| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹87.3 LAccepted-AOC | L1 | Accepted-AOC Accepted | |
| 2 | L2₹89.8 L+₹2.5 L (2.82%)Rejected-AOC | L2 | Rejected-AOC Not Accepted | |
| 3 | Not Admitted-Fee/PreQual/Technical | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
₹91.9 L
EMD Value
₹1.8 L
Closing Date
20 Jan 2020, 3:00 pmClosed
SE PWD Cachar Road Circle Silchar
O/o The SE, PWD(Roads) Cachar Circle, Silchar.
Improvement of Approach Road of Digor Kashipur Hanuman Temple in Udharbond Constituency under Assam Darshan for the year 2019-20
2020_PWD_15814_1
T/CC/ETN/SIL/2019-20/3831(T)
Open Tender
Civil Works – Roads
Item Rate
210 days
Cachar District
Please refer Tender documents.
6 documents required · 6 mandatory
₹2,760
Empowered Officer Assam State Road Board Guwahati
₹1.8 L
Yes
26 Jul 2020
9 Jan 2020
20 Jan 2020
9 Jan 2020
20 Jan 2020
9 Jan 2020
9 Jan 2020 - 13 Jan 2020
Amount
Scarifying the existing bituminous road surface to a depth of 150mm and disposal of scarified materials with a lift upto 3m and lead upto 1000m as per Technical Specification Clause 301.4
Constn of embankment with approved materials deposited at site from roadway cutting etc complete as per technical specifications and approved estimate.
Constn of subgrade and earthen shoulder with approved materials obtained from borrow pits etc complete as per technical specifications and approved estimate.
Constn of GSB (Grading II material) by providing well graded materials etc complete as per technical specifications and approved estimate.
Providing laying and compacting stone aggregates of specific sizes to WBM-3 with stone screening Type B 11.2mm etc complete as per technical specifications and approved estimate.
Providing Interlocking Concrete Block Pavement 80mm as per Technical Specification Clause 1504 (Inclusive of Edge Restraint and Carriage)
Providing Interlocking Concrete Block Pavement 80mm as per Technical Specification Clause 1504 (Inclusive of Edge Restraint and Carriage) Extra for Coloured Block
Dismantling of existing structures like culverts, bridges, retaining walls and other structures etc complete as per technical specifications and approved estimate.
Earth work in excavation for structures (Upto 3m depth) etc complete as per technical specifications and approved estimate.
Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203. A. With natural gravel.II. P.C.C grade M 10 (i) Nominal mix (1:3:6)
Providing concrete for plain/reinforced concrete in substructure complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203. B. With natural gravel.III. P.C.C grade M 20 (i) Nominal mix (1:2:4)
Providing concrete for plain/reinforced concrete in substructure complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203. B. With natural gravel.III. R.C.C grade M 20 (i) For height upto 5m
Providing and laying RCC in superstructure as per drawing and technical specifications Clauses 800,1205 and 1205.5. A With crushed stone . II RCC M 25 (b) Height upto 5m to 10m
Supplying, fitting and placing TMT(Fe 500) bar reinforcement in superstructure etc complete as per technical specifications and approved estimate.
Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete... With 100 mm dia AC pipe etc complete as per technical specifications and approved estimate.
Providing and laying reinforced cement concrete pipe NP3 for culverts on first class bedding of granular material in single row…...Clause 1106. (1000 mm dia)
Providing and fixing of semi reflective cautionery, mandatory and informatory signboard as per IRC:67 made of 1.5mm thick MS sheetetc complete as per technical specifications and approved estimate. (i) 600mm Equilateral Triangle.
Planting of Trees by the road side (Avenue Tree) in 0.6m dia holes, 1m deep dug in the ground etc...... and their maintenance for three years etc complete as per technical specifications and approved estimate.
Provision of post constructional routine maintenance for a period of three years...1st year
Provision of post constructional routine maintenance for a period of three years...2nd year
Provision of post constructional routine maintenance for a period of three years...3rd year
SUSANTA DEB
stage.html
html • 0.04 MB
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .