Tender ID
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹25.0 L
EMD Value
₹25,000
Closing Date
26 Nov 2026, 6:00 pm3d left
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Executive Engineer, Panchayat R. & B. Division, Palanpur
(1) Construction of Pipe Culvert On Kasara to Mota Jampur Road (2) Construction of Pipe Culvert On Khimana to Jasali Road (3) Construction of Pipe Culvert On Ratangadh to Chimangadh Road. Ta. Kankarej Dist.Banaskantha
358708
12 (2026-27)
Open
Civil - All
Works
Banaskantha
6 documents required · 5 mandatory · 1 optional
₹900
Executive Engineer, Panchayat {R. &B.} Division Palanpur
₹25,000
16 Nov 2026
16 Nov 2026
16 Nov 2026
26 Nov 2026
16 Nov 2026
120 days
Bill Of Quantities
Memorandum showing items works to be carried out :
No Description of Item (with brief specification and reference to book of
Quantity Unit Rate In figures Amount
specifications)
Clearing and grubbing road land including uprooting trunk, vegetation, grass bushes,
shrubs, sapling and trees girth upto 300 mm removal of stumps of trees cut earlier and
disposal of unservicable materials [C] By Mechanical means in area of light jungle
Earth work for embankment with selected soil including breaking clods, dressing,
2 with all, lead and lift (excluding watering and consolidation) (A) From borrow area 148.20 Cmt 154.87
with All lead and lift & CBR not less than
Rolling of earthwork in layers with vibratory roller 80 Kn to 100 Kn static weight
3 including filling in depressions which occurs during the process. 148.20 Cmt 22.96
Provdining and laying W.B.M of B.T.M.C metal of size 45 mm to 63 mm size
including 0.12 Cu.M. Stone Screeing & 0.08 Cu.M. stone dust as filler including
4 spreading, watering & consolidation by vibratory roller 80KN to 100KN static 84.60 Cmt 1953.34
weight. 75 mm thick compected.
Providing and laying cement concrete 1:4:8 (1cement : 4 coarse sand : 8 Machine
5 Crushed stone aggregates 40 mm. nominal size) and curing complete excluding cost 78.90 Cmt 2780.37
of from work in :(a) Foundation and plinth
Providing & Laying cement concrete 1:1:5:3 (1 cement : 1:5 course sand : 3 graded
stone aggregate 20 mm nominal size) for C.C. road and curing cost of form work.
Finishing the cement concrete road by trimix process inclusive of labour charges for
trimix vacuum dewatering process on cement concrete road by using vacuum
dewatering pump, surface floater, surface vibrator including channeling & making
grooves & rough finish to surface by providing expansion joints, contraction joint &
construction joints with fillings of joints with asphalt filler as per direction by
engineer incharge & as per specsificaiton.
Providing TMT Bar FE 550D reinforcement for R.C.C. work including bending,
binding and placing in position complete upto floor two level
Excavation for foundation upto 1.5 M. depth including sorting out and stacking of
8 useful materials and disposing of excavated stuff up to 50M. lead. (a) Loose or soft 240.90 Cum 122.94
Excavation for foundation upto 1.5 M to 3.0 M depth including sorting out and
9 stacking of useful materials and disposing of excavated stuff up to 50M. lead. (a) 18.90 Cum 136.30
Loose or soft soil
Providing and casting in situ ordinary cement concrete M-150 mix and providing
10 necessary pin headers including shuttering, scaffolding, laying vibrating curing and 291.90 Cum 3765.79
finishing complete without V Grooves. (A) Height from 0.0 to 5.00 mt
No Description of Item (with brief specification and reference to book of
Quantity Unit Rate In figures Amount
specifications)
Supplying and fixing reinforced concrete heavy duty non-pressure pipes with collars
for culverts carrying heavy traffic as per IS 458-1991 specifications including setting
the pipes in C.M. 1:2 watering and laying (to level or slopes) of class NP3 of
following internal daimeters.(v) 900mm dia.
Providing TMT Bar FE 500D reinforcement for R.C.C. work including bending,
binding and placing in position complete upto floor two level
Hazard Marker Sign :-Providing and fixing sign boards made out of 3mm ACP
(Aluminum composite Panel); size 90x30 cms. rectangular as per design of IRC-67-
2012. Pre treated with phospheting process & acid etching; coated with one coat of
epoxy primer and two coats of best quality epoxy paint ; reflectorised with High
Intensity Prismatic Grade retro refiectivesheeting of Type-4 as per ASTM D-4956 and
latest MORD Specifications; 1.8mtr long stand post of Iron Angle 75 x 75 x 6mm as
13 required and frame fabricated from suitable size iron angle of 35 x 35 x 3mm; painted 6.00 No 3518.69
with bestquality epoxy coatings in black and white bends. The details of symbol for
each board shall be as per the instruction of engineer in charge. The fixing at site shall
be in 1:2:4 CC blockof size 45 x 45 x 60 Cms. for each leg including excavation,
curing etc.complete under the supervision of engineer in charge. A warranty for
years for the Retro reflective sheeting from original manufacturer shall be submitted
by contractor. (A) Class-B High Intensity Grade Retro Reflective sheeting
Total Tender amount
Rupees Twenty Four Lakh(s) Ninety Eight Thousand Four Hundred And Paise Twenty One Only
I/am we/are willing to carry out the work at _____% above /below _____________ percent (should be written in figures and words) of the estimated rates
mentioned above. Amount of my/our tender works out as under.
* Estimated amount put to tender
1. The Contractor Shall Exhibit a board with deatiled specification and details of work as directed by the Engineer-In-Charge for which no Extra
Payment shall be made.
2. The labour crss will be deducted as per prevaling Rules i.e 1% of the work done.
3. GST and Income tax TDS will be deducted at a Source while making Payments of bills.
4. In all RCC items in Rate Analysis Standard cement Consuption has been taken as per Govt.G.R: PRC -10/2017 cement consumption/16/c, Date: 11/05/2017 as
stated i. S.O.R therefore in RCC Items where there is a changed as per actual mix design the cost of diffrence of cement consumption have been deduvted from
the rate of orignal item at the rate of input rate mentioned in all the tender.
Above all items of " Schedule-B" with iem Description,Unit,Rate & Amount Have verified by me and found Order.
Deputy Executive Engineer Executive Engineer
Panchayat R & B Sub Division Panchayat R & B Division
Shihori Palanpur
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
001.SBD Book-Pkg-Pipe culvert Shihori SD.pdf
002. GR to be attached with SBD compressed.pdf
003.BOQ-Pkg-Pipe culvert shihori.pdf
005.specification pkg-Pipe culvrt Shihori.pdf
006.Testing Schedule-Pkg-Pipe culvert shihori.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .