Block Development Officer(V.P)
Block Development Office, Aravakurichi Block
Construction of CC Road, Comound wall, Boys Toilet and Threshing floor 11 Nos of work in Ammapatty Panchayat
2023_RDTN_333570_4
Aravakurichi Block -AGAMT-II-2023-24
Open Tender
Civil Works
Item Rate
90 days
Aravakurichi Block
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹45,220
Yes
17 Jul 2023
30 Jun 2023
14 Jul 2023
30 Jun 2023
13 Jul 2023
30 Jun 2023
Amount
Name of the Work : Provding CC road from Palaniyammal house to Ellammal kovil in Aariyar Street At Vallapampatty H/O Ammapatty Panchayat
Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stuff clay, stiff black cotton soil, hard red earth, earth mixed with small sized boulders and hard gravelly soil as per SS 20B
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Supplying and erecting steel centering for plane surfaces in foundation and basement for staircase steps column footings plinth beam grade beam etc.,
Cement concrete 1:3:6 mix using 20mm ISS HBG metal including cost and conveyance of all materials to site and all labour charges etc..
Cement concrete 1:2:4 mix using 20mm ISS HBG metal including cost and conveyance of all materials to site and all labour charges etc..
Name of the Work : Provding CC road from Earthen road to Kesavan house At Vellalapatty BC Street H/O AmmapattyPanchayat
Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stuff clay, stiff black cotton soil, hard red earth, earth mixed with small sized boulders and hard gravelly soil as per SS 20B
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Supplying and erecting steel centering for plane surfaces in foundation and basement for staircase steps column footings plinth beam grade beam etc.,
Cement concrete 1:3:6 mix using 20mm ISS HBG metal including cost and conveyance of all materials to site and all labour charges etc..
Cement concrete 1:2:4 mix using 20mm ISS HBG metal including cost and conveyance of all materials to site and all labour charges etc..
Name of the Work : Provding CC roadAt Othapatty BC Street H/O Ammapatty Panchayat
Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stuff clay, stiff black cotton soil, hard red earth, earth mixed with small sized boulders and hard gravelly soil as per SS 20B
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Supplying and erecting steel centering for plane surfaces in foundation and basement for staircase steps column footings plinth beam grade beam etc.,
Cement concrete 1:3:6 mix using 20mm ISS HBG metal including cost and conveyance of all materials to site and all labour charges etc..
Cement concrete 1:2:4 mix using 20mm ISS HBG metal including cost and conveyance of all materials to site and all labour charges etc..
Name of the Work : Provding CC road in Pallivasal to Hajira house At Athur Muslim Street H/O Ammapatty Panchayat
Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stuff clay, stiff black cotton soil, hard red earth, earth mixed with small sized boulders and hard gravelly soil as per SS 20B
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Supplying and erecting steel centering for plane surfaces in foundation and basement for staircase steps column footings plinth beam grade beam etc.,
Cement concrete 1:3:6 mix using 20mm ISS HBG metal including cost and conveyance of all materials to site and all labour charges etc..
Cement concrete 1:2:4 mix using 20mm ISS HBG metal including cost and conveyance of all materials to site and all labour charges etc..
Name of the Work : Provding CC road in Drama Stage to Ramasamy house At Ammapatty H/O Ammapatty Panchayat
Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stuff clay, stiff black cotton soil, hard red earth, earth mixed with small sized boulders and hard gravelly soil as per SS 20B
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Supplying and erecting steel centering for plane surfaces in foundation and basement for staircase steps column footings plinth beam grade beam etc.,
Cement concrete 1:3:6 mix using 20mm ISS HBG metal including cost and conveyance of all materials to site and all labour charges etc..
Cement concrete 1:2:4 mix using 20mm ISS HBG metal including cost and conveyance of all materials to site and all labour charges etc..
Name of the Work : Providing CC road in Vijayalakshmi house to Sakthi house At Ammapatty Asariyar Street H/O Ammapaty Panchayat
Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stuff clay, stiff black cotton soil, hard red earth, earth mixed with small sized boulders and hard gravelly soil as per SS 20B
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Supplying and erecting for centering for sides soffits including Supports and Strutting upto 3.00m height for plane surfaces and all labour charges etc.,
Cement concrete 1:3:6 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Cement concrete 1:2:4 mix using 20mm ISS HBG metal including cost and conveyance of all materials to site and all labour charges etc..
Name of the Work :Providing CC road in Rajenthiran house to Amutha house At Ammapatty SC Colony H/O Ammapatty Panchayat
Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stuff clay, stiff black cotton soil, hard red earth, earth mixed with small sized boulders and hard gravelly soil as per SS 20B
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Supplying and erecting for centering for sides soffits including Supports and Strutting upto 3.00m height for plane surfaces and all labour charges etc.,
Cement concrete 1:3:6 mix using 20mm ISS HBG metal including cost and conveyance of all materials to site and all labour charges etc..
Cement concrete 1:2:4 mix using 20mm ISS HBG metal including cost and conveyance of all materials to site and all labour charges etc..
Name of the Work : Construction of Cremation shed and Compound wall in Samathuva sudugadu @ Sangaranampatti H/O Ammapatti Panchayat
Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stuff clay, stiff black cotton soil, hard red earth, earth mixed with small sized boulders and hard gravelly soil as per SS 20B
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Brickwork in CM 1:5 using country bricks ground moulded 23x11x7 cm for the following including aving etc., complete
Supplying and erecting for centering for sides soffits including Supports and Strutting upto 3.00m height for plane surfaces and all labour charges etc.,
Supplying and fabrication of steel including cost and conveyance of all materials to site and all labour charges etc., complete.
Reinforced Cement concrete 1:1.5:3, mix using 20 mm HBG Metal including cost and conveyance of all materials to site and all labour charges etc., complete.
Finishing with exposed surface in cement mortar 1:3, mix 10mm thick including cost and conveyance of all materials to site and all labour charges etc., complete.
Plastering with C.M 1:5, mix 12mm thick including cost and conveyance of all materials to site and all labour charges etc., complete.
Painting two coats with ready mixed Exterior Emulsion paint of approved qualityand colour over a priming coat, including through scrapping,clean removel of dirt etc complete
Cement concrete 1:2:4 mix using 20mm ISS HBG metal including cost and conveyance of all materials to site and all labour charges etc..
Sub Estimate
Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stuff clay, stiff black cotton soil, hard red earth, earth mixed with small sized boulders and hard gravelly soil as per SS 20B
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Brickwork in CM 1:5 using country bricks ground moulded 23x11x7 cm for the following including aving etc., complete
Supplying and erecting for centering for sides soffits including Supports and Strutting upto 3.00m height for plane surfaces and all labour charges etc.,
Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Plastering with C.M 1:5, mix 12mm thick including cost and conveyance of all materials to site and all labour charges etc., complete.
Painting two coats with ready mixed Exterior Emulsion paint of approved qualityand colour over a priming coat, including through scrapping,clean removel of dirt etc complete
Sub Estimate
Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stuff clay, stiff black cotton soil, hard red earth, earth mixed with small sized boulders and hard gravelly soil as per SS 20B
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Supplying and erecting for centering for sides soffits including Supports and Strutting upto 3.00m height for plane surfaces and all labour charges etc.,
Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Name of the Work :Construction of Boys Toilet in P.U.M School at Z.athur H/O Ammapatty Panchayat
Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stuff clay, stiff black cotton soil, hard red earth, earth mixed with small sized boulders and hard gravelly soil as per SS 20B
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Brickwork in CM 1:5 using country bricks ground moulded 23x11x7 cm for the following including aving etc., complete
Supplying and erecting for centering for sides soffits including Supports and Strutting upto 3.00m height for plane surfaces and all labour charges etc.,
Supplying and fabrication of steel including cost and conveyance of all materials to site and all labour charges etc., complete.
Reinforced Cement concrete 1:1.5:3, mix using 20 mm HBG Metal including cost and conveyance of all materials to site and all labour charges etc., complete.
Supplying and fixing in position best Indian make White glazed earthen ware Oriya type Indian Water Closet including cost and conveyance etc.
Supplying and fixing in position best Europeon Water Closet with all fittings and 10 lit capacity flushing tank including cost and conveyance etc.
Supplying and fixing white glazed earthen ware wash hand basin of size 550x400mm including cost and conveyance of all materials to site and all labour charges etc.
Supplying and fixing GI Sheet Roofing and Truss including cost and conveyance of all materials to site and all labour charges etc.
Plastering with C.M 1:3, mix 10mm thick including cost and conveyance of all materials to site and all labour charges etc., complete.
Plastering with C.M 1:5, mix 12mm thick including cost and conveyance of all materials to site and all labour charges etc., complete.
Providing Granolithic floor finish with CC 1:2:4 using 10-12mm hbg jelly 20mm thick in all floors including curing etc., complete
Dadooing walls with following approved tiles in CM 1:3 20mm thick including cost and conveyance etc complete.,
Paving the Floor with Antiskid tiles in CM 1:3 20mm thick including cost and conveyance etc complete.,
White washing two coats using shell lime including cost and conveyance of all materials to site and all labour charges etc., complete
Painting two coats with ready mixed Exterior Emulsion paint of approved qualityand colour over a priming coat, including through scrapping,clean removel of dirt etc complete
Painting two coats of new iron works such as steel doors, window, Ventilators, Window bars, Balustrdes etc., with best approved first quality of synthetic enamel paint of approved colour over the existing priming coat etc., complete complying with standard specifications
Supply of steel Doors (1.05x1.85)
Supply of steel Doors (0.8x1.70)
Name of the Work :Providing Drainage with Sock pit at Athur SC Colony Kanthan house to Sakkaraiyappan house H/O Ammapatty Panchayat
Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stuff clay, stiff black cotton soil, hard red earth, earth mixed with small sized boulders and hard gravelly soil as per SS 20B
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Supplying and erecting for centering for sides soffits including Supports and Strutting upto 3.00m height for plane surfaces and all labour charges etc.,
Cement concrete 1:3:6 mix using 20mm ISS HBG metal including cost and conveyance of all materials to site and all labour charges etc..
Plastering with C.M 1:4, mix 20mm thick including cost and conveyance of all materials to site and all labour charges etc., complete.
Supplying and fabrication of steel including cost and conveyance of all materials to site and all labour charges etc., complete.
Reinforced Cement concrete 1:1.5:3, mix using 20 mm HBG Metal including cost and conveyance of all materials to site and all labour charges etc., complete.
Name of the Work : Construction of Threshing Floor at Ammapatty Panchayat
Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stuff clay, stiff black cotton soil, hard red earth, earth mixed with small sized boulders and hard gravelly soil as per SS 20B
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Cement concrete 1:3:6 mix using 40mm ISS HBG metal including cost and conveyance of all materials to site and all labour charges etc..
Refilling the foundation and basement with excavated earth including watering wherever necessary and laid in layers of not more than 15cm thick, compacting etc., complete complying with standard specifications and as directed.
Supplying ertecting and shuttering including necessary supports for plan surface in foundation and basement and in all floors for slabs and beams complying with standard specifications (Outer wall & Wearing Coat)
Supplying ertecting and shuttering including necessary supports for plan surface in foundation and basement and in all floors for slabs and beams complying with standard specifications (Footing sides)
Cement concrete 1:2:4 mix using 20mm ISS HBG metal including cost and conveyance of all materials to site and all labour charges etc..
Plastering with C.M 1:5, mix 12mm thick including cost and conveyance of all materials to site and all labour charges etc., complete.
Painting two coats with ready mixed Exterior Emulsion paint of approved qualityand colour over a priming coat, including through scrapping,clean removel of dirt etc complete
GST Amount for providing Service to Government Contract Works for the above ConstructionWorks. GST Amount is the Total GST Amount for overall quoted amount above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
SELVAKUMAR CONSTRUCTIONS
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .