| Sl No | Description | Qty | Unit | Dinu Electricals L1 | National Electric Co L2 | Universal ELectricals L3 |
|---|---|---|---|---|---|---|
| 1.00 | Civil works for panel movement. The scope of work includes making necessary arrangements for transportation of individual panels like removal of entrance door/windows, cutting wall/concrete beam of central substation building, constructing new brick wall after completion of panel movements, plastering, fixing new doors/windows and painting. All items required for the work shall be arranged by the contractor. All waste materials shall be transported to scrap yard or elsewhere in the complex as directed by Engineer-in charge. | 1 | LS | 75,000 ₹75,000 | 45,000 ₹45,000 Lowest | 45,550 ₹45,550 |
| 2.00 | Dismantling and transportation of existing 3.3kV panel. The scope of work includes rack out bulk oil circuit breakers from panels, properly marking and disconnecting power cables/ control cables/earth cables/motor heater cables of panels, disconnecting inter panel power/earth bus bars, disconnecting inter panel control wirings, removing inter panel mechanical connections, removing foundation bolts from MS channels/MS plate/concrete floor, removing foundation channels if necessary, transporting the panels/foundation channels/foundation plate and circuit breakers from first floor of Central substation to a temporary location as directed by the Engineer-in charge. Contractor shall arrange necessary tarpaulin sheets to protect the panel from dust and rain till completion of removal of critical items like bus bars, current transformers, switches, indications lamps, relays etc. All removed items shall be handed over to Technician in charge and panels shall be transported to scrap yard. The crane, lorry, lifting tackles, etc., required for handling and transportation of switchboard panels from work site to scrap yard shall be arranged by the contractor. Approximate dimensions of existing panel is Length-18490mm, Width-1670mm, Height-2480mm. | 28 | NO | 4,000 ₹1,12,000 Lowest | 11,000 ₹3,08,000 | 8,400 ₹2,35,200 |
| 3.00 | Transportation and erection of new 3.3kV panels. The scope of work includes loading/unloading, transportation of new 3.3kV panels from stores to Central Substation building first floor without causing any damage to the panels, handling at site, unpacking, checking of components of supply equipment/items as per BOM, listing and handing over of list of short supplied items to site-in- charge, concrete cutting/chipping of floor for cable entry/fixing foundation channels, fixing new 100x50x5mm MS C-channels as per the GA drawings submitted by the panel manufacturer, drilling foundation bolt holes in the MS channels/ MS plate/ concrete, levelling the foundation floor for placing the new panels, grouting, fixing the panels on the foundation MS channels/ MS plate/ concrete, aligning all panels properly, tightening the foundation bolts, inter-connecting all panels, inter-linking power and earth bus bars, checking positioning/alignment and tightness of bus bars and providing cable supports using MS angle of minimum size 65x65x5mm. Contractor shall supply the MS C-channels of size 100x50x5mm and MS angle of minimum size 65x65x5mm required for successful completion of the work. The MS C-channels and angles shall be painted with two coats of anti-corrosive epoxy paint (grey colour) over two coats of suitable primer.
Products of M/s. Asian Paints, Berger Paints, Kansai Nerolac Paints & Shalimar Paints alone will be accepted. Product literature of the manufacturer shall be furnished to the Engineer-in charge and the product to be used shall be got approved before starting the work. The epoxy primer shall be Zinc Phosphate primer and thinner used for the work shall conform to the brand specified by the manufacturer in the product literature. Bolt, nut washers, Epoxy primer, Epoxy paint, Sand, cement, brick, etc. for successful completion of the work shall be arranged by the contractor. The crane, lorry, lifting tackles, etc. required for handling and transportation of switchboard panels from CD Stores to work site shall be arranged by the contractor. | 36 | NO | 11,800 ₹4,24,800 Lowest | 24,650 ₹8,87,400 | 25,000 ₹9,00,000 |
| 4.00 | Laying/Re-routing of existing 3.3 KV, armoured cables. The scope of work includes Laying/Re-routing of existing 3.3 KV, armoured cables of size up to 3Cx400 sq.mm in a single panel through cable trenches, risers, walls and clamping/tying the cables at a regular interval of 500 mm. All items required for the work shall be arranged by the contractor. Number of cables in a single panel board is attached as Annexure-1. | 24 | NO | 3,000 ₹72,000 | 2,800 ₹67,200 | 2,115 ₹50,760 Lowest |
| 5.00 | Laying/Re-routing of existing LT, armoured cables. The scope of work includes Laying/Re-routing of existing LT, armoured cables of size up to 19 core, 2.5/4 Sq.mm in a single panel through cable trenches, risers, walls and clamping/tying the cable at a regular interval of 500 mm. All items required for the work shall be arranged by the contractor. Number of cables in a single panel board is attached as Annexure-1. | 27 | NO | 2,500 ₹67,500 | 700 ₹18,900 Lowest | 1,830 ₹49,410 |
| 6.00 | Laying/Re-routing of existing armoured earth cables. The scope of work includes Laying/Re-routing of existing armoured earth cables of size up to 1Cx600 Sq.mm through cable trenches, risers, walls and clamping/tying the cable at a regular interval of 500 mm. All items required for the work shall be arranged by the contractor. | 300 | M | 150 ₹45,000 | 100 ₹30,000 Lowest | 145 ₹43,500 |
| 7.00 | Laying new 3.3 KV, 3Cx400 sq.mm armoured cable. The scope of work includes loading/unloading, transporting new 3.3 KV, 3Cx400 sq.mm armoured cables from stores/cable yard to Central Substation, handling at site, laying through cable trenches, risers, walls and clamping/tying the cable at a regular interval of 500 mm. Cables shall be supplied by FACT. All other items required for the work shall be arranged by the contractor. | 300 | M | 130 ₹39,000 Lowest | 200 ₹60,000 | 380 ₹1,14,000 |
| 8.00 | Laying new 3.3 KV, 3Cx240 sq. mm armoured cable. The scope of work includes loading/unloading, transporting new 3.3 KV, 3Cx240 sq.mm armoured cables from stores/cable yard to Central Substation, handling at site, laying through cable trenches, risers, walls and clamping/tying the cable at regular interval of 500 mm. Cables shall be supplied by FACT. All other items required for the work shall be arranged by the contractor. | 300 | M | 115 ₹34,500 Lowest | 170 ₹51,000 | 360 ₹1,08,000 |
| 9.00 | Laying new armoured, LT cables. The scope of work includes loading/unloading, transporting armoured, LT cables of size up to 19 core, 2.5/4 Sq.mm from stores/cable yard to Central Substation, handling at site, laying through cable trenches, risers, walls and clamping/tying the cable at a regular interval of 500 mm. Cables shall be supplied by FACT. All other items required for the work shall be arranged by the contractor. | 500 | M | 75 ₹37,500 | 56 ₹28,000 Lowest | 200 ₹1,00,000 |
| 10.00 | Laying new earth cables. The scope of work includes loading/unloading, transporting armoured, earth cables of size up to 1Cx600 Sq.mm from stores/cable yard to Central Substation, handling at site, laying through cable trenches, risers, walls and clamping/tying the cable at a regular interval of 500 mm. Cables shall be supplied by FACT. All other items required for the work shall be arranged by the contractor. | 500 | M | 130 ₹65,000 | 70 ₹35,000 Lowest | 120 ₹60,000 |
Tender Value
Refer Docs
EMD Value
₹1 L
Closing Date
9 Jan 2024, 11:00 amClosed
AGM(Mat)-C
Corporate Materials PD Administration Building, FACT-Udyogamandal Kochi, Kerala.
Erection and Commissioning of 3.3 kV Switchboard at Central Substation of FACT-CD, Ambalamedu, as per tender documents.
2023_FACT_785565_1
04026/2023-2024/E28673
Open Tender
Miscellaneous Works
Item Rate
25 days
FACT Cochin Division, Ambalamedu
Please refer tender documents.
7 documents required · 7 mandatory
₹0
₹1 L
Yes
8 Feb 2024
15 Dec 2023
9 Jan 2024
15 Dec 2023
9 Jan 2024
15 Dec 2023
Amount
Civil works for panel movement. The scope of work includes making necessary arrangements for transportation of individual panels like removal of entrance door/windows, cutting wall/concrete beam of central substation building, constructing new brick wall after completion of panel movements, plastering, fixing new doors/windows and painting. All items required for the work shall be arranged by the contractor. All waste materials shall be transported to scrap yard or elsewhere in the complex as directed by Engineer-in charge.
Dismantling and transportation of existing 3.3kV panel. The scope of work includes rack out bulk oil circuit breakers from panels, properly marking and disconnecting power cables/ control cables/earth cables/motor heater cables of panels, disconnecting inter panel power/earth bus bars, disconnecting inter panel control wirings, removing inter panel mechanical connections, removing foundation bolts from MS channels/MS plate/concrete floor, removing foundation channels if necessary, transporting the panels/foundation channels/foundation plate and circuit breakers from first floor of Central substation to a temporary location as directed by the Engineer-in charge. Contractor shall arrange necessary tarpaulin sheets to protect the panel from dust and rain till completion of removal of critical items like bus bars, current transformers, switches, indications lamps, relays etc. All removed items shall be handed over to Technician in charge and panels shall be transported to scrap yard. The crane, lorry, lifting tackles, etc., required for handling and transportation of switchboard panels from work site to scrap yard shall be arranged by the contractor. Approximate dimensions of existing panel is Length-18490mm, Width-1670mm, Height-2480mm.
Transportation and erection of new 3.3kV panels. The scope of work includes loading/unloading, transportation of new 3.3kV panels from stores to Central Substation building first floor without causing any damage to the panels, handling at site, unpacking, checking of components of supply equipment/items as per BOM, listing and handing over of list of short supplied items to site-in- charge, concrete cutting/chipping of floor for cable entry/fixing foundation channels, fixing new 100x50x5mm MS C-channels as per the GA drawings submitted by the panel manufacturer, drilling foundation bolt holes in the MS channels/ MS plate/ concrete, levelling the foundation floor for placing the new panels, grouting, fixing the panels on the foundation MS channels/ MS plate/ concrete, aligning all panels properly, tightening the foundation bolts, inter-connecting all panels, inter-linking power and earth bus bars, checking positioning/alignment and tightness of bus bars and providing cable supports using MS angle of minimum size 65x65x5mm. Contractor shall supply the MS C-channels of size 100x50x5mm and MS angle of minimum size 65x65x5mm required for successful completion of the work. The MS C-channels and angles shall be painted with two coats of anti-corrosive epoxy paint (grey colour) over two coats of suitable primer. Products of M/s. Asian Paints, Berger Paints, Kansai Nerolac Paints & Shalimar Paints alone will be accepted. Product literature of the manufacturer shall be furnished to the Engineer-in charge and the product to be used shall be got approved before starting the work. The epoxy primer shall be Zinc Phosphate primer and thinner used for the work shall conform to the brand specified by the manufacturer in the product literature. Bolt, nut washers, Epoxy primer, Epoxy paint, Sand, cement, brick, etc. for successful completion of the work shall be arranged by the contractor. The crane, lorry, lifting tackles, etc. required for handling and transportation of switchboard panels from CD Stores to work site shall be arranged by the contractor.
Laying/Re-routing of existing 3.3 KV, armoured cables. The scope of work includes Laying/Re-routing of existing 3.3 KV, armoured cables of size up to 3Cx400 sq.mm in a single panel through cable trenches, risers, walls and clamping/tying the cables at a regular interval of 500 mm. All items required for the work shall be arranged by the contractor. Number of cables in a single panel board is attached as Annexure-1.
Laying/Re-routing of existing LT, armoured cables. The scope of work includes Laying/Re-routing of existing LT, armoured cables of size up to 19 core, 2.5/4 Sq.mm in a single panel through cable trenches, risers, walls and clamping/tying the cable at a regular interval of 500 mm. All items required for the work shall be arranged by the contractor. Number of cables in a single panel board is attached as Annexure-1.
Laying/Re-routing of existing armoured earth cables. The scope of work includes Laying/Re-routing of existing armoured earth cables of size up to 1Cx600 Sq.mm through cable trenches, risers, walls and clamping/tying the cable at a regular interval of 500 mm. All items required for the work shall be arranged by the contractor.
Laying new 3.3 KV, 3Cx400 sq.mm armoured cable. The scope of work includes loading/unloading, transporting new 3.3 KV, 3Cx400 sq.mm armoured cables from stores/cable yard to Central Substation, handling at site, laying through cable trenches, risers, walls and clamping/tying the cable at a regular interval of 500 mm. Cables shall be supplied by FACT. All other items required for the work shall be arranged by the contractor.
Laying new 3.3 KV, 3Cx240 sq. mm armoured cable. The scope of work includes loading/unloading, transporting new 3.3 KV, 3Cx240 sq.mm armoured cables from stores/cable yard to Central Substation, handling at site, laying through cable trenches, risers, walls and clamping/tying the cable at regular interval of 500 mm. Cables shall be supplied by FACT. All other items required for the work shall be arranged by the contractor.
Laying new armoured, LT cables. The scope of work includes loading/unloading, transporting armoured, LT cables of size up to 19 core, 2.5/4 Sq.mm from stores/cable yard to Central Substation, handling at site, laying through cable trenches, risers, walls and clamping/tying the cable at a regular interval of 500 mm. Cables shall be supplied by FACT. All other items required for the work shall be arranged by the contractor.
Laying new earth cables. The scope of work includes loading/unloading, transporting armoured, earth cables of size up to 1Cx600 Sq.mm from stores/cable yard to Central Substation, handling at site, laying through cable trenches, risers, walls and clamping/tying the cable at a regular interval of 500 mm. Cables shall be supplied by FACT. All other items required for the work shall be arranged by the contractor.
Straight joining 3.3 KV, 3Cx400 sq.mm armoured cables. The scope of work includes carrying out straight joining of 3.3 KV, 3x400 sq.mm armoured cables using compound/heat shrinkable type straight through joint kits as per instruction of Engineer in Charge. Straight Joint Kit and all necessary tools and items required for the work shall be arranged by the contractor. Acceptable Makes for straight through joining kit: Raychem/ 3M/ Denson.
Straight joining 3.3 KV, 3x225/240 sq.mm armoured cables. The scope of work includes carrying out straight joining of 3.3 KV, 3x225/240 sq.mm armoured cables using compound/heat shrinkable type straight through joint kits as per instruction of Engineer in Charge. Straight Joint Kit and all necessary tools and items required for the work shall be arranged by the contractor. Acceptable Makes for straight through joining kit: Raychem/ 3M/ Denson.
Glanding and indoor end termination of 3.3 KV armoured cables. The scope of work includes carrying out glanding and indoor end termination of 3.3 KV, XLPE/ PVC / PILC cables of size 3Cx400 sq.mm using proper glands, lugs and heat shrinkable end termination kit as per instruction of Engineer in Charge. Cables shall be properly clamped to the supporting MS angle. All the items required for the work shall be arranged by the contractor. Acceptable Makes for heat shrinkable end termination kit: Raychem/ 3M/ Denson.
Glanding and indoor end termination of 3.3 KV armoured cables. The scope of work includes carrying out glanding and indoor end termination of 3.3 KV, XLPE/ PVC / PILC cables of size 3Cx225/240 sq.mm using proper glands, lugs and heat shrinkable end termination kit as per instruction of Engineer in Charge. Cables shall be properly clamped to the supporting MS angle. End Termination Kit and all necessary tools and items required for the work shall be arranged by the contractor. Acceptable Makes for heat shrinkable end termination kit: Raychem/ 3M/ Denson.
Glanding and termination of armoured, LT cables of size up to 19 core, 2.5/4 Sq.mm of size. The scope of work includes providing holes at gland plate, concrete chipping/cutting, making holes in concrete if required, carrying out glanding and termination of armoured, LT cables of size up to 19 core, 2.5/4 Sq.mm of size using proper glands and lugs as per the 'as built drawing' submitted by the panel manufacturer. End Termination Kit and all necessary tools and items required for the work shall be arranged by the contractor. Cables for inter-panel is excluded from this work.
Inter-panel wiring. The scope of work includes laying, wiring, glanding, termination and testing of control cables for DC Aux. supply, AC PT supply, Trip status to common annunciator, interlocks etc. in a single panel of newly erected 3.3KV panel using proper glands and lugs as per the 'as built drawing' submitted by the panel manufacturer. Ferrules shall be provided in the wires. Ferrule printing machine shall be arranged by the contractor. Cables will be supplied by FACT. All other items required for the work shall be arranged by the contractor.
Fabrication, painting and erection of ladder type cable tray of size up to 1000mm and cable tray support using 75x75x6/8mm/ 65x65x6/8mm/ 50x50x6mm MS angles, 50x6 mm MS flat, 100x50/125x65/ 150x75 mm MS channel, 100x50/125x70/150x75 mm MS beam etc. in central substation. Loading of MS items from general stores, transportation and unloading at site, safe custody etc. is in contractor’s scope. The fabricated cable rack supports shall be welded to the structures/ insert plates at various levels of the substation building. The contractor shall provide sufficient anchor bolt of size not less than 12 X 100 mm at an interval of 1 meter for fixing the cable tray support if structures/insert plates are not present. The work shall be carried out as per the instructions of the Electrical Engineer -in-charge. MS angle, flat, channel and beam will be supplied by FACT at free of cost. The cable tray and support shall be painted with two coats of anti-corrosive epoxy paint (grey colour) over two coats of suitable primer. Products of M/s. Asian Paints, Berger Paints, Kansai Nerolac Paints & Shalimar Paints alone will be accepted. Product literature of the manufacturer shall be furnished to the Engineer-in charge and the product to be used shall be got approved before starting the work. The epoxy primer shall be Zinc Phosphate primer and thinner used for the work shall conform to the brand specified by the manufacturer in the product literature. The cable tray shall be fixed without causing any damage to the cables. Work site shall be thoroughly cleaned after the work. The contractor shall supply epoxy paint and primer required for the work.
Supply of heat shrinkable indoor end termination kit suitable for 3.3 KV , 3X 400 sq. mm armoured cable. Acceptable Makes: Raychem/ 3M/ Denson.
Supply of heat shrinkable indoor end termination kit suitable for 3.3 KV , 3X 240 sq. mm armoured cable. Acceptable Makes: Raychem/ 3M/ Denson.
Supply of heat shrinkable straight joining kit suitable for 3.3 KV , 3X 400 sq. mm armoured cable. Acceptable Makes: Raychem/ 3M/ Denson.
Supply of heat shrinkable straight joining kit suitable for 3.3 KV , 3X 240 sq. mm armoured cable. Acceptable Makes: Raychem/ 3M/ Denson.
National Electric Co
Universal ELectricals
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .