Loading…
Loading…
Tender Value
₹1.9 Cr
EMD Value
₹1.9 L
Closing Date
15 Oct 2026, 6:00 pm
Ahmedabad Municipal Corporation
Repairing work of breakdown of existing Trunk Main line machineholes near different SPS locations in Central Zone & West zone of AMC area. (ARC Tender) (ARC) (Rs.1.89 Cr) (Single Bid)
348753
2026-2027
Open
Miscellaneous Works
Works
Ahmedabad
1 document required · 1 mandatory
₹3,600
Municipal Commissioner, Ahmedabad
₹1.9 L
24 Sept 2026
24 Sept 2026
24 Sept 2026
15 Oct 2026
24 Sept 2026
Name of Work:- Repairing work of breakdown of existing Trunk Main line machineholes near
different SPS locations in Central Zone & West zone of AMC area. (ARC
Tender) (ARC) (Rs.1.89 Cr) (Single Bid)
Online Submission upto Date :- 15/10/2026 up to 18 : 00 Hrs
Physical Submission upto Date :- 16/10/2026 up to 16 : 00 Hrs
Technical Bid Opening Date :- 17/10/2026 at 17 : 00 Hrs
Detail and Tender available on www.tender.nprocure.com
AHMEDABAD MUNICIPAL CORPORATION
Notice inviting Tender
Competent authority on behalf of Municipal Commissioner of Ahmedabad Municipal
Corporation invites percentage rate sealed tenders from interested contractors for the following
work at different locations within the limit of A.M.C.
1 Name of work Repairing work of breakdown of existing Trunk Main line
machineholes near different SPS locations in Central Zone &
West zone of AMC area. (ARC Tender)
2 Estimated Tender Rs.
3 Tender fee Rs.
(Non refundable) (Demand Draft in favour of Municipal Commissioner, Ahmedabad)
4 Time Limit 12 Months
5 Download of Tender Tenders from the website www.tender.nprocure.com or shall be
Documents down loaded mentioned AS PER TENDER NOTICE INVITED
6 Required registration Register “B” class having in Road Works in PWD in Govt. R&B
/ CPWD / AMC or equivalent register with any other state Govt.
or institutions.
7 Earnest Money Deposit Rs. 1,89,885/- (Demand Draft / pay order / Bank Guarantee in
(Bid security) favour of Municipal Commissioner, Ahmedabad is to be
(1 % of Estimate put to submitted as prescribed as below. Demand Draft/Bank Guarantee
tender) shall be from approved list of AMC of banks and the issuing
branch of bank guarantee shall be of Ahmedabad city only. (As
Per AMC finance Dept . Circular No.10 Dt.01/06/2022)
8 Submission of EMD andTender Fee & EMD should Submitted physically along with
Tender Fees tender documents as described in the invitation of tender should
be submitted to Assistant Manager (PWA), 2nd Floor, B –
Wing, Sardar Patel Bhavan, Danapith, Ahmedabad-380001.
Bid submitted without bid security & tender fee shall be treated
as non responsive and shall be summarily rejected.
9 Mode of sending the The whole tender shall be submitted by two modes.Whole tender
Tender Documents shall be submitted only on www.tender.nprocure.com website as
per Schedule mentioned in Notice inviting Tender.
Tender Fee, EMD, technical bid and other relevant PQ
Documents as per check list given in tender shall be
submitted physically in two copies (Original & duplicate) in
sealed envelope as per Schedule mentioned in Notice inviting
10 Last date of receiving As per Notice inviting Tender / Addendum / Corrigendum. The
Tenders. tenders received after latest schedule date and time will not be
entertained under any circumstances.
11 Submission of Price Bid The Price bid shall be submitted online only. The bidder shall fill
percentage rate on amount of BOQ online only until specified.
Price Bid shall be submitted physically duly signed & seal without
mentioning quoted rated, else it shall be considered as rejected.
12 Opening of Technical bid As per Notice inviting Tender / Addendum / Corrigendum.
13 Tender validity period 120 days from the last date of submission of Tender.
14 Security Deposit Security Deposit shall be at 5 % of the contract value in the form of
bank Guarantee /DD (Bank Guarantee issued from Ahmedabad Branch
only as per para A.4.24).
The security deposit shall be payable in 15 days from date of receipt of
LOI failing which interest will be charged by AMC.
15 Deductions from
a. Retention Money 2 % amount of each Running Bill shall be deducted as a
Retention Money. Such retention money shall be released in the
final bill of the said work.
b. Labour welfare cess Labour welfare cess as per the Act, 1996 (non refundable) shall
be deducted from each running bill.
16 Defect & Liability Period Applicable & refer condition of contract attached over rule as per
form B-1 published by Government.
17 Compansation for Delay If the Contractor fails to complete the work under contract by the
stipulated date, he shall pay liquidated damages of 10% of
remaining work after time limit.
• All the circulars which were published by Authorities of AMC time by time will be
applicable on said Tender and bound to bidder with out any condition.
• Conditional tenders will not be accepted in any case. Municipal Commissioner reserves
the rights to reject any or all the tenders without assigning any reasons thereof.
• The authorized signatory holding Power of Attorney shall only be the Digital Signatory.
In case authorized signatory holding Power of Attorney and Digital Signatory are not the
same, the bid shall be considered non-responsive.
Seal and Signature of the Bidder Additional City Engineer (Drainage Project)
Date: Ahmedabad Municipal Corporation
(On contractor’s Letter Head / certified with Stamp and Sign with Contact Detail)
TENDER DECLARATION FORM
Additional City Engineer
(Drainage Project),
Ahmedabad Municipal Corporation,
Name of Work:- Repairing work of breakdown of existing Trunk Main line machineholes
near different SPS locations in Central Zone & West zone of AMC
I/We the undersigned have carefully gone through and clearly understood the Tender
documents of above mentioned project comprising of Notice Inviting tenders, Articles of
Agreement, Scope of work, Definition of terms, notes Instructions/Information to Bidder,
Condition of Contract, special condition of contract, Appendices, Specifications, Bill of
Quantities, furnished by AHMEDABAD MUNICIPAL CORPORATION.
I/We do hereby offer to execute and complete the whole of the work within the time
specified all in accordance with the specification, designs, drawing and instruction in writing
referred to in the said document and with such materials as mentioned for, at the respective rates
which I/we have quoted in the Price Bid or at such other rates as may be fixed under the
provisions of these conditions.
In the event of this tender being accepted I/We agree to enter into an agreement and
when required, execute the contract, according to your form 1 of agreement as or in default
where of I/we bound myself/ourselves to forfeit the "Earnest Money Deposit."
I/We understand that if I/We shall not enter in agreement within fifteen days or as
decided by AMC from the date of receipt of letter of acceptance, you will forfeit the earnest
money paid by me/us and take necessary action as deemed fit.
I/We have enclosed a Demand Draft / Bank Guarantee as an “Earnest Money Deposit",
for the sum as mentioned in NIT, the full value of which is to be absolutely forfeited to the
Employer If I/We fail to commence the work specified. Otherwise the Employer shall retain the
said sum, as on account of such Security Deposit as provided for in the aforesaid documents.
I/We agree not to employ sub-contractors other than those that may be approved in
accordance with conditions in the aforesaid documents.
I/We understand that Municipal Commissioner is not bound to accept the lowest or any
tender, which are received. I / We also understand & agree that Municipal Commissioner
Reserves the right to allot number of tenders to successful bidders at his sole discretion in case if
I / We am/are lowest in more than one tender.
I/We am/are bound to execute the job if the work order is issued within 120 days from
the date of opening of the tender.
I am bound to execute the work by maintaining all Quality aspects/parameters mentioned
in the tender terms and conditions. I am also bound to submit all supporting Genuine Original
documents as and when asked and if any discrepancy found in such documents as well as in the
executed Work with respect to Quality/Quantity at any stage of work or even after completion of
work, it will be solely my Responsibility. I am bound to prove originality of all documents
submitted by me and if any Documents found false/fake then Municipal Commissioner/AMC
has right to take any action/penalty/punishment against me.
I am also bound that if I/we, indulged into any malpractice and/or used any inferior
quality and/or the construction of road is found to be of an inferior quality under this contract
than in such case Municipal Commissioner/AMC has right to debar/ blacklist permanently.
I/We agree to pay the Government income-Tax, (excluding GST), Octroi duties, Royalty
on material (i.e. Aggregate, Sand etc.) And any other taxes prevailing and from time to time on
such items on which the same are leviable and the rates quoted by me/us are inclusive of the
Yours faithfully
Seal and Sign of Contractor
AHMEDABAD MUNICLPAL CORPORATION
MAHANAGAR SEVA SADAN
DRAINAGE PROJECT
AHMEDABAD MUNICIPAL CORPORATION
ENGINEERING DEPARTMENT
Name of Work :- Repairing work of breakdown of existing Trunk Main line
machineholes near different SPS locations in Central Zone & West zone of
AMC area. (ARC Tender)
Item Description QTY Per Amount
(GWSSB SOR 2022-23 Sec-1. C
Item.no.3 pg.43 )
Providing and casting in situ C.C. in
grade M-15 (approx. corresp. to prop.
1:2:4) (proportions as per mix design or
as per Table 9 of IS 456 2000 in masses
by weigh batching ) using granite,
quartzite trap metal of size 6 mm to
mm for RCC work, including
scaffolding centering, form work,
needle vibrated consolidation, curing
comp. up to 6 meter depth or height
(excluding cost of reinforcement and
neat finishing) with centering and
shuttering/deshuttering etc. comp. for
structure for other than water retaining.
(GWSSB SOR 2022-23 Sec-1.C Item
1. Footing (without form work) 50.00 4732.00 Cu.M
2. Footing for column or foundation
(with form work) 25.00 4906.00 Cu.M
2 C.C. M-25 Control concrete for water
retaining structures (GWSSB SOR
2022-23 Sec-1.C Item no.6 pg.44 )
Providing and cast in situ C.C. in grade
M-25 proportions of ingredients as per
mix design by weigh batching using
granite, quartzite trap metal of size
mm to 20 mm and or 6 mm to 12 mm
including scaffolding centering
formwork, needle vibrated
consolidation, curing and hydraulic
testing etc. complete (excluding cost of
reinforcement) with centering and
shuttering/ deshuttering etc. comp. up to
6 meter height /depth Av. G.L.for all
water retaining structures.
1. Bottom slab or floor slab with
2. Bottom slab or floor slab – without
shuttering 60.00 6705.00 Cu. M
3. Bottom dome / roof dome 5.00 8281.00 Cu. M
4. Slant slab/conical wall or conical
5. Beams /Ring beams/Ring girders 5.00 8347.00 Cu. M
6. up to 15 cm thick 5.00 8597.00 Cu. M
7. Above 15 cm and up to 20 cm 5.00 8262.00 Cu. M
8. Above 20 cm and up to 25 cm 5.00 8006.00 Cu. M
10. Columns 5.00 9195.00 Cu. M
3 Steel /Reinforcement bars
(GWSSB SOR 22-23 Sec-1.C Item
Supplying cutting, bending, binding and
placing in position steel as per plan and
design and as per ISS 2502 including
cost of steel and binding wire for
reservoirs/structures only including lift
up to 6 meter height or depth below
G.L. for all diameters.
9.4 Do – deformed (TMT) bars
confirming to relevant IS Fe – 500 15.00 77504.00 MT
grade for all diameters.
4 Filling available excavated earth
(excluding rock) in trenches, plinth,
sides of foundations etc. in layers not
exceeding 20 cm. in depth consolidation 1500.00 129.10 Cmt
each deposited layer by ramming and
5 Brickwork using common burnt clay
building bricks having crushing strength
not less than 35kg./Sq.Cm. in
foundation and plinth in Cement Mortar 200.00 4011.66 Cmt
1:5. (1-Cement:5- fine sand) (B)
Conventional (upto 10 ton)
6 Cement Plaster (GWSSB SOR 2022-
23 Sec-1.C Item no.12 pg.45 )
A) Cement plaster 20 mm thick in C.M.
1:2 using water proofing compound of
approved quality including finishing
B) – do – Without water proofing
7 Dewatering by pumping set
(GWSSB SOR 2022-23 Sec-E Item
Dewatering by pumping set of
Dewatering by pumping set of required
capacity including temporary platform
carting pumping at site and fixing the
same in position including all
accessories, and fuel and labour etc.
Pump set of Capacity
8 Hiring and operating the 20 KV 3 Phase
Electric Generator for operating
desilting machinery, and lighting and
other requirements with Arranging
diesel to run the D.G. Set Do As
Directed. 8 Hrs Shift. (No payment 600.00 2500.00 Shift
should be allowed for non working
condition of machinery)
(AMC Drainge SOR 2015-2016
Machinary Item No.3 - 12% GST )
9 Providing & Supplying JCB Machine
on rental basis in case of emergency
situation and break down type work &
also during unavoidable condition as
per instruction of engg.incharge , rate
includes all nece. shifting, fuel and
operating charges and stacking of useful
& non-useful materials separately up to
store. (No payment should be allowed
for non working condition of machinery
and for pipe line excavation and laying
10 Providing & Supplying Hitachi
Machine-110 capacity on rental basis
in case of emergency situation and
break down type ork & also during
unavoidable condition as per instruction
of engg.incharge, rate ncludes all
nece. shifting, fuel and operating
charges .(No payment should be
allowed for non working condition of
11 Providing & Supplying Hitachi
Machine-200 capacity on rental basis
in case of emergency situation and
break down type work & also during
unavoidable condition as per instruction 175.00 2700.00 Hrs
of engg.incharge , rate includes all nece.
shifting, fuel and operating charges .
(No payment should be allowed for non
working condition of machinery )
12 Hiring of Hydra / Crane with Driver
(8 working Hours in Day) (GWSSB
SOR 22-23 It.No.7 pg.no.105 Sec.2.E.
(i) Hiring of crane 65.00 6412.47 Day
(ii) Hiring of Hydra
13 Hiring of Tractor with trolley
considering 8 hrs. as working day hours
incl. Driver 150.00 2104.09 Day
(GWSSB SOR 22-23 It.No.7
pg.no.105 sec.2.E. mis)
14 Hiring of Three wheeler carrier
(Chakado Rickshaw) considering
hrs. as working day hours incl. Driver 100.00 1153.24 Day
(GWSSB SOR 22-23 It.No.7
pg.no.105 sec.2.E.mis)
15 Supplying Electric Breaker Machine for
RCC Slab or Asphalt Demolishing
Work on site by using Operator, fuel,
power Supply etc. Complete as
Directed. (No payment should be
allowed for non working condition of 150.00 1071.42 shift
machinery and for pipe line excavation
and M.H. work. Allowed only for break
down work) (AMC Drainage SOR 15-
16 It.No.9 pg.no.7 - 12% GST)
16 Supplying Pneumatic Breaker Machine
for RCC Slab or Asphalt Demolishing
Work on site by using Operator, fuel,
power Supply etc. Complete as
Directed. (No payment should be
allowed for non working condition of
machinery and for pipe line excavation
and M.H. work. Allowed only for
break down work) (Based on
Previously approved rate by C E sir )
(AMC Drainage SOR 15-16 It.No.10
pg.no.7 - 12% GST)
17 Providing And Jointing Stoneware
Pipes Incl. Excavation Up to 2 Mt.
Refilling, Transporting Pipes To Work
Unloading, Lowering In Trench,
jointing material Such As Cement, sand,
Hemp Bitumen As Directed, Incl.
Watering The Trenches Spreading And
Carting away Of Surplus material as
directed by engineer in charge. (Based
on R&B SOR 2023-24)
18 Providing & supplying ISI standard
RCC pipes (of sulphate resisting
cement) in standard length of following
class with socket and spigot joints as
per IS 458-2003 Including EPDM
Rubber ring as per IS 5382-1985
etc.comp. As Directed by engineering
incharge.(Vertically Cast) Class NP4
(GWSSB SOR 22-23 It.No.10.2.B
19 Making connection to the ex.M.H.in
running sewer incl. Dewatering and
other required machinery etc. of
following dia pipes at any convenient
time. All damaged work shall be well
repaired as per instructions.
etc..complete. (Based on Drainage SOR
2015-16 It.no.19 pg.no.4 - 12% GST)
20 RCC precast M.H. Frame & Cover
(GWSSB SOR 22-23 It.No.10.4A
RCC precast M.H. Frame & Cover
Manufacture, supply & Delivery at
store or at site of work precast RCC
M.200 Frame & cover suitable to
drainage M.H. and as per type design &
Drawing including cost of
reinforcement M.S. Angles or Flat,
curing mold work etc.
(i) Frame suitable for 50cm opening of
(ii) Cover suitable for 50cm opening of
21 Supplying, labour for break down
repairing work for activities like
excavation, disliting, removing debris
from trench back filling etc. comp. as
directed by Eng.in charge.
(Ahmedabadcity SOR 2023-24-page
a Labour charges - Mazdoor (Male) 2200.00 493.00 No.
b Labour charges - Supervision for
22 Barricading the entire break down or
excavated area on rental basis using
wooden ballies / M.S.angles at max.
2.00 meter centre to centre, C.G.I.
Sheet, reflective paint / Board out side
to avoid accident & for smooth traffic
diversion & movement including
cautionary board etc. Item also includes
for making temporary sufficient nos of
lighting arrangement through out the
work with necessary required
arrangement. ..The same shall be
removed after completion of work.
(Only for break down work from start to
complete) (AMC Water ARC SOR 15-
16 It.No.35 pg.no.6 - 12% GST)
23 Hire charges of high power metal
detector machine to finding out buried
manholes MH seat cove of SWD
/Drainage line with raising of finding
out MH.rate also included
protection,asphalt cutting,loosing old 5.00 12000.00 No.
manhole seat cover ,brick
masonary,plaster and fixing of MH seat
cover in c.c. and carting debries curing
comp.as per dire. of incharge of work.
24 Conveyance charge of lime , murrum,
building rubbish, earth manure or
sludge, and excavated earth and fly ash 2202.87 235.51 L.S.
upto lead of 5.00 Kms.(R&B SOR
25 Providing Dummy or Plug the
Running Sewer by using M.S. Plate
, safety measures,Labour,mud
pump,D.G. set & Transportation of
the same machinary also inclues
removing of dummy when required and
placed labour & Supervisor remain
present till the work comp.etc. as
a 600 mm dia To 1200 mm dia 15.00 60000.00 No
b Above 1200 mm dia 12.00 90000.00 No
26 Hiring and operating the 60 KV 3 Phase
Electric Generator for operating
desilting machinery, and lighting and
other requirements with Arranging
diesel to run the D.G. Set Do As 100.00 8400 Shift
Directed. 8 Hrs Shift. (No payment
should be allowed for non working
condition of machinery ) ( Based on
Previously approved rate by C E sir )
27 Renovation of manhole
(GWSSB SOR 22-23 Sec-2 D It.no.10
Renovation of manhole by increasing
the height at top including cost of
excavation, refitting of C. I. manhole
frame and cover curing etc. complete
incl. all carting and providing of
materials which is required for the
purpose (except manhole frame and
cover) For all type manhole by
providing RCC 1:2:4 Partition walls
with required reinforcement 25 cm thick
and circular opening with 500mm clear
dia and 0.40 mt. av. ht.
28 Constructing Slab type M.H. Chamber
of the following size including
excavation, refilling, brick bats cement
concrete (1:5:10) of thickness 15 C.M.,
CC Channel (1:2:4) of thickness
C.M., finished 15 mm thick cement
plaster inside & outside (Only for shaft)
in CM 1:3, finishing with cement slurry,
P/F 4 mm dia M.S.Steel HDPE coated
steps 35 cm c/c at 35 cm staggered in
masonary CM 1:5, RCC Slab in CC
1:1.5:3 of thickness 23 C.M., including
Cantering & reinforcement (double jalli
at 15 C.M. c/c bothway 12 mm dia.) but
excluding the cost of Manhole seat
cover etc..completed. of Size 1.00 X
1.40 meter (Inside Clear, M.H. length
should be parallel to the flow, for pipe
dia <= 800 mm) (Based on Drainage
a 1.00 to 2.00 meter depth, (Slab at
Ground level) 5.00 10177.68 Nos.
b 2 to 3 meter depth, (Slab at below
mt. From G.L.) 5.00 19258.04 Nos.
c 3.00 to 4.00 meter depth, (Slab at below
d 5.00 to 6.00 meter depth, (Slab at
below 1.00 mt. From G.L.) 5.00 44050.00 Nos.
e 7.00 to 8.00 meter depth, (Slab at below
29 Providing and constructing Sewer
machine holus, scraper machine hole s
and unit house connection chamber, as
per the type design in brick masonry in
C M 1 5 and inside and outside 20mm
thick plastering in C. M 1.3 necessary
100 mm coping with reinforcement in
RCCM 200 fixing C I steps and fixing
machine hole frame and covers (But
excluding supply of machine hole
frame and covers) over machine hole s
and house connection chambers and
fixing machine hole covers (but
excluding supplying of machine hole
covers) over scraper machine hole etc
complete, providing and fixing safety
chain wherever necessary as per the
stipulations in the type design complete
as per latest CPHEEO manual (excl.
excavation) (GWSSB SOR 2022-23
Item no-2, PG no-101)
A Scraper Machinehole type "S1"
rectangular type for 600 mm dia to
1200 mm dia sewer linepipes and for
depth 2.5m to 9.0m
A.1 Scraper machine hole type "S1" as
above but upto 2.5m 5.00 52319.00 No.
A.2 Extra depth beyond 2.5 m and upto
m depth for type "SI" scraper machine 5.00 31907.00 Rmt.
B Scraper Machinehole type "S2"
rectangular type for 1400 mm dia sewer
line pipes and for depth 2.5m to 9.0m
B.1 Scraper machine hole type "S2" as
above but upto 2.5m 5.00 48103.00 No.
B.2 Extra depth beyond 2.5 m and upto
m depth for type "SII" scraper machine 5.00 20370.00 Rmt.
30 Providing, laying, spreading and
compacting graded stone aggregate to
wet mix macadam specification
including premixing the Material with
water at OMC in mechanical mix plant
carriage of mixed Material by tipper to
site, laying in uniform layers in subbase
/ base course on well prepared surface
and compacting with vibratory roller to
achieve the desired density as per
MoRTH clause 406. (Road SOR 2021-
31 Providing F.R.C. MH seat cover incl.
carting to the work site etc. comp.
F.R.C. Extra Heavy Duty (EHD-35)
Manhole Covers &
Frames Cover : 728mm ø & 100 mm
thick circular cover, 35.00 MT load
design, 100x2mm MS flat allround,
16mm ø plain round bar for lifting the
cover & should be fitted with plastic
cups. Frame : 560 mm ø clear opening,
outer size- 888x888x175 mm. On the 25.00 1375.00 Set
upper periphery of frame 25 x 3 mm
wide MS flat should be well embed in
concrete to protect the edges of frame.
FRC E.H.D.-35 manhole cover & frame
described as above.Drainage SOR
2009-10) SOR - (Jan. 2016) Rates for
work of Drainage pipe line) - 12% GST
32 Excavation in bituminous road as per
required gradient and line including
safety provisions using site rails and
stacking excavated stuff including up to
all required lead cleaning the site etc.
complete for all lifts as
specified.(GWSSB SOR 2022-23 Item
33 Fabricating, supply and erecting in
position Standard Structural steel
sections conforming to IS 2062 for
railing , skywalk, stair, or other works
using ISMB, ISA, ISMC, MS plate, flat,
square bars, pipe, square
pipe,rectangular sections, square
section, tube, etc. including welding,
cutting, wastage, etc. complete. The rate
is inclusive of welding rod, supply &
fixing of correct size nut, bolts,
washers, including one primer coat of
red lead paint conforming IS:102 Zinc 3520.00 126.68 Kg
chromate paint conforming to IS:104
followed by two coat of aluminium
paint as per IS:2339 OR enamel paint of
color as selected by engineer incharge,
with all contractor's materials, labour,
tools & plants, in bolted/ welded
construction as directed by Engineer-in
Charge. The waste cut pieces shall not
be included in the paying quantity. The
work shall be done as per drawing and
specification. The work shall be carried
out as per IS:800, IS:816.(RA)
34 Providing and fixing 1.20 Metre high
fencing with 2.0 Metre long M.S.Angle
posts 40 mm x 40 mm x 6 mm and oil
painting 3coats fixed at 2.5 Mt, C/c.with
five Horizontan lines and two
diagonals of galvanised steel bar bed
wire weighting 9.38 Kg.per100 Metre,
strained and fixed to posts with G.I,
staples including fixing the post sing
round with 0.5M x 0.5.M x 0.5 M.
block in C.C 1:5:10 etc complete.
(Ahmedabadcity SOR 2023-24, Item
code no-22001, Item no-22.2 Page no-
(in words also)
CONTRACTOR'S SIGNATURE ADDL.CITY ENGINEER
& STAMP (Drainage project)
INSTRUCTIONS TO BIDDERS
1. Scope of Bid
1.1 Competent authority on behalf of The Municipal Commissioner, Ahmedabad Municipal
Corporation (referred to as Employer in these documents) invites sealed bids for the
construction of works (as defined in these documents and referred to as “the work”)
detailed in the table given in the Invitation for Bid (hereinafter called as IFB.) from
competent bidder. The bidders may submit bids for the works detailed in the table given
2.0 Source of Funds
Ahmedabad Municipal Corporation has arranged the fund for this project.
3.0 Eligible Bidders
3.1 The Invitation for Bids is open to all eligible bidders meeting the eligibility criteria as
defined in this tender.
3.2 All bidders shall provide Qualification Information and Forms of Bid mentioned in the
Clause-14. An agency that has been engaged by the Employer to provide consulting
services for the preparation or supervision of the works, and any of its affiliates, shall not
be eligible to bid.
3.3 Any entity which has been declared as non-performing by NHAI / GoG / AMC or the
firms those are blacklisted/ debarred for specified period by AMC, Governement of
Gujarat, Government of India or any other entity controlled by it, would not be eligible
to submit the Bid.
4.0 Qualification of the Bidder
4.1 Requires registration:- Register as per Notice Inviting Tender having in Road Works
in PWD in Govt. R&B / CPWD / AMC or equivalent register with any other state Govt.
or institutions.
5.0 DISQUALIFICATION
Even though the bidders meet the above mentioned qualifying criteria, they are subject to
be disqualified if they have,
• Made misleading or false representations in the forms, statements, affidavits and
attachments submitted in proof of the qualification requirements; and/or
• Record of poor performance such as abandoning the works, not properly completing
the contract, inordinate delays in completion, litigation history, or financial failures
etc. or debarring from AMC work etc.
• Tampered the bid document in any manner.
• Colluded with other prospective bidders for this work to arrive at quoted prices for the
purpose of restricting competition.
• Indulged in inducement of any official of AMC and/or their consulting engineer and
other advisors in any manner whatsoever.
• Proposal not submitted in accordance with this tender.
• During validity of the proposal, or its extended period, if any, the bidder changes his
commercial terms.
• The bidder qualifies the proposal with his own conditions.
• Proposal is received after due date and time.
• Commercial proposal is enclosed with the same envelope as technical proposal
• The envelope does not show on the outside the reference of bid and thus gets
opened before the due date of opening.
• The E.M.D. is not deposited in full and in the manner as specified in the clause of
Earnest Money Deposit.
• The tender is in a language other than English or dose not contains its English
Translation in case of other language adopted for tender preparation.
• The tender documents received are not duly signed by authorized person.
• The validity of tender is less than what is stated in the tender.
• Any of the page or pages of tender is/are removed or replaced.
• Any condition which affect the cost.
• If it is joint venture.
5.1 Debarment / Black listing
Notwithstanding the above, the Employer may debar or blacklist any of the bidder(s) for
their misleading or false representations in the forms statements etc. for the period to be
decided by the Employer.
6.0 Cost of Bidding
The bidder shall bear all costs associated with the preparation and submission of his Bid.
Employer will in no case be responsible and liable for those costs.
The Bidder, at his own cost, responsibility and risk, is encouraged to visit, examine and
familiarize himself with the site of Works and its surroundings including source of earth,
water, road aggregates etc. and obtain all information that may be necessary for
preparing the Bid and entering into a contract for construction of the Works. The costs of
visiting the Site shall be at the Bidder's own expense.
8.0 Bidders shall not have any dispute or claim for any kind of compensation in case of,
• If the quantity stipulated in the tender items varies or the scope of work changes and
thereby total amount of work increases / decreases up to any extent.
thereby total amount of work increases / decreases up to any extent.
• If the works gets delayed / postponed for some administrative / technical decision
• If the items stipulated in the tender shall not be executed as per site condition/
requirements. No claim shall be entertained for the same.
• No idle charges shall be paid to contractor for machinery and man power if remain
idle and no claim shall be entertained for the same.
B. BIDDING DOCUMENTS
9.0 Content of Bidding Documents
9.1 The set of bidding documents comprises the documents listed below and addendum (if
1. Notice inviting e-Tender
2. Special conditions of Contract
3. Instructions to Bidders
4. Qualification Information
5. Conditions of Contract
6. Technical Specifications
7. Forms of Bid
8. Bill of Quantities
• The bidder is expected to examine carefully all instructions, conditions of contract,
contract data, forms, terms, technical specifications, forms, Annexes in the bid
document. Failure to comply with the requirements of bid documents shall be at the
bidder’s own risk. Bids which are not substantially responsive to the requirements of the
bid documents shall be rejected.
10.0 Amendment of Bidding Documents
10.1 Before the deadline for submission of bids, the Employer may modify the bidding
documents by issuing addendum.
10.2 Any addendum thus issued shall be part of the bidding documents and shall be placed on
website www.nprocure.com The prospective bidder shall refer to website to check any
addendum before 24 hours of opening of bids. AMC will not give any advertisement for
10.3 To give prospective bidders reasonable time in which to take an addendum into account
in preparing their bids, the Employer may, at his desecration, extend as necessary the
deadline for submission of bids.
10.4 Prospective bidders should attach the addendum made for the work & if fails to do so
than also the changes made through such addendum shall be applicable & bound to the
C PREPARATION OF BIDS
11.0 Language of the Bid
All documents relating to the bid shall be in the English language only.
12.0 Documents comprising bid
The e bid submitted by the bidder shall be in single bid.
To qualify for award of the contract, each bidder must submit the following documents
along with bid:
• Required Registration Certificate
• Other requested documents
• Any other material / information required to be submitted in accordance with
these Instructions to Bidders (ITB)
Failure to submit these certificates/documents shall make the bid non-responsive.
Above original documents in physical form in two copies, one marked as “original” and
other marked as “Duplicate”, shall be submitted in a sealed envelope by 16:00 Hrs on the
date of physical submission of bid and addressed to the addressee given in the NIT duly
super scribed “Name of Work, Bid due date and time, Name and address of the bidder”
13.0 Bid Prices
• The contract shall be for the whole works as described in Bill of Quantity based on the
percentage rate in the Bill of Quantities submitted by the bidder..
• All duties, taxes, (except GST) and other levies payable by the contractor under the
contract, or for any other cause shall be included in the rates, prices and total Bid Price
submitted by the Bidder, except otherwise stated in the Bid document. Employer will
not compensate the bidder (contractor) for any change in duties, taxes and other levies
payable by the contractor under the contract and any other reasons.
• The percentage rate and bid price quoted by the bidder shall be fixed up to the
completion of Work and shall not be subject to adjustment on any account, except where
expressly specified, otherwise, in the contract.
14.0 Currencies of Bid and Payment
The currency of bid and payment shall be in Indian Rupees. All payments shall be made
in Indian Rupees.
15.0 Bid Validity
15.1 Bids shall remain valid for 120 days from last date of submission of tender. A bid valid
for a shorter period shall be rejected by the Employer as non-responsive.
15.2 In exceptional circumstances, prior to expiry of the bid validity (120 days), the Employer
may request that the bidders may extend the period of validity for a specified additional
period. The request and the bidders' responses shall be made in writing or by cable. A
bidder may refuse the request without forfeiting his bid security. A bidder agreeing to the
request will not be required or permitted to modify his bid, but will be required to extend
the validity of his bid security for a period of the extension.
16.0 Earnest Money / Bid Security
16.1 The Bidder shall furnish, a Bid Security of the amount as shown in the Table of IFB as
part of his bid, in the form of Demand Draft / pay order / Bank Guarantee in favour of
Municipal Commissioner, Ahmedabad valid for 120 days.
16.2 The issuing branch of the bank guarantee shall be of Ahmedabad City only.
16.3 Any bid not accompanied by an acceptable Bid Security shall be rejected by the
Employer as non-responsive.
16.4 Any bid having bid security for lesser value and shorter validity period shall be treated as
non-responsive.
16.5 (a) The bid security of the unsuccessful bidders, except for L1, L2 and L3 bidders will be
returned as promptly as possible.
(b) The bid security of the successful bidder, along with second and third lowest tenders,
will be returned when the successful bidder has furnished the required security deposit
and signed the agreement.
16.6 The Bid Security of the Successful Bidder will be discharged when the bidder has signed
the Agreement and furnished the required security deposit.
16.7 The Bid Security shall be forfeited,
a) if the Bidder withdraws the Bid after Bid opening during the period of Bid validity;
b) in the case of a successful Bidder, if the Bidder fails within the specified time limit to
(i) sign the Agreement; or
(ii) Furnish the required security deposit.
(iii)commence the work after signing the agreement within 15 days
16.8 No interest shall be paid by the owner on any tender guarantee. The issuing branch of the
bank guarantee shall be of Ahmedabad City only.
16.9 Bank Guarantee for Earnest Money Deposit should be executed on non-judicial Stamp
papers of requisite value in accordance with the stamp Act applicable to that particular
state of Indian Union, where executed.
16.10 The executing officers of the bank Guarantee for Earnest Money Bid Security shall
clearly indicate in (block letters) his name, designation, Power of Attorney No. / Signing
16.11 Each page of the bank guarantee for Earnest Money Deposit shall be duly
signed/initialed by the executing officers and the last page shall be signed in full,
indicating the particulars as aforesaid under the seal of the Bank.
D. SUBMISSION OF BIDS
17.0 Sealing and Marking of Bids
17.1 The bidder shall submit the Technical Bid only. The Bid shall be sealed in separate
envelopes and the three sealed envelopes shall be sealed in an outer envelope. The Bid
envelopes shall be marked as follows:-
• Complete Tender Document with all necessary qualification related documents (in two
Above two envelopes shall be kept in one envelope and it should be marked as
“Technical Bid” and sealed. This Outer envelope should mention the name of firm of
bidder, his address, contact details & name of the work.
17.2 The inner and outer envelopes
a) Shall be addressed to the Employer at the following address:
Assistant Manager.- PWA,
2nd Floor, B – Wing, Sardar Patel Bhavan,
Danapith, Ahmedabad-380001.
c) Bear the following identification:
Indicate the name and address of the bidder.
• If the outer envelope is not sealed and marked as above, the Employer will assume no
responsibility for the misplacement or premature opening of the bid.
18.0 DEADLINE FOR SUBMISSION OF THE BID
18.1 Complete Bids (including Technical bid and necessary documents) must be received by
the Employer at the address specified in bid information not later than the date indicated
on the face sheet of the document. In the event of the specified date for the submission of
bids declared a holiday for the Employer, the Bids will be received up to the appointed
time on the next working day. The Bidder is further required to submit Documents in
Physical Form on or before the Bid Due Date and before the time of submission as
specified in NIT, at the following address:
Assistant Manager- PWA,
2nd Floor, B – Wing, Sardar Patel Bhavan,
Danapith, Ahmedabad-380001.
18.2 AMC assumes no responsibility for inability of a bidder to submit bids through (n)
procure e-tendering portal on account of delay in submission at bidder's end. Bidder shall
ensure that they submit the bid well before the "Due Date & Time of Bid- Submission".
AMC shall not be responsible if bidder is not able to submit the bid on account of failure
in network/internet connection or any other technical reason.
18.3 The Employer may extend the deadline for submission of bids by issuing an amendment
in accordance with respective Clause, in which case all rights and obligations of the
Employer and the bidders previously subject to the original deadline will then be subject
to the new deadline.
18.4 All bidders are requested to see the website of (n) procure for amendment / corrigendum
18.5 Any Bid received by the Employer after the deadline prescribed in NIT will be rejected
and returned unopened to the bidder.
Any Bid received by the Employer after the deadline prescribed in NIT will be returned
unopened to the bidder.
20.0 NOTIFICATION OF AWARD & SIGNING OF AGREEMENT
The Bidder whose Bid has been accepted will be notified of the award by the Employer
prior to expiration of the Bid validity period by writing, facsimile or e-mail confirmed by
registered letter. This letter (hereinafter and in the Conditions of Contract called the
“Letter of Acceptance” will state the sum that the Employer will pay the Contractor in
consideration of the execution, completion, and maintenance of the Works by the
Contractor as prescribed by the Contract (hereinafter and in the Contract called the
“Contract Price”).
The notification of award will constitute the formation of the Contract, subject only to
the furnishing of a Security Deposit in accordance with the provisions of Clause.
The agreement will incorporate all correspondences between the Employer and the
Successful Bidder. It will be signed by the Employer and the Successful Bidder.
21.0 SIGNING OF CONTRACT AGREEMENT
21.1 The Employer and the successful bidder shall enter into a Contract Agreement within
days after the successful bidder (hereinafter called the Contractor) receives the Letter of
Acceptance, unless they agree otherwise, subject to furnishing the security deposit before
signing the Agreement with the Employer.
21.2 Upon issue of ‘Letter of Acceptance’ to the successful Bidder, the Employer will
promptly notify the other Bidders that their Bids have been unsuccessful and release their
Earnest Money Deposit / Bid Security.
22.0 SECURITY DEPOSIT
22.1 Security Deposit shall be at 5 % of the contract value in the form of bank Guarantee
/DD (Bank Guarantee issued from Ahmedabad Branch only as per para A.4.24). The
security deposit shall be payable in 15 days from date of receipt of LOI failing which interest will
be charged by AMC.
22.2 The security deposit shall be in the form of a Bank Guarantee in the name of the
Employer, from Ahmedabad branch of any Banks mentioned in the clause no. 16.2 of
these tender documents.
22.3 This security deposit shall be released only after the clearance of final bill including pre
22.3 Interest shall be deducted from contractor in case of late submission of security deposit
or late renewal of bank guarantee for the number of days delayed for submission or
discontinuity of the bank guarantee.
22.4 Bank Guarantee to be submitted in the prescribed format enclosed and shall be same
verbatim as per the format. Bank Guarantee shall be submitted on right value of stamp
paper and for correct value of contract.
22.5 Failure of the Successful Bidder to comply with the requirements of Sub-Clause
shall constitute sufficient grounds for cancellation of the award and forfeiture of the Bid
22.6 In case of any contract amendment during execution of the contract enhancing value of
the contract the BG value shall be enhanced accordingly. Validity of BG shall be
commercial terms and conditions of the tender.
22.7 All compensation or other sums of money payable by the Contractor to the Employer
under the terms of this Contract or any other contract or on any other account whatsoever
may be deducted from Security Deposit. Also in the event of the Contractor's Security
Deposit being reduced by reasons of such deductions, as aforesaid, the Contractor shall,
within 14 days of receipt of notice of demand from the Engineer-in-Charge, make good
the deficit in Security Deposit.
22.8 Should there arise any occasion under the Contract due to which the periods of validities
of Bank Guarantees as may have been furnished by the Contractor from time to time, are
required to be extended/renewed, the Contractor shall get the validity periods of such
guarantees extended/renewed, and furnish these to the Engineer-in- Charge one month
before the expiry date of the aforesaid Guarantees originally furnished failing which the
existing Bank Guarantees shall be invoked by the Engineer – in – charge. Also in case of
any deficit in securities on any account as might occur or is noticed, the Contractor shall
forthwith recoup/replace the same with acceptable Security Deposit.
22.9 The Bank Guarantee shall be extended within the expiry dates wherever activities as per
contract are not completed in all respects.
22.10 The Security Deposit less any amount due shall, on demand, be returned to the contractor
after 45 days of completion date / Final Bill paid date which ever is later. No interest on
the amount of Security Deposit shall be paid to the Contractor at the time of release of
Security Deposit as stated above.
22.11 The successful bidder to whom ‘LOI’ has been issued shall enter into an agreement at
Employer’s office within 15 days of.
23.0 Advance Payment and Security
The Employer will not provide any advance payment.
24.0 Dispute Review Expert
In case of all the disputes, decision of the Municipal Commissioner, Ahmedabad shall be
final and binding to the bidder.
25.0 LITIGATION HISTORY
The applicant should provide accurate information on litigation and/or arbitration
resulting from Contractors completed or under execution by him over last five years. If
the details of Litigation History are hidden by the Bidder and later on it comes to the
knowledge of the Employer, the Bidder shall be disqualified for the proposed work and
other appropriate actions shall be taken against the bidder.
DETAILS OF COMPLETED / ONGOING LITIGATION / ARBITRATION
Employer Value of the Reasons/Details for Remarks
Year Name of Project (Rs.) litigation/arbitration showing
Project Present Status
The bidder shall furnish separate table for individual project.
The above information shall be supported with necessary documents otherwise the same
shall be treat as null and void.
A consistent history of arbitration awards? Judgments against the applicants or any
partner of a joint venture may result in disqualification for proposed work.
If the details of litigation History is hidden by the applicant and later on it comes to
knowledge of the employer the bidder shall be disqualified for the proposed work and
other appropriate actions shall be taken against the bidder.
Seal and Signature of the Bidder Additional City Engineer
Date: Ahmedabad Municipal Corporation
GENERAL CONDITIONS OF CONTRACT
1.0 Liquidated Damages
1.1 If the Contractor fails to complete the works within the original or extended time limit,
the Contractor shall pay penalty of 10% of amount of actual remaining work. The
amount of work for which the scope of contractor is reduced shall not be considered for
the calculation of Liquidated Damages.
1.2 Conditions mentioned in the AMC Finance Department Circular AMC no. 18 Date:
23/05/2017 and all latest Circulars shall be applicable.
2.0 Retention Money
2 % amount of each Running Bill shall be deducted as a Retention Money. Such
retention money shall be released in the final bill of the said work. AMC reserves right to
deduct any amount to compensate the poor performance of the contractor i.e. poor
quality or abandoned / incomplete work.
3.0 Subcontracting
3.1 Except where expressly specified in the Contract, the Contractor shall not subcontract
any portion of Work without the approval of the Employer’s Representative. Any
subcontracting shall not relieve the Contractor from any contractual obligations or
responsibility under the Contract.
3.2 The Contractor shall not be required to obtain consent for a subcontract for which the
name of the subcontractor and scope of works activities to be performed by him is
already stated in the contract or supply of material or engagement of labour.
4.1 The Contractor shall employ the key personnel named in the Schedule of Key Personnel
as referred to in the Bid document to carry out the functions stated in the Schedule or
other personnel approved by the Engineer. The Engineer will approve any proposed
replacement of key personnel only if their qualifications, abilities, and relevant
experience are substantially equal to or better than those of the personnel listed in the
4.2 If the Engineer asks the Contractor to remove a person, without assigning reasons thereof,
for his misconduct or inadequacy of technical skills and experience, who is a member of
the Contractor’s staff or his work force, the Contractor shall ensure that the person leaves
the Site within seven days and has no further connection with the work in the Contract.
4.3 No residential accommodation is allowed at the site of work. The labour huts shall not be
erected on the site of work and contractor shall make his own arrangements to provide
such accommodations as per the rules of the local bodies. He shall make his own
arrangements for housing, stores, field office etc. He shall submit a site layout plan
indicating the location of various site facilities to be created by him at his cost for the
execution of work. The Owner shall in no way be responsible for any delay on this
account and no claim on this account whatsoever shall be entertained. All Basic
amenities shall be provided by the Contractor to Labours as per the prevailing labour
5.1 The Contractor shall have full regard throughout execution, completion and defects
liability period to following safety aspects and shall take all necessary steps to ensure
that danger to safety is avoided all the time in respect of,
Safety of the works
• Safety of the Contractor’s employees and all the persons directly or indirectly
engaged by him for the works
• Safety of all the employees including persons working on other contracts of
Employer at the same site of the Employer and Engineers employees engaged at
• Any authorized third party persons on the site.
• Contractor’s plant and equipment
5.2 The Contractor shall provide and maintain at his costs all lights, guards, fencing, warning
signs, barricading, and cones; when and where necessary, or required by Engineer in
Charge or by any duly constituted authority for the protection of the works or for the
safety and convenience of the public or other.
5.3 The Contractor shall take all reasonable steps to protect the environment on and off the
site and avoid damage or nuisance to persons or property of the public and others arising
as a consequence of his method of operation.
5.4 The Contractor shall maintain in good condition all work throughout execution,
completion, and defects liability period. The contractor shall be responsible for and to
make good all injuries, damages and repairs, rendered necessary by fire, rain, traffic,
floods or other causes.
5.5 All the scaffolding work, wherever required for the execution of work, shall be provided
by the contractor. Nothing extra shall be payable on this account. It shall be provided
strictly with double scaffolding system with all the accessories etc. with adjustable
suitable working platforms to access the areas, with ease for working and inspection. It
shall be designed to take all incidental loads. It should cater to the safety features for
workmen. It shall be ensured that no damage is caused to any structure due to
5.6 All temporary warning/ caution boards display shall be provided and displayed during
day as well as night time by the contractor, wherever required and as directed by the
5.7 Arrangement of temporary water and electricity and telephone connection required, by
him, shall be made by the Contractor at his own cost and also necessary permissions
directly from relevant Owners shall be obtained by him under intimation to the Owner.
Also all initial and running charges and security deposit, if any in this regard shall be
borne by him. The Contractor shall abide by all the rules/ bye laws applicable in this
regard and he shall be solely responsible for any penalty on account of violation of any
of the rules and byelaws in this regard.
5.8 In any case if any fatal accident (major or minor) occurs due to poor safety precautions,
the same shall be completely contractor’s responsibility. All the losses due to such
accidents and expenses of legal matters shall be borne by contractor.
5.9 The Contractor shall be responsible for maintenance and watch and ward of the complete
installation and shall also be responsible for any pilferage, theft, damage, penalty etc. in
this regard. The Contractor shall indemnify the Owner against any claim arising out of
pilferage / theft, damage, penalty etc. whatsoever on this account.
5.10 The Contractor shall depute Site Engineer & skilled workers as required for the work.
Necessary protective and safety equipments shall be provided to them by the Contractor
at his own cost and used at site.
6.0 Contractor to keep site clean:
During the execution of the work, the Contractor shall keep the site clean. All wreckage
rubbish, excess materials, temporary works no longer required will be removed from site
7.0 Clearance of site on completion:
The Contractor shall clear away and remove all Contractors equipment, surplus
materials, rubbish, temporary works of every kind.
A. COST CONTROL
8.0 Bill of Quantities
a. The schedule-B shall contain Memorandum showing items for the construction,
installation, testing, and commissioning work to be done by the Contractor.
b. The quantities stated in the schedule B are estimated quantities. The Contractor shall
be paid only quantities calculated after taking measurements of executed work. The
rate stated in the schedule B for each item of work shall apply. The works shall be
measured by the Contractor jointly with the authorized representative of the Engineer
and all particulars required by the representative of the Engineer shall be supplied by
the contractor.
c. The work shall be measured net. No allowance for general or local custom, working
space etc. is to be made.
9.1 The Engineer in Charge shall have power to make any variation of form, quality or
quantity of the works or any part thereof that may, in his opinion, be necessary and for
that purpose, or if for any other reason it shall, in his opinion, be appropriate, he shall
have the authority to instruct the Contractor to do and the Contractor shall do any of the
Increase or decrease the quantity of any work up to any extent included in the
Omit any such work,
Change the character or quality or kind of any such work,
Execute additional work of any kind necessary for the completion of the Works or
Change any specified sequence or timing of construction of any part of work.
9.2 No such variation shall in any way vitiate or invalidate the contract, but the effects, if
any, of all such variations shall be valued in accordance with the following sub clauses.
Provided that where the issue of an instruction to vary the Works is necessitated by some
default or breach of contract by contractor or for which he is responsible, any additional
cost attributable to such default shall be borne by the Contractor.
9.3 The Contractor shall not make any such variation without an instruction of the Engineer.
No instruction is required for quantities varying from those provided for the items in the
contract schedule B.
10.1 The basis for the valuation of variations for addition to the Contract Price shall be as
follows in the same order of priority.
a) Variations in the quantities of work in schedule of quantities shall not vitiate the
b) The contractor shall be bound to execute extra items of work as directed by the
Engineer-in-charge.
c) Contract unit rates for individual items shall apply to varied quantities where there is
a quantity variation.
d) The price variations on extra item will not be given.
e) In case of other non tender items following procedure shall apply.
10.2 If any extra item crops up during the progress of work the same shall be carried out by
the Contractor and he shall be paid at the rate fixed by Employer which shall be fixed as
lowest of the rates derived by rate analysis based on the following three methods. , the
priority of the documents forming the Contract shall be as follows:
(i) If the extra item is included in the S.O.R. of Road & Building Department, Year
2013-14, the rate of extra item shall be that rate and premium (above or below)
quoted by contractor.
(ii) Rate analysis based on prevailing Govt. of Gujarat’s SOR rates.
(iii) Rate analysis based on current market rates. This shall be based on
The material costs, the labour costs, the cost of use of all plant, machinery and
equipment, the cost of all temporary and incidental works, the overheads and the
Contractors profit.
The overheads shall be taken at 5 % of the sum of material costs, the labour costs,
the cost of use of all plant, machinery, and equipment, the cost of all temporary
and incidental works.
10.3 In case of the rate is to be derived from prevailing market rate, the Contractors profit
shall be taken at 10 % of the final rate derived.
10.4 In the event of disagreement, the Engineer in Charge shall fix such rates and prices as
are, in his opinion appropriate and shall notify the Contractor accordingly with a copy to
10.5 The Engineer shall determine provisional rates and prices to enable on account payments
to be included in the Interim Payment Certificates, until rates and prices are agreed as
final by the Employer, the Contractor, and the Engineer.
10.6 The Contractor shall not be entitled to additional payment for costs, which could have
been avoided by giving early warning.
11.1 Payments shall be adjusted for deductions for advance payments, retention, other
recoveries in terms of the contract and taxes at source, as applicable under the law. The
Employer shall pay the Contractor the amounts certified by the Engineer.
11.2 If an amount certified is increased in a later date certificate due to corrections in previous
certificates or as a result of an award from disputes review experts, Contractor shall be
paid such amount only. The Contractor shall not be paid any interest upon such delayed
11.3 Items of the work for which no rate or price has been entered in will not be paid for by
the Employer and shall be deemed covered by other rates and prices in the Contract.
11.4 All payments shall be made in Ahmedabad.
12 Taxes and duties
12.1 The rates are inclusive of all taxes, insurance, labor overhead charges, contractor’s profit,
royalties etc except GST. The Contractor will have to pay all such taxes and duties for
the performance of this Contract. The Employer will deduct from the Contractor’s
monthly and other payments all taxes and duties, which he is bound to recover in
accordance with the applicable law.
12.2 The Contractor shall keep himself fully informed of all acts and laws of the Central &
State and local Governing bodies, all orders, decrees of bodies, tribunals having any
jurisdiction or authority which in any manner affect those engaged or employed, and
anything related to carrying out the work. All the bye-laws lay down by AMC/AUDA
and any other local bodies while executing the work shall be adhered to. All taxes of
local bodies shall be borne by the contractor. The Contractor shall arrange to give all
notices required by any authority and to pay to such authority all the fees that may have
to be paid for the material, plants, equipments etc. The Contractor shall also adhere to all
traffic restrictions notified by the local authorities. He shall protect and indemnify the
Owner and its officials & employees against any claim or liability arising out of
violations of any such laws, ordinances, orders, decree, whether by himself or by his
employees or his authorized representatives. Nothing extra shall be payable on these
13.0 Labour Welfare Cess
As per circular No. GHR/2005/04/CWA/2004/841/M-3 dt. 3/1/05 and G.R. No.
CWA/2004-1831-M(3) dt. 9/12/05 issued by G.O.G. (non-refundable) shall be deducted
from every bills which shall be deposited to Govt. Labour Department for Labour
14.0 Currencies
All payments shall be made in Indian Rupees.
15.0 Advance Payment
No Advance Payment shall be made.
16.0 Cost of Repairs
Loss or damage to the Works or Materials to be incorporated in the Works between the
Start Date and the end of the Defects Correction periods shall be remedied by the
Contractor at the Contractor's cost if the loss or damage arises from the Contractor's acts
B. FINISHING THE CONTRACT
17.0 Completion
The Contractor shall request the Engineer to issue a Certificate of Completion of the
Works and the Engineer will do so upon deciding that the Work is completed.
18.0 Termination
18.1 The Employer shall be entitled to terminate the contract if the contractor:
(a) Fails to carry out any obligation under the contract.
(b) Without reasonable excuse fails –
1. To commence the works on site within the period stated in the Appendix to Bid
after receipt by him of a Notice to this effect from the Engineer/Employer after
signing the agreement or
2. To proceed with the works, or any section thereof, within 28 days after received
3. Has failed to comply with a notice issued or an instruction issued within 28 days
after having received.
4. Abandons the works or otherwise plainly demonstrates the intention not to
continue performance of his obligation under the contract.
5. Sub-contracts the works or assigns the contract without the specific prior written
permission of the engineer.
6. Has failed to furnish the required securities or extension thereof in terms of the
7. Becomes bankrupt or insolvent, goes into liquidation, has a receiving or
administration order made against him, compounds with his creditors, or carries
on business under receive, trustee or manager for the benefit of his creditors, or if
any act is done or event occurs which (under applicable Laws) has a similar effect
to any of these acts of event.
18.2 In any of these events or circumstances, the Employer may, upon giving 14 days notice
to the contractor, terminate the contract and expel the contractor from the site. However,
in the case of sub-paragraphs (h), the Employer may be notice terminate the contract
18.3 The Employer’s decision to terminate the contract shall not prejudice any other rights of
the Employer, under the contract or otherwise.
18.4 After termination, the Employer may complete the works and/or arrange for any other
entities to do so. The Employer and these entities may then use any goods, contractor’s
documents and other design documents made by or on behalf of the contractor.
18.5 The Employer or the Contractor may terminate the Contract if the other party causes a
fundamental breach of the Contract.
18.6 Fundamental breaches of Contract include, but shall not be limited to the following:
(a) the Contractor stops work for 14 days when no stoppage of work is shown on the
current Program and the stoppage has not been authorized by the Engineer;
(b) the Employer or the Contractor is made bankrupt or goes into liquidation other than
for a reconstruction or amalgamation;
(c) The contractor fails to fulfill requirements;
(d) the Engineer gives Notice that failure to correct a particular Defect is a fundamental
breach of Contract and the Contractor fails to correct it within a reasonable period of
time determined by the Engineer;
(e) the Contractor does not maintain a security which is required;
(f) the Contractor has delayed the completion of works by the number of days for which
the maximum amount of liquidated damages becomes payable as defined in the
(g) if the Contractor, in the judgment of the Employer has engaged in corrupt or
fraudulent practices in competing for or in the executing the Contract.
(h) For the purpose of this paragraph: “corrupt practice” means the offering, giving,
receiving or soliciting of anything of value to influence the action of a public official
in the procurement process or in contract execution. “Fraudulent practice” means a
misrepresentation of facts in order to influence a procurement process or the
execution of a contract to the detriment of the Borrower, and includes collusive
practice among Bidders (prior to or after bid submission) designed to establish bid
prices at artificial non-competitive levels and to deprive the Borrower of the benefits
of free and open competition.”
18.7 When either party to the Contract gives notice of a breach of contract to the Engineer for
a cause other than those listed above, the Engineer shall decide whether the breach is
fundamental or not.
18.8 Notwithstanding the above, the Employer may terminate the Contract for convenience.
18.9 If the Contract is terminated the Contractor shall stop work immediately, make the Site
safe and secure and leave the Site as soon as reasonably possible and handover the site to
the Employer including all materials and plant and equipment existing there upon.
19.0 Contractor's own responsibility
The contractor is to set out and level the works and will be responsible for the accuracy of
the same. He shall also be responsible for the correctness of the positions, levels,
dimensions, and alignment of all parts of the structures as per instructions given to him. If
at any time any error shall appear during the progress of any part of the work, the
contractor shall at his own expense rectify such error if called upon to the satisfaction of
the Engineer in charge.
20.0 Overpayment & Underpayment
20.1 Whenever any claim Fifths payment of a sum to the Municipal Corporation arises out of
or under this Contract against the contractor the same may be deducted by the Municipal
Corporation from any sum then due or which at any time thereafter may become due to
the contractor under this contract and failing that under any other contract with the
Municipal Corporation or from any sum due to the contractor with the Municipal
Corporation (which may be available with Municipal Corporation), or from his retention
money, or he shall pay the claim on demand. The Municipal Corporation reserves the
right to carry out post payment audit and technical examination of the final bill including
all supporting vouchers, abstracts, etc.
20.2 The Municipal Corporation further reserves the right to enforce recovery of any over
payment when detected notwithstanding the fact that the amount of the final bill may be
included by the Contractor.
20.3 If as a result of such audit and technical examination any over payment is discovered in
respect of any work done by the Contractor or alleged to have been done by him under
the contract, it shall be recovered by the Municipal Corporation from the contractor by
way of all the means prescribed above or if any under payment is discovered by the
Municipal Corporation, any amount due to the contractor under this contract or under
payment may be adjusted against any amount then due or which may at any time
thereafter become due before payment is made to the contractor from him to the
Municipal Corporation on any other contract account whatsoever.
21.0 Materials obtain from dismantling
If the contractor, in the course of execution of work is called upon to dismantle any part
for reasons other than on account of bad or imperfect work, the materials obtained from
dismantling will be the property of the A.M.C. and will be disposed of as per instruction
of Engineer-in-charge in the best interest of the A.M.C.
22.0 Dispute to be referred to Arbitrator
The disputes relating to this contract, so far as they relate to any of the following matters,
whether such disputes arise during the progress of the work or after the completion or
abandonment thereof, shall be referred an independent Arbitrator appointed by AMC as
far possible in consultation with the agency if it is necessary and such disputes shall be
settled in accordance with the arbitration and conciliation Act.
(i) The rates of payment under clause 5 for any tools, materials and stores, in or
upon the works of the site thereof or belonging to the contractor or procured by
him and intended to be used for execution of the work or any part thereof
possession of which may have been taken by the Engineer-in-charge under the
said clause –5.
(ii) The reduction in rates made by the Engineer-in-charge under clause 9 from the
items of works not accepted as completed fully in accordance with the sanctioned
specifications.
(iii) The rate of part of payment for any class of work which is included in the
additional or altered work carried out by the contractor in accordance with the
instructions of the Engineer-in-charge under clause 14 and the rates for which is
to be determined under the said clause
(iv) The rates of payment for materials already purchased or agreed to be purchased
by the contractor before receipt of notice given by the Engineer-in-charge under
clause 15 and/or amount of compensation payable to the contractor under the said
clause for loss in respect of such materials.
(v) The amount of compensation which the contractor shall be liable to pay under
clause 17 in the event of this failure to rectify, remove or reconstruct the work
within the period specified in the written intimation or the amount of expenses
incurred by the Engineer-in-charge under the said clause17 in rectifying,
removing or re-executing the work or in removing and replacing the materials or
articles complained of.
(vi) The reduction of rates as may be fixed by the Engineer-in-charge under clause
for the inferior work or materials as accepted or made use of.
(vii) The amount of compensation payable by the contractor for damages as estimates
and assessed under clause
(viii) The amount payable to the contractor for the work carried out under clause 33 in
accordance with the instructions and the requirement of the Engineer-in-charge in
case where there are no specifications.
(ix) The awards declared by the arbitrator shall be speaking award giving reasons and
calculations to every item of claims. The decision will have to be implemented by
all the concerned.
(x) In case of dispute leading to the contractor or Ahmedabad Municipal Corporation
approaching on Court of Law. It shall be within the jurisdiction where the site of
work is situated.
The reference to arbitration proceeding under this clause shall not:
i) Entitle the contractor to stop the Affect the right of the Engineer-in-charge under clause
5 to take possession of all or any tools, plants, materials and stores in or upon the
works of site thereof belonging to the contractor or procured by him and intended to be
used for the execution of the work or any part thereof.
ii) Preclude the Engineer-in-charge from utilizing the materials purchased by the
contractor in any work or from removing such materials to other places, during the
period the work is stopped or suspended in pursuance, of notice given to the contractor
iii) Progress of the work or the carrying out the additional or altered work in accordance
with the provisions of clause 14 or as the case may be, of clause
23.0 Drawings and Photographs of the Works
23.1 The contractor shall do photography/ videography of the site as and when asked by
AMC. No separate payment will be made to the contractor for this. . The contractor shall
have to submit the same in hard copy as well as soft copy as and when demanded by the
23.2 No photograph of the works or any part thereof or plant employed thereon, except those
permitted under clause 59.1, shall be taken, or permitted to be taken by the Contractor or
by any of his employees or any employees of his sub-Contractors without the prior
approval of the Engineer in writing. No photographs/ videography shall be published or
otherwise circulated without the approval of the Engineer in writing.
Seal and Signature of the Bidder Additional City Engineer
(Drainage Project)
Date: Ahmedabad Municipal Corporation
(1) y:- yt xuLzh su <u Jdolt અમદાવાદ યુિનિસપલ કોપ રેશન y&Jt fuLî{ y&Jt htsg
mhfthle btLg યાદીના ftuLx[fxhtu Che NfNu. dJobuLxlt btLg
ftuLx[tfxhu અમદાવાદ યુિનિસપલ કોપ રેશન btk btLg ftuLx[tfxhtule યાદીbtk
hSMxuNl fhtJJtlwk hnuNu.
c:- btLg ©uKelt ftuLx[tfxh <hefu ltuk^Kelwk «btKvºtle MJ «btKe< fhuj
lfj xuLzh mt&u stuzJtle hnuNu.
f:- xuLzhhle jtgft<
ftb જવાબદાર xuLzhh <ubs su xuLzhh mwaJuj ftuLx[tfxhle ©uKe
ytJ<t ntug <ubs ftb fhJt mûtb ntug <ublu s ytvJtbtk ytJNu. ftb
ytv<t vnujt ftuLx[tfxhu ftb mk<tu»tfthf <ubs xtRb jebexbtk ÃþY
fhJt sYhe mJj<,ylwCJ, ûtb<t ylu VtgltLmegj hemtumo hsw fhJtlt
z:- અમદાવાદ યુિનિસપલ ctuzo XhtJ lk - 3836,<t.25/11/2011 &e b¤uj bkswhe
ylwmth <&t mexe.Rsluh mh¾gwjh,lk -17,<t.09/12/2012 bwsc
yb>tJt> Bgwrlrmvj ftuvtuohuNlbtk ftuLx[t¾xh hSMxuNl Ve,
heLgwyj Ve <&t yvd{uzuNl Ve ylu btv દંડો ægtlbtk htFe <u bwsc
ybj fhJtltu hnuNu.
E. xuLzh Ch<t vnujt xuLzhhu mtRx rlheûtK fhe juJwk. xuLzhh ftblt
«fth, ngt< hM<t, vtKe btdo, mkath ylu JvhtNlt ceò hM<tytu&e
mk<wÐ ntuJtlwk btle juJtbtk ytJNu. xuLzhhu ftblu mtRx ylu
rcÕzekd(fu su ftb fhJt, ftb ÃþY fhJt <&t ftblt buRxulLm btxu cltJuj
ntug).<ubs xuLzhhu yt mtRxlt ftb btxu, rcÕzekd btxu, gtzo, zevtu
btxule søgt vtu<tle he<u bu¤Je juJtle hnuNu. (xuLzhlwk ftb fhJt,
ftb vwhwk fhJt <&t ftblt buRxulLm btxule søgt)
(h) yt ftble mbg મયાદા bubtuhuLzb (ltuxem RLJtRxuz xuLzh) btk sKtJuj
«btKu le hnuNu.
(3) xuLzh Jujezexe rvhegz bubtuhuLzb (ltuxem RLJtRxuz xuLzh) btk
sKtJuj «btKu le hnuNu.
(4) xuLzh Ch<e JF<u yluoMxble ChJtle hnuNu.
(5) xuLzh Vtubo
xuLzh Vtubo ylu ylwmwrabtkle દરેકે દરેક Ftje søgt xuLzh Chlthu Chuje yt
mt&u btufjujt દ તાવેજ vh< fhJtlt hnuNu.
(6) ftuLx[tfxhtuyu leaule ctc<tu ft¤SÃËJof JtkaJt rJlk<e Au.
(1) ftuR fkvlelu ltbu xuLzh juJtbkt ytÔgwk ntug <tu fkvle J<e xuLzh
vh mne fhlth Ôgrf<lu yr^f]< fh<wk bwFðgthltbwk xuLzh mt&u hsw
(2) Bgwrl.ftuvtuohuNllt «Joðbtl rlgbtu ylwmth yluMxble ChJtle
hnuNu.ylu xuLzh mt&u cezJtle hnuNu.
(3) ftuLx[tfxhu RLfbxuût mkckr^< vtl lkch <&t cukf zexuRj ytvJtle
(4) ftuLx[tfxh vtmu ydtWlt ylwCJt ykdult «btKvºttule lfj xuLzh mt&u
(5) xuLzh Nh<tu ylu MvuNeVefuNl <&t CtJ vºtflt >huf vtlt ylu rJd<tu
vh ftuLx[tfxhu mne fhJe.
(6) <btb mw^tht, AufAtf ylu Dwkxujt jFtK vh ftuLx[tfxhu xwkfe mne
xuLzh Chlthlu sKtJJtbtk ytJu Au fu xuLzh દ તાવેજોના jFtKbtk ftuR
AufAtf fu VhuVth fhJt દેવાશે lrn ylu ytJe ftuR AufAtf fu VuhVth
juJtNu lrn, <ultk jFtKbtk ftuR Cwj ntug <tu <ult vh l Dwkx<t Ftuxt
jFtK fu ytkfzt vh Auftu bthelu <ult mtawk jFtK fu ytkfzt MvÐ Wfju
<u he<u jFJt. «ðguf mw^tht vh xwkfe mne fhJe.
(8) y:- xuLzh hsw fh<tk vnujt Ftm fhelu xuLzhbtk >NtoJuj mwaltytulwk
vtjl fhJtbtk ytÔgw lrn ntug <tu xuLzh ybtLg dKJtbkt ytJNu <ule
ltuk^ juJt rJlk<e Au. J¤e yt Vtubolwk bwFv]ƒ ylu ftuLx[tfxhtult
btdo>Nol btxu mtbtLg rlgbtu ylu mwaltytu vK ft¤SvwJof JtkaJt
(1) ftuEvK fthK દશા યા rmJtg ftuEvK fu c^t xuLzhtu yMJefthJtltu n¬
(h) xuLzhhu ctujvtuELx vullt બદલે NtneJt¤e vul&e Chujt xuLzhtu
ðþkh< s ybtLg dKJtbtk ytJNu.
c:- Wvhle ctc<tu Wvhtk< xuLzh leault mkstudtubtk <h< ybtLg
XhJtlu vtºt &Nu.
(1) xuLzh Chlth, rlg< ftb y&Jt ftb btxu bkswh fhuj y&Jt CtJ vºtflt ftuR
ftuz y&Jt vîr< y&Jt rJd<tubtk bwfuj Nh< y&Jt mw^thtbtk ftuR
VuhVth mwaJ<t ntug.
(h) xuLzhlwk ftuR vtlwk fu vtlt ftZe ltkÏgwk/ltkÏgt ntug fu બદ યું / બદ યા
(3) c^t mw^tht J^tht y&Jt atukxtzuje ftvjeytu Wvh xuLzh Chlthu
xwkfe mne l fhe ntug.
(4) xuLzhbtk <ubKu ftuR AufAtf fhe ntug, ylu
(5) xuLzh Chlth y&Jt vuZele ctc<btk >huf Ctde>th y&Jt <u ykdulwk
bwFðgthltbwk ^htJlth Ôgrf< mne l fhu y&Jt xuLzhbt <u btxu
htFJtbtk ytJuje søgtbtk mne/mneytu Wvh ftuR mtûteyu mtF fhe
f:- Nh<e xuLzh MJefthJtbtk ytJNu lne.
z:- xuLzh MJefthJw, રદ fhJw, ftulu ytvJw ylu fgt CtJ&e ytvJw <u
ykdu Bgwrl. frb§h©eltu rlKog ytFhe hnuNu. ftuR fthKmh stu
ftuLx[tfxhlu ftb l ytve Nftg <tu <u ykdu ftuLx[tfxh ftuRvK «fthltu
lwfNtle fu J¤<hltu nff>tJtuu fhe NfNu lrn fu ftg>tfeg ftgoJtne yt
ykdu &R NfNu lrn. xuLzh bkswh >ltu y&o ftb ytve >uJtLþk Au
<uJtu &R NfNu lrn.Nh<e xuLzh MJefthJtbtk ytJNu lne.
(9) rJmkdr< ylu rnmtc stud:
nt& ^hJtlt ftbtule ctc< દશાવતા CtJ vºtfbtklt sÚ&t ylu hfble
ftuRvK Cwjawf leault rlgbtu ylwmth mhCh fhJtbtk ytJNu.
(1) xuLzh Chlthu દરના Ftltbtk sKtJuj Nç>tu ylu ytkfzt Jåau ftuR
ymkdr<lt fumbtk Nç>tuubtk sKtJuj hfb btLg htFJtbtk ytJNu.
(2) yufb દર ylu sÚ&tlt Ftuxt dwKtfthlt fthKu ftble ctc<tu દશાવતી CtJ vºtflt
Ftltbtk&e hfbbtk Cwj sKtg <tu yufb દર btLg htFJtbkt ytJNu ylu દરના
yt^thu dwKtfth mw^thJtbkt ytJNu.
(3) yufblt Ftltbtk&e <ubs ytd¤ Fuka<t mhJt¤tle <btb Cwjtu
mw^thJtbkt ytJNu.
(4) ctc<tu y&Jt mhJt¤t mtbu vwhu ytkfzu fhuj ftuR vK ctc< ægtlbtk
juJtbtk ytJNu lrn.
(10) y:- ftbltu «tud{um સમય મયાદા bwsc fhJtltu hnuNu. yt સમય મયાદા 10 jtF
mw^elt ftb btxu yuj.ytu.ytR. ytÃgt <theF&e 10 દવસથી <&t 10 jtF
&e Wvhltk ftb btxu yuj.ytu.ytR. ytÃg <theF&e 15 દવસથી શ &guj
dKJtbt ytJNu. <&t <u દર યાન ftble 5% juFu zevtuÍex Che fhthvºt
xuLzhbtk ftuLx[t¾xh îtht Chujt CtJ <btb «fthlt su <u «J<o<t
mhfthe xuût mrn<lt CtJ dKJtbtk ytJNu. ylu <ubtk atjw ftb >hBgtl
su ftuR VuhVth &Nu <ultu J^thtu awfJJtbtk ytJNu lrnk.
c:- mûtb m•tt îtht Yt.10,00,000.00 (દસ jtF) mw^elt xuLzhle
bkswheltu XhtJ vtzgt ct> (LOI) ytvJtbtk ytJNu ðgth ct> r>l -
btk rm¾gtuhexe zevtuÍex sbt fhtJJtle hnuNu. rm¾gtuhexe
zevtuÍex btuze ChJtlt rfMmtbtk Bgwrl.ftuvtuohuNlbtk «Joðbtl
rlgb ylwmth ftgoJtne fhJtbtk ytJNu.
f:- bkswh &guj xuLzhle સમય મયાદાbtk ftbdehe vqKo l &tg <tu
bubtuhuLzb (ltuxem RLJtRxuz xuLzh) btk sKtJuj «btKu bkswh
&guj mbgbgto>t ct>lt FhuFh ctfe ftble hfblt bn•tb 10% juFu
(jefJezexe zubuSm) vulÕxe Jmwj fhJtbtk ytJNu.
(11) y:- awfJKe:-
xuLzh Chlthu yu Jt< mbS juJtle hnuNu fu <uKu CtJ fu દર vwhtk
&gujt ftb btxult Au ylu <ubtk bswhe, vtjF, ÃjtLx, દેખરેખ, mhJem-
ftbdehe, Jes¤e, htugÕxe ylu ytufx[tug Jduhu ykNu <btb Faoltu
<&t sYh sKtg <tu ylu ðgthu ht<vt¤elt ftblu juJt c^t J^thtlt Faoltu
mbtJuN &Nu ylu xtkfujt CtJ fu દર fh<t J^thtle ftuR awfJKe ykdult
<ublt ftuR દાવા ægtlbtk juJtNu lnek ylu xuLzh Chlth Ftuxe
hswyt<lu fthKu y&Jt ftuR Ôgrf<yu (vAe<u ctk^ftb rJCtdltu
fboathe ntug fu l ntug) <ublu ytvuje btne<elu yt^thu vtA¤&e ftuR
દાવા hsw fhJt હકદાર hnuNu lnek. <ublw xuLzh ChJt <&t <ubtk જુ દા
જુ દા CtJ ylu દર ChJt btxu sYhe yuJe <btb btne<e vtu<tlt vûtu l
bu¤Je NfJtlu fthKu vtu<u xuLzh hsw fhJtlu je^u y&Jt <ubtk&e
WCt &<t ftuR stuFb fu sJtc>thebtk&e Axfe NfNu lnek. m>h
ftbbtk ftuR vK ò<lt ctk^ftblt bxehegj Wvh CtJ J^thtu ytvJtbtk
c:- ftuLx[tfxhtulu vubuLx / hlekd cej Bgwrl. frb§h©elt su <u «J<obtl
rlgb bwsc fhJtbt ytJNu. <&t Bgwrl. frb§h©e/mexe Rsluh©e lt su
<u JF<ltk mh¾gwjh «btKu ftbdehe/ybj fhJt rcl Nh<e ckDlf<ot
f:- ftuLx[t¾xhlt દરેક hlekd cejbtk&e ftuLx[t¾xhlu awfJJtle &<e fwj hfb
Wvh (xuLzh bwsclwk vubuLx + yu¾x[t ytRxb) 2 % juFu hexulNl
ble ftvJtbtk ytJNu su VtRlj cejbtk vh< ytvJtbtk ytJNu.
z:- htsg / fuL÷ mhfth©elt JF<tuJF<lt કાયદા bwsc su ftuR hfble fvt<
fhJtle &Nu <u bwsc ftuLx[tfxhlt cejbtk&e fvt< fhJtbt ytJNu.
(12) yu:- fhth mkc^e દ તાવેજો fhthlt ydðglt Ctd dKtNu ylu <u mD¤t mne<lt
fhth mbd{ ftblu jtdw vzNu.
ce:- xuLzhbtk દશાવેલ ftb mkck^e દ તાવેજમાં દશાવેલ rJd<btk rJmkd<<tlt
rfMmtbtk leau દશાવેલ ¢btlwmth દ તાવેજમાં દશાવેલ rJd< d{tng htFJtbkt
ytJNu. fhth mkc^e દ તાવેજો fhthlt ydðglt Ctd dKtNu ylu <u mD¤t
mne<lt fhth mbd{ ftblu jtdw vzNu.
(yu) yufb ylu કદ:-
(2) xuLzh VtuboLþk CtJvºtf
(3) MvuNeVefuNl
z[tu#dbtk કદ, ytfth, ytkfzt કદાચ Ftuxt ntug <tu btvujt કદ, ytfthlu
(2) xuLzh Vtubole yLþMþra-ce
(3) MvuNeVefuNl
Cwj Chujt fu Ftuxt JKollt rfMmtbtk yt mkck^e Wvhefûttyu
rJmkd<<t ykdule ltuk^ bwfe yuze.mexe yuLSlegh /
zu.BGþrl.frbNlh©ele bkswhe bu¤JJtbtk ytJNu ylu <u bwsc
fhJtbkt ytJuj rlKog ykr<b dKJtbkt ytJNu.
(13) xuLzhhu z[tuRkd fu MvuNeVefuNlbtk hnuje ftuR ûtr< fu Ftbeltu
duhjtC juJtle fturNN l fhJe ylu Rsluh Rlatsuo Ãjtl <&t
MvuNeVefuNlle ûtr<ytu mw^thJe <&t <ulwk mtawk y&oDxl
(14) yt Wvhtk< y.Bgw. ftuvtuo. lt slhj ftuLx[tfx fLzeNl vK btLg htFJle
(15) yufe JF<u yuf fh<t J^w søgtytuyu ftb NY fhJtltu Jfo ytuzoh b¤u
<tu ftb yuf mt&u s c^u NY fhJw vzNu.
(16) atjw ftbu mrJom jtRllu lwfNtl l &tg <u he<u ftb fhJtlw hnuNu. stu
ftuR mrJom jtRllu lwfNtl &Nu <tu <ule mkvwKo sJtc>the (òlbtj)
ftuLx[tfxhle vtu<tle hnuNu. mtRx Wvh ftb દર યાન bswhtu fu sl<tlt
ftuR btKmlt òlbtj lu lwfNtl &tg <ule જવાબદારી ftuLx[tfxhle hnuNu.
vtujem ફ રયાદ &tg <tu <ule જવાબદારી vK ftuLxtfxhle hnuNu. CuFz
Dme l vzu <ule જવાબદારી vK vtujem ફ રયાદમાં ftuLx[tfxhle hnuNu.
CuFz Dme l vzu <u btxu mjtb<elt vdjt (suJt fu દોરડું ctk^e bswh
Ftztbtk W<thJt, mtuhekd ylu Mx[xekd fhJt rJduhu) je^t Jdh
bsqhlu Ftztbtk W<thNu <tu ftuLx[tfxh s vtujem ફ રયાદમાં જવાબદાર
hnuNu ylu Bgwrl.ftuvtuohuNlltu ftuRvK MxtV ytlt btxu જવાબદાર
hnuNu lrn. ytxjwk mbSlu s xuLzh ChJwk. bswhtultu rJbtu vK
(17) bxehegÕm fu ceò xuMxed hevtuxo ftuLx[tfxhu vtu<tlt Fauo
ftuvtuohuNl sKtJu <u søgtyu fhtJJtlt hnuNu. bxehegÕm jtJJt fu
jR sJtltu mkvwKo Fao ftuLx[tfxhu CtudJJtltu hnuNu.
(18) M&¤ vrhrM&r< / sYhegt< bwsc ftb fhtJ<t xuLzhlt ytRxblt
sÚ&tbtk J^ ^x &tg <tu rlgb ylwmth <u ykdu ftb fhJt ftuLx[tfxh
(19) mtRx vh jtJJtbtk ytJuj btj mtbtl hesufx fhJtbt ytJu <tu <whk< દન
1btk vh< jR sJtltu hnuNu. yLg&t <ule lwfNtlle sJtc>the
ftuLx[tfxhle hnuNu.
(20) ftuLx[tfxhlu su ftuLx[tfx ytvJtbtk ytJu Au. <ubt mhfth©elt «Joðbtl
rlgb bwsc ve.yuV/juch yufx <&t bswhtu <&t MxtVle Jebt vtujeme
jElu <ult ftg>tlw vtjl fhJtlwk hnuNu <&t yt ykdu
Bgwrl.ftuvtuohuNl îtht su btne<e btkdJtbtk ytJu <u ytvJtle
hnuNu. bu.BGþrl.frbNlh©elt mh¾âwjh Bþsc sYhe ctknu^he vºtf
ytvJtLþk hnuNu.
(21) ftuRvK કાયદાકીય jexeduNl yb>tJt> Nnuhle ftuxobt hnuNu.
(22) btj su <u Mxtumo Wvh y&Jt mtRx Wvh jtuftulu lz<h l &tg <u
he<u mwalt bwsc W<thJtltu <ubs dtuXJJtltu hnuNu.
(23) ftuR vK mhfthe fhJuht ChJtle <btb sJtc>the ftuLx[tfxhle hnuNu.
(24) ftuLx[tfxh îtht xuLzhbt દશાવેલ MveNeVefuNl bwsc MxtLzzo
bxehegÕm MvuNeVefuNl bwsc jtJJtlt hnuNu.<&t xuMxekd
fhtJJtlwk hnuNu.<&t y ykdu «Joðbtl Bgwrl.ftuvtuohuNlt rlgbtulw
vtjl fhJtlw hnuNu.
(25) yt xuLzhbtk stu ftuR ytRxb hne dR ntug <tu <u y&Jt M&¤
M&e<e bwsc xuLzhbtk mbtJuN l ntug <uJe J^thtle ftbdehe
fhJtle &tg <uJt rfMmbtk Bgwrl.ftuvtuohuNlt «Joðbtl rlgb ylwmth
J^thtle ytRxblt CtJ lffe fhJtbtk ytJNu ylu <u bwsc awkfJKe
(26) atjw ftb દર યાન «tuxufNlle mkvwKo sJtc>the ftuLx[tfxhle hnuNu.
subtk vevzt, દોરડા, Cgmwaf ctuzo, ÃjtMxef vèe, rJ. ftuLx[tfxhu
jtJJtlwk ylu mtaJJtlwk hnuNu. ylu ftuRvK yfMbt< &Nu <tu <ule
mkvwKo sJtc>the ftuLx[tfxhle hnuNu.
(27) M&¤ Wvh atjw ftbdehe >hBgtl ftb fhlth ftuLx[tfxhlt bswh /
fboathe y&Jt yLg Ôgrf<lt yfMbt<lt rfMmbtk juch yufx bwsc fhJtle
&<e ftgoJtne <&t vtujem ftgoJtnele sJtc>the ftuLx[tfxhle hnuNu.
(28) stu MxtV mqalt ytvu <u bwsc mwalt vtu&e ftuLx[tfxhu htFJtle
hnuNu. <ubtk દરરોજ fhuj ftbdehe <&t yr^ftheytuyu ftb mw^thJt fu
«tud{um J^thJtlt ltuk^ fhuj ntug <tu <ulwk ftuBÃjtgLm ytvJtlwk
hnuNu ytJe ltu^lt sJtc l &gu fu <u «btKu M&¤ Wvh ybj l &gu
ftuLx[tfxhlu vulÕxe fhJtle m•ttt yuze.mexe yuLSlehgh©elu
(29) દરેક ytRxblt MvuNeVefuNl yb>tJt> Bgwrlrmvj ftuvtuohuNlltk
bkswh &guj <&t btLg htFuj MvuNeVefuNl Nh<tu bwsc hnuNu
su ytRxbbtk MvuNeVefuNl l ntug <uJt mkstudtubtk
yuze.mexe.yuLSlegh©eltu rlKog ytFhe hnuNu.Jtuxhekd fhJtbtk
lrn ytJu fu દરરોજ J^thtltu zucheÍ WvtzJtbtk lrn ytJu <tu ftuLx[tfxhlt
Fauo ylu sutFbu Jdh ltuxemu Jtuxhekd fhtJJtbtk <&t zucheÍ
WvtzJtbtk ytJNu ylu cejbtk&e hfb ftve juJtbtk ytJNu.
(30) juch JuÕVuh Vkz btxu ntjbtk htsg mhfth©eyu fhuj nwfb bwscle
hfb cejbtk&e ftve juJtbtk ytJNu.
(31) atubtmtltu vehegz <t.15 swl &e 14 ytufxtuch Mþ^eltu dKJtbtk
ytJNu. yt mbg દર યાન ftuLx[tfxh îtht ftbdehe fhe Nftg <ub l ntug
<tu <u Bþscle xtEb jebex J^the ytvJtbtk ytJNu.
(32) muÕm xuût / Jux lkch / ve.yuV. ftuz lkch / vtl lkch / S.yum.xe.
lkch rJduhu ftuLx[t¾xhu VhSgt< ytvJtlt hnuNu.
(33) ltbœth ftuxo îtht fhuj nwfb <ubs rlœuo»ttulwk awM<vKu vtjl
fhJtlwk hnuNu. subtk z[ulus lu jd<tk ftb btk ftuRvK mkkstudtubtk
bNel ntuj/ dxhbtk btKmlu W<thJtu lnek <ubs buLgwyj
M¾{uJSkd ykdule btdoœrNoft lwk vtjl fhJwk.
yufhthlwk Vtubo
(1) nwk/ybu yt&e yufhth fhwk Awk/fheyu Aeyu fu yt xuLzh
hsw fh<tk vnujtk buk/ybu M&¤le bwjtft< je^e Au ylu ftblu
jd<t btjmtbtl, bswhe ylu ceS ctc<tulu jd<e M&trlf
vrhrM&r<le ò<-btne<e bu¤Je Au.
(2) nwk/ybu yt&e yufhth fhwk Awk/fheyu Aeyu fu yt
ftuLx[tfxhtule Nh<tu rJd<tu ylu xuLzhlu jd<t દ તાવેજો
ft¤SvwJof yÇgtm fgtuo Au ylu <u bwsc <ultu ybj fhJt mkb<
ftuLx[tfxhle mne ylu
TECHNICAL SPECIFICATIONS:
REINFORCED CEMENT CONCRETE PIPES
SOCKET & SPIGOT
This specification covers the requirements for manufacturing, testing, supplying,
jointing and testing at work sites of Reinforced Cement Concrete (RCC) pipes, of
both pressure and non pressure varieties used for pumping mains and gravity,
sewers and storm water drains. Laying of pipes and fittings/specials are covered
in Technical Specifications: Section-D6. The two parts are complementary and
are to be read together for a correct interpretation of the provisions of this
D.1.1 APPLICABLE CODES
The manufacturing, testing, supplying, jointing and testing at work sites of RCC
pipes shall comply with all currently applicable statutes, regulations, standards
and codes. In particular, the following standards, unless otherwise specified
herein, shall be referred. In all cases, the latest revision of the codes shall be
referred to. If requirements of this specification conflict with the requirements of
the codes and standards, this specification shall govern.
D.1.2 MATERIALS
a) IS: 458 - Specification for precast concrete pipes (with and without reinf.)-
b) IS: 3597 -Method of tests for concrete pipes.
c) IS: 5382 -Specification for rubber sealing rings for gas mains, water mains
d) IS: 516 -Method of test for strength of concrete.
D.1.3 CODE OF PRACTICE
a) IS: 456 -Code of practice for plain and reinforced concrete
b) IS: 783 -Code of practice for laying of concrete pipes
Design of RCC pipes including reinforcement details and the ends of pipes shall
be in accordance with the relevant clauses of IS: 458-2021.
D.1.5 MANUFACTURING
Pipe should be with ISI mark confirming to IS-458-2021. Pipe can be
manufactured by spinning process or by vibrated casting process.
The method of manufacture shall be such that the form and the dimensions of the
finished pipes are accurate within the limits specified in relevant clause of IS:
458. The surfaces and edges of the pipes shall be well defined and true, and their
ends shall be square with the longitudinal axis. The ends of the pipes shall be
further reinforced by an extra ring of reinforcement to avoid breakage during
transportation.
The RCC pipes and rubber rings shall be systematically checked for any
manufacturing defects by experienced supervisors so as to maintain a high
standard of quality.
Owner/Engineer shall at all reasonable times have free access to the place where
the pipes and collars/rubber rings are manufactured for the purpose of examining
and testing the pipes and collars/rubber rings and of witnessing the test and
All tests specified either in this specification or in the relevant Indian Standards
shall be performed by the supplier/contractor at his own cost and in presence of
Owner/Engineer if desired. For this, sufficient notice before testing of the pipes
and fittings shall be given to Owner/Engineer.
If the test is found unsatisfactory, Owner/Engineer may reject any or all pipes of
that lot. The decision of Owner/Engineer in this matter shall be final and binding
on Contractor and not subject to any arbitration or appeal.
D.1.6 MATERIALS
Cement used for the manufacture of RCC pipes should be SRC and shall confirm
to relevant IS codes.
Aggregates used for the manufacture of RCC pipes shall conform to IS:383. The
maximum size of aggregate should not exceed one-third the thickness of the pipe
or 20 mm, whichever is smaller.
Mixing and Curing Water
Water shall be clean, colorless and free from objectionable quantities of organic
matter, alkali, acid, salts or other impurities that might reduce the strength,
durability or other desirable qualities of concrete and mortar.
Reinforcement used for the manufacture of the RCC pipes shall be mild steel
Grade I or medium tensile steel bars conforming to IS: 432 (Part-I) or hard-drawn
steel wire conforming to IS: 421 (Part-2). Reinforcement cages for pipes shall be
as per relevant requirements of IS:
Concrete used for the manufacture of RCC pipes shall conform to IS: 456. The
minimum cement content and minimum compressive strength of concrete shall
be as per relevant requirements of IS:458 (Latest Edition). Compressive strength
tests shall be conducted on 15 cm cubes in accordance with the relevant
requirements of IS: 456 and IS:
Rubber ring chords used in pipe joints shall be EPDM rubbering as per IS 5382 :
Pipes manufactured in compliance with IS:458 (Latest Edition) shall be either
water cured or steam cured for minimum stipulated curing period in accordance
with relevant requirements of the latest revised IS:458 (Latest Edition).
D.1.8 DIMENSIONS
The internal diameter, wall thickness and length of barrel and collar of pipes,
reinforcement (longitudinal and spiral), type of ends and minimum clear cover to
reinforcement and strength test requirements shall be as per the relevant
clauses/tables of IS: 458 for different classes of pipes.
Table – 3 of IS-458-2021
Design and Strength Test Requirements of Concrete Pipes of Class NP3
Reinforced Concrete, Medium Duty, Non-Pressure Pipes made by spinning process
Internal Barrel Reinforcements Strength Test Requirements
Diameter Wall for Three Edge Bearing Test
of Pipes in Thickness Longitudinal, Mild Spirals, Load to Produce Ultimate
mm Steel or Hard Drawn Hard 0.25 mm Crack Load
Steel Draws kN/linear metre
Minimum Kg/linear Kg/linear kN/linear
number metre metre metre
1. If mild steel is used for spiral reinforcement, the weight specified under col.5 shall be
increased to 140/125.
2. The longitudinal reinforcement given in this table is valid for pipes upto 2.5 m. effective
length for internal diameter of pipe upto 250 mm and upto 3 m. effective length for
higher diameter pipes.
3. Total mass of longitudinal reinforcement shall be calculated by multiplying the values
given in col.4 by the length of the pipe and then deducting for the cover length provided
at the two ends.
4. Concrete for pipes shall have a minimum compressive strength of 35 N/mm2 at 28 days.
Table – 5 of IS- 458-2021
Design and Strength Test Requirements of Concrete Pipes of Class NP3
Reinforced Concrete, Medium Duty, Non-Pressure Pipes Made by Vibrated Casting
Internal Minimum Reinforcements Strength Test Requirements
Diameter Barrel for Three Edge Bearing Test
of Pipes in Wall Longitudinal, Mild Spirals, Load to Produce Ultimate
mm Thickness Steel or Hard Drawn Hard 0.25 mm Crack Load
Steel Draws kN/linear metre kN/linear
Minimum Kg/linear Kg/linear
number metre metre
Note : Concrete for pipes shall have a minimum compressive strength of 35 N/mm2
Table – 6 of IS-458-2021
Design and Strength Test Requirements of Concrete Pipes of Class NP4
Reinforced Concrete, Heavy Duty, Non-Pressure Pipes
Internal Minimum Reinforcements Strength Test Requirements
Diameter Barrel for Three Edge Bearing Test
of Pipes in Wall Longitudinal, Mild Spirals, Load to Produce Ultimate
mm Thickness Steel or Hard Drawn Hard 0.25 mm Crack Load
Steel Draws kN/linear metre kN/linear
Minimum Kg/linear Kg/linear
number metre metre
Note : 1. If mild steel is used for spiral reinforcement, the weight specified under col.5
shall be increased to 140/125.
2. The longitudinal reinforcement given in this table is valid for pipes upto 2.5 m.
effective length for internal diameter of pipe upto 250 mm and 3 m. effective
length for higher diameter pipes.
3. Total mass of longitudinal reinforcement shall be calculated by multiplying the
values given in col.4 by the length of the pipe and then deducting for the cover
length provided at the two ends.
4. Concrete for pipes shall have a minimum compressive strength of 35 N/mm2 at
Table – 8 of IS-458-2021
Design and Strength Test Requirements of Concrete Pipes of Class NP4
Reinforced Concrete, Heavy Duty, Non-Pressure Pipes
made by Vibrated casting process
Internal Minimum Reinforcements Strength Test Requirements
Diameter Barrel for Three Edge Bearing Test
of Pipes in Wall Longitudinal, Mild Spirals, Load to Produce Ultimate
mm Thickness Steel or Hard Drawn Hard 0.25 mm Crack Load
Steel Draws kN/linear metre kN/linear
Minimum Kg/linear Kg/linear
number metre metre
Note : Concrete for pipes shall have a minimum compressive strength of 35 N/mm2 at
The tolerances regarding overall length, internal diameter of pipes or sockets and
barrel wall thickens shall be as per relevant clause of IS:
D.1.9 WORKMANSHIP AND FINISH
Pipes shall be straight and free from cracks except that craze cracks may be
permitted. The ends of the pipes shall be square with their longitudinal axis so
that when placed in a straight line in the trench no opening between ends in
contact shall exceed 3 mm in pipes up to 600 mm diameter (inclusive), and 6 mm
in pipes larger than 600 mm diameter.
The outside and inside surfaces of the pipes shall be smooth, dense and hard, and
shall not be coated with cement wash or other preparation unless otherwise
agreed to between Owner/Engineer and the manufacturer or supplier.
The pipes shall be free from defects resulting from imperfect grading of the
aggregate, mixing or moulding.
The pipes shall be free from local dents or bulges greater than 3 mm in depth and
extending over a length in any direction greater than twice the thickness of barrel.
The deviation from straight in any pipe throughout its effective length, tested by
means of a rigid straight edge parallel to the longitudinal axis of the pipe shall not
exceed, for all diameters 3 mm forever meter run.
All pipes for testing purposes shall be selected at random from the stock of the
manufacturer and shall be such as would not otherwise be rejected under the
criteria of tolerances as mentioned in IS:458 (Latest Edition).
During manufacture, tests on concrete shall be carried out as per IS:456. The
manufacturer shall supply, when required to do so by Owner/Engineer the results
of compressive tests of concrete cubes and split tensile tests of concrete cylinders
made from the concrete used for the pipes. The manufacturer shall supply
cylinders or cubes for test purposes required by the Owner/Engineer and such
cylinders or cubes shall withstand the tests prescribed by the manufacturer for the
hydrostatic test pressure. For non-pressure pipes, 2 percent of the pipes shall be
tested for hydrostatic test pressure.
The specimen of pipes for the following tests shall be selected in accordance with
relevant Clause of IS:458 (Latest Edition)and tests in accordance with the
methods described in IS:3597.
i) Hydrostatic test
ii) Three edge bearing test
iii) Absorption test
Note: Three edge bearing strength to produce 0.25 mm crack in case of special
design of pipes shall be as per IS:458:2003.
For Inspection at manufacturing site 24 hrs. access shall be provided to AMC
Engineers as well as engineer appointed by PMC/TPI agency. Apart from this
AMC will establish its own pipe testing facility where pipes will be randomly
tested. The cost of transporting the pipe to the testing facility & testing charges
shall be borne by the contractor.
D.1.11 SAMPLING AND INSPECTION
In any consignment, all the pipes of same class and size and manufactured under
similar conditions of production shall be grouped together to constitute a lot. The
conformity of a lot to the requirements of this specification shall be ascertained
on the basis of tests on pipes selected from it.
The number of pipes to be selected from the lot for testing shall be in accordance
with Table 15 of IS:458 (Latest Edition).
Pipes shall be selected at random. In order to ensure randomness, all the pipes in
the lot may be arranged in a serial order and starting from any pipe, every ‘n’th
pipe be selected till the requisite number is obtained, n being the integral part of
N/n, where N is the lot size and n is the sample size.
All pipes selected as per IS : 458 shall be inspected for dimensional requirements,
finish and deviation from straight. A pipe failing to satisfy one or more of these
requirements shall be considered as defective.
The number of pipes to be tested for tests under IS : 458 shall be in accordance
with column 4 of Table 15 of IS:458 (Latest Edition). These pipes shall be
selected from pipes that have satisfied the requirements mentioned in Clause
A lot shall be considered as conforming to the requirements of IS:458 (Latest
Edition) of the following conditions are satisfied.
(a) The number of defective pipes shall not be more than the permissible
number given in column 3 of Table 15 of IS:458 (Latest Edition).
(b) All the pipes tested for various tests as per IS-458 shall satisfy
corresponding requirements of the tests.
(c) In case the number of pipes not satisfying requirements of any one or
more tests, one or two further samples of same size shall be selected and
tested for the test or tests in which failure has occurred. All these pipes
shall satisfy the corresponding requirements of the test.
The following information shall be clearly marked on each pipe :
b) Internal diameter of pipe
c) Class of pipe
d) Date of manufacture, and
e) Name of manufacturer or his registered trademark or both.
D.1.13 LAYING OF PIPES
The laying of RCC pipes shall conform to Technical Specifications: Section.
D.1.14 JOINTING
Jointing of RCC pipes shall be done with SRC cement only and as per the
requirements of following specifications and as per the relevant IS. The type of
joints shall be as below. After jointing, extraneous material, if any, shall be
removed from the inside of the pipe and the newly made joints shall be
thoroughly cured. In case, rubber-sealing rings are used for jointing, these shall
conform to IS 5382 and shall be of such type as mentioned in IS-458:2003.
D.1.15 FLUSH JOINT (INTERNAL)
This joint shall be generally used for culvert pipes of 900-mm diameter and over.
The ends of the pipes are specially shaped to form a self-centering joint with an
internal jointing space 13-mm wide. The finished joint is flush with both inside
and outside with the pipe wall. The jointing space is filled with cement mortar in
the proportion as specified in IS-458-2003, mixed sufficiently dry to remain in
position when forced with a trowel or rammed.
FLUSH JOINT (EXTERNAL)
This joint is suitable for pipes which are too small for jointing from inside. This
joint is composed of specially shaped pipe ends. Each end shall be butted against
each other and adjusted in correct position. The jointing space shall then be filled
with cement mortar as specified in IS-458-2003, sufficiently dry and finished off
flush. Great care shall be taken to ensure that the projecting ends are not
damaged as no repairs can be readily affected from inside the pipe.
SPIGOT AND SOCKET JOINT (FLEXIBLE)
The RCC pipe with the rubber ring accurately positioned on the spigot shall be
pushed well home into the socket of the previously laid pipe by means of
uniformly applied pressure with the aid of a jack or similar appliance. The RCC
pipes shall be of spigot and socket type and rubber rings as specified in IS-458-
2003, shall be used, and the manufacturers instructions shall be deemed to form a
part of these specifications. The rubber rings shall be lubricated before making
the joint and the lubricant shall be soft soap water or an approved lubricant
supplied by the manufacturer.
Socket & Spigot NP3 & NP4 pipe with rubber ring roll on joint for diameter upto
900 mm should be provided as per table 14 pf IS 458 :
Socket & spigot NP3 & NP4 pipe with rubber ring confined joint for diameter
1000 mm to 2200 mm should be provided as per Table -17 of IS 458:2003.
D.1.16 CLEANING OF PIPES
As soon as a stretch of RCC pipes has been laid complete from Machinehole to
Machinehole or for a stretch as directed by Owner/Engineer, contractor shall run
through the pipes both backwards and forwards a double disc or solid or closed
cylinder 75 mm less in diameter than the internal diameter of pipes. The open
end of the incomplete stretch of pipeline shall be securely closed as may be
directed by Owner/Engineer to prevent entry of mud or silt etc.
If as a result of the removal of any obstructions Owner/Engineer considers that
damages may have been caused to the pipelines, he shall be entitled to order the
stretch to be tested immediately. Should such test prove unsatisfactory,
contractor shall amend the work and carry out such further tests as are required
by Owner/Engineer.
It shall also be ascertained by contractor that each stretch from Machinehole to
Machinehole or the stretch as directed by Engineer is absolutely clear and
without any obstruction by means of visual examination of the interior of the
pipeline suitably enlightened by projected sunlight or otherwise.
D.1.17 TESTING AT WORK SITE
After laying and jointing of RCC pipes is completed the pipeline shall be tested at
work site as per the following specifications and as directed by Owner/Engineer.
All equipment for testing at work site shall be supplied and erected by contractor.
Water for testing of pipes shall be arranged by him. Damage during testing shall
be contractor’s responsibility and shall be rectified by him to the full satisfaction
of Owner/Engineer. Water used for test shall be removed from pipes and not
released to the excavated trenches.
After the joints have thoroughly set and have been checked by Owner/Engineer
and before backfilling the trenches, the entire section of the sewer or storm water
drain shall be proved by contractor to be water tight by filling in pipes with water
to the level of 1.50 m above the top of the highest pipe in the stretch and heading
the water up for the period of one hour. The apparatus used for the purpose of
testing shall be approved by Owner/Engineer. Contractor if required by
Owner/Engineer shall dewater the excavated pit and keep it dry during the period
of testing. The loss of water over a period of 30 minutes should be measured by
adding water from a measuring vessel at regular 10 minutes intervals and noting
the quantity required to maintain the original water level. For the approval of this
test the average quantity added should not exceed 1 litre/hour/100 linear
metres/10 mm of nominal internal diameter. Any leakage including excessive
sweating which causes a drop in the test water level will be visible and the
defective part of the work should be removed and made good.
In case of pressure pipeline the completed stretch of pipeline shall be tested for
site test pressure as specified in IS-458-2003. The site test pressure should not be
less than the maximum operating pressure plus the calculated surge pressure, but
in no case should it exceed the hydrostatic test pressure as specified in IS:458
(Latest Edition).
D.1.18 MEASUREMENT
All RCC pipes shall be measured according to the work actually done and no
allowance will be made for any waste in cutting to the exact length required. The
measurement for pipes shall be in running meter nearest to a cm. of length along
the centre line of pipe as actually laid at work sites.
The rate for providing, laying and jointing of RCC pipes shall be deemed to
include the cost of rubber rings, jointing material, testing and extra excavation
required for ordinary bedding of pipes and also for pipe sockets, if any.
If any damage is caused to the pipeline during the execution of work or while
cleaning/testing the pipeline as specified. Contractor shall be held
responsible for the same and shall replace the damaged pipeline and retest the
same at his own cost to the full satisfaction of Engineer.
Water for testing of pipeline shall be arranged by Contractor at his own cost.
Pipes shall be brought on site proportionate to the required progress for Thirty
D-5 : SITE FILLING
D.5.1.1 Apart from any other work / purpose for which this specification may be made applicable by
Engineer, this shall generally govern work involving filing site / plant over the entire area /
most of the area to raise the general grade level to the desired elevation. This work shall be
carried out as per applicable clauses “Earthwork in Grading, Excavation and Backfilling”
particularly clauses 10 &
D.5.2 FILL MATERIAL
D.5.2.1 General
D.5.2.1.1 All fill material whether such material is brought from outside borrow areas or excavation
within the site, will be subject to Engineer’s approval. Notwithstanding any approval given
to the fill material or borrow areas from which fill material is proposed to be brought,
Engineer / Owner reserves the right to reject such material which in his opinion either does
not meet the specification requirements or is unsuitable for the purpose for which it is
D.5.2.2 Borrow Areas
D.5.2.2.1 It shall be Contractor’s responsibility to locate suitable borrow areas for borrowing fill
material. Such areas will be inspected by Engineer and approved before Contractor makes
arrangements to borrow the fill material. The top soil which may contain vegetation,
rubbish, slush etc. shall not be used. If demanded by Engineer. Contractor shall arrange to
have trial pits of specified dimensions and numbers dug at locations specified, for Engineer
to examine the nature and type of material likely to be obtained from the borrow area.
D.5.2.3 Lead, Lift and Transportation
D.5.2.3.1 Unless separately provided, for, all lead, lift and transportation required for bringing in the
fill material from borrow areas or from excavation from within the site shall be included in
the Contractor’s quote unit rates.
D.5.2.4 Quality
D.5.2.4.1 The borrowed soil shall be generally granular, and non-cohesive. It shall consist of sand,
silty sand, murrum, ordinary soil, gravel and shingle. Dredged material, free from clayey
deposit, will be accepted. Fill material shall also be free from sulphates, salts, organise,
foreign and other harmful or objectionable materials. Any material rejected by Engineer
shall be removed from the site immediately.
D.5.3 ACCESS ROAD
D.5.3.1 Roads, whether of temporary or other nature, required to be constructed for access and for
movement of man, materials. Equipments, transport vehicles, vehicles carrying fill material
etc. to or over borrow areas and/or to or over areas on which fill has to be deposited shall be
constructed by Contractor at his cost. Such costs shall be deemed to have been included in
the unit rates quoted by Contractor. Such access roads shall be maintained in good condition
during all seasons to ensure completion of work according to time schedule.
D.5.4.1 Site clearing before filling shall be carried out as specified in the enclosed specification.
Earthwork in Grading, Excavation and backfilling.
D.5.5.1 Backfill
D.5.5.1.1 Backfill shall be deposited to bring the grade level to desired elevation after compaction of
D.5.5.1.2 Back fill shall be compacted, where so specified, by 12 tonne rollers as indicated in Clause
D.5.5.2.3 below. The fill material shall be compacted to the specified density, where so
D.5.5.1.3 If the density of fill use of rollers for compaction is not specified. Contractor shall ensure
necessary compaction by the passage of trucks, carrying the fill material over the deposited
fill in such a way that the entire fill area is covered. These will reasonably compact the
sand fill will be accepted by Engineer. However, Contractor shall ensure that every layer is
thus compacted before the succeeding layers are deposited. Each layer shall not exceed
mm in thickness.
D.5.5.1.4 Compaction of back fill by flooring the area shall be carried out where so specified. In this
case, Contractor should ensure that the fill material is not washed away. This work shall be
carried out as directed by Engineer.
D.5.5.2 Soil Fill
D.5.5.2.1 Approval soil fill consisting of ordinary soil, murrum, soil containing gravel, shingle etc.
shall be deposited in layers not exceeding 200 mm. Contractor should ensure that all clods of
earth are broken down to a size not larger than 100 mm.
D.5.5.2.2 Where density of fill or use of rollers is not specified, the fill shall be carried out as specified
in Clause D.5.5.1.3 above.
D.5.5.2.3 Where the fill material has to be compacted by use of rollers procedure as specified in Clause
D.1.10.5.2 of specification for “Earthwork in Grading, Excavation and Backfilling”.
D.5.5.2.4 Where specified, the required density of fill shall be obtained by proper compaction.
D.5.6 MEASUREMENT
D.5.6.1 The rate quoted by the contractor for filling available excavated earth (excluding rock if
any) will be considered for payment for site filling as per the quantity executed and measured
in cubic meter.
D-6 : CONCRETE WORKS
D.6.1.1 This Specification covers the general requirements for concrete using on-site production
facilities including requirements in regard to the quality, handling, storage of ingredients,
proportioning, batching, mixing, transporting, placing, curing, protecting, repairing, finishing
and testing of concrete; form work; requirements in regard to the quality, storage, bending
and fixing of reinforcement; grouting as well as mode of measurement and payment for
complete works.
D.6.1.2 It shall be very clearly understood that the specifications given herein are brief and do not
cover minute details. However, all work shall have to be carried out in accordance with the
relevant standards and codes of practices or in their absence in accordance with the best
accepted current engineering practices or as directed by Engineer from time to time. The
decision of Engineer as regards the specification to be adopted and their interpretation and
the mode of execution of work shall be final and binding on Contractor and no claim
whatsoever will be entertained on this account.
D.6.2 APPLICABLE CODES AND SPECIFICATIONS
D.6.2.1 The following specifications, standards and codes, including all official amendments /
revisions and other specifications and codes referred to therein, should be considered a part
of this specification. In all cases the latest issue / edition / revision shall apply. In case of
discrepancy between this specification and those referred to herein below or other
specifications forming a part of this bid document, this specification shall govern.
D.6.2.2 Code for Materials
1. IS : 269 - Specification for 33 grade ordinary portland cement
2. IS : 455 - Specification for portland slag cement
3. IS : 1489 - Specification for portland pozzolana cement
4. IS : 8112 - Specification for 43 grade ordinary portland cement.
5. IS : 12330 - Specification for sulphate resisting portland cement
6. IS : 383 - Specification for coarse and fine aggregates from natural
sources for concrete.
7. IS : 432 - Specification for mild steel and medium tensile steel bars
(Part 1 and 2) and hard drawn steel wires for concrete reinforcement.
8. IS : 1786 - Specification for high strength deformed steel bars and
wires for concrete reinforcement.
9. IS : 1566 - Specification for hard drawn steel wire fabric for concrete
10. IS : 9103 - Specification for admixtures for concrete.
11. IS : 2645 - Specification for integral cement water proofing
12. IS : 4990 - Specification for plywood for concrete shuttering work.
13. IS : 12269 - Specification for 53 grade ordinary portland cement.
D.6.2.3 Code for Material Testing
1. IS : 4031 - Methods of physical tests for hydraulic cement.
(Parts 1 to 15)
2. IS : 4032 - Methods of chemical analysis of hydraulic cement.
3. IS : 650 - Specifications for standard sand for testing of cement.
4. IS : 2430 - Methods for sampling of aggregates for concrete.
5. IS : 2386 - Methods of test for aggregates for concrete.
6. IS : 3025 - Methods of sampling and test (physical and chemical)
water used in industry.
7. IS : 6925 - Methods of test for determination of water soluble
chlorides in concrete admixtures.
D.6.2.4 Code for Materials Storage
1. IS : 4082 - Recommendations on stacking and storing of construction
materials at site.
D.6.2.5 Code for Concrete Mix Design
1. IS : 10262 - Recommended guidelines for concrete mix design.
2. SP : 23 - Handbook on Concrete Mixes.
D.6.2.6 Code for Concrete Testing
1. IS : 1199 - Method of sampling and analysis of concrete.
2. IS : 516 - Method of test for strength of concrete
3. IS : 9013 - Method of making, curing and determining compressive
strength of accelerated cured concrete test specimens.
4. IS : 8142 - Method of test for determining setting time of concrete by
penetration resistance.
5. IS : 9284 - Method of test for abrasion resistance of concrete.
6. IS : 2770 - Methods of testing bond in reinforced concrete.
D.6.2.7 Code for Equipment
1. IS : 1791 - Specification for batch type concrete mixers.
2. IS : 2438 - Specification for roller pan mixer.
3. IS : 4925 - Specification for concrete batching and mixing plant.
4. IS : 5892 - Specification for concrete transit mixer and agitator.
5. IS : 7242 - Specification for concrete spreaders.
6. IS : 2505 - General Requirements for concrete
vibrators : Immersion type.
7. IS : 2506 - General Requirements for screed board concrete vibrators.
8. IS : 2514 - Specification for concrete vibrating tables.
9. IS : 3366 - Specification for pan vibrators.
10. IS : 4656 - Specification for form vibrators for concrete.
11. IS : 11993 - Code of practice for use of screed board concrete vibrators.
12. IS : 7251 - Specification for concrete finishers.
13. IS : 2722 - Specification for portable swing weigh batchers for concrete
(single and double bucket type).
14. IS : 2750 - Specification for steel scaffoldings.
D.6.2.8 Codes of Practice
1. IS : 456 - Code of practice for plain and reinforced concrete.
2. IS : 457 - Code of practice for general construction of plain and
reinforced concrete for dams and other massive structures.
3. IS : 3370 - Code of practice for concrete structures for storage of
(Parts 1 to 4) liquids.
4. IS : 3935 - Code of practice for composite construction.
5. IS : 2204 - Code of practice for construction of reinforced concrete
6. IS : 2210 - Criteria for the design of reinforced concrete shell structures
and folded plates.
7. IS : 2502 - Code of practice for bending and fixing of bars for concrete
8. IS : 5525 - Recommendation for detailing of reinforcement in
reinforced concrete works.
9. IS : 2751 - Code of practice for welding of mild steel plain and
deformed bars used for reinforced concrete construction.
10. IS : 9417 - Specification for welding cold worked bars for reinforced
concrete construction.
11. IS : 3558 - Code of practice for use of immersion vibrators for
consolidating concrete.
12. IS : 3414 - Code of practice for design and installation of joints in
13. IS : 4326 - Code of practice for earthquake resistant design and
construction of building.
14. IS : 4014 - Code of practice for steel tubular scaffolding.
15. IS : 2571 - Code of practice for laying in-situ cement concrete flooring.
16. IS : 7861 - Code of practice for extreme weather concreting.
(Part – 1) - Recommended practice for hot weather concreting.
(Part – 2) - Recommended practice for cold weather concreting.
D.6.2.9 Code for Construction safety
1. IS : 3696 - Safety code for scaffolds and ladders.
(Parts I and III)
2. IS : 7969 - Safety code for handling and storage of building materials.
3. IS : 8989 - Safety code for erection of concrete framed structures.
D.6.2.10 Code for Measurement
1. IS : 1200 - Method of measurement of building and engineering
(Part 1 to 28) works.
2. IS : 3385 - Code of practice for measurement of Civil Engineering
D.6.3.1 Engineer shall have the right at all times to inspect all operations including the sources of
materials, procurement, layout and storage of materials, the concrete batching and mixing
equipment, and the quality control system. Such an inspection shall be arranged and
Engineer’s approval obtained, prior to starting of concrete work. This shall, however, not
relieve Contractor of any of his responsibilities. All materials which doe not conform to this
specification shall be rejected.
D.6.3.2 Materials should be selected so that they can satisfy the design requirements of strength,
serviceability, safety, durability and finish with due regards to the functional requirements
and the environmental conditions to which the structure will be subjected. Materials
complying with codes / standards shall generally be used, other materials may be used after
approval of the Engineer and after establishing their performance suitability based on
previous data, experience or tests.
D.6.4 MATERIALS
D.6.4.1.1 Unless otherwise specified or called for by the Engineer, cement shall be Ordinary Portland
cement conforming to IS (latest edition) as per Schedule-B for construction box etc.
D.6.4.1.2 Where Portland pozzolana or slag cement are used, it shall be ensured that
consistency of quality is maintained, there will be no adverse interactions between the
materials and the finish specified is not marred.
D.6.4.1.3 Only one type of cement shall be used in any one mix. The source of supply, type or brand
of cement within the same structure or portion thereof shall not be changed without approval
D.6.4.1.4 Cement which is not used within 90 days from its date of manufacture shall be tested at a
laboratory approved by Engineer and until the results of such tests are found satisfactory, it
shall not be used in any work.
D.6.4.2 Aggregates (General)
D.6.4.2.1 General
D.6.4.2.1.1“Aggregate” in general designates both find and coarse inert materials used in the
manufacture of concrete (vide BIS 456 & BIS 383) and conforming to tests as per BIS
(Part I to VI).
D.6.4.2.1.2“Coarse Aggregate” is aggregate most of which is retained when passed through on 4.75 mm
D.6.4.2.1.3All fine and coarse aggregates proposed for use in the works shall be subject to the Engineer-
in-Charge’s approval and after specific materials have been accepted, the source of supply of
such materials shall not be changed without prior approval of the Engineer-in-charge.
D.6.4.2.1.4Aggregates shall consist of natural sand, stone (crushed or uncrushed) and gravel from a
source known to produce satisfactory aggregate for concrete and shall be chemically inert,
non-flaky, strong, hard, durable against weathering, or limited porosity and free from
deleterious materials that may cause corrosion of the reinforcement or may impair the
strength and or durability of concrete. The grading of aggregates shall be such as to produce
a dense concrete of specified strength and consistency that will work readily into position
without segregation and shall be based on the “mix design” and preliminary tests on concrete
specified later. The aggregates shall be brought from the source as mentioned in Volume–I
D.6.4.2.2 Sampling and testing
D.6.4.2.2.1 Samples of the aggregates for mixed design and determination of suitability shall be taken
under the supervision of the Engineer-in-charge and delivered to the laboratory, well in
advance of the scheduled placing of concrete. Records of tests, which have been made on
proposed aggregates and on concrete made from this source of aggregates shall be furnished
to Engineer-in-charge in advance of the work, for use in determining aggregate suitability.
The costs of all such tests, sampling etc. shall be borne by the contractor.
D.6.4.2.3 Storage of aggregates
D.6.4.2.3.1All coarse and fine aggregates shall be stacked separately in stock piles in the material yard
near the work site in bins properly constructed to avoid inter mixing of different aggregates.
Contamination with foreign material and earth during storage and while heaping the
materials shall be avoided. The aggregates must be of specified quality not only at the time
of receiving at site but more so at the time of loading into mixer. Rakers shall be piled in
layers not exceeding 1.20 m in height to prevent coning or segregation. Each layer shall
cover the entire area of stock pile before succeeding layers are started. Aggregates that have
become segregated shall be rejected.
D.6.4.2.4 Specific Gravity
D.6.4.2.4.1 Aggregates having a specific gravity below 2.4 (saturated surface dry basis) shall not be
D.6.4.3 Fine Aggregate
D.6.4.3.1 Fine aggregate shall consist of natural or crushed sand conforming to IS 383 conforming to
tests as per IS 2386 part I to IV. The sand shall be clean, sharp, hard, strong and durable and
shall be free from dust, vegetable substances, adherent coating, clay, alkali, organic matter,
mica, salt or other deleterious substances, which can be injurious to the setting qualities /
strength/ durability of concrete.
D.6.4.3.2 Screening and Washing : Sand shall be prepared for use by such screening or washing, or
both, as necessary, to remove all objectionable foreign matter while separating the sand
grains to the required size fraction.
D.6.4.3.3 Foreign Material limitations : The percentage deleterious substances in sand delivered to the
mixer shall not exceeding the following :
Sr. Foreign Material Percentage by weight
No. Uncrushed Crushed
1 Material finer than 75 micron IS sieve 3.0
3 Coal and Lignite 1.0
4 Clay Lumps 1.0
D.6.4.3.4 Gradation : Unless otherwise directed or approved by the Engineer-in-charge, the grading of
sand shall be within the limits indicated hereunder.
IS : Sieve Grading Grading Grading Grading
Designation Zone-I Zone-II Zone-III Zone-IV
D.6.4.3.4.1 Where the grading falls outside the limits of any particular grading zone of sieves, other than
600 microns IS sieve, by total amount not exceeding 5%, it shall be regarded as falling
600 microns IS sieve, by total amount not exceeding 5%, it shall be regarded as falling
within that grading zone. This tolerance shall not be applied to percentage passing the
micron IS sieve or to percentage passing any other sieve on the coarser limit of grading zone
I or the finer limit of grading zone IV. Fine aggregates conforming to grading zone IV shall
not be used. Mix designs and preliminary tests shall show its suitability for producing
concrete of specified strength and workability.
D.6.4.3.5 Fineness Modulus
The sand shall have a fineness modulus of not less than 2.2 or more than 4.2. The fineness
modulus is determined by adding the cumulative percentages retained on the following IS
sieve sizes (4.75 mm, 2.35 mm, 1.18 mm, 600 microns and 150 microns) and dividing the
D.6.4.4 Coarse Aggregate
D.6.4.4.1 Coarse aggregate for concrete, except as noted above, shall conform to IS 383 and IS
This shall consist of crushed stone and shall be clean and free from elongated, flaky or
laminated pieces, adhering coatings, clay lumps, coal residue, clinkers, slag, alkali, mica,
organic matter or other deleterious matter.
D.6.4.4.2 Screening and Washing : Crushed rock shall be screened and or washed for the removal of
dirt or dust coating, if so requested by the Engineer-in-charge.
D.6.4.4.3 Grading
D.6.4.4.3.1Coarse aggregate shall be either in single size or graded, in both cases the grading shall be
within the following limits :
IS Percentage passing for single sized Percentage passing for graded
Sieve aggregate of normal size aggregate of normal size
D.6.4.4.3.2 The pieces shall be angular in shape and shall have granular or crystalline surfaces. Friable,
flaky and laminated pieces, mica and shale, if present, shall be only within tolerance limits
which will not affect adversely the strength and or durability or concrete. The maximum size
of coarse aggregate shall be 40 mm for M7.5 and M10 and 20 mm for M15 to M20 concrete,
or as directed by the Engineer-in-charge or specified otherwise. The maximum size of
coarse aggregate shall be the maximum size specified above but in no case greater than ¼th
of the minimum thickness of the member, provided that the concrete can be placed without
difficulty so as to surround all reinforcement thoroughly and fill the corners of the form. For
plain concrete the maximum size of aggregate shall be of 40 mm. for heavily reinforced
concrete members, the nominal maximum size of the aggregate shall be 5 mm less than the
minimum clear distance between the reinforcing main bars or 5 mm less than the minimum
cover reinforcement whichever is smaller.
D.6.4.4.4 Foreign material limitations
D.6.4.4.4.1 The percentage of deleterious materials in the aggregate delivered to the mixer shall not
exceed the following :
Sr. Foreign Material Percentage by weight
No. Uncrushed Crushed
1 Material finer than 75 micron 3.0
2 Coal and lignite 1.0
3 Clay lumps 1.0
4 Soft fragments 3.0 --
D.6.4.5.1 Water used for both mixing and curing shall conform to IS : 456. Potable water is generally
satisfactory. Water containing any excess of acid, alkali, sugar or salt shall not be used.
D.6.4.6 Reinforcement
D.6.4.6.1 Reinforcement bars shall conform to IS : 432, IS : 226 or IS : 1786 and the welded wire
fabric to IS : 1566 as shown or specified on the drawings. Only T.M.T. bars as for
specification will be followed.
D.6.4.6.2 All reinforcement shall be clean, free from pitting, oil, grease, paint, loose mill scales, rust,
dirty dust or any other substance that will destroy or reduce bond.
D.6.4.6.3 If permitted by Engineer, welding of reinforcement shall be done in accordance with IS ;
2751 or IS : 9417 as applicable.
D.6.4.7 Admixtures
D.6.4.7.1 Plasticizer, water-reducing add mixture and concrete water proofer shall conform to IS :
9103 and integral water proofing admixtures to IS : 2645. Dosage of plasticizer used in
concrete work shall be 300 ml / 50 kg of cement. Manufacturer must comply ISO-9002
specifications.
D.6.4.7.2 Admixtures may be used in concrete as per manufacturer’s instructions only with the
approval of Engineer based upon evidence that with the passage of time neither the
compressive strength nor its durability is reduced. An admixture’s suitably and effectiveness
shall be verified by trial mixes with the other material used in the works. If two or more
admixtures are to be used simultaneously in the same concrete mix, their interaction shall be
checked and trial mixes done to ensure their compatibility. There should also be no increase
in risk of corrosion of the reinforcement or other embedments.
D.6.4.7.3 Calcium chloride shall not be used for accelerating set of the cement for any concrete
containing reinforcement or embedded steel parts. When calcium chloride is permitted such
as in mass concrete works, it shall be dissolved in water and added to the mixing water by an
amount not exceeding 1.5 percent of the weight of the cement in each batch of concrete. The
designed concrete mix shall be corrected accordingly.
D.6.4.8 Wastage
D.6.4.8.1 No wastage allowance for cement and steel shall be considered and paid for.
D.6.5 SAMPLES AND TESTS
D.6.5.1 All materials used for the works shall be tested before use.
D.6.5.2 Manufacturer’s test certificate shall be furnished, for each batch of cement / steel and when
directed by Engineer samples shall also be got tested by the Contractor in a laboratory
approved by Engineer at no extra cost to Client. However, where material is supplied by
Client, all testing charges shall be borne by Client; but transportation of material samples to
the laboratory shall have to be done by Contractor at no extra cost.
D.6.5.3 Sampling and testing shall be as per IS : 2386 under the supervision of Engineer. The cost of
all tests, sampling etc. shall be borne by Contractor.
D.6.5.4 Water to be used shall be tested to comply with requirement of IS :
D.6.5.5 Contractor shall furnish manufacturer’s test certificates and technical literature for the
admixture proposed to be used. If directed the admixture shall be got tested and approved
laboratory at no extra cost.
D.6.6 STORING OF MATERIALS
D.6.6.1 All material shall be stored in a manner so as to prevent its deterioration and contamination
which would preclude its use in the works. Requirements of IS : 4082 shall be complied
D.6.6.2 Contractor will have to make his own arrangements for the storage of adequate quantity of
cement even if cement is supplied by Client. Cost of such rejected cement, where cement is
supplied by Client, shall be recovered at issue rate or open market rate which ever is higher.
Cement bags shall be stored in dry weatherproof shed with a raised floor, well away from the
outer walls and insulated from the floor to avoid moisture from ground. Not more than
bags shall be stacked in any tier. Storage arrangement shall be approved by Engineer.
Storage under tarpaulins shall not be permitted. Each consignment of cement shall be stored
separately and consumed in its order or receipt.
D.6.6.3 Each size of coarse and fine aggregates shall be stacked separately and shall be protected
from leaves and contamination with foreign material. The stacks shall be on hard, clean, free
draining bases, draining away from the concrete mixing area.
D.6.6.4 Contractor shall make his own arrangements for storing water at site in tanks to prevent
D.6.6.5 The reinforcement shall be stacked on top of timber sleepers to avoid contract with ground /
water. Each type and size shall be stacked separately.
D.6.7.1 General
Concrete grade shall be as designated on drawings. In concrete grade M15, M20, M25 etc.
the number represents the specified characteristic compressive strength of 150 mm cube at
28 days, expressed in N/sq.mm as per IS : 456. Concrete in the works shall be “Design Mix
Concrete” or “Normal Mix Concrete”. All concrete works of grade M5, M7.5 and M10 shall
be Nominal whereas all other grades, M15 and above, shall be Design Mix Concrete.
D.6.7.2 Design Mix Concrete
D.6.7.2.1 Mix Design and Testing
D.6.7.2.1.1 For Design Mix Concrete, the mix shall be designed according to IS : 10262 and SP: 23 to
provide the grade of concrete having the required workability and characteristics strength not
less than appropriate values given in IS : 456. The design mix shall in addition be such that
it is cohesive and does not segregate and should result in dense and durable concrete and also
capable of giving the finish as specified. For water retaining structures, the mix shall also
result in water-tight concrete. The Contractor shall exercise great care while designing the
concrete mix and executing the works to achieve the desired result.
D.6.7.2.1.2 Unless otherwise specifically mentioned, the minimum cement content for Design Mix
Concrete shall be as given below.
Grade of Concrete Minimum Cement Content in
Kg/Cu.m of concrete
The minimum cement content stipulated above shall be adopted irrespective of whether the
Contractor achieves the desired strength with less quantity of cement. The Contractor’s
quoted rates for concrete shall provide for the above eventually and nothing extra shall
become payable to the Contractor in this account. Even in the case where the quantity of
cement required is higher than that specified above to achieve desired strength based on an
approved mix design, nothing extra shall become payable to the Contractor.
D.6.7.2.1.3 It shall be Contractor’s sole responsibility to carry out the mix designs at his own cost. He
shall furnish to Engineer at least 30 days before concreting operations, a statement of
proportions proposed to be used for the various concrete mixes and the strength results
obtained. The strength requirements of the concrete mixes ascertained on 150 mm cubes as
per IS : 516 shall comply with the requirements of IS :
Grade of Concrete Minimum Compressive Specified compressive
Strength strength
(N/Sq.mm at 7 days) (N/Sq.mm at 28 days)
D.6.7.2.1.4 A range of slumps, which shall generally be used for various types of construction unless
otherwise instructed by the Engineer is given below :
Structure / Member
Slump in millimeters
Maximum Minimum
Reinforced foundation walls and footings 75
Plain footings, caissons and substructure walls 75
T.G. and massive compressor foundations 50
Slabs, beams and reinforced walls 100
Pumps and miscellaneous equipment foundations 75
Building columns 100
Heavy mass construction 50
D.6.7.2.2 Batching and Mixing of Concrete
D.6.7.2.2.1 Proportions of aggregates and cement, as decided by the concrete mix design, shall be by
weight. These proportions shall be maintained during subsequent concrete batching by
means of weigh batchers capable of controlling the weights within one percent of the desired
D.6.7.2.2.2 Amount of water added shall be such as to produce dense concrete of required consistency,
specified strength and satisfactory workability and shall be so adjusted to account for
moisture content in the aggregates. Water cement ratio specified shall be maintained. Each
time the work stops, the mixer shall be cleaned out, and while recommencing, the first batch
shall have 10% additional cement to allow for sticking in the drum.
D.6.7.2.2.3 Arrangement should be made by Contractor to have the cubes tested in an approved
laboratory or in field at his own expense, with prior consent of Engineer. Sampling and
testing of strength and workability of concrete shall be as per IS : 1199, IS : 516 and IS :
D.6.7.3 Nominal Mix Concrete
D.6.7.3.1 Mix Design and Testing
D.6.7.3.1.1 Mix design and preliminary tests are not necessary for Nominal mix Concrete. However
works tests shall be carried out as per IS : 456. Proportions for Nominal Mix Concrete and
water / cement ratio may by adopted as per Table 3 of IS : 456. However it will be
Contractor’s sole responsibility to adopt appropriate nominal mix proportions to yield the
specified strength.
D.6.7.3.2 Batching and Mixing Concrete
D.6.7.3.2.1 Based on the adopted nominal mixes, aggregates and cement shall be measured by weight.
D.6.8 FORM WORK
D.6.8.1 Form work shall be all inclusive and shall consist of but not limited to shores, bracings, sides
of footings, walls, beams and columns, bottom of slabs etc. including ties, anchors, hangers,
inserts, falsework, wedges etc.
D.6.8.2 The design and engineering of the formwork as well as its construction shall be the
responsibility of Contractor. However, if so desired by Engineer the drawings and
calculations for the design of the formwork shall be submitted to Engineer for approval.
D.6.8.3 Formwork shall be designed to fulfill the following requirements :
a) Sufficiently rigid and tight to prevent loss of grout or mortar from the concrete at all
stages and appropriate to the methods of placing and compacting.
b) Made of suitable materials.
c) Capable of providing concrete of the correct shape and surface finish within the
specified tolerance limits.
d) Capable of withstanding without deflection the worst combination of self weight,
reinforcement and concrete weight, all loads and dynamic effects arising from
construction and compacting activities, wind and weather forces.
e) Capable of easily striking without shock, disturbance or damage to the concrete.
f) Soffit forms capable of imparting a camber if required.
g) Soffit forms and supports capable of being left in position if required.
h) Capable of being cleaned and / or coated if necessary immediately prior to casting
the concrete; design temporary openings where necessary for these purposes and to
facilitate the preparation of construction joints.
D.6.8.4 The formwork may be of timber, plywood, steel, plastic or concrete depending upon the type
of finish specified. Sliding forms and slip for may be used with the approval of Engineer.
Timber for formwork shall be well seasoned, free from sap, shakes, loose knots, work holes,
warps and other surface defects. Joints between formwork and formwork and between
formwork and structures shall be sufficiently tight to prevent loss of slurry from concrete,
using seals if necessary.
D.6.8.5 The faces of formwork coming in contact with concrete shall be cleaned and two coats of
approved mould oil applied before fixing reinforcement. All rubbish, particularly chippings,
shavings, sawdust, wire pieces dust etc. shall be removed from the interior of the forms
before the concrete is placed. Where directed, cleaning of forms shall be done by blasting
with a jet of compressed air at no extra cost.
D.6.8.6 Forms intended for reuse shall be treated with care. Forms that have deteriorated shall not be
used. Before reuse, all forms shall be thoroughly scraped, cleaned, nails removed, holes
suitably plugged, joints repaired and warped lumber replaced to the satisfaction of Engineer.
The Contractor shall equip himself with enough shuttering to allow for wastage so as to
complete the job in time.
D.6.8.7 Permanent formwork shall be checked for its durability and capability with adjoining
concrete before it is used in the structure. It shall be properly anchored to the concrete.
D.6.8.8 Wire ties passing through beams, columns and walls shall not be allowed. In their placed
bolts passing through sleeves shall be used. Formwork spacers left in situ shall not impair
the desired appearance or durability of the structure by causing spalling, rust staining or
allowing the passage or moisture.
D.6.8.9 For liquid retaining structures sleeves shall not be provided for through bolts or shall through
bolts be removed if provided. The bolts, in the latter case, shall be cut at 25 mm depth from
the surface and the hole made good by cement mortar of the same proportion as the concrete
just after striking the formwork.
D.6.8.10 Where specified or shown on drawings, all corners and angles exposed in the finished
structure shall have chamfers or fillets of 20 mm x 20 mm size.
D.6.8.11 Forms for substructure may be omitted when, in the opinion of Engineer, the open
excavation is firm enough (in hard non-porous soils) to act as a form. Such excavations shall
be slightly larger, as directed by Engineer, than that required as per drawing to compensate
for irregularities in excavation.
D.6.8.12 The Contractor shall provide adequate props carried down to a firm bearing without
overloading any of the structures.
D.6.8.13 The shuttering for beams and slabs shall be so erected that the side shuttering of beams can
be removed without disturbing the bottom shuttering. If the shuttering for a column is
erected for the full height of the column, one side shall be built up in sections as placing of
concrete proceeds or windows left for placing concrete from the side limit the drop of
concrete to 1.0 m or as directed by Engineer. The Contractor shall temporarily and securely
fix items to be cast in (embedments / inserts) in a manner that will not hinder the striking of
forms or permit loss of grout.
D.6.8.14 Formwork showing excessive distortion, during any stage of construction, shall be
repositioned and strengthened. Placed concrete affected by faulty form work, shall be
entirely removed and formwork corrected prior to placement of new concrete at the cost of
the Contractor.
D.6.8.15 The striking time for formwork shall be determined based on following requirements :
a) Development of adequate concrete strength;
b) Permissible deflection at time of striking form work;
c) Curing procedure employed – its efficiency and effectiveness;
d) Subsequent surface treatment to be done;
e) Prevention of thermal cracking at re-entrant angles;
f) Ambient temperature; and
g) Aggressiveness of the environment (unless immediate adequate steps are taken to
prevent damage to the concrete).
D.6.8.16 Under normal circumstances (generally where temperatures are above 20 Deg. C) forms may
be struck after expiry of the time period given in IS : 456, unless directed otherwise by
Engineer. For portland pozzolona / slag cement the stripping time shall be suitably modified
as directed by the Engineer. It is the Contractor’s responsibility to ensure that forms are not
struck until the concrete has developed sufficient strength to support itself, does not undergo
excessive deformation and resist surface damage and any stressed arising during the
construction period.
D.6.9 Reinforcement Workmanship
D.6.9.1 Reinforcing bars supplied bent or in coils shall be straightened cold without damage at no
extra cost. No bending shall be done when ambient temperature is below 5 Deg. C. Local
warming may be permitted if steel is kept below 100 Deg. C.
D.6.9.2 All bars shall be accurately bent gradually and according to the sizes and shapes shown on
the drawings / schedules or as directed by Engineer.
D.6.9.3 Re-bending or straightening incorrectly bent bars shall not be done without approval of
D.6.9.4 Reinforcement shall be accurately fixed and maintained firmly in the correct position by the
use of blocks, spacers, chairs, binding wire etc. to prevent displacement during placing and
compaction of concrete. The tied in place reinforcement shall be approved by Engineer prior
to concrete placement. Spacers shall be of such materials and designs as will be durable, not
lead to corrosion of the reinforcement and not cause spalling of the concrete cover.
D.6.9.5 Binding wire shall be 16 gauge soft annealed wire. Ends of the binding wire shall be bent
away from the concrete surface and in no case encroach into the concrete cover.
D.6.9.6 Substitution of reinforcement, laps / splices not shown on drawing shall be subject to
Engineer’s approval.
D.6.10 TOLERANCES
D.6.10.1 Tolerance for formed and concrete dimensions shall be as per IS : 456 unless specified
D.6.10.2 Tolerances specified for horizontal or vertical building lines or footings shall not be
construed to permit encroachment beyond the legal boundaries.
D.6.11 PREPARATION PRIOR TO CONCRETE PLACEMENT
D.6.11.1 Before concrete is actually placed in position, the inside of the formwork shall be cleaned
and mould oil applied, inserts and reinforcement shall be correctly positioned and securely
held, necessary openings, pockets etc. provided.
D.6.11.2 All arrangements formwork, equipment and proposed procedure, shall be approved by
Engineer. The Contractor shall maintain separate Pour Card for each pour as per the
format enclosed and shall produce before commencement of concreting to Engineer-in-
D.6.12 TRANSPORTING, PLACING AND COMPACTING CONCRETE
D.6.12.1 Concrete shall be transported from the mixing plant to the formwork with minimum time
lapse by methods that shall maintain the required workability and will prevent segregation,
loss of any ingredients or ingress of foreign matter or water.
D.6.12.2 In all cases concrete shall be deposited as nearly as practicable directly in its final position.
To avoid segregation concrete shall not be rehandled or caused to flow. For locations where
direct placement is not possible and in narrow forms. The Contractor shall provide suitable
drops and ‘Elephant Trunks’. Concrete shall not be dropped from a height of more than
m as stipulated in clause D.6.8.13.
D.6.12.3 Concrete shall not be placed in flowing water. Under water, concrete shall be placed in
position by tremies or by pipeline from the mixer and shall never be allowed to fall freely
through the water.
D.6.12.4 While placing concrete the Contractor shall proceed as specified below and also ensure the
a) Continuously between construction joints and predetermined abutments.
b) Without disturbance to forms or reinforcement.
c) Without disturbance to pipes, ducts, fixings and the like to be cast in; ensure that
such items are securely fixed. Ensure that concrete cannot enter open ends of pipes
and conduits etc.
d) Without dropping in a manner that could cause segregation or shock.
e) In deep pours only when the concrete and formwork designed for this purpose and
by using suitable chutes or pipes.
f) Do not place if the workability is such that full compaction cannot be achieved.
g) Without disturbing the unsupported sides of excavations; prevent contamination of
concrete with earth. Provide sheeting if necessary. In supported excavations,
withdraw the lining progressively as concrete is placed.
h) If placed directly onto hardcore or any other porous material, dampen the surface to
reduce loss of water from the concrete.
i) Ensure that there is no damage or displacement to sheet membranes.
j) Record the time and location of placing structural concrete.
D.6.12.5 Concrete shall normally be compacted in its final position within thirty minutes of leaving
the mixer. Concrete shall be compacted during placing with approved vibrating equipment
without causing segregation until it forms a solid mass free from voids thoroughly worked
around reinforcement and embedded fixtures and into all corners of the formwork.
Immersion vibrators shall be inserted vertically at points not more than 450 mm apart and
withdrawn slowly till air bubbles cease to come to surface, leaving no voids. When placing
concrete in layers advancing horizontally, care shall be taken to ensure adequate vibration,
blending and melding of the concrete between successive layers. Vibrators shall not be
allowed to come in contact with reinforcement, formwork and finished surfaces after start of
initial set. Over vibration shall be avoided.
D.6.12.6 Concrete may be conveyed and placed by mechanically operated equipment after getting the
complete procedure approved by Engineer. The slump shall be held to the minimum
necessary for conveying concrete by this method. When concrete is to be pumped concrete
mix shall be specially designed to suit pumping. Care shall be taken to avoid stoppages in
work once pumping has started.
D.6.12.7 Except when placing with slip forms, each placement of concrete in multiple lift work, shall
be allowed to set for at least 24 hours after the final set of concrete before the start of
subsequent placement. Placing shall stop when concrete reaches the top of the opening in
walls or bottom surface of slab, in slab and beam construction, and it shall be resumed before
concrete takes initial set but not until it has had time to settle as determined by Engineer.
Concrete shall be protected against damage until final acceptance.
D.6.13 MASS CONCRETE WORKS
D.6.13.1 Sequence of pouring for mass concrete works shall be as approved by Engineer. The
Contractor shall exercise great care to prevent shrinkage cracks and shall monitor the
temperature of the placed concrete if directed.
D.6.14.1 Curing and protection shall start immediately after the compaction of the concrete to protect
(a) premature drying out, particularly by solar radiation and wind;
(b) leaching out by rain and flowing water;
(c) rapid cooling during the first few days after placing;
(d) high internal thermal gradients;
(e) low temperature of frost;
(f) vibration and impact which may disrupt the concrete and interfere with its bond to the
D.6.14.2 All concrete, unless directed otherwise by Engineer, shall be cured by use of continuos
sprays or ponded water or continuously saturated coverings of sacking, canvas, hessain or
other absorbent material for the period of complete hydration with a minimum of 7 days.
The quality of curing water shall be the same as that used for mixing.
D.6.14.3 Where a curing membrane is directed to be used by the Engineer, the same shall be of a non-
wax base and shall not impair the concrete finish in any manner. The curing compound to be
used shall be got approved from the Engineer before use and shall be applied with spraying
equipment capable of a smooth, even textured coat.
D.6.14.4 Curing may also be done by covering the surface with an impermeable material such as
polyethylene, which shall be well sealed and fastened.
D.6.14.5 Extra precautions shall be exercised in curing concrete during cold and hot weather.
D.6.15 CONSTRUCTION JOINTS AND KEYS
D.6.15.1 Construction joints will be as shown on the drawing or as approved by Engineer. Concrete
shall be placed without interruption until completion of work between construction joints. If
stopping of concreting becomes unavoidable anywhere, a properly formed construction joint
shall be made with the approved of Engineer.
D.6.15.2 Dowels for concrete work, not likely to be taken up in the near future, shall be coated with
cement slurry and encased in lean concrete as indicated on the drawings or as directed by
D.6.15.3 Before resuming concreting on a surface which has hardened all laitance and loose stone
shall be thoroughly removed by wire brushing / hacking and surface washed with high
pressure water jet and treated with thin layer of cement slurry for vertical joints and a 15 mm
thick layer of cement sand mortar for horizontal layers, the ratio of cement and sand being
the same as in the concrete mix.
D.6.15.4 When concreting is to be resumed on a surface which has not fully hardened, all laitance
shall be removed by wire brushing, the surface wetted, free water removed and a coat of
cement slurry applied. On this a layer of concrete not exceeding 150 mm thickness shall be
placed and well rammed against the old work. Thereafter work shall proceed in the normal
D.6.16 FOUNDATION BEDDING
D.6.16.1 All earth surfaces upon which or against which concrete is to be placed, shall be well
compacted and free from standing water, mud or debris. Soft or spongy area shall be cleaned
out and back filled with either soil cement mixture, lean concrete or clean sand compacted as
directed by Engineer. The surfaces of absorptive soils shall be moistened.
D.6.16.2 Concrete shall not be deposited on large sloping rock surfaces. The rock shall be cut to form
rough steps or benches by picking, barring or wedging. The rock surface shall be kept wet
for 2 to 4 hours before concreting.
D.6.17 FINISHES
D.6.17.1 General
D.6.17.1.1 The formwork for concrete works shall be such as to give the finish as specified. The
Contractors shall make good as directed any unavoidable defects consistent with the type of
concrete and finish specified; defects due to bad workmanship (e.g. damaged or misaligned
forms, defective or poorly compacted concrete) will not be accepted. The Contractor shall
construct the formwork using the correct materials and to meet the requirements of the
design and to produce finished concrete to required dimensions, plumbs, planes and finishes.
D.6.17.2 Surface finish Type F1
D.6.17.2.1 This type of finish shall be for non-exposed concrete surface against which back fill or
concrete is to be placed. The main requirement is that of dense, well compacted concrete.
No treatment is required except repair of defective areas, filling all form tie holes and
cleaning up of loose or adhering debris. For surfaces below grade which will receive
waterproofing treatment the concrete shall be free of surface irregularities which could
interfere with proper and effective application or waterproofing material specified for use.
D.6.17.3 Surface finish Type F2
D.6.17.3.1 This type of finish shall be for all concrete work which will be exposed to view upon
completion of the job. The appearance shall be that of a smooth dense, well-compacted
concrete showing the slight marks of well fitted shuttering joints. The Contractor shall make
good any blemishes.
D.6.17.4 Surface finish Type F3
D.6.17.4.1 This type of finish shall be for concrete work which will be exposed to view but to give an
appearance of smooth, dense, well-compacted concrete with no shutter marks, stain free and
with no discoloration, blemishes, arrises, air holes etc. Only lined or coated plywood with
very tight joints shall be used to achieve this finish. The panel size shall be uniform and as
large as practicable. Any minor blemishes that might occur shall be made good by
D.6.17.5 Integral cement finish on concrete floor
D.6.17.5.1 In all cases where integral cement finish on a concrete floor has been specified, the top layer
of concrete shall be screened off to proper level and tamped with tamper having conical
projections so that the aggregate shall be forced below the surface. The surface shall be
finished with a wooden float and a trowel with pressure. The finish shall be continued till the
concrete reaches its initial set. No cement or cement mortar finish shall be provided on the
surface. Where specified, a floor hardener as approved by the Engineer shall be supplied and
used as recommended by the manufacturer.
D.6.18 REPAIR AND REPLACEMENT OF UNSATISFACTORY CONCRETE
D.6.18.1 Immediately after the shuttering is removed, all the defective areas such as honey-combed
surfaces, rough patches, holes left by form bolts etc. shall be brought to the notice of
Engineer who may permit patching of the defective areas or reject the concrete work.
D.6.18.2 All through holes for shuttering shall be filled for full depth and neatly plugged flush with
D.6.18.3 Rejected concrete shall be removed and replaced by Contractor at no additional cost to
D.6.18.4 For patching of defective areas all loose materials shall be removed and the surface shall be
prepared as directed by the Engineer.
D.6.18.5 Bonding between hardened and fresh concrete shall be done either by placing cement mortar
or by applying epoxy. The decision of the Engineer as to the method of repairs to be adopted
shall be final and binding on the Contractor and no extra claim shall be entertained on this
account. The surface shall be saturated with water for 24 hours before patching is done with
1:5 cement sand mortar. The use of epoxy for bonding fresh concrete shall be carried out as
directed by Engineer.
D.6.20 HOT WEATHER REQUIREMENTS
D.6.20.1 Concreting during hot weathers shall be carried out as per IS : 7861 (Part – I)
D.6.20.2 Adequate provisions shall be made to lower concrete temperatures which shall not exceed
Deg. C at the time of placement of fresh concrete.
D.6.20.3 Where directed by Engineer, Contractor shall spray non-wax based curing compound of
unformed concrete surfaces at no extra costs.
D.6.21 COLD WEATHER REQUIREMENTS
D.6.21.1 Concreting during cold weather shall be carried out as per IS : 7861 (Part-II).
D.6.21.2 The ambient temperature during placement and upto final set shall not fall below 5 Deg. C.
Approved antifreeze / accelerating additives shall be used where directed.
D.6.21.3 For major and large scale concreting works the temperature of concrete at times of mixing
and placing, the thermal conductivity of the formwork and its insulation and stripping period
shall be closely monitored.
D.6.22 LIQUID RETAINING STRUCTURES
D.6.22.1 The Contractor shall take special care of concrete for liquid retaining structures, underground
structures and those others specifically called for to guarantee the finish and water tightness.
D.6.22.2 The minimum level of surface finish for liquid retaining structures shall be type F2. All such
structures shall be hydro-tested.
D.6.22.3 The Contractor shall include in his price of hydro-testing of structure, all arrangements for
testing such as temporary bulk heads, pressure gauges, pumps, pipelines etc.
D.6.22.4 Any temporary arrangements that may have to be made to ensure stability of the structures
shall also be considered to have been taken into account while quoting the rates.
D.6.22.5 Any leakage that may occur during the hydro-test or subsequently during the defects liability
period or the period for which the structure is guaranteed shall be effectively stopped either
by cement / epoxy pressure grouting, guniting or such other methods as may be approved by
the Engineer. All such rectification of the Client / Engineer at no extra cost to the Client.
D.6.23 TESTING CONCRETE STRUCTURES FOR LEAKAGE
D.6.23.1 Hydro-static test for water tightness shall be done at full storage by Engineer, as described
D.6.23.1.1 In case of structures whose external faces are exposed, such as elevated tanks, the
requirements of the test shall be deemed to be satisfied if the external faces show no sign of
leakage or sweating and remain completely dry during the period of observation of seven
days after allowing a seven day period for absorption after filling with water.
D.6.23.1.2 In the case of structures whose external faces are submerged and are not accessible for
inspection, such as underground tanks, the structures shall be filled with water and after the
expiry of seven days after the filling, the level of the surface of the water shall be recorded.
The level of water shall be recorded again at subsequent intervals of 24 hrs. over a period of
seven days. Backfilling shall be withheld till the tanks are tested. The total drop in surface
level over a period for seven day shall be taken as an indication of the water tightness of the
structure. The Engineer shall decide on the actual permissible nature of this drop in the
surface level, taking into account weather the structures are open or closed and the
corresponding effect it has on evaporation losses. Unless specified otherwise, a structure
whose top is covered shall be deemed to be water tight if the total drop in the surface level
over a period of seven days does not exceed 40 mm.
D.6.23.1.3 Each compartment / segment of the structure shall be tested individually and then all
D.6.23.2 For structures such as pipes, tunnels etc. the hydro-static test shall be carried out by filling
with water, after curing as specified, and subjecting to the specified test pressure for
specified period. If during this period the loss of water does not exceed the equivalent of the
specified rate, the structure shall be considered to have successfully passed the test.
D.6.24 OPTIONAL TESTS
D.6.24.1 If Engineer feels that the materials i.e. cement, sand coarse aggregates, reinforcement and
water are not in accordance with the specifications or if specified concrete strengths are not
obtained, he may order tests to be carried out on these materials in laboratory, to be approved
by the Engineer, as per relevant IS Codes. Client shall pay only for the testing of material
supplied by the Client, otherwise Contractor shall have to pay for the tests. Transporting of
all material to the laboratory shall however be done by the Contractor at no extra cost to
D.6.24.2 In the even of any work being suspected of faulty material or workmanship requiring its
removal or if the works cubes do not give the stipulated strengths, Engineer reserves the right
to order the Contractor to take out cores and conduct tests on them or do ultrasonic testing or
load testing of structure, etc. All these tests shall be carried out by Contractor at no extra
cost to the Client. Alternatively Engineer also reserves the right to ask the Contractor to
dismantle and re-do such unacceptable work at the cost of Contractor.
D.6.24.3 If the structure is certified by Engineer as having failed, the cost of the test and subsequent
dismantling / reconstruction shall be borne by Contractor.
D.6.24.4 The quoted unit rates / prices of concrete shall be deemed to provide for all tests mentioned
D.6.25 GROUTING
D.6.25.1 Grout shall be provided as specified on the drawings. The proportion of standard Grout shall
be such as to produce a flowable mixture consistent with minimum water content and
shrinkage. Surface to be grouted shall be thoroughly roughened and cleaned. All structural
steel elements to be grouted, shall be cleaned of oil, grease, dirt etc. The use of hot, strong
caustic solution for this purpose will be permitted. Prior to grouting, the hardened concrete
shall be saturated with water and just before grouting water in all pockets shall be removed.
Grouting once started shall be done quickly and continuously. Variation in grout mixes and
procedures shall be permitted if approved by ENGINEER. The grout proportions shall be
limited as follows :
Use Grout Thickness Mix Proportions W/C Ratio
a) Fluid mix Under 25 mm One part Portland cement
to one part sand.
b) General mix 25 mm and over but One part Portland cement
less than 50 mm to 2 part sand.
c) Stiff mix 50 mm and over One part Portland cement
to 3 part sand.
D.6.25.2 Non Shrink Grout
D.6.25.2.1 Non-shrink grout where called for in the Schedule of Quantities or specified on the drawings
shall be provided in strict accordance with the manufacturer’s instructions/ specifications on
D.6.26 INSPECTION
D.6.26.1 All materials, workmanship and finished construction shall be subject to continuous
inspection and approval of Engineer. Materials rejected by Engineer shall be expressly
removed from site and shall be replaced by Contractor immediately at no extra cost to Client.
D.6.27 CLEAN-UP
D.6.27.1 Upon the completion of concrete work, all forms, equipment, constructiontools, protective
coverings and any debris, scraps of wood etc. resulting from the work shall be removed and
the premises left clean.
D.6.28 ACCEPTANCE CRITERIA
D.6.28.1 Any concrete work shall satisfy the requirements given below individually and collectively
for it to be acceptable.
a) Properties of constituent materials;
b) Characteristic compressive strength;
c) Specified mix proportions;
d) Minimum cement content;
e) Maximum free-water / cement ratio;
f) Workability;
g) Temperature of fresh concrete;
h) Density of fully compacted concrete;
i) Cover to embedded steel;
k) Tolerances in dimensions;
l) Tolerances in levels;
n) Surface finishes;
o) Special requirements such as :
i) water tightness;
ii) resistance to aggressive chemicals
iii) resistance to freezing and thawing
iv) very high strength
v) improved fire resistance
vi) wear resistance
vii) resistance to early thermal cracking
D.6.28.2 The Engineer’s decision as to the acceptability or otherwise of any concrete work shall be
final and binding of the Contractor.
D.6.28.3 For work not accepted, the Engineer may review and decide whether remedial measures are
feasible so as to render the work acceptable. The Engineer shall in that case direct the
Contractor to undertake and execute the remedial measures. These shall be expeditiously and
effectively implemented by the Contractor. Nothing extra shall become payable to the
Contractor. Nothing extra shall become payable to the Contractor by the Client for executing
the remedial measures.
D.6.29 MODE OF MEASUREMENT AND PAYMENT
D.6.29.1 The unit rate for concrete work under various categories shall be all inclusive and no claims
for extra payment on account of such items as leaving holes, embedding inserts, etc. shall be
entertained unless separately provided for in the schedule of quantities. No extra claim shall
also be entertained due to change in the number, position and / or dimensions of holes, slots
or openings, sleeves, inserts or on account of any increased lift, lead of scaffolding etc. All
these factors should be take into consideration while quoting the unit rates. Unless provided
for in the Schedule of Quantities the rates shall also include fixing insets in all concrete
work, whenever required.
D.6.29.2 Payments for concrete will be made on the basis of unit rates quoted for the respective items
in the Schedule of Quantities. No deduction in the concrete quantity will be made for
reinforcements, inserts etc. and opening less than 0.100 of a sq.m in areas where concrete is
measured in sq.m and 0.010 cu.m where concrete is measured in cu.m. Where no such
deduction for concrete is made, payment for shuttering work provided for such holes,
pockets, etc. will not be made. Similarly the unit rates for concrete work shall be inclusive or
exclusive of shuttering as provided for in the Schedule of Quantities.
D.6.29.3 Payment for beams will be made for the quantity based on the depth being reckoned from the
understide of the slabs and length measured as the clear distance between supports. Payment
for columns shall be made for the quantity based on height reckoned upto the underside of
D.6.29.4 The unit rate for precast concrete members shall include formwork, mouldings, finishing,
hoisting and setting in position including setting mortar, provision of lifting arrangement etc.
complete. Reinforcement and inserts shall be measured and paid for separately under
respective item rates.
D.6.29.5 Only the actual quantity of steel embedded in concrete including laps as shown on drawings
or as approved by Engineer shall be measured and paid for, irrespective of the level or height
at which the work is done. The unit rates for reinforcement shall include lap chairs, spacer
D.6.29.6 Where the formwork is paid for separately, it shall be very clearly understood that payment
for formwork is inclusive of formwork, shuttering, shoring, propping scaffolding etc.
complete. Only the net area of concrete formed (shuttered) shall be measured for payment.
CONCRETE POUR CARD
Client : Date :
Project : Structure :
Contractor : Max. Aggregate size slump : mm/ mm/
Drg. NO. : Start/ Completion Time :
Concrete Grade : Mixing Time :
Sr. Item Contractor’s Engineer’s Remarks
No. Rep. Signature Signature
1 Centre lines Checked
2 Form work and Staging checked for Accuracy,
Strength & finish
3 Reinforcement Checked
4 Cover to Reinforcement Checked
5 Verified test certificate for cement / steel Yes / No Yes / No
6 Adequacy of Materials / Equipment Yes / No Yes / No
7 Embeded Parts checked Civil
(Location and Plumb)
Pour Authorised site Engineer
8 Soffit(S) and pour top ( T ) levels S(B) T(B)
checked before ( B ) and after (A) S(A) T(A)
from removal (Only of Beams of over
1 M. span & Important structures link
9 Construction joint location & time (If
not as per Drawing)
10 Cement Consumption in Kgs.
11 Numbers of cubes and identification
12 Test cube results (7 Days / 28 Days)
13 Concrete Condition on Form removal
Very Good/ Good / Fair / Poor
Engineer-in-Charge Contractor
1. Each item to be checked & signed by the respective engineers.
2. Item 8 to 13 ( Both inclusive ) to be filled by only engineers of the client.
3. Each pour to have separate cards in triplicate one each for client & site office.
4. Under remarks indicate deviations from drawings & specifications congestion in
reinforcement if any unusual occurrences such as failure of equipment sinking of
supports / props, heavy rain affecting reasonable. Poor compaction improper
curing other deficiencies observations etc.
D.6.31 MATERIALS : STRUCTURAL STEEL
All structural steel shall be comply with the requirements of IS 226-1961 and structural
steel work IS 1915-1962 specifications for structural steel.
D.6.31.1 Steel for Pins and Rollers
Rolled steel pins and rollers, shall comply with requirements of the IS specifications
appropriate for the work. Steel casting for cast steel pins shall conform to grade 1 or 3 of
IS 1030-1956 specifications for steel casting (for general engineering purposes as
D.6.31.2 Bolts and Nuts
Mild steel for bolts and nuts when tested shall comply with IS 1608-1960 and shall have
tensile strength of not less than 2500 Kg/cm2. Plain washers shall be made of steel.
D.6.31.3 Welding Electrode
Mild steel electrodes shall comply with requirements of IS 814-1957 specification for
covered electrodes for metal arc welding of mild steel.
D.6.31.4 Workmanship
All work shall be in accordance with the drawings and shall satisfy IS specification No.
1915-1961. Care shall be taken to ensure that all parts in assembly fit accurately together.
Notes or specifications on the drawings supplied by the Engineer-in-Charge/consulting
Engineer, are to be constructed as superseding or cancelling any clause of this
specifications with which they conflict. On all drawings dimensions shown in figures shall
be acted in preference to measurement by scale.
D.6.31.5 Straightening
All structural steel members and parts shall have straight edges. All straightening shaping
and levelling etc. shall be done by pressure only and not by hammering. All joggles and
knees shall be formed by pressure and where practicable in making these, the metal shall
not be cut and welded.
D.6.31.6 Cutting
All structural steel parts where required shall be sheared, cropped sawn or flame cut and
ground accurately to the required dimensions and shape.
D.6.31.7 Bolts Holes
The diameter of bolts holes shall be 1.5 to 2.0 mm. larger than the nominal diameter of
bolt. All holes for bolts shall be drilled unless permitted by Engineer-in-Charge for
punching the holes. Care shall be taken, such as surrounding material is not deformed or
damaged in case of punching the hole is allowed.
D.6.31.8 Welding
Welding of steel conforming to relevant IS specifications shall be in accordance with
general requirements of metal arc welding. In additional to general requirement, the
following care shall be taken :-
(a) The welding shall be positioned for downward welding wherever practicable.
(b) The welding current shall conform with respect of voltage and empeare to the
recommendations of the manufacturers of the electrode being used. The arc length,
voltage and empeare shall be suited to the thickness of material, type of groove
and other circumstances of the work.
(c) The surface to be welded and surrounding material for a distance of atleast
mm shall be free from scale, dirt, grease, paint, heavy rust or other surface deposit.
(d) Members to be welded shall be held in correct position by holes, clamps, wedges,
jigs or other suitable devices or by tack welding until welding has been completed,
such fastening as may be used shall be adequate to ensure safety. Suitable
allowance shall be made for war page and shrinkage.
(e) Tack welds located where the final welds will later be made shall be subject to the
same quality requirements as final welds. Defective and broken tack welds shall
be removed before final welding.
(f) Fusion faces shall be made or cut by shearing, chipping, machining or by gas
(g) Exposed faces of welds shall be made reasonably smooth and regular so as to
conform as closely as practicable to design requirements and shall not be of less
than the required cross section.
(h) Finished welds and adjacent parts shall be protected with clean boiled linseed oil
after all slag has been removed.
D.6.31.9 Safety Precautions
D.6.31.9.1 (a) Operators of welding and cutting equipment shall be protected from the rays of the
arc flame gloves and by helmet, hand shields, or goggles equipped with suitable
(b) Closed space shall be ventilated properly while welding is being gone therein.
(c) Welders should be provided with such staging as will enable them to perform the
welding operation. For site welding shelter should be provided to protect welders
and the parts to be welded from the weather.
D.6.31.9.2 The Constructor shall employ a competent welding supervisor to ensure that the standard
of workmanship and the quality of materials comply with requirements laid in these
D.6.31.9.3 The Constructor shall provide free access to the representative of Engineer-in-
Charge/Consulting Engineer to the work being carried out at all reasonable times and
facilities shall be provided so that during the course of welding he may be able to inspect
any layer of weld metal. He shall be at liberty to reject any material that does not conform
to the terms of the specifications and to require any defective welds to be cut out and
welded. The representative of the Engineer-in-Charge/Consulting Engineer shall be
notified in advance of any welding operations.
D.6.31.9.4 Inspection and testing of welds shall be done as laid down in IS 822 and IS
D.6.31.9.5 No welder shall be employed in any position expect those who are fully qualified to
welding. Qualification for welders shall be as laid down in IS
D.6.31.10 Joints
All steel work intended to be bolted together must be in contact over the whole surface.
Joints which have to take compressive stress and the ends of all stiffeners shall meet truly
over the whole of the butting surface.
D.6.31.11 Assembling
All member shall be so arranged that they can be accurately assembled, without being
unduly packed, strained or forced into position and when built shall be true and free from
twist kinks, buckets or open joints between component pieces. Work shall be kept properly
bolted together and no drifting shall be allowed except for the purpose of drawing
assembled sections together in accuracy’s in matching of holes may be corrected. But
drifting to enlarge holes is prohibited. Failure in any of the above respect will involve the
rejection of defective members.
D.6.31.12 Mode of Measurement and Payment
D.6.31.12.1 Measurement of this item shall be as per IS 1200(Part VIII) - 1974 or as per its latest
revision so far as applicable.
D.6.31.12.2 The contract rate shall be suitable for unit of one metric tonne of structural steel.
D.6.32 MATERIALS : REINFORCEMENT
D.6.32.1 Specification for TMT bars reinforcement
D.6.32.1.1 Scope of work :
The scope of work consists of providing and laying mild steel reinforcement and TMT
Fe-500 reinforcement for RCC works of various components of the structure. This may
be Tiscon or any other approved manufacturer branch and corrossion resistant steel bars
approved by the Engineer-in-charge. This includes cuttings, bending, binding, placing,
with all equipments and labour required for the work as directed by the City Engineer,
AMC, Ahmedabad and all operations covered within the intent and purpose of the
D.6.32.1.2 Bending of Reinforcement :
Reinforcing steel shall conform accurately to the dimensions shown on relevant drawings
and conforming to the relevant IS codes (latest revision)
Bars shall be bent cold to the specified shape and dimensions or as directed by the City
Engineer, AMC, Ahmedabad using a proper bar bender, operated by hand or power to
attain proper radii of bends.
Bars shall not be bent or strainghened in a manner that will cause injury to the material.
Bars bent during transport or handling shall be straightened before being used on work;
they shall not be heated to facilitate bending.
The bending of the TMT bars shall be carried out as per the following :
Sr. No. Operation Size TMT Fe-500
1 Bend Upto 22 mm dia. 3d
Over 22 mm dia. 4d
2 Rebend Upto 10 mm dia. 4d
Over 10 mm dia. 5d
D.6.32.1.3 Placing of Reinforcement :
All reinforcing bars shall be accurately placed in the exact position shown on the
drawings, and shall be securely held in position during placing of concrete by annealed
binding wire not less than 1 mm. in size and conforming to IS : 280 and by using stays
blocks or metal chairs, spacer, metal hangers, supporting wires or other approved
devices at sufficiently close intervals. Bars will not be allowed to sag between supports
nor displaced during concreting or any other operation over the work. All devices used
for positioning shall be of noncorrodible material. Wooden and metal supports will not
extend to the surface of concrete, except where shown on the drawings, Placing bars on
layers of freshly laid concrete as the work progresses for adjusting bar spacing will not
be allowed. Pieces of broken stone, brick or wooden blocks shall not be used. Layers of
bars shall be separated by spacer bars, precast mortar blocks or other approved devices.
Reinforcement after being placed in position shall be maintained in a clean condition
untill completely embedded in concrete. Special care shall be exercised to prevent any
displacement of reinforcement in concrete already placed.
To protect reinforcement from corrosion, concrete cover shall be provided as indicated
on the drawings. All bars protruding from concrete to which other bars are to be spliced
and which are likely to be exposed for an indefinite period shall be protected by a thick
coat of neat cement grout.
In the case of columns and walls, vertical bars shall be kept in normal position with
timber templates having slots accurately cut in for bar position. Such templates shall be
removed after the concreting has progressed upto a level just below them.
Bars crossing each other, where required, shall be secured by binding wire (annealed) of
size not less than 1 mm and conforming to IS : 280 in such a manner that they do not slip
over each other at the time of fixing and concreting. As far as possible, bars of full length
shall be used. In case this is not possible, overlapping of bars shall be done as directed by
the City Engineer, AMC, Ahmedabad. When practicable, overlapping bars shall not
touch each other, but be kept apart by 25 mm or 1 1/4 times the maximum size of the
coarse aggregates whichever is greater, by concrete between them. Where this is not
feasible, overlapping bars shall be bound with annealed steel wire, not less than 1mm
thickness twisted tight in eight shape around the lapped bars. The overlaps shall be
staggered for different bars and located at fixed locations only along the span where
neither shear nor bending moment is maximum.
D.6.32.1.4 Welding of Bars
Welding of TMT bars can be permitted if specified on the drawings, joints of
reinforcement bars shall be butt welded so as to transmit their full strength. Welded
joints shall preferably be located at points where steel will not be subject to more than
percent of the maximum permissible stresses and welds so staggered that at any one
section, not more than 33 per cent of the rods are welded. No pre-warming or post heat
treatment is necessary. Interpass temperature should be limited to 200oC with low heat
input and equivalent strength low hydrogen type electrode. Suitable means shall be
provided for holding the bars securely in position during welding. It must be ensured that
no voids are left in welding and when welding is done in 2 or 3 stages, previous surface
shall be cleaned property. Ends of the bars shall be cleaned of all loose scale, rust.
grease, paint and other foreign matter before welding. Only competent welders shall be
employed on the work. Welded pieces of reinforcement shall be tested. Specimens shall
be taken from the actual site and their number and frequency of tests shall be as directed
by the Additional City Engineer, PWA, AMC, Ahmedabad.
The TMT bars shall be tested for any or all of the following tests as directed by the
Engineer-in-charge.
(1) Alternate immersion test
(2) Salt spray test
(3) Atmospheric exposure test
(4) Sluphur dioxide test
(5) Potentio dynamic test
D-7 : GENERAL BUILDING WORKS
D.7.1.1.1 This specification covers the general requirement for brick and stone masonry, plastering,
flooring, doors, windows, ventilators, wood work, water proofing, false ceiling, painting and
such other related works forming a part of this job, which may be required to be carried out
though not specifically mentioned above. The work under this specifications shall consist of
furnishing of all tools, plants, labour, materials, any and everything necessary for carrying
D.7.2 APPLICABLE CODES AND SPECIFICATIONS
D.7.2.1 The following codes, standards and specifications are made a part of this specifications. All
standards, tentative specification, specification, codes of practices referred to herein shall be
latest edition including all applicable official amendments and revisions.
D.7.2.2 In case of discrepancy between this specification and those referred to herein, these
specifications shall govern.
IS : 1077 - Common brunt clay bricks
IS : 3102 - Classification of brunt clay bricks
IS : 2180 - Burnt clay building bricks, heavy duty
IS : 3495 - Method of sampling and testing clay building bricks
IS : 2691 - Burnt clay facing bricks
IS : 2212 - Code of practice for brick work
IS : 2185 - Load bearing hollow concrete blocks
IS : 5498 - Lime-Cement-Cinder hollow concrete blocks
IS : 3115 - Lime-Cement-Cinder soil blocks
IS : 1597 - Code of practice for construction of stone masonry
IS : 2394 - Code of practice for application of lime plaster finish
IS : 2645 - Integral cement water proofing compounds
IS : 1443 - Code of practice for laying and finishing of cement concrete
IS : 2114 - Code of practice for laying in situ terrazzo floor finish
IS : 777 - Glazed Earthenware tiles
IS : 4021 - Timber door, window and ventilator frames
IS : 2202 - Wooden flush door shutters (Solid Core Type)
IS : 1003 - Timber panelled and glazed shutters (Parts – I and II)
IS : 4020 - Methods of tests for wooden flush doors : Type tests
IS : 1761 - Transparent sheet glass for glazing and framing purposes
IS : 4351 - Steel door frames
IS : 1038 - Steel doors, windows and ventilators
IS : 1081 - Codes of practice for fixing and glazing of metal (steel and
aluminum) doors, windows and ventilators
IS : 5807 - Method of test for clear finishes for wooden furniture (Part-I to
IS : 1477 - Code of practice for painting of ferrous metals in buildings and
(Part-I & II) allied finishes.
IS : 2338 - Code of practice for finishing of wood and wood-based materials
IS : 437 - Distemper, dry, colour as required
IS : 428 - Distemper, oil emulsion, colour as required
IS : 2395 - Code of practice for painting concrete, masonry and plaster
IS : 3384 - Bituminous primer for use in water proofing and damp proofing
IS : 1580 - Bituminous compound for water proofing and caulking purpose
IS : 1322 - Bitumen felts for water proofing and damp proofing
IS : 1346 - Code of practice for water proofing of roofs with bitumen felts
D.7.3 BRICK WORK
D.7.3.1 Bricks used in works shall confirm to the relevant Indian Standards. They shall be sound,
hard, homogenous in texture, well bunt in kiln without being vitrified, table moulded, deep
red, cherry or copper coloured, of regulator shape and size and shall have sharp and square
edges and parallel faces. The bricks shall be free from pores, chips, flaws or humps or any
kind. Bricks containing unground particles and / or which absorb water more than 1/6 th of
their weight when soaked in water for twenty-four hours shall be rejected. Over-burnt or
under-burnt bricks shall be liable to rejection. The bricks shall give a clear ringing sound
when struck and shall have a minimum crushing strength of 35 Kg/sq. cm. Unless otherwise
noted in drawings. The classes and quality requirements of bricks shall be as laid down in IS
D.7.3.2 The size of the brick shall be 23.0 x 11.5 x 7.5 cm unless otherwise specified; but tolerance
upto (+/-) 3 mm in each direction shall be permitted. However, bricks conforming in size to
IS : 1077 could be used. Bricks shall be provided with frogs. Only full size bricks shall be
used for masonry work. Brick bats shall be used only with the permission of the Engineer to
make up required wall length or for bonding. Sample bricks shall be submitted to the
Engineer for approval and bricks supplied shall conform to approved samples. If demanded
by Engineer, brick sample shall be got tested as per IS : 3495 by Contractor at no extra cost
to Client. Bricks rejected by Engineer shall be removed from the site of works within
D.7.3.3.1 Mortar for brick masonry shall be prepared as per IS : 2250 Mix for cement mortar shall be
specified in the respective items of work. Gauge boxes for sand shall be of such dimensions
that one completed bag of cement containing 50 kg of cement forms one unit. The sand shall
be free from clay, shale, loam, alkali and organic matter shall be of sound, hard, clean and
durable particles. Sand shall be approved by Engineer, sand shall be thoroughly washed till
it is free of any contamination.
D.7.3.3.2 For preparing cement mortar, the ingredients shall first be mixed thoroughly in dry condition.
Water shall then be added and mixing continued to give a uniform mix of required
consistency. Cement mortar shall preferably by machine mixed, though hard mixing in a
thorough manner may be allowed. The mortar so mixed shall be used within 25 minutes of
mixing. Mortar left unused in the specified period shall be rejected.
D.7.3.3.3 The Contractor shall arrange for test on mortar samples if so directed by the Engineer. Re-
tempering of mortar shall not be permitted.
D.7.3.4 Workmanship
D.7.3.4.1 All bricks shall be thoroughly soaked in clean water for at least one hour immediately before
being laid. The cement mortar for brick masonry work shall be as specified in the respective
item of work. Brick work 230 mm thick and over shall be laid English Bond unless
otherwise specified. 115 mm thick work shall be laid with stretchers. For laying bricks a
layer of mortar shall be spread over the full width of suitable length of the lower course.
Each brick shall be pressed into the mortar and shoved into final position so as to embed the
brick fully in mortar. Bricks shall be laid with frogs uppermost.
D.7.3.4.2 All brickwork shall be plumb, square and true to dimensions sown. Vertical joints in
alternate courses shall come directly one over the other and be in line. Horizontal courses
shall be levelled. The thickness of brick course shall be kept uniform. For walls of thickness
greater than 230 mm both faces shall be kept in vertical planes. All interconnected
brickwork shall be carried out at nearly one level (so that there is uniform distribution of
pressure on the supporting structure) and so portion of the work shall be left more than one
course lower than the adjacent work. Where this is not possible, the work shall be racked
back according to bond (and not saw toothed) at an angle not exceeding 45 degree. But in no
case the level difference between adjoining walls shall exceed 1.25 m. Workmanship shall
conform to IS :
D.7.3.4.3 Bricks shall be so laid that all joints are well filled with mortar. The thickness of joints shall
not be less than 6 mm and not more than 10 mm. The face joints shall be raked to a
minimum depth of 10/15 mm by raking tools daily during the progress of work when the
mortar is still green, so as to provide a proper key for the plaster or pointing to be done.
When plastering or pointing is not required to be done, the joints shall be uniform in
thickness and be struck flush and finished at the time of laying. The face of brick work shall
be cleaned daily and all mortar droppings removed. The surface of each course shall be
thoroughly cleaned of all dirt before another course is laid on top. If the mortar in the lower
course has begun to set, the joints shall be raked out to a depth of 12 mm before another
course is laid.
D.7.3.4.4 All brick work shall be built tightly against columns, floor slabs or other structural members.
D.7.3.4.5 Where drawings indicate that structural steel columns are to be fireproofed with brickwork,
the brick shall be built closely against all flanges and webs with all spaces between the steel
and brickwork filled with mortar. Steel members partly embedded in brickwork and not
indicated to be fireproofed with concrete, shall be covered with nor less than 12 mm thick
mortar unless directed otherwise by Engineer.
D.7.3.5 Miscellaneous inserts in masonry e.g. sleeves, wall ties, anchors, conducts, structural steel,
steel inlets etc. shall be installed by the Contractor at no extra cost to the Owner. Furnishing
of any of these inserts by the Contractor, will be paid for separately. Openings, arches etc.
shall be provided as shown on the drawings. Chases, pockets etc. shall be provided as shown
on the drawings to receive windows, louvers, doors frames etc. Wall ties and flashings shall
be built into the brickwork in accordance with the drawings and specifications. It shall be
clearly understood that the rates quoted by the Contractor include for fixing of inserts,
leaving openings, cutting chases in brickwork for various trades etc.
D.7.3.6 Facing Brickwork
D.7.3.6.1 Facing bricks of the type specified shall be laid in the positions indicated on the drawings
and all facing brickwork shall be well bonded to the backing bricks. No facing brickwork
shall at any time be more than 600 mm above the backing brickwork.
D.7.3.6.2 All facing brickwork shall be pointed as the work proceeds and internal faces of the
brickwork shall be pointed with neat flush joint to give a fair face.
D.7.3.6.3 Faced work shall be kept clean and free from damage, discoloration etc. at all times. The
Contractor shall fill carefully all holes with bricks similar to the surrounding brickwork,
point brickwork as required.
D.7.3.6.4 For facing brickwork, double scaffolding shall be used no holes in brickwork for scaffolding
shall be permitted.
D.7.3.7 The green work shall be protected from rain by suitable covering bricks shall be kept
constantly moist on all faces for a minimum period of ten days. Brickwork shall not be
raised more than one metre per day.
D.7.3.8 The rates quoted by the Contractor are exclusive or transoms and mullions. Contractor shall
provided the same as shown or indicated on the drawings. These shall be generally provided
only in half and full brick walls. Dimensions of the transoms and mullions shall conform to
the thickness of the wall. Concrete work for transoms and mullions shall conform to the
specifications for concrete and shall be of grade M200.
D.7.3.9 Where shown on the structural drawings, bricks for partitions walls shall be stacked adjacent
to the structural member to pre deflect the structural member before the wall is built.
D.7.3.10 Measurement
D.7.3.10.1 Brick work of thickness one brick i.e. 230 mm and above shall, unless otherwise stated in the
Schedule of Quantities, be paid in units of cu.m. or part thereof. Brickwork of thickness less
one brick i.e. less than 230 mm thick shall be measured and paid on the basis of rates quoted
per sq.m. of part thereof in all cases, the quantities measured and paid for shall be those
actually executed after making necessary deductions for openings etc. Brick masonry for
steps and such other mass works and encasement shall be paid on the basis of rates quoted
per cu.m. or part thereof.
D.7.4 CONCRETE BLOCK MASONRY
D.7.4.1 Concrete blocks (hollow or solid) shall generally conform to IS : 2185. Blocks shall be
regular size and shape and shall be of specified strength. Blocks shall be properly cured
before they are brought to site. Half of three quarter size blocks are to be used wherever
required to make up length of wall and broken blocks shall not be used. The texture of the
blocks shall be such that plaster will adhere to it. The Contractors shall supply samples for
approval. Blocks supplied shall conform to approved samples.
Mortar shall be similar to mortar in brickwork as given Clause D.7.3.3 herein before.
D.7.4.3 All block work shall be plumb, square and properly bonded. The joints shall be broken. The
thickness of the courses shall be uniform with courses horizontal. All connected work shall
be carried out at nearly one level and no portion of the work shall be left more than one
course lower than the adjacent work.
D.7.4.4 Blocks shall be so laid that all joints are well filled with mortar. The thickness of joints shall
not be less than 6 mm and nor more than 8 mm. The face joints shall be raked to a minimum
depth of 10 mm by raking tools daily during the progress of work when the mortar is still
green, so as to provided a proper key for the plaster or pointing. When plastering or pointing
is not required, the joints shall be struck flush. For pointed masonry or for masonry without
plaster, smooth textured concrete shall be use. The face of block work shall be kept clean at
D.7.4.5 Where blocks are to be used for load bearing walls, the uppermost layer of blocks supporting
slab or other structural members, shall be solid of treated as directed by the Engineer.
D.7.4.6 Precast concrete screen blocks or ‘jali’ work may be used for decorative purpose. The
Contractor shall furnish samples for approval.
D.7.4.7 Measurement
D.7.4.7.1 Block work of specified thickness shall be paid in units of sq.m. or parts thereof. If
reinforcing bars are specified in horizontal courses, it shall measured and paid for separately
at quoted rate for reinforcement. In all cases, the quantities measured and paid for, shall be
those actually executed after making necessary deductions for openings etc.
D.7.4.7.2 Miscellaneous inserts e.g sleeves, ties, anchors, conduits etc. in block masonry shall be
installed by Contractor, at no extra cost to Owner. Furnishing of any of these inserts by
Contractor will be paid for separately.
D.7.5 RANDOM RUBBLE MASONRY, UNCOURSED IN FOUNDATION, PLINTH AND
D.7.5.1 Stones for this work shall be hard, durable rock, close or fine grained and uniform in colour,
free from veing, flaws and other defects and shall conform to IS : 1597 (Part-I). The stones
shall be laid in mortar proportions specified for the particular item of work. Stones shall be
got approved, if desired by Engineer.
D.7.5.2 For all work below ground level the masonry shall be random rubble uncoursed with
ordinary quarry dressed stones for hearting and faced with selected quarry dressed stones.
D.7.5.3 For all work above ground level and in superstructure the masonry shall random rubble, well
bonded, faced with hammer dressed stones with squared quoins at joints and corners.
D.7.5.4 No stones shall tail into the wall, either with a point or to length less than 1.5 times its height.
The thickness of the joint shall not exceed 12 mm.
D.7.5.5 Spawls and pinnings shall not be allowed to show on the face of the wall. Two bond stones
each of minimum area of 500 sq.cm. for every 1.0 sq.m. of each wall face shall be provided.
These shall be through stones in walls 600 mm thick and under. In walls thicker than
mm, the length of bond stones shall be 2/3 times the thickness of walls. The stones for
hearting of the wall shall not be less than 150 mm in any direction. Chips and Spawls shall
be wedged in to avoid thick mortar beds and joints. The quoins shall be of selected stones
neatly dressed with chisel to form the required angles and laid harder and stretcher
D.7.5.6 The exposed face of the work shall be carefully and neatly pointed with mortar in all joints.
On the other sides, the joints shall be neatly struck with trowel while the mortar is fresh.
The mortar for the work shall be as specified in the respective items of work and shall be
prepared as per Clause D.7.3.3.
D.7.5.8 Curing of masonry shall continue for a minimum of ten days.
D.7.5.9 Measurement
The unit of measurement shall be cu.m. or part thereof. Actual quantity of masonry shall be
calculated from dimensions shown on the drawings less opening and shall be paid for.
D.7.6 COURSED RUBBLE MASONRY (FIRST SORT) FOR SUPERSTRUCTURE
D.7.6.1 The stones used shall be hard, durable, rock free from veins, flaws and other defects and
shall conform to IS : 1597 (part-I). Height of each course in the masonry shall not be less
than 150 mm. The stones n each course shall be or equal height. All courses shall be f the
same height unless otherwise specified. All stones shall be set in full cement mortar of
proportion specified for the respective items of works. Stones shall be got approved, if
desired by Engineer.
D.7.6.2 The free stones shall be squared on all joints and beds. The beds being hammer or chisel
dressed true and square for at least 75 mm from the face and the joints for atleast 40 mm.
The face of the stone shall be hammer dressed so that bushings shall not project more than
D.7.6.3 No spauls or pinnings shall be allowed in the face. All bed joint shall be horizontal and side
joints vertical and no joints shall be more than 10 mm thickness.
D.7.6.4 No face stone shall be less in breadth than in height or shall tail into the work to a length less
than the height and atleast 1/3rd the number of stone shall tail into the work to atleast twice
their or in walls over 600 mm in thickness 3 times their height.
D.7.6.5 Through stones shall be inserted every 1.5 metres to 1.8 metres apart in every course and
shall run right when the wall is not more than 600 mm thick. When the wall is more than
600 mm thick a line of two or more headers be laid from the face to face which shall overlap
each other by atleast 150 mm. A header shall have a length of atleast thrice its height.
D.7.6.6 Stones shall break joint atleast half the height of the courses. Quoins shall be formed of
stones atleast 45 cm. Long, laid stretcher and header alternately. They shall be laid square in
their beds, which shall be fair dressed to a depth of atleast 100 mm. The corner shall be
chisel dressed for a width of 25 mm.
D.7.6.7 The work on the interior face shall be precisely the same as on the exterior face unless the
work is to be plastered in which case the side joints need not be truly vertical.
D.7.6.8 Hearting shall consist of flat bedded stone carefully laid on their proper beds and solidly
bedded in mortar, chips and spauls of stone being wedged in wherever so as to avoid thick
beds or joints of mortar. Care shall be taken so that no dry work or hollow spaces shall be left
anywhere in the masonry. The face and backing shall be brought up evenly but the backing
should not be levelled up at each course by the use of chips.
The mortar for the work shall be as specified in the respective items of work and shall be
prepared as of Clause D.7.3.3.
D.7.6.10 Curing of masonry shall continue for a minimum of ten days.
D.7.6.11 Measurement
The unit of measurement shall be cu.m. of part thereof. Actual quantity of masonry shall be
calculated from dimensions shown on drawings less openings and shall be paid for.
D.7.7 INSERTS, BOLTS ETC.
D.7.7.1 Inserts, bolts etc. shall be provided in masonry and concrete works as indicated on the
drawings. It is imperative that all inserts, bolts, fixtures and fittings shall be provided in their
position very accurately. If the Engineer directs that such inserts and bolts be fixed by use of
templates, the Contractor shall make arrangements for providing such templates. If as a
consequence of negligence on the part of the Contractor, the inserts, bolts, fixtures, fittings
etc. are out of alignment, the Contractor shall make arrangement to have the inserts and bolts
removed and refixed in their proper position as directed by the Engineer, at no cost to the
D.7.7.2 Measurement
Inserts, bolts etc. shall be measured and paid for as indicated in Schedule of Quantities.
D.7.8 RUBBLE PACKING
D.7.8.1 Rubble used for packing under floors, foundations etc. shall be hard, durable rock free from
veins, flaws and other defects. The quality and size of the rubble shall be subject to the
approval of the Engineer.
D.7.8.2 Rubble shall be hand packed as directed by Engineer. This shall be laid closely in position
on the sub-grade. All interstices between the stones shall be wedged in with smaller stones
of suitable size well driven to ensure tight packing and complete filling of interstices. Such
filling shall be carried out simultaneously with the placing in position of rubble stones and
shall not lag behind.
D.7.8.3 Small interstices shall be filled with hard clean sand and well watered and rammed.
D.7.8.4 Measurement
D.7.8.4.1 The unit of measurement shall be sq.m. for the specified thickness of rubble packing.
D.7.9 CEMENT POINTING
D.7.9.1 The joints of masonry shall be raked atleast 12 mm deep. 3 or 4 days after the courses are
laid if not done earlier. The dust shall then be brushed out of the joints and the wall, washing
D.7.9.2 The mortar shall consist of one part of cement to one part of fine sand. Mortar shall filled
into joints and well pressed with special steel trowels. The joints hall not be touched again
after it has once begun to set.
D.7.9.3 The joints of the pointed work shall be neat. The lines shall be regular and uniform in
breadth and the joints shall be raised, flat, sunk of ‘V’ as may be directed. No false joints
shall be allowed.
D.7.9.4 The work shall be kept we for a after the pointing is complete. Whenever coloured pointing
has to be done, the colouring pigment of the colour requirement shall be added to cement in
such proportion as recommended by the manufactures and as approved by the Engineer.
D.7.9.5 Measurement
D.7.9.5.1 The area pointed shall be calculated in sq.m. from dimensions shown on drawings less
opening and shall be paid for.
D.7.10 CEMENT PLASTER WORK
D.7.10.1 All joints in masonry shall be raked to a depth of 12 mm with a hooked tool made for the
purpose when the mortar is still green and in any case within 48 hours of its laying. The
surface to be rendered shall be washed with fresh clean water free from all dirt, loose
plastering work is commended. Concrete surfaces to be rendered will however be kept dry.
The wall should not too wet but only damp at the time of plastering. The damping shall be
uniform to get uniform bond between the plaster and the wall. Cement shall be ordinary
Portland cement confirming to IS
D.7.10.2 The proportion if the mortar shall be as specified under the respective items of work.
Cement shall be mixed thoroughly in dry condition and then just enough water added to
obtain a workable consistency. The quality of water, sand and cement shall be as per IS :
Standards. The mortar thus mixed shall be used immediately and in no case shall the mortar
be allowed to stand for more than 25 minutes after mixing with water.
D.7.10.3 Curing of plaster shall be started as soon as the applied plaster has hardened enough so as not
to be damaged. The decision, as to when the plaster has hardened, will be given by the
Engineer. Curing shall be done by continuous applying water in a spray and shall carried out
for atleast 7 days.
D.7.10.4 Whenever the specifications or the item of work calls for water proofing, the Contractor shall
provided the percentage of water proofing compound as specified in the items of work.
D.7.10.5 Where lath plaster is specified, it shall be paid for at the same rate as for plasterwork without
metal lath except that separate payment for metal lath will be made.
D.7.10.6 Ceiling plaster shall be done before wall plaster and wall plaster shall commence at top and
work downwards.
D.7.10.7 Interior plaster - This plaster shall be laid in a two coats of 12 and 8 mm for 20 mm and
single coat for 15 mm & 10 mm thickness. The mortar shall be dashed on the prepared
surface with a trowel and finished smooth by trowelling on the surface with neeru (lime
cream)/ or by trowelling to get the mala finshing. The standard of finish expected is high and
shall conform to IS : 2394. Interior plaster shall be carried out on jambs, lintel and sill faces,
top and undersides etc. as shown in the drawing or as directed by the Engineer. Rate quoted
for plasterwork shall be deemed to include plastering of all those surfaces. However, if the
item of work includes plaster finish, no separate payment would be made under ‘plastering
D.7.10.8.1 Exterior Plaster – Exterior plasterwork shall be carried out in 2 layers. The first layer being
12 mm thick and the second layer being 8 mm thick. The first layer shall be dashed against
the prepared surface with a trowel to obtain as even surface. The second layer shall then be
applied and finished leaving as even and uniform surface, trowel finished unless otherwise
directed by the Engineer.
D.7.10.8.2 Exterior Sand Faced Plaster – The plaster shall be applied in 2 coats. The first coat or the
scratch coat should be approximately 12 mm and shall be continuously carried be without
break to the full length of wall or natural breaking points such as doors, windows etc. The
scratch coat shall be dashed on the prepared surface with heavy pressure, brought to true and
even surface and then lightly roughened by cross scratch lines, to provide bond for the
finishing coat. The mortar proportion for this scratch coat shall be as specified in the
respective item of work. The scratch coat shall be cured for atleast 7 days and then allowed
D.7.10.8.3 The second coat shall be 8 mm thick and it shall not be applied until atleast 10 days have
elapsed after the application of the scratch coat shall be evenly damped. This coat shall be
applied from top to bottom in one operation and without joints, finish shall be straight, true
and even. The mortar proportions of this coat shall be as specified under the respective item
of work. Only approved white sand shall be used for the second coat and for finishing work.
Sand for finish shall be used for the second coat and for finishing work. Sand for finish shall
be even coarse size and shall be dashed on the surface and sponged.
D.7.10.8.4 Wherever 32 mm thick plaster has been specified, this is intended for purpose of providing
beading, bands etc. This work should be carried out in two or three layers and as directed by
D.7.10.8.5 In the case of pebble face finished plaster, pebbles of approved size and quality shall be
dashed against the final surface to obtain as far as possible uniform pattern. In all cases,
workmanship shall conform to IS :
D.7.10.9 Measurement
D.7.10.9.1 The quantity of work to be paid for under this item shall be calculated by taking the projected
surface of the area plastered after making necessary deductions for opening, doors, windows,
fan openings etc. The actual plasterwork carried out on jambs of doors, windows openings
etc. shall be measured and added. However, for purposes of payment under this item, plaster
work carried on surface of items of work, which include plaster finished, shall not be taken
Seal and Signature of the Bidder Addl. City Engineer (Drainage Project)
Date: Ahmedabad Municipal Corporation
AHMEDABAD MUNICIPAL CORPORATION
BILL OF QUANTITIES
General Instruction for the BOQ
1. The Bill of Quantities shall be reading conjunction with the Instruction to Bidders,
Conditions of Contract, Technical Specifications.
2. The bidder is advised to visit and examine the Site of Works and its surroundings and
obtain for itself on its own responsibility all information that may be necessary for
preparing the bid and entering into a contract for construction of the Works. The costs of
visiting the Site shall be at the bidders own expense. No claim in future for unknown
with the site by the bidder shall be granted in any case.
3. The quantities given in the Bill of Quantities are estimated and provisional and are given
to provide a common basis for bidding. The basis of payment will be the actual
quantities of work ordered and carried out, as measured by the Contractor and verified by
the Engineer and valued at the rates and prices bid in the priced Bill of Quantities, where
applicable, and otherwise at such rates and prices as the Engineer may fix within the
terms of the Contract. Contractor shall not raise any claim for too less or too more
quantities executed by him. Quantity may vary with respect to BOQ as well as place
of work also may change cited in the tender.
4. The rates and prices Bid in the priced Bill of Quantities, except in so far as it is
otherwise, provided under the Contract, include all constructional plant, labour,
supervisions, materials, all temporary works and false works, erection, maintenance,
establishment and overhead charges, profit, any taxation and levies, octroi and other
charges together with all general risks, liabilities and obligations set out or implied in the
Contract and including remedy of any defects during the Defects Liability Period.
5. The stipulated rates in BOQ are entirely in India Rupee Currency.
6. Rates shall be entered both in figures and words against total amount of Bill of
6. Rates shall be entered both in figures and words against total amount of Bill of
Quantities. However, Items (for which rate has been provided) against which no quantity
is entered will be paid for by the Employer on actual measurement onsite when executed.
7. The whole cost of complying with the provisions of the Contract shall be deemed to have
been included in the items provided in the priced Bill of Quantities.
8. General directions and descriptions of work and materials are not necessarily repeated
or summarized in the Bill of Quantities. Reference to the relevant sections of the contract
documentation shall be made before quoting the bid against each item in the Bill of
9. The method of measurement of completed work for payment shall be in accordance with
the requirement as stated in the individual sections of the Technical Specifications.
10. Contractor shall credit the material dismantled during the work in progress in AMC store
suggested by Engineer in charge of the work.
11. AMC reserves the right to decrease the scope of work or to incase of any condition.
AMC may start it after approval of competent authority.
Detailed technical specification for all the Items above shall be relevant to PWD manual general
material specification there in during the construction period of the contract. Contractor should
adhere to the specifications and same shall be considered as the tender document.
Incase of any discrepancy the decision of engineer in-charge shall be considered as final.
In case of any dispute the decision of City Engineer shall be considered as final.
Seal and Signature of the Bidder Additional City Engineer
(Drainage Project)
Date: Ahmedabad Municipal Corporation
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
Technical bid.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .