Loading…
Loading…
| # | Company | Amount | Status |
|---|---|---|---|
| 1 | ₹26.2 Laccepted-aoc | accepted-aoc |
Tender Value
₹26.2 L
EMD Value
₹26,155
Closing Date
5 Feb 2026, 4:00 pmClosed
Executive Officer
Sri Trikoteswara Swamy Temple, Kotappakonda(V), Narasaraopet(M), Palnadu Dist
Renovation of Annapurna Satram and Pravachana Mandapam at Sri Trikoteswara Swamy Temple at Kottappakonda Uphill(V), Narasaraopet(M), Palanadu Dist
891953
A2/15/2024-11, Dt. 21-01-2026
OPEN
Civil Engineering Works
PALNADU, ANDHRA PRADESH
8 documents required · 8 mandatory
₹926
₹26,155
20 Feb 2026
22 Jan 2026
22 Jan 2026
( Renovation of Annapurna Satram and Pravachana Mandapam at Sri Trikoteswara swamy Temple at Kotappakonda Uphill (V),Narasaraopeta(M),Palnadu (D). Brick Masonry for partition walls (115 mm thick) in CM (1:5) prop.(Cement:Sand) using Bricks second class or ground moulded (Non-Modular or traditional size) 23 x 11 x 7 cm from approved source having minimum crushing strength of not less than 3.5 N/sq.mm. including cost and conveyance of all materials like cement, sand, bricks, water etc., to site, excluding cost of seigniorage charges on all materials, scaffolding charges and all labour charges like mixing cement mortar, lift charges, curing, complete but excluding cost of steel and its fabrication charges for finished item of work.(APSS No.509 & 501)
Brick masonry for panel walls in superstructure with CM (1:6) prop: (Cement : Screened sand) using common burnt clay bricks of class as per Table- I of IS:1077-1992, Non- Modular or traditional size 23 x 11 x 7 cms from approved source having minimum crushing strength of 35 Kg/Sqcm. including cost and conveyance of all materials like cement, screened sand, bricks, water etc., to site, excluding seigniorage charges, sales & other taxes on all materials and such as labour charges, like mixing cement mortar, scaffolding charges, constructing masonry, lift charges, curing, etc.,and overheads & contractors profit complete for finished item of work.(APSS.NO.501&504)
Plastering 12 mm thick single coat in CM (1:5) with sponge finishing including cost and conveyance of all materials like cement, sand, water etc., to site and all operational, incidental charges on materials and all labour charges for mixing mortar, finishing, scaffolding, lift charges, curing, including cutting Grooves etc., complete for finished item of work as per SS901,903&904
Dismantling, clearing away and carefully stacking useful materials for re-use and disposal of unserviceable materials with 100m lead as directed by Executive Engineer duly taking actual premeasurements before dismantling including all labour charges , overheads & contractor profit etc., complete
Door frame section of 63.5x100mm . The two vertical members are to be joined together with the horizontal member using 8x75mm long MS star full thread screws to be used with reverse forward speed control hand drilling machine . The ready assembled door frame is fixed door frame is fixed to the wall using hold fast or bolt fastweners .A minimum of screws to be provided for each member and min 2no's for horizontal member.(BMT -N83C)
Door frame section of 45x75mm . The two vertical members are to be joined together with the horizontal member using 8x50mm long MS star full thread screws to be used with reverse forward speed control hand drilling machine . The ready assembled door frame is fixed door frame is fixed to the wall using hold fast or bolt fastweners .A minimum of screws to be provided for each member and min 2no's for horizontal member.
Flush door shutters solid bond wood block board type with commercial ply on both faces -30mm thick confirming to is-2022.
providing & fixing 28-30mm thick solid wood polymer composite (WPC) single extruded door shutter with3mm top and bottom rigid layer with an overall density of 750kg/Cum . It will be fixed to the frame using 3inch /4 inch hinges .a minimum of 4 hinges will be required for fixing the door wit the frame.
Preparation and fixing of M.S. heavy grills for Trusses, Stanchions,Heavy beams and Girders using chain pulley block,derek pole arrangements etc., in position including cost of Mild Steel squares/Flats etc.,welding rods,power charges and fixing charges etc., complete.
Providing and fixing factory made uPVC white colour sliding glazed window upto1.50m in height dimension comprising of uPVC multi chambered frame with in-built roller trackand sash extruded profiles duly reinforced with 1.60±0.2mm thick galvanized mild steel section made from roll forming process of required length (shape & size according to uPVCprofile),appropriate dimension of uPVC extruded glazing beads and uPVC extruded inter locks,EPDM gasket,wool pile,zin calloy(white powder coated) touch locks with hook,zinc alloy body with single nylon rollers (weight bearing capacity to be 40kg).G.I fasteners 100x8mm size for fixing frame to finished wall and necessary stainless steel screwsetc. Profile offrame & sash shall be mitred cut andfusion welded at all corners, including drilling of holes forfixing hardware's and drainage of water etc. After fixing frame the gap between frame and adjacent finished walls shall be filled with weather proof silicon sealent over backer rod of required size and of approved quality, all complete as per approved drawing & direction of Engineer-in -Charge inclusive of cost of Single/double glasspanes, wiremesh and silicon sealent.Note: For uPVC frame and sash extruded profiles minus 5% tolerance in dimension i.e. in depth & width of profile shallbe acceptable. Variation in profile dimension in higher side shall be accepted but no extra payment on this account shall be made. Three track three panels sliding window with fly proof SS wire mesh (Two nos. glazed & one no.wire mesh panels) made of (small series) frame 92 x44mm & sash 32 x 60 mm both having wall thickness of 1.9 ±0.2 mm and single glazing bead of appropriate dimension (Area of window upto1.75 sqm)
VRCC M-20 grade design mix (cement :fine aggreegate: coarse aggregate) corresponding to table 9 of IS456 using (20mm 60%, 10mm 30% & 6mm 10%) size graded machine crushed hard granite metal (coarse aggreegate)from approved Quarry including cost and conveyancej of all materials like cement,fine aggregate(sand)coarse aggregate, water etc, to site and excluding seigniorage charges,sales and other taxes on all materials including all operational incidental and labour charges such as machine mixing , laying concrete, curing etc., complete but excluding cost of steel and its fabrication charges for finished item of work, but excluding centering shuttering :
Providing High Yield Strength Deformed (HYSD) (Fe 415/500 grade as per IS 1786-1979) of different diameters for RCC works , including labour charges for straightening, cutting, bending to required sizes and shapes, placing in position with cover blocks of approved materials and size and tying and lap-splicing with binding wire of 18 SWG, forming grills for reinforcement work as per approved designs and drawings, including cost and conveyance of steel bars, including all wastages such as overlaps, couplings, chairs, spacer bars including cost and conveyance of binding wire, cover blocks and all incidental, operational, labour charges such as cutting, bending, placing in position, tying including sales and other taxes on all materials etc. ,and overheads & contractors profit complete for finished item of work in all floors.( APSS No.126)
Flooring with Non-skid red or white full body Ceramic floor tiles of Size 300 mm x 300mm and thickness between 7-8 mm and 1st quality conforming to IS:13711, IS:13712, IS:13630 (Parts1to15) of any colour and finish in all shades and designs 7.30mm thick , 1st quality and of size as approved by Engineer-in-charge, set over base coat of cement mortar (1:8), 12mm thick using screened sand over CC bed already laid or RCC roof slab, including neat cement slurry of honey like consistency spread @ 3.3 Kgs per Sqm & jointed neatly with white cement paste to full depth mixed with pigment of matching shade, including cost of all materials like cement, sand , water and tiles etc., and overheads & contractors profit complete for finished item of work. (APSS No.701 & 707)
Supply & application of one coat of deco orient base & two coats of acrylic exterior emulsion paint having VOC (Volatile Organic Compound) content less than 50 grams/litre for exterior walls including cost and conveyance of all materials to site, sales & other taxes, incidental, operational and all labour charges etc.,and overheads & contractors profit complete for finished item of work in all floors.
Supply and fixing of P.V.C.pipes including cost and conveyance of all materials etc,. complete.
(b)2 1/2'' pipe
(d)4"-nahany trap
(e)4'' Y- bend (single
(f)4'' T (single)
Supply and fixing of C. P.V.C.pipes including cost and conveyance of all materials etc,. complete.
Supply and installation of Pre-painted Galvanized Trapezoidal Profile Roofing sheets with 0.50mm thickness, Coating: Zinc coating Z120 GSM.Tensile Strength: 550 MPA. Paint coating: Regular Modified Polyester painting. Painting Thickness (Top): 18 to 20 Microns,(Bottom): 5 to 7 Microns. Sheet Width: 1.020, Length: Maximum 12 Meters with Regular Range Colours including cost and conveyance of all meterials and labour charges ctc; complete per finished item of work; as per drawing and as directed by Engineer In-charge.
Flooring with vitrified tiles with matt finish of size 600x600 mm and thickness between 9-10 mm 1st quality confirming to IS:13711,IS:13712,IS:13630 (Parts 1to 15) of any colur and finish in all shades and designs. as per the approved flooring pattern as directed by the Engineer-In -Charge, laying tiles using spacers of 2mm thick, set over a base coat of CM (1:8) prop. 12mm thick using screened sand over CC bed already laid or RCC roof slab , including neat cement slurry of honey like consistancy spread @ 3.3 kgs per Sqm. and jointed neately with white cement paste to full depth mixed with pigment of matching shade including cost and conveyance of all materials like cement, sand, water, tiles, white cement etc,.(APSS.No.701& 707)
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
BId Document- below 50 lakhs.doc
TENDER_DOCUMENT • 0.36 MB
BOQItems- kotappakonda annapurna satram.xls
TENDER_DOCUMENT • 0.16 MB
DECLARATION.docx
TENDER_DOCUMENT • 0.02 MB
Renovation of Annapurna Satram Estimate and Data (1).pdf
TENDER_DOCUMENT • 26.87 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .