Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹4.7 CrAccepted-AOC AHROLA NAWAGI JUNAWAI GUNNAUR DISTT SAMBHAL | GUNNAUR | SAMBHAL | ₹4.7 Cr | L1 | Accepted-AOC AOC |
| 2 | L2₹4.7 Cr+₹2.1 L (0.45%)Rejected-Finance 83 AKASH PURAM VISTAR PILIBHIT BYPASS ROAD BAREILLY 243006 | BAREILLY | BAREILLY | UTTAR PRADESH | 243006 | ₹4.7 Cr+₹2.1 L (0.45%) | L2 | Rejected-Finance NON RESPONSIVE |
| Sl No | Description | Qty | Unit | AM BUILDERS AND INFRASTRUCTURES PRIVATE LIMITED L2 | PRADEEP KUMAR CONTRACTOR L1 |
|---|---|---|---|---|---|
| 1.01 | Construction of embankment with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2 including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T. | 701 | Cum | 183.9 ₹1,28,913.9 | 183 ₹1,28,283 Lowest |
| 1.02 | Providing and constructing temporary island 24m diameter for construction of well foundatiom for 8m dia well including all taxes, material labour T&P Etc including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T. | 2 | Nos | 2,91,972.1 ₹5,83,944.2 | 2,50,000 ₹5,00,000 Lowest |
| 1.03 | Providing and constructing one span service road to reach island location from one pier location to another pier location including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T. | 60 | RM | 4,625.2 ₹2,77,512 | 4,625 ₹2,77,500 Lowest |
| 1.04 | Earth work in excavation for foundation of structure by mechanical means as per drawings and clause 304 of MORT&H specifications (2001)(placing for well curb) including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T. | 85 | cum | 147.3 ₹12,520.5 | 147 ₹12,495 Lowest |
| 1.05 | Providing and laying of cutting edge of mild steel weighing 150 kg per meter of well foundation as per drawings and clause 1200 & 1900 of MORT&H Specifications (2001) including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T. | 3 | MT | 1,13,994.5 ₹3,41,983.5 | 1,13,994 ₹3,41,982 Lowest |
| 1.06 | Plain/Reinforced Cement Concrete, in Well Foundation complete as per Drawing and Technical Specification No 12.11A (iii), 1200, 1500 & 1700 including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T. | 28 | Cum | 9,128.9 ₹2,55,609.2 | 9,128 ₹2,55,584 Lowest |
| 1.07 | RCC work in M-30 in well steining with cement aproved coarse sand & 2cm. Gauge well graded grit including nece-sarry shuttring, placing and fixing of reinforcement including its binding with wire but excluding cost of reinforcement and also including supply of all materials, labours T&P etc. required for proper completion of the work including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T. | 662 | cum | 8,380.6 ₹55,47,957.2 | 8,300 ₹54,94,600 Lowest |
| 1.08 | Sinking of 6 m external diameter well (other than pneumatic method of sinking) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is reckoned from bed level. as pe Specification No 12.12 Section 1200 including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T.
depth below bed level up to 3.0M including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T. | 12 | Rm | 13,231.7 ₹1,58,780.4 | 13,231 ₹1,58,772 Lowest |
| 1.09 | depth below 3.00 to 10 M including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T. | 28 | Rm | 20,451.3 ₹5,72,636.4 | 20,451 ₹5,72,628 Lowest |
| 1.10 | Beyond 10.00 M including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T. | 44 | RM | 43,742.45 ₹19,24,667.8 | 43,742 ₹19,24,648 Lowest |
Tender Value
₹4.8 Cr
EMD Value
₹9.6 L
Closing Date
11 May 2026, 12:00 pmClosed
SE, MORADABAD CIRCLE PWD MORADABAD
SE, MORADABAD CIRCLE PWD MORADABAD
Construction of minor bridge 3x19 m Approach road and Protection work on Ramganga Feeder Channel on Dhanaura Sherpur road (ODR) in District Amroha
2026_CEMBD_1145041_1
2329/Nivida-Moradabad/26-27 Dated 04-04-2026
Open Tender
Civil Works - Bridges
Percentage
365 days
EXECUTIVE ENGINEER PD PWD AMROHA
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,354
₹9.6 L
Yes
SE, MORADABAD CIRCLE PWD MORADABAD
28 Jul 2026
4 May 2026
11 May 2026
4 May 2026
11 May 2026
4 May 2026
7 May 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1.01 | Construction of embankment with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2 including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T. | 701 | Cum | 10 | ₹7,010 |
| 1.02 | Providing and constructing temporary island 24m diameter for construction of well foundatiom for 8m dia well including all taxes, material labour T&P Etc including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T. | 2 | Nos | 10 | ₹20 |
| 1.03 | Providing and constructing one span service road to reach island location from one pier location to another pier location including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T. | 60 | RM | 10 | ₹600 |
| 1.04 | Earth work in excavation for foundation of structure by mechanical means as per drawings and clause 304 of MORT&H specifications (2001)(placing for well curb) including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T. | 85 | cum | 10 | ₹850 |
| 1.05 | Providing and laying of cutting edge of mild steel weighing 150 kg per meter of well foundation as per drawings and clause 1200 & 1900 of MORT&H Specifications (2001) including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T. | 3 | MT | 10 | ₹30 |
| 1.06 | Plain/Reinforced Cement Concrete, in Well Foundation complete as per Drawing and Technical Specification No 12.11A (iii), 1200, 1500 & 1700 including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T. | 28 | Cum | 10 | ₹280 |
| 1.07 | RCC work in M-30 in well steining with cement aproved coarse sand & 2cm. Gauge well graded grit including nece-sarry shuttring, placing and fixing of reinforcement including its binding with wire but excluding cost of reinforcement and also including supply of all materials, labours T&P etc. required for proper completion of the work including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T. | 662 | cum | 10 | ₹6,620 |
| 1.08 | Sinking of 6 m external diameter well (other than pneumatic method of sinking) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is reckoned from bed level. as pe Specification No 12.12 Section 1200 including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T.
depth below bed level up to 3.0M including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T. | 12 | Rm | 10 | ₹120 |
| 1.09 | depth below 3.00 to 10 M including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T. | 28 | Rm | 10 | ₹280 |
| 1.1 | Beyond 10.00 M including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T. | 44 | RM | 10 | ₹440 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.65 MB
Tendernotice_2.pdf
PDF • 7.54 MB
BOQ_2140027.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .