Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹5.3 LAccepted-AOC | ₹5.3 L | L1 | Accepted-AOC 1ST. LOWEST |
| 2 | L2₹5.3 L+₹5,390.13 (1.02%)Rejected-Finance | ₹5.3 L+₹5,390.13 (1.02%) | L2 | Rejected-Finance 2ND. LOWEST |
| 3 | L3₹5.4 L+₹10,726.89 (2.03%)Rejected-Finance 32 A SWAMI SATYANANDA SARANI BARANAGAR | ₹5.4 L+₹10,726.89 (2.03%) | L3 | Rejected-Finance 3 RD LOWEST |
Tender Value
₹5.3 L
EMD Value
₹10,674
Closing Date
12 Mar 2026, 5:00 pmClosed
EE_MEMD
Office of the Executive Engineer Mayurakshi Electrical and Mechanical Division Benimadhab More Suri Birbhum
Complete Replacement of 02 nos Draw Shutter, Guide Channel along with Hoisting Systems at Cross Regulator _Behind Police Line_, Block- Balurghat, under South Dinajpur Irrigation Division.
2026_IWD_1013351_4
WBIW/EE/MEMD/e-NIT-16/2025-26
Open Tender
MECHANICAL
Percentage
30 days
BALURGHAT
Please refer Tender documents.
8 documents required · 8 mandatory
₹10,674
15 Sept 2026
23 Feb 2026
13 Mar 2026
26 Feb 2026
12 Mar 2026
26 Feb 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Engagement of mazdoor cutting jungle, cleaning of garbage and mud of each U/S gate. Unskilled. | 16 | Nos | 520.46 | ₹8,327.36 |
| 2 | Taking out old existing unservicable damaged draw/flap gate shutter of distributories/ branch canal/minor canal/channel completely after disengaging from hoisting system completely for installation of new gate shutter. The work includes cutting of gates into suitable pieces by gas cutting, removing the same by mechanical means or suitable crane, stacking all the pieces at the suitable place or departmental godown or as directed by the Engineer in charge. The cost includes cost of man power employed for dismantling and cost of consumables like oxygen, accetylene gas, hire charges of machineries, like chain pulley block, gas set, tools & tackles, scaffolding and safety equipments etc including carriage loading & unloading with all lead & lift. | 565.5 | Nos | 7.01 | ₹3,964.15 |
| 3 | Supplying to site empty cement polythene bags (capacity 50kg) in good condition including stacking, incedental charges etc. all complete (capacity 50 kg). | 429 | Nos | 7.15 | ₹3,067.35 |
| 4 | Labour charges for filling empty cement gunny bag / polythene bag (capacity 50 kg) with all kinds of earth (wet or dry), sand or agreegates(stone / brick) and sewing as done in case of cement bags ,( tying with a knot after filling will not be accepted ) , and stacking within a lead of 30 metre as per direction of Engr-in-charge (cost is excluding the cost of any types of filling materials). NB:- Volume of earth/ sand filled bags should not be less than 0.028 cum/ bag. | 429 | Nos | 7.15 | ₹3,067.35 |
| 5 | Dumping in position earth / sand filled gunny / poly bags (capacity 50 kg) within a lead of 30 metre inclusive of all lifts. | 429 | Nos | 3.58 | ₹1,535.82 |
| 6 | Bailing out water by pump including all leads and lifts and including making all arrangement for disposal, where continous flow or seepage of water is encountered and rating of pumps and hours of operation is specifically of ascertained as per direction of Eingineer-in-charge. | 75 | Nos | 27.41 | ₹2,055.75 |
| 7 | Dismantling of damaged embeded part like guide channel/bottom seal beam/top seal beam of gates of canal/river from civil structure as directed by the Engineer-in- charge.The cost of man power employed for dismantling and hire charges of Tools and Plant, scaffolding charges etc. Payment will be made on actual length of Guide Channel. | 16 | Nos | 504.52 | ₹8,072.32 |
| 8Fabrication , supply, erection and commissioning of embeded parts consisting of seal beam, Guide channel with all accessories for vertical gate of canal/river made of MS material consisting of angle, channel, beam, plate, flat, etc. conforming to IS : 2062 - 2011/latest revision manufactured as per approved drawing and direction including cost of Materials, Machinaries , Manpower, Cutting, ligning, nchoring, Welding, Finishing, Consumables, Carriage and all overheads with all leads and lifts complete as per specification (without painting). Remarks: Cost for civil works to be taken from PWD (R) directorate seperatly. | |||||
| 8.01 | Insert plate welded with J hook | 118.5 | Nos | 196.41 | ₹23,274.59 |
| 8.02 | Seal beam | 90 | Nos | 174.31 | ₹15,687.9 |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.09 MB
BOQ_2489155.xls
BOQ • 0.30 MB
2911.pdf
Tender Documents • 0.50 MB
CORRI_16_4_2.pdf
PDF • 0.15 MB
Corri_16_4.pdf
PDF • 0.14 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .