| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹36.2 LAccepted-AOC | ₹36.2 L | L1 | Accepted-AOC lowest quotted bidder |
| 2 | L2₹38.0 LRejected-Finance SHABANA MANZIL IRIKKUR | IRIKKUR | KANNUR | KERALA | ₹38.0 L | L2 | Rejected-Finance second lowest bidder |
| 3 | L3₹38.4 LRejected-Finance | ₹38.4 L | L3 | Rejected-Finance Third lowest bidder |
| Sl No | Description | Qty | Unit | KODIKKANDY GROUP L3 | Sajeer C V K L2 | FAISAL K I L1 |
|---|---|---|---|---|---|---|
| 1.00Earth work | ||||||
| 1.00 | 2.4.2.A:Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 metres Cement Concrete Grade M-15 & M-20 - By Mechanical Means | 33.75 | cum | 677.57 ₹22,867.99 | 671.62 ₹22,667.18 | 638.59 ₹21,552.41 |
| 1.00 | 2.1.2:Cutting of trees, including cutting of trunks, branches and removal of stumps, roots, stacking of serviceable material with all lifts and up to a lead of 1000 metres and earth filling in the depression/pit. <br> Girth from 600 mm to 900 mm | 4 | each | 1,025.85 ₹4,103.40 | 1,016.84 ₹4,067.36 | 966.84 ₹3,867.36 |
| 1.00 | 3.6:Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m | 585.35 | cum | 44.95 ₹26,311.48 | 44.55 ₹26,077.34 | 42.36 ₹24,795.43 |
| 1.00 | 12.4:Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. | 155.7 | cum | 6,252.27 ₹9.7 L | 6,197.37 ₹9.6 L | 5,892.65 ₹9.2 L |
| 1.00 | 12.8.A.1:Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. PCC Grade M15 | 276.52 | cum | 7,236.43 ₹20.0 L | 7,172.88 ₹19.8 L | 6,820.19 ₹18.9 L |
| 1.01 | 12.8.1.C.1:Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications RCC Grade M20 - Using Concrete Mixer | 91.3 | cum | 7,859.73 ₹7.2 L | 7,790.74 ₹7.1 L | 7,407.65 ₹6.8 L |
| 1.01 | 12.40:Supply, Fitting and Placing un- coated HYSD bar Reinforcement in Foundation complete as per Drawing and Technical Specifications | 0.06 | MT | 85,606.56 ₹4,708.36 | 84,854.8 ₹4,667.01 | 80,682.54 ₹4,437.54 |
| 1.01 | 12.8.B:Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications <br> PCC Grade M20 (Without formwork) <br> | 11.5 | cum | 7,499.46 ₹86,243.79 | 7,433.61 ₹85,486.52 | 7,068.1 ₹81,283.15 |
Tender Value
₹42.1 L
EMD Value
₹50,000
Closing Date
1 Jan 2026, 4:00 pmClosed
Executive Engineer
PWD Roads Division ,kannur
Construction of CC Drain at Ayipuzha school zone ch 30.000 to 31.240 along Thalassery Irikkur road Mattannur LAC General Civil Work
2025_PWD_823886_1
PWD/RB/TR/15743/2025_5_1_1/1
Open Tender
Civil Works - Roads
90 days
Ayippuzha
Please refer Tender documents.
8 documents required · 8 mandatory
₹2,760
Yes
₹50,000
Yes
3 Mar 2026
24 Dec 2025
3 Jan 2026
24 Dec 2025
1 Jan 2026
24 Dec 2025
Earth work
2.4.2.A:Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 metres Cement Concrete Grade M-15 & M-20 - By Mechanical Means
2.1.2:Cutting of trees, including cutting of trunks, branches and removal of stumps, roots, stacking of serviceable material with all lifts and up to a lead of 1000 metres and earth filling in the depression/pit. <br> Girth from 600 mm to 900 mm
3.6:Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m
12.4:Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.
12.8.A.1:Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. PCC Grade M15
12.8.1.C.1:Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications RCC Grade M20 - Using Concrete Mixer
12.40:Supply, Fitting and Placing un- coated HYSD bar Reinforcement in Foundation complete as per Drawing and Technical Specifications
12.8.B:Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications <br> PCC Grade M20 (Without formwork) <br>
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1381071.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.05 MB
BOQ_1381071.xls
BOQ • 0.30 MB
epay1.pdf
Other Document • 0.05 MB
viewsbd.pdf
Tender Documents • 1.64 MB
Download all tender documents and submit your bid