Tender Value
₹2.6 L
EMD Value
₹2,700
Closing Date
11 May 2026, 12:00 pmClosed
Similar tender results from the same govt authority in the past 3 years.
DEPUTY EXECUTIVE ENGINEER, CAPITAL PROJECT ELECTRICAL SUB DN NO 23, GANDHINAGAR
Annual maintenance of Inverter type split A.C machines in Gujarat Mahiti Aayog ,Second floor Karmayogibhavan-1, Sector -10A ,Gandhinagar.(For the year 2026-27)
300068
01/02 OF 2026/2027
Open
Electrical and Maintenance Works
Gandhinagar
8 documents required · 8 mandatory
₹600
Dy. Executive Engineer, Capital Project Electrical Sub Division No 23, Gandhinagar.
₹2,700
1 May 2026
1 May 2026
1 May 2026
11 May 2026
1 May 2026
Name of Work Annual maintenance of Inverter type split A.C machines in Gujarat Mahiti Aayog ,Second floor Karmayogibhavan-1,
Sector -10A ,Gandhinagar.(For the year 2026-27)
Fund Head : Deposited work
Sr. No. Item No. Particulars. Qty. Rate Amount
Signature of Contractor Deputy Executive Engineer
C.P Electrical R & B Sub Dn
Name of Work Annual maintenance of Inverter type split A.C machines in Gujarat Mahiti Aayog ,Second floor Karmayogibhavan-1,
Sector -10A ,Gandhinagar.(For the year 2026-27)
Estimated Quantity Item Description Unit Amount in Rs.
No. in Figure In Word
All inclusive comprehensive maintenance cost for the
period of one year for the Inverter Based Split type Air- Rupees Two Thousand
1 33 Nos. conditioning Unit of following Capacity (B) 1.5 ton 2,282.60 Two Hundred Eighty Two Ea.
capacity. (A) Charges for breakdown Maintenance as per And Paise Sixty Only
requirement throughout the year
(B) Charges for 1st Routine Maintenance of Dry Services Rupees Two Hundred
33 Nos. between date of commencement to 3rd Months from date 267.65 Sixty Seven And Paise Ea.
of issue of work order. Sixty Five Only
(C) Charges for 2nd Routine Maintenance of wet Services
Rupees Four Hundred
with water or Chemical as per site requirement Services
33 Nos. 494.90 Ninety Four And Paise Ea.
between 3rd months to 6th Months from date of issue of
(D) Charges for 3rd Routine Maintenance of Dry Services Rupees Two Hundred
33 Nos. between 6th months to 9th Months from date of issue of 267.65 Sixty Seven And Paise Ea.
work order. Sixty Five Only
(E) Charges for 4th Routine Maintenance of wet Services
Rupees Four Hundred
with water or Chemical as per site requirement Services
33 Nos. 494.90 Ninety Four And Paise Ea.
between 9th months to 12th Months from date of issue of
Estimated Quantity Item Description Unit Amount in Rs.
No. in Figure In Word
All inclusive comprehensive maintenance cost for the
period of one year for the Inverter Based Split type Air-
conditioning Unit of following Capacity (C) 1.7 to 2.0 ton
Rupees Two Thousand
(A) Charges for breakdown Maintenance as per
29 Nos. 2,829.01 Eight Hundred Twenty Ea.
requirement throughout the year
Nine And Paise One Only
(B) Charges for 1st Routine Maintenance of Dry Services Rupees Three Hundred
29 Nos. between date of commencement to 3rd Months from date 330.27 Thirty And Paise Twenty Ea.
of issue of work order. Seven Only
(C) Charges for 2nd Routine Maintenance of wet Services
with water or Chemical as per site requirement Services Rupees Six Hundred
between 3rd months to 6th Months from date of issue of Twelve And Paise Six Only
(D) Charges for 3rd Routine Maintenance of Dry Services Rupees Three Hundred
29 Nos. between 6th months to 9th Months from date of issue of 330.27 Thirty And Paise Twenty Ea.
work order. Seven Only
(E) Charges for 4th Routine Maintenance of wet Services
with water or Chemical as per site requirement Services Rupees Six Hundred
between 9th months to 12th Months from date of issue of Twelve And Paise Six Only
RUPEES IN WORDS : Rupees Three Lacs Sixsty six thousand three hundred sixty two & Paise Tirty five only.
Estimated Quantity Item Description Unit Amount in Rs.
No. in Figure In Word
I/We am/are willing to carry out the work at(No above rates allowed) ____________% below ___________________________________
__________________percent (Should be written in figures and words) below the tendered rates mentioned above.
Amount of my/our tender works out as under :
Put to Tender Rs. 262,350.53 Put to Tender Rs.
(Please strike out whichever is not applicable)
1 I/We hereby declare that I/We have visited the site, fully exquisite myself/ourselves with the local situation regarding materials and other factors pertaining to the work
before submitting this tender.
2 I/we hereby declare that I/We carefully studied the conditions of specifications and other tender documents of this work and agree to execute the same accordingly.
3 A tender with any overwriting in percentage (should both in word and figures) rejected out right.
4 Insertions and/or corrections in the percentage quoted ( both in word and figures) resulting into increase in the value of the work shall be rejected outright unless it is
authenticated by the office opening the tender at the time of opening of tender.
5 Dismentaling the existing material taken by contractor as mention rates.
Signature of Contractor Deputy Executive Engineer
C.P Electrical R & B Sub Dn
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
G S T LTR.pdf
GR.pdf
notice-1.pdf
PQ.pdf
SBD Document.pdf
schedule a and b.pdf
ac amc condition.pdf
Download all tender documents and submit your bid