| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹5.9 LAccepted-AOC PARAYIL CHUNAKKARA NADUVIL | L1 | Accepted-AOC l1 | |
| 2 | L2₹7.6 L+₹1.6 L (27.4%)Rejected-AOC | L2 | Rejected-AOC l2 |
Tender Value
₹5.9 L
EMD Value
₹14,825
Closing Date
16 Oct 2024, 6:00 pmClosed
Assistnant Engineer
O/O The Assistant Engineer,Chunakkara GP
Annual Plan-CGP 175/2024-25 Side protection Wall in Chiravarambu colony Road,ward 8 of Chunakkara GP-Road Protection Work
2024_LSGD_695007_1
01/AE/LID EW/CGP/2024-25
Open Tender
Civil Works - Roads
Item Rate
180 days
chunakkara
Please refer Tender documents.
7 documents required · 7 mandatory
₹1,310
Yes
₹14,825
Yes
26 Nov 2024
9 Oct 2024
21 Oct 2024
9 Oct 2024
16 Oct 2024
9 Oct 2024
Amount
Road Side protection work
2.7.D:Dismantling Stone Masonry as per Technical Specification Clause 202.<br> Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of stone masonry, including disposal of unserviceable material and stacking the serviceable material with all lift and lead of 1000 m as per Technical Specification Clause 202.<br> (D) Dry Rubble Masonry
11.1.1.1:Excavation for Structures <br> Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material. <br> I. Ordinary soil <br> (i) Upto 3 m depth
75.7.1:DRY RUBBLE MASONRY with hard stone, including Through/Bond stone in foundation and superstructure including packing to compactness to lines and levels, cost and conveyance of all materials labour charges etc. complete as per approved drawing and relevant technical specifications.
OD91495/2024-2025:DEPARTMENTAL DRY RUBBLE MASONRY _Dry rubble masonry with departmental hard stone, in foundation and superstructure including packing to compactness to lines and levels, cost and conveyance of all materials labour charges etc. complete as per approved drawing and relevant technical specifications.
11.4.4:Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203<br> IV. R.C.C grade M 20
11.8:Supplying, fitting and placingTMT bar reinforcement in foundation complete as per drawings and technical specifications Clauses 1000 and 1202
75.8.1.1.A:Providing Plain cement concrete for wearing coat CC 1:2:4 (1 cement: 2 fine aggregate:4 course aggregate) laid to required slope as required including compaction, finishingand tamping etc .complete. Max. size of course aggregate not exceeding 25mm , mixedin concrete mixer etc complete as per specification (i) Nominal mix (1:2:4)
OD164362/2024-2025: Cod1742630/2022_2023 :Construction of Subgrade and Earthen Shoulders - Construction of sub grade and earthen shoulders with approved materials material obtained from borrow pits with all lifts and leads, transporting to site, spreading grading to required slope and compacted to meet requirement with lead up to 1000 mas per Technical Specification Clause303.1 (With Out Roller) JP
SHIBU NAGOOR
Bidder Name
SHIBU NAGOOR
ABDUL JABBAR
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1083388.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .