Tender Value
₹20.6 L
EMD Value
₹21,000
Closing Date
27 Apr 2026, 6:00 pmClosed
Similar tender results from the same govt authority in the past 3 years.
Executive Engineer, Panchayat (R&B) Division, Tapi
Mukhyamantri Border Village Sarvangi Utkarsh Scheme 2025-26 Const.of Causeway on Kanji village near Smashan Ta.Songadh Dist.Tapi.
298008
31 OF 2025-26
Open
Civil Works - Bridges
Tapi
6 documents required · 6 mandatory
₹900
Executive Engineer, Panchayat (R&B) Division, Tapi-Vyara
₹21,000
20 Apr 2026
20 Apr 2026
20 Apr 2026
27 Apr 2026
20 Apr 2026
Name of Work:- મુ યમં ી બોડર િવલેજ સવાગી ઉ કષ યોજના 2025-26. Const.of Causeway on Kanji village
near Smashan Ta.Songadh Dist.Tapi.
: : BILL OF QUANTITY.' : :
Percentage Rate Tender
It. Description of Item (with brief Specification and Rate In
Quantity Unit Amount
No. reference to book of specifications) Figures
1 Excavation for foundation up to 1.5m depth including 213.00 Cum. 254.36
sorting out and stacking of useful material and
disposing off the excavated stuff as directed by
Engineer in charge with all lead and lift in (2) Dense
2 Providing & filling in foundation with ordinary cement 61.90 Cum. 3326.71
concrete M 100 mix and providing necessary vertical
pin headers including formwork vibrating ramming &
curing complete.
3 Providing flood gauge marks on substructure as per 1.90 Sqmt 164.68
design including painting complete.
4 Providing and laying rubble for appron (each stone 33.40 Cum. 1067.08
weighting not less than 40Kg.) including and packing
and filing in the interestices with quarry-spalls.
5 Providing & casting in situ ordinary cement concrete 239.00 Cum. 3904.76
M-150 mix and providing necessary pin headers
including shuttering, scaffolding, laying, vibrating,
curing and finishing complete without V-Groves.(A)
Height from 0.0 M. to 5.0 M.
6 Supplying fixing & joining reinforced concret heavy 90.00 rmt 5560.01
duty non pressure pipe with collars for culverts
carring heavy traffic as per IS 458-1991 specification
including setting and joining the pipe in cement
mortar 1:2 watering or laying of class NP-3 1200mm
7 Filling available excavated earth (excluding rock) in 239.00 Cum. 133.65
trenches. plinth, sides of foundations etc. in layers
not exceeding 20 cm. in depth consolidating each
disposited layer by ramming and watering.
8 Filling in foundation and plinth with murrum or 39.00 Cum. 296.29
selected soil in layers of 20 cm thickness including
watering ramming consolidating etc. complete
9 Providing and casting in situ Controlled cement 30.00 Cum. 5280.86
concrete M-200 for average 100 mm thick wearing
coat laid as directed including temping vibra-ting
finishing curring and filling in joints with Bitumen etc
10 Providing and fixing in position FE 500D TMT bar 1.65 M.T. 73243.02
reinforement including cutting, bending and tying
complete as per detailed drawings. (D) Wearing Coat.
11 Providing and fixing Guard stone as per I.R.C. type 34.00 Nos. 350.80
design including white washing etc. complete (II)
Fixing in C.C. 1:5:10
I / Weam / are willing to carryout the work at…………………. % above/ below percent (Should Be written in
figures and words) of the estimated rate mentioned above Amount of my / our tender works out as under.
*Estimated amount put to tender *Estimated amount put to tender
Deduct ……. % below Rs…………………… Add ………........% Above
*( please strike out whichever is not applicable)
1 The Contractor shall exhibition board with detailed specification and details of works directed by
the Engineer – In – Charge for which no extra payment shall bemade.
2 The labourcess will be deducted as per prevailing rules i.e. 1% of the work done.
3 GST and Income tax TDS will be deducted at a source while making payments of bills.
4 In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as per Govt G.R.:
PRC-10/2017 Cement Consumption/16/C Date: 11/05/2017 as stated in S.O.R. therefore in R.C.C. items
where the reisa change as per actual mix design the cost of difference of cement consumption have been
deducted from the rate of original item at the rate of input rate mentioned in all the tender.
Executive Engineer
Signature of the contractor Panchayat (R & B) Division
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
SBD Kanji Smashan Causeway.pdf
BOQ_ Causeway Kanji Smashan.pdf
Specification Causeway.pdf
GRs - SBD with Index.pdf
Download all tender documents and submit your bid