Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.5 LAccepted-AOC | L1 | Accepted-AOC Agreement executed on 12-08-2025 |
| Sl No | Description | Qty | Unit | SHEEBA P L1 |
|---|---|---|---|---|
| 1.00Building maintenance | ||||
| 1.00 | 51.2.3:Filling with Quarry Muck <br> Filling up low lying and water logged areas with local material/ quarry muck, spreading in layers, leveling the top at site and consolidation by ramming, etc complete for improving the CBR value of subgrade | 8.96 | cum | 902.34 ₹8,084.97 Lowest |
| 1.00 | 2.25:Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m. | 8.96 | cum | 258.56 ₹2,316.7 Lowest |
| 1.00 | OD522734/2024-2025:Providing and laying 60 mm thick factory made cement concrete interlocking paver block of M - 30 grade made by block making machine with strong vibratory compaction, of approved size, design & shape, laid in required colour and pattern over and including 50 mm thick compacted bed of 6mm metal, filling the joints with M- sand etc. all complete as per the direction of Engineer-in-charge. | 89.6 | sqm | 991.77 ₹88,862.59 Lowest |
| 1.00 | 13.61.1:Painting with synthetic enamel paint of approved brand and manufacture to give an even shade:Two or more coats on new work | 2.25 | sqm | 143.05 ₹321.86 Lowest |
| 1.00 | 10.25.2:Item Shifted to Sub head 14 as item 14.73
Item Shifted to head 14 as item 14.74
Steel work welded in built up sections/framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required.In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works | 47 | kg | 154.18 ₹7,246.46 Lowest |
| 1.01 | 13.48.1:Finishing with Deluxe Multi surface paint system for interiors and exteriors using primer as per manufacturers specifications:Two or more coats applied on walls @ 1.25 ltr/10 sqm over and including one coat of special primer applied @ 0.75 ltr /10 sqm | 81.25 | sqm | 167.36 ₹13,598 Lowest |
| 1.01 | 13.1.1:12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand) | 30.96 | sqm | 314.11 ₹9,724.85 Lowest |
| 1.01 | 13.16.1:6 mm cement plaster of mix:1:3 ( 1 cement : 3 fine sand) | 4.02 | sqm | 267.59 ₹1,075.71 Lowest |
| 1.01 | 5.3:Reinforced cement concrete work in beams, suspended floors, roofs, having slope up to 15<sup>0</sup> landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases up to floor five level excluding the cost of centering, shuttering, finishing and reinforcement, with1:1.5:3 (1 cement : 1.5 coarse sand (Zone III) : 3 graded stone aggregate 20 mm nominal size). | 0.4 | cum | 11,492.91 ₹4,620.15 Lowest |
Tender Value
₹2.5 L
EMD Value
₹6,185
Closing Date
5 Jul 2025, 9:00 amClosed
ASSISTANT ENGINEER
ASSISTANT ENGINEER LID and EW Section Andoorkonam Gramapanchayat
PROJ NO 304/25 STORAGE AND SELLING CENTRE FOR AGRICULTURAL PRODUCTS (RE-TENDER)
2025_LSGD_771998_18
01/2026/AE/LSGD/ANDKM
Open Tender
Civil Works - Buildings
Item Rate
180 days
Andoorkonam Gramapanchayat Office
Please refer Tender documents.
10 documents required · 10 mandatory
₹555
₹6,185
13 Sept 2025
28 Jun 2025
7 Jul 2025
28 Jun 2025
5 Jul 2025
28 Jun 2025
Amount
Building maintenance
51.2.3:Filling with Quarry Muck <br> Filling up low lying and water logged areas with local material/ quarry muck, spreading in layers, leveling the top at site and consolidation by ramming, etc complete for improving the CBR value of subgrade
2.25:Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
OD522734/2024-2025:Providing and laying 60 mm thick factory made cement concrete interlocking paver block of M - 30 grade made by block making machine with strong vibratory compaction, of approved size, design & shape, laid in required colour and pattern over and including 50 mm thick compacted bed of 6mm metal, filling the joints with M- sand etc. all complete as per the direction of Engineer-in-charge.
13.61.1:Painting with synthetic enamel paint of approved brand and manufacture to give an even shade:Two or more coats on new work
10.25.2:Item Shifted to Sub head 14 as item 14.73 Item Shifted to head 14 as item 14.74 Steel work welded in built up sections/framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required.In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works
13.48.1:Finishing with Deluxe Multi surface paint system for interiors and exteriors using primer as per manufacturers specifications:Two or more coats applied on walls @ 1.25 ltr/10 sqm over and including one coat of special primer applied @ 0.75 ltr /10 sqm
13.1.1:12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
13.16.1:6 mm cement plaster of mix:1:3 ( 1 cement : 3 fine sand)
5.3:Reinforced cement concrete work in beams, suspended floors, roofs, having slope up to 15<sup>0</sup> landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases up to floor five level excluding the cost of centering, shuttering, finishing and reinforcement, with1:1.5:3 (1 cement : 1.5 coarse sand (Zone III) : 3 graded stone aggregate 20 mm nominal size).
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
5.9.5:Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers
10.6.2:Supplying and fixing rolling shutters of approved make, made of required size M.S. laths, interlocked together through their entire length and jointed together at the end by end locks, mounted on specially designed pipe shaft with brackets, side guides and arrangements for inside and outside locking with push and pull operation complete, including the cost of providing and fixing necessary 27.5 cm long wire springs manufactured from high tensile steel wire of adequate strength conforming to IS: 4454 - part 1 and M.S. top cover of required thickness for rolling shutters.80x1.20 mm M.S. laths with 1.20 mm thick top cover
50.6.5.1:Hollow block masonry using pre cast blocks ( Factory made) of size 40x20x15cm or nearest available size confirming to IS 2185 part 1 of 1979 for foundation and plinth with thickness 15cm in: CM 1:6 ( 1 cement : 6 coarse sand ) etc complete
50.6.1.1:Solid block masonry using pre cast solid blocks ( factory made) of size 40x20x20cm or nearest available size confirming to IS 2185 part 1 of 1979 for foundation and plinth with thickness 20 cm and above in: CM 1:6 ( 1 cement : 6 coarse sand) etc complete
11.37:Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved make, in colours such as White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick cement mortar 1:4 (1 Cement : 4 Coarse sand), including pointing the joints with white cement and matching pigment etc., complete.
17.7.4:Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps, 32 mm C.P. brass waste of standard pattern, including painting of fittings and brackets, cutting and making good the walls wherever require:White Vitreous China Flat back wash basin size 550x 400 mm with single 15 mm C.P. brass pillar tap
50.18.9.14.2:Providing and fixing PVC pipes, fittings including fixing the pipe with clamps at 1.00 m spacing. this includes jointing of pipes & fittings with one step PVC solvent cement and testing of joints complete as per direction of Engineer-in-Charge 32 mm dia 6 Kgf/cm2 - External work - Exposed on wall
2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
50.6.1.7:Solid block masonry using pre cast solid blocks ( Factory made) of size 40x20x15cm or nearest available size confirming to IS 2185 part I of 1979 for foundation and plinth with thickness 15 cm in : CM 1:6 ( 1 cement : 6 coarse sand ) etc complete
5.1.2:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size
5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
10.25.1:Item Shifted to Sub head 14 as item 14.73 Item Shifted to head 14 as item 14.74 Steel work welded in built up sections/framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required.In stringers, treads,landings etc. of stair cases, including use of chequered plate wherever required, all complete
OD508715/2024-2025:Supplying and fixing stainless steel lettering
Bidder Name
SHEEBA P
stage.html
html • 0.03 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .