| 1 | L1₹17.4 LAccepted-AOC | ₹17.4 L Quoted ₹14.8 L | L1 | Accepted-AOC L1 |
| 2 | L2₹14.9 L+₹14,771.73 (1.00%)Rejected-Finance 277 1 355 KANDHAIPUR DHOOMANGANJ PRAYAGRAJ | PRAYAGRAJ | PRAYAGRAJ | UTTAR PRADESH | ₹14.9 L+₹14,771.73 (1.00%) | L2 | Rejected-Finance L2 |
Tender Value
₹17.4 L
EMD Value
₹34,900
Closing Date
25 May 2026, 12:00 pmClosed
EXECUTIVE ENGINEER
EE RED SECOND FLOOR VIKAS BHAWAN BAREILLY
In village Kargaina Jagriti Nagar, Badaun Road, from S.K. Aryan Store to Sunil Sankdhar s house (MLAY -Kiyara)
2026_REDUP_1141559_1
3496/04/EE/RED/2025-26 DATE 18-03-2026
Open Tender
Civil Works
Percentage
90 days
KYARA
Please refer Tender documents.
2 documents required · 2 mandatory
₹854
₹34,900
20 Jul 2026
24 Apr 2026
25 May 2026
24 Apr 2026
25 May 2026
24 Apr 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 0 | BOQ | - | - | - | - |
| 1 | Excavation in foundation in ordinary soil, loame, clay or sand inculuding lift upto 1.5 m & lead upto 30m including filling watering & ramming of excavated earth into the trenches or into the space between the building & the sides of foundation trenches or in to the plinth removal & disposal of surplus earth as directed by the engineer in charge upto a distance of 30mfrom the foundation trenches. SI. No. 251 | - | cum | - | - |
| 2 | Earth Work in embankment in ordinary soil excavation to be in the regulour pits not exceeding 0.5 m depth and earth work in embankment to be in 20 cm layers including ramming and dressing the surface to required levels and slops and also in inculding 1.5 m lift & 30m lead.including watering dressing ...... as per SI.No. 253 upto a cartage of 3 km. distance.As per SI 253+C | - | cum | - | - |
| 3 | Concrete with 4 cm. gauge brick ballast, final local sand of 1.25 FM and cement in proportion of 12 :6 : 1 in foundation and under floor, Including supply of all Material with mixer machine, Labour and T & P etc. required for proper completion the work.As per S.I. No. 273. | - | cum | - | - |
| 4 | First class Brick work in 1:4 cement and coarse Sand morter in foundation & Plinth inculding supply of all materials Labour T & P etc.required for proper completion of work. As per S.I. No. 305 | - | cum | - | - |
| 5 | 12 m.m. thick Plaster with Cement mortar consisting of one part of cement and 4 part of coarse sand of 2.25 FM on brick work including supply of all material, labour, T&P etc.S.I No 584 (i) | - | Sqm | - | - |
| 6 | Supply and Laying of 125 Micron Polythin Sheet over Base Concrete Including Labour Material T&P etc. | - | Sqm | - | - |
| 7 | Cement Concrete with 2cm. Guage approved stone grit approved coarse sand and cement to the proportion 1:2:4 as per Sl. No. 279 (i) | - | Sqm | - | - |
| 8 | Making conracion join in cc road wih 0.8kg biumen,0.01kg cemen & 0.0025cum c/s as per sencioned by SE,RED,BLY. | - | RM | - | - |
| 9 | Rcc work in 1:2:4 with cement ,c.sand & 20 mm stone grit including all labour &t&p s.no-284. | - | cum | - | - |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.65 MB
T1.pdf
Tender Documents • 1.57 MB
BOQ_2131904.xls
BOQ • 0.25 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .