Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.5 CrAccepted-AOC SEVALUR | SEVALUR | ₹1.5 Cr | L1 | Accepted-AOC L1 |
| 2 | L2₹1.6 Cr+₹80,787.45 (0.52%)Rejected-Finance | ₹1.6 Cr+₹80,787.45 (0.52%) | L2 | Rejected-Finance Above Est rate |
| Sl No | Description | Qty | Unit | DRS Constructions L2 | RRD CONSTRUCTION L1 |
|---|---|---|---|---|---|
| 1.00Strengthening to the road from Kunnagoundanpatty to 2/8 of Perur - Desiyamangalam road (Km 0/0 -2/165) (R-410) | |||||
| 2.00 | Clearing the Scrub jungle including all labour charges for burryingng and burning etc.,Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201. etc. comp. | 3,099.46 | Sqm | 6 ₹18,596.76 Lowest | 6 ₹18,596.76 Lowest |
| 3.00 | Picking 5 cm to 10 cm old metalled surface and sectioning - 1 sq.m | 2,701.33 | Sqm | 23 ₹62,130.59 Lowest | 23 ₹62,130.59 Lowest |
| 4.00 | Earth work excavation and depositing on bank within initial lead and lift in hard gravelly soil for Cutting sidedrain etc, complete. as per SS20 B | 203.14 | Cum | 141 ₹28,642.74 | 140 ₹28,439.6 Lowest |
| 5.00 | Providing and Laying Gravel Soling to compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compaction at optimum moisture content and hire & fuel charges for power roller , water sprinkler and all other incidental charges such as traffic barricading and providing danger lights etc, complete. | 726.43 | Cum | 343 ₹2,49,165.49 | 341 ₹2,47,712.63 Lowest |
| 6.00 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete. | 1,217.22 | Cum | 3,138 ₹38,19,636.36 | 3,120 ₹37,97,726.4 Lowest |
| 7.00 | Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it. | 8,114.8 | Sqm | 86 ₹6,97,872.8 Lowest | 86 ₹6,97,872.8 Lowest |
| 8.00 | Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., | 8,162.05 | Sqm | 20 ₹1,63,241 Lowest | 20 ₹1,63,241 Lowest |
| 9.00 | Providing and laying Bituminious concrete to 25 mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5 | 204.05 | cum | 12,561 ₹25,63,072.05 | 12,489 ₹25,48,380.45 Lowest |
| 10.00 | Cost of HM Stone ( 650x150x100mm) | 8 | No | 577 ₹4,616 | 574 ₹4,592 Lowest |
Tender Value
₹1.6 Cr
EMD Value
₹1.6 L
Closing Date
3 Sept 2025, 3:00 pmClosed
District Collector/Chairman
II Floor, DRDA, Collectorate, Karur
Karur District - Package No.TN-07-62-Strengthening of 2 Road works in Thogamalai Block under MGSMT - 2025-2026 - Phase III
2025_RDTN_594128_16
DIPR/4437/Tender/2025
Open Tender
Civil Works - Roads
Item Rate
180 days
II Floor, DRDA, Collectorate
Please refer Tender documents.
9 documents required · 9 mandatory
₹0
₹1.6 L
II Floor, DRDA, Collectorate, Karur
15 Oct 2025
18 Aug 2025
3 Sept 2025
18 Aug 2025
3 Sept 2025
21 Aug 2025
26 Aug 2025
Amount
Strengthening to the road from Kunnagoundanpatty to 2/8 of Perur - Desiyamangalam road (Km 0/0 -2/165) (R-410)
Clearing the Scrub jungle including all labour charges for burryingng and burning etc.,Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201. etc. comp.
Picking 5 cm to 10 cm old metalled surface and sectioning - 1 sq.m
Earth work excavation and depositing on bank within initial lead and lift in hard gravelly soil for Cutting sidedrain etc, complete. as per SS20 B
Providing and Laying Gravel Soling to compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compaction at optimum moisture content and hire & fuel charges for power roller , water sprinkler and all other incidental charges such as traffic barricading and providing danger lights etc, complete.
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it.
Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
Providing and laying Bituminious concrete to 25 mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
Cost of HM Stone ( 650x150x100mm)
Cost of KM Stone ( 1110x350x250mm)
Construction of 2.00M Span RCC slab culvert at CH:230m of Kunnagoundanpatty to 2/8 of Perur - Desiyamangalam road
Earth work excavation for foundation in all Clauses of soils and sub soils to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring struttng and boiling out water whenever necessary etc completed complying with stabdard specification etc., ordinary soil complete
Cement concrete 1:4:8 mix using 40mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more then 15cm thick including all charges etc
BGL - Supplying and erection centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for RCC column footing column plinth beam, beams , roof slabs, staircase steps, bed rock blocls , critical pier etc., suing mild steel.
AGL - Supplying and erection centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for RCC column footing column plinth beam, beams , roof slabs, staircase steps, bed rock blocls , critical pier etc., suing mild steel.
Cement concrete 1:3:6 mix (one cement two sand and four aggregate ) using 40mm gauge hard broken granite stone jelly for foundation including dewatering if found necessary and laid in layers of not more then 15cm thick including all charges etc
Cement concrete 1:2:4 mix (one cement two sand and four aggregate ) using 20mm gauge hard broken granite stone jelly for foundation including dewatering if found necessary and laid in layers of not more then 15cm thick including all charges etc
Supplying and fabrication of steel including cost and conveyance of steel to site and all labour Charges for Staightening, cutting to length etc.,
Reinforced Cement concrete 1:1.5:3 mix using 20mm ISS motar including cost and conveyance including all charges etc
Provision for fixing 20mm Bitumen felt for expansion joint between dirtwall and deck slab etc complete.,
Provision for weep hole pipes etc complete.,
Provision for fixing Tar paper for bearing between Bed block & Deck slab etc complete.,
Construction of Retaining wall at CH:235m of Kunnagoundanpatty to 2/8 of Perur - Desiyamangalam road
Earth work excavation for foundation in all Clauses of soils and sub soils to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring struttng and boiling out water whenever necessary etc completed complying with stabdard specification etc., ordinary soil complete
Cement concrete 1:4:8 mix using 40mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more then 15cm thick including all charges etc
BGL - Supplying and erection centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for RCC column footing column plinth beam, beams , roof slabs, staircase steps, bed rock blocls , critical pier etc., suing mild steel.
Cement concrete 1:3:6 mix (one cement two sand and four aggregate ) using 40mm gauge hard broken granite stone jelly for foundation including dewatering if found necessary and laid in layers of not more then 15cm thick including all charges etc
Provision for weep hole pipes etc complete.,
Provision for Guard stones etc complete.,
Construction of 2.00M Span RCC slab culvert at CH:437m of Kunnagoundanpatty to 2/8 of Perur - Desiyamangalam road
Earth work excavation for foundation in all Clauses of soils and sub soils to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring struttng and boiling out water whenever necessary etc completed complying with stabdard specification etc., ordinary soil complete
Cement concrete 1:4:8 mix using 40mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more then 15cm thick including all charges etc
BGL - Supplying and erection centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for RCC column footing column plinth beam, beams , roof slabs, staircase steps, bed rock blocls , critical pier etc., suing mild steel.
AGL - Supplying and erection centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for RCC column footing column plinth beam, beams , roof slabs, staircase steps, bed rock blocls , critical pier etc., suing mild steel.
Cement concrete 1:3:6 mix (one cement two sand and four aggregate ) using 40mm gauge hard broken granite stone jelly for foundation including dewatering if found necessary and laid in layers of not more then 15cm thick including all charges etc
Cement concrete 1:2:4 mix (one cement two sand and four aggregate ) using 20mm gauge hard broken granite stone jelly for foundation including dewatering if found necessary and laid in layers of not more then 15cm thick including all charges etc
Supplying and fabrication of steel including cost and conveyance of steel to site and all labour Charges for Staightening, cutting to length etc.,
Reinforced Cement concrete 1:1.5:3 mix using 20mm ISS motar including cost and conveyance including all charges etc
Provision for fixing 20mm Bitumen felt for expansion joint between dirtwall and deck slab etc complete.,
Provision for weep hole pipes etc complete.,
Provision for fixing Tar paper for bearing between Bed block & Deck slab etc complete.,
Construction of 1.50M Span RCC slab culvert at CH:1770m of Kunnagoundanpatty to 2/8 of Perur - Desiyamangalam road
Earth work excavation for foundation in all Clauses of soils and sub soils to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring struttng and boiling out water whenever necessary etc completed complying with stabdard specification etc., ordinary soil complete
Cement concrete 1:4:8 mix using 40mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more then 15cm thick including all charges etc
BGL - Supplying and erection centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for RCC column footing column plinth beam, beams , roof slabs, staircase steps, bed rock blocls , critical pier etc., suing mild steel.
AGL - Supplying and erection centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for RCC column footing column plinth beam, beams , roof slabs, staircase steps, bed rock blocls , critical pier etc., suing mild steel.
Cement concrete 1:3:6 mix (one cement two sand and four aggregate ) using 40mm gauge hard broken granite stone jelly for foundation including dewatering if found necessary and laid in layers of not more then 15cm thick including all charges etc
Cement concrete 1:2:4 mix (one cement two sand and four aggregate ) using 20mm gauge hard broken granite stone jelly for foundation including dewatering if found necessary and laid in layers of not more then 15cm thick including all charges etc
Supplying and fabrication of steel including cost and conveyance of steel to site and all labour Charges for Staightening, cutting to length etc.,
Reinforced Cement concrete 1:1.5:3 mix using 20mm ISS motar including cost and conveyance including all charges etc
Provision for fixing 20mm Bitumen felt for expansion joint between dirtwall and deck slab etc complete.,
Provision for weep hole pipes etc complete.,
Provision for fixing Tar paper for bearing between Bed block & Deck slab etc complete.,
Construction of 1.50M Span RCC slab culvert at CH:2160m of Kunnagoundanpatty to 2/8 of Perur - Desiyamangalam road
Earth work excavation for foundation in all Clauses of soils and sub soils to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring struttng and boiling out water whenever necessary etc completed complying with stabdard specification etc., ordinary soil complete
Cement concrete 1:4:8 mix using 40mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more then 15cm thick including all charges etc
BGL - Supplying and erection centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for RCC column footing column plinth beam, beams , roof slabs, staircase steps, bed rock blocls , critical pier etc., suing mild steel.
AGL - Supplying and erection centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for RCC column footing column plinth beam, beams , roof slabs, staircase steps, bed rock blocls , critical pier etc., suing mild steel.
Cement concrete 1:3:6 mix (one cement two sand and four aggregate ) using 40mm gauge hard broken granite stone jelly for foundation including dewatering if found necessary and laid in layers of not more then 15cm thick including all charges etc
Cement concrete 1:2:4 mix (one cement two sand and four aggregate ) using 20mm gauge hard broken granite stone jelly for foundation including dewatering if found necessary and laid in layers of not more then 15cm thick including all charges etc
Supplying and fabrication of steel including cost and conveyance of steel to site and all labour Charges for Staightening, cutting to length etc.,
Reinforced Cement concrete 1:1.5:3 mix using 20mm ISS motar including cost and conveyance including all charges etc
Provision for fixing 20mm Bitumen felt for expansion joint between dirtwall and deck slab etc complete.,
Provision for weep hole pipes etc complete.,
Provision for fixing Tar paper for bearing between Bed block & Deck slab etc complete.,
Strengthening to the road from Thirumalaireddipatti to Gudalur panchayat limit road Km 0/0-0/560 (R-492)
Clearing the Scrub jungle including all labour charges for burryingng and burning etc.,Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201. etc. comp.
Picking 5 cm to 10 cm old metalled surface and sectioning including etc complete
Earth work excavation and depositing on bank within initial lead and lift in hard gravelly soil for Cutting sidedrain etc, complete. as per SS20 B
Providing and Laying Gravel Soling to compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compaction at optimum moisture content and hire & fuel charges for power roller , water sprinkler and all other incidental charges such as traffic barricading and providing danger lights etc, complete.
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it.
Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
Providing and laying Bituminious concrete to 25 mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
Cost of HM Stone ( 650x150x100mm)
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
DRS Constructions (BID ID -1445964)
stage.html
html • 0.04 MB
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .