10.4. Storage : 10.4.1 Mortar shall always be kept damp, protected form sum and rain till used up
covering it by tarpaulin or open sheds.
10.5. Use : 10.5.1 All mortar shall be used as soon as possible after grinding it should be used on
the day on which it is prepared. But in no case mortar made earlier than 36 hours shall be
permitted for use.
M-11. Cement Mortar:
11.1 Water shall conform to specification M –1. Cement : Cement shall conform to specification
Sand: Sand shall conform to M-6
11.2 Preparation of Mix :11.2.1 Cement and shall be mixed to specified proportion, sand being
measured by measuring boxes. The proportion of cement will be by volume on the basic of
kg / Bag of cement being equal to 0.0342 Cu.m. The mortar may be hand mixed or machine
mixed as directed.
11.3 Preparation of mortar : 11.3.1 In hand mixed mortar cement and sand in the specified
proportions shall be thoroughly mixed dry on a clean impervious platform by turning over at
least 3 times or more till a homogenous mixture of uniform colour is obtained., Mixing
platform shall be so arranged that no delirious extraneous material shall get mixed with mortar
or mortar shall be gradually added and thoroughly mixed to form a stiff plastic mass of
uniform colour so that each particle of sand shall be completely covered with a film of wet
cement. The water cement ratio shall be adopted as directed.
11.3.1 The mortar so prepared shall be used within 30 minutes of adding water Only such quantity of
mortar shall be prepared as can be used within 30 minutes.
M-12 Stone Coarse Aggregate For nominal Mix Concrete :
12.1 Coarse aggregate shall be machine crushed stone of black trap or equivalent and be hard,
strong m dense, durable clean and free form skin and coating likely to prevent proper
adhesion for mortar.
12.2 The aggregate shall generally be cubical in shape. Unless special stones of particular quarries
are mentioned aggregates shall be machine crushed from the best black trap or equivalent hard
stone as approved. Aggregate shall have no deleterious reaction with cement. The size of the
coarse aggregate for plain cement concrete and ordinary reinforced cement concrete shall
generally be as per the table given below. However in case of reinforced cement concrete the
maximum limit may be restricted to 6 mm. less than the minimum lateral clear distance
between bars or 6 mm. less than the cover, Whichever is smaller.
l.s.sieve percentage passing for single I.S.Sieve Percentage passing for single
sized aggregates of nominal Designati aggregates of Nominal size
NOTE: This percentage may be carried some what by Engineer-in-charge when considered necessary
for obtaining better density and strength of concrete.
12.3. The grading test shall be taken in the beginning and at the change of source of materials. The
necessary test indicated in I.S. 383-1970 and I.S. 456-1978 shall have to be carried out to
ensure the acceptability. The aggregates shall be stores separately and handled in such a
manner as to prevent the intermixing of different aggregates. If the aggregates. are covered
with dust, they shall be washed with water to make them clean.
M-13. Black Trap or Equivalent Hard Stone Coarse :
13.1 Aggregate For Design Mix Concrete :Coarse aggregate shall be of machine crushed stone of
black trap or equivalent hard stone and be hard strong dense, durable clean and free skin and
coating likely to prevent proper adhesion of mortar.
13.2 The aggregates shall generally be cubical in shape. Unless special stones of particular quarries
are mentioned, aggregates shall be machine crushed from the best, black trap or equivalent
hard stones as approved. Aggregate shall have no deleterious reaction with cement.
13.3 The necessary tests indicated in I.S. 383-1970 and I.S. 456-1978 shall have to be carried out
to ensure the acceptability of the material.
13.4 If aggregate is covered with dust it shall be washed with water to make it clean.
M-14. Brick Bats Aggregate :
14.1 Brick bat aggregate shall be broken from well burnt or slightly over burnt and dies brick. It
shall be homogeneous in texture roughly cubical shape, clean and free from dirt of any other
foreign material. The brick bats shall be of 40 mm. to 50 mm. size unless otherwise specified
in the item. The unburnt or over burnt brick bats shall not be allowed.
14.2 The brick bats shall be measured by volume by suitable boxes or as directed.
15.1 The bricks shall be hand or machine moulded and made from suitable soils and kiln-burnt.
They shall be free from crack and nodules of free lime. They shall have smooth rectangular
faces with sharp corers and shall be of uniform colour.
The bricks shall be moulded with a frog of 100 mm. X 40 mm. and 10 mm. to 20 mm. deep on
one of its flat sides. The bricks shall not break when thrown on the ground from a height of
15.2 The size of modular bricks shall be 190 mm. X 90 mm. X 90 mm.
15.3 The size of the conventional bricks shall be as under : (9”x4 ” x 2 ”)225 x 110 x 75 mm.
15.4 Only bricks of one standard size shall be used on one work. The following tolerances shall be
permitted in the conventional size adopted in a particular work.
Length : 1.8 (3.0 mm.) Width : 1/6 “ (1.51 mm.) Height : 1/6” 1.50 mm.)
15.5 The crushing strength of the bricks shall not be less than 35 Kg./Sq.Cm. The average water
abscriptics shall not be more than 20 prevent by weight. Necessary tests for crushing strength
and water absorption etc. shall be carried out as per I.S. .3493 (Part-I to IV)
16.1 The stone shall be of the specified variety such as Granite/Trap Stone. Quartzite or any other
type of good hard stones. The stones shall be obtained only from the approved quarry and
shall be hard, sound, durable and free from defects like cavities, cracks, sand holes, flaws,
injurious veins, patches of loose or soft materials etc. and weathered portions and other
structural defects or imperfections tending to affect their soundness and strength. The stone
with round surface shall not be used. The percentage of water absorption shall not be more
that 5% of dry weight, When tested in accordance with I.S. 1134-1974. The minimum
crushing strength of the stone shall be 200 kg./Sq. Cm. unless otherwise specified.
16.2 The samples of the stone to be used shall be got approved before the work is started.
16.3 The Khanki facing stone shall be dressed by chisel as specified in the item for khanki facing
in required shape and size. The face of stone shall be so dressed that the bushing on the
exposed ace shall not project by more than 40 mm. from the general wall surface and on face
to be plastered it shall not project by more than 19 mm. nor shall it have depressions more
than 10 mm. from the average wall surface.
M-17. Laterite Stone :
17.1 Laterite stone shall be obtained from the approved quarry. It shall be compacted in texture,
sound, durable and free from soft patches. It shall have a minimum crushing strength of
K.G/S.q. Cm. in its dry condition. It shall not absorb water more than 20% of its own weight,
When immersed for 24 hours in water. After quarrying the stone shall be allowed to weather
for some time before using in work.
17.2 The stone shall be dressed into regular rectangular blocks so that all faces are free from
waviness and unevenness, edges true and square.
17.3 Those types of stone in which white clay occur, should not be used.
17.4 special corner stones shall be provided where so directed.
M-18. Mild Steel Bars :
18.1 Mild steel bars reinforcement for R.C.C work shall conform to I.S. 432(Part-II) 1966 and shall
be tested quality. It shall also comply with relevant part of I.S. 456-1978.
18.2 All the reinforcement shall be clean and free from dirt, paint, grease, mile scale or loose or
thick rust at the time of placing.
18.3 For the purpose of payment, the bar shall be measured correct upto 100 mm. length and
weight payable worked out at the rate specified below :
1. 6mm. x 0.22 Kg./Rmt 8. 20mm. 2.47 Kg./Rmt
2. 8mm. x 0.39 Kg./Rmt. 9. 22mm. 2.98 Kg./Rmt
3. 10mm x 0.62 Kg./Rmt 10. 25mm. 3.85 Kg./Rmt
4. 12mm x 0.89 Kg./Rmt 11. 28mm. 4.83 Kg./Rmt
5. 14mm x 1.21 Kg./Rmt 12. 32mm. 6.31 Kg./Rmt
6. 16mm x 1.58 Kg./Rmt 13. 36mm. 7.99 Kg./Rmt
7. 18mm x 3.00 Kg./Rmt 14. 40mm 9.86 Kg./Rmt.
M-19. High yield Strength Steel Deformed Bars :
19.1 High yield strength steel deformed bars are either cold twisted or hot rolled, shall conform to
I.S. 1739-1966 and I.S.1139-1966 respectively.
19.2 Other provision and requirements shall conform to specification NO. M-18 for Mild steel
M-20. High Tensile Steel Wire:
20.1 The high tensile wires for the use in prestressed concrete work shall conform to I.S. 2090-
20.2 The tensile strength of the high tensile steel bars shall be as specified in the item. In absence
of the given strength, the minimum strength shall be taken as per para 6.1 of I.S. 1785-1962.
Testing shall be done as per I.S. requirements.
20.3 The high tensile steel shall be free from loose mill scale, rust oil, grease, or any other harmful
matter, Cleaning of steel bars may be carried out by immersion in solvent solution, wire
brushing or passing through a pressure box containing carborundum.
20.4 The high tensile wire shall be obtained from manufactures in coil having diameter not less
than 350 times the diameter of wire itself so that wire springs back straight back straight on
being uncoiled.
M-21. Mild Steel Binding Wire :
21.1. The mild steel wire shall be of 1.63 mm or 1.22 mm. (16 or 18 gauge) diameter and shall
conform to I.S. 280-197.
21.2. The use of black wire be permitted for binding reinforcement bars. It shall be free from rust,
Oil paint, grease, looser mile scale or any other undesirable coating which may prevent
adhesion of cement mortar.
M-22. Structural Steel :
22.1. All structural steel shall conform to I.S. 226-1965. The steel shall be free from the defects
mentioned in I.S. 226-1975 and shall have a smooth finish. The material shall have a smooth
finish. The material shall be free from loose mile scale, rust pits or other defects affecting the
strength and durability. Rivet bars shall conform to I.S. 1148-1973.
22.2. When the steel is supplied by the Contractor test certificates of the manufactures shall be
obtained according to I.S. 226-1975 and other relevant Indian Standards.
M-23. Galvanised Iron Sheets :
23.1 The galvanised iron sheets shall be plain or corrugated sheets of specified in item. The G.I.
sheets shall conform it I.S. 217-1977. The sheets shall be undamaged in carriage and handling
either by rubbing off of zinc coating or otherwise they shall have clean and bright surface and
shall be as directed as per site condition.
23.2 The length and width of G.I. sheet shall be as directed as per site condition.
M-23 (A) G.I Valleys gutter ridges :
23.A.1. The G.I.ridges and hips shall be of plain galvanised sheets class-3 of the thickness as specified
in item. These shall be 600 mm. in width and properly bent up to shape without damage to the
sheets in process of bending.
23.A.2. Valleys gutters and flashings shall also be galvanised sheet of thickness as specified in item.
Valleys shall be 900 mm. Wide overall and flashing shall be 380 mm. wide overall. They shall
be bent to the required shape without damage to the sheet in the process of bending.
M-24. Asbestos Cement Sheets :
24.1. Asbestos cement sheets plain, corrugated or semi corrugated shall conform to I.S. 459-1970.
24.2. Ridges & Hips :
24.2.1 Ridges and hips shall be same thickness at that of A.C.sheets. The types of ridges suitable for
the type of sheets and locations.
24.2.2 Other accessories to be used in roof such as flashing pieces, caves filler pieces valley gutters,
north light and ventilator curves, barge boards etc. shall be standard manufacture and shall be
suitable for the type of sheets and location.
M-25. Manglore Pattern Roof Tiles :
25.1 The manglore pattern tiles shall conform to I.S. 654-1972 for Class AA or Class “A” type as
specified in item. Samples of the tiles to be provided shall be got approved from the Engineer-
in-charge. Necessary tests shall be carried out as directed.
M-26. Shuttering :
26.1. The shuttering shall be either of widen planking of 30 mm. minimum thickness with or
without steel lining roof steel plates stiffened by steel angles. The shuttering shall be
supported on battens and beams and props of vertical ballies properly cross braced togather so
as to make the centering rigid. In places of bully props, brick pillar of adequate section built in
mud mortar may be used.
26.2. The form work shall be sufficiently strong and shall have camber, so that it assumes correct
shape after deposition of the concrete and shall be able to resist forces caused by vibration of
live load of men working over it and other incidental loads associated with it. The shuttering
shall have smooth and even surface and its joints shall not permit leakage of cement grout.
26.3. If at any stag of work during or after placing concrete in the structure, the form work sags or
bulges out beyond the required shape of the structure, the concrete shall be removed and
work redone with fresh concrete and adequately rigid form work. The complete from work
shall be got inspected by and got approved from the engineer-in-charge, before the
reinforcement bars are placed in position.
26.4. The props shall consist of bullies having 100 mm. minimum diameter measured at mix length
and 80 mm, at thin end and shall be placed as per design requirement. These shall rest
squarely on wooden sole plates 40 mm. thick and minimum bearing area if 0-10 sq. m. laid on
sufficiently hard base.
26.5. Double wedges shall further be provided between the sole plate and the wooden props so as
to facilitate tightening and easing of shuttering without jerking the concrete.
26.6. The timber used in shuttering shall not be so dry as to absorb water from concrete and swell or
bulge nor so green or wet as to shrink after erection. The timber shall be properly sawn and
planed on the sides and surface coming in contact with concrete. Wooden from work with
metal sheet lining or steel plates stiffened by steel angles shall be permitted.
26.7. As far as practicable, clamps shall be used to hold the forms together and use of nails and
spikes avoided.
26.8. The surface of timber shuttering that would come in contact with concrete shall be well wetted
and coated with soap solutions before the concreting is done. Alternatively coat of raw linseed
oil or oil of approved manufacturer may be applied in place of soap solution. In case of steel
shuttering either soap solution or raw linseed oil shall be applied after thoroughly cleaning the
surface. Under no circumstances black or burnt oil shall be permitted.
26.9. The shuttering for beams and slabs shall have camber of 4 mm. per meter (1 to 250) or as
directed by the Engineer-in-charge so as to offset the subsequent deflection. For cantilevers,
The camber at free end shall be 1/50 of the projected length or as directed by the Engineer-in-
M-27. Expansion joints-Premoulded filter :
27.1 The item provides for expansion joints in R.C.C frame structures for internal joints, as well as
exposed joints, with the use of premoulded bituminous joint filler.
27.2 Premoulded bituminous joint filler, i.e. performed strip of expansion joint filler shall not get
deformed or broken by twisting, bending or other handling when exposed to atmospheric
condition. Pieces of joint filler that lave been damaged shall be rejected.
27.3 Thickness of the pre-moulded joint filler shall otherwise specified.
27.4 Premoulded bituminous joint filler shall conform to I.S. 1838-1961.
M-28 Expansion joints-Copper strips & hold fasts :
28.1 The item provide for expansion joints in R.C.C frame structure for internal joints as well as
for exposed joints with the use of necessary copper strip and hold fasts.
28.2 Copper sheet shall be of 1.25 mm. thick and of 1.25 mm. width when the ‘U’ shape in middle.
Copper strips shall have hold fast of 3 mm. diameter copper rod fixed to the plate soldered on
strip at intervals of about 30 cm. or as shown in the drawing or as directed. The width of each
flange (horizontal side) of the copper plate to be embedded in the concrete work shall be
mm. Depth of ‘U’ to be provide in the expansion joint, in the copper plate shall be of 25 mm.
M-29. Teak wood :
29.1 The teak wood shall be of good quality as required for the item to be executed. When the kind
of wood is not specifically mentioned, good Indian teak wood as approved shall be used.
29.2 Teak wood shall generally be free from large, loose, dead or cluster knots, flaws, shakes,
warps, twists bends or any other defects. It shall generally be uniform in substance and of
straight fibres as far as possible. It shall be free from rot, decay, harmful fungi and other
defects of harmful nature which will affect the strength durability of its usefulness for the
purpose for which it is required. The colour shall be uniform as far as possible. Any effort like
painting, using any adhesive or resins materials made to hide the defects shall render the
pieces liable to rejection by the Engineer-in-charge.
29.3 All scantlings, planks etc. shall be sawn in straight lines and planes in the direction of grains
and of uniform thickness.
29.4 The tolerances in the dimensions shall be allowed at the rate of 1.5 m.m. per face to be planed.
29.5 First class teak wood : 29.5.1. First class teak wood shall have no individual hard and sound
knots, more than 6 sq. cm. size and the aggregate area of such knots shall not be more than
1% of area of piece. The timber shall be closed grained.
29.6 Second Class Teak Wood : 29.6.1. No individual hard and sound knots shall be more than
Sq. cms. in size and aggregate area of such knots shall not-exceed 2% of the area of piece.
M-29. (A) Non-teak wood :
The non teak-wood shall be chemically treated, seasoned as per IS Specifications and of good
quality. The type of wood shall be got approved before collecting the same on site.
Fabrication of wooden members shall be started only after approval.
For this purpose wood of Bio, Kalali, Siras, Behda, Jamun, Sisoo will be used for door frames
where as only Kalali, Siras,Halda,Kalam etc. will be permitted for shutters after proper
seasoning and chemical treatment.
The non-teak wood shall be free from large, loose, dead of cluster knots, flows, shakes warps
bends or any other defect. It shall be uniform in substance and of straight fibers as far as
possible. It shall be free rots, decay harmful fungi and other defects of nature which effect the
strength, durability or its usefulness for the purpose for which it is required. The colour of
wood shall be uniform as far as possible. The scantlings planks etc. shall be sawn in straight
lines and planes in the direction of grain and uniform thickness.
The department will use the Agency to produce certificate from forest Department in event of
Disputes and the decision of the Department shall be final and binding to the contractor.
The tolerance in the dimension shall be allowed as 1.5 mm. per face to be planed.
M-30. Wooden flush door shutters (solid core) :
30.1 The solid core type flush door shutters shall be decorative or non-decorative type as specified
in the drawing. The size and thickness of the shutter shall be as specified in drawings or as
directed. The timber species for core shall be used as per I.S. 2202- (Part-I) 1980. The timber
shall be free from decay and insect attack. Knots and knot holes less than half the width of
cross-section of the members in which they occur may be permitted. Pitch pockets, Pitch
streaks and harmless pin holes shall be permissible except in the exposed edges of the core
members. The commercial plywood, cross-bands shall conform to I.S. 303-1275.
30.2 The face panel of the shutters shall be formed by gluing by the hot press process on both faces
of the core with either plywood or cross-bands and face veneers. The hopping rebating
opening of glazing, Venetian etc. shall be provided if specified in the drawing.
30.3 All edges of the door shutters shall be square. The shutters shall be free twist or warp in its
plane. Both faces of the shutters shall be sand papered to smooth even texture.
30.4 The shutters shall be tested for
(1) End immersion test : The test shall be carried out as per I.S. 2202 (part-I) 1980. There shall
be no delamination at the end of the test.
(2) Knife test : The face panel when tested in accordance with I.S. 1659-1979 shall pass the test.
(3) Glue adhesion Test : The flush door shall be tested for glue adhesive test in accordance with
I.S. 2202 (Part-I) 1980. The shutters shall be considered to have passed the test if no
delamination occurs in the glue lines in the plywood and if no single declamination more than
80 mm. in length and more than 3 mm. in depth has occurred in the assembly glue lines
between the plywood face and the style and rail. Delamination at the corner shall be measured
continuously around the corner. Delamination at the knots, knots holes and other permissible
wood defects shall not be considered in assessing the sample.
30.5 The tolerance in size of solid core type flush door shall be as under :
In Normal thickness + 1.2 mm. In Normal height + 3 mm.
30.6 The thick of the shutters shall be uniform throughout with a permissible variation of not more
than 0.8 mm. when measured at any two points.
M-31. Aluminum doors, Windows, Ventilators.
31.1 Aluminum alloy used in the manufacture of extruded window sections shall conform to I.S.
designation HEA-WP of I.S. :733-1975 and also to I.S. Designation WVG-WP of I.S. 1285-
1975. The Section shall be as specified in the drawing and design. The fabrication shall be
done as directed.
31.2 The hinges shall be cast or extruded aluminum hinges of same type as in windows but of large
31.3 The hinges shall normal be of 50 mm. projecting type. Non-projecting type of hinges may also
be used if directed. The handles of door shall be of specified in the drawing and design. The
fabrication shall be done as directed.
M-32. Rolling Shutters :
1 The rolling shutter shall conform to I.S. 6248-1979. Rolling shutters shall be supplied of
specified type with accessories. The size of the rolling shutters shall be specified in the
drawings. The shutters shall be constructed with interlocking lath sections formed from cold
rolled steel strips not less than 0.9 mm. thick and 80 mm. wide for shutters upto 3.5 mm.,
width not less than 1.25 mm. thick and 80 mm. wide for shutters 3.5 mm in width and above
unless otherwise specified.
2 Guide channels shall be of mild steel deep channel section and of rolled pressed or built up
(fabricated) jointures construction. The thickness of sheet used shall not be less than 3.15 mm.
3 Hood covers shall be made of M.S. Sheets not less that 0.92 mm. thickness For shutters
having width 3.5 Meter and above the thickness of M.S. Sheet for the hood cover shall be not
less than 1.25 mm.
4 The spring shall be of best quality and shall be manufactured from tested high tensile spring
steel wire or strip of adequate strength to balance the shutters in all position. The spring pipe
shaft etc. shall be supported on strong M.S. or malleable C.I. brackets. The brackets shall be
fixed on or under the lintel as specified with raw plugs and screws bolts etc.
5 The rolling shutters shall be of self rolling type up to 8 Sq.m. clear area without ball bearing
and p to 12 Sq.m. clear area with ball bearing. If the rolling shutters are larger, then gear
operated type shutters shall be used.
6 The locking arrangement shall be provided at the bottom of shutter at both ends. The shutters
shall be opened from outside.
7 The shutters shall be completed with door suspension shafts, locking arrangements pulling
hooks, handles and other accessories.
M-33. Collapsible Steel Gate :
33.1 The collapsible steel gate shall be in one or two leaves and size as per approved drawings or
as specified. The gate, shall be fabricated from best- quality mild steel channels, flats etc.
Either steel pulleys or ball bearing shall be provided in every double channel. Unless
otherwise specified the particulars of collapsible gate shall be as under :
(a) Pickets : These shall be of 20 mm. M.S., channels of heavy sections unless otherwise shown
on drawings. The distance center to center of pickets shall be 12 cms. with an opening of
(b) Pivoted M.S. flats shall be 20 mm x 6 mm.
(c) Top and bottom guides shall be from tee or flat iron of approved size.
(d) The fittings like stoppers, fixing hold fasts, locking cleats, brass handles and cast iron rollers
shall be of approved design and size.
M-34. Welded Steel Wire Fabric :
34.1. Welded steel wire fabric for general purpose shall be manufactures from cold drawn steel wire
“as drawn” or galvanised steel conforming to I.S. 226-1975 with longitudinal and transverse
wire securw4ely connected at every intersection by a process of electrical resistance welding
and conforming to I.S. 4948-1974. It shall be fabricated and finished in workmanlike manner
and shall be free from injurious defects and shall be rust proof. The type of mesh shall be
oblong or square as directed. The mesh sizes and size of wire for square as well as oblong
welded steel wire fabric shall be as directed. The steel wire fabric in panels shall be in one
whole piece in each panel as far as stock size permit.
M-35. Expanded Metal Sheets :
35.1. The expanded metal sheets shall be free from flaws, joints, broken strands, laminations and
other harmful surface Expanded metal steel sheet shall conform to I.S. 412-1975, Except that
blank sheets need not be with guaranteed mechanical properties. The size of the diamond
mesh of expended metal and dimensions of strands (width and thickness) shall be as specified.
The tolerance in nominal weight of expended metal sheets shall be of + 10 percent.
35.2. Expanded metal in panels shall be in one whole piece panel each as far as stock size permit.
The expanded metal sheets shall be coated with suitable protective coating to prevent
M-36. Mild Steel Wire (Wire ) :
36.1 Mild steel wire may be galvanised, as indicated All finished steel wire shall be well cleanly
drawn to the dimensions and size of wire as specified in item. The wire shall be sound, free
from splits, surface flaws, rough jagged and imperfect edges and other harmful surface defects
and shall conform to I.S. 280-1978.
M-37. Plywood :
37.1 The plywood for general purpose shall conform I.S. 303-1975. Plywood is made by
cementing together thin boards or sheets of wood into panels. There are always an odd
number of layers 3,5,7,9 ply etc. The plies are placed so that grain of each layer is right angle
to the grain in the adjacent layer.
37.2 The Chief advantages of plywood over a signal board of the same thickness is the more
uniform strength of the plywood, along the length and width of the plywood and grater
resistance to cracking and splitting with change in moisture content.
37.3 Usually synthetic resins are used for gluing, pherolic resins are usually cured in a hot press
which compresses and simultaneously heats the plies between hot plates which maintain a
temperature of 90 degrees C. to 140 degrees C. and a pressure of 11 to 14 kg/sq.cm. on the
wood. The time of heating may be anything from 2 to 69 minutes depending upon thickness.
37.4 When water glue are used , the wood absorbs so much water that the finished plywood must
be dried carefully. When synthetic resins are used as adhesive finished by plywood must be
exposed to an atmosphere of controlled humidity until the proper amount of moisture has been
37.5 According to I.S. 303-1975 the plywood for general purpose shall be of three grades BWR,
WWR and CWR, depending upon the adhesives used for bonding and veneers, and it will be
further classified into six types namely AA,AB,AC,BB,BC and CC based on the quality of the
two faces, each face being of three kinds namely, A,B and C, After pressing, the finished
plywood should be reconditioned to a moisture content not less than 8 percent and not more
than 16 percent.
37.6 Thickness of plywood Boards :
Board Thickness Board Thickness Board Thickness Board Thickness
3 ply 3 mm. 5 ply 5 mm. 7 ply. 9 mm. 9 ply. 16 mm.
5 mm. 8 mm. 16 mm. 11 ply. 19 mm.
6 mm. 9 mm. 9 ply. 13 mm. 22 mm.
38.1 All glass shall be of the best quality free from specks, bubbles, smokes, veins, air holes
blisters and other defects. The king of glass to be used shall be mentioned in the item or
specification or in the special provisions or as shown in detailed drawings. Thickness of glass
panes shall be uniform. The specifications or different kinds of glass shall be as under.
38.2 Sheet Glass :
38.2.1 In absence of any specified thickness or weight in the item or detailed specifications of the
item of work, sheet glass shall be weighing 7.5 Kg/Sq.m. for panes upto 600 mm x 600 mm.
38.2.2 For panes larger than 600 mm. x 600 mm. and upto 800 m. x 800 mm. the glass weighing not
less than 8.75 Kg/Sq.m. shall be used. For bigger panes upto 900 mm. x 900 mm. glass
weighing not less than 11.25 Kg/Sq.m. shall be used.
38.2.3 Sheet glass shall be patent flattened glass of best quality and for glazing and framing purposes
shall conform to I.S. : 1761-1960. Sheet glass of the specified colours shall be used, if so
shown on detailed drawings or so specified. For important buildings and for panes with any
dimension over 900 mm. plate glass of specified thickness shall be used.
38.3. Plate Glass. 38.3.1. When plate glass is specified it shall be ‘Polished patent plate glass’ of
best quality. It shall have both the surface ground flat and parallel and polished to obtain clear
undisturbed vision and reflection. The plate glass shall be of the thickness mentioned in the
item or as shown in the detailed drawing or as specified. In absence of any specified thickness
and type of glass shall be as per details on drawings or as specified or as directed.
38.4 Obscured Glass : 38.4.1. This type of glass transmits light so that vision is Partially or almost
completely obscured. Glass shall be plain rolled, figured, ribbed or fluted or frosted glass as
may be specified as required. The thickness and type of glass shall be as per details on
drawings or as specified or as directed.
38.5. Wired Glass : 38.5.1 Glass shall be with wire netting embedded in a sheet of plate glass
electrically welded 13 mm. Georgian square mesh may be used. Thickness of glass shall not
be less than 6 mm. Wired glass shall be of type and thickness as specified.
M-39. Acrylic Sheets :
39.1. Acrylic sheet be of thickness as specified in the item and of an specified shape and size as the
case may be. Panels may be flat or curved . It should be light in weight. It shall be colourless
or coloured or opaque as specified in the item. Colourless sheet shall be as transparent as the
finest optical glass. Its light transmission rate shall be about 95%. Transparency shall not be
affected for the sheets of larger thickness. It shall be extremely resistant to sunlight, weather
and low temperatures. It shall not show any significant yellowing or change in physical
properties or loss of light transmission over a longer period of use. The sheet shall be impact
resistant also. Sheets should be available in complete range of standard transparent,
translucent and opaque colours. Sheets shall be of such quality that they can be cut bent and
jointed as desired. Solution for the joints shall be used as per the requirement of manufacturer.
M-40. Particle board :
40.1. The particle boards used for face panels shall be of best quality free from any defects. The
particle boards shall be made with phenolmaldehyde adhesive. The particle boards shall
conform to I.S. 3087-1965. “Specification for wood particle board for general purpose”. The
size and the thickness shall be as indicated.
M-41. Expanded polystyrene of framed stopper slabs :
41.1 The expanded polystyrene ceiling boards and tiles shall be approved make and shall be of
size, thickness, finish and colour as indicated. It shall be of high density and suitable for use
as insulating material. The insulating material shall be like slab of Thermocol etc.
M-42. Resin bonded fiber glass :
42.1 The resin bonded fiber glass tiles, or rolls shall be of approved make and shall be of sizes,
thickness and finish as indicated.
42.2. For test of Minerrak wool thermal insulation Blanket I.S. : 3144?1965 shall be followed.
42.3. Insulation wool blanket shall be with following coverings on one or both sides as indicated.
(1) Bituminised hessain Kraft paper for keeping out dust.
(2) Hessian cloth or Kraft paper for keeping out dust.
(3) G.I. wire netting, suitable for surface to be plastered over.
M-43. Fixtures and fastenings :
43.1.1 The fixtures and fastenings, that is, butt, hinges, tee and strap hinges sliding door bolts, tower
bolts, door latch, bath room latch, handles, door stoppers, casement window fasteners,
casement stays and ventilators catch shall be made of the metal as specified in the item or its
specifications.
43.1.2 They shall be of iron, bras, aluminum, chromium plated iron chromium plated brass, copper
oxidised iron, copper oxidised brass or anodized aluminum as specified.
43.1.3 The fixtures shall be heavy, Medium or light type. The fixtures and fastenings shall be smooth
finished and shall be such as will ensure ease of operation.
43.1.4 The samples of fixtures and fastenings shall be got approved as regards quality and shape
before providing them in position.
43.1.5 Brass and anodised aluminum fixtures and fastenings shall be bright finished.
43.2. Holdfasts :
43.2.1. Holdfasts shall be made from mild steel flat 30 cm. length and one of the holdfasts shall be
bent at right angle and two nos. of 6 mm. diameter holes shall be made in it for fixing it to the
frame with screws. At the other end. The holdfast shall be forked and bent at right angles n
opposite directions.
43.3. Butt hinges :
43.3.1. Railway standard heavy type butt hinges shall be used when so specified.
43.3.2. The strap hinges shall be manufactured from M. S. Sheet.
43.4 Siding door bold (Aldrops): 43 The Aldrops as specified in the item shall be used and shall
be got be got approved.
43.5 Tower bolts (Barrel Type):43.5.1 : Tower bolts as specified in the item shall be used as shall
be used and shall be got approved.
43.6 Door Latch:43.7.1 The size of door latch shall be taken as the length of latch.
43.7 Bathroom Latch :43.5.1 Bathroom latch shall be similar to tower bolt.
43.8 Handle : The size of the handles shall be determined by the inside grip length of the handles.
Handles shall have a base plate of length 50 mm more than size of the handle.
43.9 Door Stopper: 43.9.1 door stoppers shall be either floor door stopper type or door catch type
floor stopper shall be of overall size as specified as shall have rubber cushion.
43.10 Door Catch :43.10.1 Door catch shall be fixed as height of about 900 mm from the floor level
so that one part of the catch is fitted on the inside of the shutter and the other part is fixed in
the wall with necessary wooden plug arrangements for appropriate fixate. The catch shall be
fixed 20 mimesed the face of the door for easy operation of catch.
43.11 Wooden Door stop with highs :
43.11.1wooden door stop of size 100mm X 60 mm X 40 mm shall be fixed on the door frame with a
high of 75 mm size at high of 900 mm from the floor level the wooden door stop shall be
provided with 3 coats of approve oil paint.
43.12 Case meant window fastener : Casement window fastener for single leaf window shutter
shall be left or right handled as directed.
43.13 Casement stays (straight peg stay) :
43.13.1The stays shall be made from a channel section having three holes at appropriate position so
that the window can be opened either fully or partially as directed as directed. size of the stay
shall be 250 mm to 300 mm as directed.
43.14 Ventilator catch :
43.14.1The pattern and shape of the catch shall be as approved .
43.15.1The base and socket plate shall be made form minimum 3 mm thick plate and projected pivot
shall not be less than 12 mm length and shall be firmly riveted to the base plate in case of
44.1 (A) Oil Paints :
44.1.1. Oil Paints shall be of the specified colour and shade, and as approved. The ready mixed paints
shall only be used. However, if ready mixed paint or specific shade or tint is not available,
white ready mixed paint with approved stainer will be allowed. In such a case, the contractor
shall ensure that the shade of the paint so allowed shall be uniform.
44.1.2. All the paints shall meet following general requirements :
(i) Paint shall not show excessive setting in a freshly opened full can and shall easily be
redispressed with a paddle to a smooth homogeneous state. The paint shall show no curing,
livering, caking or colour separation and shall be free from lumps and skins.
(ii) The paint as received shall brush easily, possess good levelling properties and show no
running or sagging tendencies.
(iii) The paint shall not skin within 48 hours in a three quarters filled closed container.
(iv) The paint shall dry to a smooth uniform finish free from roughness, grit, unevenness and other
44.1.3. Ready mixed paint shall be used exactly as received from the manufactures and generally
according to their instructions and without any admixtures whatsoever.
44.2. (B) Enamel Paints :
44.2.1. The enamel paint shall satisfy in general requirements as mentioned in specification of oil
paints. Enamel paint shall conform to I.S. 2933-1975.
M-45 French polish :
45.1. The french polish of requirement and shape shall be prepared with the below mentioned
ingredients and other necessary materials:
(I) Denatured sprit of approved quality (ii) Chandras (iii) Shellac (iv) Pigment.
45.2. The French polish so prepared shall conform to I.S. : 348-1968.
M-46 Marble chips for marble mosaic terrazzo :
46.1. The marble chips shall be of approved quality and shades. It shall be hard, sound, dense and
homogenous in texture with crystalline and coarse grains. It shall be uniform in colour and
free from stains, cracks decay and weathering.
46.2. The size of various colours of marble chips of approved quality and colours only as per
grading as decided by the Engineer-in-charge shall be used for marble mosaic tiles or works.
46.3. The marble chips shall be machine crushed. They shall be free from foreign matter, dust etc.
Except as above, the chips shall conform to I.S. : 2114-1962.
M-47. Flooring Tiles :
47.1. (A) Plain Cement tiles :
47.1.1. The plain cement tiles shall be general purpose type. These are the tiles in the manufacturer of
which no pigments are used Cement used in the manufacturer of tiles shall be as per Indian
47.1.2. The tiles shall be manufactured from a mixture of cement and natural aggregates by pressure
process. During manufacture, the tiles shall be subjected to a pressure of not less than
Kg/Sq. Cm. The proportion of cement to aggregate in the backing of the tiles shall be not less
than 1:3 by weight. The wearing face through the tiles are of plain cement, shall be provided
with stone chips of 1 to 2 mm. Size. The proportions of cement to the marble chips aggregate
in the wearing layer of the tiles shall be three parts of cement to one part chips by weight. The
minimum thickness Of wearing layer shall be 3 mm. The colour and texture of wearing layer
shall be uniform through out its face and thickness. On removal from mould, the tiles shall be
kept in moist conditions continuously at least for seven days and subsequently, if necessary,
for such long period as would ensure their conformity to requirements of I.S. : 1237-1980
regarding strength resistance to wear and water absorption.
47.1.3. The wearing face of the tiles shall be plain, free from projections, depressions and cracks and
shall be reasonably parallel to the back face of the title. All angles shall be right and all edges
shall be sharp and true.
47.1.4. The size of tiles shall generally be square shape 24.85 Cm. x 24.85 Cm. or 25 Cm. x25 Cm.
The thickness of tiles shall be 20 mm.
47.1.5. Tolerance of length and breadth shall be plus or minus one millimeter, Tolerance or thickness
shall be plus 5 mm.
47.1.6. The tiles shall satisfy the tests as regards transverse strength, resistance to wear and water
absorption as per I.S.:1237-1980.
47.2. (B) Plain Coloured Tiles :
47.2.1. These tiles shall have the same specification as per plain cement tiles as per (A) above except
that they shall have a plain wearing surface where in pigments are used. They shall conform to
47.2.2. The pigment used for colouring cement shall not exceed 10 percent by weight of cement used
in the mix. The pigments, synthetic or otherwise, used for colouring tiles shall have permanent
colour and shall not contain materials detrimental to concrete.
47.2.3. The colour of the tiles shall be specified in the item or as directed.
47.3. (C) Marble mosaic tiles :
47.3.1. These tiles have the same specifications as per plain cement tiles except the requirements as
47.3.2. The marble mosaic tiles shall conform to I.S. 1237-1980. The wearing face of the tiles shall be
mechanical ground and filled. The wearing face of tiles shall be free from projections,
depressions and cracks and shall be reasonably parallel to the back face of the tiles. All angles
shall be right angles and all edges shall be sharp and true.
47.3.3. Chips used in the tiles be from smallest up to 20 mm. size. The minimum thickness of wearing
layer of tiles shall of 6 mm. For pattern of chips to be used on the wearing face, a few samples
with or without their full size photographs as directed shall be presented to the Engineer-in-
charge for approval.
47.3.4. Any particular samples, If found suitable shall be approved by the Engineer-in-charge, or he
may ask for a few more samples to be prepared indicating roughly the particular sized chips to
be more or less in the samples presented. The samples have to be made by the contractor till a
suitable sample is finally approved for use in the work.
The Contractor shall ensure that the tiles supplied for the work shall be in conformity with the
approved sample only, in terms of its dimensions, thickness of backing layer and wearing
surface, materials, ingredients, colour shade, chips, distribution etc. required.
47.3.5. The tiles shall be prepared from cement conforming to Indian Standards or coloured Portland
cement generally depending upon the colour of tiles to be used or as directed.
47.4. (D) Chequred Tiles:
47.4.1. Chequred tiles shall be plain cement tiles or marble mosaic tiles. The former shall have the
same specification as per (A) above and the letter as per marble mosaic tiles as per (C) except
as mentioned below :
47.4.2. The tiles shall be of nominal size of 250 mm. x 250 mm. or as specified. The center to center
distance of chequer shall not be less than 25 mm. and not more than 50 mm. The overall
thickness of the tile shall be 22 mm.
47.4.3. The grooves in the chequers shall be uniform and straight. The depth of the grooves shall not
be less than 3 mm. The chequred shall be plain, coloured or mosaic as specified. The
thickness of the upper layer measured from the top of the chequres shall not be less than
mm. The tiles shall be given the first grinding with machine before delivery to site.
47.4.4. Tiles shall conform to relevant I.S. 1237-1980.
47.5 (E) Chequred Tiles for Stair cases :
47.5.1. The requirements of these tiles shall be the same as chequred as per (D) above except in
following respects;
(1) The length of a tile including nose shall be 330 mm.
(2) The minimum thickness shall be 28 mm.
(3) The noising shall have also the same wearing layer as at the top.
(4) The nosing edge shall be rounded.
(5) The front portion of the tile for a minimum length of 75 mm. from and including the nosing
shall grooves running parallel to noising and at center not exceeding 25 mm. Beyond that the
tiles shall have normal chequer pattern.
M-48. Rough Kotah Stone :
48.1. The kotah stones shall be hard, even, sound, and regular in shape and generally be green.
Brown colour stones shall not be allowed for use. They shall be without any soft veins, cracks
48.2. The size of the stones to be used for flooring shall be of size 600 mm x 600 mm and/or size
600 mm x 450 mm, as directed. However smaller sizes will be allowed to be used to the
extent of maintaining required pattern. Thickness shall be as specified.
48.3. Tolerance of minus 30 mm. on account of chisel dressing of edges shall be permitted for
length as well as breadth. Tolerance in thickness shall be + 3 mm.
48.4. The edges of stones shall be truly chiselled and table rubbed with coarse sand before paving.
All angles and edges of the stone shall be true, Square and free from chipping and the surface
shall be true and plain.
48.5. When machine cut edges are specified, the exposed edges and the edges at joints shall be
machine cut. The thickness of the exposed machine cut edges shall be uniform.
M-49. Polished Kotah Stones
49.1. Polished kotah stone shall has same specifications as per rough kotah stone except as
mentioned below:
49.2. The stones shall have machine polished smooth surface. When brougth on site, the stones
shall be single polished or double polished depending upon its use. The stones for paving shall
generally be single polished. The stones to be used for dedo, skirting, platforms, sink,
veneering, sills, steps, etc. Where machine polishing after the stones are fixed in situ is not
possible, shall be double polished.
M-50. Dholpur Stone Slab :
50.1. Dholpur stone slab shall be of best qualityas approved by the Engineer-in-charge The stone
slab shall be even, sound and durable, regular in shape and of uniform colour.
50.2. The size of the stone shall be specified in the item or detailed drawings or as approved by the
Engineer-in-charge. The thickness of the stone shall be as specified in the item of work with
the permissible tolerance of plus or minus 2 mm. The provisions in respect of polishing as for
polished Kotah stone shall apply to polished Dholpur stone also. All angles and edges of the
face of the stone slab shall be fine chiseled or polished as specified in the item of work and all
the four edges shall be machine cut. All angle and edges of the stone slab shall be true and
50.3. The sample of stone shall be got approved form the Engineer-in-charge for shade and tint for
a particular work. It shall be ensured that stones to be used in a particular work shall not differ
much in shade or tint from the approved sample.
M-51. Marble Slab :
51.1. Marble slab shall be while or of other colour and of best quality as approved by the Engineer-
51.2. Slabs shall be hard, uniform and homogeneous in texture. They shall have even crystalline
grain and free from defects and cracks. The surface shall be machine polished to an even and
perfectly plant surface and edges machine cut true and square. The rear face shall be rough to
provide key for the mortar.
51.3. Marble slabs with natural veins, if selected shall have to be laid as per the pattern given by the
Engineer-in-charge. Size of the slab shall be minimum 450mm x 450mm. and preferable
mm x 600 mm. However, smaller sizes will be allowed to be used to the extent of maintaining
required pattern.
51.4. The slab shall not be thinner than the specified thickness at its thinnest part. A few specimen
of finished slab to be used shall be deposited by the Contractor in the office for reference.
51.5. Except as above, the marble slabs shall conform to I.S. 1130-1969.
M-52 Granite Stone Slab :
52.1 Granite shall be of approved colour and quality. The stone shall be hard, even, sound regular
in shape and generally uniform in colour. It shall be without any soft veins, cracks of flows.
52.2 The thickness of the stone shall be as specified in items.
52.3 All exposed face shall be double polished to tender truly smooth and the even reflecting
surface. The exposed edges and corners shall be rounded off as directed. The exposed edges
shall be machine cut and shall have uniform thickness.
M-53 P.V.C. Flooring :
53.1 P.V.C sheets for P.V.C. floor covering shall be homogenous flexible type, conforming to I.S.
3452-1966. The P.V.C covering shall neither develop any toxic effect while put to use nor
shall give off any disagreeable order.
53.2 Thickness of flexible type covering tiles shall be as specified in the description of the item.
53.3 The flexible type shall be backed with Hussein or other woven fabric. The following
tolerances shall be applicable on the nominal dimension of the sheet rolls or tiles :
(a) Thickness + 0.15 mm
(b) Length or Width :
1. 300 mm. square tiles + 0.20 mm. 39.00 mm.square tiles +0.30 mm.
2. 600 mm. square tiles + 0.40 mm. 4 Sheets ad rolls +0.10 percent
53.4 Adhesive :
53.4.1 The adhesive for PVC flooring shall be of the type and make recommended by the
manufactures of PVC sheets/tiles.
M-54. Facing tiles :
54.1. The facing tiles (burnt clay facing bricks) shall be free from cracks, flaws and nodules of free
lime. They shall be thoroughly burnt and shall have plane rectangular faces with parallel sides
and sharp straight right edged faces. The texture of the finished surface that will be exposed
when in place, Shall conform to an approved sample consisting not less than four stretcher
bricks each representing the texture desired. The facing tiles shall have a pleasing appearance,
sufficient resistance to penetration by rain and greater durability than common bricks. The
tiles shall conform to I.S. 2691-1972.
54.2. The standard size of facing brick tiles shall be 19 x 9 x 4 cms. The facing brick tiles shall be
provided with frog which shall conform to I.S. 1077-1976.
54.3. The permissible tolerance in dimensions specified above shall be as follows :
Size Tolerance for
1 class Brick 2nd class Brick
54.4 The tolerance for distortion or war page of face or edges of individual brick from a plane
surface and from a straight line respectively shall be as follows :
Facing dimensions Permissible tolerance
Max. below 19 cms. Max. 2.5 mm.
-do- above 19 cm. Max 3.0 mm.
54.5 The average compressive strength obtained as sample of five tiles when tested in accordance
with the procedure laid as per I.S. 1077-1976 shall be not less than 175 Kg./Sq. Cm. The
average compressive strength of any individual bricks shall be not less than 160 Kg/Sq.Cm.
54.6 The average water absorption for five bricks tiles shall not exceed 12 percent of average
weight of brick before testing.
The absorption for each individual bricks shall not exceed 25 percent.
54.7 The brick tiles when tested in accordance with I.S. 1077-1976, the rate of efflorescence shall
not be more than ‘Slightly effloresced.
M-55. White glazed tiles :
55.1 The tiles shall be of best quality as approved by the Engineer-in-charge. They shall be flat and
true to shape. They shall free from cracks , crazing, spots chipped edges and corners. The
glazing shall be of uniform shade.
55.2 The tiles shall be nominal size of 150 mm x 150 mm. unless otherwise specified. The
maximum variation from the stated sizes, other than the thickness of tile, shall be plus or
minus 1.5 mm. The thickness of tile shall be 6 mm. Except as above the tiles shall conform to
M-56. Galvanised iron pipes and fittings : 56.1. Galvanised iron pipe shall be of the medium type
and of required diameter and shall comply with I.S. 1239-1979. The specified diameter of the
pipes shall refer to the inside diameter of the bore, Clamps, screw and all galvanised iron
fittings shall be of the standard ‘R’ or equivalent make.
M-57. Bib cock and stop cock :
57.1 A bib cock is a draw off tap with a horizontal inlet and free outlet. A stop cock is a valve with
a suitable means of connection for insertion in a pipe line for controlling or stopping the flow.
57.2 They shall be of screw down type and of brass chromium plated and of diameter as specified
in the description of the item. They shall conform to I.S. 781-1977 and they shall be of best
Indian make. They shall be polished bright.
57.3 The minimum finished weight of bib cock and stop cock shall be as given below :
Diameter Bib cock Stop cock Diameter Bibcock Stop cock
M-58. Gun metal wheel valve :
58.1. The gun metal wheel valve be of approved quality. These shall be gun metal fitted with wheel
and shall be of gate valve opening full way and of the size as specified. These shall conform
M-59. White glazed porcelain wash basin :
59.1. Wash basin shall be of white porcelain first quality best Indian make and it shall conform it
I.S. 2556 (Part-IV) 1972 and I.S. 771-1979.
The size of the wash basin shall be as specified in the item, Wash basin shall be of one piece
construction with continued over-flow arrangements. All internal angles shall be designed so
as to facilitate cleaning. Wash basin shall have single tap hole or two holes as specified. Each
basin shall have a circular waste hole which is either rebated or beveled internally with
mm. diameter at top and 10 mm. depth to suit the waste fitting. The necessary stud slot to
receive the bracket on the under side of the basin shall be provided. Basin shall have an
internal soap holder recess which shall fully drain into the bowl.
59.2. White glazed pedestal of the quality and colour as that of the basin shall be provided where
specified in the item. it shall be completely recessed at the back for reception of supply and
wash pipe. It shall be capable of supporting the basin rigidly and adequately and shall be so
designed as to make the height from floor to top of basin 750mm. to 800 mm. as directed.
M-60. European type water closet/with low level flushing :
60.1. The European type water closet shall be white glazed porcelain first quality and shall be of
wash down type conforming to I.S. 2556-1973 and I.S. 771-1979.
60.2. ‘S’ trap shall be provided as required with water seal not less than 50 mm. The solid plastic
seat and cover shall be of the best Indian make conforming to I.S. 2548-1980. They shall be
made of moulded syntactic materials which shall be tough and hard with high resistance to
solvents and shall be free from blisters and other surface defects and shall have chromium
plated brass hinges and rubber buffer of suitable size.
M-61. Orissa type water closet :
61.1. The specification of Orissa type white glazed water closet of first quality shall conform to I.S.
2556 (Part-III) 1981 and relevant specification of Indian type water closet except that pan
will be with the integral squatting pan of size 580 mm x 440 mm. with raised footrest.
M-62. Indian type water closet :
62.1. The Indian type white glazed water closet of first quality shall be of size as specified in the
item and conforming to I.S. 771-1979 and I.S. 2556 (Part-II) 1981. Each pan shall have
integral flushing ring of suitable type with adequate number of holes alroung as directed to
have satisfactory flushing. It shall also have inlet at back or front connecting flush pipe as
directed. The inside of the bottom of the pan shall have sufficient slope from the front towards
the outlet and surface shall be uniform and smooth.
Pan shall be provided with 100 mm. diameter ‘P’ or ‘S’ trap with approximately 50 mm.
water seal and 50 mm. diameter vent horn.
M-62. (A) Foot Rests :
62-A-1 A pair of white glazed earthen ware rectangular foot rests of minimum size 250 mm. x
mm 20 mm. shall be provided with water closet.
M-63. Glazed Earthen Ware Sink :
63.1. The glazed earthen-ware sink shall be specified size colour and quality. The sink shall
conform to I.S. 771 Part-II-1979 waste coupling of standard pattern with brass chain and
rubber plug shall be provided with sink.
63.2. The pipes shall conform to I.S. 1239-Part-I 1973 and I.S. 404-1962 for steel and lead pipes
respectively 32 mm. brass waste coupling of standard pattern with brass chain and rubber plug
shall be provided with sink.
M-64. Glazed earthen ware Lipped type flat back urinal/corner type urinal :
64.1 The lipped type urinal shall be flat back or corner type as specified in the item and shall
conform to I.S. 771-1979. It shall be of best Indian make and size as specified and approved
by the Engineer-in-charge. The flat back or corer type urinal must be 1 st quality free from any
defects, cracks, etc.
M-65. Low level enamel flushing tank :
65.1. The low level flushing tank shall be of 15 liters capacity. It shall conform to I.S. 774-1971.
The flushing vaster shall be of best quality and free from any defects. The flushing tank shall
have outlet 32 mm. diameter The outlet shall be connected with W.C. Pan by lean pipe or
P.V.C. pipe as specified. The flushing tank shall be provided with inlet and outlet for fixing
G.I. inlet pies and over-flow pipes. The flushing castern shall be provided with chromium
plated handle for flushing. The flushing tank shall be provided with brackets of cast iron so
that it can be fixed on wall at specified height. The brackets shall Conform to I.S. 775-1970.
M-66. Cast iron flushing cistern :
66.1. The cast iron flushing cistern shall be of 15 liters capacity. It shall conform to I.S. 774-1971.
The flushing cistern shall be of best quality free from any defects. The flushing cistern shall
have outlet of 32 mm. diameter. The outlets shall be connected to lead pipe of 32 mm.
diameter. The lead pipe shall conform to I.S. 404 (Part-I) 1962. For fixing G.I. inlet pipes and
overflow pipe 20 mm. diameter. inlet and outlet shall be provided. The flushing cistern shall
be provided with galvanised iron chain and pull of sufficient length and shall be got approved
from the Engineer-in-charge. The cast iron flushing cistern shall be painted with one coat of
anticorrosive paint and two coats of paints. The flushing cistern shall be fixed on two C.I.
brackets. The C.I. brackets shall conform to I.S. 775-1970.
M-67. Flush cock :
67.1. Half turn flash cock (Heavy Weight) shall be of gun metal chromium plated of diameter as
specified in the description of the item. The flush cock shall conform to relevant Indian
M-68. Cast iron pipes and fittings :
68.1. All soil waster, vent and antisyphonage pipes and fittings shall conform to I.S. 1729-1964.
The pipe shall have spigot and socket ends with head on spigot end. The pipes and fittings
shall be true to shape, smooth, cylindrical, their inner and outlet surfaces being as nearly as
practicable concentric. They shall be sound and nicely cast and shall be free from cracks, laps,
pinholes or other imperfection and shall be neatly dressed and carefully fettled.
68.2. The end of pipes and fittings shall be of reasonable square to their axis.
68.3. The sand cast iron pipes shall be of the diameter as specified in the description and shall be in
lengths of 1.5 M, 1.8 M. and 2 M. including socket ends of the pipe unless shorter lengths are
either specified or required at junctions etc. The pipes and fittings shall be supplied without
ears unless specified or directed otherwise.
68.4. Tolerances.
68.4.1. The Standard weights and thickness of pipes shall be as shown in the following table : A
tolerance up to minus 10 percent may however be against these standard weights.
Sr. Nominal Thickness Overall Weight of pipe excluding
1.5 m. long 1.8m. long 2.m. long
68.4.2. A tolerance upto minus 15 percent in thickness and 20 mm. in length will be allowed. For
fittings tolerance in lengths shall be plus 15 mm. and minus 10 mm.
68.4.3. The thickness of fittings and their socket and spigot dimensions shall conform to the
thickness and dimensions specified for the corresponding sizes of straight pipes. The
tolerances in weights and thickness shall be the same as for straight pipes.
M-69. Nahni Trap :
69.1. Nahni trap shall be of cast iron and shall be sound and free from porosity or other defects
which affect serviceability The thickness of the base metal shall not be less than 6.5 mm. The
surface shall be smooth and free from craze, ships and other flaws or any other kind of defects
which affect serviceability. The size of nahni trap shall be as specified and shall be of self
cleaning design.
69.2. The Nahni trap shall be of quality approved by the Engineer-in-charge and shall generally
conform to the relevant Indian Standards.
69.3. The Nahni trap provided shall be with deep seal, minimum 50 mm, except at places where
trap with deep seal can not be accommodated. The cover shall be cast iron. Performed cover
shall be provided on the trap of appropriate size.
M-70. Gully Trap :
70.1 Gully Trap shall conform to I.S. 651-1980. It shall be sound, free defects such as fire cracks.
The glaze of the traps shall be free from crazing. They shall give a sharp clear note when
struck with light hammer. There shall be no broken blisters.
70.2 The size of the gully trap shall be as specified in the item.
70.3 Each gully trap shall have one C.I. gratings of square size corresponding to the dimensions of
inlet of gully trap, It will also have a water tight. C.I. cover with frame inside dimensions
mm. x 300 mm., the cover with frame inside dimension, 300 mm. 300 mm., the cover
weighing not less than 4:53 Kg. and the frame not less than 2.72 Kg. The grating cover and
frame shall be of sound and good casting and shall have truly square machined seating faces.
M-71. Glaze Stone Ware Pipe And Fitting :
71.1. The pipes and fittings shall be of best quality as approved by the Engineer-in-charge. The pipe
shall be of best quality manufactured from stone-ware of fire clay, salt glazed thoroughly
burnt through the whole thickness, of a close even texture, shall be smooth and perfectly
glazed. The pipe shall be capable to withstand pressure of 1.5 mm. lead without showing sign
of leakage. The thickness of the wall shall not be less than 1/12 th of the internal dia. The depth
of socket shall not be less than 38 mm. The socket shall be sufficiently large to allow a joint
of 1 mm. around the pipe.
71.2. The pipes shall generally conform to relevant I.S. 651-1980.
M-72. Wall Peg Rail :
72.1. The aluminum wall peg rail shall have three aluminum pegs of approved quality and size. It
shall be fixed on teakwood plant of size 450 mm. x 75 mm. x 20 mm. The teakwood shall be
french polished or oil painted as specified.
M-73. G.I.Water Spot :
73.1. The G.I.pipes of 40 mm. dia shall be of medium quality and specials shall be of ‘R’ brand or
equivalent brand of best approved quality.
73.2. The pipe shall have length as required for the thickness of wall in which it is fixed. and at the
outside end tee and bend cut at half the length shall be provided and at other end coupling
shall be provided to have better fixing. The water spout shall be provided as per detailed
drawings or as directed.
M-74. Asbestos Cement Pipe (A.C. Pipe):
74.1. The asbestos cement pipe of diameter as specified in the description of the item shall conform
to I.S. 1626-1980. Specials like bends, shoes cowls, etc. shall conform to relevant Indian
Standards. The interior of pipe shall have a smooth finish, regular surface and regular, internal
diameter. The tolerance in all dimensions shall be as per I.S. 1626-Part-I
M-75. Crydon Ball valve :
75.1. Ball valve of screwed type including polyethylene float and necessary lever etc. shall be of the
size as mentioned in the description of item and shall conform to I.S. 1703-1977.
M-76. Bitumen Felt For Water Proofing And Damp Proofing :
76.1 Bitumen felt shall be on the fiber bases and shall be type 2, self finished grade-2 and shall
conform to I.S. 1322-1970.
M-77 Selected Earth :
77.1. The selected earth shall be hat obtained from excavated material or shall have to brought from
outside as indicated in the item. If item does not indicate anything, The selected earth shall
have to be brought from outside.
77.2. The selected earth shall be good yellow soil and shall be got approved from the Engineer-in-
charge. In no case black cotton soil or similar expansive and suitable soil shall be used. It shall
be clean and free from all rubbish and perishable materials, stones or brick bats. The clods
shall be broken to a size of 50. mm or less, Contractor shall make his own arrangement at his
own cost for land for borrowing selected earth. The stacking of material shall be done as
directed by the Engineer-in-charge in such a way as not to interfere with any constructional
activities and in proper stacks.
77.3. When excavated material is to be used, only selected stuff got approved form the Engineer-
In-Charge shall be used. It shall be stacked separately and shall comply with all the
requirements of selected earth mentioned above :
M-78. Barbed Wire :
78.1. The barbed wire shall be of galvanised steel and it shall generally conform to I.S. 278-1978.
The barbed wire shall be if type-I whose nominal diameter for line wire shall be 2.5 mm. and
point wire 2.24 mm. The nominal distance between two bars shall be 75 mm. Unless
otherwise specified in the item. The barbed wire shall be formed by twisting together two line
wires, One containing the barbs. The size of the line and point wires and barb spacings shall
be as specified above. The permissible deviation form the nominal diameter of the line wore
and point wire shall not exceed + 0.08 mm.
78.2. The barbs shall carry four points shall be formed by twisting two point wires each two turns,
lightly round one line wire, making altogether four complete turns. The barbs shall be so
finished that the four points are set and locked at right angles to each other. The barbs shall
have a length of not less than 13 mm. and not more than 13 mm. and not more18 MM. The
points shall be sharp and cut at an angle not greater than 35 degree of the axis of the wire
forming the barbs.
78.3. The lind and point wire shall be circular section free from scale and other defects and shall be
uniformly galvanised. The line wire shall be in continuous length and shall not contain any
weld other than those in the rod before it is drawn. The distance between two successive
splices shall not be less than 15 meters.
78.4. The lengths per 100 Kg. of barbed wire I.S. type I shall be as under
Nominal 1000 meter Minimum 834 Meter Maximum 1066 Meter.
TECHNICAL SPECIFICATIONS FOR CIVIL WORK
Clearing and grubbing road land including uprooting rank vegetation grass bushes, shrubs,
sapling and trees girth up to 300 mm removal of stumps of trees cut earlier and disposal of
unserviceable materials(A) By manual means in area of light jungle
Before the earth work is started, the area coming under cutting and filling shall be cleared of shrubs, rank
vegetation, grass, brushwood, trees and saplings of girth up to 30cm measured at a height of one metre above
ground level and rubbish removed up to a distance of 50 metres outside the periphery of the area under
clearance. The roots of trees and saplings shall be removed to a depth of 60cm below ground level or 30 cm
below formation level or 15 cm below sub grade level, whichever is lower, and the holes or hollows filled up
with the earth, rammed and leveled.
Mode of measurements & payment
The rate shall be for unit of one Hectare.
Excavation for foundation upto 1.5 m depth including sorting out and stacking of useful
materials and disposing off the excavated stuff upto 50 Meter lead.(B) Dense or Hard soil
1.1. Any soil which generally yields to the application of pickaxes and shovels, phawaras rakes or
any such ordinary excavating implement or organic soil, gravel silt, sand turf loam, clay, peat etc., fail
under this category
2.0. Clearing the site
2.1. The site on which the structure is to be built shall be cleared, and all obstructions loose stone,
materials and rubbish of all kind bush wood and trees shall be remove! as directed The materials so
obtained shall be property of the Government and shall be conveyed und stacked as directed within
50 m lead. The roots of the trees coming in the sides shall be cut and coated with a hot asphalt
2.2. The rate of side clearance is deemed to be included in the rate of earth work for which no
extra will be paid.
3.0. Setting out
After clearing the site the centre lines will be given, by the Engineer-in-charge. The contractor shall
assume full responsibility for alignment, elevation and dimension of each and all 'parts of the work.
Contractor shall supply labours materials, etc. required for setting out the reference marks and bench
'marks and shall maintain them as long as required and directed.
4.0. Excavation
The excavation in foundation shall be carried out in true line and level and shall have the width and
depth as shown in the drawings or as directed. The contractor shall do the necessary shoring and
shutting or providing necessary slopes to a safe angle, at his own cost. The payment for such
precautionary measures shall be paid separately it not specified. The bottom of the excavated area
shall be leveled both longitudinally and transversely as directed by removing and watering as
required No. earth filling will be allowed for brining it to level If by mistake or any excavation is
made deeper or wider than, that shown on the plan or directed. The extra depth or width shall be
made up with concrete of same proportion as specified for the foundation concrete at the cost of the
contractor. The excavation up to 1.5 m depth shall be measured under this item.
5.0. Disposal of the excavated stuff
5.1. The excavated stuff of the selected type shall be used in filling the trenches and plinth or
leveling the ground in layers including ramming and watering etc.
5.2. The balance of the excavated quantity shall be removed by the contractor from the site of
work to a place as directed with lead up to 50 M. and all lift.
6.0. Mode of measurements & payment
6.1. The measurement of excavation in trenches for foundation shall be made according to the
sections of trenches shown on the drawing or as per sections given by the Engineer-m-charge. No
payment shall be made for surplus excavation made in excess of above requirements or due to
stopping and sloping back as found necessary on account of conditions of soil and requirements of
6.2. The rate shall be for a unit of one cubic meter
Excavation for foundation for depth from 1.5 m to 3.0 m including sorting out and stacking
of useful materials and disposing off the excavated stuff upto 50 Meter
lead.(B) Dense or Hard soil
Any soil which generally require close application of picks or jumpers or scarifies to. loosen it stiff
clay, gravel and stone etc. fall under this category.
2.0. Workmanship
The relevant technical specifications of item No. 2 shall be followed except that the excavation work
shall be carried out in dense or hard soil.
3.0. Mode of measurements & payment
3.1. The relevant technical specifications of item No2 shall be followed
3.2. The rate shall be for unit of one cubic meter.
Filling in plinth with sand under floors including watering reamming, consolidating and
dressing etc. comp.
1.1. Sand shall conform to M
2.0. Workmanship
The relevant specifications of item No. 4.12 shall be followed except that sand shall be filled in under
floors, including watering, ramming, consolidating and dressing etc , complete.
3.0. Mode of Measurements & Payment
3.1. The relevant specifications of item No. 4.12 shall be followed.
3.2. The rate includes cost of collecting, carting sand with all lead and labour for filling the same
in plinth under floors.
3.3. The rate shall be for a unit of one cubic meter.
Filling in foundation and plinth with murrum or selected soil in layers of 20 cm. thickness
including watering ramming and consolidating etc. completed.
1.1. Murrum shall be clean, of good binding quality and of approved quality obtained from
approved pots/ quarries of disintegrated rocks which contain silicon material and natural mixture of
clay of clarions origin. The size of murrum shall not be more than 20 mm
2.0. Workmanship
2.1. The relevant specifications of item No. 4.12 shall be followed except that the murrum or
selected soil shall be filled in foundations and plinth in 20 cms layer including consolidating,
ramming, watering, dressing etc. complete
3.0. Mode of Measurements & Payment
3.1. The relevant specifications of item No. 4.12 shall be followed-.
3.2. The rate includes cost of collecting and carting murrum / or selected earth of approved quality
with all lead and labour required for filling in trenches and plinth.
3.3. Rate shall be for a unit of one cubic meter.
Filling available excavated earth (excluding rock) in trenches. plinth, sides of foundations
etc. in layers not exceeding 20 cm. in depth consolidating each disposited layer by ramming
1.0. Workmanship
1.1. The earth to be used for filling shall be free from salts, organic or other foreign matter. All
clods of earth shall be broken.
1.2. As soon as the work in foundation has been completed and measured the site of foundation
shall be cleared of all debris, brick bats: mortar dropping etc., and filled with earth in layers not
exceeding 20 cms. Each layer shall be adequately watered, rammed and consolidated before the
succeeding layer is laid The earth shall be rammed with iron rammers where feasible and with the but
ends of crow-bars, where rammer cannot be used.
1.3. The plinth shall be similarly filled with earth in layers not exceeding 20 cms. adequately
watered and consolidated by ramming with iron or wooden rammers. When filling reaches finished
level the surface shall be flooded with water for at least 24 hours and allowed to dry and then rammed
and consolidated.
1.4. The finished level of filling shall be kept to shape intended to be given to floor.
1.5. In case off large heavy duty flooring like factory flooring, the consolidation may be done by
power rollers, where so specified. The extent of consolidation required, shall also be as specified.
1.6. The excavated stuff of the selected type shall be allowed to be used in filling the trenches and
plinth. Under no circumstances black cotton soil be used for filling the plinth.
2.0. Mode of Measurements & Payment
2.1. The payment shall be made for filling in plinth and trenches. No deduction shall be made for
shrinkage or voids, if consolidated as instructed above.
2.2. The rate shall be for a unit of one cubic meter.
Providing and laying in position cement concrete (PCC or RCC) work of mix 1:2:4 (1
Cement : 2 sand : 4 graded stone aggregate 20 mm & down nominal size) in sub structure for
all type of foundations, in floors, wall, pedestals, beam, columns etc. including mixing, laying,
placing, consolidating, vibrating, levelling and curing etc. complete with all tools and tackles,
labour and materials, machineries, excluding the cost of formwork and reinforcement steel
as directed by the EIC. : Ground Beam & Plinth Beam
Water shall conform to M-1. Cement shall conform to M-3. Sand shall conform to M-6. Grit shall
conform to M-8. Graded stone aggregate 20 mm nominal size shall conform to M-12.
2.1. The concrete mix is not required to be designed by preliminary testes. The proportion of the
concrete mix shall be 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm. nominal
size) by volume concrete work shall have exposed concrete surface or as specified in the item
2.2. The designation ordinary M-100, M-150m M-200, M-250 specified as per I.S. correspond
approximately to 1:3:6, 1.2:4, 1:1:1/2:3 and 1:1:2 nominal mix of ordinary concrete by volume
2.3. The ingredients required for ordinary concrete containing one beg of cement of 50 kg. by
weight (0.0342 Cu M.) for different proportions of mix shall be as under:
Grade of Total quantity of dry Proportion of fine aggregate Quantity of water
concrete aggregate by volume per 50 to coarse aggregate per 50 Kegs. of
kgs. of cement to be taken cement maximum
as the sum of individual
volume of fine and coarse
aggregates, maximum
M-100 (1:3:6) 300 Liters Generally 1:2 for line 34 Liters
M-150 (1:2:4) 220 Liters aggregate to coarse 32 Liters
M-200 aggregate by volume 160 but 30 Liters
(1:1.1/2:3) 100 Liters subject to an upper limit of 1:3 27 Liters
M-250 (1:1:2) 1:1.1/2 and lower limit
2.4. The water cement ratios shall not be more than specified in the above table. The cement
content of the mix specified in the table shall be increased if the quantity of water in mix has to be
met eased to overcome the difficulties of placements and compaction so that the water-cement ratio
specified in the table is not exceeded.
2.5. Workability of the concrete shall be controlled by maintaining a water -cement-ratio that is
found to give a concrete mix which is just sufficient wet to be placed and compacted without
difficulty with the means available.
2.6. The maximum size of course aggregate shall be as large as possible within the limits specified
but in no case greater than one forth of the minimum thickness of the member provided that the
concrete can be placed without difficulty so as to surround all reinforcement thoroughly and to fill the
corners of the form.
2.7. For reinforced concrete work; coarse aggregates having a nominal size of 20 mm. are
generally considered satisfactory.
2.8. For heavily reinforced concrete members as in the case of ribs of main beams, the nominal
maximum size of coarse aggregate should usually be restricted to 5 mm. less than the minimum clear
distance between the main bar or 5 mm. less than the minimum cover to the reinforcement whichever
2.9. Where the reinforcement is widely spaced as in solid slabs, limitations of size of the aggregate
may not be so important, and the nominal maximum size may some times be as great as or greater
than the minimum cover.
2.10. Admixture maybe used in concrete only with approval of Engineer-in-charge based upon the
evidence that with the passage of time neither the compressive strength of concrete is reduced not are
other requisite qualities of concrete and steel impaired by the use of such admixtures.
3.0. Workmanship
3.1. Proportioning : Proportioning shall be done by volume, except which shall be measured in
terms of bags of 50 kg. weight, the volume of one such bag being taken as 0.0342 cu. meter Boxes of
suitable size shall be used for measuring sand aggregate. The size of boxes (internal) shall be 35 x
cms. and 40 cms deep while measuring the aggregate and sand the boxes shall be filled without
shaking ramming or hammering. The proportioning of sand shall be on the basis of its dry volume
and in case of damp saner, allowances for bulk age shall be made.
3.2.1. For all work, concrete shall be mixed in a mechanical mixed which along with other
accessories shall be. kept in first class working condition and so maintained throughout the
construction Measured quantity of aggregate, sand and cement required for each batch shall be
poured into the claim of the mechanical mixer while it is continuously running. After half a minute of
dry mixing measured quantity of water required for each batch of concrete mix shall be added
gradually and mixing continued for another one and a half minute Mixing shall be continued till
materials are uniformly distributed and uniform colour of the entire mass is obtained and each
individual particle of the coarse aggregate shows complete coating of mortar containing its
proportionate amount of cement. In no case shall the mixing he done for less than 2 minutes after-oil
ingredients have been put into the mixer.
3.2.2. When hand mixing is permitted by the Engineer-in-charge for small jobs or for certain other
reasons, it shall be done on the smooth watertight platform large enough to allow efficient tuning over
the ingredients of concrete before and after adding water Mixing platform shall be so arranged that no
foreign malarial gets mixed with concrete nor does the mixing water flow out. Cement in required
number of bags shall be spread in n layer of uniform thickness on the mixing platform. Dry coarse
and fine aggregate and cement shall then be mixed thoroughly be turning over to get a mixture to
uniform colour. Specified quantity water shall then be added gradually through a rose can and the
mass turned over till a mix of required consistency is obtained. In hand mixing quantity of cement
shall be increased by 10 percent above that specified
3.2.3. Mixers which haw been out of use for more than 30 minutes shall be thoroughly cleaned
in a new batch. Unless otherwise agreed to by the Engineer in-charge the first batch of concrete from
the mixture shall contain only two thirds of normal quantity of coarse aggregate Mixing plant shall
be thoroughly cleaned before changing from one type of cement to another
3.3. Consistency:
3.3.1. The degree of consistency which shall depend upon the nature of the work and methods of
concrete, shall be determined by regular slump tests in accordance with I.S. 1199-193. The skimp of
10 mm. to 25 mm shall be adopted when vibrators are used and 80 mm. when vibrators are not used.
3.4. Inspection:
3.4.1. Contractor shall give the Engineer-in-charge due notice before placing any concrete in the
forms to permit him to inspect and accept the false work and forms as to their strength, alignment and
general fitness but such inspection shall not relieve the contractor of his responsibility for the safely
of men machinery materials and for results obtained immediately before concreting all forms shall be
thoroughly cleaned.
3.4.2. Centering design and its erection shall be got approved from the engineer-in-charge. One
carpenter with helper shall invariably be kept present throughout the period of concreting. Movement
of labour and other persons shall be totally prohibited for reinforcement laid in position. For access to
different parts suitable mobile platforms shall be provided so that steel reinforcement in position is
not disturbed. For ensuring proper cover, mortar blocks of suitable size shall be cast and tied to the
reinforcement. Timber kapachi or metal pieces shall not be used for this purpose.
3.5. Transporting and laying:
3.5.1. The method of transporting and placing concrete shall be as approved. Concrete shall be so
transported and placed that no contamination, segregation or loss of its constituent material takes
place. All from work shall be cleaned and made free from standing water dust, show or ice
immediately before placing of concrete. No concrete shall be placed in any part of the structure until
the approval of the engineer-in-charge has been obtained.
3.5.2. Concreting shall proceed continuously over the area between construction joints. Fresh
concrete proper contraction joint is formed. Concrete shall be compacted in its final position within
30 minutes of its discharge from the mixer. Except where otherwise agreed to by the engineer-in-
charge, concrete shall be deposited in horizontal layers to a compacted depth of not more than
meter when internal vibrators are used and not exceeding 0.30 meter in all other cases.
3.5.3. Unless otherwise agreed to by the Engineer-in-charge concrete shall be dropped in to place
from a height exceeding 2 meters. When trucking or chutes are used they shall be kept close and used
in such a way as to avoid segregation. When concreting has to be resumed on a surface which has
hardened, it shall be roughened, swept clean, thoroughly wetted and covered with a 13 mm. thick
layer of mortar composed of cement and sand in the same ratio as in the concrete mix itself. This
mm. layer of mortar shall be freshly mixed and placed immediately before placing of new concrete.
Where concrete has not fully hardened, all lateness shall be removed by scrubbing the wet surface
with wire or bristle brushes, care being taken to avoid dislodgement of any particles of coarse
aggregate. The surface shall then be thoroughly wetted, all free water removed and then coated with
neat cement grout. The first layer of concrete to be placed on this surface shall not exceed 150 mm. in
thickness and shall be well rammed against old work, particular attention being given to corners and
3.5.4. All concrete shall be compacted to produce a dense homogeneous mass with the assistance of
vibrators, unless otherwise permitted by the Engineer-in-charge for exceptional cases, such as
concreting under water, where vibrators cannot be used. Sufficient vibrators in serviceable condition
shall be kept at site so that spare equipment is always available in the even of breakdowns. Concrete
shall be judged to be compacted when the mortar fills the spaces between the coarse aggregate and
begins to cream up to form an even surface. Compaction shall be completed before the initial setting
stats i.e. within 30 minutes of addition of water to dry mixture. During compaction, it shall be
observed that needle vibrators are not applied on reinforcement which is likely to destroy the bond
between concrete and reinforcement.
Immediately after compaction, concrete weather including rain, running water, shocks, vibration,
traffic, rapid temperature charges, frost and drying out process. It shall be covered with wet sacking
has Sian or other similar absorbent material approved, soon after the initial set, and shall be kept
continuously wet for a period of not less than 14 days from the date of placement. Masonry work over
foundation concrete may be started after 48 hours of its laying but curing of concrete shall be
continued for a minimum period of 14 days.
3.7. Sampling and testing of concrete:
3.7.1. Samples from fresh concrete shall betaken as per I.S. 1199-1959 and cubes shall be made,
tested at 7 days of 28 days as per requirements in accordance with I.S. 526-1959. A random sampling
procedure shall be adopted to ensure that each concrete batch shall have a reasonable chance of being
tested i.e. the sampling should be spread over the entire period of concreting and cover all mixing
units. The minimum frequency of sampling of concrete of each grade shall be in accordance with
Quantity of concrete in the No of samples Quantity of concrete in the No of samples
51 and above 4+ one additional for each additional 50 mm. or part thereof.
Note : At least one simple shall be taken from each shift, Ten test specimens shall be made from each
sample, five for testing at 7 days and the remaining five at 28 days. The samples of concrete shall be
taken on each day of concreting as per above frequency. The number of specimens may be suitably
increased as deemed necessary by the Engineer-in-charge when procedure of tests given above
reveals a poor quality of concrete and in other special cases.
3.7.2. The average of the group of cubes cast for each day shall not be less than the specified cube
strength of 150 K/g Cm 2 at 28 days. 20% of the cubes cast for each day may have value less than the
specified strength provided the lowest value is not less than 85% of the specified strength. If the
concrete made in accordance with the proportions given for a particular grade does not yield the
specified strength, such concrete shall be classified as belonging to the appropriate lower grade.
Concrete made in accordance with the Proportions given for a particular grade shall not, however be
placed in a higher grade on the ground that the test strength are higher then the minimum specified.
3.8. Stripping:
3.8.1. The Engineer-in-charge shall be informed in advance by the contractor of hr> intention to
strike the form work. While fixing the time of removal of form work, due consideration shall be given
to localconditions, character of the structure, the weather and other conditions that influence the
setting of concrete and of the materials used in the mix. In normal circumstances (generally where
temperatures are above 20.C) and where ordinary concrete is used, forms may be struck after expire
or periods specified in item No.9.1 (A) for respective item of form work.
3.8.2. All form work shall be removed without causing any shock or vibration as would damage the
concrete. Before the soft and struts are removed, the concrete surface shall be gradually exposed,
where necessary in order to ascertain that concrete has sufficiently hardened. Centering shall be
gradually and uniformly lowered in such a manner as to permit the concrete to take stresses due to its
own weight uniformly and gradually. Where internal metal tiles are permitted, they or their removable
parts shall be extracted without causing any damage to the concrete and remaining holes filled with
mortar. No permanently embedded metal part shall have less than 25 mm. cover to the finished
concrete surface. Where it is intended to re-use the form work, it shall be cleaned and made good to
the satisfaction of the Engineer-in-charge. After removal of form work and shutting, the Executive
Engineer shall inspect the work and satisfy by random checks that concrete produced is of good
3.8.3. Immediately after the removal of forms, all exposed bolts etc. passing through the cement
concrete member and used for stuttering or any other purpose shall be cut inside the cement concrete
member to a depth of at least 25 m. below the surface of the concrete and the resulting holes be filled
by cement mortar, all fins, caused by form joints, all cavities produced by the removal of form tiles
and all other holes and depressions, honeycomb spots, broken edges or comers and other defects,
shall be thoroughly cleaned", saturated with water and carefully pointed an rendered true with mortar
of cement and fine aggregate mixed in proportions used in the grade of concrete that is being
furnished and of as dry consistency as is possible to use. Considerable pressure shall be applied in
filling and pointing to ensure through filling in all voids. Surface which are pointed shall be kept
moist for a period of 24 hours. If rock pockets/honeycombs in the opinion of the Engineer-in-charge
are of such an extent or character as to effect the strength of the structure materially or to endanger
the life of the steel reinforcement, he may declare the concrete defective and require the removal and
replacement of the portions of structure affected.
4.0. Mode of Measurement & Payment
4.1. The consolidated cubical contents of concrete work as specified in item shall be measured. No
deduction shall be made for
(a) Ends of dissimilar materials such as joints, beams, posts, girders, falters, purling trusses, corbels
and steps etc., up to 500 Sq, Cm. in section.
4.2. The rate includes cost of all materials labour, tools and plant required for mixing, placing in
position, vibrating and compacting, finishing, as directed, curing and all other incidental expenses for
producing centre of specified strength. The rate excludes the cost of form work.
4.3. The rate shall be for a unit of one cubic meter.
Providing laying controlled cement concrete M-250 work with curing complete excluding
the cost of form work and excluding the rate of reinforcment for reinforced concrete work
in. (A) Foundations, footings,base of columns and mass concrete,grade slab etc.
1.1. Water shall conform to M-1. Cement shall conform to M-3. Sand shall conform to M-6. Grit
shall conform to M-8 Course aggregate shall conform M-12.
2.1. The relevant specification of item No. 5.4.1. of ordinary concrete shall be followed except that
the concrete mix shall be designed form preliminary tests. The proportioning of cement and
aggregates shall be done by weight and necessary precautions shall be taken in the production to
ensure that the required work cube strength is attained and maintained. The controlled concrete shall
be in grades of M-100, M-150, M-200, M-250, M-300, M-350 & M-400 with prefix controlled added
to it. The letter M refers to mix and the numbers specify 28 days works cube compressive strength of
150 mm. cubes of the mix expressed in Kg./Crnt.
2.2. The proportion of cement, sand and coarse aggregate shall be determined of weight. The
weight batch machine shall be used for maintaining proper control over the proportion of aggregates
as per mix design. The strength requirements of different grades of concrete shall be as under:
Grade Compressive strength of 15 cms. cubes in Kg./Cmt. at Work test Min.
Concrete 28 days, conducted in accordance with I.S. 516-1959.
Preliminary test Min.
In all cases, the 28 days compressive strength specified in above be the criteria for acceptance or rejection of the concrete.
Where the strength of a concrete mix as indicated by tests, lies in between the strength of any two grades specified in the
above table, such concrete shall be classified in for purpose as concrete belonging to the lower of the grades between
which its strength lies.
3.0. Workmanship
3.1. The proportions for ingredients chosen shall be such that concrete has adequate workability
for conditions prevailing on the work question and can be property compacted with means available
except where ft can be shown to the satisfaction of the Engineer-in-charge, that supply of properly
graded aggregate of uniform quality can be maintained till the completion of work, grading of
aggregate shall be controlled by obtaining the coarse aggregates in different sizes and bending them
in the right proportions as required. Aggregates of different sizes shall be
stocked in separate stock piles. The required quantity of material shall be stock piled several hours,
preferably a day before use. The grading of coarse and fine aggregate shall be checked as frequently
as possible, the frequency for a given job being determined by Engineer-in-charge to ensure that the
suppliers are maintaining the uniform grading as approved for samples used in the preliminary tests..
3.2. In proportioning concrete, the quantity of both cement and aggregate shall be determined by
weight. Where the weight of cement is determined by accepting the maker's weight per bag, a
reasonable number of bags shall be weighted separately to check the net weight. Where cement is
weighted form bulk stocks at site and not by bags, it shall be weighed separately from the aggregate.
Water, shall either be measured by volume in calibrated tanks or weighed. All measuring equipment
shall be maintained in clean, and serviceable condition. Their accuracy shall be periodically checked.
3.3. It is most important to keep the specified water cement ratio constant and at its correct value.
To this end, moisture content in both fine and coarse aggregates shall be determined by the Engineer-
in-charge according to the weather conditions. The amount of mixing water shall then be adjusted to
compensate for variations in the moisture content. For the determination of moisture content in the
aggregates. I.S. 2386 (Part-Ill) shall be referred to. Suitable adjustments shah also be made in the
weights of aggregates due to variation in their moisture content. Minimum quantity of cement to be
used in controlled concrete shall not be less than 220 kg./M-3 in plain concrete and not less than
kg/M-3 in reinforced concrete.
4.0. Mode of measurement & payment
4.1. The relevant specifications of item No.5.4.1 shall be followed, except that the controlled
concrete R.C.C. work as specified in item shall be measured under this item. The rate excludes cost of
Providing laying controlled cement concrete M-250 work with curing complete including
the cost of form work and excluding the rate of reinforcment for reinforced concrete work
in.For (D)Columns,Pillars posts and struts, etc complete at all floor level.
The item shall be executed as per the relevant specifications & mode of measurement of above item
Providing and laying controlled cement concrete M.250 and curing complete excluding the
cost of formwork and reinforcement for reinforced concrete work in (C) Beams at all floor
The item shall be executed as per the relevant specifications & mode of measurement of above item
Providing and laying controlled cement concrete M.250 and curing complete excluding the
cost of formwork and reinforcement for reinforced concrete work in (C) slab at all floor
The item shall be executed as per the relevant specifications & mode of measurement of above item
Providing and laying controlled cement concrete M.250 and curing complete excluding the
cost of formwork and reinforcement for reinforced concrete work in (C) lintel & chajja at
all floor level
The item shall be executed as per the relevant specifications & mode of measurement of above item
Providing and laying controlled cement concrete M.250 and curing complete excluding the
cost of formwork and reinforcement for reinforced concrete work in (B) Walls at all floor
The item shall be executed as per the relevant specifications & mode of measurement of above item
Providing formwork of ordinary timber planking so as to give a rough finish including
centering shuttering strutting and propping etc. Height of propping and centering below
supporting floor to ceiling not exceeding 4 M. and removal of the same for in situ reinforced
concrete and plain concrete work in. (A) Foundations Footings Bases of Columns etc. and
1.1. The shuttering to be provided shall be of ordinary timber plank and shall conform to M-26.
1.2. The dimensions of scantlings and battens shall conform to the design. The strength of the
wood shall not be less than that assumed in the design.
2.0. Workmanship
2.1. The form work shall conform to the shape lines and dimensions as shown on the plans and be
constructed as to remain sufficiently rigid during the placing and compacting of the concrete.
Adequate arrangements shall be made by the contractor toe safe-guard against any settlement of the
form-work during the course of concreting and after concreting. The form work of shuttering,
centering, scaffolding, bracing etc. shall be as per design.
2.2. Clearing and Treatment of forms:
2.2.1. All rubbish, particularly chipping shaving and saw dust shall be removed from the interior of
before the concrete work is placed and the-form in contact with concrete shall be cleaned and
wetted or treated. The surface shall be then coated with soap solution applied before concreting is
solution for the purpose shaft prepared by dissolving yellow soap in water to get consistency of paint.
Alternatively a coat of raw linseed oil shall be applied after thoroughly cleaning the surface. Care
that the coating does not get on construction joint surface and reinforced bars.
2.3. Stripping time:
2.3.1. In normal circumstances and where ordinary cement is used forms may be struck after expire
of following periods.
(a) Sides of walls columns and vertical faces of
beams…………………………………………………24 to 48 hours.
(b) Beam soffits, (props, left
(c) Removal of props slabs:
(i) Slabs spanning up to 4.5.
(ii) Spanning over
(d) Removal of props t beams and Arches:
(i) Spanning up to
(ii) Spanning over
2.4. Procedure when removing the form work:
2.4.1. All form work shall be removed without such shock or vibrations as would damage the
reinforced concrete surface. Before the soffits form work and struts are removed, the soffits and the
concrete surface shall be exposed where necessary in order to ascertain that the concrete has
sufficiently hardened
2.5. Centering:
2.5.1. The centering to be provided shall be got approved. It shall be sufficiently strong to ensure
absolute safety of the form work and concrete work before, during and after pouring concrete. Watch
should be kept to see that behavior or centering and form work is satisfactory during concreting.
Erection should also he such that it would allow removal of forms in proper sequence without
damaging either the concrete or the forms to be removed.
2.5.2. The props of centering shall be provided on firm foundation or base of sufficient strength to
carry the loads without any settlement.
2.5.3. The centering and form work shall, be inspected and approved by the Engineer-in-charge
before concreting. But this will not relieve the contractor of his responsibility for strength,-adequacy
and safety of form work and centering. If there is a failure of form work or centering, contractor shall
be responsible for the damages to property.
2.6. Scaffolding:
2.6.1. All scaffolding, hoisting arrangements and ladders etc., required for the facilitating of
conceding shall be provided and removed on completion of work by contractor at his own expense.
The scaffolding, hoisting arrangements and ladders etc. shall be strong enough to with sand all live,
dead and impact loads expected to act and shall be subject to the approval of the Engineer-in-charge.
However contractor shall be solely responsible for the safety of the scaffolding, hoisting arrangement,
ladders, work and workman etc. 2.6.2. The scaffolding, hoisting arrangements and ladder shall allow
easy approach to the work spot and afford easy inspection.
2.6.3. The rate is applicable to all condition of working and height up to 4 mts. The rate shall include
the cost of materials and labour for various operations involved such as:
(a) Splayed edges, notching, allowance for overlaps and passing at angles, battens centering,
shuttering propping, bolting, wedging easing, striking and removal.
(b) Filleting to form stop chamfered edges or splayed external angles not exceeding 20 mm:
width to beams, columns and the like.
(c) Temporary openings in the forms for pouring concrete, if required removing rubbish etc.
(d) Dressing with oil to prevent adhesion of concrete with shuttering and.
(e) Raking or circular cutting.
2.7.1. Before re-use, all from shall be inspected by Engineer-in-charge and their suitability
ascertained. The forms shall be scarred, cleaned and joints are gone over, repaired where required.
Inside surface shall be retreated to prevent adhesion of concrete.
3.0. Mode of Measurements & Payment
3.1. From work shall be measured as the area in square meters to shuttering in contract with
concrete except in the case of inclined member and portion of curved profile and upper side in which
case on area of underside shall be measured for payment.
3.4. From work to secondary beams shall be measured up to the sides of main beams but no
deduction shall be made form the form work of the main beam at the inter section point. No
deduction shall be made form the form work of a column at inter section of beams.
3.5. The rate is for the completed item
3.6. The rate shall be for a unit of one sq. meter.
Providing formwork of ordinary timber planking so as to give a rough finish including
centering shuttering strutting and propping etc. height of propping and centering below
supporting floor to ceiling not exceeding 4 M. and removal of the same for in situ reinforced
concrete and plain concrete work in. (G) Columns PillarsPosts and struts. (1) Square
Rectangular Polygonal in plan.
The item shall be executed as per the relevant specifications & mode of measurement of above item
Providing formwork of ordinary timber planking so as to give a rough finish including
centering shuttering strutting and propping etc. height of propping and centering below
supporting floor to ceiling not exceeding 4 M. and removal of the same for in situ reinforced
concrete and plain concrete work in. (H) (1) Sides and soffits of Beams Beam Haunchings
cantilevers Girders Bressumers and Lintels not exceeding 1 M. in Depth.
The item shall be executed as per the relevant specifications & mode of measurement of above item
Providing formwork of ordinary timber planking so as to give a rough finish including
centering shuttering strutting and propping etc. height of propping and centering below
supporting floor to ceiling not exceeding 4 M. and removal of the same for in situ reinforced
concrete and plain concrete work in (B)Flat surfaces such as soffits of supspened floors slabs
Landings and the like. (1) Floors etc. up to 200 mm in thickness.
The item shall be executed as per the relevant specifications & mode of measurement of above item
Providing formwork of ordinary timber planking so as to give a rough finish including
centering shuttering strutting and propping etc. height of propping and centering below
supporting floor to ceiling not exceeding 4 M. and removal of the same for in situ reinforced
concrete and plain concrete work in. (L) Chullah Hoods, weather shades Chhajjas Corbels
etc. including edges.
The item shall be executed as per the relevant specifications & mode of measurement of above item
Providing formwork of ordinary timber planking so as to give a rough finish including
centering shuttering strutting and propping etc. height of propping and centering below
supporting floor to ceiling not exceeding 4 M. and removal of the same for in situ reinforced
concrete and plain concrete work in. (C) Vertical surface such as walls (any thickness)
partitions and the like including attached buttresses & string course & the like.
The item shall be executed as per the relevant specifications & mode of measurement of above item
Providing formwork of ordinary timber planking so as to give a rough finish including
centering shuttering strutting and propping etc. height of propping and centering below
supporting floor to ceiling not exceeding 4 M. and removal of the same for in situ reinforced
concrete and plain concrete work in. (M) Staircase with sloping or stepped soffits including
risers and stringers excluding landing.
The item shall be executed as per the relevant specifications & mode of measurement of above item
Providing TMT Bar FE 500D reinforcement for R.C.C. work including bending, binding and
placing in position complete upto floor two level. (For all Floors)
This work shall consist of furnishing and placing coated, T.M.T. or high strength deformed
reinforcement, bars (intentioned) of the shape and dimensions shown on the drawings and
conforming to these Specifications or as approved by the Engineer in charge. The T.M.T. FE-500 bar
shall be TATA, JINDAL,JSW brand as directed by Engineer-in-charge.
2.1. TMT Bars Reinforcements may be either TMT/medium tensile steel or high strength deformed
2.2. TMT bars reinforcement for RCC work shall conform to IS 1786 FE-500 and shall be of tested
quality. It shall also comply with relevant part of IS 456-1966
2.3. All reinforcement shall be clean and free from dirt, paint, grease or oil, oil scale or loose or thick
rust at the time of placing
2.4. All steel shall be procured form original producers no re-rolled steel shall be incorporated in the
2.5. Only new steel shall be delivered to the site every bar shall be inspected before placing to its
position and defective brittle or burnt bar shall be discarded cracked ends of bars shall be discarded
3.1. Distance between bars shall be as specified in drawings and as directed by the Engineer in
Charge. All bars shall be placed at an accurate distance from each other and shall be bind tightly to
maintain the desired pitch Suitable means shall be provided for holding bars securely in position
4.0. Binding wire
4.1. Mild steel binding wire shall be of 1.63 mm or 1.22 mm (16 to 18 gauge diameter and shall
conform IS 280-1972
4.2. The use of black wire will be permitted for binding reinforcement bars. It shall be free form free
from dirt, paint, grease or oil, oil scale or loose or thick rust and any other undesirable coating which
may prevent adhesion of cement mortar at the time of binding
4.3. Only new binding wire shall be delivered to the site all binding wire shall be inspected before
binding to its position and defective brittle, rusted, used wire, shall be discarded
5.0. PROTECTION OF REINFORCEMENT
5.1. Uncoated reinforcing steel shall be protected from rusting or chloride contamination.
Reinforcements shall be free from rust, mortar, loose mill scale, grease, oil or paints. This may be
ensured either by using reinforcement fresh from the factory or thoroughly cleaning all reinforcement
to remove rust using any suitable method such as sand blasting, mechanical wire brushing, etc. as
directed by the Engineer. Reinforcements shall be stored on bricks, racks or platforms and above the
ground in a clean and dry condition and shall be suitably marked to facilitate inspection and
identification.
5.2. Portions of uncoated reinforcing steel and dowels projecting from concrete shall be protected
within one week after initial placing of concrete with a brush coat of neat cement mixed with water to
a consistency, of thick paint. This coating shall be removed by lightly tapping with a hammer or other
tool not more than one week before placing of the adjacent pour of concrete. Coated reinforcing steel
shall be protected against damage to the coating. If the coating on the bars is damaged during
transportation or handling and cannot be repaired, the same shall be rejected.
6.0. Workmanship
6.1. The work shall consist of furnishing and placing reinforcement to the shape and dimensions
shown as on the drawings or as directed by The Engineer in charge.
6.2. Reinforcing steel shall conform accurate to the dimensions given in the bar bending schedules
shown on relevant drawing
7.0. BENDING OF REINFORCEMENT
7.1. Bar bend g schedule shall be furnished by the Contractor and got approved by the Engineer
before start of work.
7.2. Reinforcing steel shall conform to the dimensions and shapes given in the approved bar bending
7.3. Bars shall be bent cold to the specified shape and dimensions or directed by the Engineer using a
proper bar bender operated by hand power to obtain the correct radius of bends and shape. Bars, shall
not be bent or straightened in a manner that will damage parent material or the coating bars bent
during transport or handling shall, be straightened before being used on work and shall not be heated
to facilitate straightening.
8.0. PLACING OF REINFORCEMENT
8.1. The reinforcement cage should generally be fabricated in the yard at ground level, and then
shifted and placed in position. The reinforcement shall be placed strictly, in accordance with the
drawings and shall be assembled in position, only when structure is otherwise ready for placing of
concrete. Prolonged time gap, between assembling of reinforcements and casting of concrete, which
may result in rust formation on the surface, shall not be permitted.
8.2. Reinforcement bars shall be placed accurately in position as shown on the drawings. The bars,
crossing one another shall be tied together at every intersection with binding wire (annealed),
conforming to IS: 280 to make the skeleton of the reinforcement rigid such that the reinforcement
does not get displaced during placing of concrete, or any other operation. The diameter of binding
wire shall not be less than 1 mm.
8.3. Bars shall be kept in. position usually by the following methods:
In case of beam an slab construction, industrially produced polymer cover blocks of thickness equal
to the specified cover shall be placed between the bars and formwork subject to satisfactory evidence
that the polymer composition is not harmful to concrete and reinforcement. Cover blocks made of
concrete may be permitted by the Engineer, provided they have the same strength and specification as
those of the member.
8.4. In case of dowels for Columns and walls the vertical reinforcement shall be kept in position by
means of timber templates with slots in them accurately, or with cover blocks tied to the
Reinforcement Timber templates shall be removed after the concreting has progressed up to a level
just below their location.
8.5. Layers of reinforcements shall be separated by spacer bars at approximately One meter intervals.
The minimum diameter of spacer bars shall be 12 mm or: equal to maximum size of main
reinforcement or maximum size of coarse aggregate, whichever is greater. Horizontal reinforcement
shall not be, allowed to sag between supports.
8.6. Necessary stays, blocks, metal chairs, spacers, metal hangers supporting wires etc, or other
subsidiary, reinforcement shall be provided to fix the reinforcements firmly in its correct position.
8.7. Use of pebbles, broken stone, metal pipe, brick, mortar or wooden blocks etc as devices for
positioning reinforcement shall not be permitted.
8.8. Placing and fixing of reinforcement shall be inspected and approved by the Engineer before
concrete is deposited.
9.1. All reinforcement shall be furnished in full lengths as indicated on the drawing. No splicing of
bars, except where shown on the drawing; will be permitted without approval of the Engineer. The
lengths of the splice shall be as indicated on drawing or as approved by the Engineer. Where
practicable, overlapping bars shall not touch each other, and shall be kept apart by 25mm or 1:1.1/4
times the maximum size of coarse aggregate, whichever is greater; if this is not feasible, overlapping
bars shall be bound with annealed steel binding wire, not less than 1 mm diameter and twisted tight in
such a manner as to maintain minimum clear cover to the reinforcement from the concrete surface.
Lapped splices shall be staggered or located at points, along the span where stresses are low.
10.1 Splicing by welding of reinforcement will be permitted only if detailed on the drawing or
approved by the Engineer. Weld shall develop an ultimate strength equal to or greater than that of the
bars connected.
10.2. While welding may be permitted for TMT .reinforcing bars conforming to IS: 432, welding of
deformed bars conforming to IS: 1786 shall in general be prohibited. Welding may be permitted in
case of bars of other than S 240 grade including special. Welding grade of S 500 grade bars
conforming to IS: 1786, for which necessary chemical analysis has been secured and the carbon
equivalent (CE) calculated from the chemical composition using the formula: CE = C + Mn + Cr +
Mg + V + Ni + Cu 6 5 15 are 0.4 or less.
10.3. The method of welding shall conform to IS: 2751 and IS: 9417 and to any supplemental
specifications to the satisfaction of the Engineer
10.4. Bars shall be bent cold to the specified shape and dimensions or as directed by Engineer in
charge using the proper bender tool, operated by hand or power to attain proper radius of bends. Bars
shall not be bending or straightened in a manner that will injure the material. Bars bent during
transport or handling shall be straightened before being used in the work. Bars shall not be heated to
facilitate bending.
10.5. Unless otherwise specified a ‘U’ type hook at the end of each bar shall invariably be provided to
main reinforcement. The radius of the bane shall not be less then twice the diameter of the round bar
and the length of the straight part of the bar beyond the end of the curve shall be at least four times of
the diameter of the round bar. In case of bars which are not round and in case of deformed bars, the
diameter shall be taken as the diameter of circle having an equivalent effective area the hooks shall be
suitably encased to prevent any spiting of the concrete.
10.6. All reinforcement bars shall be accurately placed in exact position shown on the drawings and
shall be securely held in position during placing of concrete by annealed binding wire not less than
mm in size and by using say blocks or metal chairs spacers, metal hangers, supporting wires or other
approved devices at sufficiently close intervals, Bars shall not be allowed to sag between supports not
displaced during concreting or any other operations of the work All devices used for positioning shall
be of not corrodible material wooden and metal supports shall not extended to the surface of the
concrete, except where shown in drawings. Placing bars on layers of freshly laid concrete as the work
progresses for adjusting bar spacing shall not be allowed. Pieces of broken stone or brick and wooden
blocs shall not be used Layers of bars shall be separated by spacer bars pre-cast mortar blocks or
other approved devices. Reinforcement after bending placed in position shall be maintained in a clean
condition until completely embedded in concrete, Special care shall be exercised to prevent any
displacement of reinforcement in concrete already placed. To prevent reinforcement form corrosion,
concrete cover shall be provided as indicated on drawings. All bars protruding from concrete and to
which other bars are to be sliced and which are likely to be exposed for a period exceeding 10 days
shall be protected by a thick coat of neat cement grout
10.7. Bars crossing each other where required shall be secured by binding wire (annealed) of size not
less than 1 mm in such a manner that they do not slip over at the time of fixing and concreting.
10.7. As far possible bars of full length shall be used In case this is not possible, overlapping of bars
shall be done as directed by the Engineer in charge When practicable overlapping bars shall not touch
each other, but be kept apart by 25 mm Where no feasible overlapping bars shall be bound with
annealed wires not less than 1 mm thick twisted tight The overlaps shall be staggered for different
bars and located at points along the span where neither sheer not bending moments is maximum.
10.8. Whenever indicated on drawing or desired the Engineer in charge bars shall be joined by
coupling which shall have a cross section sufficient to transmit the full stresses of bars The end of the
bars that are joined by coupling shall be upset for sufficient length so that the effective cross section
at the base of threads is not less than the normal cross section of the bar. Threads shall be standards
threads Steel for coupling shall conform to IS
10.8. When permitted or specified on the drawings joints of reinforcement bars shall butt-welded so
as to transmit their full stresses Welded joints shall preferably be located at points when steel will not
be subject to more than 75 percent of the maximum permissible stresses and welds so staggered that
at any one section not more than 20 percent of the rods are welded Only electric are welding using a
process which excludes air form the molten metal and conforms to any or other special provisions for
the work shall be accepted Suitable means shall be provided for holding bars securely in position
during welding It shall be ensured that no voids are left in welding and when welding is done in two
or three stages previous surface shall be cleaned properly Ends of bars shall be cleaned of all loose
scale rust stages paint and other foreign matter before welding Only competent welders shall be
employed on the work. The M S electrodes used for welding shall conform IS 814 Welded pieces of
reinforcement shall be tested. Specimen shall be taken form the actual site and their number shall
frequency to test shall be as directed by the Engineer in charge
11.0 MODE OF MEASUREMENTS & PAYMENT
11.1. For the purpose of payment the bar shall be measured correct up to 10 mm length and weight
payable works out at the rate specified below
6. mm /Rmt. 13. mm /Rmt.
14 /Rmt. 32 /Rmt.
mm /Rmt. mm /Rmt.
mm /Rmt. mm /Rmt.
11.1. Reinforcement shall be measured in length including overlaps, separately for different diameters
as actually used in the work. Where welding or coupling is resorted to, in place lap joints, such joints
shall be measured for payment as equivalent length of overlap as per design requirement. From the
length so measured, the weight of reinforcement shall be calculated in Kg. on the same basis of as per
table given above. Length shall include hooks at the ends. Wastage and annealed steel wire for
binding shall not be measured and the cost of these items shall be deemed to be included in the rate
for reinforcement.
11.2. The rate for reinforcement includes cost of steel binding wires, cutting, bending, placing in
position, binding and fixing in position as shown on the drawings and as directed. It shall also include
all devices for keeping reinforcement in approved position, cost of joining as per approved method
and all wastage and spacer bars.
11.4. The contract rate shall be for a unit of one kilogram for completed item as directed.
The payment will be made on one kilogram basis of the finished work.
Brick work using Common burnt clay building bricks having crushing strength not less than
35 kg./sq.cm. in foundation and plinth in cement mortar 1: 5 (1 cement : 5 fine sand) (B )
Cement mortar of proportion 1:5 shall conform to M-11. Conventional bricks shall conform to M-15.
2.0. Workmanship
2.1. Proportion:
2.1.1. The proportion of the cement mortar shall be 1:5 (1 cement: 5 fine sand) by volume.
2.2. Wetting of bricks:
2.2.1. The bricks required for masonry shall be thoroughly wetted with clean water for about two
hours before use or as directed. The cessation of bubbles, when the bricks are wetted with water is as
indication of through wetting of bricks.
2.3.1. Bricks shall be laid in English bond unless directed otherwise. Half or cut bricks shall not be
used except when necessary to complete to bond; closures in such case shall be cut to required size
and used near the ends of walls.
2.3.2. A layer of mortar shall be spread on full width for suitable length of the lower course. Each
brick shall first be property bedded and set home by gently tapping with handle of trowel or wooden
mallet. Its inside face shall be flushed with mortar before the next brick is laid and pressed against it.
On completion of course, the vertical joints shall be fully filled from the top with mortar.
2.3.3. The walls shall be taken up truly in plumb. All courses shall be laid truly horizontal and all
vertical joint shall be truly vertical. Vertical joints in alternate course shall generally be directly one
over the other. The thickness of brick course shall be kept uniform.
2.3.4. The brick shall be laid with frog up wards. A set of tools comprising of wooden straight edges,
man son's spirit level, square half meter rub, and pins, string and plumb shall be kept on the site of
work for frequent checking during the progress of work.
2.3.5. Both the faces of walls of thickness greater than 23 cms. shall be kept in proper place. All the
connected brick work shall be kept not more than one meter over the rest of the work. Where this is
not possible, the work shall be raked back according to bond (and not left toothed) at an angle not
steeper than 45 degrees.
2.3.6. All futures, pipes, outlets of water, hold fasts of doors and windows etc. which are required to
be built in wall shall be embedded in cement mortar
2.4.1. Bricks shall be so laid that all joints are quite flush with mortar. Thickness of joints shall not
exposed 12 mm. The face joints shall be raked out as directed by raking tools daily during the
progress of work, when the mortar is still green so as to provide key for plaster or pointing to done.
2.4.2. The face of brick shall be cleaned the very day on which the work is laid and all mortar
dropping removed.
2.5.1. Green work shall be protected from rain suitably. Masonry work shall be kept moist on all the
faces for a period of seven days. The top of masonry work shall be kept well wetted at the close of the
2.6. Preparation of foundation bed:
2.6.1. If the foundation is to be laid directly on the excavated bed, the shall be leveled, cleared of all
loose materials, cleaned and wetted before stating masonry, If masonry is to be laid on concrete
footing, the top of concrete shall be cleaned and moistened. The contractor shall obtain the engineer's
approval for the foundation bed before foundation masonry is started. When pucca flooring is to be
provided flush with the top to plinth, the inside plinth offset shall be kept lower than the outside
plinth top by the thickness of the flooring.
3.0. Mode measurements & payment
3.1. The measurements of this item shall be taken for the brick masonry fully completed in
foundation up to plinth. The limiting dimensions not exceeding those shown on the plinths or as
directed shall be final. Battered tapered and curved portions shall be measured net.
3.2. No deduction shall be made from the quantity of brick work, for any extra payment made for
embedding in masonry or making holes in respect of following items:
(1) Ends of joists, beams, posts, girders, purlins, trusses, corbel, steps etc. where cross sectional
area does not exceed 500 Sq.Cm.
(2) Openings not exceeding 1000 Sq.Cm.
(3) Wall plates and bed plates, bearing of slabs, chajjas and the like whose thickness does not
exceed 10 Cms. and the bearing does not extend to the full thickness of wall.
(4) Drainage holes, and recesses for cement concrete blocks to embed hold fasts for doors,
(5) Iron fixtures, pipes up to 300 mm. dia hold fasts, and doors and windows built into masonry
and pipes etc. for concealed wiring.
(6) Forming chases of section not exceeding 350 -Sq. Cm. in masonry.
3.3. Apertures for fire places shall not be deducted nor shall be paid for separately.
3.4. The rate shall be for a unit of one cubic meter.
Brick work using Common burnt clay building bricks having crushing strength not less than
35 kg./sq.cm. above plinth level in cement mortar 1:6 (1 cement : 6 fine sand) (B )
Conventional upto floor two level
The item shall be executed as per the relevant specifications & mode of measurement of above item
Half brick masonry in common brunt clay building bricks having crushing strength not less
than 35 Kg/Sq.Cm. in Cement mortar 1:4 (1- Cement : 4 -coarse sand ) in foundation and
plinth (B) Conventional upto floor two level
Bricks shall conform to M-15. Water shall conform to M-1. Cement shall conform to M-3. Sand shall
conform to M-6. Cement mortar shall conform to M-11.
2.0. Workmanship
2.1. Proportion:
2.1.1. The proportion of the cement mortar shall be 1:3 (1 cement: 3 fine sand) by volume.
2.2. Wetting of bricks:
2.2.1. The bricks required for masonry shall be thoroughly wetted with clean water for about two
hours before use or as directed. The cessation of bubbles, when the bricks are wetted with water is as
indication of through wetting of bricks.
2.3.1. Bricks shall be laid in English bond unless directed otherwise. Half or cut bricks shall not be
used except when necessary to complete to bond; closures in such case shall be cut to required size
and used near the ends of walls.
2.3.2. A layer of mortar shall be spread on full width for suitable length of the lower course. Each
brick shall first be property bedded and set home by gently tapping with handle of trowel or wooden
mallet. Its inside face shall be flushed with mortar before the next brick is laid and pressed against it.
On completion of course, the vertical joints shall be fully filled from the top with mortar.
2.3.3. The walls shall be taken up truly in plumb. All courses shall be laid truly horizontal and all
vertical joint shall be truly vertical. Vertical joints in alternate course shall generally be directly one
over the other. The thickness of brick course shall be kept uniform.
2.3.4. The brick shall be laid with frog up wards. A set of tools comprising of wooden straight edges,
man son's spirit level, square half meter rub, and pins, string and plumb shall be kept on the site of
work for frequent checking during the progress of work.
2.3.5. Both the faces of walls of thickness greater than 23 cms. shall be kept in proper place. All the
connected brick work shall be kept not more than one meter over the rest of the work. Where this is
not possible, the work shall be raked back according to bond (and not left toothed) at an angle not
steeper than 45 degrees.
2.3.6. All futures, pipes, outlets of water, hold fasts of doors and windows etc. which are required to
be built in wall shall be embedded in cement mortar
2.4.1. Bricks shall be so laid that all joints are quite flush with mortar. Thickness of joints shall not
exposed 12 mm. The face joints shall be raked out as directed by raking tools daily during the
progress of work, when the mortar is still green so as to provide key for plaster or pointing to done.
2.4.2. The face of brick shall be cleaned the very day on which the work is laid and all mortar
dropping removed.
2.5.1. Green work shall be protected from rain suitably. Masonry work shall be kept moist on all the
faces for a period of seven days. The top of masonry work shall be kept well wetted at the close of the
2.6. Preparation of foundation bed:
2.6.1. If the foundation is to be laid directly on the excavated bed, the shall be leveled, cleared of all
loose materials, cleaned and wetted before stating masonry, If masonry is to be laid on concrete
footing, the top of concrete shall be cleaned and moistened. The contractor shall obtain the engineer's
approval for the foundation bed before foundation masonry is started. When pucca flooring is to be
provided flush with the top to plinth, the inside plinth offset shall be kept lower than the outside
plinth top by the thickness of the flooring.
2.2. Cement mortar used in masonry work shall be in proportion of 1 part of cement and 4 parts of
sand by volume.
2.3. AH bricks shall be laid stretcher wise, breaking joints with those in the upper and lower
courses. The wall shall be taken truly plumb. All courses shall be said truly horizontal and all vertical
joints shall be truly vertical. The bricks shall be laid with frogs upwards. A set of masons tools shall
be maintained on work as
required for frequent checking.
3.0. Mode of measurement and payment
3.1. The half brick masonry work in foundation and plinth shall be measured under this item the
limiting dimensions shall not exceed those shown in the plan or as directed. Any work done extra
over the specified dimensions shall be ignored.
3.2. No deduction shall be made from the quantity of brick work, for any extra payment made for
embedding in masonry or making holes in respect of following items:
(1) Ends of joists, beams, posts, girders, purlins, trusses, corbel, steps etc. where cross sectional
area does not exceed 500 Sq.Cm.
(2) Openings not exceeding 1000 Sq.Cm.
(3) Wall plates and bed plates, bearing of slabs, chajjas and the like whose thickness does not
exceed 10 Cms. and the bearing does not extend to the full thickness of wall.
(4) Drainage holes, and recesses for cement concrete blocks to embed hold fasts for doors,
(5) Iron fixtures, pipes up to 300 mm. dia hold fasts, and doors and windows built into masonry
and pipes etc. for concealed wiring.
(6) Forming chases of section not exceeding 350 -Sq. Cm. in masonry.
3.3. The rate shall be for a unit of one sq. meter.
Providing 10mm thick cement plaster in single coat on ceiling and finishing with a floating
coat of neat cement slurry. finished even and smooth including providing and mixing water
proofing materials in cement mortar in proportion recommended by the manufacturer.
(ii)Cement mortar 1:4 (1-cement :4-sand)
1.1. Water shall conform to M-1. The cement mortar of proportion 1:4 shall conform to M-13.
2.0. Workmanship
2.1. Scaffolding:
Wooden bullies, bamboos, planks, trestles and other scaffolding shall be sound. These shall be
properly examined before erection and use. Stage scaffolding shall be provided for ceiling plaster
which shall be independent of the walls.
2.2. Preparation of back-ground :
2.2.1. The surface shall be cleaned of all dust, loose mortar droppings, traces of algae, efflorescence
and other foreign matter by water or by brushing. Smooth surface shall be toughened by wire
brushing if it is not hard and by hacking if it is hard. In case of concrete surface, if a chemical
retarded has been applied to the form work, the surface shall be roughened by wire brushing and all
the resulting dust and loose particles cleaned off and care shall be taken that none of the readers if left
on the surface. Trimming of projections on brick/concrete surfaces where necessary shall be carried
out to get an even surface.
2.2.2. Raking of joints in case of masonry where necessary shall be allowed to dry out for sufficient
period before carrying out the plaster work.
2.2.3. The work shall not be soaked but only damped evenly before applying the plaster. If the
surface becomes dry, such area shall be moistened again.
2.2.4. For external plaster, the pestering operation shall be started from top floor and carried
downwards. For internal plaster, the plastering operations may be-started wherever the building frame
and cladding work are ready and the temporary supports of the ceiling resting on the wall of the floor
have been removed. Ceiling plaster shall be completed before starting plaster to walls.
2:3. Application of plaster:
2.3.1. The plaster about 15x15 cms. shall be first applied horizontally and vertically at not more than
2 meters intervals over the entire surface to serve as gauge. The surfaces of these gauges shall be truly
in plane of the finished plastered surface. The mortar shall then be applied in uniform surface slightly
more than the specified thickness, then brought to a true surface by working a wooden straight edge
reaching across the gauges with small upward and sideways movements at a time. Finally, the surface
shall be finished off true with a trowel or wooden float according as a smooth or a smooth or a sandy
granular texture is required Excessive troweling or overworking the float shall be avoided. All
corners, arises, angles and junctions shall be truly vertical or horizontal as the case may be and shall
be carefully finished. Hounding or chamfering, corners, arises junctions etc. shall be carried out with
proper templates to be size required.
2.3.2. Cement plaster shall be used within half an hour after addition of water. And mortar or plaster
which is partially set shall be rejected and removed forthwith from the site.
2.3.3. In suspending the work at the end of the day, the plaster shall be left out clean to the line both
horizontally and vertically, when recommencing the plaster, the edges of the old work shall be
scraped clean and wetted with cement putty before plaster is applied to the adjacent areas to enable
the two to properly join together. Plastering work shall be closed at the end of the day on the body of
the wall and nearer than 15 cm. to any corners or arises. It shall not be closed on the body of features
such as plaster bands and cornices not at the corners or arises. Horizontal joints in plaster work shall
not also occur on parapet tops and copings as these invariably lead to leakage. No portion of the
surface shall be left out initially to be packed up later on.
2.3.4. Each coat shall be kept damp continuously till the next coat is applied or for a minimum
period of 7 days. Moistening shall commence as soon as plaster is hardened sufficiently. Soaking of
walls shall be avoided and only as much water as can be readily absorbed shall be used, excessive
evaporation on the sunny or windward side of building in hot air or dry weather shall be prevented by
hanging matting or gunny bags oh the outside of the plaster and keeping them wet.
3.0. Mode of measurements & payment
3.1. The rate shall include the cost of all materials, labour and scaffolding etc. involved in the
operations described under workmanship.
3.2. All plastering shall be measured in square meters unless otherwise specified. Length breadth
or height shall be measured correct to a centimeter.
3.3. Thickness of the plaster shall be exclusive of he thickness of the key i.e. grooves or open
joints in brick work, stone work etc. or space between laths. Thickness of plaster shall be average
thickness with minimum 10 mm. at any point on this surface.
3.4. This item includes plastering up to floor two level.
3.5. The measurement of wall plastering shall be taken between the walls or partition (dimensions
before plastering being taken) for length and from the top of floor or skirting to ceiling for height.
Depth of cover of cornices if any shall be deducted.
3.6. Soffits of stairs shall be measured as plastering on ceilings, following soffits shall be
measured separately.
3.7. For jambs, soffits, sills etc. for openings not exceeding 0.5 sq. met each in area for ends of
joints beams, posts, girders, steps etc. not exceeding 0.5 sq. mt each in area and for openings
exceeding 0.5. sq. mt and not exceeding 3.00 sq. mt. in each area deductions and additions shall be
made in the following manners.
(a) No deductions shall be made for ends of joints, beams, posts etc. and openings not exceeding
0.5 sq. mt each and no addition shall be made for reveals, jambs, soffits, sils etc. of these openings,
for finish to plaster around ends of joints, beams posts etc.
(b) Deduction for openings exceeding 0.5 sq. mt but not exceeding 3 sq.mt. each shall be made as
follows and no addition shall be made for ravels, jambs, soffits, sills etc. of these openings, (i) When
both faces of all wall are plastered with same plaster, deduction shall be made for one face only, (ii)
When two faces of wall are plastered with different types of plasters or if one face is plastered and the
other pointed, deductions shall be made from the plaster or pointing on the side of frame for door,
window etc. on which width of reveals is less than that on the other side but no deductions shall be
made on the other side. Where width of reveals on both faces of all are equal, deductions of 50% of
area of opening on each face shall be made from areas of plaster and / or pointing as the case may be.
3.8. For openings having door frames equal to or projecting beyond the thickness of wall, full
deduction for opening shall be made from each plastered face of the wall.
3.9. tn case of openings of area above 3 sq. mt. each, deduction shall be made for openings but
jambs, soffits sand sills shall be measured.
3.10. The rate shall be for a unit of One sq. meter.
Providing 15 mm thick cement plaster in single coat on brick/concrete wall for interior
plastering upto floor two level finished even and smooth in [I] Cement mortar 1:3 (1 cement :
3 fine sand) including for finishing with a floating coat of neat cement slurry etc complete at
all floor level.
1.1. Water shall conform to M-1. The cement mortar of proportion 1:4 shall conform to M-13.
2.0. Workmanship
2.1. Scaffolding:
Wooden bullies, bamboos, planks, trestles and other scaffolding shall be sound. These shall be
properly examined before erection and use. Stage scaffolding shall be provided for ceiling plaster
which shall be independent of the walls.
2.2. Preparation of back-ground :
2.2.1. The surface shall be cleaned of all dust, loose mortar droppings, traces of algae, efflorescence
and other foreign matter by water or by brushing. Smooth surface shall be toughened by wire
brushing if it is not hard and by hacking if it is hard. In case of concrete surface, if a chemical
retarded has been applied to the form work, the surface shall be roughened by wire brushing and all
the resulting dust and loose particles cleaned off and care shall be taken that none of the readers if left
on the surface. Trimming of projections on brick/concrete surfaces where necessary shall be carried
out to get an even surface.
2.2.2. Raking of joints in case of masonry where necessary shall be allowed to dry out for sufficient
period before carrying out the plaster work.
2.2.3. The work shall not be soaked but only damped evenly before applying the plaster. If the
surface becomes dry, such area shall be moistened again.
2.2.4. For external plaster, the pestering operation shall be started from top floor and carried
downwards. For internal plaster, the plastering operations may be-started wherever the building frame
and cladding work are ready and the temporary supports of the ceiling resting on the wall of the floor
have been removed. Ceiling plaster shall be completed before starting plaster to walls.
2:3. Application of plaster:
2.3.1. The plaster about 15x15 cms. shall be first applied horizontally and vertically at not more than
2 meters intervals over the entire surface to serve as gauge. The surfaces of these gauges shall be truly
in plane of the finished plastered surface. The mortar shall then be applied in uniform surface slightly
more than the specified thickness, then brought to a true surface by working a wooden straight edge
reaching across the gauges with small upward and sideways movements at a time. Finally, the surface
shall be finished off true with a trowel or wooden float according as a smooth or a smooth or a sandy
granular texture is required Excessive troweling or overworking the float shall be avoided. All
corners, arises, angles and junctions shall be truly vertical or horizontal as the case may be and shall
be carefully finished. Hounding or chamfering, corners, arises junctions etc. shall be carried out with
proper templates to be size required.
2.3.2. Cement plaster shall be used within half an hour after addition of water. And mortar or plaster
which is partially set shall be rejected and removed forthwith from the site.
2.3.3. In suspending the work at the end of the day, the plaster shall be left out clean to the line both
horizontally and vertically, when recommencing the plaster, the edges of the old work shall be
scraped clean and wetted with cement putty before plaster is applied to the adjacent areas to enable
the two to properly join together. Plastering work shall be closed at the end of the day on the body of
the wall and nearer than 15 cm. to any corners or arises. It shall not be closed on the body of features
such as plaster bands and cornices not at the corners or arises. Horizontal joints in plaster work shall
not also occur on parapet tops and copings as these invariably lead to leakage. No portion of the
surface shall be left out initially to be packed up later on.
2.3.4. Each coat shall be kept damp continuously till the next coat is applied or for a minimum
period of 7 days. Moistening shall commence as soon as plaster is hardened sufficiently. Soaking of
walls shall be avoided and only as much water as can be readily absorbed shall be used, excessive
evaporation on the sunny or windward side of building in hot air or dry weather shall be prevented by
hanging matting or gunny bags oh the outside of the plaster and keeping them wet.
3.0. Mode of measurements & payment
3.1. The rate shall include the cost of all materials, labour and scaffolding etc. involved in the
operations described under workmanship.
3.2. All plastering shall be measured in square meters unless otherwise specified. Length breadth
or height shall be measured correct to a centimeter.
3.3. Thickness of the plaster shall be exclusive of hethickness of the key i.e. grooves or open joints
in brick work, stone work etc. or space between laths. Thickness of plaster shall be average thickness
with minimum 10 mm. at any point on this surface.
3.4. This item includes plastering up to floor two level.
3.5. The measurement of wall plastering shall be taken between the walls or partition (dimensions
before plastering being taken) for length and from the top of floor or skirting to ceiling for height.
Depth of cover of cornices if any shall be deducted.
3.6. Soffits of stairs shall be measured as plastering on ceilings, following soffits shall be
measured separately.
3.7. For jambs, soffits, sills etc. for openings not exceeding 0.5 sq. met each in area for ends of
joints beams, posts, girders, steps etc. not exceeding 0.5 sq. mt each in area and for openings
exceeding 0.5. sq. mt and not exceeding 3.00 sq. mt. in each area deductions and additions shall be
made in the following manners.
(a) No deductions shall be made for ends of joints, beams, posts etc. and openings not exceeding
0.5 sq. mt each and no addition shall be made for reveals, jambs, soffits, sils etc. of these openings,
for finish to plaster around ends of joints, beams posts etc.
(b) Deduction for openings exceeding 0.5 sq. mt but not exceeding 3 sq.mt. each shall be made as
follows and no addition shall be made for ravels, jambs, soffits, sills etc. of these openings, (i) When
both faces of all wall are plastered with same plaster, deduction shall be made for one face only, (ii)
When two faces of wall are plastered with different types of plasters or if one face is plastered and the
other pointed, deductions shall be made from the plaster or pointing on the side of frame for door,
window etc. on which width of reveals is less than that on the other side but no deductions shall be
made on the other side. Where width of reveals on both faces of all are equal, deductions of 50% of
area of opening on each face shall be made from areas of plaster and / or pointing as the case may be.
3.8. For openings having door frames equal to or projecting beyond the thickness of wall, full
deduction for opening shall be made from each plastered face of the wall.
3.9. tn case of openings of area above 3 sq. mt. each, deduction shall be made for openings but
jambs, soffits sand sills shall be measured.
3.10. The rate shall be for a unit of One sq. meter.
Providing 20 mm thick double coat mala cement plaster on interior brick / concrete work for
plastering comprising of base coat of 12 mm thick cement plaster in cement mortar (1
Cement : 4 coarse sand) in rough finishing and 8 mm thick top coat of cement mortar 1:2 (1
Cement : 2 Coarse sand) finished with trovel including scaffolding curing etc. complete.
1.1. Water shall conform to M-1. The cement mortar of proportion 1:4 shall conform to M-13.
2.0. Workmanship
2.1. Scaffolding:
Wooden bullies, bamboos, planks, trestles and other scaffolding shall be sound. These shall be
properly examined before erection and use. Stage scaffolding shall be provided for ceiling plaster
which shall be independent of the walls.
2.2. Preparation of back-ground :
2.2.1. The surface shall be cleaned of all dust, loose mortar droppings, traces of algae, efflorescence
and other foreign matter by water or by brushing. Smooth surface shall be toughened by wire
brushing if it is not hard and by hacking if it is hard. In case of concrete surface, if a chemical
retarded has been applied to the form work, the surface shall be roughened by wire brushing and all
the resulting dust and loose particles cleaned off and care shall be taken that none of the readers if left
on the surface. Trimming of projections on brick/concrete surfaces where necessary shall be carried
out to get an even surface.
2.2.2. Raking of joints in case of masonry where necessary shall be allowed to dry out for sufficient
period before carrying out the plaster work.
2.2.3. The work shall not be soaked but only damped evenly before applying the plaster. If the
surface becomes dry, such area shall be moistened again.
2.2.4. For external plaster, the pestering operation shall be started from top floor and carried
downwards. For internal plaster, the plastering operations may be-started wherever the building frame
and cladding work are ready and the temporary supports of the ceiling resting on the wall of the floor
have been removed. Ceiling plaster shall be completed before starting plaster to walls.
2:3. Application of plaster:
2.3.1. The plaster about 15x15 cms. shall be first applied horizontally and vertically at not more than
2 meters intervals over the entire surface to serve as gauge. The surfaces of these gauges shall be truly
in plane of the finished plastered surface. The mortar shall then be applied in uniform surface slightly
more than the specified thickness, then brought to a true surface by working a wooden straight edge
reaching across the gauges with small upward and sideways movements at a time. Finally, the surface
shall be finished off true with a trowel or wooden float according as a smooth or a smooth or a sandy
granular texture is required Excessive troweling or overworking the float shall be avoided. All
corners, arises, angles and junctions shall be truly vertical or horizontal as the case may be and shall
be carefully finished. Hounding or chamfering, corners, arises junctions etc. shall be carried out with
proper templates to be size required.
2.3.2. Cement plaster shall be used within half an hour after addition of water. And mortar or plaster
which is partially set shall be rejected and removed forthwith from the site.
2.3.3. In suspending the work at the end of the day, the plaster shall be left out clean to the line both
horizontally and vertically, when recommencing the plaster, the edges of the old work shall be
scraped clean and wetted with cement putty before plaster is applied to the adjacent areas to enable
the two to properly join together. Plastering work shall be closed at the end of the day on the body of
the wall and nearer than 15 cm. to any corners or arises. It shall not be closed on the body of features
such as plaster bands and cornices not at the corners or arises. Horizontal joints in plaster work shall
not also occur on parapet tops and copings as these invariably lead to leakage. No portion of the
surface shall be left out initially to be packed up later on.
2.3.4. Each coat shall be kept damp continuously till the next coat is applied or for a minimum
period of 7 days. Moistening shall commence as soon as plaster is hardened sufficiently. Soaking of
walls shall be avoided and only as much water as can be readily absorbed shall be used, excessive
evaporation on the sunny or windward side of building in hot air or dry weather shall be prevented by
hanging matting or gunny bags oh the outside of the plaster and keeping them wet.
3.0. Mode of measurements & payment
3.1. The rate shall include the cost of all materials, labour and scaffolding etc. involved in the
operations described under workmanship.
3.2. All plastering shall be measured in square meters unless otherwise specified. Length breadth
or height shall be measured correct to a centimeter.
3.5. The measurement of wall plastering shall be taken between the walls or partition (dimensions
before plastering being taken) for length and from the top of floor or skirting to ceiling for height.
Depth of cover of cornices if any shall be deducted.
3.6. Soffits of stairs shall be measured as plastering on ceilings, following soffits shall be
measured separately.
3.7. For jambs, soffits, sills etc. for openings not exceeding 0.5 sq. met each in area for ends of
joints beams, posts, girders, steps etc. not exceeding 0.5 sq. mt each in area and for openings
exceeding 0.5. sq. mt and not exceeding 3.00 sq. mt. in each area deductions and additions shall be
made in the following manners.
(a) No deductions shall be made for ends of joints, beams, posts etc. and openings not exceeding
0.5 sq. mt each and no addition shall be made for reveals, jambs, soffits, sils etc. of these openings,
for finish to plaster around ends of joints, beams posts etc.
(b) Deduction for openings exceeding 0.5 sq. mt but not exceeding 3 sq.mt. each shall be made as
follows and no addition shall be made for ravels, jambs, soffits, sills etc. of these openings, (i) When
both faces of all wall are plastered with same plaster, deduction shall be made for one face only, (ii)
When two faces of wall are plastered with different types of plasters or if one face is plastered and the
other pointed, deductions shall be made from the plaster or pointing on the side of frame for door,
window etc. on which width of reveals is less than that on the other side but no deductions shall be
made on the other side. Where width of reveals on both faces of all are equal, deductions of 50% of
area of opening on each face shall be made from areas of plaster and / or pointing as the case may be.
3.8. For openings having door frames equal to or projecting beyond the thickness of wall, full
deduction for opening shall be made from each plastered face of the wall.
3.9. tn case of openings of area above 3 sq. mt. each, deduction shall be made for openings but
jambs, soffits sand sills shall be measured.
3.10. The rate shall be for a unit of One sq. meter.
Providing cement vata (10cm. x 10 cm. size) quarter round in cement mortar 1:1 including
neat cement finishing, watering etc. complete.
1.1. Water shall conform to M-1 .Cement mortar shall conform to M-11.
2.0. Workmanship
2.1. The work of cement vata of 10 cms x 10 cms. size shall be earned out at Functions of parapets
and terraces as directed. The vata shall he finished in quarter round shape. The work shall be earned
out in the nest workman like manner. The inter portion of rain water pipe shall be rounded off
properly during constructing the vata. The work shall be cured for 7 days.
3.0. Mode of measurements and payment
3.1. The work shall be measured for finished item in running meter.
3.2. The rate shall be for a One running meter.
Providing throating or plaster drip and moulding to R.C.C. Chhajja.
Water shall conform to M-1. Cement shall conform to M-3. Sand shall conform to M-6 Cement
mortar shall conform to M-11
2.0. Workmanship
2.1. The work shall be carried out as directed. The proportion of mix for finishing shall be in C.M.
1:2 by volume. Curing shall be done for not less than 7 days. The work shall be carried our in best
workman like manner. The thwarting or plaster drip and mounding shall be one centimeter in
Providing and applying BRICK BET BASE chemical water proofing treatment to the
terrace, sunk slab including roughing cleaning the surface opening the crackers in "V"
grooves pattern and filing the same with water proofing mortar 1:1 (1 Cement :1 sand)
including brick bats bedding as directed to have proper slope over a layer of C.M.1:6 (1
Cement : 6 sand ) and filling the joints with C.M. 1:1 (1 Cement : 1 sand ) including finishing
the top surface with 40 mm thick water proof cement concrete 1:2:4 with using 6 mm grit in
C.M. 1:3 (1 Cement : 3 sand) and finished with a floating coat of neat cement slurry using
chemical water proofing compound as per manufactures specifications (as per indian water
proofing co.surat or equivalent) including curing at specified period as directed and
imprinting fals square of 0.30 x 0.30 mt gradient including making vata of 10 cmx10 cm
(quater round) on inside periphery of the parapet in C.M. 1:1 ( 1 Cement : 1 sand ) etc.
Complete as directed by Engineer in charge.
Cement shall confirm to Specification M-3/P-9, sand shall confirm to M-6/P-9, crushed brickbats
aggregates shall confirm M-14/P-12, Water shall confirm M-1/P-9.
Providing and applying BRICK BET BASE chemical water proofing treatment to the terrace, sunk
slab including roughing cleaning the surface opening the crackers in "V" grooves pattern and filing
the same with water proofing mortar 1:1 (1 Cement :1 sand) including brick bats bedding as directed
to have proper slope over a layer of C.M.1:6 (1 Cement : 6 sand ) and filling the joints with C.M. 1:1
(1 Cement : 1 sand ) including finishing the top surface with 40 mm thick water proof cement
concrete 1:2:4 with using 6 mm grit in C.M. 1:3 (1 Cement : 3 sand) and finished with a floating coat
of neat cement slurry using chemical water proofing compound as per manufactures specifications (as
per indian water proofing co.surat or equivalent) including curing at specified period as directed and
imprinting fals square of 0.30 x 0.30 mt gradient including making vata of 10 cmx10 cm (quater
round) on inside periphery of the parapet in C.M. 1:1 ( 1 Cement : 1 sand ) ,After finishing the whole
sunk shall be flooded with water for a period of one weeks. etc. complete at all floor levels
The brick bats aggregates shall be broken from well burnt or slightly over burnt and dense brick. It
shall be homogeneous in texture roughly cubical in shape clean and free from dirt, and any other
foreign materials.
MODE OF MEASUREMENT AND PAYMENT
The length and breadth shall be measured correct to cm. as per the dimension of the sanctioned
plants. No deduction shall be made not extraforpaid for any opening for pipes etc. up to 0.1 sq.mt.
The rate shall include the cost of all labour and materials required for the operation involved. For
satisfactory completion.
Consolidated item shall be measured and paid for the whole work for unit of one Sq.mt.
FORM OF GUARANTEE BOND
Contractor I/ We___________________ here by guarantee that work will remain unaffected and will
not be in anyway damaged by water, rain and will not leak from surface for a period of for 3 years
after completion of work as per terms and conditions of the contract and damaged that might be
caused on account of water, rain and or similar of dampness of leakage from walls or above floor. the
guarantee shall remain in force for the period of 10 years from the completion of the work under the
contract and it shall remain binding to the contract for period of 10 years.
Deposit of 10 % of total amount shall be kept with the executing authority for a period of Three year
Deposit of 10 % of total amount shall be kept with the executing authority for a period of Three year
(At least passing of one Monsoon after execution. A Guarantee bond shall be given in written on
stamp paper for the guarantee of work. Any leakage found in the work shall be repaired without any
extra cost. 50 % of deposit shall be released after one monsoon passed & 50 % deposit will be
released after Three years. Item shall be measured and paid for the whole work per unit of
one square meter.
Providing and laying white glazed tiles equal size pieces for CHINA MOSAIC WATER
PROOFING TREATMENT WITH BRICK BET BASE to terrace including cleaning the
surface opening the creaks in " V " grooves pattened filling the same water proof cement
mortar 1:1(1 Cement : 1 sand ) including BRICK BAT as directed to have proper slope over
a layer of C.M. 1:1 (1 Cement : 1 sand) including finishing the top surface with 15mm thick
water proof cement plaster in C.M. (1:3) (1 Cement : 3 sand) and finishing with a floating
coat of neat cement slurry using chemical water proofing compound as per manufactures
specifications and standard specifications as per indian Water proofing or equivalent
including curing at specified period as directed including finishing the top surface with equal
size white glazed tiles pieces including round shape vata 100mm x 100mm size with filling
white cement in joints, using chemical water proofing as per mfg., specification & standards
with cleaning top surface using acid including drip moulding at the junction of vata &
plaster etc..complete as directed by E.I.C.
Cement shall confirm to Specification M-3/P-9, sand shall confirm to M-6/P-9, crushed brickbats
aggregates shall confirm M-14/P-12, Water shall confirm M-1/P-9.
Providing and laying white glazed tiles equal size pieces for CHINA MOSAIC WATER PROOFING
TREATMENT WITH BRICK BET BASE to terrace including cleaning the surface opening the
creaks in " V " grooves pattened filling the same water proof cement mortar 1:1(1 Cement : 1 sand )
including BRICK BAT as directed to have proper slope over a layer of C.M. 1:1 (1 Cement : 1 sand)
including finishing the top surface with 15mm thick water proof cement plaster in C.M. (1:3) (1
Cement : 3 sand) and finishing with a floating coat of neat cement slurry using chemical water
proofing compound as per manufactures specifications and standard specifications as per indian
Water proofing or equivalent including curing at specified period as directed including finishing the
top surface with equal size white glazed tiles pieces including round shape vata 100mm x 100mm
size with filling white cement in joints, using chemical water proofing as per mfg., specification &
standards with cleaning top surface using acid including drip moulding at the junction of vata&
plaster , After finishing the whole terrace shall be flooded with water for a period of two weeks.
The brick bats aggregates shall be broken from well burnt or slightly over burnt and dense brick. It
shall be homogeneous in texture roughly cubical in shape clean and free from dirt, and any other
foreign materials.
First stage : After complete brickbet work it shall be well watered and cured for a sufficient period of
time i.e. at least 2 days.
Second stage: After finishing the whole terrace shall be flooded with water for a period of two
weeks. etc. complete at all floor levels
MODE OF MEASUREMENT AND PAYMENT
The length and breadth shall be measured correct to cm. as per the dimension of the sanctioned
plants. No deduction shall be made not extraforpaid for any opening for pipes etc. up to 0.1 sq.mt.
The rate shall include the cost of all labour and materials required for the operation involved. For
satisfactory completion.
Consolidated item shall be measured and paid for the whole work for unit of one Sq.mt.
FORM OF GUARANTEE BOND
Contractor I/ We___________________ here by guarantee that work will remain unaffected and will
not be in anyway damaged by water, rain and will not leak from surface for a period of for 3 years
after completion of work as per terms and conditions of the contract and damaged that might be
caused on account of water, rain and or similar of dampness of leakage from walls or above floor. the
guarantee shall remain in force for the period of 10 years from the completion of the work under the
contract and it shall remain binding to the contract for period of 10 years.
Deposit of 10 % of total amount shall be kept with the executing authority for a period of Three year
Deposit of 10 % of total amount shall be kept with the executing authority for a period of Three year
(At least passing of one Monsoon after execution. A Guarantee bond shall be given in written on
stamp paper for the guarantee of work. Any leakage found in the work shall be repaired without any
extra cost. 50 % of deposit shall be released after one monsoon passed & 50 % deposit will be
released after Three years.
Item shall be measured and paid for the whole work per unit of one square meter.
Providing and laying polished Kota stone slab flooring over 20mm (Average) thick base of
cement mortar 1:6 (1-cement : 6-coarse sand) or L.M. 1.1.5 (1-Lime putty :1.5 - coarse sand)
laid over and jointed with grey cement slurry mixed with pigment to match the shade of slab
including rubbing and polishing etc. complete. (A) 25mm thick
1.1. Water shall conform to M-1. Lime mortar shall conform to M-10. Cement mortar shall
conform to M-11 Polished kota stone shall conform to M-49,
2.0. Workmanship
1. 2. Each slab shall be cut to the required size and shape and fine chisel dressed at all the edges.
The sides trust dressed shall have a full contract if a straight edge is laid along. The sides shall be
table rubbed with coarse sand before paving. All angles and edges of the slabs shall be true square
and free from chippings and giving a plane surface. The thickness shall be 25 mm. (Average) as
specified in the item but not less than 20 mm. at any place of the slab.
2.2. Bedding for the Kota stone slabs shall be of cement mortar 1:6 (1 cement : 6 coarse sand) or
L.M. 1:1.5 of average thickness 20 mm given in the description of the item. Sub grade shall be
cleaned, wetted and mopped Mortar of the specified mix and thickness shall then be spread on an area
sufficient to receive one kota stone slab. The slab shall be washed clean before laying. It shall be laid
on top, pressed, tapped gently to bring it in level with the other slabs. If shall then be lifted and laid
aside. Top surface of the mortar shall then be corrected by adding fresh mortar at hollows or
depressions. The mortar shall then be allowed to harden bit. Over this surface, cement slurry of
honey-like consistency shall be applied. The slab shall then be gently placed in position and tapped
with wooden mallet till it is properly padded in level with and close to the adjoining slab. The joint
shall be as fine as possible. The slabs fixed in the floor adjoining, the walls shall enter not less than
mm. under the plaster, skirting or dedo. The junction between the wan and floor shall be finished
neatly. The finished surface shall be true to levels and slopes as directed.
2.3. The floor shall be kept wet for a minimum period of 7 days so that bedding and joints set
2.4. Polishing shall be normally commenced after 14 days of laying the stone slab. First polishing
shah be done with carborundum stones of 120 grade grit fitted in the heavy machine and then second
polishing shall be done with carborundum stone of 220 to 350 grade grit fitted in heavy machine.
Water shall be properly used during polishing. The stone shall then be washed clean with water When
directed by the Engineer-in-charge, wax polish of approved quality shall be applied on the surface
with the help of soft cloth over a clean and dry surface. Then the polishing machine fitted with bobs
shall be run over it.
2.5. The holes required for Nahni traps, pipes and any other fittings shall be made, without any
3.0. Measurement & payment
3.1. The rate shall include the cost of all materials and labour involved in ail the operations
described above. The kota stone flooring shall be measured in square meters correct to two places
decimal, length and breadth shall be measured correct to a centimeter and between the finished face
of skirting dedo plaster and no deduction shall be made nor extra paid for any opening in floor of
areas up to 0 1 sq
3.2. The rate shall be for a unit of one sq. meter
Note: The flooring work shall be done as per right angle & as per architectural drawings & as
suggestion by architect/E.I.C .
P & L 24" x 24" vitrified 8 mm thick tile flooring over 20 mm (average) base of cement
mortar 1:6 ( 1 cement: 6 coarse sand) on new surface or fixing on existing flooring by
adhesive material including dismentaling of existing flooring and jointed with color cement
slurry including finised with flush pointing & cleaning the surface etc. complete for antiskit
Water shall conform to M-1 Cement mortar shall conform to M-11 tiles shall conform to M-55
2.0. Workmanship
2.1.1. The sub grade shall be cleaned, wetted and mopped. The bedding shall then be laid evenly over
the surface tamped and corrected to desired level and allowed to harden enough to offer a rigid
cushion to tiles and to enable the monsoon to place wooden planks across and squat on it.
2.1.2. The tiles shall be laid on cement mortar bedding of 20 mm. thick in C.M. 1:6. The mortar shall
have sufficient plasticity for laying and there shall be no hard lumps that would interfere with the
evenness of bedding. The base shall be cleared and well wetted. The proportion of the cement mortar
shall be as specified in the item.
2.2. Fixing tiles :
2.2.1. The tiles before laying shall be soaked in water for at least two hours. Neat gray cement grout
at 33 kg/Cement/Sq. mt. of honey like consistency shall be spread over the mortar bedding as
directed. The edges of the tiles shall be smeared with neat cement slurry. The tiles shall be well
pressed and gently tapped with a wooden mallet till they are properly bedded and in level with the
adjoining tiles. There shall be. no hollows in bed or joints. The joints between the tiles shall be as thin
as possible in straight line or as per pattern.
2.2.2. The tiles shall not have staggered joints. The joints shall be true to centre line both ways. The
Nahni trap coming in the flooring shall be so positioned that its grating shall replace only one tile as
far as possible. Where full size tiles cannot be fixed they shall be cut (Swan) to the required size and
the edges rubbed smooth to ensure straight and true joints. The joints shall be filled with grey cement
grout with wire brush or trowel to a depth of 5 mm. and loose material removed. White cement shall
be used for pointing the joints. After fixing the tiles finally in an even plane the flooring shall be kept
wet and allowed to nature undisturbed for 7 days.Providing & laying GVT Vitrified tiles 9mm thick
flooring over 20 mm (average) base of cement mortar 1:6 ( 1 cement: 6 coarse sand) on new surface
or fixing on existing flooring by adhesive material including dismentaling of existing flooring and
jointed with color cement slurry including 3mm Making spacer at joint of tiles and fill the spacer
with epoxy jointing material finised with flush pointing & cleaning the surface etc complete selection
as directed by Architect/E.IC
2.3.1. The surplus cement grout that may have come out of the joints shall be cleaned off before it
sets. Once the floor has set, it shall be carefully washed, cleared by dilute acid and dried. Proper
precautions and measures shall be taken to ensure that the tiles are not damaged in any way till the
completion of the .construction.
3. MODE OF MEASUREMENT & PAYMENT:
The measurement shall be taken on Sq. Meter basis as per IS : 1200 or as revised from time to time so
far as applicable
The contract rate shall be for a unit of one Sq. Meter of visible surfaces.
The rate shall be for a unit of one Square meter
Note: The flooring work shall be done as per right angle & as per architectural drawings & as
suggestion by architect/E.I.C .
Providing and laying Ceramic tiles 6mm thick in flooring treads of steps and landing laid on
a bed of 12mm thick cement mortar 1:3 (1-cement : 3-coarse sand ) finishing with flush
pointing in white cement.
Providing and laying Ceramic tiles 6mm thick in flooring treads of steps and landing laid on a bed of
12mm thick cement mortar 1:3 (1-cement : 3-coarse sand ) finishing with flush pointing in white
Mode of measurement:
The rate shall be for a One square meter.
Providing and laying Ceramic tiles 6mm thick in skrting risers of steps and dedo on 10mm
thick cement plaster 1:3 (1-cement : 3-coarse sand) and jointed with white cement slurry
Providing and layingCeramic tiles 6mm thick in skrting risers of steps and dedo on 10mm thick
cement plaster 1:3 (1-cement : 3-coarse sand) and jointed with white cement slurry
Mode of measurement:
The rate shall be for a One square meter.
Providing and laying 18mm thick polished GRANITE STONE SLAB in riser of steps, dedo
& skerting laid on 10 mm thick cement mortar 1:3 (1 cement :3 coarse sand) and jointed
with coloured cement slurry including rubbing & polishing etc complete in true line and level
/ slope as directed by E.I.C.
1.1 Water shall not be salty brackish and shall be clean reasonably clear and free objectionable
quantities of silt and traces of oil j\injurious alkalis salts organic matter and other deleterious material
which will either weaken the mortar of concrete or cause efflorescence or attack the steel in R C C
container for transport storage and huddling of water shall be clean, Water shall confirm to the
standard specified in I S 455 -1978
1.2 If required by the Engineer in charge it shall be tested by comparison with distilled water
compression shall be made by means of standard cement tests for soundness time of setting and
mortar strength as specified in I S 269-1976 Any indication of unsoundness charge in time of setting
by 30 minutes or more or decrease of more than 10 percent strength of mortar prepared with distilled
water sample when compared with the result obtained with mortar prepared with distilled water shall
be sufficient cause for rejection of water under test.
1.3 Water for curing mortar concrete or masonry should not be too acidic or too alkaline
1.4 It shall be free of elements which significantly affect the hydration reaction or otherwise interface
with the hardening of mortar or concrete during curing or those which produce objectionable stains or
other unsightly deposits on concrete or mortar surfaces
1.5 Hard and bitter water shall not be used for curing
1.6 Potable water will generally found suitable for curing mortar or concrete
2.1 Cement shall be ordinary Portland slag cement as per IS 1624 -1974 or Portland slag cement as
per IS 455-1976
2.2 Cement shall be stored above the ground level in perfectly dry and water tight sheds. Wherever
bulk storage containers are used, their capacity should be sufficient to cater to the requirements at site
and should be cleaned at least once every 3 to 4 months. The aggregate shall be stored in such a way
as to prevent admixture of foreign materials. Different size of fine or coarse aggregate shall be stored
in separate stock-piles sufficiently away from the each other to prevent intermixing the materials.
3.1 Sand shall be natural sand, clean well graded, hard strong durable and gritty particular free from
immures amounts of dust, clay, kankar modules, soft: or flaky particles shall alkali salts, organic
matter, learn mica or other deleterious substance and shall be got approved from the Engineer-in-
charge. The sand shall not contain more than 8 percent of slit as determined by field test. if necessary
Coarse Sand: The fineness modules of coarse sand shall not be less than 2.5 and shall not exceed 3.0.
The sieve analysis of coarse sand be as under:_
I. S. Sieve Designation % by wt. passing 4.75 mm 100 2.36mm 90 to 100 1.18 mm 70 to 100
3.2 FINE SAND: The fineness module shall not exceed 1.0 the sieve analysis of fine sand be as
IS. Sieve Designation % by wt. passing 4.75 mm 100 2.3 6mm . 100 1.18 mm 75 to 100 600 MC
3.3 Materials shall be stored as to prevent their deterioration of their quality and fitness for the work.
Any material which has deteriorated or has been damaged or is otherwise considered defective by the
Engineer-in-charge shall not be used in the work.
4.0 Machine polished Granite stone slab 18mm thick (Single place not more than 150 cm) as per
4.1. Granite stone shall be hard even sound, and regular in shape and generally uniform in colour. The
colour of the stone shall generally be green. Brown coloured shall not be allowed for use. They shall
be without any soft veins cranks of flaws
4.2. The Thickness shall be as specified 18-20 mm .
4.3. Tolerance of minus 30 mm. on accounts of chisel dressing of edges shall be permitted for length
as well as breadth. Tolerance in thickness shall be +3 mm.
4.4. The edges of stones shall be truly chiseled and table rubbed with coarse sand before paving. All
angles and edges of the stones of shall be true, square and free chipping and surface shall be true and
4.5. When machine cut edges are specified the exposed and the edges at joints shall be machine cut
the thickness of the exposed machine cut edges shall be uniform.
4.6. The stones shall have machine polished surface. When brought on site, the stones shall be single
polished or double polished depending upon its use. The stones for paving shall generally be single
polished. The stones to be used for dado, skirting, sink, veneering, sills, steps, etc. where machine
polishing after the stones are fixed in situ is not possible shall be double polished.
5.0 WORKMANSHIP
5.1 Granite stone of approved quality shall be laid evenly to level and slope as directed by Engineer
in charge over a bed of a base layer consisting of cement mortar 1:6 ( 1 cement: 6 coarse sand by
volume) or Lime Mortar 1:1.5 ( 1 lime : 1.5 lime putty by volume)
5.2. Cement and sand for base layer shall be mixed in proportions of 1:6 ( 1 cement : 6 coarse sand by
volume) Cement and sand shall be proportioned by volume after making due allowance for bulking.
The require quantity of water shall then be added and the mortar mixed to produce workable
consistency before mixing platform shall be thoroughly cleaned before changing from one type of
cement to another.
5.3. The mixing for base layer shall be done intimately, The operation shall be carried out on clean
water tight platform, and cement sand shall be first mixed dry in the required proportion to obtain
uniform colour and then the mortar shall be mixed for at least two minutes after addition of water. In
case of cement mortar, that has suffered because of evaporation of water the same shall be re-
tempered by adding water as frequently as needed to restore the requisite consistency but its re-
tempering shall be permitted only within thirty minute from the time of addition to water at the time
of initial mixing.
5.4. Cement and sand for base layer shall be mixed in proportion as specified in the item, Cement and
sand shall be proportioned by volume after making due allowance for bulking. The required quantity
of water shall then be added and the mortar mixed to produce workable consistency.
5.5. Curing shall be started as soon as the mortar used for finished has hardened sufficiently no to be
damaged when watered. It shall be kept wet for a period of at least 7 days. During this period, it shall
be suitably protected from all damages;
5.6. During hot weather, all finished or partly finished work shall be covered or wetted in such
manner as will prevent rapid drying of the flooring work.
5.7. Joints of flooring shall be through and continuous throughout the building as directed by
Engineer in charge
5.8. joints shall be filled with a stiff mixture of grey cement surly
5.9. The flooring work shall be finished by rubbing and mirror polishing after the the work of flooring
is set properly
5.10. The rate of flooring is inclusive of 7.5 cm thick skirting using same stone of Granite stone
strips including providing and laying in true line and level including filling the joints with gray
cement slurry with rubbing and polishing as directed by Engineer in charge
6.0 PROPORTION OF MIX
6.1.The proportion of cement and sand for base layer shall be one part of cement. 6 (four) parts of
sand and shall be measured by volume.
7.0 MODE OF MEASUREMENT & PAYMENT :
7.1. The unit rate flooring shall include the cost of all materials, tools and plant
7.2. The payment will be made on square Meter basis of the finished work.
Providing & fixing 18 to 20mm thick GRANITE STONE at Door ,window sill, jams & sofit
by keeping 225mm wide outer strip resting on sill towards outside & 100mm wide inner strip
resting on outer strip by overlaping 25mm towards inside at sill and 300mm wide strip at
jams & at soffit and fixing with CM (1 cement: 2 coarse sand), Araldite and screws if
necessary including mirror polishing and making half round moulding on both the sides and
finishing with colour cement etc. complete as directed by E.I.C.
The item shall be executed as per the relevant specifications & mode of measurement of above item
Providing and laying PLAT FORM CONSIDERING HEIGHT =0.75MT (sandwich type)
with machine cut single side polished 18 to 20mm thick GRANITESTONE (Green /
approved colour) & 25mm thick KOTAH STONE including making gissi in brick wall and
fixing the sized polished kotah stone pieces sandwitch type in vertical position ,single
polished granite stone horizontal and vertical facia ,facia patti,making hole for gas piping
,and at top sandwich type including half round moulding filling gap with cement putty and
cement mortar etc,complete in true line and level as per detail drawing and directed by
The item shall be executed as per the relevant specifications & mode of measurement of above item
Providing and fixing cluster stone BGB bricks on the exterior face of the building having
reddish and orange shade(mix) which shall be made up of natural volcanic rocks, polymer,
co-polymer, light weight aggregate and silica. The size of cluster stone BGB bricks shall be
of 0.22 * 0.08 m with a minimum thickness of 15 mm. The cluster stone pattern BGB bricks
shall have minimum weight of 2 Kg per brick and shall be fixed with the help of polymer
based adhesives. The rate includes cost of installation, materials, adhesives, application
(labour), grouting & protective coating for all heights and for all floor levels.The cluster
stone shall be light weight, easy to install and shall be free from algae and fungus of flextone
or equivalent make. The type of pattern shall be as per architect's selection and as per
engineer in charge.
Providing and fixing cluster stone BGB bricks on the exterior face of the building having reddish and
orange shade(mix) which shall be made up of natural volcanic rocks, polymer, co-polymer, light
weight aggregate and silica. The size of cluster stone BGB bricks shall be of 0.22 * 0.08 m with a
minimum thickness of 15 mm.
The cluster stone pattern BGB bricks shall have minimum weight of 2 Kg per brick and shall be fixed
with the help of polymer based adhesives.
The rate includes cost of installation, materials, adhesives, application (labour), grouting & protective
coating for all heights and for all floor levels.The cluster stone shall be light weight, easy to install
and shall be free from algae and fungus of flextone or equivalent make.
The type of pattern shall be as per architect's selection and as per engineer in charge .
Mode of measurement:
The rate shall be for a One square meter.
Providing & Applying high quality acrylic modified resin based texture of Dholpur/Red
sand stone Pattern with anti algae and UV resistance properties to be applied as
intermediate finish in desired pattern @ 43.04 kg/10 sqm to form film of 1- 1.5 mm thickness
after scrapping and properly cleaning the surface to remove loose particles from the plaster
surface, followed by top coating with Premium Acrylic Smooth exterior paint with Silicone
additives of required shade by two or more coats @ 1.43 litre/10 sqm, complete as the
direction of Engineer -in-Charge.
Item should be include as Providing and applying of surface cleaning then crack filling with nerolec
perma crack filler then dholpur texture two coats then one coat of nerolec parma damp protect
exterior primer on wall surfaces after thoroughly brushing the surface free from mortar droppings and
other foreign matter. Item includes making the surface even and smooth by sand papers. then after
required for the work with weather proof nerolec exterior emulsion paint on wall surface (two coats)
to give an required shape even shade after thoroughly brushing the surface to remove all dirt, and
remains of loose powdered materials. Rates are inclusive of all the material and labourers and
scaffolding work, cleaning of the floors etc.& 8 years warrenty etc complete as directed & suggested
by Architect & EIC
Mode of measurement:
The rate shall be for a unit of one square meter.
Applying two coats of putty & two coats of primer of approved brand and manufacture on
new wall surface to give an even shade including thoroughly brushing the surface free from
mortar dropping and other foreign matter and sand papered smooth. & Wall painting (two
coats) with plastic emulsion paint of approved brand and manufacture on undecorated wall
surface to give an even shade including throughly brushing the surface free from mortar
droppings and other foreign matter and sand papered smooth.
1.0. Materials ( M-44)
1.1. Birla or equivalent quality white putty approved by engineer in charge shall be used for
finishing coat on 15mm plastered surface as directed.
1.2. Plastic emulsion paint of approved brand and manufacturer of required shade on wall surface.
2.0. Application White Putty for finishing coat.
Birla or equivalent approved make white putty shall be applied in true line and plumb on 15mm sand
face plastered surface as directed by engineer in charge. The smooth finish shall be in proper manner
so that the depressions or un evenness shall not be found on the finished surfae.
3.0. Application of Plastic emulsion paint for finishing coat.
Wall painting ( two coats ) with distempering with dry distemper of approved brand and manufacturer
of required shade on wall surface to give an even shade.
4.0. Workmanship –
Preparation of Surface - The surface shall be thoroughly cleaned of all dust, dirt, mortar
droppings and other foreign matter before painting is to be applied.
The surface spoiled by smoke soot shall be scraped with steel wire brushes or steel scrapers or
shall be rubbed with over burnt surkhi or brickbats. The surface shall be then broomed to
remove all dust, durt and shall be washed with clean water.
Oil or grease spots shall be removed by suitable chemical and smooth surface shall be rubbed with
All unsound portion of the surface plaster shall be removed to full depth of plaster in rectangular
patches and plastered again after raking the masonary joints properly. Such portion shall be
wetted and allowed to dry. They shall then be given one coat of paint. Each coat shall be allowed
to dry before the next coat is applied. The number of coats as specified in item shall be
All unnecessary nails shall be removed, the holes, cracks, patches etc. shall be made good with
materials similar in composition to the surface to be prepared.
Splashing and dropping if any on the flooring, doors and windows, ventilators etc. shall be
removed and the surface cleaned.
5.0. Scaffolding - Where scaffolding is necessary it shall be erected in such a way that as far as
possible no part of scaffolding shall rest against the surface to be painted. A properly secured
strong and well tied suspended paltform ( zoola) may be used for painting. Where ladders are
used, pieces of old gunny bags shall be tied at top and bottom to prevent scratches to the floors
and walls. For painting of ceilings, proper stage scaffolding shall be erected where necessary.
6.0. Mode of Measurement & payment
The rate includes all labor materials tools and plants etc. required for satisfactory completion of this
item.All the works shall be measured in the decimal system as under ---
Dimensions shall be measured to the nearest 0.01 M.
Area in individual items shall be worked out to the nearest 0.01 Sq.M.
All the works shall be measured in Sq.Mts. Deductions for jambs, soffits, sills etc. for openings
not exceeding 0.5 Sq.Mts. each in area, for ends of joints, posts, beams, girders, steps etc. not
exceeding 0.5 Sq.Mts. each in area and for openings exceeding 0.5 Sq.Mts. but not 3.0 Sq.Mts.
each in area deductions and additions shall be made as under.
No deductions shall be made for ends of joints, beams, posts etc. and openings not exceeding
Sq.Mts. each. No additions shall be made for reveals, jambs, soffits, sills etc. of these
openings not for finish around ends of joints, beams, posts, etc.
Deductions of openings exceeding 0.5 Sq. Mts. but not exceeding 3 Sq.Mts. each shall be
made as follows and no additions shall be made for reveals, jambs, soffits etc. of these
- When both the faces of walls are provided with finish, deduction shall be made for one face
- When each face of wall is provided with a different finish deduction shall be made for that
side of frame for door, windows etc. on which width of reveals is less than that of the other side,
where width of reveals on both faces of wall are equal, dedcution of 50% of area of opening
on each face shall be made from total area to finish.
- When only one face of wall is treated and the other face is not treated, full deduction shall be
made if the width of reveal on the treated side is less than that on the untreated side, but if the
width of the reveal is equal or more than on the untreated side neither deductions nor additions to
be made for reveals, jambs, soffits, sills etc.
In case of area of openings exceeding 3 Sq.Mts. each, deduction shall be made for openings but
jambs, soffits, sills shall be measured.
No deductions shall be made for attachment such as casing, conducts, pipe, electric wiring and the
Cornices and all other features, when they are not picked out in a different finish colour shall
be girthed and included in the general area.
The rate shall include the cost of all materials, labour scaffolding, protective measures etc.
involved in all the operations described above.
The rate shall be for a unit of one Sq. Mt.
Providing and applying one coat of water based exterior primer of approved brand and
make as mentioned below on wall surfaces after thoroughly brushing the surface free from
mortar droppings and other foreign matter. Item includes making the surface even and
smooth by sand papers. Rates are inclusive of all the material and labourers and scaffolding
work, cleaning of the floors etc. required for the work with weather proof exterior emulsion
paint on wall surface (two coats) (5 Years Warranty) to give an required shape even shade
after thoroughly brushing the surface to remove all dirt, and remains of loose powdered
materials.etc complete at all floor level. As per make list.
The surface shall be inspected and approved by the Engineer-in-Charge before commencement of
Painting shall not be carried out on damp surfaces or during rainy or adverse weather conditions.
Primer and paint shall be mixed and diluted strictly as per the manufacturer's recommendations.
Adequate drying time shall be maintained between successive coats.
Each coat shall be applied evenly to obtain complete and uniform coverage.
Adjacent finished surfaces such as glass, aluminium, stone, flooring, and fixtures shall be protected
from paint splashes and stains.
Any defective work shall be rectified by the contractor at no extra cost.
After completion, all paint stains, debris, empty containers, and waste materials shall be removed,
and the work area shall be left neat and clean.
Mode of Measurement & payment
Measurement shall be made in Square Metres (Sq.m.) of the actual painted surface.
The net painted area shall be measured in accordance with IS 1200 and relevant CPWD/PWD
specifications.
The rate shall include surface preparation, one coat of water-based exterior primer, two coats of
weather-proof exterior emulsion paint, sand papering, labour, materials, scaffolding, tools and plants,
protection of adjacent work, and final cleaning.
No separate payment shall be made for scaffolding, surface preparation, primer application, sand
papering, or cleaning, as these are deemed to be included in the item rate.
The finished work shall be measured only after satisfactory completion and approval by the
Engineer-in-Charge.
Providing & fixing Door considering block board flush door sheet of 35mm thickness
covered both side by 1 mm thick laminate(laminate make:Century,greenlam,Formica )on
both sides of shutter and , fixed with 75 mm x 19 mm burmateak Patti , rest on Floor spring
heavy duty & Top-Bottom fitting for door-pivot. All exposed framing made by Burma teak
wood complete with laminate Patti. Finishing with all necessary S.S hardwires like DOOR
S.S Handles 5PHO 2218SS -FPHO 2218 , conceal Door lock Mortize Body 85x60M S.S
DOOR UK key CYLI,60MM 1CK S.S 5 KEY M/HL 125 ROSE SS ,cylinders, stoppers,
tower bolt, MS nails, SS-304 screws,,including providing and applying prime coat Asian
/Berger make and two coats of oil painting of Asian /Berger make to the edges etc. as per
details given in drawing and as per instructions of Architect/Engineer In charge.
The opening shall be checked for dimensions, plumb, level, and alignment before installation.
The door shutter shall be accurately cut and finished without damaging the laminate.
Laminate shall be applied without bubbles, wrinkles, open joints, or visible adhesive marks.
Burma Teak lipping shall be fixed firmly, properly mitred at corners, and finished smooth.
Floor spring and pivot fittings shall be installed strictly in accordance with the manufacturer's
recommendations.
The door shall swing freely and close smoothly without noise or misalignment.
All hardware shall be fixed with SS-304 screws and aligned correctly.
Exposed timber surfaces shall be sanded smooth before application of primer and paint.
All paint finishes shall be uniform, smooth, and free from runs, brush marks, or patches.
After completion, all hardware shall be cleaned, adjusted, lubricated where necessary, and
protected until handing over.
Any damaged laminate, timber, hardware, or paintwork shall be replaced or repaired by the
contractor at no extra cost.
6.0. Mode of Measurement & payment
Measurement shall be made in Square Metres (Sq.m.) of the actual area of the completed door
Providing and fixing FRP frame size 125x65 mm and 35mm thick FRP shutter having
Extra reinforcement on sides & edges in polish finish. The core of the shutter & frame is to
be filed up with injected polyurethene foam done in situ alongwith embedded wooden pieces
for stiffening & also taking hinges & fintures. The whole FRP frame & shutter is to be water
proof weather proof, termite proof & resistance to mild acid/alkali. Rates are to be inclusive
of S.S hinges with necessary screws & alluminium S.S fixtures & fastenings & fastener
sleeve. at all floor level.
The door opening shall be checked for correct dimensions, line, level, and plumb before
The FRP frame shall be fixed rigidly using approved fasteners, sleeves, and anchor bolts as
The frame shall be securely grouted or packed with suitable mortar/PU foam where required to
ensure stability.
The shutter shall be fixed using approved SS hinges and all hardware shall be properly aligned.
Embedded wooden blocks shall be accurately positioned to receive hinges and fittings without
damaging the FRP surface.
Care shall be taken to prevent scratches, cracks, or damage to the FRP finish during transportation
and installation.
The door shall open and close smoothly without rubbing, warping, or misalignment.
All hardware shall be securely tightened and checked for proper operation.
Upon completion, the surface shall be cleaned and any protective film removed without damaging
Any damaged frame, shutter, or hardware shall be replaced by the contractor at no extra cost.
MODE OF MEASUREMENT & PAYMENT:
1. Measurement shall be made in Square Metres (Sq.m.)
Providing and fixing rolling shutters of approved make made of 80 mm wide M.S. laths
inter-locked together through their entire length and jointed together at the ends by end
locks mounted on specially designed pipes haft with bracket plates, guide channels and
arragements for inside and outside locking with push-pull operation including the cost of
hood cover and spring etc. complete. (A) Shutters having width below 3.5 M.
The collapsible steel gate shall conform to M-33.
2.0. Workmanship
J-rails shall be fixed to the floor and to the lintel at top by means of Anchor bolls, embedded in
cement concrete-of floor and lintel. The anchor bolts shall be placed approximately at 45 mm. centers
alternatively in groove shall be formed along the runner for the purpose. The collapsible gate shall
fixed at the sites by fixing the double channels in the T-iron rail and also by hold fasts bolted to the
end double channel and fixed in the masonry of the side walls or the otherwise.
In case where the collapsible gate is not required to the lintel beams or slop above, a toe iron suitably
designed may be fixed at the top embedded in masonry and provided with necessary clamps and
roller arrangement at the top.
All the adjoining work damaged while fixing of gate shall be made good to match the existing work
without any extra payment.
All the members of the collapsible gate including. T-iron shall be thoroughly cleaned of rust, scales
dust etc., and given a priming coat of red lead, before fixing them in position.
3.0. Mode of measurement and payment
3.1. The collapsible gate shall be measured in sq. meter. The height of the gate shall be measured
as the length of double channels and breadth from outside to outside of the end fixed double channels
in open position of the gate. The rate includes providing handles, arrangements stoppers etc.
3.2. The rate -shall be for a unit of one sq. meter.
Providing and fixing 1mm thick M.S. sheet sliding shutters with frame and diagonal braces
of 40 x 40 x 6 mm angle iron, 3.15 mm M.S. gusset plates at Junctions and corners 25 mm
dia. pulley, 40 x 40 x 6mm angle and T-iron guide rail at top and bottom Respactively with
handles, stoppers and locking agangement etc, including applying a priming coat of red lead
M.S. sliding shutters shall be fabricated of M.S. component as given in the description of item M.S.
sheets 1 mm. thick shall be fixed to the frame with rivets of weld as approved. The shutters shall he
provided with top and bottom guide rails of Angles or T-iron as specified and 25 mm. dia. steel
pulleys at the-bottom guide black with steel pulleys at the top. The frame shall be riveted and /or
welded and wherever riveting shall be done 3.15 mm. gussets plates shall be provided at the
2.0. Workmanship
2.1. The shutters shall be single or double leaf shutters as specified. The guide rails shall be
sufficiently long and continued along the wall on the both ends so that the sliding shutters can rest
against walls, living full opening when so required.
2.2. The guide rails shall be fixed to the floor by means of anchor bolts embed in the cement
concrete floor. The steel section at the top shall be suitably supported from the walls. Two channel
section shall suitably fixed vertically below the extreme clamps in the wall and floor to avoid the
shutters from going out of the supports at the top and bottom. A suitable clamping arrangement will
be provided at either end of the opening to avoid the shutters from rolling back into opening.
2.3. All the adjoining work damaged while fixing shall be made good to match the existing work.
2.4. All members of the sliding shutter including T-iron shall be thoroughly cleaned of nisi scales
dust etc. and given a priming coat of red lead before fixing them in position
3.0. Mode of measurements & payment
3.1. The sliding doors shall be measured on sq. meter. The height of the shutters shall be measured
form outside to outside of the guide, rail and width outside of shutters including vertical channels in
sides. The rate includes providing handles stopped and locking arrangement etc. complete.
3.2. The rate shall be for a unit of one sq. meter.
Providing and fixing standard extruded of alluminium section of size 63.0 mm x 38.10 mm x
1.2 mm/as per design/drawing with colour anodized alluminium frame for ventilation with
mm thick frosted glass as per details etc complete for ventilation.
21.6 DOOR, WINDOW, VENTILATOR AND PARTITION FRAMES
The tenderer/ contractoe shall supply and fix the various type of Aluminum window on specific
location up to all floor with all lead and lift having followings
21.6.1 Frame Work
First of all the shop drawings for each type of doors/windows/ventilators etc. Shall be prepared by
using suitable sections based on architectural drawings, adequate to meet the requirement/
specifications and by taking into consideration varying profiles of Aluminum sections being extruded
by approved manufacturers. The shop drawings shall show full size sections of glazed doors,
windows, ventilators etc. The shop drawings shall also show the details of fittings and joints. Before
start of the work, all the shop drawings shall be got approved from the Engineer-in-Charge.
Actual measurement of openings left at site for different type of door/window etc. Shall be taken. The
fabrication of the individual door/windows/ventilators etc. Shall be done as per the actual sizes of the
opening left at site. The frames shall be truly rectangular and flat with regular shape corners
fabricated to true right angles. The frames shall be fabricated out of section which have been cut to
length, mitered and jointed mechanically using appropriate machines. Mitered joints shall be corner
crimped or fixed with self tapping stainless steel screws using extruded aluminum cleats of required
length and profile. All Aluminum work shall provide for replacing damaged/broken glass panes
without having to remove or damage any member of exterior finishing material.
21.6.2 Fixing of Frames
The holes in concrete/masonry/wood/any other members for fixing anchor bolts/fasteners/screws
Shall be drilled with an appropriate electric drill. Windows/doors/ventilators etc. Shall be placed in
correct final position in the opening and fixed to Sal wood backing using stainless steel screws of star
headed, counter sunk and matching size groove. Of required size at spacing not more than 250 mm
c/c or dash fastener. All joints shall be sealed with approved silicone sealants. In the case of
composite windows and doors, the different units are to be assembled first. The assembled composite
units shall be checked for line, level and plumb before final fixing is done. Engineer-in-Charge in his
sole discretion may allow the units to be assembled in their final location if the situation so warrants.
Snap beadings and EPDM gasket shall be fixed as per the detail shown in the shop drawings.
Where Aluminum comes into contact with stone masonry, brick work, concrete, plaster or dissimilar
metal, it shall be coated with an approved insulation lacquer, paint or plastic tape to ensure that
electrochemical corrosion is avoided. Insulation material shall be trimmed off to a clean flush line on
The contractor shall be responsible for the doors, windows etc. Being set straight, plumb, level and
for their satisfactory operation after fixing is complete.
21.6.3 Measurements
Rate shall be for a unit of square meter basis of the complete item of anodize aluminum window. The
measurement of the square meter should be cross checked with the weight of the aluminum section
used in per square meter. The weight calculated on the basis of actual average (average of five
samples after anodizing ) .The weight of glass, rubber gasket, handle and other accessories shall not
be considered while calculating weight. The contractor / tenderer have to produce the authentic
weight slip showing the correct and actual weight of the aluminum section. The rate of the item shall
include the cost of all materials, T&P, Double Scaffolding and labor, water charges , minor, civil work
, lead lift at all levels ,wastage etc. required in all the above operations and item complete in all aspect
up to satisfaction of architect.
Providing and fixing window having extruded aluminum Colour anodized section frame
main outer size 63.50 x 38.10 x 1.95 mm,@ Wt 1.094 Kg / Rmt, horizontal Two Track
Member size 61.85 mm x 31.75 mm x 1.20mm @ wt.of 0.695 Kg/mt, vertical member of size
61.85 mm x 31.75mm x 1.30 mm @ wt.of 0.659 Kg/mt with sliding shutters of horizontal
member size 40mm x 18mm x 1.29mm @ wt.of 0.456Kg/mt, vertical member of size 40mm x
18mm x 1.29mm @ wt.of 0.456Kg/mt, @ Wt. 0.457 Kg/mt with 5 mm thick transparent
bronze colour tinted float glass with powder coated aluminum fittings and fixtures and
transparent silicon sealant glass fixing to frame as per details etc complete for window
Providing and fixing window having extruded aluminum Colour anodized section frame main outer
size 63.50 x 38.10 x 1.95 mm,@ Wt 1.094 Kg / Rmt, horizontal Two Track Member size
mm x 31.75 mm x 1.20mm @ wt.of 0.695 Kg/mt, vertical member of size 61.85 mm x 31.75mm x
1.30 mm @ wt.of 0.659 Kg/mt with sliding shutters of horizontal member size 40mm x 18mm x
1.29mm @ wt.of 0.456Kg/mt, vertical member of size 40mm x 18mm x 1.29mm @ wt.of
0.456Kg/mt, @ Wt. 0.457 Kg/mt with 5 mm thick transparent bronze colour tinted float glass with
powder coated aluminum fittings and fixtures and transparent silicon sealant glass fixing to frame
as per details etc complete for window
MODE OF MEASUREMENT & PAYMENT:
1. The payment will be made on square Meter basis of the finished work.
Providing and fixing window having extruded aluminum Colour anodized section frame
main outer size 95mmx24mmx1.17mm of approved make ,horizontal Three Track Member
size 92mmx31.75mmx1.30mm of approved make ,vertical member of size
92mmx31.75mmx1.50mm of approved make with sliding shutters of horizontal and vertical
member size 40mmx18mmx1.29mm of approved make with 5mm thick transparent bronze
colour tinted float glass with powder coated aluminum fittings and fixtures and transparent
silicon sealant glass fixing to frame as per details etc complete job.including one
MOSQUITO Shutter conststing of s.s. wire gage of avaerage width aperature 1.4 mm with
wire of dia meter 0 .63mm necessary cutting and making good etc. for window.
Providing and fixing window having extruded aluminum Colour anodized section (2 nos. glazed &
one no. Mosquito net) frame main outer size 95mm x 24mm x 1.17mm @ wt.of 0.738 Kg/mt
horizontal Three track member size 92mm x 31.75mm x 1.30mm,@ Wt.1.07 Kg/mt , vertical member
of size 92mm x 31.75mm x 1.50mm @ Wt. 1.06 Kg/mt with sliding shutters of horizontal member
size 40 mmx18mm x1.29mm @ wt.of 0.456 Kg/mt, vertical member of size 40mm x 18mm x
mm @ wt.of 0.456Kg/mt/ with 5 mm thick transparent bronze colour tinted float glass with powder
coated aluminum fittings and fixtures and transparent silicon sealant glass fixing to frame as per
details etc at all floor level.
MODE OF MEASUREMENT & PAYMENT:
1. The payment will be made on square Meter basis of the finished work.
Providing and fixing M.S. grills of required pattern to wooden frames of windows etc. with
M.S. flats at required spacings and frame alround, square or round bars with round headed
bolts and nuts or by screws (A) Plain Grill.
The structural steel shall conform to M-22
2.0. Workmanship
2.1. The M.S. Grill shall be prepared as per the drawing or as directed for fixing to wooden frames
of windows etc.
2.2. The grill shall be fabricated to the designs and patterns shown in the drawings and the weight
shall be as directed, and the joints shall be reverted or welded as shown in the plan or as directed. The
grill so formed shall be fixed into the frames of the windows etc. before they are erected in position.
The outside strip frame of the grill shall be housed to its full thickness into the recess cut into the
frame of the windows etc. The grill shall be fixed to the frame with number of bolts and nuts or
screws viz. bolt nut/screw per 30 cm. of the length of outer strip subject to minimum of 2 Nos. on
each side of the frame or as indicated in the drawing or as directed.
2.3. The bolts and nuts or screws shall be counter sunk and shall be fixed with the top of their
heads flush with the face of the frame strips.
3.0. Mode of measurements & payment
3.1. No payment shall be made for weight of screws, bolts nuts etc. only weight of grill shall be
3.2. The rate shall be for a unit of one kg.
Providing & fixing Steel work,grill work,stair ladders,parking shead ,etc welded in built
up/rolled steel sections framed work including cutting, hoisting, fixing in position and
applying a priming coat of read lead paint. (A)In beams and joists, channels angles Tees,
flats, with connecting plates or angle cleats as in main and cross beams. Hip and jack rafters,
purlins conneted to common rafters etc completed as directed by architect / Engineer In
The structured steel work shall conform to M-22. Red lead paint shall conform to I.S : 102-1962.
2.0. Workmanship
2.1. The steel sections as specified or required, shall be cut, square and to correct lengths, as per
drawings and design. The .cut ends exposed to view shall be finished smooth. No two pieces shall be
welded or otherwise jointed to make up the required length of member, except as indicated in the
drawing or as directed. All straightening and shaping to form shall be done by application of pressure
and not by hammering. Any bending or cutting shall be carried out in suet] a manner as not to impair
the strength of the metal. All operations shall be done in cold state unless otherwise
directed/permitted.
2.2. Steel riveted or bolted in built up sections, frame work.
2.2.1. The steel structure as shown in the drawings or as per direction of the Engineer-in-charge shall
be laid out on a level platform to full scale and to full size in parts. A steel tape shall be used for
measurements to ensure maximum accuracy.
2.2.2. Wooden templates 12 mm. to 19 mm. thick or metal sheet template shall be made to
correspond to each connecting gussets plate and rivet holes shall be accurately marked on them and
drilled. The templates shall be laid on the steel members and holes of the steel members shall also be
marked for curing. The base of steel column and the .position of Anchor bolts shall be carefully set
2.2.3. Ail stiffeners shall be formed by pressure and where practicable the metal shall not to be cut
and welded in making these. In major work', or whore so specified, shop drawings giving complete
details and information for the fabrication of the component parts of the structure including location,
type, size, (origin and details or rivets, bolts or weld shall be prepared in advance of the actual
fabrication and as distinctly marked or stenciled with paint with the identification mark as given in the
stop drawings. The bars shall be thickened at the ends, so as to provide for screwed threads and
gradually tapered off to meet their normal section.
Great accuracy shall be observed in fabrication of various member, so that these can be assembled
without being unduly packed, stained, or forced into position and when build up, shall be true and tree
from twists, brinks, buckles, or open joints.
Before making holes in individual members for fabrication the steel work intended to be riveted or
belted together shall be as ambled or clamped properly and tightly so as to ensure close abutting or
lapping or the surfaces of the different members. All softeners shall bear tightly both at top and
bottom without being drawn or caulked. The abutting joints shall be cut or crossed true and straight
and fitted close together. Web splice plates and tillers under stiffened shall be cut to fit within 3 mm.
or flange Angles Web plates of Girders shall have no cover. Plates, shall have their ends flush with the
top of angles forming the flanges unless otherwise required. The web plates when spiced ^.hall have
clearance of not more than 6 mm. The erection, clearance for created ends of members connecting
steel shall preferably be not greater than i.5 mm. The erection clearance at the ends o' beams without
web cleats shall not be more than 3 mm. at each end but where for a practical reason greater clearance
is necessary, suitably designed seating shall be provided.
Pains and rollers shall be accurately tuned to gauge. These straight and smooth and free from flows.
The roller bearing shall be provided with adequate arraignments fur holding the girders or truss
resting on it. In columns caps and bases, the ends of shifts together with the attached gussets Angles,
channels etc after riveting together shah be accurately mechanized so that the parts connected butt
against each other over the entire surfaces of contact connecting angles or channels shall he fabricated
and placed in position with greater accuracy so that they are nut unduly reduced in thickness by
machining. The ends of bearing stiffeners shall be mechanized or ground to tit tightly both at the top
and bottom, Alt holes shall generally be drilled to the required size and at required, position. Sub
punching shall be permitted provided it is done 3 mm. or less in diameter and reamer thereafter to the
require size. The holes for rivets and bolts shall be larger by 0 4. to 6 mm. than the nominal diameter
of rivets or black holts depending upon me diameter of rivets.
Holes shall have their axis perpendicular to the surface bored through. The drilling or remarrying shall
be free from burrs, and the holes should be clean and accurate holes for counter sunk bolts shall be
made in such a mariner that their heads fit flush with the surface after fixing.
The fabrication work shall be completed in workshop as far as it is practicable to do so. Site joints
shall be done with rivets and fitted bolts or black bolts, as shown in the drawings or as directed.
Generally the following principles shall govern the use of reverts turned and fitted bolts, and block
(i) Rivets and turned and fitted bolts shall be used where the connections is such that slip under
load has to be avoided.
(ii) Black bolts may be used very sparingly where a force is carried through a connection without
impact, vibration or reversal or stresses.
2.2.4. Riveting:
The parts assembled for riveting shall be in close contact with each other and the bearing stiffeners
shall bear tightly both at top and bottom without being drawn or caulked. Members to be riveted shall
be properly pinned or bolted and rigidly held to gather while riveting. Drifting of holes shall no! be
permitted Except to draw the parts together and the drifting tools so used shall have maximum
diameter not exceeding, the nominal diameter of rivets or bolls. Drifting done during assembling shall
not distort the metal 01 enlarge the holes.
The shanks of rivets shall project beyond the plate-surface sufficiently so as to fill hole thoroughly
and form the required head after riveting.
The riveting shall be done by hydraulic or pneumatic process. However, where such facilities air not
available, hand riveting may be permitted. The rivet shall be heated red hot, care being taken to
control the temperature of heating so as not to burn the steel. Rivers of diameter less than 10 mm. may
be fitted cold. Rivets shall be of heat finish with heads full and of equal size. All loose, burnt or badly
formed reverts with concentric or deficient heads shall be cut out and replaced. The heads of rivets
shall be central to shanks and shall grip the assembled member firmly. In cutting out rivets, care shall
be taken so as not be injure assembled members, caulking or reequipping shall not be permitted.
For testing rivets, a hammer weighing approximately 0 25 kg shall be used. Both heads of the rivets
shall be tapped, slack rivets will give a hollow sound and a jar.
All rivet heads shall be painted with red lead paint within a week of their fixing.
2.2.5. All bolt heads and nuts shall be hexagonal arid of equal size unless specified otherwise. The
screwed heads shall conform to I.S. 1363-1960 and the threaded surface shall not be tapered. The
bolts shall be of such length so as to project two clear threads beyond the nuts when fixed in position
and these shall lit in the holes without any shakes. The nut shall be fit in the threaded ends of bolts
Where turned and fitted bolts are required to be used in place of rivets shall be provided with washers
not less than 6 mm. thick so that the nut when tightened shall not bear on the unthreaded body of the
bolt Tapered washers shall be provided for all heads and nuts bearing on leveled surfaces. The
threaded portion of the bolt shall not be within the thickness of the parts bolted together, the faces of
the bolt heads and nuts abutting against steel members shall be machine finished. Where there is a risk
of the nut being removed or becoming loose due to vibrations or reversal of stresses, these shall be
secured from slackening by me use of locknuts, spring washers, cross-cutting or hammering down of
threads as directed.
Bolts, nuts, and-washers shall be thoroughly cleaned and dipped m double boiled linseed oil before
use. The whole steel work shall be painted with a coat of priming coat of red lead, as per relevant
specification of painting.
3.0 Mode of measurements & payment
3.1. The steel work shall be measured in general as under:
(a) All work shall be measured on the basis of finished dimensions as fixed at site and measured
net unless specified otherwise.
(b) The weight of steel sections, steel rods, and steel strips in finished work shall be calculated
Hum standard weight on the same basis on which steel is supplied to Contractor by department or
those given in relevant I S : if steel is arranged by the contractor.
(c) The weight of steel plates and strips shall be taken from relevant I.S. based on 7.35 kg./ sq.
meter fur every millimeter sheet thickness if steel is supplied to the contractor by department.
(d) Unless otherwise specified, weight of cleats, brackets, packing pieces, bolts, nuts, washer,
distance pieces, separators, diaphragm gusset (taking overall square dimensions) fish plates etc. shall
lie added to the weight of respective items.
(c) In riveted work allowance is to be made for weight of rivet hands. No deductions shall be
made for rivet or bolts holes excluding holes for anchor or holding down bolts.
(I) For forged steel and steel castings, weight shall be calculated on the basis of 7850 kg./cum.
(y) Unless otherwise specified, no allowance shall be made for the weld metal in case of welded
steel structure.
(i) Dimensions other than cross sections and thickness of plates shall be measured to nearest
(j) Mill tolerance shall be ignored when weight is determined by calculation.
3.2. The rate includes cost of all material, labour, erection, hoisting scaffolding, protective
measure, required for proper completion of the item of work. This shall also include conveyance and
delivery handling, loading, unloading and storing etc. required for completing the item described
above including necessary wastage involved.
3.3. The rate shall be for a unit of one quintal.
Painting two coats (excluding priming coat) on new steel and other metal surface with
enamel paint, brushing, interior to give an even shade including cleaning the surface an even
shade including cleaning the surface of all dirt, dust and other foreign matter etc. complete
as directed by Engineer Incharge.
The enamel pain shall conform to M-44 B.
2.0. Workmanship
2.1. General : The materials required for work of painting work shall be obtained directly from
approved manufactures or approved dealer and brought to the site in maker's drums; kegs. etc. with
2.1.2. All materials not in actual use shall be kept properly protected, lids of containers shall be kept
closed and surface of paint in open or partially open containers covered with a thin layer of turpentine
to prevent formation of skin. The materials which have become state or flat due to improper and long
storage shall not be used. The paint shall be stirred thoroughly in its container before pouring into
small containers. While applying also, the paint shall be continuously stirred in smaller container. No
left over paint shall be put back into stock tins. When not in use the containers shall be kept properly
2.1.3. If for any reasons, things is necessary, the brand of thinner recommended by the manufacturer
2.1.4. The surface to be painted shall be thoroughly cleaned and dusted. All rust, dirt and grease shall
be thoroughly removed before painting is started. No painting on exterior or other exposed part o the
work shall be carried out in wet, damp or otherwise unfavorable weather and all the surfaces shall be
thoroughly dry before painting work is started.
2.2. Application of paint:
2.2.1. Brushing operations are to be adjusted to the spreading capacity advised by the manufacture of
particular paint. The paint shall be applied evenly and smoothly by means of crossing and laying off.
The crossing and laying off consists of covering the area over with paint, brushing the surface hard for
the first time over and then brushing alternately in opposite directions two or three times and then
finally brushing lightly in a direction at right angles to the same. In this process, no brush marks shall
be left after the -laying off is finished. The full process of crossing and laying off will constitute one
2.2.2. Each coat shall be allowed to dry completely and lightly rubbed with very fine grade of sand-
paper and loose particles brushed off before next coat is applied. Each coat shall vary slightly in shade
and shall be got approved from Engineer-in-charge before next coat is started.
2.2.3. Each coat the last shall be lightly rubbed down with sand paper of fine pumice stone and
cleaned of dust before the next coat is applied. No hair marks from the brush of clogging of paint
puddles in the corners of panels, angles of moldings etc. shall be left on the work.
2.2.4. Special care shall be taken while painting over bolts, nuts, rivets, overlaps etc. Approved best
quality brushes shall be used.
3.0. Mode of measurements and payment
3.1. The relevant specifications of item No. 19.12 shall be followed for mode of measurements and
payment. The rate is excluding priming coat.
3.4. The rate shall be for a unit of One sq. meter.
19.15. Extra over item No. 19.7 and 19.11 for every subsequent coat of paint.
1.0. Materials and Workmanship
1.1. The relevant specifications of item No. 19.7 shall be followed except that the work of painting
shall be carried out for subsequent coat.
2.0. Mode of measurements and payment
2.1. The relevant specifications of item No. 19.7 shall be followed except that the extra rate shall
be paid for every subsequent coat of paints applied over and above the rate of item No. 19.7 and
2.2. The rate shall be for a unit of One sq. meter.
Providing and fixing S.S. (8% nickel, SS304) PIPE RELLING of 0.90m height as pattern
shown in drawings at STAIRCASE with anchoring 0.075m in RCC or masonry including
50mm dia. SS pipe 18 gauge @ 1.40 kg./m as hand rail, 40x40mm SS pipe 18 gauge @
kg./m as vertical support and 16mm dia. SS pipe 18 gauge @ 0.45 kg./m as intermediate
horizontal member including welding, grinding, fixing in position with necessary fixtures
and fastenings (25mm bracket, base SS cap 50mm dia. hole, base SS cap 40x40mm hole, SS
pipe cap 16mm hole & 16mm long) and polishing etc. complete as per detailed drawings &
directed by E.I.C.
The rate shall be on Running metre basis of railing. The rate shall include providing and fixing all
pipe railing work with necessary jointing welding labour for fixing the in position, etc. complete
Whole work should be carried out as per requirement and as directed by Engineer-in-charge. All steel
pipes shall be used 304 grade.
It should be carried out as follows.
Providing and fixing S.S. (8% nickel, SS304) PIPE RELLING of 0.90m height as pattern shown in
drawings at STAIRCASE with anchoring 0.075m in RCC or masonry including 50mm dia. SS pipe
18 gauge @ 1.40 kg./m as hand rail, and 16mm dia. SS pipe 18 gauge @ 0.45 kg./m as intermediate
horizontal member including welding, grinding, fixing in position with necessary fixtures and
fastenings (base SS cap 50mm dia. hole, SS pipe cap 16mm hole & 16mm) and polishing etc.
complete as per detailed drawings & directed by E.I.C.
The Item shall be measured and paid as finished work on Running Metre basis.
Providing & fixing on roof pressed clay tile (Mangalore tile) of 20 mm nominal thickness and
of approved size and as per approved pattern on steel frame work complete (steel frame
work to be paid separately).
(1) Mangalore pattern roof tiles shall conform to M-25, (2) Teak wood batten shall conform to M-29.
2.0. Workmanship
The maximum distance between centre to centre of rafters shall be not more than 500 mm. Teak
wood reapers 50 mm. x 25 mm. be nailed to each rafter at central distances suited to the size of the
tilesby means of nails 50 mm. long. The reapers shall bje of well seasoned teak wood and shall be
straight pieces of uniform size and colour and not shorter than the length necessary to cover at least
four rafter. The under face and sides of the reapers shall be planned before fitting up. Joints shall
come over the rafter. The joints of two adjacent rows of reapers shall not come over the same rafter.
At the eaves, there shall be two reapers of such thickness and shape that the uniformity of the top
slope of the roof shall be preserved.
2.2. The work of valleys shall be executed as under :
Galvanized iron sheet 1200 mm. wide and 1.25 mm. thick shall be used for valleys. The sheet shall be
extended by about 450 mm. under the tiles on either side in a depth of 100 mm. at centre. The sheet
shall be carried 75 mm. into the wall and set with cement mortar unless flushing is specified. The
laps, if any, on the slope shall be 300 mm. The sheets shall be laid over the reapers and nailed. Two
reapers 50 mm x 25 mm. each shall be fixed over the galvanized iron sheet 150 mm. away from the
centre line of the valley, on either side to keep the tiles and mortar from falling into the gutter of the
The tiles shall be laid from the eaves towards the fudges after fitting of the reapers, the rebate of the
tiles resting fully against the reapers. The joints of the hips and ridges tiles and also those between
them and the plain tiles shall be set in and well grouted with lime mortar and the mortar surface
painted and finished off with a mixture of red paint and port land cement or preserve informality of
colour. The finished slope of roof shall be uniform from ridges to eaves. The eaves line shall be
perfectly straight, horizontal and parallel to each other. The end over gales shall be protected by lime
borders and neatly finished.
2.4. At the side of valleys and for 230 mm. on either side of the roof at valleys cement plastering
12 mm. thick shall be done to prevent the rain water from the gutter leaking by the sides of valleys.
2.5. At the eaves, wide tie shall be placed over the ends of the last tiles and secured by means of
galvanized iron washers and screws 25 mm. into the rafter to prevent tiles from being blow up. Care
shall be taken to put the screws in the, ridges and not in the gutter or the tiles, Where full tiles are not
necessary, half tiles manufactured for the purpose shall be used.
3.0. Mode of measurements and payment
3.1. The measurement of the roof shall be taken for finished work for superficial area flat in the
plane, of the roof and not girthed. Laps shall not be measured.
3.2. No deduction in measurements of roofed shall be made for openings of area up to 0.40 sq. mt.
nor shall any extra be paid for labour and wastage in forming such openings.
3.3. The rate includes the cost of all materials and labour including ridges, hips, eaves and
3.4. The rate shall be for a unit of one square meter.
LOUVERS: Supplying and Installation of GI 84C powder coated louvers etc complete as per
drawing& selection as directed by Architect/Engineer incharge.
Panel details (galvanized steel):
Metalium make 84 R ,Round edge panels,84mm wide x15mmdeepx length up to 5 meter formed out
of 0.50mm thick(TCT) Galvanized steel as per IS -513 fixed on louvers carriers.panels shall be power
coated on exterior surface.
Carrier ,20mm wide at the bottom x39 mm deep formed out of 0.5mmthick galvanized steel sheet
stove enameled black with protruding ears to hold the panels in module of 100mm .
GS clit shall be fixed on vertical columns with dash fasteners at distance not more than 1mtr.center to
center on which tubular stud section will be laid with corrosion proof screw and on this rigid structure
carrier shall be fixed vertically at distance of 1meter .center to center .panel shall be clipped to black
Lovers as per drawing& selection as directed by Architect/Engineer in charge.
Mode of measurement:
The item shall be measured as finished work in square meter.
Supplying & installing M.S Pyre etc complete as directed by EIC
S. No. Particulate Specification
01 Cremation Pyre C.I. Pyre approximately weight 700 kg suitable for I.W.C. to
(Bearing Temp. 900 be fixed at least 6 inch into the ground, pyre size
meter long, 1.00 meter wide and 1.30 meter height o
Degree Celsius )
perforated plate. Made up of Cast Iron Alloy & Supported
on mild steel channels and angels
Ash collection trays shall be fabricated with 20 gauge
Ash handling Tray stainless steel (SS) sheet of grade 316. Minimum dimension
02 of the trays shall be 2200 mm x 800 mm x 150 mm.
(Customer Scope)
Ash Collection Tray Rack shall have suitable dimensions
Ash collection Tray Rack to store minimum 4 Ash collectiontray, made of Mild Steel
03 with pre‐coated GI sheet (24G) topping.
(Customer Scope)
Art painting on wall as per suggestion by architect incharge.
Art painting work per drawing& selection as directed by Architect/Engineer in charge.
Mode of measurement:
The item shall be measured as finished work in square meter.
Providing & Fixing Terracotta jali as per selection by Architect/Engineer incharge.
Providing & Fixing Terracotta jali as per selection by Architect/Engineer incharge.
Mode of measurement:
The item shall be measured as finished work in square meter
Big Sculpture: Providing and constructing and fixing on site 3D structure of required
material(Approvedby consultant) including M-150 PCC base and M250 required pedestal, as
per photo,drawing and instructions of EIC/Consultant.All complete job as directed.Theme
base Elements or Structures:- Providing, moulding, fabricating, sculpting, constructing,
finishing, painting and installing fibre/ FRP/ Metel/ Stone/ Ferro cement/ Concrete/ Glass
fibre reinforced concrete( GRC) Elements/Sculptures installation on site including all civil
work required for installation as per instruction of EIC/ Consultants. The
Elements/Sculptures installation made out of fibre/ FRP/ Matel/ Stone/ Ferro cement/
Concrete/ Glass Fibre reinforced concrete( GRC) shall also include required sub elements
made and installed in required material and finish, all complete. The Elements/Sculptures
installation shall have internal supports structure of mild steel angles, pipes, box sections etc.
of required size and thickness.The Elements/Sculptures installation shall be finished with
weatherproof auto paint (metallic if required) in multi tone/ fully colored effects if required.
The Elements/Sculptures installation shall be devloped based on photograph/image/artist's
impression/drawing of an approved theme and as mutually agreed by clients, consultant as
well as selected agency. The Elements/Sculptures installation shall have an approximate size
as mentioned below and pedestal height of minimum 1.2m/as required as agreed
upon/instructed by the clients and consultant. The agency shall present mecquettes of all
Elements/Sculptures installation before execution for approval by Architect Consultant. size
as per detail drawing and selection by architect/EIC & Sample mock up shall be approved
from architect /E.I.C (5 years warrenty /guranntee certificate)
Providing and constructing and fixing on site 3D structure of required material(Approvedby
consultant) including M-150 PCC base and M250 required pedestal, as per photo,drawing and
instructions of EIC/Consultant.
All complete job as directed.Theme base Elements or Structures:- Providing, moulding,
fabricating, sculpting, constructing, finishing, painting and installing fibre/ FRP/ Metel/ Stone/
Ferro cement/ Concrete/ Glass fibre reinforced concrete( GRC) Elements/Sculptures installation on
site including all civil work required for installation as per instruction of EIC/ Consultants. The
Elements/Sculptures installation made out of fibre/ FRP/ Matel/ Stone/ Ferro cement/ Concrete/
Glass Fibre reinforced concrete( GRC) shall also include required sub elements made and installed
in required material and finish, all complete.
The Elements/Sculptures installation shall have internal supports structure of mild steel angles,
pipes, box sections etc. of required size and thickness.The Elements/Sculptures installation shall be
finished with weatherproof auto paint (metallic if required) in multi tone/ fully colored effects if
The Elements/Sculptures installation shall be devloped based on photograph/image/artist's
impression/drawing of an approved theme and as mutually agreed by clients, consultant as well as
selected agency. The Elements/Sculptures installation shall have an approximate size as mentioned
below and pedestal height of minimum 1.2m/as required as agreed upon/instructed by the clients
and consultant.
The agency shall present mecquettes of all Elements/Sculptures installation before execution for
approval by Architect Consultant. size as per detail drawing and selection by architect/EIC &
Sample mock up shall be approved from architect /E.I.C (5 years warrenty /guranntee certificate)
Mode of measurement:
The item shall be measured as finished work in one number.
Small Sculpture: Providing and constructing and fixing on site 3D structure of required
material(Approvedby consultant) including M-150 PCC base and M250 required pedestal, as
per photo,drawing and instructions of EIC/Consultant.All complete job as directed.Theme
base Elements or Structures:- Providing, moulding, fabricating, sculpting, constructing,
finishing, painting and installing fibre/ FRP/ Metel/ Stone/ Ferro cement/ Concrete/ Glass
fibre reinforced concrete( GRC) Elements/Sculptures installation on site including all civil
work required for installation as per instruction of EIC/ Consultants. The
Elements/Sculptures installation made out of fibre/ FRP/ Matel/ Stone/ Ferro cement/
Concrete/ Glass Fibre reinforced concrete( GRC) shall also include required sub elements
made and installed in required material and finish, all complete. The Elements/Sculptures
installation shall have internal supports structure of mild steel angles, pipes, box sections etc.
of required size and thickness. The Elements/Sculptures installation shall be finished with
weatherproof auto paint (metallic if required) in multi tone/ fully colored effects if required.
The Elements/Sculptures installation shall be devloped based on hotograph/image/artist's
impression/drawing of an approved theme and as mutually agreed by clients, consultant as
well as selected agency. The Elements/Sculptures installation shall have an approximate size
as mentioned below and pedestal height of minimum 1.2m/as required as agreed
upon/instructed by the clients and consultant. The agency shall present mecquettes of all
Elements/Sculptures installation before execution for approval by Architect Consultant. size
as per detail drawing and selection by architect/EIC & Sample mock up shall be approved
from architect /E.I.C (5 years warrenty /guranntee certificate)
Providing and constructing and fixing on site 3D structure of required material(Approvedby
consultant) including M-150 PCC base and M250 required pedestal, as per photo,drawing and
instructions of EIC/Consultant.
All complete job as directed.Theme base Elements or Structures:- Providing, moulding,
fabricating, sculpting, constructing, finishing, painting and installing fibre/ FRP/ Metel/ Stone/
Ferro cement/ Concrete/ Glass fibre reinforced concrete( GRC) Elements/Sculptures installation on
site including all civil work required for installation as per instruction of EIC/ Consultants. The
Elements/Sculptures installation made out of fibre/ FRP/ Matel/ Stone/ Ferro cement/ Concrete/
Glass Fibre reinforced concrete( GRC) shall also include required sub elements made and installed
in required material and finish, all complete.
The Elements/Sculptures installation shall have internal supports structure of mild steel angles,
pipes, box sections etc. of required size and thickness.The Elements/Sculptures installation shall be
finished with weatherproof auto paint (metallic if required) in multi tone/ fully colored effects if
The Elements/Sculptures installation shall be devloped based on photograph/image/artist's
impression/drawing of an approved theme and as mutually agreed by clients, consultant as well as
selected agency. The Elements/Sculptures installation shall have an approximate size as mentioned
below and pedestal height of minimum 1.2m/as required as agreed upon/instructed by the clients
and consultant.
The agency shall present mecquettes of all Elements/Sculptures installation before execution for
approval by Architect Consultant. size as per detail drawing and selection by architect/EIC &
Sample mock up shall be approved from architect /E.I.C (5 years warrenty /guranntee certificate)
Mode of measurement:
The item shall be measured as finished work in one number.
TECHNICAL SPECIFICATIONS FOR FURNITURE WORK
LAMINATE FINISH TABLE (size- 2.0 x1.0 x0.81 m)Providing & fixing laminate finish
table having given size with height of 0.75m (as per attached detail drawing) Table having
40 mm Thick .at top made by 19 mm thick sandwich ply . Top is cantilever then its base
supports. Base supports made by 19 mm thick sandwich ply. A Table having drawers and a
shutter in a pedestal . Drawers rest on telescopic channels. Shutters & drawers having
thickness of 25 mm which are made by 19 mm + 6 mm ply to create conceal grooves as
handle. Drawers sides, Bottom is covered with 19 mm ply & Back of pedestal are made up
of 12 mm thick Ply Wood.
All internal and external surfaces covered by 1mm thick laminate. all complete with given
nos of , drawers on telescopic channels, locks, stoppers, SS Screws,MS nails, Auto hinges,
Cable Manager etc as per shown in detail drawings & as per instructions of
architect/consultant / in charge engineer. Contractor has to provide all necessary cut outs for
Electrical works & no extra payment shall be made for it.
Providing & fixing laminate finish table having given size with height of 0.75m (as per
attached detail drawing) Table having 40 mm Thick .at top made by 19 mm thick sandwich
Top is cantilever then its base supports.
Base supports made by 19 mm thick sandwich ply.
A Table having drawers and a shutter in a pedestal . Drawers rest on telescopic channels.
Shutters & drawers having thickness of 25 mm which are made by 19 mm + 6 mm ply to
create conceal grooves as handle.
Drawers sides, Bottom is covered with 19 mm ply & Back of pedestal are made up of 12 mm
thick Ply Wood.
All internal and external surfaces covered by 1mm thick laminate. A
ll complete with given nos of , drawers on telescopic channels, locks, stoppers, SS Screws,MS
nails, Auto hinges, Cable Manager etc as per shown in detail drawings & as per instructions of
architect/consultant / in charge engineer.
Contractor has to provide all necessary cut outs for Electrical works & no extra payment shall
be made for it.
Mode of measurement:
The item shall be measured as finished work in number.
LAMINATE FINISH BACK LOW HEIGHT STORAGE ( ht1.35m ) Providing & fixing
Laminate Finish side storage having depth of 375 mm , with 18 mm mr grade ply top, based
on sandwidth vertical supports made by 18 mm Thick. mr grade Ply Wood with all shutters
& horizontal single self (made by 18 mm thick MR grade ply) as per given in detail
drawings. Backside of low ht storage is covered with 12 mm thick plywood. Shutters made
with 18 mm + 6 mm ply with conceal handles. All exposed and internal Joints complete with
burma border bidding patti finished with melamine polish. All exposed and internal surfaces
covered with 1 mm thick approved shade laminates as instructed by
Architect/consultant/Engineer in charge. Complete with all hardware like MS nails, ss-304
screws, magnet, Stoppers, L - hinges, 19 mm multilocks, table chain, conceal handles etc
Providing & fixing Laminate Finish side storage having depth of 375 mm , with 18 mm mr
grade ply top, based on sandwidth vertical supports made by 18 mm Thick. mr grade Ply
Wood with all shutters & horizontal single self (made by 18 mm thick MR grade ply) as
per given in detail drawings.
Backside of low ht storage is covered with 12 mm thick plywood. Shutters made with
mm + 6 mm ply with conceal handles.
All exposed and internal Joints complete with burma border bidding patti finished with
melamine polish. All exposed and internal surfaces covered with 1 mm thick approved
shade laminates as instructed by Architect/consultant/Engineer in charge.
Complete with all hardware like MS nails, ss-304 screws, magnet, Stoppers, L - hinges,
mm multilocks, table chain, conceal handles etc
Mode of measurement:
The item shall be measured as finished work in number.
Supplying & installing Perforated Chair etc complete as directed & selection by
Supplying & installing Perforated Chair etc complete as directed & selection by architect/EIC
Mode of measurement:
The item shall be measured as finished work in number.
THREE SEATER SOFA: Providing & Fixing 3 seater Fabric Upholstery sofas. Three seater
overall size -1.70L x0.68B x 0.45H m & SH-450mm. SEAT FOAM: The seat is made of PU
foam with Density 32 ± 2 kg/cu.mtr having an additional top layer of PU foam with Density
28 ± 2 kg/cu. Seat is upholstered with fabric or leatherette. BACK FOAM: The back is made
of PU foam with Density 28 ± 2 kg/cu. mtr with two additional top layer of supersoft foam of
density 23±2 kg/cu. mtr, upholstered with fabric or leatherette. UNDERSTRUCTRE :
Understructure is made up of 1.2±0.1 cm. thick hot pressed plywood. Dia 4mm zigzag spring
assembly is mounted in understruCture for support and additional cushioning purpose. LEG
ASSEMBLY: It is a welded assembly made in Stainless steel (grade SS 202) tube & plate.
The rate shall include all materials, hardware and labour etc. complete as per instruction of
engineer-in charge and consultant. Approved Make: Godrej / Herman Miller / Haworth /
Providing & Fixing 3 seater Fabric Upholstery sofas.
Three seater overall size -1.70L x0.68B x 0.45H m & SH-450mm. SEAT FOAM: The seat
is made of PU foam with Density 32 ± 2 kg/cu.mtr having an additional top layer of PU
foam with Density 28 ± 2 kg/cu. Seat is upholstered with fabric or leatherette.
BACK FOAM: The back is made of PU foam with Density 28 ± 2 kg/cu. mtr with two
additional top layer of supersoft foam of density 23±2 kg/cu. mtr, upholstered with fabric or
UNDERSTRUCTRE : Understructure is made up of 1.2±0.1 cm. thick hot pressed
plywood. Dia 4mm zigzag spring assembly is mounted in understruCture for support and
additional cushioning purpose. LEG ASSEMBLY: It is a welded assembly made in
Stainless steel (grade SS 202) tube & plate. The rate shall include all materials, hardware
and labour etc.
complete as per instruction of engineer-in charge and consultant. Approved Make: Godrej /
Herman Miller / Haworth / Knoll.
Mode of measurement:
The item shall be measured as finished work in number.
HIGH BACK CHAIR Providing & Fixing High Back Chair of Overall size-
763W*763D*1009-1229H*434-554SH mm Cushion Chair :The seat and back are made up of
1.2 ±0.1em. thick hot pressed plywood measured as per QA method described in OCP-
QLTA-P14-18 and upholstered with fabric and moulded Polyurethane foam with PVC
lipping all around. The back foam is designed with contoured lumbar support for extra
comfort.(HIGH BACK) SIZE:49.5cm. (W) X 69.5cm. (H) SEAT SIZE: 49.5cm. (W) X
43.0cm. The HR polyurethane foam is moulded with density =4S+/-2 kg/m3and hardness
load 16 ± 2 kgf as per IS:7888 for 2S% compression.The one-piece armrests made of black
integral skin polyurethane with SO-70Shore Hardness and reinforced with M.S. insert. The
armrests are scratch and weather resistant. The armrests are fitted to the seat with seat
armrest connecting bracket made of 0.3 ±0.022cm. thk. HR steel.The center pivot
mechanism is designed with the following features:360° revolving type.17° ±2°maximum tilt
on pivot at cerntre.Tilt tension adjustmen.Upright position locking.The pneumatic height
adjustment has an adjustment stroke of 12.0 ±0.3cm.The bellow is 3 piece telescopic type and
injection moulded in black Polypropylene.The pedestal is injection moulded in black 33%
glass-filled Nylon-66 and fitted with S nos. twin wheel.castors. The pedestal is
±0.Scm.(76.3 ±1.0 cm with castors).The twin wheel castors are injection moulded in Black
Nylon.The rate shall include all materials, hardware and labour etc.Fixed Arms, Centre tilt
Mechanism, Nylon Padestal complete as per instruction of engineer-in charge and
HIGH BACK CHAIR Providing & Fixing High Back Chair of Overall size-
763W*763D*1009-1229H*434-554SH mm Cushion Chair :The seat and back are made up
of 1.2 ±0.1em. thick hot pressed plywood measured as per QA method described in OCP-
QLTA-P14-18 and upholstered with fabric and moulded Polyurethane foam with PVC
lipping all around.
The back foam is designed with contoured lumbar support for extra comfort.(HIGH
BACK) SIZE:49.5cm. (W) X 69.5cm. (H) SEAT SIZE: 49.5cm. (W) X 43.0cm. The HR
polyurethane foam is moulded with density =4S+/-2 kg/m3and hardness load 16 ± 2 kgf as
per IS:7888 for 2S% compression.The one-piece armrests made of black integral skin
polyurethane with SO-70Shore Hardness and reinforced with M.S. insert.
The armrests are scratch and weather resistant. The armrests are fitted to the seat with seat
armrest connecting bracket made of 0.3 ±0.022cm. thk. HR steel.The center pivot
mechanism is designed with the following features:360° revolving type.17° ±2°maximum
tilt on pivot at cerntre.Tilt tension adjustmen.Upright position locking.The pneumatic
height adjustment has an adjustment stroke of 12.0 ±0.3cm.The bellow is 3 piece telescopic
type and injection moulded in black Polypropylene.The pedestal is injection moulded in
black 33% glass-filled Nylon-66 and fitted with S nos. twin wheel.castors.
The pedestal is 66.3 ±0.Scm.(76.3 ±1.0 cm with castors).The twin wheel castors are
injection moulded in Black Nylon.The rate shall include all materials, hardware and labour
etc.Fixed Arms, Centre tilt Mechanism, Nylon Padestal complete as per instruction of
engineer-in charge and consultant.
Mode of measurement:
The item shall be measured as finished work in number.
VISITOR CHAIR :- Providing & Supplying of visitor Chairs, having single touch
adjustable seat , Frame construction should be of nylon & black in color having dimenssion
of 1200mm Ht., 475mm width & 431 mm Depth & Back cushion Ht. sholud be 535 mm. It
should have Nylon base Arms, Armrest is T fixed.having ht. of 260mm, It should have
minimum 5 years warranty. Complete as per instructions given by the Architect & Engineer
Incharge & as per shown in the View. Samples should be approved by the Architect &
Engineer Incharge. Please see the Attached Make List for Apporoved Makes.like wipro,(
Model : Smart Fabric :- Plano - Delta)
Providing & Supplying of visitor Chairs, having single touch adjustable seat , Frame
construction should be of nylon & black in color having dimenssion of 1200mm Ht.,
475mm width & 431 mm Depth & Back cushion Ht. sholud be 535 mm.
It should have Nylon base Arms, Armrest is T fixed.having ht. of 260mm, It should have
minimum 5 years warranty.
Complete as per instructions given by the Architect & Engineer Incharge & as per shown in
the View. Samples should be approved by the Architect & Engineer Incharge.
Mode of measurement:
The item shall be measured as finished work in number.
MEDIUM BACK CHAIR Providing & Fixing Mid Back Chair of Overall size-
763W*763D*784-904H*434-554SH mmCushion Chair :The seat and back are made up of
1.2 ±0.1em. thick hot pressed plywood measured as per QA method described in OCP-
QLTA-P14-18 and upholstered with fabric and moulded Polyurethane foam with PVC
lipping all around. The back foam is designed with contoured lumbar support for extra
comfort..(MID BACK) SIZE: 49.5cm. (W) X 45.5cm. (H)*SEATSIZE: 49.5cm.(W)X 43.0cm.
(D) The HR polyurethane foam is moulded with density =4S+/-2 kg/m3and hardness load
± 2 kgf as per IS:7888 for 2S% compression.The one-piece armrests made of black integral
skin polyurethane with SO-70Shore Hardness and reinforced with M.S. insert. The armrests
are scratch and weather resistant. The armrests are fitted to the seat with seat armrest
connecting bracket made of 0.3 ±0.022cm. thk. HR steel.The center pivot mechanism is
designed with the following features:360° revolving type.17° ±2°maximum tilt on pivot at
cerntre.Tilt tension adjustmen.Upright position locking.The pneumatic height adjustment
has an adjustment stroke of 12.0 ±0.3cm.The bellow is 3 piece telescopic type and injection
moulded in black Polypropylene.The pedestal is injection moulded in black 33% glass-filled
Nylon-66 and fitted with S nos. twin wheel.castors. The pedestal is 66.3 ±0.Scm.(76.3 ±1.0 cm
with castors).The twin wheel castors are injection moulded in Black Nylon.The rate shall
include all materials, hardware and labour etc. complete as per instruction of engineer-in
charge and consultant.
Providing & Fixing Mid Back Chair of Overall size- 763W*763D*784-904H*434-554SH
mmCushion Chair :The seat and back are made up of 1.2 ±0.1em. thick hot pressed
plywood measured as per QA method described in OCP-QLTA-P14-18 and upholstered
with fabric and moulded Polyurethane foam with PVC lipping all around. The back foam is
designed with contoured lumbar support for extra comfort..(MID BACK) SIZE: 49.5cm.
(W) X 45.5cm. (H)*SEATSIZE: 49.5cm.(W)X 43.0cm. (D) The HR polyurethane foam is
moulded with density =4S+/-2 kg/m3and hardness load 16 ± 2 kgf as per IS:7888 for 2S%
compression.The one-piece armrests made of black integral skin polyurethane with SO-
70Shore Hardness and reinforced with M.S. insert.
The armrests are scratch and weather resistant. The armrests are fitted to the seat with seat
armrest connecting bracket made of 0.3 ±0.022cm. thk. HR steel.The center pivot
mechanism is designed with the following features:360° revolving type.17° ±2°maximum
tilt on pivot at cerntre.Tilt tension adjustmen.Upright position locking.The pneumatic
height adjustment has an adjustment stroke of 12.0 ±0.3cm.
The bellow is 3 piece telescopic type and injection moulded in black Polypropylene.The
pedestal is injection moulded in black 33% glass-filled Nylon-66 and fitted with S nos. twin
The pedestal is 66.3 ±0.Scm.(76.3 ±1.0 cm with castors).The twin wheel castors are
injection moulded in Black Nylon.The rate shall include all materials, hardware and labour
etc. complete as per instruction of engineer-in charge and consultant.
Mode of measurement:
The item shall be measured as finished work in number.
TECHNICAL SPECIFICATIONS FOR DEMOLITION WORK
Demolition including stacking of serviceable materilas and disposal of unserviceable
materials with all lead and lift. (i) R.C.C. work
1.0. Workmanship
1.1. The demolition shall consist of demolition of one or more parts of the building as specified or
shown in the drawings. Demolition implies taking up or down or breaking up. This shall consist of
demolishing whole or part of work including all relevant items as specified or shown in the drawings.
1.2. The demolition shall always be planned before hand shall be done in reverse order to the one
in which the structure was constructed. This scheme shall be got approved form the Engineer-in-
charge before starting the work. This however will not absolve the contractor from the responsibility
of proper and safe demolition.
1.3. Necessary propping, shoring and under pinning shall be provided for the safety of the
adjoining work or property, which is to be left intact, before dismantling and demolishing is taken up
and the work shall be carried out in such a way that no damage is caused to the adjoining property.
1.4. Wherever required, temporary enclosures or partitions shall also be provided. Necessary
precautions shall be taken to keep the dust nuisance down as and where necessary.
1.5. Dismantling shall be commenced in a systematic manner. All materials which are likely to be
damaged by dropping from a height or demolishing roof, masonry etc. shall be carefully dismantled
first. The dismantled articles shall be properly stacked as directed.
1.6. All materials obtained from demolition shall be the property of Government unless otherwise
specified and shall bee kept in safe custody until handed over to the Engineer-in-charge.
1.7. Any serviceable materials, obtained during dismantling or demolition shall be separated out
and stacked properly as directed with all lead and lift. All unserviceable materials, rubbish etc., shall
be stacked as directed' by the Engineer-m-charge.
1.8. On completion of work, the site shall be cleared of all debris rubbish and cleaned as directed.
2.0. Mode of measurements and payment
2.1. Measurements of all work except hidden work shall be taken before demolition or dismantling
and no allowance for increase in bulk shall be allowed. The demolition of lime concrete shall be
measured under this item. Specification for deduction for voids, openings etc. shall be on same basis
as that employed for construction of work,
2.2. All work shall be measured in decimal system as fixed in its place subject to the following
limits; unless otherwise stated hereinafter : (a) Dimensions shall be measured to the nearest 0.01 mt.
(b) Area shall be worked out to the nearest 0.01 sq. mt.(c) Cubical contents shall be worked out to the
nearest 0.01 Cu.m.
2.3. The rate shall include cost of all labour involved and tools used in demolishing and
dismantling including scaffolding. The rate shall also include the charges for separating out and
stacking the serviceable materials properly and disposing the unserviceable materials with all lead
and lift. The rate also includes for temporary shoring for the safety of the portion not required to be
pulled down or of adjoining property arid providing temporary enclosures or portions where
considered necessary.
2.4. The rate shall be for a unit of one cubic meter.
Demolition of Brick work and stone masonry including stacking of serviceable materilas and
disposal of unserviceable materials with all lead and lift.(ii) In Cement Mortar
1.0. Workmanship
1.1. The relevant specifications of item No. 20.1.(i) .shall be followed except that demolition of
brick or stone masonry in lime mortar is to be done.
2.0. Mode of measurements and payment
2.1. The relevant specifications of item No. 20.1(i) shall be followed except that the wall and
independent piers or columns of brick or stone masonry shall be measured in cubic meters. All
copings, corbels, comics and other projections shall be included with the wall measurements.
2.2. In measuring thickness of plastered walls, the thickness of plaster shall be included. The
unserviceable materials shall be disposed off with all lead and lift. Ashlars face stones dressed stone
etc., if required to be taken down intact shall be dismantled and measured separately in cubic meters.
2.3. The rate is exclusive of cleaning of bricks or stones. Honey comb works or hollow block
walling shall be measured as solid.
2.4. The rate shall be for a unit of one cubic meter.
Dismentaling tiled of stone floors/dedo wall laid in mortar including stacking of serviceable
materilas and disposal of unserviceable materials with all lead and lift.
1.0. Workmanship
1.1. The relevant specification of item 70 shall be followed except the dismantling of tiled or stone
floors laid on mortar shall be done. Dismantling implies carefully taking up or down or removing
without ^damage. The articles shall be passed by hand where necessary and lowered and where these
are fixed by nail, screws, bolts etc., these shall be taken out with proper tools.
2.0. Mode of measurements and payment
2.1. The supporting materials such as joints, beams if any etc. shall be measured separately. The
relevant specifications of item No. 70 shall be followed, The rate shall include staking the
unserviceable materials as directed with all lead and lift.
2.2. The late shall be for a unit of one sq. meter
Dismentling doors, windows, ventilators etc. (wood or steel) shutters including chowkhats
architraves, holdfasts and other attachment etc. complete and stacking them within all lead
and lift.(ii) Exceeding 3 Sq.M. in area.
1.0. Workmanship
The relevant specifications of item No. 70 shall be followed except that the door, windows,
ventilators etc. (wood or steel) shutters including chowkhats, architraves, hold fasts and other
attachments etc. are to be dismantled.
2.0. Mode of measurements & payment
2.1. The relevant specifications of item No. 70 shall be followed.
2.2. The doors, windows, ventilator etc. not exceeding 3 sq. mt. in area (each) including shutters
and chowkhats. Architraves, hold fasts and other attachments to frames etc. will be-^mantled and
measured under this item.
2.3. The rate includes stacking the serviceable materials as and where directed with all leads and
2.4. The rate shall be for a unit of One number.
Dismentaling of sheet roofing including ridges,Hips, Valleys, Gutters etc. stacking of
serviceable materilas and disposal of unserviceable materials with all lead and lift.(i)
G.I.sheet roofing.
1.1. The relevant specifications of item 70 shall be followed except that G.I. sheet roofing shall be
dismantled instead of concrete work.
2.0. Mode of measurements and payment
2.1. The area of G.I. sheets roofing shall be measured in sq. meter. Ridges, hips and valleys shall
be girded and included with roof area. Corrugated and semi-corrugated surfaces shall be measured
flat and not girthed.
2.2. Supporting members such as rafters, purlins, beams, joints, trusses etc. shall be measured
2.3. The rate shall include disposal of unserviceable materials with all leads and lifts and stacking
the serviceable materials as directed.
2.4. The rate shall be for a unit of one sq. meter.
TECHNICAL SPECIFICATIONS FOR ROAD WORK & GARDEN WORK
Graded Granular sub base (GSB)
Providing & laying of compacted thickness of 200 mm Closed Graded Granular sub base
(GSB) of graded granular material consisting of river sand, graval, pabbles and crushed
stone aggregate, shingle as per grading -V given in table 400-1 of the specification MORT&H
and compactor to the required density with 8 - 10 tonne vibratory roller with plain drum or
heavy pneumatic tyred roller of minimum 200 to 300 KN weight in all seasons as per
MORT&H , maintaining the required slope & grade during the operation as approved by
the engineer in charge & watering to the proper moisture content and sprinkled with the
help of truck mounted water tank fitted with suitable arrangement. (fully saturated having
CBR value minimum 30)
Providing & laying of compacted thickness of 200 mm Closed Graded Granular sub base (GSB) of
graded granular material consisting of river sand, graval, pabbles and crushed stone aggregate,
shingle as per grading -V given in table 400-1 of the specification MORT&H and compactor to the
required density with 8 - 10 tonne vibratory roller with plain drum or heavy pneumatic tyred roller of
minimum 200 to 300 KN weight in all seasons as per MORT&H , maintaining the required slope &
grade during the operation as approved by the engineer in charge & watering to the proper moisture
content and sprinkled with the help of truck mounted water tank fitted with suitable arrangement.
(fully saturated having CBR value minimum 30)
Mode of measurement:
The item shall be measured as finished work in cumt..
Providing laying and construction of avrage 250 mm thick Wet Mix Macadam (WMM) in
two layers sub base / base course with graded aggregates confirming to gradings as per the
MORT&H , graded aggregate and granular material premixed with water to a dense mass,
laid by Sensor Paver finisher on a prepared sub-grade / sub-base / base in proper grade and
camber and compated with roller and plate compactor where use of roller is not possible
(widening portions) as per MORT&H (materials to be use only crushed in mechanical
Providing laying and construction of avrage 250 mm thick Wet Mix Macadam (WMM) in two layers
sub base / base course with graded aggregates confirming to gradings as per the MORT&H , graded
aggregate and granular material premixed with water to a dense mass, laid by Sensor Paver finisher
on a prepared sub-grade / sub-base / base in proper grade and camber and compated with roller and
plate compactor where use of roller is not possible (widening portions) as per MORT&H (materials
to be use only crushed in mechanical crushers).
Mode of measurement:
The item shall be measured as finished work in cumt..
Providing and laying in position cement concrete (PCC or RCC) work of mix 1:2:4 (1
Cement : 2 sand : 4 graded stone aggregate 20 mm & down nominal size) in sub structure
for all type of foundations, in floors, wall, pedestals, beam, columns etc. including mixing,
laying, placing, consolidating, vibrating, levelling and curing etc. complete with all tools and
tackles, labour and materials, machineries, excluding the cost of formwork and
reinforcement steel as directed by the EIC. : Ground Beam & Plinth Beam
The item shall be executed as per the relevant specifications & mode of measurement of above item
Providing and laying controlled cement concrete M-250 for RCC work as per detailed
drawings including centering, shuttering (Only Fresh Ply), machine mixing, vibrating,
scaffolding, curing, centering having double or more height wherever required & finishing
etc. but excluding cost of reinforcement etc. complete at all levels for RCC Footing /road
The item shall be executed as per the relevant specifications & mode of measurement of above item
Providing and fixing CAPCELL HD - 100 pre-moulded compressible filler board in black
colour confirming to MoRT&H Specifications (Clause 1015), having minimum density
95kg/cum.metre, non-staining with less than 1% water absorption & compression recovery
of 93% minimum as per specification for 12 mm wide expansion joint including cutting to
required size and shape at all levels etc. complete as directed.
Providing and fixing CAPCELL HD - 100 pre-moulded compressible filler board in black colour
confirming to MoRT&H Specifications (Clause 1015), having minimum density 95kg/cum.metre,
non-staining with less than 1% water absorption & compression recovery of 93% minimum as per
specification for 12 mm wide expansion joint including cutting to required size and shape at all levels
etc. complete as directed.
Mode of measurement:
The item shall be measured as finished work in sqmt.
Providing TMT Bar FE 500D reinforcement for R.C.C. work including bending, binding
and placing in position complete at all floor level.
The item shall be executed as per the relevant specifications & mode of measurement of above item
Supplying and fixing reinforced concrete heavy duty non-pressure pipes with collars for
culverts carrying heavy traffic as per IS 458-1991 specifications including setting the pipes in
C.M. 1:2 watering and laying (to level or slopes) of class NP3 of following internal
daimeters.(ii) 450mm dia.
1.0. Materials : The reinforced concrete light duly non-pressure pipes of specified diameter shall
conform to I.S. 458-1971.
2.0. Workmanship
2.1. The relevant specifications of item No. 24.1. A shall be followed for work of trenches
except that the excavation in trenches shall be for. reinforced concrete pipes of specified diameter.
2.2.1. The pipes shall be lowered into the trenches carefully. Mechanical appliances may be used.
Where necessary pipe shall be laid in straight lines or with easy curves and true to line and gradient as
specified. The laying of pipe shall proceed upgrade of a slope. In the pipe spigot and socket joints, the
socket ends shall face upstream. In case of pipes with joints to be made with loose collars, the collars
shall be slipped on before the next pipe is laid.
2.2.2. In case where the foundation conditions are unusual such as the proximity of trees or holes,
under existing or proposed all round in 150 mm. thick cement concrete 1:5; 10 (1 cement: 5 fine sand
: 10 graded stone aggregate 40 mm. nominal size) or compacted sand or gravel:
2.2.3. In case where the natural foundation is inadequate the pipes shall be laid either in concrete
cradle, supported on proper foundations or on any other suitably designed structure. If concrete
bedding is used, the depth of concrete below bottom of the pipe shall be at least 1/4th of the internal
diameter of the pipe subject to a minimum of 100 mm. and a maximum 300 mm. The concrete shall
be extended up the sides of the pipe at least to a distance of 1/4th of the outside diameter for pipes
300 mm. and over in diameter.
2.2.4. The pipes shall be laid in the concrete bedding before the concrete has set. Pipes laid in
trenches in earth shall be bedded evenly and firmly and as far as up to the haunches of the pipe as to
safely transmit the load expected from the back fill through the pipe to the bed. This shall be done
either by excavating the bottom of the trenches to fit the curve of the pipe or by compacting the earth
under a round curve of the pipe to form an even bed, Necessary provision shall be made for joints
wherever required.
2.3.1. The joints shall be done by slipping the collar over and clear of the end of the pipe. The recess
of the end of the pipe shall be filled with jute braiding in hot bitumen. The new pipe shall then be
brought forwarded until the bitumen ring in recess of first pipe is set into the recess of the second
pipe. The process shall be repeated for two or three pipes which shall then jacked up so as to
thoroughly compress the bitumen. The quantity of jute and bitumen shall be just enough to fill the
recess when pressed hard by jacking, care being taken that no offset of the jute braiding shall be
visible either outside or inside of pipe. The collar shall then be set up over the joints covering equally
both the pipe and leaving, an even caulking space all round. Cement and sand mortar: 1: 1.1/2 shall
then be well punched or pressed home with a caulking tool within this caulking space. Care shall be
taken that the underside of the joints is properly filled with mortar.
2.4.1. Every joints shall be kept wet for about 10 days for maturing. The section of the pipe line laid
and jointed shall be covered immediately to protect from weather effects. Minimum bore of 100 mm.
is considered adequate.
2.4.2. The joints shall be left exposed for observation.
2.5. Testing of Joints :
2.5.1. The testing of joints shall be done as per relevant specifications of item No. 24.1 (A) except
that the testing of reinforced concrete pipes shall be done.
3.0. Mode of measurements & payment
3.1. The relevant specifications of item 24.1 .(A) shall be followed except that the rate includes for
laying to level or slope in trenches etc. (measured separately), making the joints a; Seated and testing
to stand the water test.
3.2. The measurements shall be net without any allowance for cutting and waste. The length of
bends, junctions and other connections (measured along the centre line) shall be included in the total
length of the pipes, the connections being numbered afterwards and paid for extra over pipes.
3.3. The size of bend, junctions, etc, shall suit the size of pipe. The bore (internal diameter of pipe)
shall be the criterion for payment.)(
3.4. Nothing extra shall be paid separately for the use of mechanical appliances, where necessary,
as described above.
3.5. The rate shall be for a unit of One running meter.
Providing and fixing pre-cast Rubber Dye / steel Dye inter locking concrete block 60mm
thick with grade of concrete M300 pnumatic compressed / vibrated mechanically and as per
approved design Confirming to IS 15658 : 2006 including 35 mm Sand layer for levelling and
filling the joint with sand in proper line and level as per guidlines of IRC : SP 63-2018 etc.
Providing and fixing pre-cast Rubber Dye / steel Dye inter locking concrete block 60mm thick with
grade of concrete M300 pnumatic compressed / vibrated mechanically and as per approved design
Confirming to IS 15658 : 2006 including 35 mm Sand layer for levelling and filling the joint with
sand in proper line and level as per guidlines of IRC : SP 63-2018 etc. Complete.
Mode of measurement:
The item shall be measured as finished work in sqmt.
Providing and fixing pre-cast concrete kerb stone of gray cement based concrete block 30cm
length,30cm height and 15cm thick of M250 grade concret as per approved design and
including excavation for fixing in proper line and level,filling the joint with C:M 1:3
(1cement:3fine sand) etc complete.
The kerb shall be a M-25 concrete grade. The min. strength of kerb should not less than 250 Kg/cm2.
The blocks must be manufactured on vacuum wet press type machine with hydraulic pressing of
concrete mixture only.The faces of the kerb shall not exhibit any defects such as cracking or flaking.
The blocks must be cured in controlled environment. The block shall be supplied in uniform size and
shape as approved by Engineer in charge.The size of kerb shall be 60cm length,30cm height and
15cm thick or as directed by engineer in charge.
The concrete mix design should be followed for each batch of materials separately and automatic
batching plant is to be used to achieve uniformity in strength and quality.
Trenches shall first be made along the edge of the wearing course of the road to receive the kerb
stones of cement concrete of specified grade. The bed of the trenches shall be compacted manually
with steel rammers to a firm and even surface and then the stones shall be set in cement mortar of
specified proportion.
The joints of kerb and channel stones shall be staggered and shall be not more than 10 mm. Wherever
specified all joints shall be filled with mortar 1:3 (1 cement : 3 coarse sand) and pointed with mortar
1:3 (1 cement: 3 fine sand) which shall be cured for 7 days. The necessary drainage openings of
specified sizes shall be made through the kerb as per drawings or as directed by the Engineer-in-
Charge for connecting to storm water drains. Finishing Berms and road edges shall be restored and all
surplus earth including rubbish etc. disposed off as directed by the Engineer-in-charge. Nothing extra
shall be paid for this.
This item includes all necessary excavation and filling of joints pointed with mortar 1:3 (1 cement:
fine sand) in line and level. The debris or excavated stuff shall be dispose off as directed by engineer
It shall be measured in running metre along the edge of the road correct to a cm.
Supplying and spreading good earth like firtile soil as directed etc compt.
The item shall be executed as per the relevant specifications & mode of measurement of above item
Supply and planting of saplings of Hedge plants like kadvi mahendi, karmda, dyuranta,
nikodeviya and etc. specifies bag size is 4 inch x 6 inch, well established & free from
disease at site. as per the instructions
Supply and planting of saplings of Hedge plants like kadvi mahendi, karmda, dyuranta, nikodeviya
and etc. specifies bag size is 4 inch x 6 inch, well established & free from disease at site. as per the
Mode of measurement:
The item shall be measured as one number.
Supply and planting of (Jasud, Ixora, Ticoma Gaudi-chaudi, Gultora, Jetropha,
Haemeliya, Chandani, Mogaro, Galfemia, , Allamenda, Desi Gulab, Euphorbia mili, Jasud
Hybrid, Chandani double, Madhukamini, Madhumalti, Ticoma Capensis, Ixora draft,
Nikadevia, English Karen etc.) having height of minimum 2.00 to 2.5 ft. and bag size is
inch x 13 inch, well branched, well established & free from disease at site as per the
Supply and planting of (Jasud, Ixora, Ticoma Gaudi-chaudi, Gultora, Jetropha, Haemeliya,
Chandani, Mogaro, Galfemia, , Allamenda, Desi Gulab, Euphorbia mili, Jasud Hybrid, Chandani
double, Madhukamini, Madhumalti, Ticoma Capensis, Ixora draft, Nikadevia, English Karen etc.)
having height of minimum 2.00 to 2.5 ft. and bag size is 13 inch x 13 inch, well branched, well
established & free from disease at site as per the instructions.
Mode of measurement:
The item shall be measured as one number.
Supply and planting of Diff. Varieties of Palm(Botal palm,foxtel, ) having height of
minimum 10.00 to 12.00 ft. and bag size is 25 inch x 25 inch, well branched, well established
& free from disease at site as per the instructions
Supply and planting of Diff. Varieties of Palm(Botal palm,foxtel, ) having height of minimum
to 12.00 ft. and bag size is 25 inch x 25 inch, well branched, well established & free from disease at
site as per the instructions
Mode of measurement:
The item shall be measured as one number.
LAYING OUT LAWN - After excavating soil upto 30 cm. depth & removing unwanted
stuff, stones etc. Preparing soil for planting by supplying, mixing and 0.5 cmt FYM
maximum 100 sqmt of lawn area and doing termicide @ 1 lit / 100 sqmt area and planting
selection 1 type / English lawn / approved lawn grass at maximum 6 cm x 6 cm distance and
maintain it upto 120 days. Maintainance include all operations i.e. watering, grass cutting,
gap filling, applying of fertizer if require etc.
LAYING OUT LAWN - After excavating soil upto 30 cm. depth & removing unwanted stuff, stones
etc. Preparing soil for planting by supplying, mixing and 0.5 cmt FYM maximum 100 sqmt of lawn
area and doing termicide @ 1 lit / 100 sqmt area and planting selection 1 type / English lawn /
approved lawn grass at maximum 6 cm x 6 cm distance and maintain it upto 120 days. Maintainance
include all operations i.e. watering, grass cutting, gap filling, applying of fertizer if require etc.
Mode of measurement:
The item shall be measured as one sq.mt.
Providing corrugated G.I. sheet of class-3 roofing fixed with glavanished iron J or L Hooks,
Bolts and nuts 8mm diameter with bitumen and G.I. limpet washer or G.I. limpet washer.
filled with white lead complete excluding the cost of purlins, Rafters and Trusses.(1) 0.80 mm
The supporting framework shall be checked for correct line, level, spacing, and alignment before
laying the roofing sheets.
Corrugated G.I. sheets shall be laid with the specified end and side laps, ensuring proper alignment
and adequate slope for drainage.
Sheets shall be fixed securely using 8 mm diameter galvanized iron J or L hooks, bolts and
nuts, complete with G.I. limpet washers and bitumen washers, filled with white lead to ensure
watertight joints.
Holes for fixing shall be drilled accurately and shall not be made by hammering or punching in a
manner that damages the sheets.
Fasteners shall be tightened adequately without over-tightening to avoid distortion or damage to the
Sheets shall be handled carefully during transportation and installation to prevent bending,
scratches, dents, or damage to the galvanized coating.
The completed roofing shall be true to line and level, free from waviness, gaps, loose fixings, or
All cut edges, damaged galvanized surfaces, and fixing points shall be properly treated as directed
by the Engineer-in-Charge.
After completion, the roof shall be cleaned of all debris, metal filings, and surplus materials.
Mode of measurement:
The item shall be measured as one sq.mt.
Boring holes 3.5 m deep in ordinary soil (for cast in situ piles) and getting out the soil and
disposal of the surplus excavated soil as directed within a lead of 50 Meter for following
diameter of pipes.(iii) 300 mm.
The boring location shall be marked accurately as per the approved layout and drawings.
Boring shall be carried out vertically to the required depth of 3.50 m using approved mechanical or
manual boring equipment suitable for 300 mm diameter cast-in-situ piles.
The bore shall be maintained to the specified diameter throughout its depth without collapse of the
The excavated soil shall be removed continuously during boring and disposed of as directed by the
Engineer-in-Charge within a lead of 50 m.
Loose soil, debris, and water (if any) shall be removed from the bore before further construction of
Care shall be taken to avoid disturbance to adjacent structures, foundations, or underground utilities
The completed bore shall be true to line, level, depth, and verticality as specified in the drawings.
Any collapsed or oversized bore due to the contractor's negligence shall be rectified by the
contractor at no extra cost.
The bore shall be inspected and approved by the Engineer-in-Charge before proceeding with
reinforcement or concreting.
Mode of measurements & payment
Measurement shall be made in Number (Nos.) for each completed bore of 300 mm diameter and
3.50 m depth, unless otherwise specified in the Schedule of Quantities.
The rate shall include setting out, boring, removal of excavated soil, disposal of surplus soil within
50 m lead, labour, tools and plants, equipment, handling, and all incidental operations required to
complete the work.
No separate payment shall be made for cleaning the bore, maintaining verticality, temporary
supports (if required), dewatering (where not specifically provided), or disposal of excavated material
within the specified lead.
Reinforcement, concreting, pile caps, and any additional depth beyond the specified 3.50 m shall
be measured and paid for separately under the relevant items.
The completed work shall be measured only after inspection and approval by the Engineer-in-
Extra for under reaming inside the bore Holes for under reamed piles of following
Diameter.(iii) 300 mm
Under-reaming shall be carried out at the specified depth after boring the 300 mm diameter pile
The under-reamed bulb shall be formed to the required size and shape using approved under-
Loose soil and debris shall be removed before reinforcement and concreting.
The completed under-ream shall be true to size and approved by the Engineer-in-Charge.
Mode of measurement:
Measurement shall be made in Number (Nos.).
Providing and filling rubbles including hand packing and filling interstices with quarry
spalls behind abutments and between returns as directed.
Rubbles shall be placed behind abutments and between returns in layers and hand packed tightly.
Interstices shall be completely filled with approved quarry spalls to obtain a dense and stable fill.
Filling shall be carried out to the required line, level, and thickness as directed by the Engineer-in-
The completed filling shall be firm, well-packed, and free from voids.
Measurement shall be made in Cubic Metres (Cum).
Carring out plinth treatment to post construction / existing structure by spraying chemical
solution for termite control treatment including labour and material consistment with I.S.I
specification. Using Chlordene and Chiorpurfiles 20 EC. As Per 6131_paret-II
Consentration Weight one percent is recommended i.e one litre 20 EC chemical emulsion
with 19 liter give 1 %
concrentration inclusive of one litre chemical emulsion appication at the rate of 5 Litre
chemical / Sqm of surface is recommended as per I.S.
The treatment area shall be cleaned and prepared before application of the chemical emulsion.
Holes shall be drilled at suitable spacing around the plinth and chemical solution injected/sprayed
uniformly to achieve complete coverage.
The chemical emulsion shall be prepared using Chlorpyrifos 20 EC (or approved equivalent) in the
proportion specified under IS 6313 (Part II) to obtain 1% concentration.
The emulsion shall be applied at the specified rate of 5 litres per sq.m. of treated surface.
Care shall be taken to ensure continuous chemical barrier without untreated gaps.
The treated area shall be protected from disturbance until the chemical has penetrated the soil.
Mode of Measurement
Measurement shall be made in Square Metres (Sq.m.) of the actual treated plinth area.
Providing and fixing 600mm x 450mm bevelled edge mirrror of superior glass mounted on
6mm thick A.C. sheet or plywood sheet and fixing to wooden pluge with C.P. brass screws
and washers. at all floor level.
The mirror shall be fixed at the specified location, line, level, and height as shown in the drawings.
The 600 mm × 450 mm superior quality bevelled edge mirror shall be mounted securely on a
mm thick A.C. sheet or plywood backing.
The backing shall be fixed to the wall using approved wooden plugs, C.P. brass screws, and
The mirror shall be fixed firmly without cracks, distortion, or visible gaps and shall be aligned true
to plumb and level.
The surface shall be cleaned after installation, leaving the mirror free from stains, scratches, or
adhesive marks.
Mode of measurement:
The item shall be measured as one number.
Providing & Fixing the Chikenmesh - 20 guage(Crimp Jali) of approved size applying
between the RCC and masonry junction in proper line, level and plumb with all material,
labour, tools, tackles and equipment. Including providing and fixing the jali with nails, etc
complete as directed by the site-in-charge. at all floor level.
The RCC and masonry junction shall be cleaned and made free from dust, loose particles, and
20 gauge crimped chicken mesh (jali) of approved size shall be fixed centrally over the RCC and
masonry junction with the required overlap on both sides.
The mesh shall be fixed firmly using approved nails, fasteners, or other suitable fixing
arrangements to prevent displacement during plastering.
The mesh shall be maintained true to line, level, and plumb, free from wrinkles or sagging.
The work shall be completed as directed by the Engineer-in-Charge before commencement of
Mode of measurement:
Measurement shall be made in Square Metres (Sq.m.)
Providing Logo and Letter's Of different sizes Engraved on Black Granite Stone, Painted
with Gold Foil on it. Making a Plaque and Fixing it on the structure etc complete as per
drawings & as directed by EIC
The black granite plaque shall be cut, polished, and finished to the approved size and thickness.
The logo and letters shall be accurately engraved as per the approved drawing and finished with
gold foil/gold paint.
The plaque shall be fixed securely to the structure using approved clamps, anchor fasteners,
adhesive, or stainless steel fixtures as specified.
The plaque shall be installed true to line, level, and plumb without cracks, chips, or visible defects.
After fixing, the surface shall be cleaned, and the engraving shall be neat, clear, and uniformly
Mode of measurement:
Measurement shall be made in Square Metres (Sq.m.).
TECHNICAL SPECIFICATIONS FOR PLUMBING & DRAINAGE WORK
Providing and fixing in position cowel went to pipes.(C) 100mm dia
Item should be include as Providing & Fixing 75 mm d. PVC -U SWR COWL VENT of (FiINOLEX
/ SUPREME) brand of working pressure 4 kg/sq.cm including jointing with adhesive solvent cement
including fixing thensame in true line and level etc complete as directed by EIC.
Mode of measurement:
The rate shall be for a unit of One number.
Providing and fixing Gun metal check or non-return fullway wheel valve.(A) 15mm dia.
1.0. Materials : The gun metal check or not return full way wheel valve or specified dial, shall
conform to I.S. : 778-1964. The non-return valve shall be of tested quality.
2.0. Workmanship
2.1. The gun metal check or non return valve shall be fully cleared of all foreign matter before
fixing. The fixing of shall be done by means of bolts nuts and 3 mm. rubber insertions with flags of
spigot and socketed tail pieces, drilled to the same specifications as in case of socket and spigot
flanges in case of flanged pipes. The joining shall be done leak proof.
3.0. Mode of measurements and payment
3.1. The rate includes all labours, materials, tools and plant etc. required for satisfactory
completion of this item.
3.2. The rate shall be for a unit of One number.
Providing and fixing Gun metal check or non-return fullway wheel valve.(C) 25mm dia.
The item shall be executed as per the relevant specifications & mode of measurement of above item
Providing and fixing Gun metal check or non-return fullway wheel valve.(D) 32mm dia.
The item shall be executed as per the relevant specifications & mode of measurement of above item
Providing and fixing Gun metal check or non-return fullway wheel valve.(D) 40mm dia.
The item shall be executed as per the relevant specifications & mode of measurement of above item
Providing and fixing ball cock of approved. quality as directed.(B) Abonite (ii) 50mm dia.
1.0. Materials & Workmanship : The relevant specifications of item No. 23.00.5 (A) shall be
followed except that the ball cock of specified dia of Ebonite shall be fixed.
2.0. Mode of measurements & payment
2.1. The relevant specifications of item NO. 23.00.5 (A) shall be followed.
2.2. The rate shall be for a unit of One number.
Providing laying and jointing in true line and level 15mm dia. U.P.V.C. Pipe ( SCH- 40) for
cold water including fittings as approved by Engineer In Charge. Pipe shall be fixed on the
wall with the help of clamp at every two metre C/C or shall be concealed as directed
including necessary fittings etc. including testing of pipe and joints and fixing the same with
adhesive solvent, including cost of all materials.
1.1. The low density polythene pipe of specified diameter with 6 Kg/Sq. Cm, working pressure
shall conform to I.S. 3076-1968. The specials and fittings required shall be of best quality.
2.0. Workmanship
2.1. The P.V.C. pipes of specified diameter shall be fixed as directed. Due to thermal expansion of
rigid ' P.V.D. pipes, due allowance shall be made particularly in over ground pipe lines for any change
in length of pipe line which may occur during installation or when pipe line which may occur during
installation or when pipe line is in service.
2.2. Above ground installation of rigid P.V.C. pipe should be under taken after preparations are
observed for their protection against direct sun rays and mechanical damage.
2.3. The rigid P.V.C. pipe lines should not be kept exposed above ground when it passes through
public places, railway lines, road side and foot paths.
2.4. P.V.C. pipes shall be supported at the following intervals :
-20 mm. dia 500 mm. -25 mm. dia 750.mm. -32 mm. dia.900 mm.
2.5. Closer support spacing shall be provided if recommended by the manufacture.
2.6. The guide lines indicated by the manufacturer regarding handling, transportation, storing,
laying and jointing pf pipes shall be kept in view during execution.
2.7. P.V.C. pipes shall be fixed on wall with wooden plugs and suitable plastic clamps.
2.8. Jointing the pipes :
2.8.1. The pipes and sockets shall be accurately cut. The ends of the pipes and fittings should be
absolutely free from dirt and dust. The outside surface of the pipes and the inside of the fittings shall
then be roughened with emery paper, and then solvent cement joint. Since solvent cement is
aggressive to P V.C. care must be taken to avoid applying excessive cement to the inside of pipe
sockets as any surplus cement cannot be wiped of after jointing. Empty solvent cement tins, brushes,
rags, or paper impregnated with cement should not be buried in the trenches. They should be gathered
not left scattered about, as-they can prove to be a hazard to animals, which may chew them.
2.8.2. If any manufacturer recommends its own methods of jointing the same shall be adopted after
necessary approval from the Engineer-in-charge.
2.9. Laying pipes in Trenches :
2.9.1. The pipes shall be laid over uniform relatively soft fine trained soil found to be free of
presence of hard object such as large flints, rocky projections, large tree roots etc. The width of the
trenches shall be minimum width required for working.
2.9.2. The pipes laid underground shall not be less than one meter from the ground level. The pipe
shall be positioned in the trenches so as to avoid any induced stressed due to deflection. Any
deviation required shall be obtained by using proper type of rubber ring joints.
3.0. Mode of measurements & payment
The unit rate shall be for a unit of One running meter
Providing laying and jointing in true line and level 25mm dia. U.P.V.C. Pipe ( SCH- 40) for
cold water including fittings as approved by Engineer In Charge. Pipe shall be fixed on the
wall with the help of clamp at every two metre C/C or shall be concealed as directed
including necessary fittings etc. including testing of pipe and joints and fixing the same with
adhesive solvent, including cost of all materials.
The item shall be executed as per the relevant specifications & mode of measurement of above item
Providing laying and jointing in true line and level 32mm dia. U.P.V.C. Pipe ( SCH- 40) for
cold water including fittings as approved by Engineer In Charge. Pipe shall be fixed on the
wall with the help of clamp at every two metre C/C or shall be concealed as directed
including necessary fittings etc. including testing of pipe and joints and fixing the same with
adhesive solvent, including cost of all materials..
The item shall be executed as per the relevant specifications & mode of measurement of above item
Providing laying and jointing in true line and level 40mm dia. U.P.V.C. Pipe ( SCH- 40) for
cold water including fittings as approved by Engineer In Charge. Pipe shall be fixed on the
wall with the help of clamp at every two metre C/C or shall be concealed as directed
including necessary fittings etc. including testing of pipe and joints and fixing the same with
adhesive solvent, including cost of all materials.
The item shall be executed as per the relevant specifications & mode of measurement of above item
Providing laying and jointing in true line and level 50mm dia. U.P.V.C. Pipe ( SCH- 40) for
cold water including fittings as approved by Engineer In Charge. Pipe shall be fixed on the
wall with the help of clamp at every two metre C/C or shall be concealed as directed
including necessary fittings etc. including testing of pipe and joints and fixing the same with
adhesive solvent, including cost of all materials.
The item shall be executed as per the relevant specifications & mode of measurement of above item
Providing, laying and jointing in true line and level 110 diametre U.P.V.C (Type B)
conforming to IS 13592-1992 with one end plain and other end socketed with rubber ring, &
fittings conforming to ISI 14735-1999 of approved make for drainage system pipe line, pipe
shall be jointed with each other with rubber lubricant, pipe shall be fixed on wall using of
PVC clamp of the size 110 mm diametre x 149 mm length x 145 mm heigh at every 2000 mm
center to center or shall be concealed in walls as directed including necessary fittings such as
bends, shoes etc. including testing of pipes and joints and jointed with adhesive solvent
cement including cost of all materials.
Providing, laying and jointing in true line and level 110 diametre U.P.V.C (Type B) conforming to IS
13592-1992 with one end plain and other end socketed with rubber ring, & fittings conforming to ISI
14735-1999 of approved make for drainage system pipe line, pipe shall be jointed with each other
with rubber lubricant, pipe shall be fixed on wall using of PVC clamp of the size 110 mm diametre x
149 mm length x 145 mm heigh at every 2000 mm center to center or shall be concealed in walls as
directed including necessary fittings such as bends, shoes etc. including testing of pipes and joints and
jointed with adhesive solvent cement including cost of all materials.
Mode of measurements:
The rate shall be for a unit of one running meter.
Providing and fixing PVC SWR Nahni trap IS 14735 for drain - 100 mm diameter with jali
of the following nominal diameter of self cleansing design with C.I scread down or hinged
grating including the cost of cutting and making good the walls.
1.1. The cast iron (spun) Nahni trap shall conform to M-69. The C.I. hinged or screwed down
cover shall be of best quality
2.0. Workmanship
2.1. The Nahni trap with 100 mm. dia inlet and 50 mm. dia. outlet shall be fixed as per drawing or
2.2. The Nahni trap shall be jointed with C.I. Pipe, 75 mm. dia. with lead joints. The lead joints
shall be done in conformation with I.S. 782.-1976.
3.0. Mode of measurements and payment
3.1. The rate includes cost of all labour, materials, tools and plants etc. required for satisfactory
completion of this item including lead, jointing and testing.
3.2. The rate shall be for a unit of one number.
Providing erecting and fixing double coated ISI water tank of required capacity each with all
necessary fittings and connection etc. complete on terrace
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
Vol-1 Narol crematorium_compressed.pdf
Vol-2 Narol crematorium.pdf
CIVIL FURNITURE PLUMBING DETAIL SPEC NAROL PART B CREAMATORIUM.pdf
ELECTRIFICATION WORK DETAIL SPEC NAROL PART C CREAMATORIUM.pdf
FIRE FIGHTING SPEC NAROL PART DCREAMATORIUM.pdf
R5_CREMATORIUM_layout.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .