SH ROFD, C/O passing places, side drain, Parapets, CD works, and M/T including five year routine maintenance Package No.HP-06-203.
2026_CEHP_148127_1
No.2165-2264 dated 02.06.2026
Open Tender
Civil Works - Roads
365 days
Kullu
As per refer to bid documents
10 documents required · 10 mandatory
₹7,000
₹6.9 L
3 Jun 2026
3 Jun 2026
19 Jun 2026
3 Jun 2026
18 Jun 2026
3 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | Item Code |
|---|---|---|---|---|---|---|
| 1 | Excavation in soil in hilly areas by mechanical/manual means, in all heights and depths, in all kinds of soil including saturated soil comprising of mixed soil, ordinary rock and hard rock. All work of rock cutting by blasting shall be carried out by taking all necessary precautions against soil erosion, damages to hill side, water pollution etc. and to protect stability of hill side. Rock shall be excavated with chiseling and wedging out of rock (where blasting is prohibited). All earth work in cutting/excavation including rock excavation shall be carried out true to lines, grades, side slopes, width, camber, super-elevation and levels as shown on the drawings and as directed by the Engineer-in-Charge in conformity with the requirements of MoRD technical specification for Rural Road, Section. 300 & 1600 to achieve designed formation width including hauling and stacking of materials useful for construction at suitable sites safe manner and disposal of all surplus material to the approved dumping sites through all modes of transportation including head load and animal transport and mechanical means along with its leveling, fine dressing and carriage of machineries, tools, equipment’s and safety measures and other incidentals necessary to complete the work by mechanical means and labour if required. During the mobilization period, contractor should take the advanced x-sec in 15 m (fifteen metre) interval of whole road length in the presence of Engineer-in-Charge or his representative. In case the advanced x-section has been taken in the presence of Engineer-in-Charge representative, in that case the same has to be got approved from Engineer-in-Charge. The land for dumping sites shall be arranged by the contractors himself and nothing extra shall be paid on this account, filling of unevenness blind age and finishing of the road to specified dimensions or as directed by the Engineer-in-Charge for smooth riding. The recovery for stones, whether useful or 752.74 (Seven Hundred Fifty Two point Seven Four) cubic metre at the rate of Rs 300/-only (Rupees three hundred only) per cubic meter amounting to Rs. 2, 25,822.00 only shall be effected on prorata basis in all circumstances. Any loss to the public and private property during the course of excavation shall be the absolute responsibility of the contractor, which shall have to be duly compensated by him in all cases. The rate is including Octroi, Royality, Malkana, Toll Tax or any other Taxes imposed by the Government but excluding GST. | 1 | Per cubic metre | 267.12 | ₹266.85 | BI01010001010000000000000515BI0100001114 |
| 2 | Earth work in excavation for all type of road structure such as retaining walls, breast walls, culverts, drain and Parapets etcetra in all type of classification of soil comprising of ordinary soil, ordinary rock, hard rock chiseling/wedging out rocks (Where blasting is prohibited) as per drawings and MORD technical specification section 300 and 1600 and as per direction of the Engineer-in-Charge including setting out, construction of shoring, bracing, removal of stumps and other deleterious materials and disposal of materials upto any leads and lifts including dressing of sides, bottom and back filling in trenches with excavated suitable approved material to the original surface in layer not executing 150 mm (one hundred fifty millimetre) compacted thickness including shoring, strutting, pumping and bailing out water (surface and sub soil water) upto any depth any quantum of water including cleaning of slush which may arise out during dewatering complete as per direction of Engineer-in-Charge including carriage of materials within all leads, lifts and other incidentals. The rate is including Octroi, Royality, Malkana, Toll Tax or any other Taxes imposed by the Government but excluding GST. | - | Per cubic metre | 441.2 | - | BI01010001010000000000000515BI0100001115 |
| 3 | Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of Tables 300.1 and 300.2 with all leads as per MORD Technical Specification section 300 complete and as per direction of Engineer-in-Charge including carriage of materials within all leads, lifts and other incidentals. The rate is including Octroi, Royality, Malkana, Toll Tax or any other Taxes imposed by the Government but excluding GST. | 1 | Per cubic metre | 97.6 | ₹97.5 | BI01010001010000000000000515BI0100001116 |
| 4 | Loosening of the ground upto a level of 300 mm (three hundred millimetres) below the subgrade level, watered, graded with motor grader and compacted in layers to meet requirement of Tables 300. 1 and 300. 2 of MORD with three wheel 80-100 kN (eighty to one hundred kiloNewton) static roller for subgrade construction as per MORD Technical Specification section 300 as per direction of Engineer-in-Charge. The rate is including Octroi, Royality, Malkana, Toll Tax or any other Taxes imposed by the Government but excluding GST. | 1 | Per cubic metre | 100.7 | ₹100.6 | BI01010001010000000000000515BI0100001117 |
| 5 | Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with in all lifts and leads, transporting to site, spreading, grading by mechanical means to required slope and compacted with three wheel 80-100 (eighty to one hundred) kN (kiloNewton) static roller to meet requirement of Table 300.2 complete as per MORD technical Specification section 300 & 1600 and as per direction of Engineer-in-Charge including carriage of materials within all leads, lifts and other incidentals. The rate is including Octroi, Royality, Malkana, Toll Tax or any other Taxes imposed by the Government but excluding GST. | - | Per cubic metre | 169.6 | - | BI01010001010000000000000515BI0100001118 |
| 6 | Back filling with granular material behind abutments, wing walls, return walls and retaining walls complete as per drawing and MORD technical specifications section 1200, 1600 and as per direction of Engineer-in-Charge including carriage of materials within all leads, lifts and other incidental. The rate is including Octroi, Royality, Malkana, Toll Tax or any other Taxes imposed by the Government but excluding GST. | 1 | Per cubic meter | 1,111.7 | ₹1,110.59 | BI01010001010000000000000515BI0100001119 |
| 7 | Providing, laying and spreading Material for sub base course on a prepared sub grade, adding the designed quantity of cement to the spread Material, mixing in place with rotavator, grading with the motor grader and compacting with the road roller at OMC to achieve the desired unconfined compressive strength and to form a layer of sub-base Quantity of cement assumed as 4% (Four Percent) of quantity of crushed rock by weight Cement Treated Crushed Rock or combination as per clause 403 and Table 400.4 as per the entire satisfaction and directions of Engineer-in-Charge including carriage of material within all leads, lifts and other incidentals. The rate is including Octroi, Royality, Malkana, Toll Tax or any other Taxes imposed by the Government but excluding GST. | - | Per cubic metre | 3,033.7 | - | BI01010001010000000000000515BI0100001120 |
| 8 | Providing, laying and spreading Material for base course on a prepared sub grade, adding the designed quantity of cement to the spread Material, mixing in place with rotavator, grading with the motor grader and compacting with the road roller at OMC to achieve the desired unconfined compressive strength and to form a layer of sub-base Quantity of cement assumed as 4% (Four Percent) of quantity of crushed rock by weight Cement Treated Crushed Rock or combination as per clause 403 and Table 400.4 as per the entire satisfaction and directions of Engineer-in-Charge including carriage of material within all leads, lifts and other incidentals. The rate is including Octroi, Royality, Malkana, Toll Tax or any other Taxes imposed by the Government but excluding GST. | - | Per cubic metre | 3,131.3 | - | BI01010001010000000000000515BI0100001121 |
| 9 | Construction of Granular Sub-Base (Grade-1) by providing well graded materials, spreading in uniform layers with tractor mount grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with three Wheel 80-100 kN (Eighty-hundred kilonewton) static roller to achieve the desired density, complete as per MORD Technical Specification section 400 for grading-I Material, as per the entire satisfaction and directions of Engineer-in-Charge including carriage of material within all leads, lifts and other incidentals. The rate is including Octroi, Royality, Malkana, Toll Tax or any other Taxes imposed by the Government but excluding GST. | 1 | Per cubic metre | 2,458.7 | ₹2,456.24 | BI01010001010000000000000515BI0100001122 |
| 10 | Providing, laying, spreading and compacting by mechanical means crushed stone aggregate size 63mm to 45mm (sixty three millimetre to forty five millimetre) Grading-II consolidated thickness to water bound Macadam specification including spreading in uniform thickness using template, hand packing, rolling with three wheel 80-100 kN (eighty to one hundred kilonewton) static roller in stages to proper grade and camber including applying and brooming, stone screening type-B of size 11.2 mm (eleven point two millimetres) nominal size at the rate of 0.20 cum (zero point two zero cubic metres) per 10 sqm (ten square metres) and binding material at the rate of 0.06 cum (zero point zero six cubic metre) per 10 sqm (ten square metre) to fill up the interstices of coarse aggregate, watering and compacting to the required density as per MORD technical specifications section 400 and as per the entire satisfaction and direction of Engineer-in-Charge including carriage of materials with in all leads, lifts and other incidental. The rate is including Octroi, Royality, Malkana, Toll Tax or any other Taxes imposed by the Government but excluding GST. | 1 | Per cubic metre | 3,056.6 | ₹3,053.54 | BI01010001010000000000000515BI0100001123 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.06 MB
SBD.pdf
Tender Documents • 4.21 MB
BOQ_231681.xls
BOQ • 0.42 MB
Download all tender documents and submit your bid