Tender Value
₹20.7 L
EMD Value
₹21,000
Closing Date
16 May 2026, 6:00 pmClosed
Similar tender results from the same govt authority in the past 3 years.
Executive Engineer’s office, Valsad (R&B) Division,
Repairing & renovation of various office on G.F.of Jilla Seva Sadan - 2 Office Building at Valsad Dist: Valsad
303397
02 Of 2026-27
Open
Civil - All
Valsad
8 documents required · 8 mandatory
₹900
Executive Engineer, Valsad (R&B)Division, Valsad
₹21,000
8 May 2026
8 May 2026
8 May 2026
16 May 2026
8 May 2026
Name of work :-
Repairing & renovation of various office on G.F.of Jilla Seva Sadan - 2 Office Building at Valsad, Dist: Valsad
Bill of Quantities
(A) Percentage Rate Tender (Up to INR 50 Cr. )
Memorandum showing items of work to be carried out
Ite Quantity Unit Estimated Rates Total Amount
Ite Quantity Unit Estimated Rates Total Amount
No. Item of work In figure estimated
Rs. Ps. quantities
1 DISMENTAL WORK
Dismentaling tiled of stone floors laid in mortar including stacking of 76.18 Sq. Mt 48.21
serviceable materilas and disposal of unserviceable materials with all lead
2 Vitrified tiles 8 to 10 mm thick 36''x 36''
Providing and laying Vitrified tiles 8 to 10 mm thick , 36''x 36'' in flooring 76.18 Sq. Mt 1484.61
treads of steps and landing laid on a bed of 12mm thick cement mortar
1:3 (1-cement : 3-coarse sand )finishing with flush pointing in white
3 GYPSUM CEILING
Supplying and Fixing of Suspended ceiling system components which 76.18 Sq. Mt 687.81
includes Single Layer Boarding with 12.5mm thick USG Boral Standard
Plasterboard This includes of USG Boral Thundersteel Perimeter Channel
(0.50mm thick having one flange of 20mm and another flange of 30mm
and a web of 28mm) screw fixed to brick wall/partition with the help of
approved screws at 600mm centers. Then suspending of USG Boral
Thundersteel Intermediate channel (45mm x 0.90mm thick with two
Providing and fixing of POP Punning and finished by company approved 118.00 Sq. Mt 303.00
gypsum, taping, lapi, including scaffolding etc. and including grooves as
shown in drawing And including satin paint complete with all material,
labour with all lead, lift and transport.and complete the work
satisfactorily as per instruction of architect or Engineer-in charge.
5 WALL COLOR - SATIN
Providing and applying satin paint of approved quality, company and 145.17 Sq. Mt 252.50
shade upto finishing (min 3 coats) including lappi and primer work and all
material, labour including scaffolding etc. and complete the work
satisfactorily as per instruction of architect or Engineer-in charge.
6 CEILING COLOUR
Providing and applying plastic paint of approved quality, company and 78.85 Sq. Mt 252.50
shade upto finishing (min 3 coats) including all material, labour including
scaffolding etc. and complete the work satisfactorily as per instruction of
architect or Engineer-in charge.
7 WOODEN PANELLING
Providing and making of panelling on Wall & columns using 12mm ply, 134.43 Sq. Mt 1530.15
aluminium pipe for (2" x 1") framing, Ghana bidding patti (11/2" x 3/4")
including all material, labour and hardware complete,including 3 mmx
3mm groove (if shown) with all materials,polish work,beading patti,
labour, lead and wastage etc. complete. And Finished with different
materials,and complete the work satisfactorily as per instruction of
architect or Engineer-in charge.
8 HDF FINISH with SATIN PAINT
Providing and fitting of 6mm waterproof HDF sheet of brand green,action 134.43 Sq. Mt 597.92
tesla etc (as per drawing) on ply partition including all material, labour
and hardware, waste of materials & finished by atleast 3 COATS of satin
paint including lappi and primer and complete the work satisfactorily as
per instruction of architect or Engineer-in charge.
9 WOODEN PARTITION
Providing and fixing of full height solid sandwitch partitions (AS PER 30.54 Sq. Mt 2628.02
DRAWINGS) using 50 x 50 mm aluminium pipe for framing (minimum grid
size of 600 mmx 600mm ), 12mm ply (both sides)of brand greenply
ecotech mr,T plus mr,srg omen mr etc, teak wood beading patti etc.
making of rebates and including all hardware items, groove (if shown)50
MM TK , 24 kg density insulation if required,with all
materials,hardwares,ss or powdercoated screws, labour, lead and
wastage,scaffolding etc. complete. And Finished with different
materials,and complete the work satisfactorily as per instruction of
10 LAMINATE FINISH
Providing and fitting of 1 mm laminate (as per drawing & selection) on ply 15.12 Sq. Mt 914.31
partition of brand greenlam,merinolam or shivshakti, including all
material, adhesives,labour and hardware, waste of materials complete as
per instruction of architect. 3 mmx 3mm groove (if shown) with all
materials,polish work,beading patti, labour, lead and wastage etc.
complete. And Finished with different materials,and complete the work
satisfactorily as per instruction of architect or Engineer-in charge.
11 WOODEN BLINDS
Providing and fixing of approved quality wooden vanishing blinds 50 mm 23.45 Sq. Mt 1874.56
wide slit of brand signature -essential series, with easy lift cord/chain
operation, including all acceessories, material, labour,installation etc. and
complete the work satisfactorily as per instruction of architect or
Engineer-in charge.
12 REFURBISHED THE EXISTING DOORS WITH CONCEALED DOOR CLOSER
Providing and fitting of 6mm ply & 1mm laminate on both the side (as 5.00 NOS. 13143.13
per drawing & selection) on existing flush door and 25 mm teakwood
beading patti with 300 mm width 5 mm glass with frosted film work as
per selection, and finishing it with laminate with 3mm x 3mm grooves if
shown ,including all material, labour and hardware,conceal door closer,
mortise door lock,tower bolt,stopper,etc waste of materials, and
complete the work satisfactorily as per instruction of architect or
13 PAINTING charge.
Providing and fixing of painting as per selection and complete the work 8.00 NOS. 4040.00
satisfactorily as per instruction of architect or Engineer-in charge.Basic
rate of chair is 3500/- per painting
14 2 SEATER SOFA
Providing and fixing 2-seater sofa,as per drawings or selection using base 10.00 NOS. 8080.00
WHITE ASH WOOD for framing with molded foam,and high density fom
warwick brand rexine(as per architects selection) in sofa upholstery and
CORNERgrade corner
TABLE (0.75legs with 5 years warranty and instructions provided,
Providing and fixing corner table of brand as per architects selection,and 8.00 NOS. 3030.00
complete the work satisfactorily as per instruction of architect or
Engineer-in charge.BRANDS: SHEARLING , COHUMAN , HAYWORTH
Providing and fixing 13 inch dia planter/pots of frp or plastic including 15.00 NOS. 2525.00
drain tray with real indoor plants as per selection,including 3 feet ht
plants of brand seasonal dekor or as per selection and complete the
work satisfactorily as per instruction of architect or Engineer-in
charge.(BASIC RATE OF POT IS RS 2000/-)
Providing and fixing pre-cast Rubber Dye inter locking concrete block 1101.12 Sq. Mt 686.91
60mm thick with grade of concrete M300 pnumatic compressed/Vibrated
mechanically and as per approved design confieming to IS 15658:
including 35 mm Sand layer for levelling and filling the joint with sand in
proper line and level as per guidelines of IRC : SP 63-2018 etc complete.
18 PARKING SHED
Steel Work welded, in build up sections framed work including cutting, 34.94 Q 9047.87
hoisting fixing in position and applying a priming coat of red lead paint (A)
In beams and joints, channels, angles, tees, flats with connection plates
or angle cleats as in main and cross beams, hip and trussed purlins
connected to common rafters and the like.
19 PARKING SHED
Providing U.P.V.C sheet roofing fixed with glavanished iron J or L Hooks, 102.72 Sq. Mt 727.20
Bolts and G.I. limpet washer or G.I. limpet washer. filled with white lead
complete. (1) 2.50 mm thick sheet.
Rupees Twenty Lakh Seventy Three Thousand Seven Hundred Eighty Three And Eleven Paisa Only.
I/We am /are willing to carry out the work at…………% above/below percent (should be written in figures and words) at the estimated rates
mentioned above amount of my/your tender works out as under.
*Estimated Amount *Estimated Amount
put to Tender Rs. 2073783.11 put to Tender Rs.
Deduction …………….. % below………………… Add ………… % above Rs. …………….
1 The Contractor shall be exhibit board as per government circular No.BDG/3277/1657 N dated 26/01/1997 S (M.GUJ) with detailed
specification and details of work and amount Involved at site without any payment as directed by Engineer-In-Charge.
2 All work shall be carried out as per public work department hand book and other specifications of Division or as directed.
3 All columns in the Schedule should be filled in ink & the total of the entries in the last column should be struck by Contractor under his sign.
4 Rates quoted include clearance of site (Prior commencement of work and its close) in all respects and hold good for work under all
condition, site, moisture/ weather etc.
5 The Boards stating the detailed specification & detailes of Work shal be provided by the contractor as per Government Resolution
T.No.1890-240- Dtd.18/11/1990 and directed by contractor at his own cost immediately on recommanding the work order.
6 Testing of Material Shall be done as per the statement attached with specification,The material IS Tested in GERI by Executive Engineer
Surat and Bill for the testing charges shall be paid by Executive Engineer,1% of the Amount put to Tender.
7 1% of the Construction Cost Shall be deducted from the bill Amount of the contract as per the Buildig and other Construction works walfare
cess at 1996(Labour and Employment Department Letter No CWA-2004-1831-M(3)Dated 9/12/2005 notification Of Labour & Employment
department dt.03/01/2005 & Labou & Employment Department Letter no GWA/2004-841M(B) Dt 14/12/2005 & Dt.30/1/2006.
8 In Case of RCC items Where there is a change in Grade of Mix or Change as per Actual Mix design the cost of difference of Cement
Difference shall be deducted from the rate of original item at the rate of star rate mentioned in the tender.
9 Contractor are advised to visit site before loading tender rate.
10 Necessary wiring point and drainage point are installed at Site however any modification in electrical installation and drainage & water
supply connection and minor correction to perform experienced in Lab shall be done by contractor at his risk and cost.
11 The Rates are inclusive of all the taxes (Excluding GST),Transport Charges,Octroi duty and storage Charges up to date.
12 The materials Covered for wiring should be got approved from the Engineer Incharge of the work.
13 GST and Income tax TDS will be deducted at a source while making payments of bills.
14 GST will be paid extra as per Govt. amendment.
15 The Materials on the work shall have to be used and carried out as specified in technical note.
I/We hereby Declare that I/we have Visited the site and fully Exquisite myself/ourselves with the local situation regarding materials,Labour
and other factors pertaininfg to work before submitting tender.
I/We hereby Declare that I/we have carefully Studied the condition of Contracts,Detailed Specification and other tender Document of this
work and agree to execute the same accordingly.
Deputy Executive Engineer
Valsad (R&B) Sub-Division
Signature of Bidder
Executive Engineer
Valsad (R&B) Division
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
6 GR.pdf
7 GR.pdf
8 Building Booklet.pdf
BOQ.pdf
NIIT.pdf
SBD.pdf
Specification.pdf
Download all tender documents and submit your bid