| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹6.8 LAdmitted-Finance | -15.00% | ₹6.8 L | L1 | Admitted-Finance |
| 2 | L2₹7.9 L+₹1.1 L (16.4%)Admitted-Finance | -1.10% | ₹7.9 L+₹1.1 L (16.4%) | L2 | Admitted-Finance |
| 3 | Rejected-Technical | - | - | - | Rejected-Technical Technically Not Qualified |
| 4 | Rejected-Technical | - | - | - | Rejected-Technical Technically Not Qualified |
Tender Value
₹8 L
EMD Value
₹16,000
Closing Date
8 Jun 2026, 1:00 pmClosed
Executive Engineer CMD PDC Udhampur
Executive Engineer CMD PDC Udhampur
Repair of damaged portion of canal bed at spots between RD 10900m to RD 11300m Swena area of CHEP I by laying M25 Grade concrete Shutdown Works
2026_SPDC_310033_2
eNIT 01 of 2026-27
Open Tender
Civil Works
Percentage
45 days
Udhampur
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,000
CPAO Jammu
₹16,000
Office of Chief Engineer CIandD Wing JKPDC Jammu
21 Jul 2026
18 May 2026
10 Jun 2026
18 May 2026
8 Jun 2026
18 May 2026
18 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Demolishing cement concrete manually/by mechanical means including disposal of material within 50 meters lead as per direction of Engineer-incharge:
1:3:6 or richer mix (i/c equivalent design mix) | 23.12 | Cum | 1,725.2 | ₹39,886.62 |
| 2 | Providing and laying in position machine batched and machine mixed design mix M-25 grade cement concrete for reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishing and reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer-incharge.Note: - Cement in this item is @ 330 kg/ cum. Excess or less cement used as per design mix is content considered payable or recoverable separately.
All works upto plinth level | 77.06 | Cum | 8,021.1 | ₹6,18,105.97 |
| 3 | Filling expansion joints (12mm wide) with special Impervious hot-pour | 0.29 | Cum | 96,506.6 | ₹27,986.91 |
| 4 | Pumping out water caused by springs, tidal or river seepage, broken water mains or
drains and the like. | 316.16 | K.Ltrs | 167.8 | ₹53,051.65 |
| 5Carriage of Materials by Mechanical Transport: | |||||
| 5.1 | Cement 10 Km | 42.72 | MT | 248.03 | ₹10,595.84 |
| 5.2 | Sand 90 Km | 29.66 | CuM | 1,182.74 | ₹35,080.07 |
| 5.3 | Aggregate 10 Km | 59.34 | CuM | 279.04 | ₹16,558.23 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.16 MB
SBDW2.pdf
Other Document • 0.56 MB
BOQ_1003230.xls
BOQ • 0.38 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .