| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹31.3 LAccepted-AOC | ₹31.3 L | L1 | Accepted-AOC Ist Lowest |
| 2 | L2₹31.6 LRejected-Finance | ₹31.6 L | L2 | Rejected-Finance IInd Lowest |
Tender Value
₹32 L
EMD Value
₹3.2 L
Closing Date
26 Feb 2026, 12:00 pmClosed
Shri Krishna Kumar
Office of the EE, C.D. PWD, Chandauli
Negura Masouni sampark marg par Vishesh marammat yojana antargat surakshatmak diwar ka karya
2026_CEUVZ_1118333_1
EE Ref No. 269/4A Dt. 05.02.2026
Open Tender
Civil Works - Roads
60 days
Chandauli
Please refer Tender documents.
3 documents required · 3 mandatory
₹944
₹3.2 L
Yes
Chandauli
18 Mar 2026
20 Feb 2026
26 Feb 2026
20 Feb 2026
26 Feb 2026
20 Feb 2026
20 Feb 2026
Construction of Embankment with Material Obtained from R.O.W. Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 as per Technical Specification Clause 301.5 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST)
Exacavation in foundation in moorum/single/Kanker including lift upto 1.50 m and lead up to 30 m and including filling watering and ramming of excaveted earth into the space between the building and the sides of foundation tranches or into the plinth and removal and disposal of surface earth and directed by the Engineer in charge upto a distance of 30 m. from the foundation tranches including all T&P phowarah and basket etc. complete. SOR SL.No.-252 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST)
Concrete with 4Cm gauge approved Stone ballast, approved coarse sand and cement in the proportion of 6:3:1 including supply of all matireal labour,tools and plants etc. required for proper completion for the work (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST)
R.C.R with cement and coarse sand mortar in proportion of 1 and 4 respectively in foundation including cost of all material labour T&P etc. required for proper completion of work. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST)
R.C.R with cement and coarse sand mortar in proportion of 1 and 4 respectively in sub structure including cost of all material labour T&P etc. required for proper completion of work. Above GL (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST)
Struck pointing with cement mortar consisting of 1 part cement and 2 parts of sand of 1.25 FM including Supply of all material , labour T&P etc required for proper completion of work.As per SOR SI No-574 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST)
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.27 MB
Tendernotice_2.pdf
PDF • 1.90 MB
BOQ_2078577.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid