Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.9 CrAccepted-Finance | ₹1.9 Cr | L1 | Accepted-Finance L1 |
| 2 | L2₹15.6 L−₹1.7 Cr (91.6%)Rejected-Finance | ₹15.6 L−₹1.7 Cr (91.6%) | L2 | Rejected-Finance L2 |
Tender Value
₹21.9 L
EMD Value
₹43,900
Closing Date
4 Aug 2026, 12:00 pmClosed
EXECUTIVE ENGINEER
EE RED SECOND FLOOR VIKAS BHAWAN BAREILLY
Construction of a community center (Sadbhavna Mandap) in village Ganeshpur Majra Gurgaon (MLAY-Majhgawan)
2026_REDUP_1165559_1
414/01/EE/RED/NIVIDA/2026-27 DATE 02-05-2026
Open Tender
Civil Works
Percentage
90 days
MAJHGANWAN
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,354
₹43,900
24 Aug 2026
1 Jul 2026
4 Aug 2026
1 Jul 2026
4 Aug 2026
1 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 0 | BOQ | - | - | - | - |
| 1 | Excavation in foundation in ordinary soil, loam, clay or sand including lift upto 1.5m & lead upto 30m including filling watering & ramming of excavated earth into the space between the building & the siides of foundation trenches or into the plinth removal & disposal of surplus earth as directed by the engineer in charge upto a distance of 30m from the foundation trenches SI. No. 251 | 76.7 | Cum | 209 | ₹16,030.3 |
| 2 | Concrete with 4 cm gauge brick ballast, fine sand and cement in proportion of 12:6:1 in foundation including supply of all materials labour and T& P etc required for proper completion of the work.( S.I.No. 273) | 14.17 | Cum | 3,705 | ₹52,499.85 |
| 3 | First class Brickwork in 1:6 cement and coarse sand mortar in foundation & plinth includiiing supply of all materials labour T & P etc. required for proper completion of work as per SI.No. 303 | 24.39 | Cum | 5,300 | ₹1,29,267 |
| 4 | RCC work with cement, approved coarse sand and 2cm gauge approved stone ballast in proportion of 1:1.5:3 in RCC column SI.No. 289 | 9.58 | Cum | 8,976 | ₹85,990.08 |
| 5 | RCC work with cement, approved coarse sand and 2cm gauge approved stone ballast in proportion of 1:1.5:3 in P/L beam SI.No. 283(a) | 7.61 | Cum | 8,881 | ₹67,584.41 |
| 6 | First class Brickwork in 1:4 cement and coarse sand mortar in Super Structure including supply of all materials Labour T&P etc. required for proper completion of work as per SI.No. 305+309+310 | 27.14 | Cum | 6,290 | ₹1,70,710.6 |
| 7 | RCC work with cement, approved coarse sand and 2cm gauge approved stone ballast in proportion of 1:1.5:3 but in verandha beam SI.No. 285 | 0.84 | Cum | 8,893 | ₹7,470.12 |
| 8 | RCC work with cement, approved coarse sand and 2cm gauge approved stone ballast in proportion of 1:1.5:3 but in T beam SI.No. 288 | 1.34 | Cum | 8,534 | ₹11,435.56 |
| 9 | First class Brickwork in 1:4 cement and coarse sand mortar in Super Structure including supply of all materials Labour T&P etc. required for proper completion of work as per SI.No. 305+309+310(a) | 9.59 | Cum | 6,480 | ₹62,143.2 |
stage.html
html • 0.04 MB
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.69 MB
BOQ_2186004.xls
BOQ • 0.32 MB
T1.pdf
Tender Documents • 1.63 MB
2corrigendumgate.pdf
PDF • 0.36 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .