Loading…
Loading…
Tender Value
₹12.6 L
EMD Value
₹13,000
Closing Date
7 Sept 2026, 6:00 pm
Executive Engineer Panchayat R&B Division BOTAD
Construction of Library Hall at Ratanpar Village Tal.Gadhada Dist. Botad
337512
nivida 18
Open
Civil Works - Buildings
Works
Botad
5 documents required · 0 mandatory · 5 optional
₹900
Executive Engineer Panchayat R and B Division BOTAD
₹13,000
21 Aug 2026
21 Aug 2026
21 Aug 2026
7 Sept 2026
21 Aug 2026
Name of Work :-Construction of Library Hall at Ratanpar Village (Under 15% Vivekadhin Yojna Year 2026-27)
Tal.Gadhada Dist. Botad
Bill of Quantities
Memorandum showing items of works to be carried out
Item Discription of Item (With Brief Specification and reference to Quantity Unit Rate In Amount
No. book of Specification) Figures
In Figure Rs. Ps
1 Excavation for foundation upto 1.50 M.depth including sorting out 16.20 Cum 212.52
&stacking of useful materials i.e. dispositing the excavated stuff
up to all lead (a)Loose or soft soil.
2 Excavation for foundation upto 1.50 M.depth including sorting out 21.30 Cum 272.57
&stacking of useful materials i.e. dispositing the excavated stuff
up to All lead (b)Dense or Hard soil.
3 Providing and laying cement concrete 1:4:8 (1- Cement : 4- 14.70 Cum 2927.46
coarse sand : 8- machine crushed stone aggregates 40 mm
nominal size) and curing complete excluding cost of formwork in
(A) Foundation and Plinth
4 Providing and laying ordinary cement concrete1:1.5:3 10.50 Cum 4094.10
(1cement,1.5 sand, 3 gradedstone aggregates 20 mm.Nominal
size) and finishing smooth with curing etc. complete excluding
cost of form work and reinforcement for reinforced cement
concrete work in in A) Foundations, footings, base of columns
and mass concrete
5 Providing and laying ordinary cement concrete1:2:4 (1cement, 2 5.90 Cum 10469.21
sand, 4 graded stone aggregates 20 mm.Nominal size) and
finishing smooth with curing etc. complete including the cost of
formwork but excluding the cost of reinforcement of R.C.C. work
in Column (iii) Having cross-sectional area more than
Sq.M.and up to 0.12Sq.M.
6 Brickwork using common burnt clay building brick shaving 0.60 Cum 4214.33
crushing strength not less than 35 Kg/Sqcm. in foundation and
plinth in cement mortar 1:6(1 Cement ; 6 Fine sand) Conventional
7 Filling available excavated earth (excluding rock) in trenches. 22.60 Cum 136.92
plinth, sides of foundations etc. in layers not exceeding 20 cm. in
depth consolidating each disposited layer by ramming and
8 Brickwork using common burnt clay building brick shaving 18.87 Cum 4496.05
crushing strength not less than 35 Kg/Sqcm. in super structure
Upto floor two level in cement mortar 1:6(1 Cement ; 6 Fine sand)
9 Providing and laying cement concrete1:1.5:3 (1cement,1.5sand, 0.51 Cum 7207.39
3 gradedstone aggregates20 mm.Nominal size) and curing
complete, including cost of formwork in sill and sides (R.C.C.
band) but excluding the cost of reinforcement upto All floor level
10 Providing & laying ordinary C.C. 1:1 1/2:3 ( 1 cement ,1 1/2 0.90 Cum 8888.19
course sand, 3 graded stone agg. of 20 mm nominal size )and for
R.C.C. LINTELS incl. Finishing smooth with curring of formwork
but excl. the cost of reinforcement.for above floor upto All Floor
11 Providing & laying cement concrete 1:11/2:3 (1 cement ,11/2 1.40 Cum 7063.33
course sand,3graded stone agg.of 20 mm nominal size) for rein-
forcement concrete CHHAJJAS not exceeding 10cm. thickness
upto floor two level incl. finishing the exposed surface with C.M.
1:3 (1 cement ,3 fine sand) to give a smooth and ever surface,
centering, formwork and curring comp.Excl. the cost of
reinforcement.above plinth Upto All floor level.
12 Providing & laying C.C. 1:11/2:3 (1 cement ,11/2 course sand,3 17.00 Cum 8035.64
graded stone agg.of 20 mm nominal size) and finishing smooth
with curring etc. comp. incl. the cost of formwork but excl. the cost
of reinforcement for R.C.C. work in. (A) Beam :- Having cross
sectional Area 0.085 to 0.12 Sqm.upto All floor level
13 Providing & laying ordinary cement concrete1:11/2:3 (1 cement 10.08 Cum 7258.19
,11/2 course sand,3 graded stone agg.of 20 mm nominal size)
exposed work with curring etc.comp. incl. the cost of formwork but
excluding the cost of reinforce ment for R.C.C. work in. SLAB :-
having more then 10cm. and end upto 13cm. thickness.upto All
14 Providing TMT Bar FE 500/500D reinforcement for R.C.C. work 6176.00 Kg 77.29
including bending, binding and placing in position complete upto
All floor level
15 Providing fixing of Polished Kotah stone frame for Doors & 4.20 Sqm 949.84
wIndows of 15cmx4 cm. Size including necessary holdfasts, holes
for fixtures and fastenings incl. all labour & materials etc. comp
16 Providing fixing of Polished Kotah stone frame for windows of 12.00 Sqm 2398.94
15cmx4cm. Size including ordinary grill fitting,painting the grill,
necessary holdfasts, holes for fixtures and fastenings incl. all
labour & materials etc. comp
17 Providing and laying polished Kota stone slab flooring over 20mm 81.60 Sqm 1019.39
(Average) thick base of cement mortar 1:6 (1-cement : 6-coarse
sand) or L.M. 1.1.5 (1-Lime putty :1.5 - coarse sand) laid over and
jointed with grey cement slurry mixed with pigment to match the
shade of slab including rubbing and polishing etc. complete.
18 Providing and fixing 35mm. Thick Panelled,glazed orPanelled 13.50 Sqm 3933.51
and glazed shutters for doors,windows andclearstory windows
including anodised alluminiumbutt hinges with necessary screws
and Indian TeakWood shutters with-(B) Partical board
panells.12mm. thick including applying primer and two coats of
oil painting etc. complete
19 Providing 15mmthick cement plaster in single coat on fair side of 252.80 Sqm 195.42
Brick/concrete walls for interior plastering upto floor two level and
finished even and smooth in (I)cement mortar 1:3 (1 cement:3
sand) .Upto floor All level
20 Providing 10 mmthick cement plaster in single coat on fair side of 184.00 Sqm 196.27
Brick/concrete walls for interior plastering upto floor two level and
finished even and smooth in (I)cement mortar 1:3 (1 cement:3
sand) .Upto floor two level finished even & Smooth with floating
coat of neat cement slurry.
21 Finishing wall with weather proof exterior emulsion paint on wall 252.80 Sqm 120.26
surface(two coats) to give an required shape even shade after
thoroughly brushing the surface to rempve all dirt, and remains of
loose powdered materials etc complete.
22 Distempering (Two coats) with oil bound distemper of approved 184.00 Sqm 75.68
brand and manufacture and of required shade on wall surface to
give an even shade over and including a priming coat with
distemper primer of approved brand and manufacture after
thoroughly brushing the surface free from mortar dropping and
other foreign matter and also including preparing the surface even
and papered smooth
23 Providing and fixing S.W. gully trap with C.I. grating brick masonry 1.00 No 1292.19
chamber and water tight C.I. cover with frame of 300mm x
300mm size (inside) with standard weight.(i) Square mouth traps.
(A) 100mm x 100mm size P type.
24 Providing, laying and jointing in true line and level 110 diametre 6.00 Rm 876.90
U.P.V.C (Type B) conforming to IS 13592-1992 with one end
plain and other end socketed with rubber ring, & fittings
conforming to ISI 14735-1999 of approved make for drainage
system pipe line, pipe shall be jointed with each other with rubber
lubricant, pipe shall be fixed on wall using of PVC clamp of the
size 110 mm diametre x 149 mm length x 145 mm heigh at every
2000 mm center to center or shall be concealed in walls as
directed including necessary fittings such as bends, shoes etc.
including testing of pipes and joints and jointed with adhesive
solvent cement including cost of all materials.
25 Providing & Fixing Marble Takti of Size 60cm x45 cm. including 1.00 No 505.00
carving & painting the letters related to scheme & year as
Dismentled Material Credit Rs. 0 will be deducted from 1 St R.A. Bill
Rupees Twelve Lakh Sixty Two Thousand One Hundred Thirty Nine and Paise Eighty Six only
I \ We am \ are willing to carry out the work at ……………………… % above\bellow percent ( Should be written in
figures and words ) of the estimated rate mentioned above. Amount of My \ Our tender works put as under.
* Estimated Amount * Estimated Amount
Put to tender Rs…………………… Put to tender Rs……………………
Deduct……..……..% Add……..……..%
In words………………….……………… In words………………….………………
1.The Contractor shall exhibit a board with detailed specification and details of work as directed by the Engineer-In-
Charge for which no extra payment shall be made.
2.The labour cess will be deducted as per prevailing rules i.e. 1% of the work done.
3.GST and Income tax TDS will be deducted at a source while making payments of bills
4.In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as per Govt. G.R.: PRC-10/2017
Cement Consumption/16/C Date:11/05/2017 as stated in
S.O.R. therefore in R.C.C. items where there is a change as per actual mix design the cost
of difference of cement consumption have been deducted from the rate of original item at the rate of input rate mentioned
in all the tender.
Signature of Contractor
Deputy Executive Engineer Executive Engineer
Panchayat R.& B. Sub Division Panchayat R.& B. Division
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
3 Test Schedule.pdf
8 Cement.pdf
BOQ.pdf
Circlular.pdf
SBD Library Hall Ratanpar Village Botad.pdf
Specification.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].