Loading…
Loading…
Tender Value
₹9.7 L
EMD Value
₹24,300
Closing Date
28 May 2026, 3:30 pmClosed
ASSISTANT EXECUTIVE ENGINEER
ELECTRICAL SUBDIVISION TRIPUNITHURA
Reconductoring LT OH line with LT ABC
2026_KSEB_850195_1
ESD-TPRA/e-tender1/2026-27
Open Tender
Electrical Works
Percentage
90 days
Valiyaparambu, Panangad
Please refer Tender documents.
3 documents required · 3 mandatory
₹2,360
₹24,300
12 May 2026
12 May 2026
29 May 2026
12 May 2026
28 May 2026
13 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Deposit Work for Shifting of 11KV UG Cable, HT/LT Poles & Transformer from the widwening area of service road NHAI Kannadikadu in favour of IWAI Kannadikadu under Electrical Section Maradu | |||||
| 1.01 | Transporting poles by hired vehicle to a distance upto 5km and carrying upto 4 numbers of poles excluding loading& unloading charges. | 23 | Trip | 3,142.26 | ₹72,271.98 |
| 1.02 | Dismantling (without damage) one km LT three phase 4 wire OH line conductor by dismantling cross arms, insulators and stacking the conductors in rolls properly. | 2.4 | Km | 14,129.32 | ₹33,952.76 |
| 1.03 | Labour charges for loading LT PSC pole from the stacking place and unloading the same at work site (transportation by any vehicle). | 85 | No | 478.82 | ₹40,699.7 |
| 1.04 | Dismantling (without damage) one km LT additional conductor line by dismantling cross arms, insulators and stacking the conductors in rolls properly. | - | Km | 3,351.73 | - |
| 1.05 | Dismantling (without damage) one km LT single phase 2 wire OH line conductor by dismantling cross arms, insulators and stacking the conductors in rolls properly. | 2.6 | Km | 7,443.64 | ₹19,331.13 |
| 1.06 | Providing WP support with PSC pole including digging & back filling pit in ordinary soil. excluding transportation of poles. | 75 | No | 1,943.5 | ₹1,45,762.5 |
| 1.07 | Additional rate for excavation of one Pit for LT Pole/LT Stay in Hard Laterite. | 105 | No | 434.91 | ₹45,665.55 |
| 1.08 | Labour charges for loading HT PSC pole from the stacking place and unloading the same at work site (transportation by any vehicle). | 6 | No | 762.14 | ₹4,572.84 |
| 1.09 | Insertion of one HT PSC pole in existing OH line including digging & backfilling pit in ordinary soil, fitting cross arm, insulators, binding etc., drawing sufficient length of GI earth leads to the ground for earthing (excluding provision of earthing) | 6 | No | 3,433.27 | ₹20,599.62 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.58 MB
ETENDERDOCPNGD.pdf
Tender Documents • 1.27 MB
BOQ_1436620.xls
BOQ • 0.31 MB
TIMEXTNSNPNGD.pdf
PDF • 1.71 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .