| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹1.9 CrAdmitted-Finance | L1 | Admitted-Finance |
Tender Value
₹2 Cr
EMD Value
₹4 L
Closing Date
11 Aug 2026, 6:00 pmClosed
Executive Engineer
KDA Kota
CIVIL WORK
2026_UITKo_581300_1
NIT 16/2026-27 (12)
Open Tender
Civil Works
Percentage
365 days
Kota
Please refer Tender documents.
2 documents required · 2 mandatory
₹6,000
6000 Secrectry KDA, 2000 MD
₹4 L
Yes
28 Sept 2026
4 Aug 2026
12 Aug 2026
4 Aug 2026
11 Aug 2026
4 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross-sections, and transporting to the embankment location with a lift upto 1.5 m and lead upto 1000 m as per MoRTH Specification Clause 301.3 | 5,000 | Cum | 31 | ₹1,55,000 |
| 2 | CARRIAGE OF MATERIALS Earth, Sand, Lime, Morrum manure or sludge For 1 Km Including loading unloading and all lead and lift | 5,000 | Cum | 80 | ₹4,00,000 |
| 3 | Construction of granular sub-base by providing well graded material, spreading in uniform layers with Tractor Mount Grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per MoRTH Specification Clause 401. Plant Mix Method For Grading III Material | 500 | Cum | 450 | ₹2,25,000 |
| 4 | Providing laying spreading and compacting specified graded sand, gravel (crushed stone) as per Table 400-1,400-2 or any other course material as per design mix, as per CBR in sub base course including premixing the material at OMC in wet mix plant, carriage of mixed material spreading in uniform layers with motor grader F.E loader on a prepared base and compacting with vibratory roller to achieve desired density (as per I.S.2720) including all material, labor, machinery, lighting guarding, barricading and maintenance of diversion
complete.[MoRTH specification : Clause 401]. By mechanical means. For Grading-III Material | 500 | Cum | 845 | ₹4,22,500 |
| 5 | Providing crushed run stone aggregate greading conforming to table 400-14 depositing on a prepared surface by hauling vehicles, spreading and mixing with a motor grader, watering and compacting with a three wheel 80-100 kN static roller as per MoRTH Specification Clause 407 to form a layer of sub-base/base By mixing plant method With 37.5 mm maximum size of aggregates | 500 | Cum | 1,139 | ₹5,69,500 |
| 6 | Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub-base/base course on a well prepared sub-base and compacting with smooth wheel roller of 80 to 100kN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc as per Tables 400-12 & 400-13 and MoRTH Specification Clause 406. By Mechanical Means with all lead | 800 | Cum | 1,147 | ₹9,17,600 |
| 7 | Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base(WBM/WMM) including cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means as per MoRTH Specification Clause 502 | 12,000 | Sqm | 31 | ₹3,72,000 |
| 8 | Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.20 to 0.30 kg per sqm on the prepared bituminous surface cleaned with Hydraulic broom as per MoRTH Specification Clause 503. | 12,000 | Sqm. | 9.6 | ₹1,15,200 |
| 9 | Providing and laying bituminous macadam with hot mix plant using crushed aggregates of grading as per Table 500-7 premixed with bituminous binder, transported to site with all leads laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled to achieve the desired compaction as per MoRTH Specification Clause 504. Bitumen (VG-30) | 600 | Cum | 6,613 | ₹39,67,800 |
| 10 | Mix Seal Surfacing Providing, laying and rolling of close-graded premix surfacing material of 20 mm thickness composed of 11.2 mm to 0.9 mm (Type-A) or 13.2 mm to 0.9 mm (Type-B) aggregates using Viscosity grade bitumen to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 8-10 kN static roller and finishing to required level and grades as per MoRTH Specification Clause 508
By Manual Means Bitumen (VG-30) | 12,000 | Sqm | 157 | ₹18,84,000 |
stage.html
html • 0.02 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.88 MB
Special_Condition_ARC_12.pdf
Tender Documents • 0.42 MB
BOQ_1032932.xls
BOQ • 0.34 MB
Corrigendum_16.pdf
PDF • 0.15 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .