| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹12.3 LAccepted-AOC | ₹12.3 L | L1 | Accepted-AOC Agreement executed on 09.03.2026 |
| Sl No | Description | Qty | Unit | govind L1 |
|---|---|---|---|---|
| 1.00Re-Construction of Retaining Wall in Puthan Thodu | ||||
| 1.00 | OD1395/2025-2026 60.7.3 DISMANTLING DR - Dismanling , clearing away and carefully stacking materials useful for reuse for any thickness of walls in DR masonry including disposal of debris within a distance of 150m. | 155.07 | cum | 700 ₹1.1 L |
| 1.00 | 2.6.1 Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge.All kinds of soil | 48.3 | cum | 200 ₹9,660 |
| 1.00 | OD1396/2025-2026 60.7.1 DRY RUBBLE MASONRY Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site | 149.75 | cum | 3,993 ₹6.0 L |
| 1.00 | OD1394/2025-2026 60.7.8 DR with Departmental. Stone - DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course using departmental rubble including packing to compactness to lines and levels, labour charges etc. complete as per direction of Departmental officers at site | 93.04 | cum | 1,715 ₹1.6 L |
| 1.00 | 7.1.1 Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse sand) | 34.69 | cum | 8,200 ₹2.8 L |
| 1.01 | 4.3.1 Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns | 24.75 | sqm | 386 ₹9,553.50 |
| 1.01 | 4.1.3 Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) | 6.1 | cum | 9,235 ₹56,333.50 |
Tender Value
₹12.4 L
EMD Value
₹31,072
Closing Date
13 Jan 2026, 5:00 pmClosed
District Soil Conservation Officer Alappuzha
District Soil Conservation Office Alappuzha 688001
Retaining wall 2 m Ht 115 RM
2025_ALPY_820066_3
DSCO/ALP/231/2024-C4
Open Tender
Civil Works - Others
365 days
Arookutty and Panavally GP
Please refer Tender documents.
10 documents required · 10 mandatory
₹2,760
Yes
₹31,072
Yes
9 Mar 2026
3 Jan 2026
15 Jan 2026
3 Jan 2026
13 Jan 2026
3 Jan 2026
Amount
Re-Construction of Retaining Wall in Puthan Thodu
OD1395/2025-2026 60.7.3 DISMANTLING DR - Dismanling , clearing away and carefully stacking materials useful for reuse for any thickness of walls in DR masonry including disposal of debris within a distance of 150m.
2.6.1 Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge.All kinds of soil
OD1396/2025-2026 60.7.1 DRY RUBBLE MASONRY Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
OD1394/2025-2026 60.7.8 DR with Departmental. Stone - DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course using departmental rubble including packing to compactness to lines and levels, labour charges etc. complete as per direction of Departmental officers at site
7.1.1 Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse sand)
4.3.1 Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns
4.1.3 Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources)
stage.html
html • 0.03 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1384025.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.11 MB
Retendernotice3.pdf
Tender Documents • 0.10 MB
new.pdf
Tender Documents • 1.22 MB
Dwg.pdf
Tender Documents • 0.54 MB
BOQ_1384025.xls
BOQ • 0.37 MB
Download all tender documents and submit your bid