| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹82.6 LAdmitted-Finance | ₹82.6 L | L1 | Admitted-Finance |
| 2 | L2₹87.9 LAdmitted-Finance 2ND FLOOR SHOP NO 303 MARUTI PLAZA RONCHI BANGAR TOWNSHIP MATHURA | MATHURA | UTTAR PRADESH | 281001 | ₹87.9 L | L2 | Admitted-Finance |
| 3 | L3₹1.2 CrAdmitted-Finance | ₹1.2 Cr | L3 | Admitted-Finance |
| Sl No | Description | Qty | Unit | P&H Engineering L2 | Technocrat Electrical L3 | SATKAR TRADERS L1 |
|---|---|---|---|---|---|---|
| 1.00PART- A: Supply of Materials | ||||||
| 2.00Supply for 132KV Main bus strengthening and construction of 132KV Transfer bus | ||||||
| 3.00 | 132KV Bolted type Single suspension fitting for moose conductor complete with ball hook, socket eye, yoke plate etc, confirming to BIS : 2486 Part I. | 18 | Nos. | 632.49 ₹11,384.82 | 900 ₹16,200 | 632 ₹11,376 |
| 4.00 | 132KV Bolted type Single tension fitting wth turn buckle for moose conductor of 250 mm spacing without turn buckle, D-shackle, D-socket, yoke plate, tension clamp 2 Nos. confirming to BIS: 2486 Part I. | 24 | Nos. | 1,023.28 ₹24,558.72 | 1,200 ₹28,800 | 1,019.9 ₹24,477.60 |
| 5.00 | 132KV Bolted type double suspension fitting with suspension insulator string for moose conductor complete set with ball hook, socket eye, yoke plate etc, confirming to BIS : 2486 Part I. | 6 | Nos. | 5,111 ₹30,666 | 5,555 ₹33,330 | 5,109.9 ₹30,659.40 |
| 6.00 | 132KV Bolted type double tension fitting with tension insulator string wth turn buckle for moose conductor of 250 mm spacing without turn buckle, D-Shackle, D-Socket, Yoke Plate, Tension Clamp 2 Nos. confirming to BIS: 2486 Part I. | 18 | Nos. | 9,271 ₹1.7 L | 9,999 ₹1.8 L | 9,190 ₹1.7 L |
| 7.00 | Anti-Fog Disc Insulator 70KN | 685 | Nos. | 571.77 ₹3.9 L | 600 ₹4.1 L | 570 ₹3.9 L |
| 8.00 | 20 mm GI U-bolt of MS rod having thread on both side complete with washer and spring washer 04 Nos. nuts,duly hot dip galvanized as per IS. | 66 | Nos. | 550 ₹36,300 | 555 ₹36,630 | 549.9 ₹36,293.40 |
| 9.00 | 132KV C.B. Clamp for Twin Panther Conductor made of aluminium alloy LM-6 complete with nuts, bolts & washers as per sample confirming to BIS : 5561. | 6 | Nos. | 950 ₹5,700 | 999 ₹5,994 | 949 ₹5,694 |
| 10.00 | 132K.V Isolator Clamp made of LM -6 Alloy suitable for ACSR twin Panther Conductor complete as per sample confirming to BIS : 5561. | 24 | Nos. | 950 ₹22,800 | 999 ₹23,976 | 949 ₹22,776 |
Updated dates
Tender Value
₹98.6 L
EMD Value
₹99,000
Closing Date
5 Jan 2026, 4:00 pmClosed
S.E, ETC I, Lucknow
Pareshan Bhawan, Gomti Nagar, Lucknow
work
2025_UPTCL_1097455_1
E-Tender No.69/ETC-ILKO/2025-26
Open Tender
Electrical Works
30 days
Pareshan Bhawan, Gomti Nagar, Lucknow
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,770
A/c No 2408002190005438, IFS PUNB0691100, PNB, Lko
₹99,000
24 Feb 2026
8 Dec 2025
6 Jan 2026
8 Dec 2025
5 Jan 2026
8 Dec 2025
PART- A: Supply of Materials
Supply for 132KV Main bus strengthening and construction of 132KV Transfer bus
132KV Bolted type Single suspension fitting for moose conductor complete with ball hook, socket eye, yoke plate etc, confirming to BIS : 2486 Part I.
132KV Bolted type Single tension fitting wth turn buckle for moose conductor of 250 mm spacing without turn buckle, D-shackle, D-socket, yoke plate, tension clamp 2 Nos. confirming to BIS: 2486 Part I.
132KV Bolted type double suspension fitting with suspension insulator string for moose conductor complete set with ball hook, socket eye, yoke plate etc, confirming to BIS : 2486 Part I.
132KV Bolted type double tension fitting with tension insulator string wth turn buckle for moose conductor of 250 mm spacing without turn buckle, D-Shackle, D-Socket, Yoke Plate, Tension Clamp 2 Nos. confirming to BIS: 2486 Part I.
Anti-Fog Disc Insulator 70KN
20 mm GI U-bolt of MS rod having thread on both side complete with washer and spring washer 04 Nos. nuts,duly hot dip galvanized as per IS.
132KV C.B. Clamp for Twin Panther Conductor made of aluminium alloy LM-6 complete with nuts, bolts & washers as per sample confirming to BIS : 5561.
132K.V Isolator Clamp made of LM -6 Alloy suitable for ACSR twin Panther Conductor complete as per sample confirming to BIS : 5561.
132 K.V Isolator Clamp made of LM -6 Alloy suitable for ACSR Moose Conductor complete as per sample confirming to BIS : 5561.
132 K.V. PT Clamp for moose Conductor made of aluminium alloy LM-6 complete with nuts, bolts & washers as per sample confirming to BIS : 5561.
PG Clamps suitable for Panther/Moose
PG Clamps suitable for Panther/Panther
PG Clamps suitable for Moose/Moose
250 mm spacing spacer of twin moose conductor made of aluminium alloy LM-6 complete with nuts, bolts & washers confirming to BIS : 5561.
100 mm spacing spacer of twin moose conductor made of aluminium alloy LM-6 complete with nuts, bolts & washers confirming to BIS : 5561.
100 mm spacing spacer of twin panther conductor made of aluminium alloy LM-6 complete with nuts, bolts & washers confirming to BIS : 5561.
Various size of nuts, bolts & washers etc. as per sample.
Supply of material for 63 MVA T/F-III Bay including 132KV and 33KV side along with 132KV Transfer Bus-Coupler Bay
HV Connector for 132/33 KV 63 MVA T/F
LV Connector for 132/33 KV 63 MVA T/F
PG Clamps suitable for Moose/Panther
PG Clamps suitable for Panther/Panther
PG Clamps suitable for Moose/Moose
132 KV Bus Post Clamp suitable for Panther
132 KV Bus Post Clamp suitable for Moose
Single Tension Fittings Suitable for ACSR Panther
Single suspension Fittings Suitable for ACSR Panther
Anti-Fog Disc Insulator 70KN
20 mm GI U-bolt of MS rod having thread on both side complete with washer and spring washer 04 Nos. nuts,duly hot dip galvanized as per IS.
GI Perforated tray of various size
Digital multimeter (4 1/2 digit) motwani make
MS Flat 25x6mm
MS Flat 50x6mm
MS Flat 75x10mm
Necessary interconnection from data transmission of already installed SAMAST complaint meters to Lan switch upto DCU/ Gateway and all other H/W, S/W per No.
Dismantling of 10MVAr Capacitor Bank along with Column Beam, Disconnecting and Destringing of concerned section of Bus-Bar, including equipments like NCT, CT, isolator, Shunt Reactor, Capacitor Cells with unit structure, Breaker & accessories, Electrical Connections, Disconnection and Removal of Control Cables, along with removal of earthing with other associated works to complete the job satisfactorily along with Shifting of material to the required place. (2 Nos. at 132 KV S/S, Barabanki and 01 No. at 132 KV S/S. Sector-67, Noida)
Laying of Control Cable into Cable Trench including termination of the same and ferrulling it as per drawing, with other associated works to complete the job satisfactorily
Portable Mechanical Foam type Fire Extinguisher 45/50 litre capacity
5KV Digital Insulation Tester of Motwane make with Safety - IP 54, CAT IV 600V and CE conformity and Robust ABS body with self-carrying handle along with Automatic discharge for capacitive circuits and Guard terminal to minimize the surface leakage.
Flexible Copper Bond
36KV Dropout fuse set with post insulator
132KV CB Terminal Connector duly made of aluminium alloy (LM 6) suitable for Twin ACSR panther
132KV CB Terminal Connector duly made of aluminium alloy (LM 6) suitable for Twin ACSR Moose Conductor
120KV LA Terminal Connector duly made of aluminium alloy (LM 6) suitable for panther
132KV CT Terminal Connector duly made of aluminium alloy (LM 6) suitable for Twin ACSR Moose
132KV CT Terminal Connector duly made of aluminium alloy (LM 6) suitable for Twin ACSR Panther
132 KV Isolator Bi-metallic terminal Connector duly made of aluminium alloy (LM 6) suitable for twin panther
132 KV Isolator Bi-metallic terminal Connector duly made of aluminium alloy (LM 6) suitable for twin Moose
33 KV CB Terminal Connector duly made of aluminium alloy (LM 6) suitable for twin moose
33 KV LA Terminal Connector duly made of aluminium alloy (LM 6) suitable for twin moose
33 KV CT Terminal Connector duly made of aluminium alloy (LM 6) suitable for twin moose
33 KV Isolator Bi-metallic terminal Connector duly made of aluminium alloy (LM 6) suitable for twin moose
33KV Bus Post Clamp suitable for twin moose
Supply for Extension of 33 KV Main Bus and Transfer Bus including Jack Bus for extending Main & Transfer Bus and 33 KV outgoing feeder bay
Bolted type Single suspension fitting for ACSR Moose conductor complete with ball hook, socket eye, yoke plate etc, confirming to BIS : 2486 Part I.
132 KV Bolted type Single tension fitting wth turn buckle for ACSR Moose conductor of 250 mm spacing without turn buckle, D-shackle, D-socket, yoke plate, tension clamp 2 Nos. confirming to BIS: 2486 Part I.
Bolted type Single tension fitting wth turn buckle for ACSR Panther conductor , D-shackle, D-socket, yoke plate, tension clamp 2 Nos. confirming to BIS: 2486 Part I.
Bolted type Single suspension fitting for ACSR Panther conductor complete with ball hook, socket eye, yoke plate etc, confirming to BIS : 2486 Part I.
Bolted type double suspension fitting with suspension insulator string for ACSR Moose conductor complete with ball hook, socket eye, yoke plate etc, confirming to BIS : 2486 Part I.
Bolted type double tension fitting with tension insulator string wth turn buckle for ACSR Moose conductor of 250 mm spacing without turn buckle, D-shackle, D-socket, yoke plate, tension clamp 2 Nos. confirming to BIS: 2486 Part I.
Anti-Fog Disc Insulator 70KN
20 mm GI U-bolt of MS rod having thread on both side complete with washer and spring washer 04 Nos. nuts,duly hot dip galvanized as per IS.
PG Clamps suitable for Panther to Moose
PG Clamps suitable for Panther to Panther
PG Clamps suitable for Moose to Moose
PG Clamps suitable for Zebra to Panther
60 mm spacing spacer of twin ACSR Panther conductor made of aluminium alloy LM-6 complete with nuts, bolts & washers confirming to BIS : 5561.
100 mm spacing spacer of twin ACSR Moose conductor made of aluminium alloy LM-6 complete with nuts, bolts & washers confirming to BIS : 5561.
33 KV CB Terminal Connector duly made of aluminium alloy (LM 6) suitable for panther
33 KV CT Terminal Connector duly made of aluminium alloy (LM 6) suitable for panther
33 KV Isolator Bi-metallic terminal Connector duly made of aluminium alloy (LM 6) suitable for twin ACSR Panther
33KV Bus Post Clamp suitable for ACSR Panther
33 KV PT Terminal Connector duly made of aluminium alloy (LM 6) suitable for Twin ACSR Moose
Supply for 33KV Jack Bus / 33KV Outgoing Bay (2) for extending 33KV Main Bus with 2*(2*5MVAr) Capacitor Bank with the Bay
Bolted type Single tension fitting wth turn buckle for ACSR Panther conductor , D-shackle, D-socket, yoke plate, tension clamp 2 Nos. confirming to BIS: 2486 Part I.
Bolted type Single suspension fitting for ACSR Panther conductor complete with ball hook, socket eye, yoke plate etc, confirming to BIS : 2486 Part I.
Anti-Fog Disc Insulator 70KN
20 mm GI U-bolt of MS rod having thread on both side complete with washer and spring washer 04 Nos. nuts,duly hot dip galvanized as per IS.
PG Clamps suitable for Panther to Moose
PG Clamps suitable for Panther to Panther
60 mm spacing spacer of twin ACSR Panther conductor made of aluminium alloy LM-6 complete with nuts, bolts & washers confirming to BIS : 5561.
33 KV CB Terminal Connector duly made of aluminium alloy (LM 6) suitable for panther
33 KV CT Terminal Connector duly made of aluminium alloy (LM 6) suitable for panther
33 KV Isolator Bi-metallic terminal Connector duly made of aluminium alloy (LM 6) suitable for twin ACSR Panther
33KV Bus Post Clamp suitable for ACSR Panther
33 KV PT Terminal Connector duly made of aluminium alloy (LM 6) suitable for Twin ACSR Moose
PART- B: Works
Erection of The 132/33KV 63MVA Transformer, including Centrifusing, Testing & Commissioning
Complete erection of 132/33KV, 63MVA T/F. The erection of radiator, conservator tank, all bushings, turrets, Bucholz relay, connecting pipe lines, cooling fans, motor drive mechanism of tap changer jumpering of HV & LV side etc.Filling & topping up of the T/F oil in tank, radiator, all pipe lines, conservator tank etc. and attending the oil leakages if any and all other associated works for satisfactory completion of work. All T & P shall be provided.
40mm dia MS electrodes of 3 metre length ( Supply will be from Ispat Nigam/SAIL and its authenticated purchase Invoice, dated after tender date and specific for the S/S should be maintained and be submitted at the time of supply)
Both side Jumpering of the 63MVA T/F.
HV side with single ACSR panther conductor.
LV side with ACSR Twin Moose conductor.
Termination of 63MVA, 132/33 KV T/F Bay control cables in control & relay panel as per cable schedule including making necessary holes in the glands plates or box wherever required, the job satisfactorily as per technical specification.
Erection & installation of RTCC panel of 63MVA T/F along with shifting from storage place to Control room including termination & connection of control cables at RTCC panel side & transformer side as per technical specification.
Earthing by Cutting, Straightening & Laying 500mm below Inside Ground & above Ground of Following sizes MS Flat for Diagonal / Double Earthing of the Main & Aux. Structures, Equipments and Cable Trenches including Welding with Main Earth Mat and with the Object to be Earthed including Excavation of Trenches & its Back Filling etc. And Earthing of both 63MVA T/F and 132KV TBC bay including Main Tank, marshelling box, Drive mechanism of 63MVA Transformer and 6Nos. of 145KV CT, 3Nos. of 36KV CTs along with their JBs and 3Nos. of 120KV LAs & 30KV LAs each, 145KV CBs and 36KV CBs and other equipments and associated structures with 40mm MS Round Bar, 40mm Round Bar Electrode of 03 meter length, 75x10 mm, 50x6mm and 25x6mm Copper / MS Flat strips, earthing of cable trenches with 25x6mm MS Flat strips which includes providing, cutting,welding, strengthening and bending of MS flat and shifting of all other associated material from store to work site:-
25x6mm. MS Flat
50x6mm. MS Flat
75x10mm. MS Flat
Painting of newly erected MS Flat following with 01 coat red oxide and 02 coat with bus green ISI mark paint complete with its MS Flat & vertical support after proper removal of Rust / Dust and cleaning of it .
25x6mm. MS Flat
50x6mm. MS Flat
75x10mm. MS Flat
Pre commissioning test of 63 MVA 132/33Kv Transformer in which following tests are to be conducted and provide it's result in hard copy of appropriate number of copies:- i) SFRA ii) Tan Delta Capacitance measurement of windings iii) Tan Delta capacitance measurement of bushings iv) Winding resistance measurement v) Voltage Ratio Test vi) Magnetizing Current test vii) Magnetic Balance Test viii) Insulation resistance Test & PI Test ix) Short Circuit Test x) DGA Test xi) PPM of T/F Oil xii) Other relevent tests not mentioned here for T/F
Obtaining No Objection Certificate from office of Electrical Safety Directorate, Lucknow for first time energisation of 63 MVA 132/33KV Transformer and associated bays (including payment of fee as per challan.)
Dismantling of 132KV Equipments for Construction of 132KV Transfer Bus
Dismantling of 132KV Equipments for making space for Construction of 132KV Transfer Bus Bar along with all associated work at 132 KV S/S Barabanki
Dismantling of 145KV SF6 CB of all 4 No 132 KV Bays (2 Nos. Line Bays and 2 Nos. T/F Bays) by disconnection of AC and DC supply and opening of nut bolts, jumpers, cable connectors, earthing, GI Structures and lifting with the help of Hydra then shifting of all dismenteled material from old foundation to new foundation of Circuit Breaker with all other associated works to complete the job satisfactorily.
Dismantling of 145KV Bus/Line isolator of all 4 No 132 KV Bays (2 Nos.Line Bays and 2Nos. T/F Bays) by disconnection of AC and DC supply and opening of nut bolts, jumpers, cable connectors, earthing, GI Structures and lifting with the help of Hydra then shifting of all dismenteled material from old foundation to new foundation of Isolator with all other associated works to complete the job satisfactorily.
Removal of Unused 1.1KV Insulated Unarmoured Copper Control Cables from dismantled equipments (rates are taken as 60% of Control Cable Laying rates as per attached E T. No.-40/ETC-I(L)/2024-25 SL No.116-118
2Cx 2.5 Sq. mm size Control Cable
4Cx 2.5 Sq. mm size Control Cable
6C x 2.5 Sq. mm size Control Cable
10C x 2.5 Sq. mm size Control Cable
Erection of Existing 132KV Equipments after Shifting for making space for Construction of 132KV Transfer Bus
Construction of 132 KV Transfer bus bar by providing Moose conductor and Extension of 132 KV Main Bus of twin moose alongwith all associated work at 132 KV S/S Barabanki
Erection of 145KV SF6 CBs of all 4 No 132 KV Bays (2 NO line bays and 2No T/F Bays) by fixing of supporting structures,fixing of interrupting unit at the frames as per drawing, checking level of all the three poles, with level meter, the connecting all mechanical linkage,connecting gas pipes, complete cable connection, electrical terminations as per drawing, the work also includes all the modifications required for the fixing base legs of CB with the help of welding machine etc, providing fixing 50x6 mm ms flat for connection of earthing and painting it by 1 coat red oxide primer and 2 coat synthetic enamel green colour paint with all other associated works to complete the job satisfactorily.
Erection of 145KV Bus isolators of all 4 No 132 KV Bays (2 NO line bays and 2No T/F Bays) by fixing of supporting structures as per drawing, the connecting all mechanical linkage, complete cable connection, electrical terminations as per drawing, the work also includes all the modifications required for the fixing base legs of bus isolators with the help of welding machine etc, providing fixing 50x6 mm ms flat for connection of earthing and painting it by 1 coat red oxide primer and 2 coat synthetic enamel green colour paint with all other associated works to complete the job satisfactorily.
Laying of following sizes Control Cables to be Provided by Department as per Requirements in Cable Trenches from C&R Panels in Control Room to the Equipment Terminal Box of newly shifted 132KV CBs & Isolators of all 4 No 132 KV Bays (2 NO line bays and 2No T/F Bays) in Switchyard as per Cable Schedule including Shifting of Cables in Drums from Storage Place at the Sub Station to Erection Site & Shifting Back the Balance Cables to Stores at the Sub Station :
2Cx 2.5 Sq. mm size Control Cable
4Cx 2.5 Sq. mm size Control Cable
6C x 2.5 Sq. mm size Control Cable
10C x 2.5 Sq. mm size Control Cable
Carriage of required Structures & Other Equipments from other locations to 132KV S/S, Barabanki
Sorting out and Stacking of Main & Auxiliary Structure as per BOM at EFU Naini (Allahabad)
Loading of structure on Private Truck / trailer at EFU Naini.
Transportation of structure from EFU Naini, Allahabad to 132KV S/S Barabanki
Unloading and proper stacking of structure parts at 132 KV S/S Barabanki
Carriage of 145 KV SF6 CB from near by any s/s belongs to ETC-I, Lucknow/ its equivalent distance to 132 KV S/S Barabanki along with safe loading and unloading to and from the vehicle arranged with shifting of the CB from store place including cost of Truck/Trailer, labour and T&Ps to be arranged by the contractor at his own cost (Approx. Distance 120 Km a side).
Loading of ACSR Moose from near by any s/s belongs to ETC-I, Lucknow to 132 KV S/S Barabanki along with safe loading and unloading to and from the vehicle arranged with shifting of the conductor from store place including cost of Truck/Trailer, labour and T&Ps to be arranged by the contractor at his own cost.
Safe Carriage of above ACSR Moose Conductor in Drums, Loaded on the Vehicle arranged by the Contractor from available s/s to 132 KV S/S Barabanki (Approx. Distance 120 Km).
Safe Unloading of above ACSR Moose Conductor in Drums from the Vehicle and Shifting of same to Safe Storage Place at 220KV Sub Station, Barabanki (1 Job per Drum)
Loading of 10 No. Control Cable Drum (as per requriment) from near by any s/s belongs to ETC-I, Lucknow to 132 KV S/S Barabanki including cost of Truck/Trailer, labour and T&Ps to be arranged by the contractor at his own cost.
Safe Carriage of above 10 No. Control Cable Drum (as per requriment) , Loaded on the Vehicle arra
nged by the Contractor from available s/s to 132 KV S/S Barabanki (Approx. Distance 120 Km).
40mm dia MS round bar ( Supply will be from Ispat Nigam/SAIL and its authenticated purchase Invoice, dated after tender date and specific for the S/S should be maintained and be submitted at the time of supply)
Safe Unloading of above 10 No. Control Cable Drum (as per requriment) in Drums from the Vehicle and Shifting of same to Safe Storage Place at 132 KV Sub Station, Barabanki (1 Job per Drum)
Safe Carriage of above 01 No. 10 (2x5) MVAr Capacitor Bank unit complete set with accessories, such as Shut Reactors, NCT, PT, CRP, and others, not specified here, Loaded on the Vehicle arranged by the Contractor from available s/s to 132 KV S/S Barabanki (Approx. Distance 690 Km a side).
Safe Unloading of above 01 No. 10 (2x5) MVAr Capacitor Bank unit complete set with accessories, such as Shut Reactors, NCT, PT, CRP, and others, not specified here, rom the Vehicle and Shifting of same to Safe Storage Place at 132 KV Sub Station, Barabanki (1 Job per Drum)
Erection of new Structures, new Equipments, new C&R Panels for 63 MVA Transformer and 132 KV TBC Bay
BCT (132KV / 220KV CT / PT Structure) (9 Set) 1.613 MT
ATM (132KV Column) (9 Set) 12.722 MT
BTM (132KV Column) (8 Set) 5.754 MT
AXM (132KV Beam) (21 Set) 17.051 MT
XPM (Peak for 132KV Column) (8 Set) 0.675 MT
YMM (Mast for 132KV Column) (4 Set) 0.85 MT
ALP (PI 132KV) (25 Set) 3.025 MT
TMR (Mast for 33KV Column) (8 Set) 0.231 MT
CGR/ CGM (Beam for 33KV Column) (7 Set) 2.133 MT
CCR/ CCM (33KV Column) (6 Set) 2.916 MT
CPR (Peak for 33KV Column) (8 Set) 0.469 MT
ABL (Isolator Structure) (5 Set) 1.705 MT
ALP (PI 33KV) (16 Set) 1.936 MT
TMR (Mast for 132KV Column) (5 Set) 0.100 MT
APR (Peak for 132KV Column) (7 Set) 0.641 MT
EKR (132KV Column- Narrow Base) (9 Set) 7.608 MT
Erection of Main & Aux Structures
Erection of 132KV Side Equipments
Erection of 132 KV C.B.
Erection of 132 KV C.T.
Erection of 132 KV C.T. Junction Box
Erection of 132 KV P.I.
Erection of 132 KV Bus Isolator
Erection of 132 KV Bus Tendom Isolator
Erection of 132 KV L.A.
Erection of 33KV Side Equipments
Erection of 33 KV V.C.B.
Erection of 33 KV C.T.
Erection of 33 KV C.T. Junction Box
Erection of 33 KV P.T.
Erection of 33 KV P.T. Junction Box
Erection of 33 KV P.I.
Erection of 33 KV Bus Isolator without Earth Blade & with P.I.
Erection of 33 KV L.A.
Erection of C&R Panel for 63 MVA Transformer and 132KV TBC
Laying of of 132KV Transfer Bus and Strengthening of 132KV Main Bus along with extension of the sameExisting 132KV Equipments after Shifting for making space for Construction of 132KV Transfer Bus
Laying tensioning & stringing of 132KV Transfer bus bar of ACSR Moose conductor including hoisting of Disc Insulator string & Fitting etc. and jointing section of 132KV Transfer Bus by U shaped jumper between adajacent bus section with the help of suitable PG clamps including shifting of the conductor/ Material from store to switchyard (1 job for each phase per section)
Laying tensioning & stringing of 132KV Main bus bar of ACSR Twin Moose conductor including hoisting of Disc Insulator string & Fitting etc. and jointing section of 132KV Main Bus by U shaped jumper between adajacent bus section with the help of suitable PG clamps including shifting of the conductor/ Material from store to switchyard (1 job for each phase per section)
Fixing of spacers in twin ACSR Moose conductor For maintaining 250mm spacing between twin Moose / Zebra conductor. Each spacers is to be installed at every 3mtr distance of twin Moose conductor of all three phase conductor and in ther jumpers. All required labour, T&P etc. will be arranged by the contractor at his own cost.
Rejumpering of Twin/Single ACSR Panther/ Zebra/ Moose conductor between newly shifted main bus isolator to CB and CB to another bus and Tandem isolators and CTs with each other of all 4 No 132 KV Bays (2 NO line bays and 2No T/F Bays) and 132 KV Transfer Bus also (1 Job per single jumper/ 2 Job per twin jumper reconnection from both ends)
Erection of SAMAST Energy Meter and Data communication work
TMR (Mast for 33KV Column) 0.058 MT
Installation of new 3P4W, 0.2s accuracy class Interface Energy Meters (one HV side and one LV side)
Extension of of 33KV Main and 33KV Transfer Bus and Strengthening of 33KV Main Bus
Stringing of 132KV Jack Bus for 63 MVA Transformer jumpering HV, LV side & 132KV TBC Bay work
Stringing of 132KV Jack Bus Bar of Span 36 to 42.5 Meter with Single ACSR Panther Conductors including Hoisting of Disc Insulator Tension String with associated Tension Fitting alongwith Shifting of the Conductors, Tension Fittings, Clamps etc. from Stores at the Sub Station to Switchyard for 132KV side of new 63MVA T/F (02 Span)and 132KV Bus-Coupler (01 Span). (1 Job for each Phase of each Section of the Jack Bus Bar)
Jumpering of 132KV side Equipments of 63 MVA T/F with the help of ACSR Panther conductor to connect the Bus Bar Conductors of 132KV Main Bus & 132KV Transfer Bus with Equipment and Equipment to Equipment with the help of suitable clamps/connectors including cutting, bending, shaping etc. of the Conductor as per site requirements:
Jumpering of 33KV side Equipments of 63 MVA T/F with the help of Twin ACSR Moose/ Zebra conductor to connect the Bus Bar Conductors of 33KV Main Bus with Equipment and Equipment to Equipment with the help of suitable clamps/ connectors including cutting, bending, shaping etc. of the Conductor as per site requirements:
Installation of communication cable (CAT-6 alongwith necessary hardware wherever required in between Energy meter to Lan switch to SDH equipments upto DCU/ Gateway and all other H/W, S/W per No.
Jumpering of all 132KV euipments of 132KV TBC Bay with the help of ACSR Panther/Zebra/moose conductor to connect the Bus Bar Conductors of 132KV Main Bus & 132KV Transfer Bus with Equipment and Equipment to Equipment with the help of suitable clamps/connectors including cutting, bending, shaping etc. of the Conductor as per site requirements:
Extension of 33KV Transfer Bus by Laying tensioning & stringing of 33KV Transfer bus bar of ACSR Moose conductor including hoisting of Disc Insulator string & Fitting etc. and jointing section of 33KV Transfer Bus by U shaped jumper between adajacent bus section with the help of suitable PG clamps including shifting of the conductor/ Material from store to switchyard (1 job for each phase per section)
Laying tensioning & stringing of 33KV Main bus bar of ACSR Twin Moose conductor including hoisting of Disc Insulator string & Fitting etc. and jointing section of 33KV Main Bus by U shaped jumper between adajacent bus section with the help of suitable PG clamps including shifting of the conductor/ Material from store to switchyard (1 job for each phase per section)
Fixing of spacers in twin ACSR Moose conductor For maintaining 100mm spacing between twin Moose / Zebra conductor. Each spacers is to be installed at every 3mtr distance of twin Moose conductor of all three phase conductor and in ther jumpers. All required labour, T&P etc. will be arranged by the contractor at his own cost.
Rejumpering of Twin/Single ACSR Panther/ Zebra/ Moose conductor between newly shifted main bus isolator to CB and CB to another bus and Tandem isolators and CTs with each other of all 2 Nos. 33KV Bays (2 Nos. Outgoing Bays) and 33KV Capacitor Banks also at 33KV Main Bus (1 Job per single jumper/ 2 Job per twin jumper reconnection from both ends)
Laying of control cable in switchyard area and other miscellaneous work for 132/33KV, 63MVA Transformer Bay, 132KV Bus Coupler Bay, 33KV Capacitor Bank Bays, 33KV Outgoing Bays, Lighting and Other Associated Works
Laying of following sizes Control Cables to be Provided by Department as per Requirements in Cable Trenches from C&R Panels in control room to various 132KV & 33KV Equipments, Junctions Boxes, 63MVA TF Marshelling Box, RTCC Panel, and all equipments of the 132KV and 33KV side of the new 63MVA, 132/33KV T/F Bay, 132KV TBC Bay, 33KV Capacitor Bank Bays (2), 33KV Outgoing Bays (shifting- 2, Extension- 2, Spare- 1, Total- 5) in Switchyard, also for lighting work from LT ACDB to lighting junction boxes as per Cable Schedule including Shifting of Cables in Drums from Storage Place at the Sub Station to Erection Site & Shifting Back the Balance Cables to Stores at the Sub Station : -
2 x 2.5 Sq. mm size Control Cable
4 x 2.5 Sq. mm size Control Cable
6 x 2.5 Sq. mm size Control Cable
stacking of the same at the desired place along with other associated works to complete the work satisfactorily.
10 x 2.5 Sq. mm size Control Cable
63MVA Transformer Bay HV side at Switchyard end (including Marshalling Box)
63MVA Transformer Bay LV side
132KV TBC Bay
03 Nos. 33KV Outgoing Bays
Erection of Sub-Station Structure including making of earthing, with other associated works to complete the job satisfactorily
Earthing of L.T. A.C. Supply Cubical with Providing & Fixing of 600×800×8mm size G.I. Plate with its Top At Least 3 Meter below the Ground Level with 20mm dia. G.I. Pipe & Funnel for Watering, 1 No. 8 SWG G.I. Wire Earthing Lead etc. with Alternate Layer of Charcoal / Coke and Salt at Least 150 mm Thick Around it.
Providing & Fixing of 150 Watt L
.E.D. Street Light Luminaries Fittings of Philips / Compton Greaves / Havells make with IP 65 rating in Single Piece Die Cast Aluminium Alloy Housing with Pot Optics Reflector & Toughened Clear Glass Cover with Frame for Lamp Compartment (with two year standard warranty period) inlcuding Cable Terminations.
Portable CO2 type Fire Extinguisher 22.5KG capacity
Laying of above Control Cables from L.T. Lighting Junction Box to LED Street Light Fittings by clamping with suitable M.S. Strip Clamp with proper Dressing etc.
Providing & Fixing of Cable Marker duly made of Cast Iron.
Extension of MS Round Bar Earthmat 40mm by digging of earth cutting, laying, welding and back filling of earth and doing all other associated work to complete the job satisfactorily.
Making of Shielding Mesh, Diamond earthing, Delta etc and earthing of various equipments and elements with following details:
Earth Fault Detection Meter ( Kit shall be able to locate earth faults on live Floating 220 V/110V DC system. The instrument shall be capable of finding faulty interconnection (Source Mixing) on dual battery system, even in case of no earth fualt in both DC system. Also, capable to identify AC-DC mixing capable to detect earth fault in AC/DC ungrounded system (IT) upto 500V, Capable to measure leakage current in 415 V AC grounded system of Taurus/ Greenwatt make)
Making of Shielding Mesh for 03 Nos. 120KV LA by Fabrication of 06 Nos., 03 Meter Long Electrode with 40mm diameter MS Rod having 150mm Long Conical Shape and then its Piercing Vertically in the Ground with top 500mm below Ground Level, its Welding with 75x10mm size MS Flat for Making of Shielding Mesh for LAs and Finally, Connecting the Shielding with Main Earth Mat at 2 Places and finally Painting with Black Anti-Corrosive Paint, with due Digging of Earth / Trench, its Back Filling. Two no risers of 75x10mm MS Flat will be welded with exixting main earth mat to Auxiliary structure, one separate riser will be taken from the laid earth mat to corresponding LA through surge counter for making of proper mesh.
Excavation of trench in rectangular shape around LA structures for Diamond earthing for 03Nos. 30KV LA by fabrication of 06nos 3 Meter Long Electrode with 40 mm dia. MS Rod having 150 mm Long Conical Shape and then its Piercing Vertically in the Ground with top 700 mm below Ground Level, jointing electrodes with 75x10 mm size MS Flat by proper welding. Two no of risers of 75x10 sq mm MS Flat shall be welded with existing earthmatto Auxiliary structure, one separate riser will be taken from the laid earth mat to corresponding LA through surge counter for making of proper mesh.. Painting of shielding Mesh/Earthing strips with Black Anti-Corrosive Paint, with due Digging of Earth / Trench, its Back Filling.
Special earthing by way of boring & lowering of GI Pipe 50mm dia 60 feet long from ground upto water level and it will be connected to the MS strip 50x6mm including providing, laying of MS strip with cutting welding bending etc. for 36KV VCB’s & 36KV CT’s etc. of different bays at 132KV Sub-station, Barabanki. The earth strip will be welded to the GI Pipe. The work also includes cap & clamps for pouring water. All the materials, labour and T&P shall be supplied by the firm (02 Nos. Capacitor Banks, 02 Nos. Outgoing Bays).
CPR (Peak for 33KV Column) 0.117 MT
Providing & fixing of updated single line diagram in PVC sheet of size 6x6 feet of complete 132/33KV switchyard of 132KV S/S, Barabanki as per instruction by concerned JE/ SDO.as applicable norms of UPPTCL
Special Earthing by way of boring and lowering of 'B' Class GI pipe of size 2.5mm2 dia * 20meter long from ground level upto the water level and it will be connected to the G.I. Strip 50x6mm (Providing & Laying of G.I. Strip including Digging, Laying, Bending, Cutting, Welding, Cleaning, Painting, Filling work, etc., whatever applicable, for Making Boring of 60 feet long for Earthing of 145KV CT's (3), 36KV CT's (3), 120KV LA (3), 30KV LA (3) on 33KV Bus (3), 145KV CB (1) and 36KV CB (1), including cost of 2.5" GI pipes required for boring with accessories and lowering of it along with other associated works to complete the work as per technical specification and UPPTCL norms, The work also includes the cost of Cap and Clamps for pouring water, cost of Labour and T&P
BTI (132KV Tendam Isolator Structure) (5 Set) 2.923 MT
ATMS (132KV Column) 0.00 MT
ABL (36KV Isolator Structure) 1.364 MT
BBL (132KV Isolator Structure) (8 Set) 4.008 MT 65.595 MT
CCR/ CCM (33KV Column) 3.888 MT
CGR/ CGM (Beam for 33KV Column) 1.219 MT
Dismantling, Shifting, and Erection of 2x5 MVAr Capacitor Bank including equipment & acessories
BTI (132KV Tendam Isolator Structure) (5 Set) 2.923 MT
ATMS (132KV Column) 0.00 MT
CPR (Peak for 33KV Column) 0.352 MT
BBL (132KV Isolator Structure) (8 Set) 4.008 MT 65.595 MT
CCR/ CCM (33KV Column) 3.888 MT
CGR/ CGM (Beam for 33KV Column) 1.219 MT
Erection of 10MVAr Capacitor Bank along with Column Beam, Connecting and Stringing of concerned section of Bus-Bar, including equipments like NCT, CT, isolator, Shunt Reactor, Capacitor Cells with unit structure, Breaker & accessories, Laying and Connection of Control Cables, Termination of Control Cable to the Control and Relay Panel of Capacitor Bank, Electrical Connections, along with making of earthing with other associated works to complete the job satisfactorily as per UPPTCL norms along with Shifting of material to the required place along with Preparation of Inter-Connection Drawing and Commissioning of the Panel / Feeders in Co-Ordination with T&C Wing including Providing of 2 Sets of Hard copies of as Executed Inter-connection Drawing..
Filling of transformer oil in to main tank and Centrifuging of oil in main transformer tank on even temperature (between 60-65°C) with uninterrupted period (minimum 72 hours) till the desired BDV valve of the oil is achieved, including recording of all the parameters hourly such as temperature, vacuum, BDV, moisture, air molecules PPM, material, centrifuging machine and T & P.
Erection of Auxiliary and Sub-Station Gantry Structures as per drawing with GI Nut-Bolts and washers including fabrication, cutting, bending, making hole to the GI Structure, if required, including cost of men and T&P but excluding GI Structure and Nut-Bolt Washer, including shifting and stacking of the same from stored place along with other associated works to complete the work satisfactorily.
Dismantling and Construction of 33 KV Outgoing Feeder Bay after Shifting and Other Equipments along with Preparation of Inter-Connection Drawing and Commissioning of the Panel / Feeders in Co-Ordination with T&C Wing including Providing of 2 Sets of Hard copies of as Executed Inter-connection Drawing.
36KV VCB with it's jumpers and opening of cable coneections
36KV CT with it's jumpers and opening of cable coneections
36KV CT Junction Box
36KV BSI with it's jumpers and opening of cable coneections
Laying of following sizes Control Cables to be Provided by Department as per Requirements in Cable Trenches from C&R Panels in control room to various 132KV & 33KV Equipments, Junctions Boxes, 63MVA TF Marshelling Box, RTCC Panel, and all equipments of the 132KV and 33KV side of the new 63MVA, 132/33KV T/F Bay, 132KV TBC Bay, 33KV Capacitor Bank Bays (2), 33KV Outgoing Bays (shifting- 2, Extension- 2, Spare- 1, Total- 5) in Switchyard, also for lighting work from LT ACDB to lighting junction boxes as per Cable Schedule including Shifting of Cables in Drums from Storage Place at the Sub Station to Erection Site & Shifting Back the Balance Cables to Stores at the Sub Station : -
2 x 2.5 Sq. mm size Control Cable
4 x 2.5 Sq. mm size Control Cable
36KV LSI with it's jumpers and opening of cable coneections
Removal of Control Cable from Cable Trench including making roll of the same and shifting it to the desired place, with other associated works to complete the job satisfactorily
Dismantling of Sub-Station Structure including removal of earthing, with other associated works to complete the job satisfactorily
ABL Structure
ALP Structure
Erection of 33KV Outgoing Bay including all equipments and earthing, making of jumpers, connection of control cables, laying of control cable, electrical connections, with other associated works to complete the job satisfactorily
36KV VCB with it's jumpers and opening of cable coneections
36KV VCB
36KV VCB with it's jumpers and opening of cable coneections
36KV BSI with it's jumpers and making of cable connections
Laying of following sizes Control Cables to be Provided by Department as per Requirements in Cable Trenches from C&R Panels in control room to various 132KV & 33KV Equipments, Junctions Boxes, 63MVA TF Marshelling Box, RTCC Panel, and all equipments of the 132KV and 33KV side of the new 63MVA, 132/33KV T/F Bay, 132KV TBC Bay, 33KV Capacitor Bank Bays (2), 33KV Outgoing Bays (shifting- 2, Extension- 2, Spare- 1, Total- 5) in Switchyard, also for lighting work from LT ACDB to lighting junction boxes as per Cable Schedule including Shifting of Cables in Drums from Storage Place at the Sub Station to Erection Site & Shifting Back the Balance Cables to Stores at the Sub Station : -
2 x 2.5 Sq. mm size Control Cable
4 x 2.5 Sq. mm size Control Cable
36KV LSI with it's jumpers and making of cable connections
ALP (36KV CT/ PT/ LA Structure) 0.726 MT
TMR (Mast for 33KV Column) 0.116 MT 7.664 MT
CGR/ CGM (Beam for 33KV Column) 0.914 MT
TMR (Mast for 33KV Column) 0.116 MT 7.664 MT
ABL Structure 2.728 MT
ALP Structure 1.452 MT
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.69 MB
td.pdf
Tender Documents • 1.33 MB
BOQ_2020780.xls
BOQ • 0.42 MB
Download all tender documents and submit your bid