Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹33.3 L
EMD Value
₹34,000
Closing Date
29 Oct 2026, 6:00 pm
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Executive Engineer, Panchayat (R&B) Division SURENDRANAGAR
Construction of Slab Drain on Sara Nadadhri Road (VR) Km. 2/4 to 2/60 Ta.Muli , Dist.; Surendranagar. (Remaining work)
355613
14/2026-27 Sr. no. 3
Open
Civil - All
Works
Surendranagar
6 documents required · 6 mandatory
₹1,500
Executive Engineer,R&B Panchayat Divison, Surendranagar
₹34,000
15 Oct 2026
15 Oct 2026
15 Oct 2026
29 Oct 2026
15 Oct 2026
Name of work :- Construction of Slab Drain on Sara Nadadhri Road (VR) Km. 2/4 to 2/60
Ta.Muli , Dist.; Surendranagar. (Remaining work)
BILL OF QUANTITIES
Item Description of Item (With brief specification Quantity Unit Rate Amount
No. and reference to book of Specification)
1 Dismentaling the existing structure 0.00 One 562.57
including removing and stacking the Cum
dismentelled materials as and where
directed .(A) RCC work.
2 Excavation of foundation in Sand graval caly 0.00 One 309.06
soft soil and murrum etc. including shoring, Cum
struting dewatering as necessary and
disposing of the excavated stuff as directed.
Depth upto 3.00mt.
3 Providing and filling in foundation with 0.00 One 2110.90
ordinary cement concrete M-100 mix and Cum
providing necessary vertical pin headers
incl. Formwork, vibrating, ramming and
curing complete. (More than 10 tone)
4 Providing and laying plain cement concrete 14.90 One 2110.90
with ordinary M- 100 ordinary mix levelling Cum
below approach slab complete as per
drawing and technical specification. (more
5 Providing and casting in situ nominal mix 42.10 One 3345.02
concrete M-200 mix and providing Cum
necessary pin headers V - shaped false joints
to form suitable panels on exposed faces as
per approved design including cost of
shuttering , scaffolding, laying, vibrating
curing finishing etc complete without v
6 Providing and casting in situ Nominal mix 37.55 One 4159.99
concrete M 250 mix for R.C.C. works in pier Cum
cap, abutment cap, and dirt wall including
controlled cement concrete M 250 bed block
or pedestals for required size below bearings
as per detailed drawings, centering,
shuttering, scaffolding wherever necessary
laying, vibrating, curing and finishing
7 Providing and casting in situ Controlled 361.50 One 4411.78
cement concrete M 250 for R.C.C. slab Cum
including centering, scaffolding, curing and
finishing complete.
Item Description of Item (With brief specification Quantity Unit Rate Amount
No. and reference to book of Specification)
8 Providing and casting in situ Contolled 14.90 One 3621.76
cement concrete- M-250 mix for Approach Cum
slab including formwork, curing and
finishing complete. (more than 10 ton)
9 Providing and casting in situ Controlled 48.00 One 3621.76
cement concrete M-250 mix for average Cum
75mm thick wearing coat laid as directed
incuding. tamping, vibrating, finishing,
curring and filling in joints with bitumen
10 Providing parapet of ordinary cement 168.00 One 817.09
concrete M-200 as per detailed drawing with Rmt.
necessary reqinforcement including
shuttering laying vibrating and finishing to
line and level complete (ii) cast in situ.
11 Providing and placing in position FE-415 21.990 One 43875.09
(TMT) bar reinforcement including cutting, MT
bending, hooking, tying etc complete as per
detailed drawing (A) solid slab.(up to 10 ton)
12 Providing and fixing in position Mild steel 24.00 One 244.42
dowel bars in pier cap or abutment caps for No
anchorage in fixed end as per detailed
drawings including cutting bending and
welding complete.
13 Providing and fixing in position Mild steel 24.00 One 355.52
dowel bars in pier cap or abutment caps for No
anchorage in free end as per detailed
drawings including cutting bending and
welding complete.
14 Providing and laying weep hole in 83.00 One 33.94
Abutment and returns by using A.C pipe of No
100mm. Incl. fixing in proper grade and
jointing the complete as per detailed
15 Providing Pre-moulded asphalt filler joints 48.00 One 735.28
as per drawings Sqm
16 Providing flood gauge marks on sub 0.00 One 94.54
structure as per design including painting Rmt.
17 Providing and laying filter media 600mm. 0.00 One 749.42
thick directed at the back of abutments, Sqm
returns and wing walls as per detailed
specifications.(More than 10 tone)
Item Description of Item (With brief specification Quantity Unit Rate Amount
No. and reference to book of Specification)
18 Providing G.I. 100mm. Diameter water 56.00 One 506.01
spouts including necessary iron gratings as No
per drawings.(More than 10 ton)
19 Providing and fixing marble slab including 1.00 One 626.20
engraving painting etc complete 75cm x No
20 Providing temporary all weather and fair 0.00 One 611.96
weather diversion suitable for traffic during Rmt.
the construction period of the Bridge
including porviding necessary drains and all
safty measures including red / signals at
night for traffic etc. complete
Rupees Thirty Three Lakh(s) Thirty Four Thousand Seven Hundred Eight And
Paise Fifty Three Only
I \ We am \ are willing to carry out the work at ……………………… % above \ bellow percent
( Should be written in figures and words ) of the estimated rate mentioned above. Amount of My
\ Our tender works put as under.
* Estimated Amount * Estimated Amount
Put to tender Rs…………………… Put to tender Rs……………………
Deduct……..……..% Add……..……..%
In words………………….……………… In words………………….………………
1.The Contractor shall exhibit a board with detailed specification and details of work as directed
by the Engineer-In-Charge for which no extra payment shall be made.
2.The labour cess will be deducted as per prevailing rules i.e. 1% of the work done.
3.GST and Income tax TDS will be deducted at a source while making payments of bills
4.In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as per
Govt. G.R.: PRC-10/2017 Cement Consumption/16/C Date:11/05/2017 as stated in
S.O.R. therefore in R.C.C. items where there is a change as per actual mix design the cost
of difference of cement consumption have been deducted from the rate of original item at the
rate of input rate mentioned in all the tender.
Signature of Contractor.
Deputy Executive Engineer Executive Engineer
Panchayat R&B Sub Division Panchayat R&B Division
Surendranagar Surendranagar
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
B-1 Naddhari.pdf
BOQ.pdf
Speci. Nadadhari.pdf
GR SBD_compressed.pdf
nivida 14.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .