Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Tender Value
₹23.6 Cr
EMD Value
₹23.6 L
Closing Date
10 Jan 2023, 11:00 amClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
NBCC Bhawan
NBCC Bhawan
CONSTRUCTION WORK OF BOUNDARY WALL ALONG WITH INDUSTRIAL FENCING, SITE DEVELOPMET, CONCRETE ROAD AND CONCRETE PILLAR WITH BARBRD WIRE FENCING IN ASH POND AREA OF OTPC IN KAMAKHYANAR TAHASIL, DHENKANAL, ODISHA.
NBCC/ODISHA/ZO/OTPC/22-23/87~EW1657a1e866b27b9cd10fc2f8
NBCC/ODISHA/ZO/OTPC/22-23/87
Open Tender-Domestic
Civil Works General
NBCC Bhawan
₹11,800
₹23.6 L
10 Jan 2023
27 Dec 2022
10 Jan 2023
27 Dec 2022
10 Jan 2023
Grand Total(A+B+C) 236213351.95
Sl No Item Description Unit Quantity Rate Amount
Excavatiom of foundation including dressing and levelling
the bed and depositing the soil with initial lead of 50m and
initial lift of 1.5m in all kinds of soil including rough
dressing breaking clods to maximum 5cm to 7cm & laying
in layers not exceeding 0.3m depth and as per the direction
of the Engineer-in-charge.
2 Sand Filling
Labour & materials for filling foundation & plinth with river
sand watering ramming etc complete and as per the
direction of the Engineer-in-charge.
3 Concrete Work
C C work of M-15 grade with 20mm and down grade black
hard granite (crusherbroken) stone chips including hoisting cum 32.50 5676.26 184478.46
and laying and as per the direction of the Engineer-in-
4 Concrete Work
C C work of M-25 grade with 20mm and down grade black
hard granite (crusherbroken) stone chips including hoisting cum 250.58 6772.41 1696996.39
and laying and as per the direction of the Engineer-in-
5 Shuttering & Centring Work
Rigid and smooth centering and shuttering for RCC works
including false works and dismantling them after casting
including cost of materials complete in grounf floor and as
per the direction of the Engineer-in-charge.
6 Reinforcement Work
Supplying fiting and placing uncoated HYSD bar
reinforcement complete as per drawing and technical kg 8139.14 114.74 933911.43
specification and as per the direction of the Engineer-in-
7 Fencing Work
Supply and fixing of barbed wire fencing and post by means
of staples and straining hooks by means of tying with G.I
wire and including cost of staples, hooks and tying wire etc.
and complete in all respect as per the direction of the
Engineer-in-charge.
TOTAL(A) Total 3666656.66
Digitally signed by
Rakesh Rakesh Narayan Sinha
Narayan Sinha Date: 2022.12.27
Site Development in Boundary Wall Area in Block-A
Sl No Item Description Uom Quantity Rate Amount
8 Bush Clearing Work
Clearing and grubbing road land including uprooting rank
vegetation, grass, bushes, shrubs, saplings and trees girth
up to 300 mm, removal of stumps of trees cut earlier and
disposal of unserviceable materials and stacking of
serviceable material to be used or auctioned, up to a lead
of 1000 metres including removal and disposal of top
organic soil not exceeding 150 mm in thickness and as per
the direction of the Engineer-in-charge.
9 Earth Work Cutting
Excavatiom of foundation including dressing and levelling
the bed and depositing the soil with initial lead of 50m and
initial lift of 1.5m in all kinds of soil including rough
dressing breaking clods to maximum 5cm to 7cm & laying
in layers not exceeding 0.3m depth and as per the direction
of the Engineer-in-charge.
i All kind of soil cum 118800.00 216.12 25674699.60
iii Hard rock (Blasting Prohibited) cum 19800.00 1051.40 20817791.28
10 Earth Work Filling
Watering earthwork upto OMC condition and compaction
by sheepfoot rollers and dozer in layers not exceeding 22.5
cm to 95% dry density including hire and running charges
of all the machineries complete as per direction of Engineer-
in-charge. (measurement to be taken on the finished
compacted section of the fill under OMC condition.)
Stacking of excavated hard rock in proper manner in side
the property of project area as per direction of Engineer-in-
TOTAL(B) Total 90124672.57
Digitally signed by
Rakesh Rakesh Narayan Sinha
Narayan Sinha Date: 2022.12.27
Construction of Boundary wall in the peripheri of Block - A (Calculation for 11.200 mtr)
Sl No Item Description Unit Quantity Rate Amount
12 Bush Clearing Work
Clearing and grubbing road land including uprooting rank
vegetation, grass, bushes, shrubs, saplings and trees girth
up to 300 mm, removal of stumps of trees cut earlier and
disposal of unserviceable materials and stacking of
serviceable material to be used or auctioned, up to a lead
of 1000 metres including removal and disposal of top
organic soil not exceeding 150 mm in thickness and as per
the direction of the Engineer-in-charge.
Earth work in excavation of foundation trenches in all kinds
of soil including moorum stoney earth and earth mixed
with boulders except sheet rock and boulders requiring
blasting including dressing of sides and leveling the bed
upto the required depth and depositing the excavated
materials away from the work site with all lead and lift.
including shoring, shuttering & dewatering (if required)
with cost of all labour, hire & running charges of the water
pumps sundries T & P required for the work complete as
directed by the Engineer-in-Charge.
i Approach (for movement of machinery & stacking of
ii Foundation for PSC Columns cum 3.89 259.34 1008.31
14 Sand Filling
Supplying & filling in foundation trenches, ditches with
river sand well watered and rammed in layers not
exceeding 23 c.m in depth withn all lead and lift, including
cost, conveyance, loading, unloading, stacking, royalties
and taxes of all materials, cost of all labour, sundries, T&P
required for the work etc. complete in all respect as
directed by the Engineer-In-Charge. (Measurement will be
taken on finished compacted section only)
15 Granular Sub Base
Construction of granular sub-base by providing close
graded Material, mixing in a mechanical mix plant at OMC,
carriage of mixed Material to work site spreading in
uniform layers with motor grader on prepared surface and
compacting with vibratory power roller to achive the
desired density and as per the direction of the Engineer-in-
16 Concrete Work
C C work of M-15 grade with 20mm and down grade black
hard granite (crusherbroken) stone chips including hoisting cum 0.49 5676.26 2758.66
and laying and as per the direction of the Engineer-in-
Digitally signed by
Rakesh Rakesh Narayan Sinha
Narayan Sinha Date: 2022.12.27
17 PSC Panels (RCC)
3000 mm high boundary wall - 50mm thick consists of Pre
Stressed concrete (PSC) Panels of size
300mmx2133mmx50mm. The panel shall be reinforced
with 3nos of 4mm dia tensile steel bars @ 110mm c/c with
40mm cover by using M-30 grade of concrete including
The cost of the above items should be inclusive of all
material inc all taxes, cost of high tensile steel, fabrication
in the proper yard, curing as per requirement, carriage to nos 50.00 1056.10 52805.00
site, lifting by crane and placing in proper alignment, fixing
the post on foundation concrete in proper line and level
including all contingencies, site mobilization demobilization
site illuminations etc complete.
The rate should be inclusive of preparation of curing tank ,
platform, cement storage, steel shuttering to Prestressed
panels and quality control lab and store and fabrication
Digitally signed by
Rakesh Rakesh Narayan Sinha
Narayan Sinha Date: 2022.12.27
18 PSC Column (RCC)
3600mm long Pre Stressed concrete (PSC) Columns in M-30
grade concrete, 3000mm above ground and 600mm for
fixing in the foundation concrete grade of M-25. the
column size is 200mm x 150mm with 2 grooves (65mm x
65mm) on either face of columns face size 200mm. Column
shall be provided with 4mm dia 10 nos steel reinforced
bars as shown in the drawing the post shall be fixed to the
foundation 600mmx900mmx900mm base foundation. A 14
mm dia hole for 12mm dia and 200mm length bolt are to
be kept at one end of the post.
The cost of the above items should be inclusive of all nos 6.00 2295.10 13770.60
material inc all taxes, cost of high tensile steel, fabrication
in the proper yard, curing as per requirement, carriage to
site, lifting by crane and placing in proper alignment, fixing
the post on foundation concrete in proper line and level
including all contingencies, site mobilization demobilization
site illuminations etc complete.
The rate should be inclusive of preparation of curing tank ,
platform, cement storage, steel shuttering to Prestressed
panels and quality control lab and store and fabrication
19 Conrete Work
Providing lifting, hoisting & laying Reinforced Cement
Concrete of M-25 grade in column base,
900mmx900mmx800mm column footings, stem of the
columns up to plinth level and raft foundation as per
approved designs and drawings having a minimum
compressive strength (in work test) 250kg/ square cm in
15cm. Cubes at 28 days after mixing and test conducted in
accordance with I.S.456 and I.S.516 using screened &
washed sharp river sand for mortar and 10mm to 20mm
size black hard crusher broken granite stone chips from
weathered skins required quantities, of approved quality & cum 2.92 6772.41 19748.34
form approved quarry, washed and cleaned to be mixed in
concete mixture with approved quantity of cement
including hoisting, lowering, Laying and compacting
concrete by using vibrators, watering and curing for 28
days, centering and shuttering then after dismantling and
removing the debries away from the work site and finishing
the exposed surface smooth providing grooves or beads
wherever necessary including cost, conveyance, loading,
unloading, stacking, royalties and taxes of all materials,
cost of all labours scaffolding, sundries.
Digitally signed by
Rakesh Rakesh Narayan Sinha
Narayan Sinha Date: 2022.12.27
20 Fencing Work
Supply and fixing of concecertina razor wire shall be of size
8 to 10 confirming to ASTM 653 including carrige charges mtr 11.20 1829.00 20484.80
loading unloading and stacking on the site.
Digitally signed by
Rakesh Rakesh Narayan Sinha
Narayan Sinha Date: 2022.12.27
21 Supply and fixing of barbed wire fencing and post by means
of staples and straining hooks by means of tying with G.I
wire and including cost of staples, hooks and tying wire etc. mtr 11.20 495.60 5550.72
and complete in all respect as per the direction of the
Engineer-in-charge.
22 Supplying, fitting and fixing M.S iron angle of size 50x50x6
mm of approved drawings & designs of approved
specifications / dimensions with necessary welded clamps
fixed in proper position & plumb including a single coat of
priming using approved quality metallic primer, making
required holes in column post with bolts, including cost,
conveyance, loading, unloading, stacking, royalties and
taxes of all materials , cost of all labours, staging, nos 6.00 885.00 5310.00
scaffolding, sundries, T&P etc. complete as directed by the
Engineer in-Charge. Weight to be taken up properly prior
to fixing the grills in the works and payment to be made
accordingly. It should also include cost of 12mm dia
200mm length bolt and MS Plate of size 75x75x6mm thick
to be fixed on top of each column.
23 Painting with synthetic enamel paint of approved colour,
shade and brand like ICl/ Asian/ Berger on Steel work/New
wood work in two or more coats as required to give an
even shade including an under coat of suitable primer of
approved brand and manufacturer including cost of all
materials with taxes and transportation, loading,
unloading, scaffolding, all labour, sundries, T&P, etc. nos 6.00 112.10 672.60
complete as per the direction of the Engineer-in-charge
including filling gaps with putties, scrapping, sand papering
and cleaning the surface to make free from rusts, dusts and
oily substances before applying primer etc. complete.
24 Drilling holes 12mm to 25mm dia in iron Oates, angles, tees
etc of 6mm to 10mm thick complete.
25 Groove cutting and fixing hooks in column post for fixing
fencing wire 4 hooks in each column proper position &
plumb as directed by the Engineer-in-Charge.
Total for 11.200 mtr 145011.51
For 1 mtr 12947.46
TOTAL(C) For 11000 mtr 142422022.72
Digitally signed by
Rakesh Rakesh Narayan Sinha
Narayan Sinha Date: 2022.12.27
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.06 MB
NIT87.pdf
Tender Document
GCC Contracting PMC2022.pdf
Tender Document
MAKE LIST.pdf
Tender Document
SCC.pdf
Tender Document
Master Plan.PDF
Tender Document
Physical Milestone.pdf
Tender Document
BOQ.pdf
Tender Document
addendum-eb5357b499b3-Addendum01.pdf
pdf • 0.13 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .