| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹4.2 LAccepted-AOC | ₹4.2 L | 1 | Accepted-AOC Awarded |
| 2 | 2₹4.3 LRejected-AOC | ₹4.3 L | 2 | Rejected-AOC Not Awarded |
| 3 | 3₹4.3 LRejected-AOC | ₹4.3 L | 3 | Rejected-AOC Not Awarded |
Tender Value
₹4.3 L
EMD Value
₹5,000
Closing Date
2 Apr 2020, 5:00 pmClosed
S.E., E.T.C., Bareilly
Superintending Engineer Transmission Campus Near L.I.C. Office Rampur Garden, Bareilly
Replacement of old Equipments Installed in various 400KV and 220KV Bays alongwith other associated Works at 400KV Sub Station Bareilly under Electy. 400KV Sub Station Division, Bareilly
2020_UPTCL_456201_1
Short Term E-Tender No. 106 / W / ETC(B) /2019-20
Open Tender
Electrical Works
30 days
Bareilly
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,180
A/c No 10897666087 IFSC SBIN0000615 S.B.I. Bly
₹5,000
18 Sept 2020
27 Mar 2020
3 Apr 2020
27 Mar 2020
2 Apr 2020
27 Mar 2020
27 Mar 2020 - 2 Apr 2020
Amount
Replacement of old Equipments Installed in various 400KV & 220KV Bays alongwith other associated Works at 400KV Sub Station Bareilly, with all Cost of Men, Misc. Consumables, Crane, T&Ps, etc. Required for Satisfactory Completion of the Work, with all due Care of Safety & Precautions as per Technical Specifications and Direction of the Supervising Engineer as per Details below : (1) Dismantling of Following existing / old Equipments by due Opening of Jumpers, Cable Terminations, Cutting & Removal of Earthing etc. : (a) 400KV C.T. of ABB make installed in 400KV Bareilly - Unnao Ckt. - I Bay (1 Job per C.T.)
(b) 400KV SF6 C.B. of ABB make installed in 315MVA ICT - I Bay
(c) 220KV SF6 C.B. of ABB make installed in 220KV Pilibhit Feeder - II Bay
(d) 220KV L.A. installed in 315MVA ICT - I, 315MVA ICT - II, 220KV Dohna Feeder - I & 220KV C.B. Ganj Feeder - I Bays (1 Job per L.A.)
(2) Shifting of Following dismantled Equipments from Site to Stores at the Sub Station with due Stacking & Placing Properly & Safely : (a) 400KV C.T. of ABB make taken out from 400KV Bareilly - Unnao Ckt. - I Bay (1 Job per C.T.)
(b) 400KV SF6 C.B. of ABB make taken out from 315MVA ICT - I Bay
(c) 220KV SF6 C.B. of ABB make taken out from 220KV Pilibhit Feeder - II Bay
(d) 220KV L.A. taken out from 315MVA ICT - I, 315MVA ICT - II, 220KV Dohna Feeder - I & 220KV C.B. Ganj Feeder - I Bays (1 Job per L.A.)
(3) Shifting of Following Equipments from Stores to Erection Site : (a) 400KV C.T. of Mehru make for Installation in 400KV Bareilly - Unnao Ckt. - I Bay (1 Job per C.T.)
(b) 400KV SF6 C.B. of Siemens make for Installation in 315MVA ICT - I Bay
(c) 220KV SF6 C.B. of Siemens make for Installation in 220KV Pilibhit Feeder - II Bay
(d) 220KV L.A. of Lamco make for Installation in 315MVA ICT - I, 315MVA ICT - II, 220KV Dohna Feeder - I & 220KV C.B. Ganj Feeder - I Bays (1 Job per L.A.)
(4) Erection of Following Equipments with due Earthing, Cable Terminations, Jumpering etc. including Replacement of damaged Jumpers, Terminal Connectors, PG Clamps etc. as Required : (a) 400KV C.T. of Mehru make in 400KV Bareilly - Unnao Ckt. - I Bay (1 Job per C.T.)
(b) 400KV SF6 C.B. of Siemens make in 315MVA ICT - I Bay
(c) 220KV SF6 C.B. of Siemens make in 220KV Pilibhit Feeder - II Bay
(d) 220KV L.A. of Lamco make in 315MVA ICT - I, 315MVA ICT - II, 220KV Dohna Feeder - I & 220KV C.B. Ganj Feeder - I Bays (1 Job per L.A.)
LASHANI ENTERPRISES
M/s S.S. Refregeration
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid