Tender ID
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹62.2 Cr
EMD Value
₹12 L
Closing Date
10 Dec 2026, 4:00 pm
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Additional Chief Engineer(Procurement & Contracts)
Supply, Erection (Laying), Testing & Commissioning of OPGW cable (24 F & LILO Section 48 Fiber) by replacing existing Earth wire on existing critical 66kV Tower Transmission Lines. [1] Package -1 : Bharuch Zone & Mehsana Zone [2] Package -2 : Anjar, Gondal, Jamnagar Circles (Rajkot Zone) [3] Package -3 : Amreli, Junagadh, Surendranagar Circles (Rajkot Zone)
366140
T.N.No.ACE(P&C):TN-18 :26-27, Tender No.: ACE(P&C)/Contract/E-467/OPGW/66kV/S&E
Open
Electrical Works
Works
Vadodara
31 documents required · 26 mandatory · 5 optional
₹11,800
Gujarat Energy Transmission Corporation Vadodara
₹12 L
19 Nov 2026
19 Nov 2026
19 Nov 2026
10 Dec 2026
19 Nov 2026
180 days
4 Estimated Cost including GST
(1. Payment of EMD accepted by RTGS / NEFT /
(2. For BG Validity will be 06 (Six) Months from the
date of submission of tender.)
6 Tender Fee (Non-refundable) Rs.
in Rs. Non-Refundable (Incl. GST-18%, Rs. 1800.00)
1. Note: Payment of Tender fee accepted by RTGS /
NEFT / online /Cash only.
7 Time Limit 24 (Twenty-Four) months from the date of LOA.
8 On line (E-tendering) tender /
offer submission last date up 10-12-2026
to 16.00 hours only (This is
9 Physical submission of Tender
fees, EMD and Integrity pact, 16-12-2026
last date up to 15.00 hours. By
RPAD or SPEED POST only.
10 Date of opening of Tender fee,
EMD cover, and QR bid on
line opening at 16.00 Hours.
11 Item Rate basis. (Zone wise package)
12 Prices FIRM PRICE basis
13 Validity of Offer 180 Days from the opening of Technical Bid.
For Billing process, nodal circle is as under;
1. Package-1 (Bharuch Zone & Mehsana Zone): Mehsana Circle
Seal & Signature of Bidder
2. Package-2 (Anjar, Gondal & Jamnagar): Gondal Circle
3. Package-3(Amreli, Junagadh & Surendranagar): Amreli Circle
Additional Chief Engineer (Procurement & Contracts)
Seal & Signature of Bidder
Document Part Page No.
1. Notice Invited Tender - I
2. General Conditions of Contract GCC I
3. Erection Conditions of Contract ECC I
Special Conditions of Contract
with Declaration Form
5. Technical Specifications (EPC) TSP II
Technical Data Sheets and
General Data Schedules
Seal & Signature of Bidder
CLAUSE TITLE PAGE
TENDER SPECIFICATION NUMBER
NOTICE INVITED TENDER
INDEX FOR SPECIFICATION
GENERAL CONDITION OF CONTRACT (GCC)
1 GENERAL PARTICULAR
2 DEFINITION OF TERMS
5 SCOPE OF THE PROPOSAL AND WORK
6 PROJECT PARTICULARS
7 Bidding Costs
8 BID DOCUMENTS
9 Knowing the Bid Documents
10 Clarifications on Bid Documents
11 Amendment of bidding document
12 PREPARATION OF BIDS
13 Local Conditions
14 Documents comprising the bids
17 Goods & Service Tax
18 Time schedule
19 Contract quality assurance
21 Erection tools and tackles
23 Bid security / EMD
25 Signature of bid
26 Sealing and marking of bid
27 Deadline for submission of bids
29 Modification and withdrawal of bid
30 Information required with proposal
31 Opening of bid by owner
32 Purpose of evaluation of bid
33 Preliminary examination of bid
34 Evaluation of bid
35 Calculation of differential price
36 Award of contract
37 Owner’s right
38 Notification of award
39 Signing of contract
40 Contract performance guarantee
41 Language and measures
42 Contract documents
43 Use of contract documents
44 Construction of contract
45 Jurisdiction of contract
46 Execution of contract
Seal & Signature of Bidder
47 Enforcement of terms
48 Completion of contract
49 Time essence of contract
50 Effectiveness of contract
51 Penalty for delay
53 Taxes permission and license
54 Replacement of defective parts
55 Patent right and royalties
56 Defense of suit
57 Limitation of liability
58 Engineer decision
59 Power to omit the work
60 Assessment and sub-letting of contract
61 Change of quantity
62 Packing and forwarding
63 Cooperation with other contractor
64 No waiver rights
65 Certification to affect right
66 Progress report
68 Contract performance guarantee
70 Payment schedule
71 Deduction from contract price
72 Transfer of title
74 Liabilities for accident and damages
75 Delay by owners
76 Damage / war fell
77 Force majeure
78 Suspension of work
79 Contracts default
80 Termination of contract on owner initiation
81 Frustration of contract
82 Graft and commission
83 Settlement of disputes
85 Reconciliation of account
86 Terms of Payment
87 Taking delivery and insurance
88 Contract quality assurance
89 Termination of contract
90 Cancellation of contract
92 Registration with P.F. Office
94 Deduction of TDS under GST
95 INCOME TAX (TDS)
97 Relationship with employee
98 Conflict of Interest
99 Use of ‘Call Before u Dig’ (CBuD) mobile application:
100 Responsibility for correctness of the information
Seal & Signature of Bidder
CLAUSE NO. TITLE Page
ERECTION CONDITIONS OF CONTRACT (ECC)
2 REGULATION OF LOCAL AUTHORITIES AND STATUTES
3 OWNER’S LIEN ON EQUIPMENT
4 ACCESS TO SITE AND WORKS ON SITE
5 CONTRACTOR’S SITE ESTABLISHMENT
6 CO-OPERATION WITH OTHER CONTRACTORS
7 DISCIPLINE OF WORKMEN
8 CONTRACTOR’S FIELD OPERATION
9 PROGRESS REPORT
10 MAN-POWER REPORT
11 PROTECTION OF WORK
12 EMPLOYMENT OF LABOUR
13 FACILITIES TO BE PROVIDED BY THE OWNER
14 FACILITIES TO BE PROVIDED BY THE CONTRACTOR
15 LINES AND GRADES
16 FIRE PROTECTION
18 MATERIALS HANDLING AND STORAGE
19 CONSTRUCTION MANAGEMENT
20 FIELD OFFICE RECORDS
21 CONTRACTOR’S MATERIALS BROUGHT TO SITE
22 PROTECTION OF PROPERTY AND CONTRACTOR’S LIABILITY
24 UNFAVOURABLE WORKING CONDITIONS
25 PROTECTION OF MONUMENTS AND REFERENCE POINTS
26 WORK & SAFETY REGULATIONS
27 CODE REQUIREMENTS
Seal & Signature of Bidder
CLAUSE NO. TITLE PAGE
SPECIAL CONDITIONS OF CONTRACT (SCC)
1 General particulars
3 Earnest money deposit
4 Confirmation by bidder
5 Qualifying requirement
6 Additional documents
7 Price inclusion
8 Security Cum Performance Guarantee
9 Guarantee Period
10 Penalty for delay
11 Completion period
12 Presentation of bill
13 Price variation
14 Penalty Clause
15 As Built Tower Schedule
16 Interse Reverse Bidding
17 Right of the Owner
Performa for Contract Agreement
Format for Bank Guarantee of EMD (Bid Security)
Bidding Schedules
Seal & Signature of Bidder
GENERAL TERMS AND CONDITIONS OF CONTRACT
1.0 General Particulars
The Gujarat Energy Transmission Corporation Ltd., Baroda hereinafter called ‘GETCO’/
‘OWNER’ intends to receive bids for “Supply, Erection (Laying), Testing &
Commissioning of OPGW cable (24 F & LILO Section 48 Fiber) by replacing existing
Earth wire on existing critical 66kV Tower Transmission Lines; including Complete
Installation of OPGW cable (24 & 48 Fibers) including laying , providing required
hardwares, in line splices to be encased in Fibre Optic Splice Enclosures, Laying &
termination of a fibre optic approach cable required to connect Overhead Fiber Optic
Cable (OPGW) between the final in line splice enclosure on the gantry/tower and the
Fibre Optic Distribution Panel (FODP) to be installed within the building at both the
sub-station ends as per technical specification etc on Package wise EPC basis all
detailed in the accompanying specifications in accordance with Terms and Conditions
herein. The bids shall be prepared and furnished as per these Instructions.
2.0 DEFINITION OF TERMS
2.1 The ‘Contract’ means the agreement entered into between the Owner and the
Contractor as per the Contract Agreement signed by the parties, including all
attachments and appendices thereto and all documents incorporated by reference
2.2 ‘Owner’ shall mean the Gujarat Energy Transmission Corporation Ltd Vadodara or
any of its group companies i.e. GUVNL, GSECL, MGVCL, DGVCL, PGVCL,
UGVCL and shall include its legal representatives, successors and assigns.
2.3 ‘Contractor’ or ‘Manufacturer’ shall mean the Bidder whose bid is accepted by the
Owner for the award of the Works and shall include such successful Bidder’s legal
representatives, successors and permitted assigns.
2.4 ‘Sub-Contractor’ shall mean the person named in the Contract for any part of the
Works or any person to whom any part of the Contract has been sublet by the
Contractor with the consent in writing of the Engineer and will include the legal
representatives, successors and permitted assigns of such person.
2.5 ‘Engineer’ shall mean the officer appointed in writing by the Owner to act as
Engineer from time to time for the purpose of the Contract.
2.6 The terms ‘Equipment’, ‘Stores’ and ‘Materials’ shall mean and include equipment,
stores and materials to be provided by the Contractor under the Contract.
2.7 ‘Works’ shall mean and include the furnishing of equipment, labour and services, as
per the Specifications and complete erection, testing and putting into satisfactory
operation including all transportation, handling, unloading and storage at the Site as
defined in the Contract.
2.8 ‘Specifications’ shall mean the Specifications and Bidding Document forming a part
of the Contract and such other schedules and drawings as may be mutually agreed
2.9 Site’ shall mean and include the land and other places on, into or through which the
works and the related facilities are to be erected or installed and any adjacent land,
paths, street or reservoir which may be allocated or used by the Owner or
Seal & Signature of Bidder
in the performance of the Contract.
2.10 The term ‘Contract Price’ shall mean the lump-sum price quoted by the Contractor
in his bid with additions and/or deletions as may be agreed and incorporated in the
Letter of Award and the contract agreement for the entire scope of the works.
2.11 The term ‘Equipment Portion’ of the Contract price shall mean the ex-works value of
the equipment/Materials supplied include structures, town materials insulators,
conducting etc.
2.12 The term ‘Erection Portion’ of the Contract price shall mean the value of field
activities of the works including erection, testing and putting into satisfactory
operation including successful completion of performance and guarantee tests to be
performed at Site by the Contractor including cost of insurances.
2.13 ‘Manufacturer’s Works’ or ‘Contractor’s Works’, shall mean the place of work used
by the manufacturer, the Contractor, their collaborators/associates or Sub-
Contractors for the performance of the Contract.
2.14 Site Engineer ‘Inspector’ shall mean the Owner owner’s Engineers or any person
nominated by the time to inspect the equipment; stores or Works under the Contract
and/or the duly authorized representative of the Owner.
2.15 ‘Notice of Award of Contract’/’Letter of Award’/’Telex of Award’ shall mean the
official notice issued by the Owner notifying the Contractor that his bid has been
2.16 ‘Order’ shall mean the official letter issued by the Owner informing the acceptance
2.17 ‘Date of Contract’ shall mean the date on which Notice of Award of Contract / Letter
of Award has been issued.
2.18 ‘Month’ shall mean the calendar month. ‘Day’ or ‘Days’ unless herein otherwise
expressly defined shall mean calendar day or days of 24 hours each.
A ‘Week’ shall mean continuous period of seven (7) days.
2.19 Writing’ shall include any manuscript, type written or printed statement, under or
over signature and/or seal as the case may be.
2.20 When the words ‘Approved’, ‘Subject to Approval’, ‘Satisfactory’, ‘Equal to’, ‘Proper’,
‘Requested’, ‘As Directed’, ‘Where Directed’, ‘When Directed’, ‘Determined by’,
‘Accepted’, ‘Permitted’, or words and phrases of like importance are used the
approval, judgment, direction etc. is understood to be a function of the
Owner/Engineer.
2.21 Test on completion shall mean such tests as prescribed in the Contract to be
performed by the Contractor before the work is taken over by the Owner.
2.22 ‘Performance and Guarantee Tests’, shall mean all operational checks and tests
required to determine and demonstrate capacity, efficiency, and operating
characteristics as specified in the Contract Documents.
2.23 The term ‘Final Acceptance’/‘Taking Over’ shall mean the Owner’s written
acceptance of the Works performed under the Contract, after successful
Seal & Signature of Bidder
commissioning/completion of Performance and Guarantee Tests, as specified in the
accompanying Technical Specifications or otherwise agreed in the Contract.
2.24 ‘Guarantee Period’/’Maintenance Period’ shall mean the period during which the
Contractor shall remain liable for repair or replacement of any defective part of the
works performed under the Contract.
2.25 ‘Latent Defects’ shall mean such defects caused by faulty designs, material or work-
man- ship which cannot be detected during inspection, testing etc, based on the
technology available for carrying out such tests.
2.26 ‘Drawing’, ‘Plans, shall mean all:
a) Drawings furnished by the Owner/Consultant as a basis of Bid/Proposals.
b) Supplementary drawings furnished by the Owner/Consultant to clarify and to
define in greater detail the intent of the Contract.
c) Drawings submitted by the Contractor with his bid provided such drawings are
acceptable to the Owner/Consultant.
d) Drawings furnished by the Owner/Consultant to the Contractor during the
progress of the work; and
e) Engineering data and drawings submitted by the Contractor during the progress
of the work provided such drawings are acceptable to the Engineer/Owner.
2.27 ‘Codes’ shall mean the following including the latest amendments and/or
replacements, if any:
a) Indian Electricity Act, 1905 and Rules and Regulations made there under.
b) Electricity Act 2003 and Rules & Regulations made there under.
c) Indian Factory Act, 1948 and Rules and Regulations made there under.
d) Indian Explosives Act, 1884 and Rules and Regulations made there under.
e) Indian Petroleum Act, 1934 and Rules and Regulations made there under.
f) A.S.M.E. Test Codes.
g) A.I.E.E. Test Codes.
h) American Society of Materials Testing Codes.
i) Standards of the Indian Standards Institution.
j) Other Internationally approved standards and/or rules and regulations touching
the subject matter of the Contract.
2.28 Words imparting the singular only shall also include the plural and vice –versa
where the context so requires.
2.29 Words imparting ‘Person’ shall include firms, companies, corporations and
associations or bodies of individuals, whether incorporated or not.
2.30 Terms and expressions not herein defined shall have the same meaning as are
assigned to them in the Indian Sale of Goods Act (1930), failing that in the Indian
Contract Act (1872) and failing that in the General Clauses Act (1897) including
amendments thereof, if any.
2.31 In addition to the above the following definitions shall also apply.
a) ‘All line materials’ to be supplied shall also mean ‘Goods’.
b) ‘Constructed’ shall also mean ‘erected and installed’.
Seal & Signature of Bidder
c) ‘Contract Performance Guarantee’ shall also mean ‘Contract Performance
2.32 GST / Cess means all applicable Tax/Cess under GST Laws. GST Laws means
IGST Act, GST (Compensation to the State for Loss of Revenue) Act, CGST Act,
UTGST Act and SGSCT Act, 2017and all related ancillary legislations.
2.33 Works contract means a contract for composite supply and covered under the
definition of Works Contract as defined under Section 2(119), of the CGST Act,
2017 or SGST Act, 2017 and similar provisions, applicable under the UTGST Act,
2017and the IGST Act,
3.0 APPLICATION
These General Conditions shall apply to the extent that they are not superseded by
provisions in other parts of the Contract.
The goods supplied under this Contract shall conform to the standards mentioned in
the Technical Specifications, and, when no applicable standard is mentioned, to the
authoritative standard appropriate to the goods and such standards shall be the
latest issued by the concerned institution.
5.0 Scope of the proposal and Work
5.1 The Scope of the proposal shall be on the basis of a single Bidder’s responsibility,
completely covering all the supply, erection & commissioning of transmission line
specified under the accompanying Technical Specifications. It will include among
others as specified therein the following: -
a) Detailed Engineering of all materials.
b) Complete manufacture including shop testing.
c) Providing engineering drawings, data, operation manual, etc for the Owner’s
d) Packing and transportation from the manufacturer’s works to the Site.
e) Receipt storage, preservation and conservation of equipment at the Site.
f) Pre-assembly, if any, erection, testing and commissioning of all the equipments.
g) Reliability tests and performance and guarantee tests on completion of
5.2 No deviation whatsoever to certain conditions of the bidding documents permitted
by the Owner and therefore, the Bidders are advised that while making Bid
Proposals and quoting prices these conditions may appropriately be taken into
consideration. Bidders are required to furnish a certificate in this regard as per the
format provided in Special Conditions of Contract in a separate sealed
envelope containing Bid security, which shall accompany the Technical Bid.
Any Bid not accompanied by such certificate shall be rejected by the Owner and
shall not be opened.
5.3 Bids not covering the above cited entire scope of works may be treated as
incomplete and hence rejected.
5.4 The Bidder shall complete all the schedules & annexure in the Bid Proposal Sheets,
Technical Data Sheets and specified elsewhere. The Qualifying Data should be
filled in the required schedule of Bid Proposal Sheets.
Seal & Signature of Bidder
5.5 This specification covers the detailing, supply, erection & commissioning and handing
over in ready to switch on condition to GETCO of complete, including fixing of
accessories, 400kV and 220/132/66KV transmission line on turnkey basis.
5.6 The scope for “Supply, Erection (Laying), Testing & Commissioning of OPGW
cable (24 F & LILO Section 48 Fiber) by replacing existing Earth wire on existing
critical 66kV Tower Transmission Lines”; including Complete Installation of
OPGW cable (24 & 48 Fibers) including laying , providing required hardwares, in
line splices to be encased in Fibre Optic Splice Enclosures, Laying &
termination of a fibre optic approach cable required to connect Overhead Fiber
Optic Cable (OPGW) between the final in line splice enclosure on the
gantry/tower and the Fibre Optic Distribution Panel (FODP) to be installed
within the building at both the sub-station ends as per technical specification
etc on Package wise EPC basis.
5.7 It is the responsibility of the GETCO for complete way leave clearance for
execution of work and compensation for Right of Way / Way Leave / Tree-
Crop damages etc. to be paid as per GoG guideline dated 14-10-
Moreover, All the procedure regarding RoW (Right of Way) compensation is to
be carried out by Agency is as follows:
a) Identification of Land Owner, their Land Survey No. with supporting
documents i.e. 7/12 Utara, etc.
b) Handing over / distribution of Notice to concern land owners.
c) Plotting of line route on tikka map.
d) Preparation of “Panchnama Case” and follow-up with concern
Sarpanch / Talati / Mamlatdar or concern Revenue Authority as well as
Land Owners / Farmers for their signature & thereof.
e) Preparation of RoW case for submission of Office of the District
Magistrate, etc. and also follow-up with them.
f) Follow-up with concern authority for getting statutory approvals
including Police Department.
6.0 PROJECT PARTICULARS
Name of the Project:
“Supply, Erection (Laying), Testing & Commissioning of OPGW cable (24 F &
LILO Section 48 Fiber) by replacing existing Earth wire on existing critical
66kV Tower Transmission Lines”
1. System Voltage and : 66kV
2. System of Earthing Pipe type /Counter poise earthing
3. Rated frequency : 50 Hz ± 5%
7.0 Bidding Costs
All costs/expenses in the preparation and submission of the Bid (including any post
Bid discussions/presentations) shall be fully borne by the Bidder. Owner will not be
responsible / liable for these costs irrespective of the course and conclusion of this
8.0 BID DOCUMENTS
Seal & Signature of Bidder
Details of Documents
The following Bid documents apart from Invitation to Bid detail the material and
equipment specifications/characteristics, the bidding procedures and the terms &
conditions of contract:
a. General Conditions of Contract (GCC-Part I)
b. Erection Conditions of Contract (ECC-Part I)
c. Special Conditions of Contract (SCC-Part I)
d. Technical Specifications (TSP-Part II)
e. Technical Data Sheets (TDS-Part II)
9.0 Knowing the Bid Documents
9.1 Every intending Bidder is to examine and understand all instructions, forms, terms,
conditions and specifications in the Bid Documents and fully know himself all the
conditions and contents therein, which may in any manner, affect the scope &
content of work and the costs thereof. Submission of a Bid not substantially
responsive to the Bid Document in all respects and/or failure to furnish all
information required by the Bid Document may entail rejection of the Bid at the
10.0 Clarifications on Bid Documents
10.1 In case an intending Bidder finds any discrepancy or omission in the documents
and specifications or is in doubt as to the true meaning of any part, he shall make a
request, in writing not later than the due date of opening of technical bid. The owner
will issue explanations, interpretations and clarifications as deemed fit in writing as a
response to this request. On receipt of such interpretations/clarifications, the Bidder
may submit his Bid within the date and time stipulated in the Bid invitation, All such
explanations, interpretations and clarifications from the Owner shall be deemed as
part of Bid Documents and shall invariably accompany the Bidder’s proposal.
10.2.1 Any verbal / telephonic clarifications and information given by the Owner or his
employee (s) or his representative(s) will not in anyway be binding on the Owner.
11.0 Amendment of bidding document:
11.1 At any time prior to the deadline for submission of Bids the Owner may, for any
reason, whether at his own initiative or in response to a clarification requested by
the intending Bidder, modify the Bidding Document with amendment(s).
11.2 The amendment will be notified in writing or Fax /web site to all intending Bidders
who have received the Bidding Document at the address contained in the letter of
request for issue of bidding document from the Bidders. Owner will bear no
responsibility or liability arising out of non-receipt of the same in time or otherwise.
11.3 In order to afford prospective bidders reasonable time in which to take the
amendment into account in preparing their bids, the Owner may, at his discretion,
extend the deadline for the submission of bids.
11.4 Such amendments, clarifications etc. shall be binding on bidders and will be given
due consideration by the Bidders while they submit their bids and shall invariably
enclose such documents as a part of the bid.
12.0 PREPARATION OF BIDS
12.1 Language of Bid:
Seal & Signature of Bidder
The Bid prepared by the Bidder and all correspondence and documents relating to
the Bid, exchanged by the Bidder and the Owner, shall be written in the English
language, provided that any printed literature furnished by the Bidder may be written
in another language so long as accompanied by an English translation of its
pertinent passages. Failure to comply with this may disqualify a bid. For purposes of
interpretation of the bid, the English translation shall govern.
12.2 Bid Format
Bidders have to make the Bid in the formats furnished with this Document verbatim
without adding any printed/typewritten text of their own.
13.0 Local Conditions:
Bidder should note that Way leave clearance for execution of work and
compensation for Right of Way / Way Leave / Tree-Crop damages etc. to be
paid as per GoG guideline dated 14-10-2024,02.12.2024 & 28-02-2025. is in
scope of GETCO.
Moreover, All the procedure regarding RoW (Right of Way) compensation is to
be carried out by Agency is as follows:
a) Identification of Land Owner, their Land Survey No. with supporting
documents i.e. 7/12 Utara, etc.
b) Handing over / distribution of Notice to concern land owners.
c) Plotting of line route on tikka map.
d) Preparation of “Panchnama Case” and follow-up with concern
Sarpanch / Talati / Mamlatdar or concern Revenue Authority as well as
Land Owners / Farmers for their signature & thereof.
e) Preparation of RoW case for submission of Office of the District
Magistrate, etc. and also follow-up with them.
f) Follow-up with concern authority for getting statutory approvals
including Police Department.
13.1 It will be imperative on each Bidder to fully inform himself of all local conditions and
factors which may have any effect on the execution of the Contract covered under
these documents and specifications. The Owner shall not entertain any request for
clarifications from the bidders, regarding such local conditions.
13.2 It must be understood and agreed that such factors have properly been investigated
and considered while submitting the proposals. No claim for financial adjustment to
the Contract awarded under these specifications and documents will be entertained
by the owner. Neither any change in the time schedule of the Contract nor any
financial adjustments arising thereof shall be permitted by the Owner, which are
based on the lack of such clear information or its effect on the cost of the works to
14.0 Documents comprising the Bid:
Requirements etc. furnished in the Bidding Documents.
14.2.1 The Bidder shall also submit documentary evidence to establish that the Bidder
meets the Qualification Requirements as detailed in Special Conditions of Contract
and (Detail of transmission line work executed with copy of completion certificate).
14.3 All Tender Documents/ formats are to be returned completed and filled in all
respects and signed by the Company Authorized Signatory wherever specified.
Seal & Signature of Bidder
14.3 The Bid Guarantee shall be furnished in a separate cover in accordance with tender
15.0 Bid Price:
F.O.R. Destination prices for Goods, the price for erection, testing and
commissioning, price for associated civil, structural works and other services it
proposes to furnish under the contract, EXCLUDING GST and Cess along with the
total bid price.
GST shall be applicable at the rate of 9% CGST plus 9% SGST or 18% IGST, or as
applicable to composite supplies in the nature of Works Contract applicable from
time to time will be paid within the original contractual delivery period. However, the
Classification Codes (i.e. HSN or SAC) for each item of different segments or
portions of the Works Contract, shall be specified separately, for information and
technical identification purpose only.
15.2 Detailed break up, covering all the price components of unit prices as well as total
be provided by the bidder. This break up shall be entered separately in the following
A) For all goods offered:
1. Prices quoted should be FIRM except for supply of items for which Price
variation will be applicable as per clause no: 13 of the SCC, Part-I of the tender
and on F.O.R. Destination basis (i.e. any of the stores of COMPANY in Gujarat).
However, the Tenderer should indicate in Price Bid, the break-up of Total Unit
F.O.R. Destination Price stating the Unit Ex-works price, freight, packing &
forwarding charges, Insurance Charges which is a must. The rate of GST shall
9% CGST plus 9% SGST or 18% IGST or as applicable to composite supplies
in the nature of Works Contract, applicable from time to time.
2. This tender is to be treated as a contract for composite supply under the
category of Works Contract, which is, as per the provisions of Section 2(30),
read with, Section 2(119), further read with, Paragraph 6(a) of the Schedule II,
to the CGST Act, 2017 and similar provisions, applicable under UTGST Act,
2017 and the IGST Act, 2017. However, classification Codes under different
segments or portions of the Works Contract, may be specified separately.
3. The Tenderer should invariably indicate the total unit end cost price considering
all their costs / calculations in the Price bid itself for each item and all sub-items
if any. This is a must. Cost components hidden / furnished elsewhere will not be
considered and will be ignored out rightly.
4. Every bidder shall inform their GSTIN No. of the registered place(s) wherefrom
the bidder intends to supply the goods / services, meaning thereby the bidder
have to supply the goods / services from the relevant declared / registered place
of supply only.
15.3 The bidder’s separation of price components in accordance with clause 15.2 supra
will be solely for the purpose of the facilitating the comparison of Bids by the owner,
for contract price amendment due to quantity variation and for on account payments
(in case of award) and shall not in any way limit the Owner’s rights.
15.4 The Bidder shall specifically note that the Tenders are invited on percentage based
Seal & Signature of Bidder
15.5 The bidder must furnish the price break up in statement for each item as
prescribed in the price bid (Part- III). The total price derived as per price break
up must be matched with quoted price. Tender will be ignored on non-
submission of prescribed statement.
16.0 Price Basis:
16.1 The Price shall be quoted on firm basis except for supply of items for which Price
variation will be applicable as per clause no: 13 of the SCC, Part – I of the
16.2 The Price quoted by the bidder shall remain fixed for all the items except for items
for which Price variation will be applicable as per clause no:13, Part – I of the
SCC, Part – I of the tender; during the bidder’s performance of the contract and
shall not be subject to variation on any account save for change in quantity. A bid
submitted with an adjustable price quotation shall be treated as non-responsive
17.0 Goods and Service Tax (GST):
17.1 The F.O.R. Destination prices are excluding GST and Cess at the rate of 9% CGST
plus 9% SGST or 18% IGST, under the GST Law or as applicable to the contract for
composite supply under the category of Works Contract from time to time which will
be paid extra on a given taxable goods and/or services within the original
contractual delivery period. (GST/Cess means all applicable Tax/Cess under GST
Laws. GST Laws means IGST Act, GST (Compensation to the State for Loss of
Revenue) Act, CGST Act, UTGST Act and SGSCT Act, 2017 and all related
ancillary legislations).
17.2 You shall have to submit a C.A Certificate & duly authorized Signatory of successful
bidder, certifying that you have not claimed Refund of any applicable GST and
Cess, charged to COMPANY or shall not claim any such Refund, on a future date,
from the concerned Authorities and if, any Refund, in respect of such GST and
Cess, is claimed by you, it will be immediately passed on to the COMPANY, without
COMPANY making any specific Claim, for the same, either from the Department or
17.3 The offers having price INCLUSIVE OF GST and Cess is likely to be rejected if the
rate of GST and Cess is not mentioned clearly. COMPANY may at its discretion
consider such offer with presumption of highest applicable rate of GST and Cess
prevailing when the price quoted is inclusive of GST and Cess.
17.4 Supplier/Contractor should charge GST in Invoice at the rate as agreed to /
mentioned in acceptance of tender only and any deviation in the same shall not be
accepted. Further, any additional liability of GST (later on due to wrong mentioning
of GST rate, mis-interpretation of HSN/SAC Code, etc.) over and above as charged
in the invoice shall be borne by the Supplier/Contractor. However, any refund
received by the supplier / contractor on account of GST charged from the company;
such refund shall have to be passed on to the company, along with interest if any.
Such refund along with interest needs to be passed on suo-moto by the supplier /
17.5 Further, the Company has a right to recover the amount of GST along with penal
interest at the rate of 15% per annum or any other amount charged by GST Dept.
whichever is higher if GST charged is not paid / short paid to the government or fail
to upload the details or uploads inaccurate particulars on GSTIN portal by the
Supplier / Contractor within the stipulated time limit.
Seal & Signature of Bidder
17.6 In case, Govt. revises the rate of GST rate / Code during the tenure of the contract,
the provision of GETCO’s statutory variation clause shall apply.
17.7 INPUT TAX CREDIT BENEFIT:
In the event of any statutory increase in the rate of Input Tax Credit and / or due to
inclusion of any other additional item of their inputs / input services under the ambit
of the Input Tax Credit provisions under the GST Act, subsequent to the date of
submission of the offer, the same should be passed on to COMPANY and you
should inform such changes to COMPANY from time to time.
17.8 GST, other taxes and other levies and duties including custom duty solely in respect
of the transaction between the owner and the contractor under this contract, if any,
shall be included in the bid price. These shall also be indicated separately wherever
applicable as mentioned in the Tender.
17.9 As regards the income Tax, surcharge on income tax and any other corporate tax,
including GST if any the owner shall not bear any tax liability whatsoever. The
bidder shall be liable and responsible for payment of such taxes as attracted under
the provisions of the law.
17.10 Notwithstanding the tax liabilities as per the sub-clause 17.9 above, the owner shall
have the right to make deduction at source from the amounts payable to the
contractor in respect of Income Tax (on the cost of items of supply included in the
works contract) as may be mandatory in terms of the law. The owner shall not bear
any liability in this regard but shall issue necessary certificate in respect of such
deduction made.
17.11 Whenever concessional rate of GST is indicated by the bidders, it shall be
confirmed whether any increase in the rates that becomes applicable during the
performance of the contract would be absorbed by the supplier. Bidder shall note
that in case of absence of such confirmation; the tenders will be evaluated taking
into account the maximum rate of GST applicable.
17.12 In case any tax or duty is newly introduced by the Government applicable for this
contract with effect from the next day of the date submission of the bid and if the
contractor is required to pay additional tax or duty, then the owner shall reimburse
the contractor the additional tax or duty so paid by the contractor against
submission by the contractor of documentary evidence to the satisfaction of the
owner. This provision will not be applicable to transaction between the contractor
and his sub-suppliers, sub-contractors for raw materials etc and will be applicable
only to the direct transactions between the contractors and owner. Besides the said
statutory variation, no other statutory variation shall be payable by the owner.
17.13 The owner’s liability for all taxes and duties including GST under the contract shall
be limited to those indicated by the Bidder in the Bid Proposal Sheets, subject to the
statutory variations and variations as per Clause No. 7.5 of SCC.
17.14 If the cost to the Contractor during the performance of the ‘Contract’ shall be
increased or reduced by reasons of the making, passing or promulgation of any law
after the date of submission of bid or by any order, regulation or bye-law having the
force of law, the amount of such increase or reduction shall be added to or
deducted from the “Contract Price” as the case may be for direct transactions
between contactor & owner. It is the Bidders responsibility to furnish details of
taxes, duties, levies etc. applicable as on the date of submission of the bid.
17.15 No claim for any increase towards the statutory variation regarding enhancement of
existing tax or duty or introduction of a new tax or duty applicable shall be
entertained by the Owner during the extended period of contract, if any, provided
Seal & Signature of Bidder
the extension of the contract is required by causes attributable to the contractor.
However, the decrease in any taxes/duties shall be passed on to GETCO.
17.16 The provision of statutory variation regarding enhancement of existing tax or duty or
introduction of a new tax or duty will be applicable only to the direct transaction
between the contractor and the owner.
17.17 Before quoting, the bidder may ascertain from the concerned tax authorities of
Government for the applicability of Entry Tax, GST etc. in respect of this work and
include the same in the quoted price. No separate claim in this regard will be
entertained by the Owner, as it is the responsibility of the Bidder to pay all these
17.18 In addition, the conditions detailed under Special Conditions of Contract shall apply.
18.0 Time Schedule:
18.1 The basic consideration and the essence of the Contract shall be strict adherence
to the time schedule for performing the specified works.
18.2 The Owner’s requirements of completion schedule for the Works are mentioned in
the accompanying Special Conditions of Contract.
18.3 The completion schedule as stated in the special conditions of contract shall be one
of the major factors in consideration of the bids.
18.4 The owner reserves the right to request for a change in the work schedule during
pre- award discussions with successful bidder.
18.5 The successful bidder will be required to prepare detailed PERT Network/ detailed
Bar chart and finalize the same with the owner as per the requirement
19.0 Contract Quality assurance:
19.1 The Bidder shall include in his proposal the Quality Assurance Programme
containing the overall quality management and procedures which he proposes to
follow in the performance of the Works during various phases as detailed in relevant
clause of the General Technical Conditions.
19.2 At the time of Award of Contract, the detailed Quality Assurance Programme to be
followed for the execution of the Contract will be mutually discussed and agreed
and such agreed Programme shall form a part of the Contract.
19.3 The Bidder shall clearly specify the list of sub-vendors from whom the bought out
items are being supplied. Such details shall be accompanied by their list of previous
supplies made performance reports etc. However, in case of orders are placed,
specific approval shall be obtained from the owner for the vendor supplied
materials. The quality assurance program shall be furnished for each material
separately for approval.
20.0 Insurance:
The Bidder’s insurance liabilities pertaining to the scope of Works are detailed out in
Clauses titled Insurance, in General Terms and Conditions of Contract and in
Erection Conditions of this Part-I. Bidder’s attention is specifically invited to these
clauses. Bid price shall include all the costs in fulfilling all the insurance liabilities
under the Contract.
21.0 Erection Tools and Tackles:
Seal & Signature of Bidder
The Bidder under a separate schedule, in his proposal shall include a list of all-
special equipment tools & tackles etc. which he proposes to bring to site for the
purpose of erection, handling, testing and commissioning including performance
and guarantee tests of the equipment. If any such equipment is listed anywhere
else in the proposal and not specially mentioned in the above schedule, it shall be
deemed to have been included in the Bidder’s proposed scope of supply.
22.0 Brand Names:
22.1 The specific reference in these specifications and documents to any
material/equipment by brand name make or catalogue number shall be construed
as establishing standards of quality and performance and not as limiting
competition. However, Bidders may offer other similar material/equipment provided
they meet the specified standard, design and performance requirements. The
Bidder shall furnish adequate technical information about such alternative material
equipment to enable the Owner to determine its acceptability. The Owner shall be
the sole judge on the acceptability or otherwise of such alternatively
material/equipment.
22.2 The bidder shall note that standards for workmanship material and equipment, and
reference to brand name of catalogue numbers designed by the Owner in its
Technical Specifications are intended to be descriptive only and not restrictive. The
Bidder may substitute alternative standards, brand name and/or catalogue numbers
in its bid, provided that it demonstrates to the Owner’s satisfaction that the
substitutions are substantially equivalent or superior to those designed in the
Technical Specification.
23.0 Bid Security/EMD:
23.1 (a) The estimated cost for of Tender is more than Rs. 100 lacs, the EMD is payable as
50 % of EMD by DD in favor of Gujarat Energy Transmission Corporation Ltd.
on any Scheduled Bank in Vadodara and Balance 50 % by Bank Guarantee
from any Nationalized Bank in the format provided herein.
(b) The estimated cost of tender is less than Rs.100 Lacs, the EMD is payable as under:-
100 % of EMD by DD in favor of Gujarat Energy Transmission Corporation
Ltd. on any Scheduled Bank in Vadodara.
(c) Payment by Cheque / Coop Bank Guarantee/ Company Guarantee is not
(d) Validity Period: - The offer should be valid for a minimum period of 180 days
from the date of opening of Technical bid.
23.2 The bid security is required to protect the owner against the risk of Bidder’s conduct,
which would warrant the guarantee forfeiture, pursuant to relevant paras elsewhere
The bid guarantee shall be made payable to the Owner without any condition
23.3.1 Any bid not secured in accordance with Para 23.1 above will be rejected by the
Owner as non-responsive. No exemptions are made in the furnishing of the
Seal & Signature of Bidder
23.3.2 Unsuccessful Bidder’s bid security/EMD will be returned/refunded on finalization of
tender or three months-from the date of submission of tender whichever is later.
23.3.3 The successful bidders, Bid Security will be discharged upon, furnishing the
contract performance guarantee
23.4 The bid guarantee may be forfeited.
a) If a Bidder withdraws its bid during the period of bid validity specified by the
bidder on the bid Form:
b) If a bidder refuses to accept the contract or fails to commence the works
(including supplies within thirty days of letter of award of contract)
24.0 Format of Bid:
24.1 The Bidder shall prepare two copies of the bid, clearly marking each “Original
bid” and “Copy of Bid”, as appropriate. In the event of any discrepancy between
them the original shall govern. All the documents furnished in original document
shall be furnished in other copies of Bids.
24.2 The original and all copies of the bid shall be typed or written in indelible ink and
shall be signed by the Bidder or a person or persons duly authorized by the Bidder
to sign the Contract. The letter of authorization shall be indicated by written power-
of-attorney accompanying the bid. All pages of the bid, except for un-amended
printed literature, shall be initialed by the person or persons signing the bid.
24.3 The Bidders must submit the qualifying data in one original and one duplicate copy
as required in this Instruction to Bidders in separate envelopes sealed and enclosed
in the envelope submitting proposals, super scribed as under:
QUALIFYING DATA FOR THE SUPPLY AND ERECTION OF
(Name of the Package)
(Specification Number)
24.3.1 The bid shall contain no interlineations, erasures or overwriting except as necessary
to correct errors made by the Bidder, in which case such corrections shall be
initialed by the person or persons signing the bid.
24.4 Bids shall be submitted as under:
Cover-I Earnest Money Deposit (Bid-Security as per the format), as per
relevant clause no.3 of SCC duly signed and Contractor’s covering
Cover-II Qualifying Requirements.
Cover-III Technical Bid
Must contain conditions and schedules of Part-III without prices and Technical Data
Requirement Sheets as per Part-II. (Cover I, II and III will be collectively called
Technical Bid).
25.0 Signature of Bids:
Seal & Signature of Bidder
25.1 The bid must contain the name, residence and place of business of the person or
persons making the bid and must be signed and sealed by the Bidder with his usual
signature. The names of all persons signing should also be typed or printed below
25.2 Bid by a partnership must be furnished with full names of all partners and be signed
with the partnership name, followed by the signature(s) and designation(s) or the
authorized partner(s) or other authorized representative(s).
25.3 Bids by Corporation/Company must be signed with the legal name of the
Corporation/Company by the President/Managing Director or by the Secretary or
other person or persons authorized to bid on behalf of such Corporation/Company
25.4 A bid by a person who affixes to his signature the word ‘President’, ‘Managing
Director’, ‘Secretary’, ‘Agent’ or other designation without disclosing his Principal will
25.5 If it is found that two or more persons who are connected with one another either
financially or as a principal and agent have bid under different names without
disclosing their connection then such bids will be liable for rejection. Satisfactory
evidence of authority of the person signing on behalf of the Bidder shall be
furnished with the bid.
25.6 The Bidder’s name stated on the proposal shall be the exact legal name of the firm.
25.7 Bids not conforming to the above requirements of signing may be disqualified and
26.0 Sealing and marking of bids(No physical submission)
26.1 Cover-I 1. Bid No.
2. Due date for opening
3. Reference of earnest money deposit
Cover-II 1. Bid No.
2. Due date for opening.
3. Qualifying Requirements.
Cover-III 1. Bid No.
2. Due date for opening
3. Technical bid & reference and certificate as per Cl. 17.00 of SCC.
Cover-I, Cover-II & Cover-III shall be individually sealed and super scribed as
indicated above and should be enclosed in the main cover duly sealed and super
scribed as Tender for …………………………………… against Bid No……………
due on…………… containing Cover-I, Cover-II, Cover-III of this tender.
The original Bid and accompanying documents clearly marked “Original” for Cover I,
II & III shall be submitted by the Bidder at the date, time and place specified. In the
event of any discrepancy between online documents and physical documents, the
online documents shall prevail and considered for evaluation.
The Bid shall be submitted by RPAD or through speed post services to the Office of
the CE (Procurement & Contracts) GETCO., Bids submitted should be posted with
due allowance for any postal delay. The Bids received after the Due Date and Time
of opening are liable to be rejected. Telegraphic/Telex/Fax/e-mail Bids shall not be
Seal & Signature of Bidder
26.2 The Bidders shall seal the original and each copy of the bid in an inner and an outer
envelope, duly marking the envelopes as “original” and “copy”.
26.3 a. Addressed to the Owner at the following address:
The Additional Chief Engineer (Procurement & Contracts)
GETCO, Sardar Patel Vidyut Bhavan, Race Course,
b. Bear the name of package bid enquiry number, name of the work and the words.
“DO NOT OPEN BEFORE……………………
26.4 The inner envelope shall indicate the name and address of the Bidder to enable
the bid to be returned unopened in case it is declared “late” or “rejected”.
26.5.1 If the outer envelope is not sealed and marked as required by para 23.2 the Owner
will assume no responsibility for the bid’s misplacement or premature opening.
26.6 The Bid Security conditions must be submitted in a separate sealed envelope.
27.0 Deadline for submission of bids:
27.1 The Bidders have the option of sending the bid by registered post or speed post
submitting the bid in person can not be taken as per prevailing condition of GETCO.
Bids submitted by telex/telegram will not be accepted. No request from any Bidder
to the Owner to collect the proposals from airlines, cargo agent etc. shall be
entertained by the Owner.
27.2.1 Bids must be received by the Owner at the address specified under para 26.3, not
later than the time & date mentioned in the Invitation to Bid.
27.2.2 The Owner may, at its discretion, extend this deadline for the submission of bids by
amending the Bidding Document in which case all rights and obligations on the
Owner and Bidders previously subject to the deadline will thereafter be subject to
the deadline as extended.
28.1 Any bid received by the Owner after the time and date fixed or extended for
submission of bids prescribed by the Owner, will be rejected and not considered for
29.0 Modification and withdrawal of bids:
29.1 The Bidder may modify or withdraw its bid after the bid’s submission provided that
written notice of the modification or withdrawal is received by the Owner prior to the
deadline prescribed for submission of bids.
29.2 The Bidder’s modification or withdrawal notice shall be prepared, sealed, marked
and dispatched in accordance with the provisions of clause 26.0. The envelope
should clearly indicate whether the modification is for the Technical bid or the Price
bid. No bid modifications notice by Telex/Grams/Fax shall be entertained by the
29.3 No bid shall be modified in any manner, whatsoever subsequent to the deadline for
submission of bids.
Seal & Signature of Bidder
29.4 No bid may be withdrawn in the interval between the deadline for submission of bids
and the expiration of the period of bid validity specified by the Bidder on the Bid
Form. Withdrawal/modification of a bid during this interval may result in the Bidder’s
forfeiture of its bid security.
30.0 Information required with the proposal:
30.1 The bids must clearly indicate the name of the manufacturer, the type and/or model
each principal item of equipment proposed to be furnished and erected. The bid
should also contain drawings and descriptive materials indicating general
dimensions, materials from which the parts are manufactured, principles of
operation, the extent of pre-assembly involved, major construction equipment
proposed to be deployed, method of erection and the proposed erection
organizational structure.
30.2 The above information shall be provided by the Bidder in the form of separate
drawings, catalogues, etc. in five copies.
30.3 Any bid not containing sufficient descriptive material to describe accurately the
equipment proposed may be treated as incomplete and hence rejected. Such
descriptive materials and drawings submitted by the Bidder will be retained by the
Owner. Any major departure from these drawings and descriptive material
submitted will not be permitted during the execution of the Contract without specific
written permission of the Owner.
30.4 Oral statements made by the Bidder at any time regarding quality, quantity or
arrangement of the equipment or any other matter will not be considered.
30.5 Standard catalogue pages and other documents of the Bidder may be used in the
to provide additional information and data as deemed necessary by the Bidder.
30.6 The Bidder, along with his Proposal, shall submit a list of recommended erection
equipment and materials which will be required for the purpose of erection of
equipment and materials supplied under the Contract.
30.7 In case the ‘Proposal’ information contradicts specification requirements, the
specification requirements will govern, unless otherwise brought out clearly in the
technical commercial deviation schedule.
BID OPENING AND EVALUATION
31.0 Opening of bids by owner:
31.1 The Owner will open the bids in the presence of Bidder’s representatives who
choose to attend on the date and time mentioned for opening of bids in the
Invitation to Bid or in case any extension has been given thereto, on the extended
bid opening date and time notified to all the Bidders who have purchased the
bidding document. The Bidder’s representative who is present shall sign a register
evidencing their attendance.
31.2 The Bidder’s names, Technical modifications, Bid withdrawal and such other details
as the Owner, at his discretion may consider appropriate, will be announced in the
Technical Bid Opening.
Seal & Signature of Bidder
31.3 The price bids of all the “Techno-Commercial” Responsive Bidders shall be opened
in the presence of representatives (up to two per firm) of such bidders who choose
to be present. The date & time of opening the Price Bid shall be intimated to all such
qualified bidders by Fax/Telex, at least one week in advance besides inviting final
price bid if found appropriate after evaluation of Technical bids.
31.4 The Bidder’s name, lump sum Bid Price, all discounts if any, modifications in the
Bid and any such other details as the Owner, at his discretion, may consider
appropriate, will be announced/ furnished in the Price Bid Opening.
31.5 No electronic recording/transmitting devices will be permitted during Bid opening.
31.6 The technical bid of those bidders will be consider who have submitted EMD cover
with DD for tender fee.
32.0 Purpose of evaluation of bids:
32.1 The Bids received/accepted/opened will be evaluated by the Owner to ascertain the
technical responsiveness of the bid for the complete scope of the proposal, as
covered under these specifications and documents. All technically responsive bids
shall then be examined to determine the LOWEST EVALUATED COMMERCIALLY
AND TECHNICALLY RESPONSIVE BIDS.
32(A) Policy for bids under consideration:
32.A.1 Bids shall be deemed to be under consideration immediately after opening of
Technical Bid and until such time official intimation of award/rejection is made by
the Owner to the Bidders. While the Bids are under consideration, Bidders and/or
their representatives and other interested parties are advised to refrain from
contacting by any means, the owner and/or his employee’s representatives on
the matters related to Bids under consideration.
32.A.2 Clarification of bids:
To assist in the examination evaluation and comparison of Bids the owner may
on his own ask the Bidder for a clarification of its bid. The request for
clarification and the response shall be in writing and no change in the price or
substance of the bid shall be sought, offered or permitted.
Preliminary Examination:
33.1 The Owner will examine the bids to determine whether they are complete, whether
any computational errors have been made, whether required sureties have been
furnished, whether the documents have been properly signed, and whether the bids
are generally in order.
33.2 Arithmetical errors will be rectified on the following basis:
If there is a discrepancy between the unit price and the total price that is obtained
by multiplying the unit price and quantity, the unit price shall prevail and the total
price shall be corrected. If there is a discrepancy between the total bid amount and
the sum of total costs, the latter shall prevail and the total bid amount will be
corrected accordingly. If there is a discrepancy between words and figures, the
amount advantageous to the Owner will prevail. If the Bidder does not accept the
correction of the errors as above, his Bid will be rejected and the amount of Bid
Security will be forfeited. The Bidder should ensure that the prices furnished in
Seal & Signature of Bidder
inconsistency in the prices furnished in the specified prices schedules to be
identified in Bid Form for this purpose, the Owner shall be entitled to consider the
highest price for the purpose of evaluation and for the purpose of award of Contract
use the lowest of the prices in these schedules.
33.3 Prior to the detailed evaluation, the Owner will determine the substantial
responsiveness of each bid to the Bidding Document. For purpose of these Clauses,
a substantially responsive bid is one which conforms to all the terms and conditions
of the Bidding Document without material deviations. A material deviation is one
which affects in any way the prices, quality, quantity or delivery period of the
equipment, completion of works or which limits in any way the responsibilities or
liabilities of the Bidder of any right of the Owner as required in these specifications
and documents. The Owner’s determination of a bid’s responsiveness shall be based
on the contents of the bid itself without recourse to extrinsic evidence.
33.4 A bid determined as not substantially responsive will be rejected by the Owner and
may not subsequently be made responsive by the Bidder by correction of non-
33.5 The Owner may waive any minor informality or non-conformity or irregularity in a bid
which does not constitute a material deviation, provided such waiver does not
prejudice or affect the relative ranking of any Bidder.
34.00 Evaluation of Price Bids:
34.1 Definitions and Meanings:
For the purpose of the evaluation and comparison of bids, the following meanings
and definition will apply: -
a) ‘Bid Price’ shall mean the price quoted by each Bidder in his proposal for the
complete scope of works.
b) ‘Differential Price’ shall mean the summation of the equalizing elements of price
for parameter differential or deficiencies in the equipment and services
determined from the Bidder’s proposal.
c) ‘Cost compensation for Deviations’ shall mean the rupee value of deviations from
the bidding document as determined from the Bidder’s proposal.
d) ‘Evaluated Bid Price’ shall be summation of ‘Bid Price’, ‘Differential Price’ and
‘Cost Compensation for Deviations.’
35.0 Calculation of differential Price & Cost Compensation for Deviations.
The Differential Price to be added to the Bid Price of each bid during evaluation and
comparison shall be derived as under:
Differential Price (DP)=n1F1+n2F2…..+nnFn, where F1, F2…..Fn are the various
factors in Indian Rupees per unit of parameter differential or deficiency in the
equipment and services offered as stipulated in these specifications: n1, n2…nn are
the respective parameter differential or deficiency in the corresponding units to be
determined from the Bidder’s proposal. The above factors and corresponding units
of parameter differential are derived from the Technical Specifications, Data sheets
and/or Special Conditions of Contract.
Seal & Signature of Bidder
Deviations from the Bidding Documents in so far as practicable will be converted to
a Rupee value (D) and from the Bidding Document while evaluating the bids. In
determining the Rupee value of the deviations the Owner will use parameters
consistent with those specified in the specifications and documents and or other
information as necessary and available to the Owner.
35.1 Comparison of Bids
The bids shall be compared on the basis of lump sum prices (i.e., for supply portion
and price for services & civil works to be rendered as quoted by the Bidder) for the
entire scope of the proposal as defined in the Bidding Document.
For comparison purposes all the evaluated bid prices shall be in Indian Rupees as
W = Q + DP + D, Where
W = Total Comparison Price
Q = Bid Price quoted by the bidder in Indian Rupees (Value of equipments/materials
Including taxes and duties plus components of erection cost including civil
engineering works & mandatory spares and other components if any.)
DP = Different price in Indian Rupees calculated as above
D = Cost compensation for deviations calculated as above.
All evaluated bid prices of all the bidders shall be compared among themselves to
determine the lowest evaluated bid and, as a result of this comparison, the lowest bid will
be selected for the award of the Contract.
AWARD OF CONTRACT
36.0 Award Criteria
36.1 The owner will award the contract to the successful Bidder, whose bid has been
determined to be substantially responsive and has been determined as the lowest
evaluated bid, providing further that the Bidder is determined to be qualified to
perform the contract satisfactorily. The Owner shall be the sole judge in this regard.
36.2 In case of award of Contract on a bidder there shall be separate contracts one for
supply of goods, the second for erection & services (and third for civil engineering
works in substations).
36.3 Further, the Owner reserves the right to award separate contracts to two or more
parties in line with the terms and conditions specified in the accompanying
Technical Specifications.
37.0 Owner’s right to accept any bid and to reject any or all bids:
37.1 The Owner reserves the right to accept or reject any bid, and to annual the bidding
process and reject all bids at time prior to award of contract, any without thereby
incurring any liability to the affected Bidder or Bidders or any obligation to inform the
affected Bidder or Bidders of the grounds for the Owner’s action.
38.0 Notification of award:
38.1 Prior to the expiration of the period of bid validity and extended validity period, if
any, the Owner will notify the successful Bidder in writing by registered letter or
cable or telex or FAX, to be confirmed in writing by registered letter, that its bid has
Seal & Signature of Bidder
38.2 The notification of award will constitute the formation of the Contract.
38.3 Upon the successful Bidder’s furnishing of performance guarantee pursuant to
relevant clause 41.0, the Owner will promptly notify each unsuccessful Bidder and
will discharge its bid security, pursuant to Clause 23.0.
39.0 Signing of contract:
39.1 At the same time as the Owner notifies the successful Bidder that his bid has been
accepted, the Owner will send the Bidder the detailed of Award, incorporating all
agreements between the parties.
39.2 Within 15 days of receipt of the detailed of Award, the successful bidder shall sign
the same with date and return it to the Owner along with clear acceptance latter.
39.3 The Bidder will prepare the Contract Agreement and Indemnity Bond as per the
proforma prescribed and the same will be signed within 30 (Thirty) days of
notification of Award.
40.0 Contract Performance Guarantee:
40.1 As a contract performance security, the successful bidder, to whom the work is
awarded, shall be required to furnish a performance guarantee in form of Bank
guarantee from a Public Sector Indian bank/Scheduled, Commercial Bank in the
form to be furnished. The guarantee amount shall be equal to ten percent (10%) of
the Contract price and it shall guarantee the faithful performance of the Contract in
accordance with the terms and conditions specified in these documents and
specifications. the guarantee shall be valid up to 90 days after the end of Warranty
40.2 The Performance Guarantee shall cover additionally the following guarantees to the
a) The successful Bidder guarantees the successful and satisfactory operation of
the equipment furnished and erected under the Contract, as per the
specifications and documents.
b) The successful Bidder further guarantees that the equipment provided by him/his
sub-vendors and installed by him shall be free from all defects in design,
material and workmanship and shall upon written notice from the Owner fully
remedy free of expenses to the Owner such defects as developed under the
normal use of the said equipment within the period of guarantee specified in the
relevant clause of the General Terms and Conditions in the Part-I/Special
Conditions of Contract.
40.3 The Contract Performance Guarantee is intended to secure the performance of the
entire contract. However, it is not to be construed as limiting the damages under
clause entitled “Equipment Performance Guarantee” in Technical Specifications,
Part-II and damages stipulated in other clauses in the Bid documents.
40.4 The performance guarantee will be discharged without any interest at the end of
guarantee period, unless otherwise specified in Special Conditions of Contract.
41.0 LANGUAGE AND MEASURES
Seal & Signature of Bidder
All documents pertaining to the Contract including specifications, schedules,
notices, correspondences, operating and maintenance instructions, drawings or any
other writing shall be written in English language. The Metric System of
measurement shall be used exclusively in the Contract.
42.0 CONTRACT DOCUMENTS
42.1 The term Contract Documents shall mean and include the following which shall be
deemed to form an integral part of the Contract:
a) Invitation to Bid including letter forwarding the Bidding Documents,
Instructions to Bidders, General Terms and Conditions of Contract and all
other documents included under Volume- I and the Special Conditions of
b) Specifications of the equipment to be furnished and erected under the
Contract as brought out in the accompanying Technical Specifications.
c) Contractor’s Bid Proposal and the documents attached there to including the
letters of clarifications thereto between the Contractor and the Owner prior to
the Award of Contract except to the extent of repugnancy.
d) All the materials, literature, data and information of any sort given by the
Contractor along with his bid, subject to the approval of the Owner
e) Letter of Award and any agreed variations of the conditions of the documents
and special terms and conditions of Contract, if any.
42.2 In the event of any conflict between the above mentioned documents the matter
shall be referred to the Engineer whose decision shall be considered as final and
binding upon the parties.
43.0 USE OF CONTRACT DOCUMENTS AND INFORMATION
43.1 The Contractor shall not, without the Owner’s prior written consent, disclose the
Contract, or any provision thereof, or any specification, plan, drawing, pattern,
sample or information furnished by or on behalf of the Owner in connection
therewith, to any person other than a person employed by the Contractor in the
performance of the Contract. Disclosure to any such employed person shall be
made in confidence and shall extend only so far as may be necessary for the
purpose of such performance.
43.2 The Contractor shall not, without the Owner’s prior written consent, make use of any
document or information enumerated in various Contract documents except for the
purpose of performing the Contract.
43.3 The Contractor shall not communicate or us in advertising, publicity, sales releases
or in any other medium, photographs or other reproduction of the Works under this
Contract, or descriptions of the site, dimensions, quantity, quality or other
information, concerning the works unless prior written permission has been
obtained from the Owner.
43.4 Any document, other than the Contract itself, enumerated in various Contract
documents shall remain the property of the Owner and shall be returned (in all
copies) to the Owner on completion of the Contractor’s performance under the
Contract if so required by the Owner.
44.0 CONSTRUCTION OF THE CONTRACT
Seal & Signature of Bidder
44.1 Notwithstanding anything stated elsewhere in the bid documents, the Contract to be
entered into will be treated as a composite contract for Supply and Erection under
the category of Works Contract. However, Separation of the Contract into Supply of
Goods and Services, is only for convenience and better economic management and
for the ease of Accountancy but the entire Contract, is to be assessed under GST
Law, as composite supply under the category of Works Contract, which is, as per
the provisions of Section 2(30), read with, Section 2(119), further read with,
Paragraph 6(a) of the Schedule II to the CGST Act, 2017 or SGST Act, 2017 and
similar provisions, applicable under the UTGST Act, 2017 and the IGST Act,
and the entire activity, would be subjected to levy of Tax, at the rate of 9% CGST +
9% SGST or 18% IGST, under the GST Law. However, Classification Codes for
different segments or portions of the Works Contract, may be specified separately,
in the Supplies, with a final common Classification Code of Works Contract Service.
44.2 In case of divisible supply and erection Contract, or where the Owner hands over his
equipment to the Contractor for executing, then the Contractor shall at the time of
taking delivery of the equipment/dispatch documents be required to execute an
Indemnity Bond in favor of the Owner in the form acceptable to the GETCO for
keeping the equipment in safe custody and to utilize the same exclusively for the
purpose of the said Contract. Samples of proforma for the Indemnity Bond will be
furnished during award of Contract.
44.3 The Contract shall in all respects be construed and governed according to Indian
44.4 It is clearly understood that the total consideration for the Contract(s) has been
broken up into various components only for the convenience of payment under the
Contract(s) and for the measurement of deviations or modifications under the
45.0 JURISDICTION OF CONTRACT
45.1 The laws applicable to the Contract shall be the laws in force in India. The Courts of
Vadodara shall have exclusive jurisdiction in all matters arising under this Contract.
46.0 EXECUTION OF CONTRACT:
46.1 The Owner, after the issue of the Letter of Award to the Contractor, will send one
copy of the final agreement to the Contractor for his scrutiny and approval.
46.2 The Agreement, unless otherwise agreed to, shall be signed within 30 days of the
acceptance of the Letter of Award, at the office the Owner at Vadodara on a date
and time to be mutually agreed. The Contractor shall provide for signing of the
Contract, Performance Guarantee, appropriate power of attorney and other
requisite materials. In case the Contract is to be signed beyond the stipulated time,
the Bid Guarantee submitted with the Proposal will have to be extended
46.3 The Agreement will be signed in copies to be specified and the Contractor shall be
provided with one signed original and the rest will be retained by the Owner.
46.4 The Contractor shall provide free of cost to the Owner all the Engineering data,
drawings, and descriptive materials submitted with the bid, to form a part of the
Contract immediately after issue of Letter of Award
46.5 Subsequent to signing of the Contract, the Contractor at his own cost shall provide
the Owner with copies of agreement within fifteen (15) days after the signing of the
Seal & Signature of Bidder
47.0 ENFORCEMENT OF TERMS
47.1 The failure of either party to enforce at any time any of the provisions of this Contract
or any rights in respect thereto or to exercise any option therein provided, shall in no
way be construed to be a waiver of such provisions, rights or options or in anyway to
affect the validity of the Contract. The exercise by either party of any of its rights
herein shall not preclude or prejudice either party from exercising the same or any
other right it may have under the Contract.
48.0 COMPLETION OF CONTRACT
48.1 Unless otherwise terminated under the provisions of any other relevant clause, this
Contract shall be deemed to have been completed on the expiry of the guarantee
period as provided for under the clause entitled ‘Guarantee’ in this section of the
GUARANTEES & LIABILITIES
49.0 TIME – THE ESSENCE OF CONTRACT
49.1 The time and the date of completion of the Contract as stipulated in the Contract by
the Owner without or with modifications, if any, and so incorporated in the Letter of
Award, shall be deemed to be the essence of the Contract. The Contractor shall so
organize his resources and perform his work as to complete it not later than the
date agreed to.
49.2 The Contractor shall submit a detailed PERT network/bar chart within the time
frame agreed consisting of adequate number of activities covering various key
phases of the work such as design, procurement, manufacturing, shipment and field
erection activities within fifteen (15) days of the date of Notification of Award. This
network shall also indicate the interface facilities to be provided by the Owner and
the dates by which such facilities are needed. The Contractor shall discuss the
network so submitted with the Owner and the agreed network shall form part of the
Contract documents. During the performance of the Contract, if in the opinion of the
Engineer, proper progress is not maintained, suitable changes shall be made in the
Contractor’s operations to ensure proper progress without any cost implication to
the Owner. The interface facilities to be provided by the Owner in accordance with
the agreed network shall also be reviewed while reviewing the progress of the
49.3 Based on the above agreed network/bar chart fortnightly reports shall be submitted
by the Contractor as directed by the Engineer.
49.4 Subsequent to the finalization of the network, the Contractor shall make available to
the Engineer a detailed manufacturing programme in line with the agreed Contract
network. Such manufacturing programme shall be reviewed, updated and submitted
to the Engineer once every two months thereafter.
49.5 The above bar charts/manufacturing programme shall be compatible with the
Owner’s computer environment and furnished to the Owner on such media as may
be desired by the Owner.
50.0 EFFECTIVENESS OF CONTRACT
Seal & Signature of Bidder
The Contract shall be considered as having come into force from the date of the
notification of award unless otherwise provided in the notification of award.
51.0 PENALTY FOR DELAY
51.1 If the Contractor fails to successfully complete the commissioning within the time
fixed under the Contract, the Contractor shall pay to the Owner as penalty a sum
specified for each specified period of delay. The details of such penalty are brought
out in the accompanying Special Conditions of Contract (SCC).
51.2 Equipment and materials will be deemed to have been delivered only when all its
components, parts are also delivered. If certain components are not delivered in
time the equipment and materials will be considered as delayed until such time the
missing parts are also delivered.
51.3 The total amount of penalty for delay under the Contract will be subject to a
51.3 The total amount of penalty for delay under the Contract will be subject to a
maximum of 10% of the Contract prices plus GST as applicable detailed in the
Special Conditions of Contract (SCC).
52.1 The Contractor shall warrant that the equipment will be new, unused and in
accordance with the Contract documents and free from defects in material and
workmanship for a period of twenty-four (24) calendar months commencing
immediately upon the satisfactory commissioning. The Contractor’s liability shall be
limited to the replacement of any defective parts in the equipment of his own
manufacture or those of his Sub-Contractors under normal use and arising solely
from faulty design, materials and/or workmanship provided always that such
defective parts are repairable at the site and are not in meantime essential in the
commercial use of the equipment. Such replaced/defective parts shall be returned
to the Contractor unless otherwise arranged. No repairs or replacement shall
normally be carried out by the Engineer when the equipment is under the
supervision of the Contractor’s Supervisory Engineer.
52.2 In the event of any emergency where in the judgment of the Engineer, delay would
cause serious loss or damages, repairs or adjustment may be made by the
Engineer or a third party chosen by the Engineer without advance notice to the
Contractor and the cost of such work shall be paid by the Contractor. In the event
such action is taken by the Engineer, the Contractor will be notified promptly and he
shall assist wherever possible in making necessary corrections. This shall not
relieve the Contractor of his liabilities under the terms and conditions of the
52.3 If it becomes necessary for the Contractor to replace or renew any defective
portions of the works the provision of this clause shall apply to portion of the works
so replaced or renewed until the expiry of twelve (12) months from the date of such
replacement or renewal. If any defects are not remedied within a reasonable time,
the Engineer may proceed to do the work at the Contractor’s risk and cost but
without prejudice to any other rights which the Owner may have against the
Contractor in respect of such defects.
52.4 The repaired or new parts will be furnished and erected free of cost by the
Contractor. If any repair is carried out on his behalf at the site, the Contractor shall
bear the cost of such repairs.
52.5 The cost of any special or general overhaul rendered necessary during the
maintenance period due to defects in the equipment or defective work carried out by
the Contractor, the same shall be borne by the Contractor.
Seal & Signature of Bidder
52.6 The acceptance of the equipment by the Engineer shall in no way relieve the
Contractor of his obligations under this clause
52.7 In the case of those defective parts, which are not repairable at site but are
essential for the commercial operation of the equipment, the Contractor and the
Engineer shall mutually agree to a programme of replacement or renewal, which will
minimize interruption to the maximum extent in the operation of the equipment.
52.8 At the end of the guarantee period, the Contractor’s liability ceases except for latent
defects. For latent defects, the Contractor’s liability shall remain till the end of
years from the date of completion of guarantee period.
In respect of goods supplied by Sub-Contractors to the Contractor where a longer
guarantee (more than 24 months) is provided by such Sub-Contractor, the Owner
shall be entitled to the benefits of such longer guarantee.
52.9 The provisions contained in this clause will not be applicable:
a) If the Owner has not used the equipment according to generally approved industrial
practice and in accordance with the conditions of operations specified and in
accordance with operating manuals, if any.
b) In cases of normal wear and tear of the parts to be specifically mentioned by the
Contractor in the offer.
53.0 TAXES, PERMITS & LICENCES
The Contractor shall be liable and pay all non-Indian taxes, duties, levies lawfully
assessed against the Owner or the Contractor in pursuance of the Contract. In
addition, the Contractor shall be responsible for payment of all Indian duties
including GST, levies and taxes lawfully assessed against the Contractor for his
personal income & property only.
54.0 REPLACEMENT OF DEFECTIVE PARTS AND MATERIALS
54.1 If during the performance of the Contract, the Engineer shall decide and inform in
writing to the Contractor that the Contractor has manufactured any equipment,
material or part of equipment unsound and imperfect or has furnished any
equipment inferior to the quality specified, the Contractor on receiving details of
such defects or deficiencies shall at his own expense within seven (7) days of his
receiving the notice, or otherwise, within such time as may be reasonably necessary
for making it good, proceed to alter, reconstruct or remove such works and furnish
fresh equipment/materials upto the standards of the specifications. In case, the
Contractor fails to do so, the Engineer may on giving the Contractor seven (7) days
notice in writing of his intentions to do so, proceed to remove the portion of the
works so complained of and at the cost of the Contractor perform all such Works or
furnish all such equipment/ material provided that nothing in this clause shall be
deemed to deprive the Owner of or affect any rights under the Contract which the
Owner may otherwise have in respect of such defects and deficiencies.
54.2 The Contractor’s full and extreme liability under this clause shall be satisfied by the
payment to the Owner of extra cost, of such replacement procured including
erection as provided for in the Contract, such extra cost being the ascertained
difference between the price paid by the Owner for such replacements and the
Contract Price by portion for such defective equipment/materials/works and
repayments of any sum paid by he Owner to the Contractor in respect of such
defective equipment/material. Should the Owner not so replace the defective
equipment/materials the Contractor’s extreme liability under this clause shall be
Seal & Signature of Bidder
limited to repayment of all sums paid by the Owner under the Contract for such
defective equipment/materials.
55.0 PATENT RIGHTS AND ROYALTIES
Royalties and fees for patents covering materials, articles, apparatus, devices,
equipment or processes used in the works shall be deemed to have been included
in the Contract Price. The Contractor shall satisfy all demands that may be made at
any time for such royalties or fees and he alone shall be liable for any damages or
claims for patent infringements and shall keep the Owner indemnified in that regard.
The Contractor shall, at his own cost and expense, defend all suits or proceedings
that may be instituted for alleged infringement of any patents involved in the Works,
and, in case of an award of damages, the Contractor shall pay for such award. In
the event of any suit or other proceedings instituted against the Owner, the same
shall be defended at the cost and expense of the Contractor who shall also
satisfy/comply with any decree, order or award made against the Owner. But it
shall be understood that no such machine, plant, work, material or thing has been
used by the Owner for any purpose or any manner other than that for which they
have been furnished and installed by the Contractor and specified under these
specifications. Final payment to the Contractor by the Owner will not be made while
any such suit or claim remains unsettled. In the event any apparatus or equipment,
or any part thereof furnished by the Contractor, is in such suit or proceedings held
to constitute infringement, and its use is enjoined, the Contractor shall at his option
and at his own expense, either procure for the Owner, the right to continue the use
of said apparatus, equipment or part thereof, replace it with non-infringing apparatus
or equipment or modify it, so it becomes non-infringing.
56.0 DEFENCE OF SUITS
If any action in court is brought against the Owner or Engineer or an officer or agent
of the Owner, for the failure, omission or neglect on the part of the Contractor to
perform any acts, matters, covenants or things under the Contract, or for damage or
injury caused by the alleged omission or negligence on the part of the Contractor,
his agents, representatives or his Sub-Contractors, or in connection with any claim
based on lawful demands of Sub-Contractors, workmen, suppliers or employees,
the Contractor shall in all such cases indemnify and keep the Owner, and the
Engineer and/or his representative, harmless from all losses, damages, expenses
or decrees arising of such action.
57.0 LIMITATION OF LIABILITIES
The final payment by the Owner in pursuance of the Contract shall mean the
release of the Contractor from all his liabilities under the Contract. Such final
payment shall be made only at the end of the Guarantee/Warranty period, and till
such time as the Contractual liabilities and responsibilities of the Contractor, shall
prevail. All other payments made under the Contract shall be treated as on-account
58.0 ENGINEER’S DECISION
58.1 In respect of all matters which are left to the decision of the Engineer including the
granting or with-holding of the certificates, the Engineer shall, if required to do so by
the Contractor, give in writing a decision thereon.
58.2 If, in the opinion of the Contractor, a decision made by the Engineer is not in
accordance with the meaning and intent of the Contract, the Contractor may file with
the Engineer, within fifteen (15) days after receipt of the decision, a written objection
to the decision.
Seal & Signature of Bidder
Failure to file an objection within the allotted time will be considered as an
acceptance of the Engineer’s decision and the decision shall become final and
58.3 The Engineer’s decision and the filing of the written objection thereto shall be a
condition precedent to the right to request arbitration. It is the intent of the
Agreement that there shall be no delay in the execution of the works and the
decision of the Engineer as rendered shall be promptly observed.
59.0 POWER TO VARY OR OMIT WORK
59.1 No alterations, amendments, omissions, suspensions or variations of the Works
(hereinafter referred to as ‘variation’) under the Contract as detailed in the Contract
Documents, shall be made by the Contractor except as directed in writing by the
Engineer, but the Engineer shall have full powers subject to the provisions
hereinafter contained, from time to time during the execution of the Contract, by
notice in writing to instruct the Contractor to make such variation without prejudice
to the Contract. The Contractor shall carry out such variation and be bound by the
same conditions as far as applicable as though the said variations occurred in the
Contract Documents. If any suggested variations would, in the opinion of the
Contractor, if carried out, prevent him from fulfilling any of his obligations or
guarantees under the Contract, he shall notify the Engineer thereof in writing and
the Engineer shall decide forthwith whether or not, the same shall be carried out
and if the Engineer confirms his instructions, the Contractor’s obligations and
guarantees shall be modified to such an extent as may be mutually agreed. Any
agreed difference in cost occasioned by any such variation shall be added to or
deducted from the Contract Price as the case may be.
59.2 In the event of Engineer requiring any variation, a reasonable and proper notice
shall be given to the Contractor to enable him to work his arrangement accordingly,
and in cases where goods or materials are already prepared or any design,
drawings or pattern made or work done as per the contract requires to be altered, a
reasonable and agreed sum in respect thereof shall be paid to the Contractor.
59.3 In any case in which the Contractor has received instructions from the Engineer as
to the requirement of carrying out the alterations or additional or substituted work
which either then or later on, will in the opinion of the Contractor, involve a claim for
additional payment, the Contractor shall immediately and in no case later than thirty
(30) days, after receipt of the instructions aforesaid and before carrying out the
instructions, advise the Engineer to that effect. But the Engineer shall not become
liable for payment of any charges in respect of any such variations, unless the
instructions for the performance of the same shall be confirmed in writing by the
59.4 If any variation in the Works results in reduction of Contract Price, the parties shall
agree, in writing, so to the extent of any change in the price, before the Contractor
proceeds with the change.
59.5 In all the above cases, in the event of a disagreement as to the reasonableness of
the said sum, the decision of the Engineer shall prevail.
59.6 Notwithstanding anything stated above in this clause, the Engineer shall have the
full power to instruct the Contractor, in writing, during the execution of the Contract
to vary the quantities of the items or groups of items in accordance with the
provisions of clause entitled ‘Change of Quantity’ in section GCC of this Volume-I.
The Contractor shall carry out such variations and be bound by the same conditions
as though the said variations occurred in the Contract Documents. However, the
Seal & Signature of Bidder
Contract Price shall be adjusted at the rates and the prices provided for the original
quantities in the Contract.
60.0 ASSIGNMENT AND SUB-LE TTING OF CONTRACT
60.1 The Contractor may, after informing the Engineer and getting his written approval,
assign or sub-let the Contract or any part thereof other than for raw material, for
minor details or for any part of the plant for which makes are identified in the
Contract. Suppliers of the equipment not identified in the Contract or any change in
the identified suppliers shall be subjected to approval by the Engineer. The
experience list of equipment vendors under consideration by the Contractor for this
Contract shall be furnished to the Engineer for approval prior to procurement of all
such items/equipment. Such assignment/sub-letting shall not relieve the Contractor
of any obligation, duty or responsibility under the Contract. Any assignment as
above, without prior written approval of Engineer, shall be void.
60.2 For components/equipment procured by the Contractor for the purposes of the
Contract, after obtaining the written approval of the Owner, the Contractor’s
purchase specifications and enquiries shall call for quality plan to be submitted by
the suppliers along with their Proposals. The quality plans called for from the
Vendors shall set out, during the various stages of manufacture and installation, the
quality practices and procedures followed by the Vendors’ quality control
organization, the relevant reference document/standard used, acceptance level,
inspection documentation raised, etc. Such quality plans of the successful vendors
shall be discussed and finalized in consultation with the Engineer and shall form a
part of the Purchase Order/Contract between the Contractor and the Vendor.
Within three weeks of the release of the Purchase Orders/Contracts for such bought
out items/components a copy of the same without price details but together with
detailed purchase specifications, quality plans and delivery conditions shall be
furnished to the Engineer by the Contractor.
61.0 CHANGE OF QUANTITY
61.1 During the execution of the Contract, the Owner reserves the right to increase or
decrease the quantities of items under the Contract but without any change in unit
price or other terms & conditions. Such variations unless otherwise specified in the
accompanying Special Conditions of Contract and/or Technical Specifications, shall
not be subjected to any limitation for the individual items but the total variations in
all such items under the Contract shall be limited to a 30% (Thirty Percent) of
the Contract price as specified in the Special Conditions of Contract.
61.2 The Contract price shall accordingly be adjusted based on the unit rates available in
the Contract for the change in quantities as above. The base unit rates, as
identified in the Contract shall however remain constant during the currency of the
Contract, except as provided for in Clause 33.0 below. In case the unit rates are
not available for the change in quantity, the same shall be subjected to mutual
62.0 PACKING, FORWARDING AND SHIPMENT
62.1 The Contractor, wherever applicable, shall after proper painting, pack and crate all
equipment in such a manner as to protect them from deterioration and damage
during rail and road transportation to the Site and storage at the Site till the time of
erection. The Contractor shall be held responsible for all damages due to improper
62.2 The Contractor shall notify the Owner of the date of each shipment from his works,
and the expected date of arrival at the Site for the information of the Owner.
Seal & Signature of Bidder
62.3 The Contractor shall also give all shipping information concerning the weight, size
and content of each packing including any other information the Owner may require.
62.4 The following documents shall be sent by registered post to the Owner within three
days from the date of shipment, to enable the Owner to make progressive payments
to the Contractor.
Application for payment in the standard format of the Owner
Pre-dispatch clearance certificate, if any
Test Certificate, wherever applicable
Insurance Certificate
62.5 The Contractor shall prepare detailed packing list of all packages and containers,
bundles and loose materials forming each and every consignment dispatched to
The Contractor shall further be responsible for making all necessary arrangements
for loading, unloading and other handling right from his works up to the Site and
also till the equipment is erected, tested and commissioned. He shall be solely
responsible for proper storage and safe custody of all equipment.
63.0 COOPERATION WITH OTHER CONTRACTORS AND CONSULTING
The Contractor shall agree to cooperate with the Owner’s other Contractors and
Consulting Engineers and freely exchange with them such technical information as
is necessary to obtain the most efficient and economical design and to avoid
unnecessary duplication of efforts. The Engineer shall be provided with three
copies of all correspondence addressed by the Contractor to other Contractors and
Consulting Engineers of the Owner in respect of such exchange of technical
information, wherever needed.
64.0 NO WAIVER OF RIGHTS
Neither the inspection by the Owner or the Engineer or any of their officials,
employees, or agents nor any order by the Owner or the Engineer for payment of
money or any payment for or acceptance of, the whole or any part of the Works by
the Owner or the Engineer, nor any extension of time, nor any possession taken by
the Engineer shall operate as a waiver of any provision of the Contract, or of any
power herein reserved to the Owner or any right to damages herein provided nor
shall any waiver of any breach in the Contract be held to be a waiver of any other or
subsequent breach.
65.0 CERTIFICATE NOT TO AFFECT RIGHT OF OWNER AND LIABILITY OF THE
No interim payment certificate of the Engineer, nor any sum paid on account by the
Owner, nor any extension of time for execution of the Works granted by the
Engineer shall affect or prejudice the rights of the Owner against the Contractor or
relieve the Contractor of his obligation for the due performance of the Contract, or
be interpreted as approval of the Works done or of the equipment furnished and no
certificate shall create liability for the Owner to pay for alterations, amendments,
variations or additional works not ordered, in writing , by the Engineer or discharge
the liability of the Contractor for the payment of damages whether due, ascertained,
or certified or not or any sum against the payment of which he is bound to
Seal & Signature of Bidder
indemnify the Owner, nor shall any such certificate nor the acceptance by him of
any sum paid on account or otherwise affect or prejudice the rights of the Owner
against the Contractor.
66.0 PROGRESS REPORTS
During the various stages of the work in pursuance of the Contract, the Contractor
shall at his own cost submit periodic progress reports as may be reasonably
required by the Engineer with such materials as, charts, net-works, photographs,
test certificates, etc. Such progress reports shall be in the form and size as may be
required by the Engineer.
67.0 TAKING OVER
Upon successful completion of all the tests to be performed at Site on equipment
furnished and erected by the Contractor, the Engineer shall issue to the Contractor
a Taking Over Certificate as a proof of the final acceptance of the equipment. Such
certificate shall not unreasonably be withheld nor will the Engineer delay the
issuance thereof on account of minor omissions or defects which do not affect the
commercial operation and/or cause any serious risk to the equipment. Such
certificate shall not relieve the Contractor of any of his obligations which otherwise
survive, by the terms and conditions of the Contract after issue of such certificate.
CONTRACT SECURITY AND PAYMENTS
68.0 CONTRACT PERFORMANCE GUARANTEE
The Contractor shall furnish Contract Performance Guarantee(s) for the proper
fulfillment of the Contract in the prescribed form within fifteen (15) days of “issue of
LOA”. The performance guarantee(s) shall be as per terms prescribed.
69.1 The payment to the Contractor for the performance of the works under the Contract
will be made by the Owner as per the guidelines and conditions specified herein. All
payments made during the Contract shall be on account payments only. The final
payment will be made on completion of all Works and on fulfillment by the
Contractor of all his liabilities under the Contract.
69.2 Currency of Payment
All payments under the Contract shall be in Indian Rupees only.
Payment terms will be as prescribed in the special conditions of contract and on
fulfillment of conditions specified thereof.
69.4 Welfare Cess
The modality of payment/ reimbursement of welfare cess will be as under.
On receipt of A/T, the contractor / bidder will get them registered under Welfare
Cess Act and submit the documentary evidence to the concern office.
Before release of payment of first R.A.Bill, the contractor has to submit the
documentary evidence of registration. Only thereafter, the bill will be processed for
Before release of payment of subsequent R.A.Bills, the contractor has to submit the
documentary evidence of payment of welfare cess of previous R.A.Bill.
Seal & Signature of Bidder
Before release of payment of Final Bill, the contractor has to submit the
documentary evidence of payment of welfare cess of previous R.A.Bill as well as
the final bill.
If the R.A.Bill happens to be first and final bill, then before release of payment,
contractor has to submit documentary evidence of registration under Welfare Cess
Act and evidence of payment of welfare cess.
The welfare cess shall be reimbursed to the contractor on submission of copy of
documentary evidence of payment by observing due formalities.
70.0 Payment Schedule
The Contractor shall prepare and submit to the Engineer for approval, a break up of
the Contract Price. This Contract Price break-up shall be interlinked with the agreed
detailed PERT network of the Contractor setting forth his starting and completion
dates for the various key phases of Works prepared as per conditions. Any payment
under the Contract shall be made only after the Contractor’s price break up is
approved by the Engineer. The aggregate sum of the Contractor’s price break up
shall be equal to the lump sum Contract Price. A price breakup over valuing those
items of supply which will be shipped first will not be accepted.
70.1 Application for Payment
70.2 The Contractor shall submit application for the payment in the prescribed proforma
of the Owner. Proforma for application for payment will be as prescribed.
70.3 Each such application shall state the amount claimed and shall set forth in detail, in
the order of the Payment Schedule, particulars of the Works including the Works
executed at Site and of the equipment shipped/brought on to the site pursuant to
the Contract upto the date mentioned in the application and for the period covered
since the last preceding certificate, if any.
70.4 Every interim payment certificate shall certify the Contract value of the Works
executed upto the date mentioned in the application for the payment certificate,
provided that no sum shall be included in any interim payment certificate in respect
of the works that, according to the decision of the Engineer, does not comply with
70.5 Mode of Payment
Payment due on dispatch of equipment shall be made by the Owner through
Owner’s Bank or directly to the Contractor as per the payment schedule.
70.6 The payment of test charges, if any, payment, taxes and duties (whenever
admissible) inland transportation (including port handling), insurance and the
erection portion of the Works shall be made direct to the Contractor by the Owner.
70.7 All payments under the Contract shall be made as stipulated in the Special
Conditions of Contract after signing the Contract Agreement. The payments linked
with the dispatch of materials shall only be made after production of all dispatch
documents as specified in the relevant Contract conditions which will interalia
include the Material Inspection Clearance Certificate issued by the Owner.
Progressive payments linked with erection shall only be made after the issue of
certificates by the Engineer, one for the quantum of work completed and the other
Seal & Signature of Bidder
for the successful completion of quality check points involved in the quantum of
70.8 Inland Transportation & Insurance
Inland transportation (including port handling) and inland insurance charges shall be
paid to the Contractor on pro-rata to the value of the equipment received at site and
on production of the invoices by the Contractor. However, wherever equipment wise
inland transportation charges have been called for in the ‘Bid Proposal Sheets’ and
have been furnished by the Contractor, the payment of inland transportation
charges shall be made after receipt of equipment at site based on the charges thus
identified by the Contractor in his Proposal and incorporated in the Contract. The
aggregate of all such pro-rata payments shall however not exceed the total amounts
aggregate of all such pro-rata payments shall however not exceed the total amounts
quoted by the Bidder in his bid and incorporated in the Contract.
71.0 DEDUCTIONS FROM CONTRACT PRICE
All costs, damages or expenses which the Owner may have paid, for which under
the Contract the Contractor is liable, or any other retention award will be claimed by
the Owner. All such claims shall be billed by the Owner to the Contractor regularly
as and when they fall due. Such bills shall be supported by appropriate and certified
vouchers or explanations, to enable the Contractor to properly identify such claims.
Such claims shall be paid by the Contractor within thirty (30) days of the receipt of
the corresponding bills and if not paid by the Contractor within the said period, the
Owner may then deduct the amount, from any monies due or becoming due by him
to the Contractor under the Contract or may be recovered by sections of Law or
RISK DISTRIBUTION
72.0 TRANSFER OF TITLE
72.1 Transfer of title in respect of equipment and materials supplied by the Contractor to
GETCO pursuant to the terms of the Contract shall pass on to GETCO with
negotiation of dispatch documents.
72.2 This Transfer of Title shall not be construed to mean the acceptance and the
consequent “Taking Over” of equipment and materials. The Contractor shall
continue to be responsible for the quality and performance of such equipment and
materials and for their compliance with the specifications until “Taking Over” and the
fulfillment of guarantee provisions of this Contract.
72.3 This Transfer of Title shall not relieve the Contractor from the responsibility for all
risks of loss or damage to the equipment and materials as specified under the
clause entitled “Insurance” of this Section.
73.1 The Contractor at his cost shall arrange, secure and maintain all insurance as may
be pertinent to the Works and obligatory in terms of law to protect his interest and
interests of the Owner against all perils detailed herein. The form and the limit of
such insurance as defined herein together with the under-writer in each case shall
be acceptable to the Owner. However, irrespective of such acceptance, the
responsibility to maintain adequate insurance coverage at all time during the period
of Contract shall be of Contractor alone. The Contractor’s failure in this regard shall
not relieve him of any of his contractual responsibilities and obligations. The
insurance covers to be taken by the Contractor shall be in the joint name of the
Owner and the Contractor. The Contractor shall, however, be authorized to deal
Seal & Signature of Bidder
directly with Insurance Company or Companies and shall be responsible in regard
to maintenance of all insurance covers. Further the insurance should be in freely
convertible currency.
73.2 Any loss or damage to the equipment during handling, transportation, storage,
erection, putting into satisfactory operation and all activities to be performed till the
successful completion of commissioning of the equipment shall be to the account of
the Contractor. The Contractor shall be responsible for preference of all claims and
make good the damages or loss by way of repairs and/or replacement of the
equipment, damaged or lost. The transfer of title shall not in any way relieve the
Contractor of the above responsibilities during the period of Contract. The
Contractor shall provide the Owner with copy of all insurance policies and
documents taken out by him in pursuance of the Contract. Such copies of
documents shall be submitted to the Owner immediately after such insurance
coverage. The Contractor shall also inform the Owner in writing at least sixty (60)
days in advance regarding the expiry/cancellation and/or change in any of such
documents and ensure revalidation, renewal etc., as may be necessary well in time.
73.3 The perils required to be covered under the insurance shall include, but not be
limited to fire and allied risks, miscellaneous accidents (erection risks) workman
compensation risks, loss or damage in transit, theft, pilferage, riot and strikes and
malicious damages, civil commotion, weather conditions, accidents of all kinds, etc.
The scope of such insurance shall be adequate to cover the
replacement/reinstatement cost of the equipment for all risks upto and including
delivery of goods and other costs till the equipment is delivered at Site. The
insurance policies to be taken should be on replacement value basis and/or
incorporating escalation clause. Notwithstanding the extent of insurance cover and
the amount of claim available from the underwriters, the Contractor shall be liable to
make good the full replacement/rectification value of all equipment/materials and to
ensure their availability as per project requirements.
73.4 All costs on account of insurance liabilities covered under the Contract will be on
Contractor’s account and will be included in Contract Price, However, the Owner
may from time to time, during the pendency of the Contract, ask the Contractor in
writing to limit the insurance coverage, risks and in such a case, the parties to the
Contract will agree for a mutual settlement, for reduction in Contract price to the
extent of reduced premia amount. The Contractor, while arranging the insurance
shall ensure to obtain all discounts on premia which may be available for higher
volume or for reason of financing arrangement of the project.
73.5 The clause entitled ‘Insurance’ under the section ECC of this Volume-I, covers the
additional insurance requirements for the portion of the works to be performed at
73.6 Special Conditions of Contract details out the various insurance liabilities.
74.0 LIABILITY FOR ACCIDENTS AND DAMAGES
Under the Contract, the Contractor shall be responsible for loss or damage to the
plant until the successful completion of commissioning as defined else where in the
75.0 DELAYS BY OWNER OR HIS AUTHORISED AGENTS
75.1 In case the Contractor’s performance is delayed due to any act of omission on the
part of the Owner or his authorized agents, then the Contractor shall be given due
extension of time for the completion of the Works, to the extent such omission on
Seal & Signature of Bidder
the part of the Owner has caused delay in the Contractor’s performance of the
Regarding reasonableness or otherwise of the extension of time, the decision of the
Engineer shall be final.
75.2 In addition, the Contractor shall be entitled to claim demonstrable and reasonable
compensation if such delays have resulted in any increase in cost. The Owner shall
examine the justification for such a request for claim and if satisfied, the extent of
compensation shall be mutually agreed depending upon the circumstances at the
time of such an occurrence.
76.0 DEMURRAGE, WHARF AGE, ETC.
All demurrage, wharf age and other expenses incurred due to delayed clearance of
the material or any other reason shall be to the account of the Contractor.
77.0 FORCE MAJEURE
77.1 Force majeure is herein defined as any cause which is beyond the control of the
Contractor or the Owner as the case may be, which they could not foresee or with a
reasonable amount of diligence could not have foreseen and which substantially
affects the performance of the Contract, such as:
a. Natural phenomena, including but not limited to floods, droughts, earthquakes
b. Acts of any Government, domestic or foreign, including but not limited to war,
declared or undeclared, priorities, guarantees, and embargoes.
Provided either party shall within fifteen (15) days from the occurrence of such a
cause notify the other in writing of such causes.
77.2 The Contractor or the Owner shall not be liable for delays in performing his
obligations resulting from any force majeure cause as referred to and/or defined
The date of completion will, subject to hereinafter provided, be extended by a
reasonable time even though such cause may occur after Contractor’s performance
of obligation has been delayed due to other causes.
78.0 SUSPENSION OF WORK
78.1 The Owner reserves the right to suspend and reinstate execution of the whole or
any part of the Works without invalidating the provisions of the Contract. Orders for
suspension or reinstatement of the Works will be issued by the Engineer to the
Contractor in writing. The time for completion of the works will be extended for a
period equal to duration of the suspension.
78.2 Any necessary and demonstrable cost incurred by the Contractor as a result of such
suspension of the works will be paid by the Owner, provided such costs are
substantiated to the satisfaction of the Engineer. The Owner shall not be
responsible for any liabilities if suspension or delay is due to some default on the
part of the Contractor or his Sub-Contractor.
79.0 CONTRACTOR`S DEFAULT
Seal & Signature of Bidder
79.1 If the Contractor shall neglect to execute the works with due diligence and
expedition or shall refuse or neglect to comply with any reasonable order given to
him, in writing by the engineer in connection with the works or shall contravene the
provisions of the contract, the Owner may give notice in writing to the Contractor to
make good the failure, neglect or contravention complained of. Should the
contractor fail to comply with the notice within thirty (30) days from the date of
serving the notice, then and in such case the owner shall be at liberty to employ
other workmen and forthwith to execute such part of the works as the contractor
may have neglected to do or if the Owner shall think fit, without prejudice to any
other right he may have under the contract to take the work wholly or in part out of
the Contractor’s hands and recontract with any other person or persons to complete
the works or any part thereof and in that event the Owner shall have free use of all
Contractor’s equipment that may have been at the time on the site in connection
with the works without being responsible to the Contractor for fair wear and tear
thereof and to the exclusion of any right of the contactor over the same, and If the
sum that the contractor is entitled to be paid plus the costs incurred by the
Owner in completing the works, exceeds the contract price or the entire
works if entire works have been completed or the price for part of the works if
part of the works have been completed, the contractor shall be liable for such
If such excess is greater than the sums due to the contractor, the contractor
shall pay the balance to the Owner and if such excess is less than the sums
due to the Contractor, Owner shall pay the balance to the Contractor. For
facilitating such payment, Owner shall encash the Bank Guarantees of
Contractor available with Owner/s and retain such other payments due to the
contractor under the Contract in question or any other Contract that the
Owner/s may have with the Contractor. Such payment of excess amount shall be
independent of the liquidated damages for delay which the Contractor shall have to
pay if the completion of works is delayed.
79.2 In addition, such action by the Owner as aforesaid shall not relieve the Contractor of
his liability to pay liquidated damages for delay in completion of Works as defined in
Clause 14.0 of this Section.
79.3 Such action by the Owner as aforesaid the termination of the Contract under this
clause shall not entitle the Contractor to reduce the value of the Contract
Performance Guarantee nor the time thereof. The Contract Performance
Guarantee shall be valid for the full value and for the full period of the Contract
including guarantee period.
80.0 TERMINATION OF CONTRACT ON OWNER`S INITIATIVE
80.1 The Owner reserves the right to terminate the Contract either in part or in full due to
reasons other than those mentioned under clause entitled ‘Contractor’s Default’.
The Owner shall in such an event give fifteen (15) days notice in writing to the
Contractor of his decision to do so.
80.2 The Contractor upon receipt of such notice shall discontinue the work on the date
and to the extent specified in the notice, make all reasonable efforts to obtain
cancellation of all orders and Contracts to the extent they are related to the work
terminated and terms satisfactory to the Owner, stop all further sub-contracting or
purchasing activity related to the work terminated, and assist Owner in
maintenance, protection, and disposition of the works acquired under the Contract
Seal & Signature of Bidder
In the event of such a termination the Contractor shall be paid compensation,
equitable and reasonable, dictated by the circumstances prevalent at the time of
80.3 If the Contractor is an individual or a proprietary concern and the individual or the
proprietor dies and if the Contractor is a partnership concern and one of the
partners dies then unless the Owner is satisfied that the legal representatives of the
individual Contractor or of the proprietor of the propriety concern and in the case of
partnership, the surviving partners, are capable of carrying out and completing the
Contract the Owner shall be entitled to cancel the Contract as to its uncompleted
part without being in any way liable to payment of any compensation to the estate of
deceased Contractor and/or to the surviving partners of the Contractor’s firm on
account of the cancellation of the Contract. The decision of the Owner that the legal
representatives of the deceased Contractor or surviving partners of the Contractor’s
firm cannot carry out and complete the Contract shall be final and binding on the
parties. In the event of such cancellation the Owner shall not hold the estate of the
deceased Contractor and/or the surviving partners of the estate of the deceased
Contractor and/or the surviving partners of the Contractor’s firm liable to damages
for not completing the Contract.
81.0 FRUSTRATION OF CONTRACT
81.1 In the event of frustration of the Contract because of supervening impossibility in
terms of Section 56 of the Indian Contract Act, parties shall be absolved of their
responsibility to perform the balance portion of the Contract, subject to provisions
contained in sub-clause 46.3 below.
81.2 In the event of non-availability or suspension of funds for any reasons, whatsoever
(except for reason of willful or flagrant breach by the Owner) and/or Contractor then
the works under the Contract shall be suspended.
Furthermore, if the Owner is unable to make satisfactory alternative arrangements
for financing to the Contractor in accordance with the terms of the Contract within
three months of the event, the parties hereto shall be relieved from carrying out
further obligations under the Contract treating it as frustration of the Contract.
81.3 In the event referred to in sub-clauses 46.1 & 46.2 above the parties shall mutually
discuss to arrive at reasonable settlement on all issues including amounts due to
either party for the work already done on quantum merit basis which shall be
determined by mutual agreement between the parties.
82.0 GRAFTS AND COMMISSIONS ETC.
Any graft, commission, gift or advantage given, promised or offered by or on behalf
of the Contractor or his partner(s), agent(s), officer(s), director(s), employee(s) or
servant(s) or any one on his or their behalf in relation to the obtaining or to the
execution of this or any other Contract with the Owner, shall in addition to any
criminal liability which it may incur, subject the Contractor to the cancellation of this
and all other Contracts and also to payment of any loss or damage to the Owner
resulting from any cancellation. The Owner shall then be entitled to deduct the
amount so payable from any monies otherwise due to Contractor under the
RESOLUTION OF DISPUTES
83.0 DISPUTE RESOLUTION MECHANISM
83.1 Amicable Settlement:
Seal & Signature of Bidder
Any dispute, difference, controversy or claim between the Parties arising out of or
relating to this contract, including interpretation, breach, termination or validity
(hereinafter referred to as “Dispute”), shall, upon written request of either Party, be
referred to the authorized representatives of the Disputing Parties for resolution. The
authorized representatives shall promptly meet and attempt to negotiate in good faith
a resolution of the Dispute within thirty (30) days of the service of the request.
83.2 Arbitration Under the Gujarat Public Works Contracts Disputes Arbitration
Tribunal Act, 1992:
If the Parties fail to amicably resolve the Dispute as per Clause 83.1 above, or if
contrary claims remain unresolved, then, notwithstanding anything to the
contrary elsewhere in the Contract, the same shall be referred to arbitration
under the provisions of the Gujarat Public Works Contracts Disputes Arbitration
Tribunal Act, 1992 (hereinafter referred to as “the Act”) as amended from time to
time, and the rules framed thereunder. The decision, award and proceedings of
the Tribunal shall be final, binding and conclusive upon the parties, subject only
to such remedies as may be available under the Act and any other applicable
83.3 Continuity of Performance:
During the pendency of any Dispute or arbitration proceedings, both Parties
shall continue to perform their respective obligations under the Contract.
83.4 Non-Affectation of Powers:
Reference to any Dispute resolution procedure, including arbitration, shall not
affect the right of the Owner and/or Engineer-in-Charge to take possession of
or utilize the Contractor’s tools, plants, materials, stores or works as per the
terms and conditions of the Contract, nor shall it entitle the Contractor to stop
the progress of work or affect the Owner’s rights under the Contract to get
work executed through alternate means, if so required under the contract.
83.5 Limitation:
Neither Party shall be entitled to invoke dispute resolution or arbitration under this
clause later than thirty (30) days after the expiration of the defects liability
period, unless otherwise provided under the Act.
84.0 ARBITRATION
84.1 All questions, disputes or differences, whatsoever which may at any time arise
between the parties to this contract in connection with the contract OR any matter
arising out of OR in relation there to, shall be referred to the “GUJARAT PUBLIC
WORKS CONTRACTS DISPUT ARBITRATION TRIBUNAL “As per the provisions
of the Gujarat Public works contracts disputes arbitration Tribunal Act-1992.
The reference to arbitration proceedings under this clause shall not:
a) Affect the right of the engineer- in- charge to take possession of all or ant tools,
plants, materials and stores, in or upon the work or site thereof or belonging to
the contractor or procured by him and intended to be used for the execution of
the work or any part thereof.
b) Preclude the Engineer-in-charge from utilizing the materials purchased by the
contractor in any work or from removing such materials to other place, during the
Seal & Signature of Bidder
period the work is stopped or suspended in pursuance of notice given to the
contractor under general conditions.
c) Entitle the contractor to stop the progress of the work or carrying out the
additional or altered work in accordance with the prevision of General Condition
for the work where there is no specification.
d) Preclude the GETCO from getting the work done by another agency.
Neither party is entitled to bring a claim to arbitration latest by thirty days after the
expiration of the defects liability period.
The provisions of the Arbitration Act-1992, Gujarat Public Works Contract Disputes
Arbitration Tribunal Act-1992, and rules made there under shall apply to the
arbitration proceeding under this clause.
This clause is intentionally left blank, as all arbitration matters are governed by
Clause 83.0 above, in compliance with the Gujarat Public Works Contracts Disputes
Arbitration Tribunal Act, 1992 and GUVNL guidelines
85.0 RECONCILIATION OF ACCOUNTS
The Contractor shall prepare and submit every six months, a statement covering
payments claimed and the payments received vis-à-vis the works executed, for
reconciliation of accounts with the Owner. The Contractor shall also prepare and
submit a detailed account of Owner Issue materials received and utilized by him for
reconciliation purpose in a format to be discussed & finalized with the Owner before
the award of Contract.
86.0 Terms of Payment
The payment for materials to be supplied and erected shall be made as under only
after execution of the contract documents/furnishing of Security Deposit and on
execution of transmission line work.
86.1 For supply
(i) 80% of supply value for each consignment of material on submission of invoice
along with 100% GST, duties, F & I shall be paid within 30 days from the actual
material receipt date mentioned in SR Note after verifying the following
documents by field office and duly recorded.
A. Tax invoice.
B. Delivery challan.
C. Endorsed RR / LR copy.
D. Dispatch clearance certificate / letter wherever applicable.
E. E Way Bill, if applicable
(ii) 10% payment out of balance 20% of supply value shall be paid on completion of
erection & testing of the transmission line and completion certificate from
Engineer-in-charge and Chief Engineer (Procurement & Contracts)) or
(iii) Balance 10% of supply value shall be paid on successful commissioning of
transmission line against completion certificate and only after settlement of
material account statement of items supplied, used, erected and successful
commissioning is settled for complete lot and balance 10% will be release only
after passing of final bill. No extra payment will be released for the tower
materials and line materials which are not required for completion of line if
Seal & Signature of Bidder
supplied excess during execution of work and recovery will be made in
final bill accordingly.
(iv) Welfare Cess
The modality of payment/ reimbursement of welfare cess will be as under.
On receipt of A/T, the contractor / bidder will get them registered under Welfare
Cess Act and submit the documentary evidence to the concern office.
Before release of payment of first R.A.Bill, the contractor has to submit the
documentary evidence of registration. Only thereafter, the bill will be processed
Before release of payment of subsequent R.A.Bills, the contractor has to submit
the documentary evidence of payment of welfare cess of previous R.A.Bill.
Before release of payment of Final Bill, the contractor has to submit the
documentary evidence of payment of welfare cess of previous R.A.Bill as well
as the final bill.
If the R.A.Bill happens to be first and final bill, then before release of payment,
contractor has to submit documentary evidence of registration under Welfare
Cess Act and evidence of payment of welfare cess.
The welfare cess shall be reimbursed to the contractor on submission of copy
of documentary evidence of payment by observing due formalities.
86.2 For Erection works.
(i) 90% payment of amount claimed covering various activities such as excavation,
foundation, tower erection, earthing, tack welding stringing of conductor and
OPGW including insulator hoisting works against R.A. bills duly certified by EIC
within 30 days from the date of R.A. bill.
(ii) 10% of erection value shall be paid against commissioning of transmission line
only after settlement of material account statement of items supplied, used,
erected and successful commissioning of transmission line the same amount will
be release in final bill only and payment will be made only after passing of final
(iii) Payment of ROW compensation amount will be given as below only after
submission of necessary supporting documents.
1) 40% amount after completion of foundation work
2) 40% amount after completion of erection work
3) 20% amount after completion of stringing work in all respects
List of supporting documents:
1) Copy of form-7/12
2) Parishisht ‘A’ and ‘B’ of GoG Tharav
3) Document of Online Jantri Rate of respective Survey No. If online Jantri
Rates are not available, then land cost shall be certified by competent
Revenue Authority.
4) Copy of APMC rate based on which compensation is paid towards
damage of tree-crop etc.
5) ‘Panchnama’ duly certified by concern Sarpanch / Talati / Mamlatdar or
concern Revenue Authority
6) Documents for the compensation cost paid to Govt. Trasurer as per
GoG Tharav for the line passing through Govt. Waste Land. / Govt.
Seal & Signature of Bidder
(Bidder should note that Way leave clearance for execution of work and
compensation for Right of Way / Way Leave / Tree-Crop damages etc. to be
paid as per GoG guideline Dated:14-10-2024,02.12.2024 & 28-02-2025is in
scope of GETCO)
(iv) Welfare Cess
The modality of payment/ reimbursement of welfare cess will be as under.
On receipt of A/T, the contractor / bidder will get them registered under Welfare
Cess Act and submit the documentary evidence to the concern office.
Before release of payment of first R.A.Bill, the contractor has to submit the
documentary evidence of registration. Only thereafter, the bill will be processed
Before release of payment of subsequent R.A.Bills, the contractor has to submit
the documentary evidence of payment of welfare cess of previous R.A.Bill.
Before release of payment of Final Bill, the contractor has to submit the
documentary evidence of payment of welfare cess of previous R.A.Bill as well
as the final bill.
If the R.A.Bill happens to be first and final bill, then before release of payment,
contractor has to submit documentary evidence of registration under Welfare
Cess Act and evidence of payment of welfare cess.
The welfare cess shall be reimbursed to the contractor on submission of copy
of documentary evidence of payment by observing due formalities.
87.0 TAKING DELIVERY AND INSURANCE:
87.1 The contractor has keep tower materials & line materials in safe custody and
transport to the respective sites and will be fully responsible for any damage to or
loss of all materials at any stage during transportation or erection or taking over of
the line by GETCO
87.2 The Contractor has to open site store nearby the route of the line and ensure for
safe custody of all the stored materials at his own cost.
87.3 The Contractor shall have total responsibility for the entire materials stored, loose,
semi assembled and/or erected by him at site in his custody. The Contractor shall
make suitable security arrangements at his own cost to ensure the protection of all
materials, equipment and works from theft, fire pilferage and any other damages
and loss. It shall be the responsibility of the contractor to arrange for security till the
works are finally taken over by the Corporation.
87.4 STORAGE-CUM-INSURANCE: -The contractor shall take suitable storage-cum-
erection insurance cover at his cost to the extent of 60 % cost of all line materials,
which are required to complete the line including materials supplied by owner.
Contractor shall have to take comprehensive insurance policy against any loss,
damage, theft, pilferage, fire etc. for the complete period of storage, erection and
commissioning up to the time of taking over of the transmission line by the Board.
The Contractor shall deal directly and pursue the claim with the Insurance Company
and shall be responsible in regard to maintenance of all insurance coverage as well
as for settlement of claim. The proof of insurance policy taken by the successful
Contractor shall be furnished to Engineer-In-Charge. In absence of the above
insurance policy, R.A. Bill payment will be withheld.
87.5 In the event of any damage, theft, loss, pilferage, fire etc., Contractor will be
responsible to lodge, pursue and settle all the claims with the Insurance Company
for all items, materials and the Corporation shall be kept informed about it.
Contractor shall replace the lost / damaged materials / items promptly irrespective
Seal & Signature of Bidder
of the settlement of the claims by underwriter and ensure that the work progress is
as per agreed schedule. The loss, if any, such replacement will have to be borne by
the Contractor and Board will not entertain any claim / representation in this regard.
However, it will be contractor's responsibility to insure the entire project till the line is
taken over by the Board.
88.0 Contract Quality assurance:
88.1 The Bidder shall include in his proposal the Quality Assurance Programme
containing the overall quality management and procedures which he proposes to
follow in the performance of the Works during various phases as detailed in relevant
clause of the General Technical Conditions.
88.2 At the time of Award of Contract, the detailed Quality Assurance Programme to be
followed for the execution of the Contract will be mutually discussed and agreed
and such agreed Programme shall form a part of the Contract.
88.3 The Bidder shall clearly specify the list of sub-vendors from whom the bought out
items are being supplied. Such details shall be accompanied by their list of previous
supplies made performance reports etc. However, in case of orders are placed,
specific approval shall be obtained from the owner for the vendor supplied
materials. The quality assurance program shall be furnished for each material
separately for approval.
89.0 Termination of Contract:
89.1 In case of contractor fail to deliver the stocks or any consignment thereof within
contractual period of delivery or in case the stores are found not in accordance with
prescribed specification and/or the approved sample, the GETCO shall exercise its
discretionary power either:
89.2 To recover, from the contractor as agreed, by way of penalty clause above plus
GST as applicable, or
89.3 To purchase from elsewhere after giving due notice to the contractor on account
and at the risk of the contractor for such stores not so delivered or other similar
description without canceling the contract in respect of the consignment not yet due
for delivery or
90.0 To cancel the contract.
In the event of the risk purchase of stores of similar description, the opinion of the
GETCO shall be final. In the event of action taken under clause above, the
contractor shall be liable to pay for any loss which the GETCO may sustain on that
account, but the contractor shall not be entitled to have any saving on such
purchases made against default.
The decision of the GETCO shall be final as regards to the acceptability of stores
supplied by the contractor and the GETCO shall not be required to give any reason
in writing or otherwise at any time for rejection of the stores.
91.0 LABOUR LAWS:
1 Persons below the age of 18 years shall not be employed for the work. No female
worker shall be employed in the night shift between 07.00 p.m. and 06.00 a.m. next
Seal & Signature of Bidder
2 Contractor shall maintain a valid labor license under the contract Labour
(Regulation and abolition) Act for employing necessary manpower required by him.
In the absence of such license, the contract shall be liable to be terminated without
assigning any reason thereof.
3 The Contractor shall at his own expenses comply with all labour laws and keep the
GETCO indemnified in respect thereof. Some of the major liabilities under various
labour and industrial laws which the Contractor shall comply with, are as under:
i) Payment of contribution by way of Employer’s Contribution towards
provident Fund, Family Pension Scheme, Deposit Linked Insurance
Scheme, Administrative charges, etc. at the rates made applicable from time
to time by the Government of Gujarat / Government of India or other
Statutory Authority.
ii) Payment of deposit in respect of each contract labour at the rate of Rs. 30/-
or later prevailing rate with the Office of Commissioner of Labour as per the
Contract Labour (Regulation and Abolition) Act.
iii) License fee as prescribed under the Contract Labour (Regulation and
Abolition) Act and Rules framed there under depending upon the number of
iv) Paid leave facility and wages as per the provision of the Factories Act at the
rate of one day for every 20 days of working.
v) Identity cards as prescribed under the Factories Act with photo affixed
thereto, for identification.
vi) Payment of retrenchment compensation, Notice Pay and other liabilities as
per Industrial Dispute Act. Any payment to the Contractor’s employee arising
out of any claim of disputes under the Industrial Disputes Act 1947 or any
other Labour Laws.
vii) Payment of compensation in case of accidental injury.
viii) Provision of crèche if the female laborers employed are more than
ix) Maternity Leave as per the provisions of the Maternity Benefit Act.
The above are some of the major liabilities of the Contractor in addition to other
liabilities prescribed under the various labour laws, in force from time to time, from
Statutory Authorities like State Government/ Government o India, which the
Contractor shall have to comply with.
4 PROVIDENT FUND AND FAMILY PENSION SCHEME:
The Contractor shall submit along with his bills (month wise) a statement regarding
deduction against employees Provident Fund and Family Pension Scheme in
respect of each concerned employee. Provident Fund and Family pension Scheme
at the rate of 18% (or at the rate made applicable by the Government from time to
time of the wages. The Contractor’s contribution and his workers contribution
towards Provident Fund and Family Pension Scheme shall be deposited by the
Contractor with Regional Provident Fund Commissioner, Ahmedabad.
5 DEPOSIT LINKED INSURANCE SCHEME
The contractor shall have to deposit ½ % of the wages in respect of employees who
is a member of the Provident Fund, as the contribution to the Deposit Linked
Insurance Scheme with Regional Provident Fund Commissioner, Ahmedabad.
Seal & Signature of Bidder
6 ADMINISTRATIVE CHARGES:
Administrative charges for maintaining Provident Fund Account shall be deposited
by the Contractor with Regional Provident Fund Commissioner, Ahmedabad at the
rates applicable.
7 PAID LEAVE FACILITY:
Paid Leave Facility at the rate of one day for every twenty days worked by the
Contract Labour, shall be provided by the Contractor to his workers. He shall
maintain Leave Records, Leave Cards, for individual laborer which shall be duly
verified, approved and certified by the authorized Officer of the GETCO.
8 WORKMAN’S COMPENSATION FUND AND EMPLOYER’S LIABILITY
The contractor shall cover all his employees under workmen’s compensation fund
and under the liability insurance. The purchaser shall not be responsible for any
payments of compensation to the workers/supervisor of the contractor for fatal or
non-fatal accidents during the pendency of the contract.
9 The contractor shall employ adequate number of experienced skilled at site for daily
supervision and for maintenance of various registers and records required under the
law and contract. No payment for supervision shall be admissible.
10 CONTRCTOR TO INDEMNIFY THE GETCO:
The Contractor shall Indemnify the GETCO and every member officer and
employees of the GETCO also, Engineer-in-Charge and his staff against all actions,
proceedings, claims, demands, costs and expenses whatsoever, arising out of or in
connection with the matters referred herein above elsewhere and against all
actions, proceedings, claims, demands, costs and expenses which may be made
against the GETCO or Government for or in respect of performance of his obligation
under the contract documents. The GETCO shall not be liable for intervention of
authority Government for or in respect of performance of his obligation under the
contract documents. The GETCO shall not be liable for or in respect of or in
consequence of any accident or injury to any workman or other person in the
employment of the Contractor or his Sub-Contractor and the contractor shall
indemnify and keep indemnified the GETCO against all claims, demands,
proceedings, cost, charges and expenses whatsoever in respect thereof or in
relation thereto.
11 WORKMEN’S COMPENSATION AND EMPLOYER’S LIABILITY INSURANCE
Insurance shall be effective for all the Contractor’s employee engages in the
performance of this contract. If any of the work is sublet, the Contractor shall require
the Sub-Contractor to provide workmen’s employer’s liability insurance for the
latter’s employees, such employees shall be covered under the Contractor’s
12 WAGES TO BE PAID & TIME OF PAYMENT ETC. BY THE CONTRACTOR
a) The Contractor shall pay minimum wages per day to his Labours/ Workers as
per rates fixed under the minimum wages act. The wages of every Contract Labour
Seal & Signature of Bidder
employed by him under this contract shall also be paid by him before the expiry of
7th day of the last day of the month in respect of the wages are payable (i.e. wages
of a month have to be paid by him in the first week of the next month). Any default
will result in cancellation of contract forthwith or else the contractor shall be
punishable to the extent of Rs. 100/- per each day or as per the prevailing rules of
b) The Contractor shall give his Telephone Number and Address to the GETCO,
so that, in case of labour trouble etc. the Contractor can be contacted. The
Contractor shall arrange to have his office outside the factory work premises and
the Contractor shall arrange to have his office outside the factory work premises
and the Contractor shall keep himself present throughout the working hours.
92.0 REGISTRATION WITH PROVIDENT FUND OFFICE
I) The separate P.F. code issued from P.F. commissioner is required to be taken
ii) If the contractor does not possess separate P.F. code number of RPFC, his
tender will not be considered for acceptance.
iii) The contractor should mention separate P.F. code number allotted by RPFC,
along with the tender.
93.0 INTRODUCTION OF LEAVY OF TCS.
TCS @ 0.075% / 0.1% will be payable extra subject to fulfilment of the conditions of
sub section (1H) of section 206C of Income Tax Act, 1961. The format of undertaking
is attached as schedule – 20 in the tender.
94.0 Deduction of TDS under GST:
“TDS under GST @ 2 % (1 % CGST & 1 % SGST or 2 % IGST, as applicable) or at the
applicable rate from time to time, will be deducted from the bill of the Suppliers /
Contractors at the time of credit or payment. TDS certificates in the prescribed
format will be issued as per prescribed rules under GST.”.
95.0 INCOME TAX (TDS)
TDS under Income Tax will be deducted on purchase of goods by GETCO @
0.1% of the sum exceeding Rs. 50 lacs u/s 194Q from the bill of
suppliers/contractors at the time of credit or payment whichever is earlier. TDS
will be deducted on advance payment being also made by GETCO to supplier.
Further in some of the cases, where TCS u/s 206 (1H) is applicable also along
with TDS u/s 194Q, then only TDS on purchase of Goods u/s 194Q shall be
deductible, as TDS u/s 194Q overrides TCS u/s 206C (1H).
• As per the Section 206AB of Income Tax Act, TDS under Income Tax will be
deducted at higher rates of the following rates: (non-fillers of ITRs for the past
two fiscal years will be subjected to higher TDS).
(a) At twice the rate specified in the relevant provision of the Act
(b) At twice the rates in force
(c) At the rate of 5%
Seal & Signature of Bidder
96. (A) Bidder should note that Way leave clearance for execution of work and
compensation for Right of Way / Way Leave / Tree-Crop damages etc. to be
paid as per GoG guideline dated 14-10-2024,02.12.2024 & 28-02-2025 is in
scope of GETCO. So matter related to payment of RoW is not applicable to
bidder in GCC, ECC, SCC and Technical specifications.
(B) All the procedure regarding RoW compensation is to be carried out by
Agency is as follows:
a) Identification of Land Owner, their Land Survey No. with supporting
documents i.e. 7/12 Utara, etc.
b) Handing over / distribution of Notice to concern land owners.
c) Plotting of line route on tikka map.
d) Preparation of “Panchnama Case” and follow-up with concern
Sarpanch / Talati / Mamlatdar or concern Revenue Authority as well as
Land Owners / Farmers for their signature & thereof.
e) Preparation of RoW case for submission of Office of the District
Magistrate, etc. and also follow-up with them.
f) Follow-up with concern authority for getting statutory approvals
including Police Department.
97. Relationship with employee:
Every bidder should, at time of submission of bid, give a declaration as
“If in any Bidder Company / Firm, the interest (i.e. Shareholding in
company and share in partnership firm) of any employee of the tendering
Company or his / her relative as defined in section 2(77) of the Company’s
Act. 2013 is 10% or more, the tendering Company will not deal with such
Company / Firm at all.
Tenderer therefore, must specifically disclose the fact in his technical bid.
Non-disclosure of such facts would immediately disqualify the tenderer for
further dealing with the tendering company.”
98. Conflict of Interest among Bidders / Agents
A bidder shall not have conflict of interest with other bidders. Such conflict of
interest can lead to anti-competitive practices to the detriment of Procuring Entity’s
interests. The bidder found to have a conflict of interest shall be disqualified. A
bidder may be considered to have a conflict of interest with one or more parties in
this bidding process, if:
a) they have proprietor/ partner(s)/ Director(s) in common; or
b) they receive or have received any direct or indirect subsidy/ financial stake
from any of them; or
c) they have the same legal representative/ agent for purposes of this bid; or
Seal & Signature of Bidder
d) they have relationship with each other, directly or through common third
parties, that puts them in a position to have access to information about or
influence on the bid of another bidder; or
e) bidder participates in more than one bid in this bidding process. Participation
by a bidder in more than one Bid will result in the disqualification of all bids in
which the parties are involved. However, this does not limit the inclusion of
the components/ sub-assembly/ assemblies from one bidding manufacturer
in more than one bid.
f) in cases of agents quoting in offshore procurements, on behalf of their
principal manufacturers, one agent cannot represent two manufacturers or
quote on their behalf in a particular tender enquiry. One manufacturer can
also authorize only one agent/ dealer. There can be only one bid from the
1. The principal manufacturer directly or through one Indian agent on his
2. Indian/ foreign agent on behalf of only one principal.
g) a Bidder or any of its affiliates participated as a consultant in the preparation
of the design or technical specifications of the contract that is the subject of
h) in case of a holding company having more than one independently
manufacturing units, or more than one unit having common business
ownership/ management, only one unit should quote. Similar restrictions
would apply to closely related sister companies. Bidders must proactively
declare such sister/ common business/ management units in same/ similar
line of business.
i) Bidder shall not act in contravention/ violation to the provisions of
competition act, as amended from time to time.
Every bidder should, at the time of submission of bid, give a declaration, that bidder
shall not have conflict of interest with other bidders, as above.
99. Use of ‘Call Before u Dig’ (CBuD) mobile application:
Bidder is note that it is mandatory to use ‘Call Before u Dig’ (CBuD) mobile
application for all excavators prior to any type of excavation / digging.
100. Responsibility for correctness of the information submitted in the bid
lies with bidder. If any information furnished in the bid is proved to be false at
a later date, GETCO reserve right to reject the bid and the bid will not only be
rejected but the bidder will be BLACKLISTED as per GUVNL Policy.
Seal & Signature of Bidder
ERECTION CONDITIONS OF CONTRACT
1.1 The following shall supplement the conditions already contained in other parts of
these specifications & document and shall govern the portion of the work of this
Contract to be performed at Site.
1.2 The Contractor upon signing of the Contract shall, nominate a responsible officer as
his representative at Site suitably designated for the purpose of overall
responsibility and coordination of the works to be performed at Site. Such person
shall function from the Site office of the Contractor during the pendency of Contract.
2.0 REGULATION OF LOCAL AUTHORITIES AND STATUTES
2.1 The Contractor shall comply with all the rules and regulations of local authorities
during the performance of his field activities. He shall also comply with the Minimum
Wages Act, 1948 and the Payment of Wages Act (both of the Government of India)
and the rules made there under in respect of any employee or workman employed
or engaged by him or his Sub-Contractor. He shall abide by labour laws.
2.2 All initial registration and statutory inspection fees, if any, in respect of his work
pursuant to this Contract shall be to the account of the GETCO. Should any such
inspection or registration need to be re-arranged due to the fault of the Contractor or
his Sub Contractor, the additional fees to such inspection and/or registration also
shall be borne by the Contractor.
3.0 OWNER’S LIEN ON EQUIPMENT
The Owner shall have lien on all equipment brought to the Site for the purpose of
erection, testing and commissioning of the equipment to be supplied & erected
under the Contract. The Owner shall continue to hold the lien on all such equipment
throughout the period of Contract. No material brought to the Site shall be removed
from the Site by the Contractor and/or his Sub-Contractors without the prior written
approval of the Engineer.
4.0 ACCESS TO SITE AND WORKS ON SITE
4.1 Suitable access to and possession of the Site shall be afforded to the Contractor by
the Owner in reasonable time.
4.2 The works so far as it is carried out on the Owner’s premises, shall be carried out at
such time as the Owner may approve and the Owner shall give the Contractor
reasonable facilities for carrying out the works.
4.3 In the execution of the works, no person other than the Contractor or his duly
appointed representative, Sub- Contractor and workmen, shall be allowed to do
on the Site, except by the special permission, in writing of the Engineer or his
representative.
5.0 CONTRACTOR’S SITE ESTABLISHMENT
The Contractor shall at all times keep posted an authorized representative for the
purpose of the Contract. Any written order or instruction of the Engineer or his duly
authorized representative shall be communicated to the said authorized resident
Seal & Signature of Bidder
representative of the Contractor and the representative shall be available at a stated
address for this purpose.
6.0 CO-OPERATION WITH OTHER CONTRACTORS
6.1 The Contractor shall co-operate with all other Contractors or tradesmen of the
Owner, who may be performing other works on behalf of the Owner and the
workmen who may be employed by the Owner and doing work in the vicinity of the
Works under the Contract. The Contractor shall also so arrange to perform his work
as to minimize, to the maximum extent possible, interference with the work of other
Contractors and their workmen. Any injury or damage that may be sustained by the
employees of the other Contractors and the Owner, due to the Contractor’s work
shall promptly be made good at the Contractor’s own expense.
7.0 DISCIPLINE OF WORKMEN
The Contractor shall adhere to the disciplinary procedure set by the Engineer in
respect of his employees and workmen at Site. The Engineer shall be at liberty to
object to the presence of any representative or employee of the Contractor at the
Site, if in the opinion of the Engineer such employee has misconducted himself or is
incompetent or negligent or otherwise undesirable and then the Contractor shall
remove such a person objected to and provide in his place a competent
8.0 CONTRACTOR’S FIELD OPERATION
8.1 The Contractor shall keep the Engineer informed in advance regarding his field
activity plans and schedules for carrying-out each part of the works. Any review of
such plan or schedule or method of work by the Engineer shall not relieve the
Contractor of any of his responsibilities towards the field activities. Such reviews
shall also not be considered as an assumption of any risk or liability by the Engineer
or the Owner or any of his representatives and no claim of the Contractor will be
entertained because of the failure or inefficiency of any such plan or schedule or
method of work reviewed. The Contractor shall be solely responsible for the safety,
adequacy and efficiency of plant and equipment and his erection methods.
8.2 The Contractor shall have the complete responsibility for the conditions of the Work-
site including the safety of all persons employed by him or his Sub–Contractor and
all the properties under his custody during the performance of the work. This
requirement shall apply continuously till the completion of the Contract and shall not
be limited to normal working hours.
9.0 PROGRESS REPORT
9.1 The Contractor shall furnish three (3) copies each to the Engineer of progress
including if any, photographs of the work done at Site in MS Project format.
9.2 The monthly progress report detailing-out the progress achieved on all erection
activities shall highlight comparison to the schedules. The report shall also indicate
the reasons for the variance between the scheduled and actual progress and the
action proposed for corrective measures, wherever necessary.
9.3 The monthly progress report shall be submitted in MS project indicating various
activities mentioned in the completion schedule.
Seal & Signature of Bidder
Monthly progress shall be submitted in following format.
Description of work as per Quantity Work Work executed Total
A/T involved as per executed up during this Progress
check survey to last month month
Check survey in km
Foundation of tower in Nos.
Erection of tower in Nos.
Tack welding & earthing
Stringing of conductor &
10.0 MAN-POWER REPORT
10.1 The Contractor shall submit to the Engineer, on the first day of every month, a man
hours schedule for the month, detailing the man hours scheduled for the month,
skill-wise and area-wise.
11.0 PROTECTION OF WORK
The Contractor shall have total responsibility for protecting his works till it is finally
taken over by the Engineer. No claim will be entertained by the Owner or by the
Engineer for any damage or loss to the Contractor’s works and the Contractor shall
be responsible for complete restoration of the damaged works to original conditions
to comply with the specification and drawings.
12.0 EMPLOYMENT OF LABOUR
12.1 The Contractor will be expected to employ on the work only his regular skilled
employees with experience of his particular work. No person below the age of
eighteen years shall be employed.
12.2 All traveling expenses including provisions of necessary transport to and from Site,
lodging, allowances and other payments to the Contractor’s employees shall be the
sole responsibility of the Contractor.
12.3 In case the Owner becomes liable to pay any wages or dues to Labour or any
Government agency under any of the provisions of the Minimum Wages Act,
Workmen Compensation Act, Contract Labour Regulation Abolition Act or any other
law due to act of omission of the Contractor, the Owner may make such payment
and shall recover the same from the Contractor’s bills.
13.0 FACILITIES TO BE PROVIDED BY THE OWNER (NOT APPLICABLE)
Land for Contractor’s Store, Workshop etc.
a) The Engineer shall at his discretion and for the duration of execution of the Contract
make available at site, land for construction of Contractor’s field office, workshop,
stores, etc. required for execution of the Contract. Any such temporary construction
shall be done by the Contractor at his cost.
b) On completion of work the Contractor shall hand over the land duly cleaned to the
Engineer. Until and unless the Contractor has handed over the vacant possession
Seal & Signature of Bidder
of land allotted to him for the above purpose, the payment of his final bill shall not
13.2 Electricity:
The concerned EE (Const.) shall apply for temporary connection at site store. Sub-
Division paying required Service Charges and Deposit. Such temporary connections
to be released on the name of EPC-Contractor on recommendation of the
concerned EE (Const.). The power so consumed shall be charged at the prevailing
14.0 FACILITIES TO BE PROVIDED BY THE CONTRACTOR
14.1 Tools, tackles and scaffoldings
The Contractor shall provide all the construction equipments; tools, tackles and
scaffoldings required for pre-assembly, erection, testing and commissioning of the
transmission line covered under the Contract. He shall submit a list of all such
materials to the Engineer before the commencement of work at Site. These tools
and tackles shall not be removed from the Site without the written permission of the
14.3 The Contractor shall provide necessary first-aid facilities for all his employees,
representatives and workmen working at the Site. Enough number of Contractor’s
personals shall be trained in administering first-aid.
14.4 Cleanliness
14.4.1 The Contractor shall be responsible for keeping the entire area allotted to him clean
and free from rubbish, debris etc. during the period of Contract. The Contractor
shall employ enough number of personnel to keep the work area clean. Materials
and stores shall be so arranged to permit easy cleaning of the area. In areas where
equipment might drip oil and cause damage to the floor surface, a suitable
protective cover of a flame resistant, oil proof sheet shall be provided to protect the
floor from such damage.
15.0 LINES AND GRADES
All the works shall be performed to the lines, grades and elevations indicated on the
drawings. The Contractor shall be responsible to locate and lay-out the works. Basic
horizontal and vertical control points will be established and marked by the Engineer
at site at suitable points. These points shall be used as datum for the works under
the Contract. The Contractor shall inform the Engineer well in advance of the times
and places at which he wishes to do work in the area allotted to him so that suitable
datum points may be established and checked by the Engineer to enable the
Contractor to proceed with his works. Any work done without being properly located
may be removed and/or dismantled by the Engineer at Contractor’s expense.
16.0 FIRE PROTECTION
16.1 The work procedures that are to be used during the erection shall be those, which
minimize fire hazards to the extent practicable. Combustible materials, combustible
waste and rubbish shall be collected and removed from the Site at least once each
Seal & Signature of Bidder
day. Fuels, oils and volatile or inflammable materials shall be stored away from the
construction and equipment and materials storage areas.
16.2 All the Contractor’s supervisory personnel and select number of workers shall be
trained for fire fighting. Enough of such trained personnel must be available at the
Site during the entire period of the Contract.
The Contractor shall have total responsibility for all line materials including tower,
conductor, insulator, OPGW / earth wire & Hardware accessories etc. in his
custody/stores, loose, semi-assembled and/or erected by him at Site. The
Contractor shall make suitable security arrangements ensure the protection of all
materials, equipment and works from theft, fire, pilferage and any other damages
18.0 MATERIALS HANDLING AND STORAGE
18.1 All the line material furnished under the Contract and arriving at Site shall be
promptly received, unloaded, transported and stored in the storage spaces by the
18.2 Contractor shall be responsible for examining all the shipment and notify the
Engineer immediately of any damages, storage, discrepancy etc, for the purpose of
Engineer’s information only. The Contractor shall submit to the Engineer every
week a report detailing all the receipts during the week. However, the Contractor
shall be solely responsible for any shortages or damages in transit, handling and /
or in storage and erection at Site. Any demurrage, wharf age and other such
charges claimed by the transporters, railways etc, shall be to the account of the
18.3 The Contractor shall maintain an accurate and exhaustive record detailing out the
list of all line materials including tower material, conductor, OPGW / earth wire,
silicon rubber insulator, hardware accessories etc received by him for the
purpose of erection and keep such record open for the inspection of the Engineer
18.4 All material shall be handled very carefully to prevent any damage or loss. The
material stored shall be properly protected to prevent damage either to the lime
material or to the floor where they are stored. The material from the store shall be
moved to the actual location at the appropriate time so as to avoid damage of such
line material at Site.
18.5 All material shall be protected against moisture ingress and corrosion during
storage and periodically inspected.
18.6 The consumable and other supplies likely to deteriorate due to storage must be
thoroughly protected and stored in a suitable manner to prevent damage or
deterioration in quality by storage.
18.7 All the materials stored in the open or dusty location must be covered with suitable
weatherproof and flame proof covering material wherever applicable.
18.8 If the materials belonging to the Contractor are stored in areas other than those
earmarked for him, the Engineer will have the right to get it moved to the area
earmarked for the Contractor at the Contractor’s cost.
Seal & Signature of Bidder
18.9 The Contractor shall be responsible for making suitable indoor storage facilities to
store all line material, which require indoor storage. The Engineer, in addition, may
direct the Contractor to move certain other materials, which in his opinion will
require indoor storage, to indoor storage areas, which the Contractor shall strictly
19.0 CONSTRUCTION MANAGEMENT
19.1 The field activities of the Contractors working at Site will be coordinated by the
Engineer and the Engineer’s decision shall be final in resolving any disputes or
conflicts between the Contractor and other Contractors and the tradesmen of the
Owner regarding scheduling and coordination of work. Such decision by the
Engineer shall not be a cause for extra compensation or extension of time for the
19.2 The Engineer shall hold weekly meetings of the Contractor at Site, at a time and
place to be designated by the Engineer. The Contractor shall attend such meetings
and take notes of discussions during the meeting and the decision of the Engineer
and shall strictly adhere to those decisions in performing his works. In addition to
the above weekly meeting, the Engineer may call for other meetings either with
individual Contractors or with selected number of Contractors and in such a case
the Contractors if called, will also attend such meetings.
19.3 Time is the essence of the Contract and the Contractor shall be responsible for
performance of his works in accordance with the specified construction schedule. If
at any time, the Contractor is falling behind the schedule, he shall take necessary
action to make good for such delays by increasing his work force or by working
overtime or otherwise accelerate the progress of the work to comply with the
schedule and shall communicate such actions in writing to the Engineer, satisfying
that his action will compensate for the delay. The Contractor shall not be allowed
any extra compensation for such action.
19.4 The Engineer shall, however, not be responsible for provision of additional labour
and/or materials or supply or any other services to the Contractor except for the
coordination work between various Contractors if any at site.
20.0 FIELD OFFICE RECORDS
The Contractor shall maintain up to date copies of all drawings, specifications and
other Contract Documents and any other supplementary data complete with all the
latest revisions thereto. The Contractor shall also maintain in addition the
continuous record of all changes to the above Contract Documents, drawings,
specifications, and supplementary data, etc. effected at the field and on completion
of his total assignment under the Contract shall incorporate all such changes on the
drawings and other Engineering data to indicate as installed conditions of the
equipment furnished and erected under the Contract. Such drawings and
Engineering data shall be submitted to the Engineer in required number of copies.
21.0 CONTRACTOR’S MATERIALS BROUGHT TO SITE
21.1 The Contractor shall bring to Site all equipment, components, parts, materials,
including construction equipment, tools and tackles for the purpose of the works
under intimation to the Engineer. All such goods shall, from the time of their being
brought vest in the Owner, but may be used for the purpose of the works only and
shall not on any account be removed or taken away by the Contractor without the
Seal & Signature of Bidder
written permission of the Engineer. The Contractor shall nevertheless be solely
liable and responsible for any loss or destruction thereof and damage thereto.
21.2 The Owner shall have a lien on such goods for any sum or sums which may at any
time be due or owing to him by the Contractor, under, in respect of or by reasons of
the Contract. After giving a fifteen (15) days notice in writing of his intention to do
so, the Owner shall be at liberty to sell and dispose off any such goods, in such
manner as he shall think fit and to apply the proceeds in or towards the satisfaction
of such sum or sums due as aforesaid.
21.3 After the completion of the Works, the Contractor shall remove from the Site under
the direction of the Engineer the materials such as construction equipment, erection
tools and tackles, scaffolding etc. with the written permission of the Engineer.
22.0 PROTECTION OF PROPERTY AND CONTRACTOR’S LIABILITY
22.1.1 The Contractor shall be responsible for any damage resulting from his operations.
He shall also be responsible for protection of all persons including members of
public and employees of the Owner and the employees of other Contractors and
Sub Contractors and all public and private property.
23.1 In addition to the conditions covered under the Clause entitled ‘Insurance’ in
General Terms and Conditions of Contract, the following provisions will also apply
to the portion of works to be done beyond the Contractor’s own or his Sub-
Contractor’s manufacturing Works.
23.2 Workmen’s Compensation Insurance
This insurance shall protect the Contractor against all claims applicable under the
Workmen’s Compensation Act, 1948 (Government of India). This policy shall also
cover the Contractor against claims for injury, disability, disease or death of his or
his Sub-Contractor’s employee, which for any reason are not covered under the
Workmen’s Compensation Act, 1948. The liabilities shall not be less than:
Workmen’s : As per statutory
Compensation Provisions
Employee’s : As per statutory
liability Provisions
23.3 Comprehensive General Liability Insurance
The insurance shall protect the Contractor against all claims arising from injuries,
disabilities, disease or death of members of public or damage to property of others,
due to any act of omission on the part of the Contractor, his agents, his employees,
his representatives and Sub-Contractors or from riots, strikes and civil commotion.
23.4 The hazards to be covered will pertain to all the works and areas where the
Contractor, his Sub-Contractors, his agents and his employees have to perform
work pursuant to the Contract.
23.5 The above are only illustrative list of insurance covers normally required and it will
be the responsibility of the Contractors to maintain all necessary insurance
coverage to the extent both in time and amount to take care of all his liabilities either
direct or indirect, in pursuance of the Contract.
24.0 UNFAVOURABLE WORKING CONDITIONS
Seal & Signature of Bidder
The Contractor shall confine all his field operations to those works, which can be
performed without subjecting the equipment and materials to adverse effects during
inclement weather conditions, like monsoon, storms etc. and during other
unfavorable construction conditions. No field activities shall be performed by the
Contractor under conditions, which might adversely affect the quality and efficiency
thereof, unless special precautions or measures are taken by the Contractor in a
proper and satisfactory manner in the performance of such Works and with the
concurrence of the Engineer. Such unfavorable construction conditions will in no
way relieve the Contractor of his responsibility to perform the Works as per the
25.0 PROTECTION OF MONUMENTS AND REFERENCE POINTS
The Contractor shall ensure that any finds such as relic, antiquity, coins, fossils, etc.
which he may come across during the course of performance of his Works either
during excavation or elsewhere, are properly protected and handed over to the
Engineer. Similarly, the Contractor shall ensure that the bench marks, reference
points, etc, which are marked either with the help of Engineer or by the Engineer
shall not be disturbed in any way during the performance of his Works. If any work
is to be performed which disturbs such reference the same shall be done only after
these are transferred to other suitable locations under the direction of the Engineer.
The Contractor shall provide all necessary materials and assistance for such
relocation of reference points etc.
26.0 WORK & SAFETY REGULATIONS
26.1 The Contractor shall ensure proper safety of all the workmen, materials, plant and
equipment belonging to him or to GETCO or to others, working at the Site. The
Contractor shall also be responsible for provision of all safety notices and safety
equipment required both by the relevant legislations and the Engineer, as he may
deem necessary.
26.2 All equipment used in construction and erection by Contractor shall meet
Indian/International Standards and where such standards do not exist, the
Contractor shall ensure these to be absolutely safe. All equipment shall be strictly
operated and maintained by the Contractor in accordance with manufacturer’s
Operation Manual and safety instructions and as per Guidelines/rules of GETCO in
26.3 Periodical examinations and all tests for all lifting/hoisting equipment & tackles shall
be carried-out in accordance with the relevant provisions of Factories Act
Indian Electricity Act 1910 and associated Laws/Rules in force from time to time. A
register of such examinations and tests shall be properly maintained by the
Contractor and will be promptly produced as and when desired by the Engineer or
by the person authorized by him.
26.4 The Contractor shall provide suitable safety equipment of prescribed standard to all
employees and workmen according to the need.
26.5 The Contractor shall provide safe working conditions to all workmen and employees
at the Site including safe means of access, railings, stairs, ladders, scaffoldings etc.
The scaffoldings shall be erected under the control and supervision of an
experienced and competent person. For erection, good and standard quality of
material only shall be used by the Contractor.
Seal & Signature of Bidder
26.6 The Contractor shall not interfere or disturb electric fuses, wiring and other
electrical equipment belonging to the Owner or other Contractors under any
circumstances, whatsoever, unless expressly permitted in writing by GETCO to
handle such fuses, wiring or electrical equipment
26.7 Before the Contractor connects any electrical appliances to any plug or socket
belonging to the other Contractor or Owner, he shall:
a. Satisfy the Engineer that the appliance is in good working condition;
b. Inform the Engineer of the maximum current rating, voltage and phases of
the appliances;
c. Obtain permission of the Engineer detailing the sockets to which the
appliances may be connected.
26.8 The Engineer will not grant permission to connect until he is satisfied that;
a. The appliance is in good condition and is fitted with suitable plug;
b. The appliance is fitted with a suitable cable having two earth conductors,
one of which shall be an earthed metal sheath surrounding the cores.
26.9 No electric cable in use by the Contractor/Owner will be disturbed without prior
permission. No weight of any description will be imposed on any cable and no
ladder or similar equipment will rest against or attached to it.
26.10 No repair work shall be carried out on any live equipment. The equipment must be
declared safe by the Engineer and a permit to work shall be issued by the Engineer
before any repair work is carried out by the Contractor. While working on electric
lines/equipment, whether live or dead, suitable type and sufficient quantity of tools
will have to he provided by the Contractor to electricians/workmen/officers.
26.11 In case any accident occurs during the construction/ erection or other associated
activities undertaken by the Contractor thereby causing any minor or major or fatal
injury to his employees due to any reason, whatsoever, it shall be the responsibility
of the Contractor to promptly inform the same to the Engineer in prescribed form
and also to all the authorities envisaged under the applicable laws.
26.12 The Engineer shall have the right at his sole discretion to stop the work, if in his
opinion the work is being carried out in such a way that it may cause accidents and
endanger the safety of the persons and/or property, and/or equipment. In such
cases, the Contractor shall be informed in writing about the nature of hazards and
possible injury/accident and he shall comply to remove shortcomings promptly. The
Contractor after stopping the specific work can, if felt necessary, appeal against the
order of stoppage of work to the Engineer within 3 days of such stoppage of work
and decision of the Engineer in this respect shall be conclusive and binding on the
26.13 The Contractor shall not be entitled for any damages/compensation for stoppage of
work due to safety reasons and the period of such stoppage of work will not be
taken as an extension of time for completion of work and will not be the ground for
waiver of levy of liquidated damages.
26.14 It is mandatory for the Contractor to observe during the execution of the works,
requirements of Safety Rules which would generally include but not limited to
Seal & Signature of Bidder
a) Each employee shall be provided with initial indoctrination regarding safety by
the Contractor, so as to enable him to conduct his work in a safe manner.
b) No employee shall be given a new assignment of work unfamiliar to him without
proper introduction as to the hazards incident thereto, both to himself and his
fellow employees.
c) Employees must not leave naked fires unattended. Smoking shall not be
permitted around fire prone areas and adequate fire fighting equipment shall be
provided at crucial location.
d) There shall be a suitable arrangement at every work site for rendering prompt
and sufficient first aid to the injured.
j) Requirements of ventilation in underwater working to licensed and experienced
divers, use of gum boots for working in slushy or in inundated conditions are
essential requirements to be fulfilled.
26.15 The Contractor shall follow and comply with all GETCO Safety Rules, relevant
provisions of applicable laws pertaining to the safety of workmen, employees, plant
and equipment as may be prescribed from time to time without any demur, protest
or contest or reservations. In case of any discrepancy between statutory
requirement and GETCO Safety Rules referred above, the latter shall be binding on
the Contractor unless the statutory provisions are more stringent.
a. Fatal injury or accident Rs. 1,00,000/- per These are applicable
causing death person : for death
b. Major injuries or accident Rs. 20,000/- per injury to any person,
causing 25% or more person whosoever
permanent disablement to
Workmen or employees
Permanent disablement shall have same meaning as indicated in Workmen’s
Compensation Act. The compensation mentioned above shall be in addition to the
compensation payable to the workmen/employees under the relevant provisions of
the Workmen’s Compensation Act and rules framed there under or any other
applicable laws as applicable from time to time. In case the Owner is made to pay
such compensation then the Contractor is liable to reimburse the Owner such
amount in addition to the compensation indicated above.
27.0 CODE REQUIREMENTS
The erection requirements and procedures to be followed during the installation of
the equipment shall be in accordance with the relevant Codes and accepted good
engineering practice, the Engineer’s drawings and other applicable Indian
recognized codes and laws and regulation of the Government of India.
Seal & Signature of Bidder
SPECIAL CONDITIONS OF CONTRACT
1.0 General Particulars:
This part of the Bid Document relates to certain specific/special terms and
conditions particular to the Contract. The provisions herein are to be read and
understood in conjunction with the relevant provisions elsewhere in the General
Conditions of Contract (GCC) and Erection Conditions of Contract (ECC). The intent
of provisions herein is specific to this contract and are, in general, supplementary to
related provisions under GCC and ECC. However, in certain provisions which are
contrary to those in GCC and ECC, the provisions in these Special Conditions of
Contract will prevail.
2.0 Tender Fee:
The tender fee plus GST as applicable specified in notice inviting tender is
payable by Demand Draft (DD) at Vadodara drawn on any Scheduled Bank in
favour of Gujarat Energy Transmission Corporation Ltd. The same will be furnished
in Cover-1 of Bid along with EMD (Bid Security).
3.0 Earnest Money Deposit (EMD):
3.1 (a) The estimated cost of Tender is more than Rs. 100 lacs, the EMD is
payable as under:
50 % of EMD by DD in favour of Gujarat Energy Transmission Corporation
Ltd. on any Scheduled Bank in Vadodara and Balance 50% by Bank
Guarantee from any Nationalized Bank in the format provided herein.
(b) The estimated cost of tender is less than Rs.100 Lacs, the EMD is payable as
100 % of EMD by DD in favour of Gujarat Energy Transmission
Corporation Ltd. on any Scheduled Bank in Vadodara
3.2 Payment by Cheque/Coop Bank Guarantee/ Company Guarantee is not
3.3 Validity Period: - The offer should be valid for a minimum period of 180 days
from the date of opening of Technical bid.
4.0 Confirmation by Bidder:
The Bidder shall sign the Confirmation enclosed to this SCC and not furnishing the
same will make the Bid invalid.
5.0 QUALIFYING REQUIREMENT
TECHNICAL CRITERIA:
FINANCIAL CRITERIA:
Details as per qualifying requirement to be submitted along-with offer, in a separate cover.
CA certificate to be attached for MAT. (This is must)
Seal & Signature of Bidder
Supply/Order executed details for offered items with name of purchaser, date and
location to be mentioned.
Performance certificate for satisfactory operation/working for period as per
qualifying requirement attached with specification. (This is must for getting the offer
6.0 Additional Documents:
Apart from various documents to be furnished along with the Bid as required in the
GCC and ECC, the following documents/details are to be furnished by the Bidder:
1. GST Registration No. and date
2. Registration. No. under Shops & Establishment Act/ issuing authority
3. Details of Partners/Directors of the Firm/Company.
4. Experience Record and details of orders pending / executed for various utilities
5. Last five years Audited Accounts
6. Detail of Manufacturing/Fabrication facilities along with list of Testing Equipment
calibrated up to date. The detail for the same may be submitted.
7. Factory Registration / License details
8. Solvency certificate from Bank (20 % of Bid value).
9. P.F registration
7.0 Price Inclusions (including Taxes & Duties):
7.1 GOODS AND SERVICE TAX (GST):
GST and Cess as applicable shall be payable/ receivable as mentioned in
clause no. 17 of GCC.
7.2 The prices quoted shall be all inclusive of freight, transportation, loading, unloading
& stacking at site of materials supplied by Contractor as well as owner supplied
7.3 No extra payment toward any type of template including extensions and special
tower will be made.
7.4 Evaluation of the tender shall be carried out on end cost basis.
7.5 Statutory Variations:
Any statutory increase or decrease in the taxes and duties subsequent to your offer
if it takes place within the original contractual delivery date will be to the GETCO’s
account subject to the claim being supported by documentary evidence. However, if
any decrease takes place after the contractual delivery date, the advantage will
have to be passed on to the GETCO.
7.12 Income Tax
Income-tax at source at the prevailing rate will be deducted from bills in accordance
with the provision of Income-Tax Laws and to that effect a certificate will be issued
to the contractor.
7.13 Welfare Cess
As per the Welfare Cess Act, the welfare cess @ 1% is applicable on supply and
erection items for supply, erection, testing & commissioning of substation,
transmission lines, EPC/Turnkey projects and civil works. The welfare cess@1%
Seal & Signature of Bidder
shall be paid by the contractor and the same shall be reimbursed by employer on
production of documentary evidence of payment.
Contractor shall get registered under Welfare Cess Act before commencement of
work. Office of the Factory Inspector is authorized at present as a registering
GETCO shall pay the welfare cess by way of reimbursing to contractors on
production of documentary evidence of payment.
The contracts for which supply or part supply of material are in the scope of
GETCO, then contractors shall deposit welfare cess on estimated cost of supplied
items to GETCO on progressive basis of utilization. As this part of welfare cess is
on GETCO account, the same shall be reimbursed to the contractor on receipt of
request letter along with documentary evidence of payment. For calculation of
welfare cess on supply part, valuation as per MR shall be taken and informed to
the contractor for payment. This will be over and above the A/T value.
The welfare cess@1% is not considered in the estimate for this project and
therefore, bidders are requested not to load welfare cess in the price
schedules as welfare cess@1% is on reimbursement basis.
7.14 (A) It is the responsibility of the GETCO for complete way leave clearance for
execution of work including estimation of the compensation for Right of Way
/ Way Leave / Tree-Crop damages etc. to be paid as per GoG guideline dated
(B) All the procedure regarding RoW compensation is to be carried out by
Agency is as follows:
a) Identification of Land Owner, their Land Survey No. with supporting
documents i.e. 7/12 Utara, etc.
b) Handing over / distribution of Notice to concern land owners.
c) Plotting of line route on tikka map.
d) Preparation of “Panchnama Case” and follow-up with concern
Sarpanch / Talati / Mamlatdar or concern Revenue Authority as well as
Land Owners / Farmers for their signature & thereof.
e) Preparation of RoW case for submission of Office of the District
Magistrate, etc. and also follow-up with them.
f) Follow-up with concern authority for getting statutory approvals
including Police Department.
It will be imperative on each Bidder to fully inform himself of all local conditions and
factors which may have any effect on the execution of the Contract covered under
these documents and specifications. The Owner shall not entertain any request for
clarifications from the bidders, regarding such local conditions.
It must be understood and agreed that such factors have properly been
investigated and considered while submitting the proposals. No claim for financial
adjustment to the Contract awarded under these specifications and documents will
be entertained by the owner. Neither any change in the time schedule of the
Contract nor any financial adjustments arising thereof shall be permitted by the
Owner, which are based on the lack of such clear information or its effect on the
cost of the works to the Bidder.
Documentary evidence / revenue records to be provided by the contractor along
with the copy of demand drafts through which compensation paid.
8.0 SECURITY DEPOSIT-CUM-PERFORMANCE GUARANTEE DEPOSIT
Seal & Signature of Bidder
8.1 The successful bidder has to submit the security deposit-cum-performance deposit
by DD/Bank Guarantee within 15 days of issue of LOA.
8.2 The successful bidder will be required to pay an amount equivalent to 10% of the
value of the order (END cost) as a Security Deposit for satisfactory execution of the
contract and as performance guarantee. Such Security Deposit will be payable
either in DD payable at Vadodara / Bank guarantees from Scheduled / Nationalized
Banks will be acceptable. If the amount of security deposit payable exceeds Rs.
50,000/- Bank Guarantees will be furnished. The Bank Guarantees furnished
should have clear one-time validity till the completion of the order in all respect and
up to the expiry of the Guarantee period of 36 months + 1 month = 37 months
from the date of Commissioning of OPGW. Bank Guarantee for interim period
will not be allowed. If by any reason the contract period is extended, then contractor
should undertake to renew the Bank Guarantee at least one month before the
expiry of the validity failing which Board will be at liberty to redeem the same,
without entering into further correspondence in the matter.
8.3 No interest will be allowed on amount of Security deposit.
8.4 The Security Deposit-cum-performance Guarantee deposit as above on total shall
be kept deposited up to 3 years from the date of charging of OPGW.
8.5 This security deposit is for the performance of contract and the same is liable to be
forfeited by the GETCO in event of non fulfillment of the term and conditions of this
contract by the contractor.
8.6 Corporate Guarantees are not admissible.
8.7 The ‘Signing of Contract ‘and ‘Contract Agreements’ will be done as per prevalent
GETCO Terms and Conditions.
8.8 A/T shall be issued on receipt of Bank Guarantees, contract agreement & Indemnity
Bond within 30 days of issue of LOA.
9.0 GUARANTEE PERIOD:
Total material supplied and work executed shall be covered under guarantee period
against any defect in materials, poor workmanship or defect/ wrong design etc. for a
period of 3 years from the date of charging of OPGW.
10.0 PENALTY FOR DELAY:
10.1 The tenderer should note that the completion time allowed for carrying out the work
should be strictly observed. Any delay that may take place in supply and erection
beyond Contractual cut-off date stated as per stipulated delivery period shall be
subject to the penalty at the rate of ½ % of the contract value per week plus GST
as applicable on delayed work (supply and erection work) with a ceiling of 10% of
the total contract value plus GST as applicable.
10.2 In event of failure of the Contractor to pay the amount of Penalty as demanded, the
Owner shall be entitled to deduct the amount of Penalty for delay from the
amounts payable to the Contractors under any bills raised under this contract
or any other amount payable under any other contract with the GUVNL and its
Subsidiary companies i.e. GETCO, GUVNL, GSECL, MGVCL, DGVCL, PGVCL,
UGCVL. It is permissible for the Owner to adjust the amount of Penalty of delay
against any Bank Guarantee furnished by the Contractor under this contract or any
other contract with GUVNL and/or its subsidiary companies.
Seal & Signature of Bidder
10.3 Tenderer shall have to supply all materials to match with the erection activities.
11.0 COMPLETION PERIOD:
11.1 Overall Completion period for this Contract will be as below;
Supply, Erection (Laying), Testing & Commissioning of OPGW cable (24 F &
LILO Section 48 Fiber) by replacing existing Earth wire on existing critical
66kV Tower Transmission Lines .: 24 (Twenty-Four) months from the date of
11.2 No mobilization period, idling or stoppage period will be allowed during this period of
11.3 The completion date will be deemed to be the date on which all works on the
Contract are demonstrated to be complete to the satisfaction of the Board/Engineer
and is complete in all respects as per the terms and conditions of this Contract.
12.0 Presentation of Bills
12.1 Monthly RA bills for 80% value of the supplied tower material and work executed
including cost of tower material and line material consumed is to be prepared in
triplicate and submitted to Site Engineers in-charge of the work, for necessary
payment. These bills shall be serially numbered with suffix SE.
12.2 10% payment out of balance 20% shall be released on completion of line work,
handing over and acceptance by the Site Engineers in charge after rectification
work if any and settlement of material account according to actual quantity utilized
for completion of line. No extra payment will be release for to material which is not
required for completion of line if supplied excess during execution work.
12.3 Balance 10% payment shall be released only after finalization of material account
and passing of final bill only. The contractor has to submit the final bill along with the
material consumption statement and other required data of the work carried out
within 3 months from the date of completion of work. These bills shall be serially
numbered with suffix SE.
12.4 All the bills in accordance with the above clauses must be submitted with the following
a) Item wise work done during billing period.
b) Item wise cumulative work done.
c) Account for material consumed and balance stock.
12.5 For non-submission or part submission of above information, an additional 5%
amount of the respective RA bill shall be withheld and shall only be released at the
time of final bill.
12.6 Payment of ROW compensation amount will be given as below only after
submission of necessary supporting documents as listed at GCC 86.2.
1) 40% amount after completion of foundation work
2) 40% amount after completion of erection work
3) 20% amount after completion of stringing work in all respects
The contractor shall make payment towards Right of Way / Way leave
Clearance / Tree-crop damages etc. as per GoG Tharav dated 14.08.17
however, GETCO shall make payment towards Right of Way / Way leave
Clearance / Tree-crop damages etc. as per awarded rate only. In no case, the
Seal & Signature of Bidder
contractor shall be entitled for any escalation to the compensation over and
above the awarded rate.
Bidder should note that Way leave clearance for execution of work and
compensation for Right of Way / Way Leave / Tree-Crop damages etc. to be
paid as per GoG guideline dated 14-10-2024,02.12.2024 & 28-02-2025. is in
scope of GETCO.
12.7 During construction of the proposed transmission line, if it is required to carry out
any modification/shifting/repair of existing transmission line then compensation
towards damage of tree-crop etc. shall be paid only. In such cases, the
compensation as per GoG Tharav shall not be applicable.
12.8 The Bidder will be deemed to be very well familiar with the route of the
transmission line before submitting an offer. Notwithstanding the difficulties of
terrain, location approaches, way leave and other obstructions the price quoted for
all the items of erection shall not undergo any change at any stage or granted by
the GETCO for any special rates / consideration.
12.9 For necessary payment against each consignment of material along with 100%
taxes, duties, F & I shall be duly recorded in the form of TRC & SR note by the
field office, which shall be now uploaded on Vendor Management System
(VMS) Portal, www.vms.guvnl.com including invoice, documents which are
digitally signed by Vendors / Suppliers. The supporting documents duly
signed, stamped and scanned are required to be uploaded. The VMS portal
also provides ‘real time’ tracking of invoice status, to monitor the process of
submissions and to receive timely updates.
13.0 PRICE VARIATION: (NOT Applicable)
Price variation will be applicable only for steel tower materials (including nut-
bolts) and ACSR panther conductor ,Hardware and accessories of conductor
and Earth wire as per the formulae given below;
13.1 For Tower material: (NOT Applicable)
The latest revised PV formula for steel tower materials (including nut- bolts) is as
P0 SBLR SBIR Zn W
100 SBLRo SBIRo Zno W0
P = Price payable as adjusted in accordance with the above formula.
P0 = Price quoted/confirmed.
SBLR0 = Price of Steel Blooms- Retail
This price is as applicable for the month, ONE month prior to the
date of tendering.
SBIR0 = Price of Steel Billets- Retail
This price is as applicable for the month, ONE month prior to the
date of tendering.
Seal & Signature of Bidder
Zn0 = Price of Electrolytic high grade zinc
This price is as applicable for the month, ONE month prior to the
date of tendering.
Wo = All India average consumer price index number for industrial
workers, as published by the Labour Bureau, Ministry of Labour,
Govt. of India (Base: 2016 = 100)
This index number is as applicable for the month, THREE
months prior to the date of tendering
SBLR = Price of Steel Bloom-Retail
This price is as applicable for the month, TWO months prior to the
date of delivery.
SBIR = Price of Steel Billets-Retail
This price is as applicable for the month, TWO months prior to the
date of delivery.
Zn = Price of Electrolytic high grade zinc
This price is as applicable for the month, TWO months prior to the
date of delivery.
W= All India average consumer price index number for industrial
workers, as published by the Labour Bureau, Ministry of
Labour, Govt. of India (Base: 2016 = 100)
This index number is as applicable for the month, FOUR months
prior to the date of delivery.
a) PV clauses are applicable to only for tower material & ACSR / AAAC conductor in
supply contract and other items are on FIRM price during entire execution of work.
b) The price variation amount in the ex-works price of fabricated tower members
(including bolts & nuts) calculated by the above formula shall not be subject to any
ceiling, whatsoever.
c) The price variation formula will be applicable from the date of inspection / waival of
inspection for the material offered.
d) The price variation will be applicable during contractual delivery period only.
However, any decrease in the price variation during delayed period shall be
e) Price variation shall not be allowed beyond the original delivery date unless
specifically stated in the time extension letter. As a rule, no price adjustment shall
be allowed for the period of delay for which the supplier is responsible; however,
purchaser will be entitled for any decrease in the prices during this delayed period.
f) In case of non-publication of applicable indices on a particular month, which
happens to be the applicable month for price variation purpose, the published
indices prevailing immediately prior to the particular month shall be applicable.
Seal & Signature of Bidder
g) If the price adjustment amount works out to be positive, the same is payable to the
contractor by the owner and if it works out to be negative, the same is to be
recovered by the owner from the contractor.
h) No price variation will be allowed on the freight and insurance component of FOR
destination prices.
i) No price variation will be allowed on zinc in case of conductor.
j) The supplier has to submit PV bills (Negative / Positive) along with supporting
documents / IEEMA circulars necessary for calculation of PV bills along with bills for
payment against SR Notes. To claim the price variation successful bidder has to
submit the supporting documents duly notary certified copy of IEEMA circulars, PV
calculation sheet etc. along with their invoices.
k) The base date for the above Price Variation formula will be first day of the month
prior to opening month of the Tender.
l) In the above price variation formula, subscript “0” refers to indices as on 30 days
prior to the date of Bid opening (referred to base date indices). Subscript “1” refers
to the indices as on 60 days prior to date of inspection / waival of inspection of the
material offered.
13.2 For Price Variation for Conductor: (Not Applicable)
Base date for price variation will be 1st working day of the month, one month prior to month
of opening of tender.
A. For ACSR Dog, Panther, Zebra & Moose Conductor
Sr. Sign = Description of Sign
Revised Ex-works price of conductor to be paid by Corporation
The average of prices as on first day of the previous calendar
month of the due date of the tender in Rupees of E.C. Grade
Aluminum wire Rods per MT exclusive of E.D. and ST as notified
3 Po = Quoted Ex-factory price per Km. of conductor.
4 X = This is the multiplication constant to be adopted for computing
price Variation per Km. of the finished goods, which is as under:
ACSR Dog Conductor = X =
ACSR Panther Conductor = X =
ACSR ZEBRA Conductor = X =
ACSR Moose Conductor = X =
P.V. will be applicable from the base date from first day of the previous calendar month
of the due date of the tender and up to first day of the previous calendar month of the
final date of contractual delivery period without ceiling
Seal & Signature of Bidder
For claiming the price variation, you shall have to submit the proof of increase of prices
viz. CACMAI circular.
Same as Ao except price shall be as applicable on first working
day of the previous calendar month in which conductor is offered
for inspection as per the delivery schedule and contractual
delivery period only.
6 So = The average of prices as on first day of the previous calendar
month of the due date of the tender in Rupees of High Tensile
Galvanized Steel Wire per MT exclusive of E.D. and ST as notified
7 Y = this is the multiplication constant to be adopted for computing
price. Variation per Km. of the finished goods, which is as under:
ACSR Dog Conductor = Y =
ACSR Panther Conductor = Y =
ACSR ZEBRA Conductor = Y =
ACSR Moose Conductor = Y =
8 Sr = Same as So except price shall be as applicable on first working
day of the previous calendar month in which conductor is offered
for inspection as per the delivery schedule and contractual
delivery period only.
Please note that price variation will not be allowed on ZINC.
1) In Ar & Sr above, Conductor offered for inspection means date of readiness of
Material shown in inspection call.
B. For AL-59 Conductor
Sr. Sign = Description of Sign
Ex. Works price payable in Rs. per km as adjusted in accordance
with the price variation clause
2 P0 = Ex. Works price quoted / confirmed in Rs. per Km
3 ALo = LME CSP Average of Aluminum (refer notes). This price is as
applicable on the 1st working day of the month, one month prior to
the date of tendering.
4 W0 = All India average consumer price index for industrial workers, as
published by the Labour Bureau, Ministry of Labour, Govt. of India
(Base 2016 = 100). This index number is as applicable on the first
working day of the month, three months prior to the date of
The above prices and indices are as published by IEEMA vide, circular reference
number IEEMA/PVC)/AL Conductor-LME/--/--- One month prior to the date of
For example, if date of tendering falls in December 2017, applicable prices of Aluminum
(ALo) should be of November 2017 and all India average consumer price Index no. (Wo)
should be for the month of September
5 AL = LME CSP Average of Aluminum (refer notes). This price is as
applicable on the 1st working day of the month, one month prior to
the date of delivery
6 W = All India average consumer price index for industrial workers, as
published by the Labour Bureau, Ministry of Labour, Govt. of India
(Base 2016 = 100). This index number is as applicable on the first
Seal & Signature of Bidder
working day of the month, three months prior to the date of
For example, if date of delivery is December 2017, applicable prices of Aluminum (AL)
should be of November 2017 and all India average consumer price Index no. (W) should
be for the month of September
The above prices and indices are as published by IEEMA vide, circular reference
number IEEMA/PVC)/AL Conductor-LME/--/--- One month prior to the date of delivery.
The date of delivery is the date on which the Conductor is notified as being ready for
inspection / dispatch (in absence of such notification, the date of manufacturer's
dispatch note is to be considered as the date of delivery) or the contracted delivery date
(including any agreed extension thereto), whichever is earlier
1) Price of raw material is exclusive of GST and other central, state or local taxes etc.
2) Price of LME average Cash SELLER Settlement price of Primary Aluminum in US$
per MT as published by London Metal Bulletin (LME) including Premium for
Aluminum Ingot in US$ per MT is converted in Indian Rs. /MT using exchange rate
and adding applicable customs duty.
Conditions of conductor PV (Price Variation):
1. For the supplies made during the contractual delivery period and matching with the
scheduled date of delivery, price shall be payable in accordance with the price
variation formula as per the purchase order. (With positive/negative variation as the
2. For delayed deliveries but within contractual delivery period, price shall be payable
at the lower of the following:
a. Worked out with indices applicable for the schedule date of delivery of materials
b. Worked out with indices applicable for the actual date of delivery of materials /
3. For delayed deliveries and also beyond the contractual delivery period, price shall
be payable at the lower of the following but subject to GETCO accept the materials:
a. Worked out with indices applicable for the schedule date of delivery of materials/
b. Worked out with indices applicable for the actual date of delivery of materials/
c. Worked out with indices applicable for the last date of contractual delivery of
materials/month
4. The pre-ponement of delivery should not be entertained to avoid the inventory
carrying cost unless it is extremely essential for the work under execution.
However, the prices as worked out indices applicable for actual date of delivery of
materials / month shall be payable.
5. The date of delivery is the date on which the material is notified as being ready for
inspection/dispatch subject to condition that material is received within 15 days for
Gujarat base suppliers / 21 days for outside Gujarat base suppliers from the date of
dispatch instruction. Otherwise actual date of receipt of material at store is to be
6. The supplier will have to submit all supporting documents like IEEMA Circulars, PV
Calculation sheet etc. duly attested along with invoice.
7. For delayed delivery beyond schedule delivery date, the penalty shall be applicable
as per A/T (P.O.) terms.
Seal & Signature of Bidder
13.3 PRICE VARIATION: For Supply of Hardware and Accessories of
Conductor and Earth wire: (Not Applicable)
Base date for price variation will be 1st working day of the month, one month prior to month
of opening of tender.
FORMULAE AS PER IEEMA CIRCULAR Dtd. 01.04.14
(A) Transmission line accessories and hardware containing both Aluminum and Steel:
(B) Transmission line accessories and hardware containing only Aluminum:
(C) Transmission line accessories and hardware containing only Steel:
P = Price payable as adjusted in accordance with the above formula
P0 = Price quoted / confirmed
AL0 = Price of EC Grade Aluminum Ingots (refer notes). This price is applicable on the
1st working day of the month, one month prior to the date of tendering.
Zn0 = Price of Electrolytic high grade zinc (refer notes). This price is applicable on the
1st working day of the month, one month prior to the date of tendering.
SBIR0 = Price of Steel Billets-Retail (refer notes). This price is applicable on the 1st
working day of the month, one month prior to the date of tendering.
W0 = All India average consumer price index number for industrial workers, as
published by the Labour Bureau, Ministry of Labour, Govt. of India (Base 2001 = 100).
This index number is as applicable on the first working day of the month, three months
prior to the date of tendering.
For example, if date of tendering falls in October 2014, the applicable prices of
Aluminum (AL0), Zinc (Zn0) and Steel Billets-Retail (SBIR0) should be for the month
September 2014 and all India average consumer price index number (W0) should be
for the month of July
The above indices are as published by IEEMA vide IEEMA circular reference number
IEEMA(PVC)/TLA&H(R-3)/_/_ prevailing as on first working day of the month ……. i.e.,
one month prior to the date of tendering.
AL = Price of EC Grade Aluminum Ingots (refer notes). This price is applicable on the 1st
working day of the month, two months prior to the date of delivery.
Zn = Price of Electrolytic high grade zinc (refer notes). This price is applicable on the 1 st
working day of the month, two months prior to the date of delivery.
Seal & Signature of Bidder
SBIR = Price of Steel Billets-Retail (refer notes). This price is applicable on the 1st
working day of the month, two months prior to the date of delivery.
W = All India average consumer price index number for industrial workers, as published by
the Labour Bureau, Ministry of Labour, Govt. of India (Base 2001 = 100).
This index number is as applicable on the first working day of the month, four months prior
to the date of delivery.
For example, if date of delivery falls in July 2015, the applicable prices of Aluminum (AL),
Zinc (Zn) and Steel Billets-Retail (SBIR) should be for the month May 2015 and all India
average consumer price index number (W) should be for the month of March
The date of delivery is the date on which the instrument transformer is notified as being
ready for inspection / dispatch (in absence of such notification, the date of manufacturer's
dispatch note is to be considered as the date of delivery) or the contracted delivery date
(including any agreed extension thereto), whichever is earlier.
a) All prices of raw materials considered for arriving at the index number for battery
charger equipment are exclusive of mod vatable excise duty and exclusive of any
other central, state or local taxes, octroi etc.
b) All prices are as on 1st working day of the month.
c) The details of the prices are as under:
1) The price of Aluminum (in Rs./MT) is the average price of EC grade
Aluminum ingots as quoted by three primary producers of Aluminum as per
2) The price of Electrolytic high grade zinc (in Rs./MT) is ex-works price as
quoted by a primary producer of zinc.
The prices of Steel Billet-Retail are the average Retail price of Billets of size 100 mm of all
cities in Rs/MT; as published by Joint Plant Committee (JPC), Kolkata.
For better clarity in place of “Date of tendering”, we may use “Due Date of Technical Bid
As can be seen from above that there are 3 different formulae for different types of
Hardware being procured. Accordingly,
Formula A (TLAH Containing both Aluminum and Steel) of the circular is
applicable to all Hardware and Accessories for ACSR/AL59 conductor like
Single / Double suspension HW with or without counter weight , Single /
Double Tension, Vibration Dampers for Earth wire & Mid span Compression
Joints for ACSR conductor only.
Formula B (TLAH Containing Only Aluminum) is applicable to all
Hardware and accessories for ACSR/AL59 conductor like PA Rods, Repair
Sleeves ,Spacer cum damper ,Rigid spacer and mid span compression
joints for AL59 conductor only. Formula B is also applied in the case of item
“Copper Earth-bond” however, rates of Copper instead of Aluminum have
been considered.
Seal & Signature of Bidder
Formula C (TLAH Containing Only Steel) is applicable to Earth-wire
accessories like Tension-clamps, Suspension clamps ,Cross by clips and
Mid Span Joints.
13.4 Price variation for Erection Portion: (Not Applicable)
13.4.1 Installation (including Civil Works) Price Component
The formula for calculation of the monthly price adjustments for Installation [including civil
works but excluding survey, soil investigation and aviation signal for river crossing towers (if
any)] price component shall be as under:
A. Installation Price Component [including Civil Works but excluding ‘Supply &
Placement of Reinforcement Steel’, ‘Concreting’, Survey, Soil investigation
and aviation signal for river crossing towers (if any)]
ER1 = Price adjustment amount payable on Installation price component
(excluding supply & placement of steel and concreting) for each billing.
ER0 = Value of erection work done (excluding supply & placement of steel and
concreting) in billing period as established by Contract.
A = Wholesale Price Index Number for `HSD’(Individual Commodity)
(monthly) (Base: 2011-12=100), as published by Office of Economic
Advisor, Ministry of Commerce & Industry(www.eaindustry.nic.in)
L = Indian field labour index – namely All India average consumer price
index for Industrial Workers (monthly) (Base: 2016= 100), as published
by Labour Bureau, Shimla, Government of India
(www.labourbureau.nic.in).
a = Co-efficient of ‘HSD’, Value of which shall be between 0.20 & 0.24.
l = Co-efficient of labour, Value of which shall be between 0.56 & 0.60.
and the sum of a & l shall be 0.80.
B. Supply and Placement of Reinforcement Steel
ER1 = Price adjustment amount payable on price components of Supply and
Placement of Steel.
ER0 = Value of supply & placement of steel in billing period as established by
A = Wholesale Price Index Number for `HSD’(Individual Commodity)
(monthly) (Base: 2011-12=100), as published by Office of
Economic Advisor, Ministry of Commerce &
Industry(www.eaindustry.nic.in).
Seal & Signature of Bidder
B = Wholesale Price Index Number for `Manufacture of Basic
Metals’(Group Item) (monthly) (Base: 2011-12=100), as published
by Office of Economic Advisor, Ministry of Commerce &
Industry(www.eaindustry.nic.in).
L = Indian field labour index – namely All India average consumer price
index for Industrial Workers (monthly) (Base: 2016= 100), as published
by Labour Bureau, Shimla, Government of India
(www.labourbureau.nic.in).
a = Co-efficient of ‘HSD’, Value of which shall be between 0.09 & 0.11.
b = Co-efficient of ‘Manufacture of Basic Metals’, Value of which shall be
between 0.63 & 0.67.
l = Co-efficient of labour, Value of which shall be between 0.04 & 0.06.
and the sum of a, b & l shall be 0.80.
ER1 = Price adjustment amount payable on price components of concreting.
ER0 = Value of concreting in billing period as established by Contract.
A = Wholesale Price Index Number for `HSD’(Individual Commodity)
(monthly) (Base: 2011-12=100), as published by Office of
Economic Advisor, Ministry of Commerce &
Industry(www.eaindustry.nic.in).
L = Indian field labour index – namely All India average consumer price
index for Industrial Workers (monthly) (Base: 2016= 100), as published
by Labour Bureau, Shimla, Government of India
(www.labourbureau.nic.in).
B = Wholesale Price Index Number for `Manufacture of cement, lime
and plaster’(Group Item) (monthly) (Base: 2011-12=100), as
published by Office of Economic Advisor, Ministry of Commerce &
Industry (www.eaindustry.nic.in).
C = Wholesale Price Index Number for `Cutting, shaping and finishing
of stone’(Group Item) (monthly) (Base: 2011-12=100), as published
by Office of Economic Advisor, Ministry of Commerce &
Industry(www.eaindustry.nic.in).
a = Co-efficient of ‘HSD’, Value of which shall be between 0.18 & 0.22.
b = Co-efficient of ‘Manufacture of cement, lime and plaster’, Value of
which shall be between 0.25 & 0.35.
Seal & Signature of Bidder
c = Co-efficient of ‘Cutting, shaping and finishing of stone’, Value of
which shall be between 0.18 & 0.22.
l = Co-efficient of labour, Value of which shall be between 0.09 & 0.11.
and the sum of a, b, c & l shall be 0.80.
4.2 i) Subscript 'o' will correspond to thirty (30) days prior to date of opening of Bids.
ii) Subscript '1' will correspond to the month of billing.
4.3 The total price adjustment amount for Installation (including civil works) price
component shall not be subject to any ceiling whatsoever.
5.0 The Bidders are required to estimate and indicate the values of different coefficients
for each of the items in the price variation formulae within the specified range such
that their summation is as specified in the Bidding Documents. Where no value or ‘-’
or ‘shall be furnished later’ is specified against the coefficient, the same will be
deemed to be zero and the fixed component would be suitably adjusted. If the
values of all coefficients in price variation formulae indicated by the Bidder are
within the specified range but their sum exceeds the summation specified in the
Bidding Documents, the values of the coefficients shall be pro-rata adjusted such
that the summation remains as per the provisions of the Bidding Documents. If the
values of all coefficients indicated by the Bidder are within the specified range but
their summation is less than the value specified in the Bidding Documents, the
values of the coefficients as indicated by the Bidder shall be considered as such
and the fixed component in the price variation formulae would be suitably adjusted.
Further, if any of values of the coefficients indicated by the Bidder is out of the
range specified in the Bidding Documents, the lower of the values, as indicated by
the Bidder vis-à-vis lower value of the range for that coefficient specified in the
Bidding Documents, shall be considered and the fixed component would be suitably
6.0 The above price adjustment provision shall be invoked by either party subject to the
following further conditions:
a) For the purpose of Price Adjustment on ex-works price components of the
equipment, the date of shipment for Goods shall mean scheduled date of
shipment or actual date of shipment, whichever is earlier. Scheduled date of
shipment will be ex-works date of dispatch, governed by the accepted PERT
Network/Bar Chart. Similarly, for the purpose of Price Adjustment on
Installation price component, the Billing period shall mean the billing period
as per Contract time schedule i.e., the agreed Bar Chart or actual period,
whichever is earlier. The Billing period for various Installation activities will
be as per agreed Installation Bar Chart indicating monthly schedule of
Installation activities for completion of works. However, when the Employer’s
specific approval for advancement of shipment/installation activities has
been obtained in such case the said advanced date shall be treated as the
schedule date of shipment/installation activities for the purpose of working
out the price adjustment payable.
No price increase shall be allowed beyond the original delivery/ Installation
dates unless specifically stated in the Time Extension Letter, if any, issued
by the Employer. The Employer will, however, be entitled to any decrease in
the Contract Price which may be caused due to lower price adjustment
amount in case of delivery of Goods/ Installation beyond the original
Seal & Signature of Bidder
delivery/Installation dates. Therefore, in case of delivery of
Goods/Installation beyond the original delivery/ Installation dates, the liability
of the Employer shall be limited to the lower of the price adjustment amount
which may work out either on schedule date or actual date of dispatch of
Goods/ Installation.
b) In case IEEMA does not publish any of the price indices, as mentioned
above, the Bidder shall indicate any nationally recognized published index
for respective items and the source of the same shall be furnished in the Bid.
c) In case of non-publication of applicable indices on a particular date, which
happens to be the applicable date for Price Adjustment purposes, the
published indices prevailing immediately prior to the particular date shall be
d) If the Price Adjustment amount works out to be positive, the same is payable
to the Contractor by the Employer and if it works out to be negative, the
same is to be recovered by the Employer from the Contractor.
e) The Contractor shall promptly submit price adjustment invoices for the
supplies made/work done, positively within three (3) months from the date of
shipment/ work done, whether it is positive or negative.
14.0 Penalty Clause:
1. In case if any safety related fatal Elect. / Mech. accident occurred to any
employee of agency or outsider due to negligence or non-compliance of GETCO
safety norms then in addition to the compensation and liability as per statutory
requirement, contractor / agency shall be penalized as under:
Amount of Contract in Rs. Penalty amount
1 Up to Rs. 1 Lac Rs.5000/- plus GST as applicable
2 Above Rs. 1 Lac to Rs. 10 Lacs Rs.40000/- plus GST as applicable
3 Rs. 10 Lacs to Rs.100 Lacs Rs.100,000/- plus GST as applicable
4 > Rs. 100 Lacs 1.0 % Plus, GST as applicable
2.1 The contractor shall inform concerned Ex. Engineer Const/TR in writing within
24 hours of fatal/non-fatal accident occurred to human being.
2.2 The GETCO investigating officer findings in to accident shall be final and
binding to the contractor /Agency.
3. Safety Requirement:
3.1 Kick off Meeting exclusively for safety shall be done in each contract in presence
of contractor’s site in charge and supervisor. Safety document shall be handed
over and vital safety norms and key points of safety related to project shall be
explained and recorded for commitment by erection contractor.
Such records are mandatory for clearing first erection bill.
Seal & Signature of Bidder
3.2 During site visit by GETCO official of Executive Engineer and above rank, the
following checks during execution of work shall be covered.
3.2.1 Safety equipments available and utilize.
(b) Safety belt.
(c) Safety shoes.
(d) Live line Voltage detector
3.2 2 Safety procedure adopted.
(a) Permit to work
(b) Earthing at the place of work.
(c) Adequate supervision.
3.2.3 T & P physical Check. (Healthiness and Quality)
(b) Wire rope and sling.
(c) Earthing rod.
3.3 If above-mentioned safety requirements found violated in any of the above three
conditions shall attract penalty of Rs.1000/-per occasion plus GST as applicable.
(Max.Rs.3000/-- plus GST as applicable for violation of three conditions)
3.4 During subsequent visit, if violation is found, then double penalty shall be deducted
from the bill of the Contractor/Agency.
15.0 As built Tower Schedule:
The Contractor must furnish the as built tower schedule as per the prescribed
format at Annexure- B within 15 days from the date of test charge or commissioning
16. Inter-se Reverse Bidding:
The Inter-se reverse bidding shall be carried out on the same day of price bid
opening. The L1 price shall be put up for starting price for Inter-se reverse bidding.
Inter-se reverse bidding shall be for reducing the price and the bidders have to
reduce their quoted price in decrement of value as decided before start of Inter-se
reverse bidding.
If any bidder bids in last 2 minutes of deadline for submission of bid for Inter-se
reverse bidding then, the time for Inter-se reverse bidding shall be extended for
further 5 minutes from its previous closing time.
Time of the Inter-se reverse bidding shall be intimated to bidder along with the
intimation of price bid opening.
Seal & Signature of Bidder
The procedure to be followed for elimination of Bidders for Inter-se reverse bidding shall be
Sr. No. No. of bidders Particulars
1 1 No scope of bidding. Re-invite tender
2 2 Scope of Inter-se reverse bidding. No elimination.
3 3 or 4 Scope of elimination:
(A) Within 10% of L-1 bidder price - No elimination.
(B) Above 10% of L-1 Bidder price - Eliminate H1
4 5 or more Scope of elimination:
bidders (A) Within 10% of L-1 bidder price - No elimination.
(B) Above 10% of L-1 Bidder price - H1 and H2 to be
17. RIGHTS OF THE OWNER:
Whenever any claim or claims for payments of a sum of money arises out of or
under the contract against the Contractor, the Owner shall be entitled to withhold
and also have a lien to retain such sum or sums in whole or in part from the
security, if any, deposited by the Contractor and for the purpose aforesaid, the
Owner shall be entitled to encash and withhold the amount of Performance Bank
Guarantee or other security, if any, furnished as the case may be. The Owner shall
also have a lien over the same pending finalization or adjudication of any such
claim. In the event of the security is insufficient to cover the claimed amount or
amounts, the owner shall be entitled to withhold and have lien to retain to the extent
of the such claimed amount or amounts referred to above, from any sum or sums
found payable or which at any time-thereafter may become payable to the
Contractor under the same contract or any contract with the Owner or GUVNL or its
subsidiary companies pending finalization or adjudication of any such claim.
Lien in respect of Claims in other Contracts:
a) Any sum of money due and payable, to the Contractor (including the
security deposit) under the contract may be withheld or retained by
way of lien by the Owner against any of its claim in respect of payment
of a sum of money arising out of or under any other contract made by
the Contractor with the Owner or GUVNL or any of its subsidiary
b) It is an agreed that the sum of money so withheld or retained under
this clause by the Owner will be kept withheld or retained as such by
the Owner till its claim arising out of the same contract or any other
contract is either mutually settled or determined by the arbitrator or
competent court, as the case may be, and the Contractor shall have
no claim for interest or damages whatsoever on this account or on any
other ground in respect of any sum of money withheld or retained
under this clause and as may be duly notified to the Contractor.
Seal & Signature of Bidder
PROFORMA FOR CONTRACT AGREEMENT
(Non Judicial Stamp Paper of Rs. 300/-)
This Agreement is made at BARODA the_____________ day of ___________ in the
Christian Year Two thousand four between M/s.
(hereinafter referred to as “THE CONTRACTOR” which expression shall unless excluded
by or repugnant to the contract include its successors or permitted assigns) of the ONE
PART and the Gujarat Energy Transmission Corporation Ltd, having their Head office at
Vidyut Bhavan, Race Course, Baroda 390 007 (hereinafter called “The GETCO” which
expression shall unless excluded by or repugnant to the context include its successors or
assigns) of the other part.
WHEREAS the aforesaid GETCO has accepted the tender of the aforesaid contractors for
_______________ hereinafter called “the works” and more particularly described and
enumerated or referred to in the specification, terms and conditions prescribed in the order
letter, covering letter and other letters and schedule of price which for the purpose of
identification have been signed by Shri ____________________________________ on
behalf of the contractors and by ---------------------------------- on behalf of the GETCO, a
list whereof is made out in the Schedule hereunder written and all of which said documents
are deemed to form part of this contract and included in the expression “The works”
wherever herein used, upon the terms and subject to the conditions hereinafter
AND WHEREAS THE GETCO has accepted the tender of contractors for the construction
of the said works for the sum of ` ___________________ Rupees (_______________
____________________________________________) upon the terms and subject to the
conditions herein mentioned.
NOW THIS AGREEMENT WITNESSESS AND IT IS HEREBY AGREED AND DECLARED
1. The contractors shall do and perform all works and things in this contract mentioned
and described or which are implied therein or there from respectively or are
reasonably necessary for the completion of the works as mentioned and at the
times, in the manner and subject to the terms and conditions and stipulations
contained in this contract, and in consideration of the due provision, executions,
supply and completion of the works agreed to by the contractor as aforesaid the
Board doth hereby covenant with the contractor to pay all the sums of moneys as
and when they become due and payable to the contractors under the provisions of
the contract. Such payment to be made at such times and in such manner as is
provided by the contract.
2. The conditions and covenants stipulated here-in-before in this contract are subject
to and without prejudice to the rights of the Board to enforce penalty for delays and
/ or any other rights whatsoever including the right to reject and cancel on default or
breach by the contractor of the conditions and the covenants as stipulated in the
general conditions, specifications, forms or tender schedule etc. attached with
Seal & Signature of Bidder
The contract value, extent of supply & erection works, delivery dates, specifications
and other relevant matters may be altered by mutual agreement and if so altered
shall not be deemed or construed to mean or apply to affect or alter other terms and
conditions of the contract and the general conditions and the contract so altered or
revised shall be and shall always be deemed to have been subject to and without
prejudice to said stipulation.
List of documents forming part of the contract:
1. GETCO’s Tender Specification No. ____________ and contractor’s offer opened on
2. GETCO LOA No. Dtd. _____ / ______/
3. Contractor’s acceptance of LOA vide letter no. _______________.
4. Contractor’s Partnership Deed dtd. ________________.
5. Contractor’s Power of Attorney / Board Resolution authorizing person to sign on
behalf of Firm.
In witness whereof the parties here to have set their hands and seals this day and month,
year first above written.
1) Signed, sealed and delivered by
(Signature with name, Designation and official seal)
For and behalf of M/s. __________________ (Signature)
In the presence of (Full Name, Address and Signatures)
2) Signed, sealed and delivered by
(Signature with name, Designation and official seal)
for and on behalf of Gujarat Energy Transmission Corporation Ltd Vidyut
Bhavan, Race Course, BARODA - 390
In the presence of name, Full address and Signature:
Seal & Signature of Bidder
E.M.D BANK GUARANTEE FORMAT
Format for EMD BG is attached separately.
Seal & Signature of Bidder
BIDDING SCHEDULE
Sr. No. DESCRIPTION PAGE
Schedules/Annexure to be uploaded online with QR Bid
01 SCHEDULE - 01 – Material
02 SCHEDULE - 02 – Completion period
02A SCHEDULE – 02A – L-2 schedule (Part-I Amendment-I)
03 SCHEDULE - 03 – Financial capability
04 SCHEDULE - 04 – Certificate-A
05 SCHEDULE - 05 – No Deviation Certificate
06 SCHEDULE - 06 – Confirmation of Details of Bidder
07 ANNEXURE – 1 – Details of Firm
08 ANNEXURE – 2 – Details of Experience
09 ANNEXURE – 3 – List of Performance Certificate
10 ANNEXURE – 4 – Undertaking (Part-I Amendment-I)
Schedules/Annexure to be uploaded online with Technical Bid
01 SCHEDULE - 07 – Acceptance letter
02 SCHEDULE - 08 – Performa for Bank Guarantee for S.D / P.B.G
03 SCHEDULE - 09 – Indemnity Bond
04 SCHEDULE - 10 – Detail of Human resources
05 SCHEDULE - 11 – Erection capacity
06 SCHEDULE - 12 – Latest income tax clearance
07 SCHEDULE - 13 – Details of partner / director
08 SCHEDULE - 14 – Memorandum of articles
09 SCHEDULE - 15 – Board resolution
10 SCHEDULE - 16 – Confirmation of attachment
11 SCHEDULE - 17 – Integrity Pact
12 SCHEDULE - 18 – Certificate for Technical Compliance
13 ANNEXURE – X
14 SCHEDULE - 19 – SAFETY CUM INDEMNITY BOND
15 SCHEDULE - 20 – TCS Undertaking
16 SCHEDULE - 21 – Option for Initial advance (Amendment –I of part-I)
17 ANNEXURE-A : OUR ENDEVOUR - Safety a habit
18 ANNEXURE-B : As Built Tower Schedule
Seal & Signature of Bidder
Following materials / equipments shall be procured / arranged by the contractor for
erection of transmission line.
1) 24F/48F OPGW cable / Earth wire and its hardware & accessories as per technical
2) Related splices.
3) Earthling sets.
4) Tools & Tackles required for erection work.
5) FOAC (Fiber Optic Approach Cable) (with installation hardware like ties/ clips /
cleats, conduits, ducts, supports, fittings, accessories etc).
6) Other materials and tools-tackles required for erection
7) Any other item not covered in specifications but is required for successful
completion of project is deemed to be considered and will be the sole responsibility
of the contractor to provide all such items at no extra cost to GETCO.
Signature of Authorized Representative
Company / Agency
Name of tendering Company
Seal & Signature of Bidder
COMPLETION PERIOD: 24 Months
Sub: Supply, Erection (Laying), Testing & Commissioning of OPGW cable (24 F &
LILO Section 48 Fiber) by replacing existing Earth wire on existing critical 66kV
Tower Transmission Lines.
Sr. Description of Supply with Detail Period in working months from the
No. Specification of Service Package - Works date of LOA
Contract (SAC Code 9954) Commencement Completion
Complete Installation of OPGW
Complete Installation of OPGW cable (24 & 48 0
Fibers) including laying, providing required
hardwares, in line splices to be encased in Fibre
Optic Splice Enclosures, Laying & termination of
a fibre optic approach cable required to connect
Overhead Fiber Optic Cable (OPGW) between
the final in line splice enclosure on the
gantry/tower and the Fibre Optic Distribution
Panel (FODP) to be installed within the building
at both the sub-station ends as per technical
Link up of OPGW Cable including all related 0
Dismantling of old Earthwire/OPGW
Dismantling of existing Earthwire/OPGW cable 0
with require accessories and credit to GETCO
Store OR Sub-Station as per instruction of EIC.
24 Fibre (DWSM) OPGW fibre Optic cable 0
Installation Hardware set * & accessories for 0
above OPGW i.e. all cable fittings & accessories
like suspension clamps, tension clamps,
vibration dampers, earthing clamps, down lead
clamps, in-line splice enclosures etc. including;
Pigtails FC-PC type)
a) Fibre Optic Approach Cable -
400 Mtrs - For 66KV S/S
(with installation hardware like ties/
clips / cleats, conduits, ducts,
supports, fittings, accessories etc).
(Any variation in quantities shall be
absorbed by contractor)
48 Fibre (DWSM) OPGW fibre Optic cable 0
Installation Hardware set * & accessories for 0
above OPGW i.e. all cable fittings & accessories
like suspension clamps, tension clamps,
vibration dampers, earthing clamps, down lead
clamps, in-line splice enclosures etc. including;
Pigtails FC-PC type)
a) Fibre Optic Approach Cable -
400 Mtrs - For 66KV S/S &
(with installation hardware like ties/
clips / cleats, conduits, ducts,
Seal & Signature of Bidder
supports, fittings, accessories etc).
(Any variation in quantities shall be
absorbed by contractor)
Signature of Authorized Representative
Company / Agency
Name of tendering Company
Seal & Signature of Bidder
FINANCIAL CAPABILITY
Sr. Details Amount Rs In Remarks
1. Liquid Assets and Income Tax clearance.
2. CA certified Liquid Assets be attached and last Income Tax certificate
3. Audited balance sheet and profit & loss account along with the schedules referred
4. Minimum Average Annual Turnover (MAAT) for last five years.
5. Price of the biggest job carried out.
Signature of Authorized Representative
Company / Agency
Name of tendering Company
Seal & Signature of Bidder
Tender for Supply & Erection of ________________________
Firms Letter Head
CERTIFICATE – “A”
I / We__________________________________ authorized signatory of
M/s.______________________________________ is not related with other firms who
have submitted tenders for the same items under this inquiry / Tender.
Seal of the Firm Signature of the Tenderer
Place: `With Designation.
Seal & Signature of Bidder
No deviation certificate
Sub: Supply, Erection (Laying), Testing & Commissioning of OPGW cable (24 F &
LILO Section 48 Fiber) by replacing existing Earth wire on existing critical 66kV
Tower Transmission Lines.
Reference: Tender enquiry no. ACE(P&C)/Contract/E-467/OPGW/66kV/S&E
Due on date: / /2026
In connection with the above subject and reference I/ We confirm the following:
I / We, the under signed have read and examined the Tender Specifications in tender
mentioned under reference along with the Commercial terms and conditions.
I / We, declare that our Technical Bid is strictly in line with the Tender specifications.
Further, I /We also agree that additional conditions / deviations, if any, found in the
Commercial terms & conditions, our offer shall be out rightly rejected without
assigning any reason thereof.
Seal of the Firm Signature of the Authorized
Representatives of the firm
Name of the Tendering Firm / Agency:
Seal & Signature of Bidder
CONFIRMATION OF DETAILS OF BIDDER
Bidders are required to furnish following information specifying YES / NO
1) Whether the Bid is on percentage basis as called for. Yes / No
2) Whether rebate furnished is in percentage basis as Yes / No
3) Whether the Bid is uploaded by Online. Yes / No
4) Whether all pages of Bid Specifications are sealed and Yes / No
signed by the Bidder.
5) a) Whether the Bidder is registered with Yes / No
GETCO for transmission line erection.
b) In case of “Yes”, please furnish following
i) Registration Letter No. & date.
ii) Class of Registration
c) Whether Bidder is having PF Code No. Yes / No
6) a) Whether EMD paid. ( DD / BG / RTGS Yes / No
b) In case “Yes”, furnish details Yes / No
7) Whether following documents as specified are
a) Human Resources detail. Yes / No
b) Availability of tools, equipments etc. Yes / No
c) Details of orders executed / on hand Yes / No
d) Financial capability. Yes / No
e) Experience as specified. Yes / No
f) Latest Income-tax certificate Yes / No
g) Company's Articles Of Association Yes / No
h) Details Of Partners / Directors Yes / No
i) B.R./P.A. Authorizing Person Yes / No
j) Power of Attorney of Consortium Members Yes / No.
Signature of Authorized Representative of
Name of tendering Company
Seal & Signature of Bidder
DETAILS OF THE FIRM
NAME OF THE FIRM:
1 Address of Registered Office
2 Contact Personal
4 Residential Address
5 Phone Nos. (Office and Residential)
7 Telegraphic code
1 Address of works
2 Contact Personal
4 Residential Address
5 Phone Nos. (Office and Residential)
7 Telegraphic code
Signature of Authorized Representative of
Name of tendering Company
Seal & Signature of Bidder
DETAILS OF THE EXPERIENCE FOR SUPPLY & ERECTION WORK IN LAST FIVE
YEARS FROM THE DUE DATE OF TENDER:
Sr. Name of Order Order Length of Date of Order fully Status if
No Transmis reference no. value line completion executed order under
sion line & Date Yes/No execution
A GUJARAT Energy Transmission Corporation Ltd., GETCO:
B OTHER STATE ELECTRICITY BOARDS:
C PRIVATE FIRMS:
Seal & Signature of Bidder
LIST OF PERFORMANCE CERTIFICATES UPLOADED WITH THE TECHNICAL BID
SR NO Name of the Authority Reference No. & Details of items
by whom certificate is Date
Seal & Signature of Bidder
Acceptance letter
(TO BE UPLOADED ON FIRM’S LETTER HEAD)
The Additional Chief Engineer (Procurement & Contracts)
Gujarat Energy Transmission Corporation Ltd,
We hereby acknowledge, agree and accept your A/T under reference above with terms and
conditions mentioned therein.
Designation ___________________
Seal & Signature of Bidder
FORM OF BANKER’S UNDERTAKING
[For Execution of contracts & performance Guarantee for warranty period]
Format for SD cum PBG is attached separately.
Seal & Signature of Bidder
1. Bank Guarantees to be submitted against SD / EMD as per Cl. No. 12 of GCC &
against Performance Guarantee as per Cl. No. 8 of SCC & wherever applicable
shall be furnished by following banks:
(A) Guarantees issued by following banks will be accepted as SD/EMD on
permanent basis:
i. All Nationalized Banks.
(B) Guarantees issued by following Banks will be accepted as SD / EMD for the
period up to 31-03-2027. The validity cut-off date in GR is with respect to date of
issue of Bank Guarantee irrespective of date of termination of Bank Guarantee.
2. AU Small Finance Bank
3. Bandhan Bank
4. City Union Bank
6. DBS Bank India Limited
8. Dhanlaxmi Bank
9. Equitas Small Finance Bank
10. FEDERAL Bank
15. IDFC First Bank
16. IndusInd Bank
17. Jammu and Kashmir Bank
18. Jana Small Finance Bank
19. Karnataka Bank
20. Karur Vysya Bank
21. Kotak Mahindra Bank
23. South Indian Bank
24. Standard Chartered Bank
25. Tamilnad Mercantile Bank
26. Ujjivan Small Finance Bank
28. Ahmedabad Mercantile Co-Op Bank
29. Nutan Nagrik Sahkari Bank Ltd.
30. Rajkot Nagarik Sahkari Bank Ltd
31. Saraswat Co-Operative Bank Ltd
32. SBPP Co-operative Bank Ltd.
33. SVC Co-Operative Bank Ltd.
34. The Cosmo Co-Op Bank Ltd.
35. The Gujarat State Co-Operative Bank
36. The Surat District Co-Operative Bank
37. The Surat People’s Co-Op. Bank Ltd
38. The Baroda Central Co-operative Bank
39. The Panchmahal District Co-Operative Bank
40. The Kalupur Commercial Co-Op. Bank
41. The Rajkot Commercial Co-Operative Bank
42. The Banaskantha Mercanttile Co-Operative Bank
43. Gujarat Gramin Bank
Seal & Signature of Bidder
Bank Guarantee of other than above mentioned banks towards EMD, SD Cum
Performance Bank Guarantee for Supply & Warranty will not be acceptable.
Seal & Signature of Bidder
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
8. EMD BG Format.pdf
4. MAAT LA Networth Form.pdf
5.POA Of JV Agreement-Format.pdf
6.EMD BG Format.pdf
7.SD cum PBG Format.pdf
8.Form of LD undertaking 1A.pdf
9.Form of LD undertaking 1B.pdf
10.Revised Annexure-C -Joint Deed of Undertaking.pdf
11.Annecure-B -Joint venture agreement.pdf
12.ON - Ammendment for ROW clause Tender Copy.pdf
15.Public Procurement Circular of GOI.pdf
16.Letter for CBuD.pdf
20.Amendment- Structure weight.pdf
21Ammendment for TTR validity 26.02.2026.pdf
Details of packages and total work.pdf
OPGW_66KV_package and line details-Final.pdf
OPGW (24F) specs final-R8-06.06.2023 final 1_compressed.pdf
OPGW (48F) specs final-R2-11.09.2023 final_compressed.pdf
Amend-1 Part-I-66kV Line OPGW E-467.pdf
Part-I Tender Spec-66kV Line OPGW E-467.pdf
Tender Notice with new clause- 66kV line OPGW-E-467.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .