Loading…
Loading…
Tender Value
₹5.0 L
EMD Value
₹9,980
Closing Date
5 Aug 2026, 4:00 pmClosed
Executive Engineer PWD RandB Division R S Pura
Executive Engineer PWD RandB Division R S Pura
BOQ
2026_PWDJK_318336_2
Short e-NIT No. DRSP/57 of 2026-27 Dated 28-07-2026
Open Tender
Civil Works
Percentage
248 days
R S Pura
eNIT/SBD
3 documents required · 3 mandatory
₹600
Executive Engineer PWD RandB Division R S Pura
₹9,980
R S Pura
28 Jul 2026
28 Jul 2026
6 Aug 2026
28 Jul 2026
5 Aug 2026
28 Jul 2026
31 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earthwork Excavation in all kinds of soil by mechnical means in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5m in width) and for shafts, wells cesspits and the like not exceeding 10 sqm on plan, depth upto 1.5m including disposal of excavated earth upto 1mtr from cutting edge, disposed earth is to be levelled and neatly dressed.. | 42.24 | Cum | 256.85 | ₹10,849.34 |
| 2 | Providing and laying in position cement concrete 1:5:10 ( 1 cement: 5 course sand: 10 crusher stone Aggregate) of specified grade excluding the cost of centring and shuttering- All work upto plinth level. | 8.8 | Cum | 4,826.5 | ₹42,473.2 |
| 3 | Providing and laying in position cement concrete 1:3:6 ( 1 cement: 3 course sand: 6 with 20mm size crusher stone Aggregate) of specified grade excluding the cost of centring and shuttering. All work upto plinth level.. | 47.52 | Cum | 5,733.6 | ₹2,72,460.67 |
| 4 | Providing and laying damp-proof Course 50 mm thick with cement concrete 1:2:4 (1 cement:2 coarse sand: 4 graded stone aggregate 20 mm nominal size) and curing complete | 26.4 | Sqm | 416.5 | ₹10,995.6 |
| 5 | Centering and shuttering including strutting,propping etc and removal of form
Foundation , footing and basis of column. | 79.2 | Sqm | 286.35 | ₹22,678.92 |
| 6 | Engagement of JCB for removal of material from road side. | 8 | hr | 950 | ₹7,600 |
| - | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. Layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering lead upto 50m and lift upto 1.5m | 16.9 | cum. | 218.4 | ₹3,690.09 |
| - | Providing and laying 450mm Dia. Of Hume pipe in proper slope including carriages complete as per directions of Engineer Incharge.. | 38.88 | Rm | 2,475.7 | ₹96,255.22 |
| - | Carriage of materials by mechanical transport including loading/unloading and stacking at site complete for an avg lead of 20 kms | 77.21 | Cum | 409.94 | ₹31,651.47 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.88 MB
BOQ_1048116.xls
BOQ • 0.24 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .