Karnataka Power Transmission Corporation Limited
Conducting preliminary & detailed survey of 110kV line pertaining to the work of Establishing 2X 20 MVA, 110/11 kV Substation at Allur.K by constructing 110kV LILO line on DC towers using lynx conductor from proposed 110kV Yagapur-Nalwar-1 line for a distance of about 20km in Chittapur Taluk, Kalaburagi District
79905
KPTCL/2026-27/SE2383
Open
KPTCL SEE Transmission Works and Mantainance Circle Kalburgi
5 documents required · 4 mandatory · 1 optional
₹500
₹21,183
29 May 2026
29 May 2026
10 Jun 2026
2 Jun 2026
KARNATAKA POWER TRANSMISSION CORPORATION LTD.,
Transmission (Projects) KPTCL, Kalaburagi
Conducting preliminary & detailed survey of 110kV line pertaining to the work of Establishing 2X 20 MVA, 110/11 kV Substation at Allur.K by constructing 110kV LILO line on DC towers using lynx conductor from proposed 110kV Yagapur-Nalwar-1 line for a distance of about 20km in Chittapur Taluk, Kalaburagi District.
NOTE :- Fill in Blue Coloured Cells and upload Annexure:-A
Bid Enquiry: SEE/TPC/KLB/DCA/EE(O)/AEE-1/2026-27/110kV Allur.K Dtd: 25.05.2026
The tenderer shall upload all documents in support of the information mentioned hereunder. This information will not be incorporated in the Contract. Failure to upload the documents mentioned hereunder will be liable for rejection of the tender.
Details of the Tenderer
1 Name of the Tenderer :
2 Address of the Tenderer :
3 Name of the Proprietor / Contact Person :
4 Mobile No./Phone No. :
7 Class of Empanellement & Validity of Empanellement
7 Good and Service Tax Registration No. or Code
8 E.P.F. No. or Code :
11 No. of Survey Works carried out using Modern Survey Technique :
13 Rubber Stamp of the Firm / bidder
KARNATAKA POWER TRANSMISSION CORPORATION LTD.,
Transmission (Projects) KPTCL, Kalaburagi
Conducting preliminary & detailed survey of 110kV line pertaining to the work of Establishing 2X 20 MVA, 110/11 kV Substation at Allur.K by constructing 110kV LILO line on DC towers using lynx conductor from proposed 110kV Yagapur-Nalwar-1 line for a distance of about 20km in Chittapur Taluk, Kalaburagi District.
Bid Enquiry: SEE/TPC/KLB/DCA/EE(O)/AEE-1/2026-27/110kV Allur.K Dtd: 25.05.2026
NOTE :- Fill in Blue Coloured Cells and upload Annexure:-B
1) The tenderer shall upload all documents in support of the information mentioned hereunder. This information will not be incorporated in the Contract. Failure to upload the documents mentioned hereunder will be liable for rejection of the tender. 2) Details of surveying and geo-technical investigation works carried out for engineering projects as Prime Contractor (in the same name) to State / Central Government Departments/ Organizations, Public sector/ Companies during the five years.
Details of Experiences
Sl. No Name of the organization Name of the project Total Contract value (Rs. in lakhs) Contract period
Rubber Stamp of the Firm / bidder
KARNATAKA POWER TRANSMISSION CORPORATION LTD.,
Transmission (Projects) KPTCL, Kalaburagi
Conducting preliminary & detailed survey of 110kV line pertaining to the work of Establishing 2X 20 MVA, 110/11 kV Substation at Allur.K by constructing 110kV LILO line on DC towers using lynx conductor from proposed 110kV Yagapur-Nalwar-1 line for a distance of about 20km in Chittapur Taluk, Kalaburagi District.
Bid Enquiry: SEE/TPC/KLB/DCA/EE(O)/AEE-1/2026-27/110kV Allur.K Dtd: 25.05.2026
NOTE :- Fill in Blue Coloured Cells and upload Annexure:-C
1) The tenderer shall upload all documents in support of the information mentioned hereunder. This information will not be incorporated in the Contract. Failure to upload the documents mentioned hereunder will be liable for rejection of the tender. 2) Details of surveying and geo-technical investigation works carried out for engineering projects as Prime Contractor (in the same name) to State / Central Government Departments/ Organizations, Public sector/ Companies during the five years.
(A) Existing commitments and on-going works:
Sl. No. Name of the organization Name of the project Total Contract value (Rs. in lakhs) Balance Contract period
(B) Works for which Tenders already submitted:
Sl. No. Name of the organization Name of the project Amount put to tender (Rs. in lakhs) Contract period
Rubber Stamp of the Firm / bidder
KARNATAKA POWER TRANSMISSION CORPORATION LIMITED
Bid Enquiry: SEE/TPC/KLB/DCA/EE(O)/AEE-1/2026-27/110kV Allur.K Dtd: 25.05.2026
Conducting preliminary & detailed survey of 110kV line pertaining to the work of Establishing 2X 20 MVA, 110/11 kV Substation at Allur.K by constructing 110kV LILO line on DC towers using lynx conductor from proposed 110kV Yagapur-Nalwar-1 line for a distance of about 20km in Chittapur Taluk, Kalaburagi District.
NOTE :- Fill in Blue Coloured Cells and upload Annexure:-D
The tenderer shall upload all documents in support of the information mentioned hereunder. This information will not be incorporated in the Contract. Failure to upload the documents mentioned hereunder will be liable for rejection of the tender.
SLNo. Particulars Financial Year Total Financial TurnOver Amount (Rs.) Total Financial TurnOver only in all types of surveying / geo-technical investigation / consultancy works Amount (Rs.)
1 Annual Financial turn over for the years. Upload Certificate certified by Chartered Accountant Year(1) 2020-21
Place Seal of the Firm
Karnataka Power Transmission Corporation Limited
Estimate for conducting detailed survey for the work of Establishing 2X 20 MVA, 110/11 kV & 1x20MVA 110/33kV Substation at Sarasamba village by constructing 110kV DC line on DC towers using panther conductor from existing 110kV Rudrawadi S/S for a distance of about 10km in Aland Taluk ,Kalaburagi District. Approved in 2nd TCCM GESCOM Proceedings Date:03.07.2025
Sl. No. Particulars of work Unit Qty. Rate in Rs. Amount
1 Preliminary survey : Preliminary survey for identification of 3 alternative routes using google Images and Survey of India maps and finalization of most economical, optimum route showing the topographical and other features on either side and indicating final selected route alignment and digital modeling in undulated hilly terrain along the proposed route using contour data from topographical map and submission of preliminary survey reports for approval as detailed in technical specifications, in all types of terrain. The rates includes walk over/reconnaissance survey along the alignment of the line with collecting topographical details on either side upto 8Kms in case of 400kV line upto 5 Kms in case of 220kV line upto 3Kms in case of 110kV line and upto 2 Kms in case of 66kV lines. The output shall be in the form of digitized route alignment colour drawings with latest topographical and other details on either side of the alignment (both in hard and soft copies) and submission of preliminary survey reports in 3 set for approval of the final route alignment. (KPTCL SR 2023-24 pg no:153 sl.no:1) Per Km 10.000 3993.00 39930.00
2 Detailed Survey: Detailed survey along the approved route alignment by using Modern Survey equipments like DGPS/Total stations/Digital theodolites/GPS including profiling, tower spotting and optimization of locations by using computer aided techniques as detailed in the scope of work, using PLS-CADD software in all types of terrains and includes the following. •Drawing the route profile including geographical features like Nalas, Rivers, Gardens, P&T Lines, Railways crossing etc., • Leveling of the profile with reference to Survey of India bench marks (MSL). • Tower Schedule with optimization of tower location/tower spotting. • Line Schedule al ong the Right of Way. • Burgie details and prov jding GPS, Co-ordinates at each anchor points for identification of anchor locations including permanent marks, like poles, telephones lines, buildings etc., • Soil resistivity along the selected route with measurement at a distance not exceeding 2Kms. •Route marking along the approved route with GPS Co-ordinates for al I tower locations duly marking river/ road /power line /telecommunication/ railway line crossings. • Route marking along the approved route with GPS Co-ordinates for al I tower locations duly marking river/ road /power line /telecommunication/ railway line crossings. • Making 150mm dia bore holes for a depth not less than 3 mtrs or refusal strata at all tower I ocaticns in case of 400kV and 220kV transmission lines and at anchor points for 110kV and 66kV transmission lines and furnishing the bore log details for soil classification for tower foundations along with GPS Co-ordinates for each bore holes and back filling of bore holes on completion of work. Digitized contouring at undulated / hil ly tower locations for assessing the quantum of benching and revetment required. • Detailed land schedule along the Right of Way duly plotting the line corridor on the digitized Revenue vi llage maps to show details of land along the corridor with Sy. No. and computation of estimate of land compensation for line corridor and tower foot area as per the prevailing guidance value notified by GOK. • Preparation of schedules for processing for statutory clearances such as PTCC proposal (30 copies), Railway crossing proposal (10 sets per crossing), Forest proposal (10 sets) in required number of copies (both hard and soft copies) as per the requirement of respective departments. • Tree schedule containing the details like name of tree, girth size of tree, distance from center line of the alignment, approximate height of tree etc. • Submission of detailed consolidated final report for surveying work done appending all the approved draft reports including all relevant information collected during survey, calibration certificates of the instruments used for the work, photos / videos taken at site arid submitting soft copies of all documents and hard copy of reports in 6 sets. The detailed report shall contain following approved draft reports Preliminary Report/ Detailed Survey Report/ Soil Resistivity Report/ Soil classification report with I ocation wise/ Tree Schedule/ Line Schedule/ Land schedule/ Burgie details/ Digitized contours/ Digitized village map geo referenced and superimposed on the line corridor. (KPTCL SR 2023-24 pg no:153 & 154 sl.no:2) Per Km 10.000 16214.00 162140.00 `
3 Preparation of Revenue Survey sketch of the land along the line corridor for the purpose of computing compensation for corridor land and tower foot area land through licensed GOK approved surveyors and submission of survey sketch, extent of land falling in the line corridor, name of the land owner and RTC in the form of a schedule with due certification from Revenue authorities for the purpose of making payment of land compensation. ( Considering 3 survey sketch per km) 50.00 72
Rural Area (Per Survey sketch) No 30.00 1970.00 59100.00 59100
TOTAL Amount in Rs. 261170.00 25000.00
Area specific loading @ 5% on basic rates for kalyan karnataka 13058.50
Miscellaneous 1410.37
TOTAL Amount in Rs. ( Including 18% GST ) 325000.00 -25000.00 -125000.00
CERTIFICATE:- Certified that the estimate is prepared as per the Corporate order No: KPTCL/B9/85334/18-19 Bengaluru, dtd:20.02.2021 for conducting the detailed survey for the work of Establishing 2X 20 MVA, 110/11 kV & 1x20MVA 110/33kV Substation at Sarasamba village by constructing 110kV DC line on DC towers using panther conductor from existing 110kV Rudrawadi S/S for a distance of about 10km in Aland Taluk ,Kalaburagi District. Approved in 2nd TCCM GESCOM Proceedings Date:03.07.2025 100000.00 125830
Report: The Estimate amounting to Rs. 3,50,000 (Rupees three lakh fifty thousand only ) is prepared for conducting detailed survey for the work of Establishing 2X 20 MVA, 110/11 kV & 1x20MVA 110/33kV Substation at Sarasamba village by constructing 110kV DC line on DC towers using panther conductor from existing 110kV Rudrawadi S/S for a distance of about 10km in Aland Taluk ,Kalaburagi District. as per the Corporate order No: KPTCL/B9/85334/18-19 Bengaluru, dtd:20.02.2021. The scheme is approved in 2nd TCCM GESCOM Proceedings Date:03.07.2025.The estimate is prepared based on the approximate distance between the locations. The quantities may be varied while execution of the survey work. Hence the estimate may be sanctioned at an earliest. -325000.00 -125000.00
Stringing of second circuit on existing DC towers from 220/110 kV Kapnoor Sub-station to 110/33/11 kV Madiyal sub-station for a distance of about 42.98 kms along with construction of terminal bays at both ends and replacement of existing DC tower to MC tower between Loc no :135 to 152 for a distance of about 5.5kms in Kalaburagi District
Check survey to be conducted during construction stage: Conducting detailed check survey along the approved route duly following the route alignment, GPS Co-ordinates, submission of detailed line schedule, tower schedule, land schedule and comparing the same with respect to detailed survey report, bringing out the differences if any. Submission of contour maps for undulated / hilly tov'er. The work also includes marking corridor width in the field and computing the quantum of beaching and revetment, preparation of detailed land schedule at ong the corridor on the digitized Reven ue vi1lage maps indicating the Sy. Nos. falling within the corridor for the purpose of estimation of the land compensation, submission of detailed consolidated hatd copy of reports of check survey in 6 sets along with soft copy for approval in all types of terrain per Km. Per Km
Karnataka Power Transmission Corporation Limited
Estimate for Conducting preliminary & detailed survey for Establishing 2X 20 MVA, 110/11 kV & 1x20MVA 110/33kV Substation at Sarasamba village by constructing 110kV DC line on DC towers using panther conductor from existing 110kV Rudrawadi S/S for a distance of about 10km in Aland Taluk ,Kalaburagi District. Approved in 2nd TCCM GESCOM Proceedings Date:03.07.2025
Sl. No. Particulars of work Unit Qty. Rate in Rs. Amount
1 Preliminary survey : Preliminary survey for identification of 3 alternative routes using google Images and Survey of India maps and finalization of most economical, optimum route showing the topographical and other features on either side and indicating final selected route alignment and digital modeling in undulated hilly terrain along the proposed route using contour data from topographical map and submission of preliminary survey reports for approval as detailed in technical specifications, in all types of terrain. Per Km 21.00 4192.65 88045.65 1287.86 2904.79 61000.60
NOTE :- The rates include walk over/reconnaissance survey along the alignment of the line with collecting topographical details on either side upto 8 km in case of 400 kV Line upto 5 km in case of 220 kV Line upto 3 km in case of 110 kV Line, upto 2 km in case of 66 kV Lines and upto 1 km in case of 33 kV Lines. The output shall be in the form of digitized route alignment colour drawings with latest topographical and other details on either side of the alignment (both in hard and soft copies) and submission of preliminary survey reports in 3 set for approval of the final route alignment. Note : Minimum 1 km length shall be considered for payment. 1193.53 2999.12 62981.56 3993 200 4192.65 754.68 4947.33 103893.867 31944 4192.6500
2 Detailed Survey: Detailed survey along the approved route alignment by using Modern Survey equipments like DGPS/Total stations/Digital theodolites/GPS including profiling, tower spotting and optimization of locations by using computer aided techniques as detailed in the scope of work, using PLS-CADD software in all types of terrains and includes the following. • Drawing the route profile including geographical features like Nalas, Rivers, Gardens, P&T Lines,Railways crossing etc., • Leveling of the profile with reference to Survey of India bench marks (MSL). • Tower Schedule with optimization of tower location/tower spotting. • Line Schedule al ong the Right of Way. • Burgie details and prov jding GPS, Co-ordinates at each anchor points for identification of anchor locations including permanent marks, like poles, telephones lines, buildings etc., • Soil resistivity along the selected route with measurement at a distance not exceeding 2Kms. •Route marking along the approved route with GPS Co-ordinates for al I tower locations duly marking river/ road /power line /telecommunication/ railway line crossings. • Route marking along the approved route with GPS Co-ordinates for al I tower locations duly marking river/ road /power line /telecommunication/ railway line crossings. • Making 150mm dia bore holes for a depth not less than 3 mtrs or refusal strata at all tower I ocaticns in case of 400kV and 220kV transmission lines and at anchor points for 110kV and 66kV transmission lines and furnishing the bore log details for soil classification for tower foundations along with GPS Co-ordinates for each bore holes and back filling of bore holes on completion of work. • Digitized contouring at undulated / hil ly tower locations for assessing the quantum of benching and revetment required. • Detailed land schedule along the Right of Way duly plotting the line corridor on the digitized Revenue vi llage maps to show details of land along the corridor with Sy. No. and computation of estimate of land compensation for line corridor and tower foot area as per the prevailing guidance value notified by GOK. • Preparation of schedules for processing for statutory clearances such as PTCC proposal (30 copies), Railway crossing proposal (10 sets per crossing), Forest proposal (10 sets) in required number of copies (both hard and soft copies) as per the requirement of respective departments. • Tree schedule containing the details like name of tree, girth size of tree, distance from center line of the alignment, approximate height of tree etc. • Submission of detailed consolidated final report for surveying work done appending all the approved draft reports including all relevant information collected during survey, calibration certificates of the instruments used for the work, photos / videos taken at site arid submitting soft copies of all documents and hard copy of reports in 6 sets. The detailed report shall contain following approved draft reports Preliminary Report/ Detailed Survey Report/ Soil Resistivity Report/ Soil classification report with I ocation wise/ Tree Schedule/ Line Schedule/ Land schedule/ Burgie details/ Digitized contours/ Digitized village map geo referenced and superimposed on the line corridor. Note : Minimum 1 km length shall be considered for payment. Per Km 21.000 17024.70 357518.70 ` 0.00 0.00 0
3 Preparation of Revenue Survey sketch of the land along the line corridor for the purpose of computing compensation for corridor land and tower foot area land through licensed GOK approved surveyors and submission of survey sketch, extent of land falling in the line corridor, name of the land owner and RTC in the form of a schedule with due certification from Revenue authorities for the purpose of making payment of land compensation. [ Maximum span is 320Mtr & average spam is 280Mtr is considered for length of 21 Kms i.e 21000/280=75 No's for tower foot locations and 75 No's for line corridor locations ]. Note : As per actual Revenue Survey sketch,payment has to be made. 1479.66 93218.39 0.00 0.00 0
TOTAL Amount in Rs.(Inclusive of Area Specific Loading on Basic Rates-Kalyana Karnataka-5% and exclusive of 18% GST) 575879.85 400045.37 #REF! 1109 496548
CERTIFICATE:- Certified that the estimate is prepared as per the ENERGY DEPARTMENT COMMON SCHEDULE OF RATES FOR KPTCL, ESCOMs & PWD Electrical 2023 - 2024 Volume – 6 for conducting the detailed survey for the work of Re-construction of existing 110 kV Moratagi-Afzalpur SC line by new 110kV DC line with Lynx conductor for a distance of about 21Kms in Kalaburagi District. Approved in 90th TCCM Proceedings held on Date:12.09.2023 and procedding issued vide letter : CEE(P&C)/SEE(Plg)/EEE/AE/F-30603/2023-24/TCCM/2216-30 Dtd:11.12.2023 -188879.85
Report: The estimate amounting to Rs. 8,00,000/- (Rupees Eight lakhs only ) is prepared for conducting detailed survey for the work of Re-construction of existing 110 kV Moratagi-Afzalpur SC line by new 110kV DC line with Lynx conductor for a distance of about 21Kms in Kalaburagi District as per the ENERGY DEPARTMENT COMMON SCHEDULE OF RATES FOR KPTCL, ESCOMs & PWD Electrical 2023 - 2024 Volume – 6. The scheme is approved in 90th TCCM Proceedings held on Date:12.09.2023 and procedding issued vide letter : CEE(P&C)/SEE(Plg)/EEE/AE/F-30603/2023-24/TCCM/2216-30 Dtd:11.12.2023. The estimate is prepared based on the approximate distance between the locations. The quantities may vary while execution of the survey work. Hence the estimate may be sanctioned at an earliest.
Karnataka Power Transmission Corporation Limited
Estimate for Conducting preliminary & detailed survey of 110kV line pertaining to the work of Establishing 2X 20 MVA, 110/11 kV Substation at Allur.K by constructing 110kV LILO line on DC towers using lynx conductor from proposed 110kV Yagapur-Nalwar-1 line for a distance of about 20km in Chittapur Taluk, Kalaburagi District. Approved in 3rd TCCM GESCOM Proceedings Date: 10.02.2026
Sl. No. Particulars of work Unit Qty. Rate in Rs. Amount
1 Preliminary survey : Preliminary survey for identification of 3 alternative routes using google Images and Survey of India maps and finalization of most economical, optimum route showing the topographical and other features on either side and indicating final selected route alignment and digital modeling in undulated hilly terrain along the proposed route using contour data from topographical map and submission of preliminary survey reports for approval as detailed in technical specifications, in all types of terrain. Per Km 20.00 0.00 0.00 0.00
NOTE :- The rates include walk over/reconnaissance survey along the alignment of the line with collecting topographical details on either side upto 8 km in case of 400 kV Line upto 5 km in case of 220 kV Line upto 3 km in case of 110 kV Line, upto 2 km in case of 66 kV Lines and upto 1 km in case of 33 kV Lines. The output shall be in the form of digitized route alignment colour drawings with latest topographical and other details on either side of the alignment (both in hard and soft copies) and submission of preliminary survey reports in 3 set for approval of the final route alignment. Note : Minimum 1 km length shall be considered for payment. 3993.00 200 4192.65 754.68 4947.33 98946.54 1379.92 3567.41 71348.16 0.00 0.00 0.00 754.68 4947.33 98946.54 31944 4192.6500
2 Detailed Survey: Detailed survey along the approved route alignment by using Modern Survey equipments like DGPS/Total stations/Digital theodolites/GPS including profiling, tower spotting and optimization of locations by using computer aided techniques as detailed in the scope of work, using PLS-CADD software in all types of terrains and includes the following. • Drawing the route profile including geographical features like Nalas, Rivers, Gardens, P&T Lines,Railways crossing etc., • Leveling of the profile with reference to Survey of India bench marks (MSL). • Tower Schedule with optimization of tower location/tower spotting. • Line Schedule al ong the Right of Way. • Burgie details and prov jding GPS, Co-ordinates at each anchor points for identification of anchor locations including permanent marks, like poles, telephones lines, buildings etc., • Soil resistivity along the selected route with measurement at a distance not exceeding 2Kms. •Route marking along the approved route with GPS Co-ordinates for al I tower locations duly marking river/ road /power line /telecommunication/ railway line crossings. • Route marking along the approved route with GPS Co-ordinates for al I tower locations duly marking river/ road /power line /telecommunication/ railway line crossings. • Making 150mm dia bore holes for a depth not less than 3 mtrs or refusal strata at all tower I ocaticns in case of 400kV and 220kV transmission lines and at anchor points for 110kV and 66kV transmission lines and furnishing the bore log details for soil classification for tower foundations along with GPS Co-ordinates for each bore holes and back filling of bore holes on completion of work. • Digitized contouring at undulated / hil ly tower locations for assessing the quantum of benching and revetment required. • Detailed land schedule along the Right of Way duly plotting the line corridor on the digitized Revenue vi llage maps to show details of land along the corridor with Sy. No. and computation of estimate of land compensation for line corridor and tower foot area as per the prevailing guidance value notified by GOK. • Preparation of schedules for processing for statutory clearances such as PTCC proposal (30 copies), Railway crossing proposal (10 sets per crossing), Forest proposal (10 sets) in required number of copies (both hard and soft copies) as per the requirement of respective departments. • Tree schedule containing the details like name of tree, girth size of tree, distance from center line of the alignment, approximate height of tree etc. • Submission of detailed consolidated final report for surveying work done appending all the approved draft reports including all relevant information collected during survey, calibration certificates of the instruments used for the work, photos / videos taken at site arid submitting soft copies of all documents and hard copy of reports in 6 sets. The detailed report shall contain following approved draft reports Preliminary Report/ Detailed Survey Report/ Soil Resistivity Report/ Soil classification report with I ocation wise/ Tree Schedule/ Line Schedule/ Land schedule/ Burgie details/ Digitized contours/ Digitized village map geo referenced and superimposed on the line corridor. Note : Minimum 1 km length shall be considered for payment. Per Km 20.000 ` 0.00 0.00 0
3 Preparation of Revenue Survey sketch of the land along the line corridor for the purpose of computing compensation for corridor land and tower foot area land through licensed GOK approved surveyors and submission of survey sketch, extent of land falling in the line corridor, name of the land owner and RTC in the form of a schedule with due certification from Revenue authorities for the purpose of making payment of land compensation. [ Maximum span is 320Mtr & average spam is 280Mtr is considered for length of 21 Kms i.e 21000/280=75 No's for tower foot locations and 75 No's for line corridor locations ]. Note : As per actual Revenue Survey sketch,payment has to be made. 0.00 0.00 0.00 0.00 0
TOTAL Amount in Rs.(Inclusive of Area Specific Loading on Basic Rates-Kalyana Karnataka-5% and exclusive of 18% GST) 0.00 0.00 1109 847327.32 610989.01 0.00 635964
CERTIFICATE:- Certified that the estimate is prepared as per the ENERGY DEPARTMENT COMMON SCHEDULE OF RATES FOR KPTCL, ESCOMs & PWD Electrical 2023 - 2024 Volume – 6 for conducting the detailed survey for the work of Re-construction of existing 110 kV Moratagi-Afzalpur SC line by new 110kV DC line with Lynx conductor for a distance of about 21Kms in Kalaburagi District. Approved in 90th TCCM Proceedings held on Date:12.09.2023 and procedding issued vide letter : CEE(P&C)/SEE(Plg)/EEE/AE/F-30603/2023-24/TCCM/2216-30 Dtd:11.12.2023 387000
Report: The estimate amounting to Rs. 8,00,000/- (Rupees Eight lakhs only ) is prepared for conducting detailed survey for the work of Re-construction of existing 110 kV Moratagi-Afzalpur SC line by new 110kV DC line with Lynx conductor for a distance of about 21Kms in Kalaburagi District as per the ENERGY DEPARTMENT COMMON SCHEDULE OF RATES FOR KPTCL, ESCOMs & PWD Electrical 2023 - 2024 Volume – 6. The scheme is approved in 90th TCCM Proceedings held on Date:12.09.2023 and procedding issued vide letter : CEE(P&C)/SEE(Plg)/EEE/AE/F-30603/2023-24/TCCM/2216-30 Dtd:11.12.2023. The estimate is prepared based on the approximate distance between the locations. The quantities may vary while execution of the survey work. Hence the estimate may be sanctioned at an earliest.
TOTAL Amount in Rs.(Inclusive of Area Specific Loading on Basic Rates-Kalyana Karnataka-5% and inclusive of 18% GST) 0.00
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
annexures 110kV Allur K.xlsx
Others - Annexures • 0.03 MB
110kV TECHNICAL SPECIFICATIONS.pdf
Others - Technical Specifications • 0.15 MB
letter of undertaking.doc
Others - Undertaking • 0.16 MB
surveying QR tender.docx
Tender Document • 0.21 MB
nit1.docx
Others - NIT • 0.04 MB
Detailed Estimate for reference purpose.xlsx
Others - Reference purpose estimate copy • 0.07 MB
Download all tender documents and submit your bid