| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹16.4 CrAdmitted-Finance | L1 | Admitted-Finance | ||
| 2 | L2₹18.7 Cr+₹2.3 Cr (14.2%)Admitted-Finance | L2 | Admitted-Finance | ||
| 3 | L3₹19.0 Cr+₹2.6 Cr (16.1%)Admitted-Finance | L3 | Admitted-Finance | ||
| 4 | L4₹19.2 Cr+₹2.8 Cr (17.3%)Admitted-Finance | L4 | Admitted-Finance | ||
| 5 | L5₹19.6 Cr+₹3.3 Cr (20.0%)Admitted-Finance | L5 | Admitted-Finance |
Tender Value
₹18.0 Cr
Closing Date
27 Sept 2021, 6:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
EE, RSAMB, Jodhpur-II
EE, RSAMB, Mandore mandi Jodhpur-II
Construction of Residential School Bhaniyana Block Sankara Distt. Jaisalmer, for Minority Department
2021_RSAMB_241122_1
NIT-05/2021-22
Open Tender
Civil Works - Buildings
Percentage
540 days
Bhaniyana
Please refer Tender documents.
2 documents required · 2 mandatory
₹5,000
ICICI Bank A/C No 683401030353 IFSC ICIC0006834
Exempted
4 Oct 2021
18 Sept 2021
28 Sept 2021
18 Sept 2021
27 Sept 2021
18 Sept 2021
50 days
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Part (A) Civil Work Earth work in excavation by mechanical means (Hydraulic Excavator)/ manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m, including taking out the excavated soil and depositing and refilling of jhiri with watering & ramming and disposal of surplus excavated soil as directed with in a lead of 50 meter. All kinds of soils | 8,925.51 | Cum | 146 | ₹13,03,124.46 |
| 2 | Add extra for foundations /trenches/ drains for every additional lift of 1.5 Mtr. or par thereof upto 4.5Mtr. depth. All kind of soil. | 1,499.7 | Cum | 19 | ₹28,494.3 |
| 3 | Filling available excavated earth (excluding rock) in trenches, plinth side of foundation etc. in layers not exceeding 20 cm. in depth , consolidating each deposited layer by ramming and watering including lead upto 50Mtr. and lift upto 1.5Mtr. | 2,353.93 | Cum | 37 | ₹87,095.41 |
| 4 | Surface dressing of the ground including removing vegetation and inequalities not exceeding 15cm deep and disposal of rubbish lead up to 50 Mtr. and lift up to 1.5 Mtr.:All Kinds of soil. | 7,877 | 100 Sqm | 645 | ₹50,80,665 |
| 5 | Providing and injection Chloropyrifous Emulsifiable concentrate 20 % with 1 % concentration for PRE-CONSGTRUCTIONAL Anti termite treatment as per IS 6313 part III and amended from time to time and creating a continous chemical barrier under and around the column pits, wall trenches, basement excavation, top surface of plinth filling, junction of wall and floor along the external perimeter of building expansion joints, over the top surface of consolidated earth of which aproch is to be laid surrounding of pipes and conduits etc. complete as per specification (Plinth floor area only shall be measured for payment.) Heptachlor E.C. 20% with 10% concentration | 3,644.29 | Sqm | 380 | ₹13,84,830.2 |
| 6 | Providing and laying in position cement concrete including curing compaction etc. complete in spcified grade excluding the cost of centering and shuttering all work upto plinth level 1:3:6 (1Cement :3 Course Sand :6 Graded stone aggregate 40 mm nominal size | 625.55 | Cum. | 2,492 | ₹15,58,870.6 |
| 7 | Providing and laying in position cement concrete including curing compaction etc. complete in spcified grade excluding the cost of centering and shuttering all work upto plinth level 1:4:8 (1Cement :4 Course Sand :8 Graded stone aggregate 40 mm nominal size | 1,074.43 | Cum | 2,235 | ₹24,01,351.05 |
| 8 | Centering and shuttering with plywood or steel sheets including strutting, propping, bracing both ways and removal of formwork for foundations in basements rafts, footings, strap beams, bases of columns , etc. up to plinth level. | 5,102.35 | Sqm | 98 | ₹5,00,030.3 |
| 9 | Centering and shuttering with plywood or steel sheets including strutting, propping, bracing both ways with wooden members and removal of formwork for superstructure up to 4.5 mtr above plinth, Suspended floors, roofs, landings, staircases, balconies, girders, cantilevers, bands , coping, bed plates, anchor blocks, sills, chhajjas lintel, beam etc.for : with Add extra for using steel props and bressings etc. instead of wooden mamber | 15,107.39 | Sqm | 255.6 | ₹38,61,448.88 |
| 10 | Centering and shuttering with plywood or steel sheets including strutting, propping, bracing both ways with wooden members and removal of formwork for superstructure up to 4.5 mtr above plinth, for: with Add extra for using steel props and bressings etc. instead of wooden mamber for Columns, pillars, posts and struts etc. | 1,756.4 | Sqm | 267.6 | ₹4,70,012.64 |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.29 MB
BOQ_430530.xls
BOQ • 0.97 MB
BID_DOCUMENT.pdf
Tender Documents • 5.12 MB
Technical_Bid.pdf
Additional Documents • 0.22 MB
Other_Document.pdf
Other Document • 2.88 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .