| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹26.5 LAccepted-AOC | ₹26.5 L | L1 | Accepted-AOC Being first lowest |
| 2 | L2₹30.2 L+₹3.7 L (14.0%)Rejected-AOC | ₹30.2 L+₹3.7 L (14.0%) | L2 | Rejected-AOC being second lowest |
Tender Value
₹27.6 L
EMD Value
₹50,000
Closing Date
8 Jan 2025, 4:00 pmClosed
The Managing Director
Kerala State Warehousing Corporation, Head Office Ernakulam, P.B.No.1727, Warehousing Corporation Road, Kochi-682016
Construction of new pump room,ground water tank and overhead tank for the fire fighting system at state warehouse Muthalamada in Palakkad district under NABARD WIF Scheme
2024_KSWC_713828_1
No. KSWC/Constn /SW/FF/Muthalamada/2024-25
Open Tender
Civil Works - Buildings
Item Rate
60 days
State Warehouse Muthalamada
Please refer Tender documents
9 documents required · 9 mandatory
₹2,950
₹50,000
Yes
21 Feb 2025
13 Dec 2024
10 Jan 2025
13 Dec 2024
8 Jan 2025
13 Dec 2024
13 Dec 2024 - 8 Jan 2025
Amount
Ground water Tank (6.40x4.00x3.50m) Clearing grass and removal of the rubbish up to a distance of 50 m outside the periphery of the area cleared.
Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 ( 1 cement : 3 coarse sand : 6 graded stone aggregate 40 mm nominal size)
Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams,girders, bressumers and cantilevers with water proofply 12 mm thick.
Centering and shuttering including strutting, etc. and removal of form for:Columns, Pillars, Piers,Abutments, Posts and Struts
Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams,girders bressumers and cantilevers
Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs,landings, balconies and access platform
Centering and shuttering including strutting, etc. and removal of form for:Edges of slabs and breaks in floors and wallsUnder 20 cm wide
Providing and laying in position machine batched and machine mixed design mix M-25 grade cementconcrete for reinforced cement concrete work, using cement content as per approved design mix,including pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishing and reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate,retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer - in-charge. Note:- Cement content considered in this item is @ 330 kg/ cum. Excess or lesscement used as per design mix is payable or recoverable separately.All work upto plinth level
Providing and laying in position machine batched and machine mixed design mix M-25 grade cement concrete for reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishing and reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate,retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer - in-charge. Note:- Cement content considered in this item is @ 330 kg/ cum. Excess or less cement used as per design mix is payable or recoverable separately.All work above plinth level upto floor V level
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete above plinth level.Thermo - Mechanically Treated bars of grade Fe-500D or more
6 mm cement plaster of mix:1:3 ( 1 cement : 3 fine sand) including cost of all materials, conveyance, labour charge, scaffolding etc complete as required.)
12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand) including cost of all materials, conveyance, labour charge, scaffolding etc complete as required.
12 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1 cement : 3 fine sand)
Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers
Applying priming coats with primer of approved brand and manufacture, having low VOC ( Volatile Organic Compound) content.With water thinnable cement primer on walls surface having VOC content less than 50 grams / litre
Wall painting with acrylic emulsion paint, having VOC (Volatile Organic Compound) content less than 50 grams/ litre, of approved brand and manufacture including applying additional coats wherever required, to achieve even shade and colour.Two coats
Over Head tank (Inside size - 4.00 x 2.10 x 1.65) Centering and shuttering including strutting, etc. and removal of form for:Columns, Pillars, Piers, Abutments, Posts and Struts up to the height of 15 M.
Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams,girders bressumers and cantilevers up to the height of 15 M.
Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses up to the height of 15M
Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform up to the height of 15 M.
Centering and shuttering including strutting, etc. and removal of form for:Edges of slabs and breaks in floors and wallsUnder 20 cm wide upto the height of 15M.
Providing and laying in position machine batched and machine mixed design mix M-25 grade cementconcrete for reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishing and reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate,retard setting of concrete, improve workability without impairing strength and durability as per direction ofEngineer - in-charge. Note:- Cement content considered in this item is @ 330 kg/ cum. Excess or lesscement used as per design mix is payable or recoverable separately.All work above plinth level upto floorV level (15m)
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete above plinth level.Thermo - Mechanically Treated bars of grade Fe-500D or more
6 mm cement plaster of mix:1:3 ( 1 cement : 3 fine sand)including cost of all materials, conveyance, labour charge, scaffolding etc complete as required.
12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand) including cost of all materials, conveyance, labour charge, scaffolding etc complete as required.
12 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1 cement : 3 fine sand)
Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers.
Applying priming coats with primer of approved brand and manufacture, having low VOC ( VolatileOrganic Compound) content.With water thinnable cement primer on walls surface having VOC contentless than 50 grams / litre
Wall painting with acrylic emulsion paint, having VOC (Volatile Organic Compound) content less than 50grams/ litre, of approved brand and manufacture including applying additional coats wherever required, toachieve even shade and colour.Two coats
PUMP room Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
Solid block masonry using pre cast solid blocks (Factory made) of size 40x20x20cm or nearest available size confirming to IS 2185 part I of 1979 for super structure up to floor two level thickness 20cm and above in: CM 1:6 ( 1 cement: 6 coarse sand) etc complete .
Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers.All works including cost and conveyance of all materials,labour charges etc. complete .
Providing and laying in position machine batched and machine mixed design mix M-25 grade cementconcrete for reinforced cement concrete work, using cement content as per approved design mix,including pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishingand reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate,retard setting of concrete, improve workability without impairing strength and durability as per direction ofEngineer - in-charge. Note:- Cement content considered in this item is @ 330 kg/ cum. Excess or lesscement used as per design mix is payable or recoverable separately.All work above plinth level upto floorV level .
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position andbinding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more.
12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand) including cost of all materials, conveyance, labour charge, scaffolding etc complete as required.
Applying priming coats with primer of approved brand and manufacture, having low VOC ( Volatile Organic Compound) content.With water thinnable cement primer on walls surface having VOC content less than 50 grams / litre.
Wall painting with acrylic emulsion paint, having VOC (Volatile Organic Compound) content less than 50grams/ litre, of approved brand and manufacture including applying additional coats wherever required, to achieve even shade and colour.Two coats
Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete.
Painting with synthetic enamel paint of approved brand and manufacture to give an even shade:Two or more coats on new work, painting over the existing structure after preparing the surface by using wirebrush or emery paper,all works including cost and conveyance of all materials,labour charges, scaffolding etc. complete as required.
Steel work in built up tubular ( round, square or rectangular hollow tubes etc.-minimum thickness 2.00 mm) trusses etc., including cutting, hoisting, fixing position and applying a priming coat of approved steel primer after preparing the surface by using wirebrush or emery paper, including welding and bolted with special shaped washers etc. complete.Hot finished welded type tubes.
Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, includingcutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete.
Finishing with Epoxy paint (two or more coats) at all locations prepared and applied as per manufacturer's specifications including appropriate priming coat, preparation of surface, etc. complete.On steel work
Lettering with black Japan pint of approved brand and manufactured
COCHIN SURAKSHA INFRASTRUCTURE PRIVATE LIMITED (BID ID -2032157)
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .