Loading…
Loading…
Tender Value
₹3.8 Cr
EMD Value
₹4.5 L
Closing Date
12 Sept 2026, 6:00 pm
CE 31 Srinagar Zone
HQ CE 31 Srinagar Zone
CONSTRUCTION OF TECHNICAL ACCN URP ALONGWITH ALLIED INFRA AT KITCHAMA UNDER GE 969 EWS
2026_MES_775054_1
800218
Open Tender
Civil Works
Lump-sum
500 days
GE 969 EWS
As per tender documents
11 documents required · 11 mandatory
₹2,000
GE 969 EWS
₹4.5 L
Yes
12 Sept 2026
27 Jun 2026
14 Sept 2026
27 Jun 2026
12 Sept 2026
7 Sept 2026
27 Jun 2026 - 8 Jul 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 2LUMPSUM/ OTHER PRE-PRICED PROVISIONAL SCHEDULES OF WORKS | |||||
| 2.01 | Lump sum price worked out by the contractor for BUILDING WORKS carried forward from Pre-Priced Schedule 'A' Part-I. | 1 | Each | 2,37,43,635 | ₹2,37,43,635 |
| 2.02 | Lump sum price worked out by the contractor for INTERNAL ELECTRIFICATION WORKS carried forward from Pre-Priced Schedule 'A' Part-II. | 1 | Each | 2,33,150 | ₹2,33,150 |
| 2.03 | Lump sum price worked out by the contractor for ROAD, PATH, CULVERT AND HARD STANDING WORKS carried forward from Pre-Priced Schedule 'A' Part-III. | 1 | Each | 33,14,558.25 | ₹33,14,558.25 |
| 2.04 | Lump sum price worked out by the contractor for AREA DRAINAGE WORKS carried forward from Pre-Priced Schedule 'A' Part-IV. | 1 | Each | 5,48,360.13 | ₹5,48,360.13 |
| 2.05 | Lump sum price worked out by the contractor for PROTECTIVE WORKS carried forward from Pre-Priced Schedule 'A' Part-V. | 1 | Each | 29,38,068.34 | ₹29,38,068.34 |
| 2.06 | Lump sum price worked out by the contractor for EXTERNAL WATER SUPPLY WORKS carried forward from Pre-Priced Schedule 'A' Part-VI. | 1 | Each | 2,36,258.24 | ₹2,36,258.24 |
| 2.07 | Lump sum price worked out by the contractor for EXTERNAL ELECTRIFICATION WORKS carried forward from Pre-Priced Schedule 'A' Part-VII. | 1 | Each | 4,82,109.65 | ₹4,82,109.65 |
| 2.08 | Lump sum price worked out by the contractor for LIGHTENING PROTECTION WORKS carried forward from Pre-Priced Schedule 'A' Part-VIII. | 1 | Each | 1,78,820.46 | ₹1,78,820.46 |
| 2.09 | Lump sum price worked out by the contractor for DUNNAGE BLOCK WORKS carried forward from Pre-Priced Schedule 'A' Part-IX. | 1 | Each | 21,980.88 | ₹21,980.88 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.21 MB
DrgURPKitchamaMerged.pdf
Additional Documents • 15.30 MB
BOQ_867892.xls
BOQ • 3.72 MB
TendermergedURPKitchama.pdf
Tender Documents • 1.56 MB
Corrigendum06date.pdf
PDF • 0.02 MB
Corrigendum05date.pdf
PDF • 0.01 MB
Corrigendum05date.pdf
PDF • 0.01 MB
Corrigendum04date.pdf
PDF • 0.01 MB
Corrigendum04date.pdf
PDF • 0.01 MB
Corrigendum03date.pdf
PDF • 0.01 MB
Corrigendum03date.pdf
PDF • 0.01 MB
Corrigendum02date.pdf
PDF • 0.01 MB
Corrigendum02date.pdf
PDF • 0.01 MB
Corrigendum01date.pdf
PDF • 0.01 MB
Corrigendum01date.pdf
PDF • 0.01 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].