The Mysore Paper Mills Limited
Palakshi TA to Director
E-TENDER FOR RAISING AND MAINTENANCE OF PULPWOOD CAPTIVE PLANTATIONS IN BHADRAVATHI/THIRTHAHALLI/ SAGARA FOREST DIVISIONS OF THE MYSORE PAPER MILLS LTD. BHADRAVATHI DURING THE YEAR 2026-27
MPML/2025-26/SE0048/CALL-2
MPML/2025-26/SE0048/CALL-2
Open
Two Tender Document System(Two Cover)
MPML Paper Town Bhadravathi
4 documents required · 1 mandatory · 3 optional
Upload all required technical qualification documents as per tender document
₹5,000
₹14.2 L
27 Mar 2026
27 Mar 2026
16 Apr 2026
10 Apr 2026
10 Apr 2026
ITEM WISE RATES TO BE QUOTED FOR RAISING EUCALYPUTS PLANATION
Tender Unit No.
Name of the plantation:
Approximate estimaed cost as shown in tender:
MPM Forest Division:
Sl. No. Particulars Unit Quantity Rates to be quoted by the Contractor Remarks
1 Survey & demarcation including preparation of boundary tree list in wooded area 1 Ha
2 Lifting the debris after extraction of pulpwood & heaping away from the ripping lines 1 Ha
3 a) Dozing & Ripping the area by Dozer D.80 1 Ha
4 Mound formation of rippied lines (D.50/D.80 dozer) & breaking clould etc., 950/ha Tr
5 Reclearing the area before planting 1 Ha
6 Pitting all along the CPT to a size of 0.3X0.3X0.3 M @ 150 pits/ha. 4.05 M3/ha
7 Carrying of pb seedlings from nursery site to tractor or lorry, loading into the same & unloading at plantation site (including 10% replacement seedlings) 2915/ha pbs
8 Transportation of pbs by private vehicle from nursery to planting area including 10% replacement 31 Kms to 40 Kms 2915/ha pbs
0 to 10 kms 1000 pbs
11 to 20 kms 1000 pbs
21 to 30 kms 1000 pbs
31 to 40 Kms. 1000 pbs
9 Conveying pbs from periphery of the planting area to plantation site by head loads. 2915/ha pbs
10 Purchase of Anti-termite solution ( Chlorophyriphos ) 0.25 Lt
11 Soaking of Pb seedlings before planting with antitermite solution 2915/ha pbs
12 Planting of pbs in pits 2650/ha pbs
13 Casualty replacement 10% 265/ha pbs
14 Purchase of urea,DAP and MOP in 1:2:1 @ 50 gms. per plant in 2 dozes 1 Kg.
15 Loading& unloading of fertilizer 132.5 Kg
16 Application of fertilizer including soil working
Urea, DAP, MOP (1:2:1) 50 gms. per plant in 2 dozes - 25 gm. each time 2650/ha Plnt
17 First weeding 1 ha
18 Second Weeding 1 ha
19 Scraping and hoeing around the individual plants (150 plants/ha) 150 pits
20 Digging of soil all along the trenches to a depth of 15cm. and width of 1 mtr manually/mechanically by tractor ploughing. 950/ha Tr
21 Fire tracing the external and internal lines of pltn to a width of 3 mtrs. 0.35/km Km
22 Providing pltn name board 1 No
23 Providing Temporary Labour shed 1 No
24 Providing Gate using the granite stone pillars and poles in plantation 1 No
25 Dibbling of Sandal Seeds including cost of seeds, gibberlic acid, fungicide, pesticide & treatment. - - - The sandal seeds should be soaked in gibberlic acid for 24 hours and the seeds dressed with fungicide and pesticide are sown.
ITEM WISE RATES TO BE QUOTED FOR RAISING ACACIA HYBRID PLANATION
Tender Unit No.
Name of the plantation:
Approximate estimaed cost as shown in tender:
MPM Forest Division:
Sl. No. Particulars Unit Quantity Rates to be quoted by the Contractor Remarks
1 Survey and demarcation including preparation of boundary tree list in wooded areas 1 Ha.
2 Clearing of unwanted trees & other growth flush with the ground level 1 Ha.
3 Lifting the debries after extraction of pulp wood & heaping away from the ripped lines 80 MT and above (Yield) 1 Ha.
50 to 79 MT/ha.
Less than 50 MT./ha.
4 Providing brush wood fence along the CPT including collection and transportation of material/and also where No CPT i.e., common rate for both 250/Ha Rmtr As per Actual
5 Ripping the area by Tractor 1 Ha.
6 Pitting all along the CPT to a size of 0.3X0.3X0.3 M @ 150 pits/ha. 4.05 M3/ha
7 Formation of trenches and mounds in the D 50 Bulldozer ripped lines 900/ha Tr
8 Formation of trenches and mounds in the Tractor ripped lines 900/ha Tr
9 Reclearing the area before planting in case of clearfelled area of last year 1 ha.
10 Carrying of pb seedlings from nursery site to tractor or lorry, loading into the same & unloading at planting site Main planting 2300 Nos. CPT mound planting 150 Nos. 10% Replacement 245 Nos. TOTAL 2695 Nos. 2695/ha Pbs
11 Trptn of pbs soft wood species by private vehicle from nursery to planting area including 10% replacement ( For 31-40 Kms. distance) 2695/ha Pbs
12 Conveying pbs from periphery of the planting area to planting site where the area is full of hillocks vehicles cannot go inside the block hence pbs must be transported in head loads. 2695/ha Pbs
13 Soaking of Pb seedlings before planting with antitermite solution 2695/ha Pbs
14 Planting of pbs in pits 2450/ha Pbs
15 Casualty replacement 10% 245 Pbs
16 Purchase of urea,DAP and MOP in 1:2:1 @ 50 gms. per plant in 2 dozes 122.5 Kg. Fertilizer purchase as per cash bill
17 Loading & unloading of fertilizer 122.5 Kg.
18 Application of fertilizer including soil working Two time application and 2450 X 2 = 4900 plants/ha. All the plants are provided with fertilizer.
Urea, DAP & MOP (1:2:1) 50 gms. per plant in 2 dozes - 25 gm. Each time 2450/ha plnt
19 First Weeding 1 Ha.
20 Scraping and hoeing around the individual plants (150 plants/ha) 150 plnt Only 30 cms. round the plant
21 II weeding 1 Ha.
22 Digging of soil all along the trenches to a depth of 15cm. and width of 1 mtr manually/mechanically by tractor ploughing. 900/ha Tr
23 Fire tracing the external and internal lines of pltn to a width of 3 mtrs. 0.35 Km Fire tracing includes about 150 M length of periphery of plantation plus 0.2 Km/ha. hence the length of the periphery to be calculated, based on actual length.
24 Providing pltn name board On Rate quotation.
25 Providing Temporary Labour shed 1 No.
26 Dibbling of Sandal Seeds including cost of seeds, gibberlic acid, fungicide, pesticide & treatment. The sandal seeds should be soaked in gibberlic acid for 24 hours and the seeds dressed with fungicide and pesticide are sown.
ITEM WISE RATES TO BE QUOTED FOR RAISING EUCALYPTUS PELLITA PLANATION
Tender Unit No.
Name of the plantation:
Approximate estimaed cost as shown in tender:
MPM Forest Division:
Sl. No. Particulars Unit Quantity Rates to be quoted by the Contractor Remarks
1 Survey and demarcation including preparation of boundary tree list in wooded areas 1 Ha.
2 Clearing of all thick growth flush with the ground level 1 Ha.
3 Lifting the debries after extraction of pulp wood & heaping away from the ripped lines in areas with an yield of 80 MT and above 1 Ha.
50 to 79 MT per ha.
Less than 50 MT per Ha.
4 Providing brush wood fence along the CPT/without CPT including collection and transportation of material 250/ha Rmtr CPT length vary from plantation to plantations and it depended on the shape of the plantations. However, rough estimate indicates, that covers about 150 mtr of cpt and taken for cost calculations. CPT length should be based on actual length.
5 Ripping the area by Tractor
6 Pitting all along the CPT to a size of 0.3X0.3X0.3 M @ 150 pits/ha. 4.05 M3/ha
7 Formation of trenches and mounds in the Bulldozer D.50 ripped lines 900/ha Tr No. of trenches depends on average distance between the two ripped lines. No. of trenches for different espacement area as follows: Ripping distance No. of trenches/ha. Plant to plant distance
8 Formation of trenches and mounds in the Tractor ripped lines 900/ha Tr
9 Reclearing the area before planting in case of clearfelled area of last year 1 ha.
10 Carrying of pb seedlings from nursery site to tractor or lorry, loading into the same & unloading at planting site Main planting 2500 Nos. CPT mound planting 150 Nos. 10% Replacement 265 Nos. TOTAL 2915 Nos. 2695/ha Pbs
11 Transportation of pbs soft wood species by private vehicle from nursery to planting area including 10% replacement (For 30-40 Kms. distance) 2695/ha Pbs
12 Conveying pbs from periphery of the planting area to planting site where the area is full of hillocks vehicles cannot go inside the block hence pbs must be transported in head loads. 2695/ha Pbs
13 Soaking of Pb seedlings before planting with antitermite solution 2695/ha Pbs
14 Planting of pbs in pits 2450/ha Pbs 2500 plants per hectare and 150 plants on CPT mounds is planted. The number of plants of CPT is approximate as it varies from plantation to plantation.
15 Casualty replacement 10% 245 Pbs
16 Purchase of urea,DAP and MOP in 1:2:1 @ 50 gms. per plant in 2 dozes 122.5 Kg.
17 Loading & unloading of fertilizer 122.5 Kg
18 Application of fertilizer including soil working Two time application and 2750 X 2 = 5500 plants/ha. All the plants are provided with fertilizer.
Urea, DAP & MOP (1:2:1) 60 gms. per plant in 2 dozes - 30 gm. Each time 2450/ha plnt
19 First Weeding 1 Ha.
20 Scraping and hoeing around the individual plants 150 plnt Only 30 cms. round the plant
21 II weeding 1 Ha.
22 Digging of soil all along the trenches to a depth of 15cm. and width of 1 mtr manually/mechanically by tractor ploughing. 900/ha Tr
23 Fire tracing the external and internal lines of pltn to a width of 3 mtrs. 0.35 Km Fire tracing includes about 150 M length of periphery of plantation plus 0.2 Km/ha. hence the length of the periphery to be calculated, based on actual length.
24 Providing pltn name board
25 Providing Temporary Labour shed No.
26 Providing Gate using the granite stone pillers and poles in plantation No. Item is discontinued.(Unskilled Rate)
27 Dibbling of Sandal Seeds including cost of seeds, gibberlic acid, fungicide, pesticide & treatment. The sandal seeds should be soaked in gibberlic acid for 24 hours and the seeds dressed with fungicide and pesticide are sown. - No revision
ITEM WISE RATES TO BE QUOTED FOR MAINTENANCE OF II YEAR. PLANATION
Tender Unit No.
Name of the plantation:
Approximate estimaed cost as shown in tender:
MPM Forest Division:
Sl. No. Particulars Unit Quantity Rates to be quoted by the Contractor Remarks
1 First weeding 1 ha.
2 IInd weeding where grass cutting not taken up 1 ha.
3 Pruning the side branches in Acacia hybrid plants/Euca. urophylla/ Euca.pellita. 1 ha.
4 Digging of soil all along the trenches to a depth of 15cm. and width of 1 mtr manually/mechanically by tractor ploughing. 900/ha Tr
5 Fire tracing the external and internal lines of pltn to a width of 3 mtrs. 0.35 Km Fire tracing includes about 150 M length of periphery of plantation plus 0.2 Km/ha. hence the length of the periphery to be calculated based on the actual length.
APCCF & Director (Forests) i/c.
ITEM WISE RATES TO BE QUOTED FOR MAINTENANCE OF III YEAR. PLANATION
Tender Unit No.
Name of the plantation:
Approximate estimaed cost as shown in tender:
MPM Forest Division:
Sl. No. Particulars Unit Quantity Rates to be quoted by the Contractor Remarks
1 First weeding 1 ha
2 Digging of soil all along the trenches to a depth of 15cm. and width of 1 mtr manually/mechanically by tractor ploughing. 900/ha Tr
3 Pruning the side branches in Acacia hybrid plants/Euca. urophylla/ Euca.pellita. 1 ha.
4 Fire tracing the external and internal lines of pltn to a width of 3 mtrs. 0.35 Km Fire tracing includes about 150 M length of periphery of plantation plus 0.2 Km/ha. hence the length of the periphery to be calculated based on the actual length.
ITEM WISE RATES TO BE QUOTED FOR MAINTENANCE OF EUCALYPTUS COPPICE PLANATION
Tender Unit No.
Name of the plantation:
Approximate estimaed cost as shown in tender:
MPM Forest Division:
Sl. No. Particulars Unit Quantity Rates to be quoted by the Contractor Remarks
1 Survey & demarcation including preparation of boundary tree list in wooded area 1 Ha
2 Clear felling the thick weed growth in the extracted area 1 Ha
3 Digging of soil all along the trenches 1 Mtr. Width or tractor ploughing along the trenches 950/ha trenches
4 Fire tracing the external and internal lines of plantation to a width of 3 Mtrs. 0.35 Km
ITEM WISE RATES TO BE QUOTED FOR RAISING EUCALYPUTS PLANATION
Tender Unit No.
Name of the plantation:
Approximate estimaed cost as shown in tender:
MPM Forest Division:
Sl. No. Particulars Unit Quantity Rates to be quoted by the Contractor Remarks
1 Survey & demarcation including preparation of boundary tree list in wooded area 1 Ha
2 Lifting the debris after extraction of pulpwood & heaping away from the ripping lines 1 Ha
3 a) Dozing & Ripping the area by Dozer D.80 1 Ha
4 Mound formation of rippied lines (D.50/D.80 dozer) & breaking clould etc., 950/ha Tr
5 Reclearing the area before planting 1 Ha
6 Pitting all along the CPT to a size of 0.3X0.3X0.3 M @ 150 pits/ha. 4.05 M3/ha
7 Carrying of pb seedlings from nursery site to tractor or lorry, loading into the same & unloading at plantation site (including 10% replacement seedlings) 2915/ha pbs
8 Transportation of pbs by private vehicle from nursery to planting area including 10% replacement 31 Kms to 40 Kms 2915/ha pbs
0 to 10 kms 1000 pbs
11 to 20 kms 1000 pbs
21 to 30 kms 1000 pbs
31 to 40 Kms. 1000 pbs
9 Conveying pbs from periphery of the planting area to plantation site by head loads. 2915/ha pbs
10 Purchase of Anti-termite solution ( Chlorophyriphos ) 0.25 Lt
11 Soaking of Pb seedlings before planting with antitermite solution 2915/ha pbs
12 Planting of pbs in pits 2650/ha pbs
13 Casualty replacement 10% 265/ha pbs
14 Purchase of urea,DAP and MOP in 1:2:1 @ 50 gms. per plant in 2 dozes 1 Kg.
15 Loading& unloading of fertilizer 132.5 Kg
16 Application of fertilizer including soil working
Urea, DAP, MOP (1:2:1) 50 gms. per plant in 2 dozes - 25 gm. each time 2650/ha Plnt
17 First weeding 1 ha
18 Second Weeding 1 ha
19 Scraping and hoeing around the individual plants (150 plants/ha) 150 pits
20 Digging of soil all along the trenches to a depth of 15cm. and width of 1 mtr manually/mechanically by tractor ploughing. 950/ha Tr
21 Fire tracing the external and internal lines of pltn to a width of 3 mtrs. 0.35/km Km
22 Providing pltn name board 1 No
23 Providing Temporary Labour shed 1 No
24 Providing Gate using the granite stone pillars and poles in plantation 1 No
25 Dibbling of Sandal Seeds including cost of seeds, gibberlic acid, fungicide, pesticide & treatment. - - - The sandal seeds should be soaked in gibberlic acid for 24 hours and the seeds dressed with fungicide and pesticide are sown.
ITEM WISE RATES TO BE QUOTED FOR RAISING ACACIA HYBRID PLANATION
Tender Unit No.
Name of the plantation:
Approximate estimaed cost as shown in tender:
MPM Forest Division:
Sl. No. Particulars Unit Quantity Rates to be quoted by the Contractor Remarks
1 Survey and demarcation including preparation of boundary tree list in wooded areas 1 Ha.
2 Clearing of unwanted trees & other growth flush with the ground level 1 Ha.
3 Lifting the debries after extraction of pulp wood & heaping away from the ripped lines 80 MT and above (Yield) 1 Ha.
50 to 79 MT/ha.
Less than 50 MT./ha.
4 Providing brush wood fence along the CPT including collection and transportation of material/and also where No CPT i.e., common rate for both 250/Ha Rmtr As per Actual
5 Ripping the area by Tractor 1 Ha.
6 Pitting all along the CPT to a size of 0.3X0.3X0.3 M @ 150 pits/ha. 4.05 M3/ha
7 Formation of trenches and mounds in the D 50 Bulldozer ripped lines 900/ha Tr
8 Formation of trenches and mounds in the Tractor ripped lines 900/ha Tr
9 Reclearing the area before planting in case of clearfelled area of last year 1 ha.
10 Carrying of pb seedlings from nursery site to tractor or lorry, loading into the same & unloading at planting site Main planting 2300 Nos. CPT mound planting 150 Nos. 10% Replacement 245 Nos. TOTAL 2695 Nos. 2695/ha Pbs
11 Trptn of pbs soft wood species by private vehicle from nursery to planting area including 10% replacement ( For 31-40 Kms. distance) 2695/ha Pbs
12 Conveying pbs from periphery of the planting area to planting site where the area is full of hillocks vehicles cannot go inside the block hence pbs must be transported in head loads. 2695/ha Pbs
13 Soaking of Pb seedlings before planting with antitermite solution 2695/ha Pbs
14 Planting of pbs in pits 2450/ha Pbs
15 Casualty replacement 10% 245 Pbs
16 Purchase of urea,DAP and MOP in 1:2:1 @ 50 gms. per plant in 2 dozes 122.5 Kg. Fertilizer purchase as per cash bill
17 Loading & unloading of fertilizer 122.5 Kg.
18 Application of fertilizer including soil working Two time application and 2450 X 2 = 4900 plants/ha. All the plants are provided with fertilizer.
Urea, DAP & MOP (1:2:1) 50 gms. per plant in 2 dozes - 25 gm. Each time 2450/ha plnt
19 First Weeding 1 Ha.
20 Scraping and hoeing around the individual plants (150 plants/ha) 150 plnt Only 30 cms. round the plant
21 II weeding 1 Ha.
22 Digging of soil all along the trenches to a depth of 15cm. and width of 1 mtr manually/mechanically by tractor ploughing. 900/ha Tr
23 Fire tracing the external and internal lines of pltn to a width of 3 mtrs. 0.35 Km Fire tracing includes about 150 M length of periphery of plantation plus 0.2 Km/ha. hence the length of the periphery to be calculated, based on actual length.
24 Providing pltn name board On Rate quotation.
25 Providing Temporary Labour shed 1 No.
26 Dibbling of Sandal Seeds including cost of seeds, gibberlic acid, fungicide, pesticide & treatment. The sandal seeds should be soaked in gibberlic acid for 24 hours and the seeds dressed with fungicide and pesticide are sown.
ITEM WISE RATES TO BE QUOTED FOR RAISING EUCALYPTUS PELLITA PLANATION
Tender Unit No.
Name of the plantation:
Approximate estimaed cost as shown in tender:
MPM Forest Division:
Sl. No. Particulars Unit Quantity Rates to be quoted by the Contractor Remarks
1 Survey and demarcation including preparation of boundary tree list in wooded areas 1 Ha.
2 Clearing of all thick growth flush with the ground level 1 Ha.
3 Lifting the debries after extraction of pulp wood & heaping away from the ripped lines in areas with an yield of 80 MT and above 1 Ha.
50 to 79 MT per ha.
Less than 50 MT per Ha.
4 Providing brush wood fence along the CPT/without CPT including collection and transportation of material 250/ha Rmtr CPT length vary from plantation to plantations and it depended on the shape of the plantations. However, rough estimate indicates, that covers about 150 mtr of cpt and taken for cost calculations. CPT length should be based on actual length.
5 Ripping the area by Tractor
6 Pitting all along the CPT to a size of 0.3X0.3X0.3 M @ 150 pits/ha. 4.05 M3/ha
7 Formation of trenches and mounds in the Bulldozer D.50 ripped lines 900/ha Tr No. of trenches depends on average distance between the two ripped lines. No. of trenches for different espacement area as follows: Ripping distance No. of trenches/ha. Plant to plant distance
8 Formation of trenches and mounds in the Tractor ripped lines 900/ha Tr
9 Reclearing the area before planting in case of clearfelled area of last year 1 ha.
10 Carrying of pb seedlings from nursery site to tractor or lorry, loading into the same & unloading at planting site Main planting 2500 Nos. CPT mound planting 150 Nos. 10% Replacement 265 Nos. TOTAL 2915 Nos. 2695/ha Pbs
11 Transportation of pbs soft wood species by private vehicle from nursery to planting area including 10% replacement (For 30-40 Kms. distance) 2695/ha Pbs
12 Conveying pbs from periphery of the planting area to planting site where the area is full of hillocks vehicles cannot go inside the block hence pbs must be transported in head loads. 2695/ha Pbs
13 Soaking of Pb seedlings before planting with antitermite solution 2695/ha Pbs
14 Planting of pbs in pits 2450/ha Pbs 2500 plants per hectare and 150 plants on CPT mounds is planted. The number of plants of CPT is approximate as it varies from plantation to plantation.
15 Casualty replacement 10% 245 Pbs
16 Purchase of urea,DAP and MOP in 1:2:1 @ 50 gms. per plant in 2 dozes 122.5 Kg.
17 Loading & unloading of fertilizer 122.5 Kg
18 Application of fertilizer including soil working Two time application and 2750 X 2 = 5500 plants/ha. All the plants are provided with fertilizer.
Urea, DAP & MOP (1:2:1) 60 gms. per plant in 2 dozes - 30 gm. Each time 2450/ha plnt
19 First Weeding 1 Ha.
20 Scraping and hoeing around the individual plants 150 plnt Only 30 cms. round the plant
21 II weeding 1 Ha.
22 Digging of soil all along the trenches to a depth of 15cm. and width of 1 mtr manually/mechanically by tractor ploughing. 900/ha Tr
23 Fire tracing the external and internal lines of pltn to a width of 3 mtrs. 0.35 Km Fire tracing includes about 150 M length of periphery of plantation plus 0.2 Km/ha. hence the length of the periphery to be calculated, based on actual length.
24 Providing pltn name board
25 Providing Temporary Labour shed No.
26 Providing Gate using the granite stone pillers and poles in plantation No. Item is discontinued.(Unskilled Rate)
27 Dibbling of Sandal Seeds including cost of seeds, gibberlic acid, fungicide, pesticide & treatment. The sandal seeds should be soaked in gibberlic acid for 24 hours and the seeds dressed with fungicide and pesticide are sown. - No revision
ITEM WISE RATES TO BE QUOTED FOR MAINTENANCE OF II YEAR. PLANATION
Tender Unit No.
Name of the plantation:
Approximate estimaed cost as shown in tender:
MPM Forest Division:
Sl. No. Particulars Unit Quantity Rates to be quoted by the Contractor Remarks
1 First weeding 1 ha.
2 IInd weeding where grass cutting not taken up 1 ha.
3 Pruning the side branches in Acacia hybrid plants/Euca. urophylla/ Euca.pellita. 1 ha.
4 Digging of soil all along the trenches to a depth of 15cm. and width of 1 mtr manually/mechanically by tractor ploughing. 900/ha Tr
5 Fire tracing the external and internal lines of pltn to a width of 3 mtrs. 0.35 Km Fire tracing includes about 150 M length of periphery of plantation plus 0.2 Km/ha. hence the length of the periphery to be calculated based on the actual length.
APCCF & Director (Forests) i/c.
ITEM WISE RATES TO BE QUOTED FOR MAINTENANCE OF III YEAR. PLANATION
Tender Unit No.
Name of the plantation:
Approximate estimaed cost as shown in tender:
MPM Forest Division:
Sl. No. Particulars Unit Quantity Rates to be quoted by the Contractor Remarks
1 First weeding 1 ha
2 Digging of soil all along the trenches to a depth of 15cm. and width of 1 mtr manually/mechanically by tractor ploughing. 900/ha Tr
3 Pruning the side branches in Acacia hybrid plants/Euca. urophylla/ Euca.pellita. 1 ha.
4 Fire tracing the external and internal lines of pltn to a width of 3 mtrs. 0.35 Km Fire tracing includes about 150 M length of periphery of plantation plus 0.2 Km/ha. hence the length of the periphery to be calculated based on the actual length.
ITEM WISE RATES TO BE QUOTED FOR MAINTENANCE OF EUCALYPTUS COPPICE PLANATION
Tender Unit No.
Name of the plantation:
Approximate estimaed cost as shown in tender:
MPM Forest Division:
Sl. No. Particulars Unit Quantity Rates to be quoted by the Contractor Remarks
1 Survey & demarcation including preparation of boundary tree list in wooded area 1 Ha
2 Clear felling the thick weed growth in the extracted area 1 Ha
3 Digging of soil all along the trenches 1 Mtr. Width or tractor ploughing along the trenches 950/ha trenches
4 Fire tracing the external and internal lines of plantation to a width of 3 Mtrs. 0.35 Km
Particulars of Plantation works
Sl. No. Particulars
1 Survey and demarcation including preparation of boundary tree list in wooded areas
2 Lifting the debries after extraction of pulp wood & heaping away from the ripped lines 80 MT and above (Yield)
50 to 79 MT/ha.
Less than 50 MT./ha.
3 Providing brush wood fence along the CPT including collection and transportation of material
4 Providing brushwood fence all along the boundary where there is no CPT Mounds (wherever necessary)
5 Ripping the area by MPM dozer
6 Pitting all along the CPT to a size of 0.3X0.3X0.3 M @ 150 pits/ha.
7 Formation of trenches and mounds in the Bulldozer ripped lines
8 Reclearing the area before planting in case of clearfelled area of last year
9 Carrying of pb seedlings from nursery site to tractor or lorry, loading into the same & unloading at planting site Main planting 2300 Nos. CPT mound planting 150 Nos. 10% Replacement 245 Nos. TOTAL 2695 Nos.
10 Trptn of pbs soft wood species by private vehicle from nursery to planting area including 10% replacement ( For 31-40 Kms. distance)
11 Conveying pbs from periphery of the planting area to planting site where the area is full of hillocks vehicles cannot go inside the block hence pbs must be transported in head loads.
12 Planting of pbs in pits
13 Casualty replacement 10%
14 Purchase of urea,DAP and MOP in 1:2:1 @ 50 gms. per plant in 2 dozes
15 Loading & unloading of fertilizer
16 Application of fertilizer including soil working
a) Urea, DAP & MOP (1:2:1) 50 gms. per plant in 2 dozes - 25 gm. Each time
17 First Weeding
18 Grass cutting in plants where 2nd weeding not taken up
19 Scraping and hoeing around the trenches.
20 Scraping and hoeing around the individual plants
22 Digging of soil all along the trenches to a depth of 15cm. and width of 1 mtr manually/mechanically by tractor ploughing.
23 Fire tracing the external and internal lines of pltn to a width of 3 mtrs.
II Year Maintenance :
Sl. No. Particulars
1 First weeding
2 IInd weeding where grass cutting not taken up
3 Pruning the side branches in pulpwood plants
4 Digging of soil all along the trenches to a depth of 15cm. and width of 1 mtr manually/mechanically by tractor ploughing.
5 Fire tracing the external and internal lines of pltn to a width of 3 mtrs.
III Year Maintenance :
Sl. No. Particulars
1 First weeding
2 Digging of soil all along the trenches to a depth of 15cm. and width of 1 mtr manually/mechanically by tractor ploughing.
3 Pruning the side branches in Pulpwood plants
4 Fire tracing the external and internal lines of pltn to a width of 3 mtrs.
IV to VII Year Maintenance
1 Fire tracing the external and internal lines of pltn to a width of 3 mtrs.
Coppice Maintenance :
Sl. No. Particulars
1 Survey & demarcation including preparation of boundary tree list in wooded area
2 Clear felling the thick weed growth in the extracted area
3 Digging of soil all along the trenches 1 Mtr. Width or tractor ploughing along the trenches
4 Fire tracing the external and internal lines of plantation to a width of 3 Mtrs.
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
Schedule B.xls
Tender Document • 0.06 MB
Tender-documents-2026.doc
Tender Document • 0.15 MB
Schedule B.xls
Tender Document • 0.06 MB
Plantation Work criteria.xls
Tender Document • 0.02 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .