ROAD WORK AT DIFFERENT AREAS IN LIMBADI MUNICIPALITY ON YEARLY BASIS CONTRACT : 2026-27 (2nd Attempt)
338493
249/2026
Open
Civil Works - Roads
Works
Surendranagar
1 document required · 1 mandatory
₹2,832
The Chief Officer, Limbdi Nagarpalika
₹1 L
24 Aug 2026
24 Aug 2026
24 Aug 2026
7 Sept 2026
24 Aug 2026
Date of Technical Bid Opening Date 16/09/2026 & 12:00 Hrs.
Date of Price Bid Document Opening On Date 16/09/2026 & 12:30 Hrs.
LIMBADI NAGARPALIKA
STANDARD BIDDING DOCUMENT
COMPLETE BIDDING DOCUMENT
GOVERNMENT OF GUJARAT
LIMBADI NAGARPALIKA
This is a generic SBD to be used for Civil works. Each user/concern department needs
to examine and put up their particular bidding requirement like; qualification criteria,
contract Data etc., marked at [#] while finalizing their own bidding process.
Sr No Section Description
1 Invitation for Bid (IFB)
2 Section -1 Instructions to Bidders
3 Section -2 Qualification Information
4 Section -3 Conditions of Contract
5 Section -4 Contract Data
6 Section -5 Technical Specification
7 Section -6 Form of Bid
8 Section -7 Bill of Quantities
9 Section -8 Securities and Other Forms
10 Section -9 Drawings
11 Section -10 Documents to be furnished by Bidder
INVITATION FOR BID
NATIONAL COMPETITIVE BIDDING
1. The LIMBADI Nagarpalika invites bids for the construction of works detailed in the table.
The bidders may submit bids for any or all of the following works.
Packag Name Approximate Bid Cost of Period of #Class of
e No. of work value of works security document completion Registration /
(Rs.) (Rs.) Category of
Details Given (18% GST) = rate work
Below 2832/- prevail for
Bid Documents for “Road work at different areas in Limbadi Municipality on yearly
basis contract : 2026-27 for Limbadi, District : Surendranagar”
Prospective / Interested bidder may download the Bid Documents from website
https://www.nprocure.com free of cost till the Time and Date as
mentioned on online NIT at website https://www.nprocure.com.
2. However, Bidder who is submitting the Bid Online will have to pay the Bid Document Fee /
Tender Fee through Demand Draft only of any Schedule Bank payable at LIMBADI
and in favour of ‘Chief Officer, LIMBADI Nagarpalika. Once the Bid is received online, Bid
Document / Tender Fee will not be refundable.
The Demand Draft for Bid Document / Tender fee and FDR / Bank Guarantee against Bid
Security / EMD shall be submitted in electronic format through online (by scanning) while
uploading the bid, this submission shall mean that bid document / tender fee and Bid Security
/ EMD has been received. Accordingly, the offer of only those shall be opened whose Bid
Document / Tender Fee and Bid Security / EMD have been received electronically. However,
for the purpose of realization of Demand Draft, and FDR / Bank Guarantee bidder shall send
the same in original through R.P.A.D. so as to reach to #‘Chief Officer, LIMBADI Nagarpalika
within mentioned in NIT (Days) from the last day of bid submission.
Penaltative action for not submitting Demand Draft / FDR / Bank Guarantee in original
to Chief Officer / Tender Inviting Authority by bidder shall be initiated.
3. Bids received online, will be opened on the time, date and place as specified in the online NIT
at website https://www.nprocure.com in the presence of the bidders or their authorized
representatives, who wish to remain present.
If the office happens to be closed on the day of opening of the bids as specified, the bids will
be opened on the next working day at the same time and venue.
4. A pre bid meeting will be held on ………………………………at ………………………..hrs. at the
office of to clarify the issues and to answer questions on any matter that may be
raised at that stage as stated in clause 9.2 of ‘instructions to Bidders’ of the bidding
5. #Bid Security (EMD) is equal to 1% of Estimated Amount put to bid / tender and should be
rounded off to the next thousand rupees.
6. Other Information is as under:
A. Agencies can prepare and edit their offers a number of times before the end of the
tender submission date and time. After the tender submission date and time, the bidder
cannot modify / edit / withdraw their submitted offer in any case. No written or online
request in this regard shall be granted.
B. Offers in physical form will not be accepted in any case.
C. Demand Draft purchased by the other then bidder and issued after the last date of
submission of Bids, will not be considered or accepted.
D. The cost incurred by the contractor for this offer for clarification or attending discussion,
conferences or site visits will not be reimbursed by the Employer or Engineer-in-Charge.
E. Conditional tender shall not be accepted.
F. Any changes, addition, alternation made in the prescribed form attached with tender are
liable to be rejected.
G. Any change in format or conditional Bank Guarantee will not be accepted and the bidder
will be considered non-responsive.
H. All the bidders are instructed to fill in information strictly in accordance with the format
given in the checklist /qualification document / tender document.
I. It is mandatory for the bidders to supply each and every information as asked strictly in
electronic format at appropriate places only.
J. Blank / insufficient information shall be treated as nil information and shall result in
disqualification.
K. Even if the bidder has been qualified in a similar or larger size of project in the past, it
shall not be deemed to be a ground / reason for not giving required information for this
L. Information supplied for earlier projects shall not be considered while evaluation of this
bid. The Government will not ask for any other information, unless it is found absolutely
necessary by the competent authority.
M. If found necessary, the contractor will be intimated for negotiation,
# For the works costing up to 7.5 crore (ROAD), 7.0 crore (BUILDING & BRIDGE) kindly
refer to SSR-10-2015-17-C dated 03-02-2017
For the works costing under 7.5 crore for Road Works and 7.0 crore for Building and Bridge
Works following documents shall be submitted in electronic format through online by
scanning and the (i) Bid Document Fee / Tender Fee (ii) Bid Security / EMD & Other should be
sent in original to the Tender opening authority through RPAD, so as to reach the Chief
(i) Bid Document Fee / Tender Fee
(ii) Bid Security / EMD or Valid EMD Exemption Certificate of Appropriate Class of
Registration of Approved Contractors
(iii) Registration Certificate of Appropriate Class
(iv) Registration Certificate of Special Category - Road / Bridge / Building and
Category I / II / III, if required
(vi) Work Experience, if necessary…
(vii) Other Documents, as required…
INSTRUCTIONS TO BIDDERS (ITB)
Section 1: Instructions to Bidders
Table of Clauses
Page No. Page No.
A. General D. Submission of Bids
1. Scope of Bid 9 19. Sealing & Marking of Bids
2. Source of Funds 9 20. Deadline for Submission of
3. Eligible Bidders 9 21. Late Bids
4. Qualification of the 9 22. Modification and
Bidder Withdrawal of Bids
5. One Bid per Bidder
6. Cost of Bidding 16 E. Bid Opening and Evaluation
7. Site Visit 16 23. Bid Opening
B. Bidding Documents 25. Clarification of Financial
8. Content of Bidding Documents 17 26. Examination of Bids and
Determination of
9. Clarification of Bidding 17 27. Correction of Errors
10. Amendment of Bidding 18 28. Deleted
29. Evaluation and Comparison
of Financial Bids
C. Preparation of Bids 30. Deleted
11. Language of Bid
12. Documents Comprising 18 F. Award of Contract
13. Bid Prices 18 31. Award Criteria
14. Currencies of Bid and Payment 19 32. Employer’s Right to Accept
any Bid and to Reject any or all
15. Bid Validity 19 33. Notification of Award and
Signing of Agreement
16. Bid Security 19 34. Performance Security
17. Alternative Proposals By 20 35. Advance Payment and Security
18. Format and Signing of Bid 20 36. Dispute Review Expert
37. Correct or Fraudulent
1. Scope of Bid
1.1 The Employer (Named in Appendix to ITB) invites bids for the Construction of works (as defined
in these documents and referred to as ‘the works”) detailed in the table given in IFB. The bidders
may submit bids for any or all of the works detailed in the table given in IFB.
1.3 The successful bidder will be expected to complete the number of works works by the intended
completion date specified in the Contract data.
1.4 Throughout these bidding documents, the terms ‘bid’ and ‘tender’ and their derivatives (bidder/
tenderer, bid / tender, bidding/ tendering, etc.) are synonymous.
2. Source of Funds
2.1 The expenditure on this project will be met from the budget of Govt. of Gujarat / Govt. of India
for centrally sponsored projects.
3. Eligible Bidders
3.1 This Invitation for Bids is open to all eligible bidders.
3.2 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a statement
that the Bidder is neither associated, nor has been associated, directly or indirectly, with the
consultant or any other entity that has prepared the design, specifications, and other documents
for the Project or being proposed as Project Manager for the Contract. A firm that has been
engaged by the Employer to provide consulting services for the preparation or supervision of the
works, and any of its affiliates, shall not be eligible to bid.
4. Qualification of the Bidder
4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary
description of the proposed work method and schedule, including drawings and charts, as
necessary. The proposed methodology should include a program of construction backed with
equipment planning and deployment duly supported with broad calculations and quality
assurance procedures proposed to be adopted justifying their capability of execution and
completion of work as per technical specifications, within stipulated period of completion.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, onlybidsfrom
prequalified bidders will be considered for ward of Contract. These qualifiedbidders should submit
with their bids any information updating their original prequalificationapplications or, alternatively,
confirmin their bids that the originally submittedprequalification information remainsessentially
correct as of date of bid submission. Theupdate or confirmation shouldbe provided in Section 2. A
copy of the originalprequalification application and the letter of prequalification should also be
furnished. With the updated information, the bidder must continue to be qualified in accordance
with the criteria laid down in the prequalification document. All bidders shall also furnish the
following information in Section
(i) Evidence of access to or availability of credit facilities (minimum 10% of estimated cost)
certified by the bankers.
(ii) Undertaking that bidder would be able to invest a minimum of cost upto 25% of the contract
value of work, during implementation of contract.
(iii) Proposal, if any, for sub-contracting of elements of work, costing more than 10% of the bid
(iv) Power of attorney.
(v) Latest income tax clearance certificate from concerned department.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the
following information and documents with their bids in Section 2:
(a) copies of original documents defining the constitution or legal status, place of registration, and
principal place of business; written power of attorney of the signatory of the Bid to commit the
(b) total monetary value of construction work performed for each of the last five years;
(c) experience in works of a similar nature and size for each of the last five years, and details of works
underway or contractually committed; and clients who may be contacted for further information on
those contracts;
(d) major items of construction equipment proposed to carry out the Contract;
(e) qualifications and experience of key site management and technical personnel proposed for
(f) reports on the financial standing of the Bidder, such as profit and loss statements and auditor's
reports for the past five years;
(g) evidence of access to line(s) of credit and availability of other financial resources facilities (10% of
contract value), certified by the Bankers (Not more than 3 months old)
(h) undertaking that the bidder will be able to invest a minimum cash up to 25% of contract value of
work, during implementation of work.
(i) authority to seek references from the Bidder's bankers;
(j) information regarding any litigation, current or during the last five years, in which the Bidder is
involved, the parties concerned, and disputed amount;
(k) proposals for subcontracting components of the Works amounting to more than 10 per cent of
the Bid Price (for each, the qualifications and experience of the identified sub-contractor in the
relevant field should be annexed); and
(l) the proposed methodology and programme of construction, backed with equipment planning and
deployment, duly supported with broad calculations and quality control procedures proposed to be
adopted, justifying their capability of execution and completion of the work as per technical
specifications within the stipulated period of completion as per milestones (for all contracts over
4.4 Bids from Joint ventures are not acceptable.
Bids from prequalified firms or prequalified joint-ventures only will be acceptable.
#4.5 QUALIFICATION CRITERIA:
(Applicable for the works which require Post Qualification)
4.5.1 Qualification will be based on Applicant’s meeting all the following minimum pass/ fail criteria
regarding the Applicant’s general and particular experience, personnel and equipment
capabilities and financial positions, as demonstrated by the applicant’s responses in the forms
attached to the letter of application ( specified requirement for joint ventures are given under
para 4.6 below ) Subcontractors experience and resources shall not be taken in to account in
determining the applicants compliance with the qualifying criteria to qualify for more than one
contract, the applicant must demonstrate having experience and resources sufficient to meet the
aggregate of the qualification criteria for each contract given in paragraphs 4.5.4, 4.5.5 and 4.5.9
4.5.2 Base year and Escalation
The base year shall be taken as Current financial year (2025-2026)
Following enhancement factors will be used for the costs of works executed and the financial
figure to a common base value for works completed in India.
Effective cost of
executed work at
Year previous completed
financial year’s price
inviting tender
Applicant should indicate actual figures of costs and amount for the works executed by them
without accounting for the above-mentioned factors.
In case the financial figures and value of completed works are in foreign currency the above
enhanced multiplying factors will not be applied. Instead, the current market exchange rate
(State Bank of India BC Selling rate as on the last date of submission of the bid) will be applied for
the purpose of conversion of the amount in foreign currency into India rupees.
4.5.3. General Experience.
To qualify, each bidder in the same name and style should have achieved the following performances:
List of Mandatory documents to be submitted
a. Registration
b. EMD/Bid Security /Tender Fee
c. Solvency Certificate
e. Bid Capacity
f. Document supporting similar nature of work & physical criteria
g. Declaration of Non-Blacklisted / Debarred from Anywhere in Gujarat & also in India. The Declaration will be
on the Rs.300/- Non-judicial paper should be submitted (Mandatory)
If bidder fails to submit above documents or mandatory criteria are not fulfilled, bidder shall be considered as
not qualified and their financial bid shall not be open. To qualify, each bidder in the same name and style
should have achieved the following performances:
a. Registration: As per Section: II, Instruction to Bidder, Clause
b. EMD and Tender Fees
As per tender notice.
C. Solvency Certificate
Bank Solvency of minimum Rs. 25,00,000.00 /-(25% of estimated cost)Solvency Value Certificate of the
organization should be of current calendar Year issued by Nationalized Bank or Bank listed as per latest GR of.
Finance Department GR. No: FD/MSM/efile/4/2023/0057/DMO, Date:21.04.2023. Such certificate should be
issued on Banker’s letter head.
4.5.3.1 TURNOVER:
Bidder must have achieved minimum annual financial turnover (at current price level) from contract receipt of
works (in all classes of civil engineering construction works only) of Rs. 50,00,000 /- in Last three financial years
i.e., from April 2022 to March
The details pertaining to turnover for the year April 2022 to March 2025 shall be certified by Chartered
Accountant on his own letter head and duly attested. Turnover of financial year 2024-25 shall be
considered subject to submission of provisional/audited certificate from chartered accountant by the
4.5.3.2 SIMILAR NATURE OF WORK:
The bidder must have completed similar nature of work i.e., Road work within last five financial years
i.e., from April 2020 to March 2025 and up to one month prior to last date of submission of the bid of
value not less than:
One similar completed work costing not less than the amount equal to Rs. 80,00,000.00 /-
Two similar completed works costing not less than the amount equal to Rs. 50,00,000.00 /-
Three similar completed works costing not less than the amount equal to Rs. 40,00,000.00 /-
4.5.3.3 AVAILABLE BID CAPACITY
The Bidder who fulfills the qualifying criteria mentioned above shall be qualified only if he fulfils the
requirement of bidder’s capacity. The bidding capacity of any tender/ Bidder is required to be more than or
equal to the estimated cost of the work i.e., Rs. 1,00,00,000 The bidder’s capacity shall be computed as
Available Bid Capacity = [(A x N x 2.0) - B)]
Maximum value of construction works executed in any one year during the last Five years updated at
the financial year updated at 2025-26 Price level.
B = Value of the existing commitments as on date of bid submission for works (complete or partial) to be
completed in the next (1 year). The details shall be countersigned by the Executive Engineer or the
equivalent officer of the employer on whose behalf the firm is carrying out the works.
Also, declaration of financial liabilities, work on hand/completed projects on Rs.300/- non-Judicial
In the case of a Joint Venture (Not Applicable), parameters A and B shall be determined based on
details pertaining to such partners who propose to undertake physical execution of work and in
proportion to their participation/stake as specified in respective clause in the tender documents.
N = Years prescribed for completion of the work for which bids are invited. - (1 year)
If the Tender has been invited as a Package/Slice Minimum aggregate required Bid Capacity shall be considered
and accordingly the Bidder may qualify for less number of Packages/Slices. In case of individual Tenders (not
invited in a single Basket) the Bidder may qualify for a particular work (based on his Technical Bid), but at the
time of evaluation of Price Bid, if a greater number of such individual Bids are evaluated simultaneously,
aggregate Bid Capacity shall be considered. In such a case, if the Bidder does not have adequate capacity for all
the Bids in which his Bid is the lowest responsive Bid, he may be considered for a smaller number of Bids.
Decision of the Employer based on the least cost combination as may be the most advantageous to Competent
authority shall be final and binding to all the Bidders.
(a) The statement showing the value and details of completed works, existing commitments and ongoing works
as well as the stipulated period of completion remaining for each of the work listed should be
countersigned by the officer not below the rank of an Engineer-In-Charge.
(b) The certificate for past performance should be as per prescribed Performa in Form11...
(c) The Bidders are required to upload latest client’s certificates in Form-11 (or in any format with yearly
breakup) obtained from the concerned authorities/ employers towards proof of their having executed
contracts satisfactorily along with their bids. The quantities involved should be certified by the top
executive of the firm in the prescribed Performa in Form 11 (or in any format with yearly breakup) of
(d) Physical and Financial Performance of Any Work Not Supported By Client Certificate in Form-11 or In Any
Form Will Not Be Considered For Qualification.
(e) The applicant Bidder must provide by uploading evidence of having adequate experience. The bid should
include supporting certificate or report relating to physical, financial, technical and other capability of
Bidder in their original language along with certified translation of relevant portion of the certificate/ report
in English. The Bidder should furnish the information about financial capability in Rupees only.
(f) Depending upon the actual bid capacity assessed and other qualifying requirements, the applicant will be
qualified for the work.
(g) The bidder is required to submit the declaration of his financial liabilities, work on hand/completed projects
on Rs.300/- non-Judicial stamp paper. In case of false statement/ declaration the bidder shall be liable for
penal action. Further, the details furnished in the relevant form as per tender should be in line to the
declaration by the bidder.
(h) The criteria mentioned above at shall be evaluated based on the details submitted with the documents.
Such bidder shall have to submit the details in the prescribed Performa which are applicable to them.
Bidders should read the note under each Form/Annexure carefully and submit the details accordingly.
(i) Turnover of previous year and cost of completed / executed similar nature of work/ O&M shall be given
additional weightage of ten percent per year to bring them to 2025-2026 Price level to account for price
escalation as illustrated below:
Effective cost of executed work
Turnover/ Cost of
Financial Year at previous completed financial
Executed work/O&M
year’s price level
(i) Financial year means period beginning from the 1st April to 31st March of the next year.
(ii) The details pertaining to Turnover for the year April 2020 to March 2025 and the details pertaining to Net
Cash Accrual, Net Worth and Net Working Capital for the year April 2020 to March 2025 shall be certified
by Chartered Accountant on his own letter head and duly attested. The cost of material supplied by the
Government/ Client shall not be taken into account for experience against Turnover & Similar nature of
4.5.4. Personnel Capabilities.
Availability for his work of personnel with adequate experience as required; as per
4.5.5. Equipment Capabilities
Based on the studies carried out by the Engineer, the minimum suggested major equipment to
attain the completion of works in accordance with the prescribed construction schedule are
shown in the Appendix.
The bidders should, however, undertake their own studies and furnish with their bid, a
detailed construction planning and methodology supported with layout and necessary drawings
and calculations to allow the employer to review their proposals. The numbers, types and
capacities of each plant/equipment shall be shown in the proposals along with the cycle time for
each operation for the given production capacity to match the requirements.
4.5.6. Financial Position
The Applicant should give undertaking that he has access to, or has available, liquid assets
(aggregate of working capital, cash in hand and uncommitted bank guarantees) and / or credit
facilities up to 25 percent of the value of the contract / contracts applied.
4.5.7. The audited balance sheets for the last five years should be submitted, which must demonstrate
the soundness of the applicant’s financial position, showing long – term profitability including an
estimated financial projection for the next two years If necessary, the employer will make
inquiries with the applicant’s bankers.
4.5.8. Litigation History
The Applicant should provide accurate information on any litigation or arbitration resulting from
contracts completed or under execution by him over the last five years. A consistent history of
awards against the Applicant or any partner of a joint venture may result in failure of the
4.5.9. Disqualification
Even though the applicants meet the above criteria, they are subject to be disqualified if they
Made misleading or false representation in the forms, statements submitted, and / or Record of
poor performance such as abandoning the work, rescinding of contract for which the reasons are
attributable to the non – performance of the contractor; consistent history of litigation awarded
against the applicant or financial failure due to bankruptcy. The rescinding of contract of a joint
venture on account of reasons other than non – performance, such as Most Experienced partner
of joint venture pulling out, court directions leading to breaking up of a joint venture before the
start of work, which are not attributable to the poor performance of the contractor will,
however, not affect the qualification of the individual partners.
#4.6 JOINT VENTURE: (Maximum 3 Members i.e. 1 Lead & 2 Others) (Applicable
only for estimated project cost of 50 Crore and above) – JV NOT APPLICABLE
4.6.1. Joint ventures must comply with the following requirement:
(a) Following are the minimum qualification requirements:
(i) The lead partner shall meet not less than 50 percent of all criteria given in para 4.5.3 &
4.5.6 above. The joint venture must collectively satisfy the criteria of para 4.5.3 & 4.5.6
above. The experience of the other joint venture partners shall be considered if it is not
less than 30 percent of the qualifying criteria in para 4.5.3 & 4.5.6 above.
(ii) Individually each member must satisfy the requirements of para 4.5.7 & 4.5.8 above.
(b) Bid shall be signed so as to legally bind all partners, jointly and severally, and shall be submitted
with a copy of the joint venture agreement providing the joint and several liabilities with
respect to the contract.
4.6.2. Qualification of a joint venture does not necessarily qualify any of its partners individually or as a
partner in any other joint venture. In case dissolution of a joint venture, each one of the
constituent firms may qualify if they meet all the qualification requirements, subject to the
written approval of the Employer.
4.7. Bid Capacity.
4.8 Even though the bidders meet the above qualifying criteria, they are subject to be disqualified
- Made misleading or false representation in the forms, statements and
Attachments the submitted in proof the qualification requirements; and / or Record of poor
performance such as abandoning the works, not properly completing the contract, inordinate
delay in completion, litigation history, or financial failures etc.; and/ or participated in the
previous bidding for the same work and had quoted unreasonably high bid prices and could
not furnish rational justification to the employer.
5. One bid per bidder
5.1. Each bidder shall submit only one bid for one package. A bidder who submits or participates in more
than one bid (other than as a subcontractor or in cases of alternatives that have been permitted
or requested) will cause all the proposals with the bidder’s participation to be disqualified.
6. Cost of Bidding
6.1. The bidder shall bear all costs associated with the preparation and submission of his Bid, and the
Employer will in no case be responsible and liable for those costs.
7.1. The Bidder, at the Bidder’s own responsibility and risk is encouraged to visit and examine the Site of
work and its surrounding and obtain all information that may be necessary for preparing the Bid
and entering into a contract for construction of the Works.
The costs of visiting the site shall be at the Bidder’s own expense.
B. BIDDING DOCUMENTS
8. Content of Bidding Documents
8.1 The set of bidding documents comprises the documents listed below and addenda issued in
accordance with Clause 10:
Section Particulars Volume No.
- Invitation for Bids
1 Instructions to Bidders
2 Qualification Information, and other forms
3 Conditions of Contract
4 Contract Data
5 Technical Specifications II & III
6 Form of Bid IV
7 Bill of Quantities
8 Securities and other forms
10 Documents to be furnished by bidder V
8.2. Volumes I, II, III and IV are available online and documents to be furnished by the bidder in
compliance to section 2 will be prepared by him and furnished as Volume- V in two parts (refer
8.3. The bidder is expected to examine carefully all instructions, conditions of contract, contract data,
forms, terms, technical specifications, bill of quantities, forms, Annexes and drawings in the Bid
Document. Failure to comply with the requirements of Bid Documents shall be at the bidder’s
own risk. Pursuant to clause 26 hereof, bids which are not substantially responsive to the
requirements of the Bid Documents shall be rejected.
9. Clarification Bidding Documents
9.1 A prospective bidder requiring any clarification of the bidding documents may notify the
Employer in writing or through E-mail at the Employer’s address indicated in the invitation to
bid. The Employer will respond to any request for clarification which he received earlier than
15 days prior to the deadline for submission of bids. Employer’s response will be published on
website including a description of the enquiry but without identifying its source.
9.2. Pre-bid meeting
9.2.1. The bidder or his official representative is invited to attend a pre-bid meeting which will take
place at the address, venue, time and date as indicated in the appendix.
9.2.3. The purpose of the meeting will be to clarify issues and to answer questions on any matter that
may be raised at that stage.
9.2.4. The bidder shall be required to submit any questions in writing or e-mail to reach the Employer
not later than 03 days before the meeting.
9.2.4 Minutes of the meeting, including the question raised (Without identifying the source of enquiry)
and the responses given will be published without delay on the tender website i.e.
www.nprocure.com. Any modification of the bidding documents listed in sub-Clause
which may become necessary as a result of the pre-bid meeting shall be made by the
Employer exclusively through the issue of an Addendum pursuant to Clause 10 and not
through the minutes of the pre-bid meeting.
9.2.5. Non-attendance at the pre-bid meeting will not be a cause for disqualification of a bidder.
10. Amendment of Bidding Documents
10.1 Before the deadline for submission of bids, the Employer may modify the bidding documents
by issuing addenda.
10.2. Any addendum thus issued shall be part of the bidding documents. The Employer will assume
no responsibility for the same.
10.3. To give prospective bidders reasonable time in which to take an addendum into account in
preparing their bids, the Employer may, at his discretion, extend as necessary the deadline for
submission of bids, in accordance with Sub-Clause 20.2 below.
C. PREPARATION OF BIDS
11. Language of the Bid
11.1 All documents relating to the bid shall be in the English language.
12. Documents Comprising the Bid
12.1. The bid be submitted by the bidder as Volume V of the bid document (refer Clause 8.1) shall be
in two separate parts:
Part I shall be named “Technical Bid” and shall comprise
(i) Bid Security in the form specified in Section
(ii) Qualification Information and supporting documents as specified in Section
(iii) Certificates, undertakings, affidavits as specified in Section
(iv) Any other information pursuant to Clause 4.5 of these instructions
(v) Undertaking that the bid shall remain valid for the period specified in Clause
Part II shall be named “Financial Bid” and shall comprise
(i) Form of Bid as specified in Section
(ii) Priced Bill of Quantities for items specified in Section
12.2. The Bidder shall submit the details / information pertaining to each part i.e. technical
as well as financial and must be submitted online only.
12.3. Following documents will be deemed to be part of the bid.
Section Particulars Volume No.
- Invitation for Bids
1 Instructions to Bidders
2 Qualification Information, and other forms
3 Conditions of Contract
4 Contract Data
5 Technical Specifications II & III
6 Form of Bid IV
7 Bill of Quantities
8 Securities and other forms
10 Documents to be furnished by bidder V
13.1 The Contract shall be for the whole works as described in Sub-Clause 1.1, based on the priced Bill
of Quantities submitted by the Bidder.
13.2 The bidder shall fill in rates and prices and line item total (both in figures and words) for all items
of the Works described in the Bill of Quantities along with total bid price (Both in figures and
words). Items for which no rate or price is entered by the bidder will not be paid for by the Bill of
13.3 All duties, taxes, and other levies except GST payable by the contractor under the contract, or for
any other cause shall be included in the rates, prices and total Bid Price submitted by the Bidder.
(GST will be paid extra)
13.4 The rates and prices quoted by the bidder are subject to adjustment during the performance of the
Contract in accordance with the provisions of Clause 47 of the Conditions of Contract (For contracts
more than 12 Months period).
13.5 The rates and prices quoted by the bidder are subject to adjustment during the performance of
the Contract in accordance with the provisions of Clause 47 of the Condition of Contract
(Irrespective of the time limit and Bid Amount)
14. Currencies of Bid and Payment
14.1 The unit rates and the prices quoted by the bidder shall be entirely in Indian Rupees. All
payments shall be made in Indian Rupees.
15. Bid Validity
15.1 Bids shall remain valid for a period of not less than 120 days after the deadline date forbid
submission specified in Clause
15.2 In exceptional circumstances, prior to expiry of the original time limit, the Employer may request
that the bidders may extend the period of validity for a specified period. A bidder may refuse the
request without forfeiting his bid security. A bidder agreeing to the request will not be required
or permitted to modify his bid, but will be required to extend the validity of his security for a
period of the extension, and in compliance with Clause 16 in all respects.
#16. Bid Security
16.1. The Bidder shall furnish, as part of his Bid, a Bid security in the amount as shown in column 4 of
the table of IFB for this particular work. This Bid security shall be in favor of Employer as named
in Appendix and may be in one of the following forms;
a. Bank Guarantee from any scheduled Indian bank, in the format given in Volume III. (Bank
Guarantee is applicable only for Bid Estimated Amount of 01 Crore and above) and
Bank Guarantee of Schedule and Private Banks shall be considered as per GoG Finance
Department’s Circular No. FD/MSM/e- file/4/2023/0057/D.M.O. Date 21/04/2023 or as
per their latest amendment.
b. Fixed Deposit Receipt issued by any Scheduled Indian Bank or a foreign Bank approved by
the Reserve Bank of India.
# A Valid Bid Security / EMD Exemption Certificate issued by (1) Road & Building
Department or (2) Narmada Water Resources, Water Supply and Kalpsar Department of
Govt of Gujarat. Exemption Certificate is applicable only when Registration Certificate
of Appropriate Class and Category of Approved Contractors is required as eligible
criteria of bidder.(EMD Exemption not allowed)
16.2. Bank guarantees (and other instruments having fixed validity) issued as surety for the bid shall
be valid for 28 days beyond the validity of the bid i.e. total validity of 120+28 = 148 Days
16.3. Any bid not accompanied by an acceptable Bid Security and not secured as indicated in Sub-
Clauses 16.1 and 16.2 above shall be rejected by the Employer as non-responsive.
16.4. The Bid Security of unsuccessful bidders will be returned within 28 days of the end of the bid
validity period specified in Sub-Clause
16.5 The Bid Security of the successful bidder will be discharged when the bidder has signed the
Agreement and furnished the required Performance Security.
16.6. The bid Security may be forfeited
(a) If the Bidder withdraws the bid after Bid opening during the period of Bid validity.
(b) If the Bidder does not accept the correction of the Bid Price, if any or
(c) In the case of a successful Bidders, if the Bidder fails the specified time limit to
(i) Sign the Agreement; or
(ii) Furnish the requirement Performance Security.
(d) #If found necessary, the bidder will be intimated for negotiation, He will be intimated
maximum three times within the validity period for negotiation, If contractor does not
respond in time, his Bid Security (EMD) will be forfeited and his tender will be rejected.
Punitive action will be taken on such contractors. (As per GoG R&B Dept’s Gr. No.
17. Alternative Proposals by Bidders.
17.1. Bidders shall submit offers that fully comply with the requirements of the bidding documents,
including the conditions of contract (including mobilization advance or time for completion),
basic technical design as indicated in the drawing and specifications. Conditional offers or
alternative offers will not be considered further in the process of tender evaluation.
18. Format and Signing of Bid
18.1. The Bidder shall prepare documents comprising the bid as described in Clause 12 of these
Instructions to bidder as the “Technical Bid “and “Financial Bid” in separate parts to be uploaded.
D. SUBMISSION OF BIDS
19. Sealing and Marking of Bids
19.1. The Bidder shall submit the bid namely, Technical Proposal & Financial Proposal through online
by the help of Digital Signature Certificate.
-Technical Bid: To be opened on 00.00. 2026 at 14.00 Hrs. (date of Technical Bid opening) in the
presence of Evaluation Committee.
-Financial Bid: Not to be opened except with the approval of Evaluation Committee The contents
of Technical and Financial Bids will be as specified in clause
19.2. The inner, outer, and separate envelopes containing Technical and FinancialBids shall
(A) be addressed to the Employer at the address given in Appendix
(B) bear the identification as indicated in Appendix.
19.3. In addition to the identification required in Sub-Clauses 19.1 and 19.2, each of the envelopes
shall indicate the name and address of the bidder to enable the bid to be returned unopened in
case it is declared late, pursuant to Clause 21, or the Evaluation Committee declares the bid as
non responsive pursuant to Clause
19.4. If the outer envelope is not sealed and marked as above, the Employer with assume no
responsibility for the misplacement or premature opening of the bid.
20. Deadline for Submission of the Bids
20.1. Complete Bids must be received online by the Employer at the tender website specified above
not later than the date indicated in appendix.
20.2. The Employer may extend the deadline for submission of bids by issuing an amendment in
accordance with Clause 10, in which case all right and obligation of the Employer and the bidders
previously subject to the original deadline will then be subject to the new deadline.
21.1. Any Bid received by the Employer after the deadline prescribed in Clause 20 will be returned
unopened to the bidder.
22. Modification and Withdrawal of Bids
22.1. Bidders may modify or withdraw their bids online before the deadline prescribed in Clause 20 or
pursuant to Clause
22.2 Withdrawal or modification of a bid between dead line for submission of bids and the expiration of
the original bid validity specified in Clause 15.1 above or as extended pursuant to Clause 15.2 may
result in the forfeiture of the Bid Security pursuant to Clause
22.3. No bid shall be modified or withdrawn after the deadline for submission of Bid.
22.4. Withdrawal or modification of a bid between the deadline for submission of bids and the
expiration of the original period of bid validity specified in Clause 15.1 above or as extended
pursuant to Clause 15.2 may result in the forfeiture of the Bid security pursuant to Clause
E. BID OPENING AND EVALUATION
23. Bid Opening
23.1 The Employer will open all the Bids received including modifications made pursuant to Clause 22, in
the presence of the Bidders or their representatives who choose to attend at time, date and the
place specified in Appendix in the manner specified in Clauses 20 and 23.3, In the event of the
specified date of Bid opening being declared a holiday for the Employer, the Bids will be opened
at the appointed time and location on the next working day.
23.2. Envelopes marked "WITHDRAWAL" shall be opened and read out first. Bids for which an acceptable
notice of withdrawal has been submitted pursuant to Clause 22shall not be opened.
23.3. The “Technical Bid” shall be opened. The amount, form and validity of the bid security furnished
with each bid will be announced. If the bid security furnished does not conform to the amount
and validity period as specified in the invitation for bid (ref. Column 4 and paragraph 3), and has
not been furnished in the form specified in Clause 16, the technical bid will not be opened.
23.4. (i) Subject to confirmation of the bid security by the issuing Bank, the bids accompanied with
valid bid security will be taken up for evaluation with respect to the Qualification
information and other information furnished in part I of the bid pursuant to Clause 12.1.
(ii) If required, the bidder will be asked in writing to clarify his Qualification Documents with
respect to any required clarification.
(iii) The bidders will respond in not more than 7 days of issue of the clarification letter.
(iv) Immediately (usually within 3 or 4 days), on receipt of these clarification the Evaluation
Committee will finalize the list of responsive bidders whose financial bids are eligible for
23.5. If, as a consequence of the modifications carried out by the bidder in responseto sub-clause
23.4, the bidders desire to modify their financial bid, they will submit the modification in
separate sealed envelope so as to reach the Employer's address (refer sub-clause 19.2) before
the opening of the financial bid as intimated in the clarification letter (refer sub-clause 23.4).
The envelope shall have clear marking "MODIFICATION TO FINANCIAL BID-Not to be opened
except with the approval ofthe Evaluation Committee"
23.6 At the time of opening of “Financial Bid”, the names of the bidders were found responsive in
accordance with Clause 23.4(iv) will be announced. The bids of only these bidders will be
opened. The responsive Bidders’ names, the Bid prices, the total amount of each bid, any
opened. The responsive Bidders’ names, the Bid prices, the total amount of each bid, any
discount and such other details as the Employer may consider appropriate, will be announced by
the Employer at the opening.
23.7 the time of opening of “Financial Bid”, the names of the bidders were found responsive in
accordance with Clause 23.4(iv) will be announced. The bids of only these bidders will be
opened. The responsive Bidders’ names, the Bid prices, the total amount of each bid, any
opened. The responsive Bidders’ names, the Bid prices, the total amount of each bid, any
discount, and such other details as the Employer may consider appropriate, will be announced
by the Employer at the opening.
23.8 In case bids are invited for more than one package, the order for opening of the “Financial Bid”
shall be in order of Estimated amount of Bids from highest to lowest.
23.9 The Employer shall prepare minutes of the Bid opening, including the information disclosed to
those present in accordance with Sub-Clause 23.6.
24.1 Information relating to the examination, clarification, evaluation, and comparison of Bids and
recommendations for the award of a contract shall not be disclosed to Bidders or any other
persons not officially concerned with such process until the award to the successful Bidder has
been announced. Any effort by Bidder to influence the Employer’s processing of Bids or award
decisions may result in the rejection of his Bid.
25. Clarification of Financial Bids
25.1. To assist in the examination, evaluation, and comparison of Bids, the Employer may, at his
discretion, ask any Bidder for clarification of his Bid, including breakdowns of unit rates. The
request for clarification and the response shall be in writing or by e- mail, but no change in the
price or substances of the Bid shall be sought, offered, or permitted except as required to
confirm the correction of arithmetic errors discovered by the Employer in the evaluation of the
25.2 Subject to sub-clause 25.1, no Bidder shall contact the Employer on any matter relating to his Bid
opening to the contract is awarded. If the Bidder wishes to bring additional information to the
notice of the Employer, it should do so in writing.
25.3. Any effort by the Bidder to influence the Employer in the Employer's bid evaluation, bid
comparison or contract award decision may result in the rejection of the Bidders’ bid.
26. Examinations of Bids and Determination of Responsiveness
26.1 During the detail evaluation of "Technical Bid", the Employer will determine whether each Bid (a)
meets the eligibility criteria defined in Clause 3 and 4; (b) has been properly signed; (c) is
accompanied by the required securities and; (d) is substantially responsive to the requirements
of the Bidding document. During the detailed evaluation of the “Financial Bid”, the
responsiveness of the bids will be further determined with respect to the remaining bid
conditions, i.e., priced bill of quantities, technical specifications, and drawings.
26.2 A substantially responsive “Financial Bid” is one which confirms all the terms, conditions and
specifications of bidding documents, without material deviation or reservation. A material
deviation or reservation is one (a) which affects in any substantial way the scope, quality, or
performance of the Works; (b) which limits in any substantial way, inconsistent with the Bidding
documents, the Employer’s rights or the Bidder’s obligations under the Contract; or (c) whose
rectification would affect unfairly the competitive position of other Bidders presenting
substantially responsive Bids.
26.3 If a “Financial Bid” is not substantially responsive, it will be rejected by the Employer, and may
not subsequently be made responsive by correction or withdrawal of the non-conforming
deviation or reservation.
27. Correction of Errors
27.2 "Financial Bids" determined to be substantially responsive will be checked by the Employer for
any arithmetic errors. Errors will be corrected by the Employer as follows:
(a) where there is a discrepancy between the rates in figures and in words, the rate in words
will govern; and
(b)where there is a discrepancy between the unit rate and the line item total resulting
from multiplying the unit rate by the quantity, the unit rate as quoted will govern.
27.2 The amount stated in the "Financial Bid" will be corrected by the Employer in accordance with
the above procedure and the bid amount adjusted with the concurrence of the Bidder in the
following manner:
a) If the Bid price increases as a result of these corrections, the amount as stated in the bid
will be the 'bid price' and the increase will be treated as rebate;
b) If the bid price decreases as a result of the corrections, the decreased amount will be
treated as the 'bid price'
Such adjusted bid price shall be considered as binding upon the Bidder. If the Bidder does not accept the
corrected amount the Bid will be rejected, and the Bid security may be forfeited in accordance with Sub-
Clause 16.6 (b).
29. Evaluation and Comparison of Financial Bids
29.1. The Employer will evaluate and compare only the Bids determined to be substantially responsive
in accordance with Sub-Clause 26.2.
29.2. In evaluating the Bids, the employer will determine for each Bid the evaluated Bid Price by adjusting
the Bid Price as follows.
a) Making any correction for errors pursuantto Clause 27; or
b) making an appropriate adjustments for any other acceptable variations, deviations; and
c) making appropriate adjustments to reflect discounts or other price modifications offered in
accordance with Sub-Clause
29.3. The Employer reserves the right to accept or reject any variation or deviation. Variation and
deviations and other factors, which are in excess of the requirements of the Bidding documents
or otherwise result in unsolicited benefits for the Employer, shall not be taken in to account in
Bid evaluation.
29.4. The estimated effect of the price adjustment conditions under Clause 47 of the Conditions of
Contact, during the period of implementation of the Contract, will not be taken in to account in
Bid evaluation.
29.5. If the Bid of the successful Bidder is seriously unbalanced in relation to the Engineer’s estimate
of the cost of work to be performed under the contract the Employer may require the Bidder to
produce detailed consistency of those prices with the construction methods and schedule
proposed. After evaluation of the price analyses, the Employer may require that the amount of
the performance security set forth in Clause 34 be increased at the expense of the successful
/bidder to a level sufficient to protect the Employer against financial loss in the event of default
of the successful Bidder under the Contract.
29.6. A bid which contains several items in the bill of Quantities which are unrealistically priced low
and which cannot be substantiated satisfactorily by the bidder may be rejected as non-
F. AWARD OF CONTRACT
31. Award Criteria
31.1. Subject to Clause 32, the Employer will award the contract to the Bidder whose Bid has been
(i) to be substantially responsive to the Bidding documents and who has offered the lowest
evaluated Bid Price; and
(ii) to be within the available bid capacity adjusted to account for his bid price which is the
lowest evaluation in any of the packages opened earlier than the one consideration.
In no case, the contract shall be awarded to any bidder whose available bid capacity is
less than the evaluated bid price, even if the said bid is the lowest evaluated bid. The contract
will in such cases be awarded to the next lowest bidder at his evaluation bid price.
32. Employer’s Right to Accept any Bid and to Reject any or all Bids
32.1. Notwithstanding Clause 31, the Employer reserves the right to accept or reject any Bid, and to
cancel the Bidding process and reject all Bids, at any time prior to the award of contract, without
thereby incurring any liability to the affected bidder or Bidder or any obligation to inform the
affected Bidder or Bidders of the grounds for the Employer’s action.
33. Notification of Award and Signing of Agreement
33.1. The Bidder whose Bid has been accepted will be notified of the award by the Employer prior to
expiration of the Bid validity period by cable, telex or facsimile confirmed by registered letter.
This letter (hereinafter and in the condition of contract called the “Letter of Acceptance”) will
state the sum that the Employer will pay the Contractor in consideration of the execution,
completion, and maintenance of the Works by the Contractor as prescribed by the Contract
(hereinafter and in the Contract called the “Contract Price”).
33.2 The notification of award will constitute the formation of the contract, subject only to the
furnishing of a performance security in accordance with the provisions of Clause.
33.3. The Agreement will incorporate all agreements between the Employer and the successful Bidder.
It will be signed by the Employer and to the successful Bidder, within 28 days following the
notification of award along with the Letter of Acceptance. Within 21 days of receipt, the
successful Bidder will sign the Agreement and deliver it to the Employer.
33.4. Upon the furnishing by the successful Bidder of the Performance Security, the Employer will
promptly notify the other Bidders that their Bids have been unsuccessful.
34. Performance Security
34.1. Within 10 (Ten) days of receipt of Letter of Acceptance, the successful Bidder shall furnish to the
Employer an irrevocable and unconditional guarantee from a Bank in the form set forth in Section
8 (the “Performance Security”) for an amount equal to 5% (five percent) of its Contract Price. In
case of bids mentioned below, the successful Bidder, along with the Performance Security,
shall also furnish to the Authority an irrevocable and unconditional guarantee from a Bank in the
same form given at Section 8 towards an Additional Performance Security (The “Additional
Performance Security”) for an amount calculated as under:
(a) If the Contract Price offered by the Selected Bidder is lower than 10% but upto 20% of the
Estimated Project Cost, then the Additional Performance Security shall be calculated @ 20%
of the difference in the (i) Estimated Project Cost (as mentioned in Bid Document) - Minus
10% of the Estimated Project Cost and (ii) Contract Price offered by the selected Bidder.
(b) If the Contract Price offered by the Selected Bidder is lower than 20% of the Estimated
Project Cost, then the Additional Performance Security shall be calculated @ 30% of the
difference in the (i) Estimated Project Cost (as mentioned in Bid Document) - Minus 10% of
the Estimated Project Cost and (ii) Contract Price offered by the selected Bidder.
(c) This Additional Performance Security shall be treated as part of the Performance Security.
(D) The Performance Security shall be valid beyond 60(sixty) days of the Defects Liability Period
and the Additional Performance Security shall be valid beyond 28 (twenty-eight) days of
Project Completion Date.
34.2. If the performance security is provided by the successful Bidder in the form of a Bank
Guarantee, it shall be issued either (a) at the Bidder’s option, by a Nationalized/Scheduled
Indian bank or (b) by a foreign bank located in India and acceptable to the Employer. As per
GoG Finance Department’s Circular No. FD/MSM/e-file/4/2023/0057/D.M.O. Date 21/04/2023
or as per their latest amendment.
34.3. Failure of the successful Bidder to comply with the requirement of Sub-Clause 34.1 shall
constitute sufficient grounds for cancellation of the award and forfeiture of the Bid Security.
35 Advance Payment and Security
35.1 The Employer will provide an Advance payment on the Contract Price as stipulated in the
Conditions of Contract, subject to maximum amount, as stated in the Contract Data.
36. Dispute Review Expert
36.1 The Employer proposes that [name of proposed Dispute Review Expert as indicated in
Appendix] be appointed as Dispute Review Expert under the Contract, at a daily fee as
indicated in Appendix plus reimbursable expenses. If the Bidder disagrees with this proposal,
the Bidder should so state in the Bid. If in the Letter of Acceptance, the Employer has not
agreed on the appointment of the Dispute Review Expert, the Dispute Review Expert shall be
appointed by the Council of Indian Roads Congress at the request of either party.
37. Corrupt of Fraudulent Practices
37.1 The Employer will reject a proposal if it determines that the Bidder recommended for award has
engaged in corrupt or fraudulent practices in completing for the contract in question and will
declare the firm ineligible, either indefinitely or for a stated period of time, to be awarded a
contract with National Highways Authority of India/ State PWD and any other agencies, if it at
any time determines that the firm has engaged in corrupt or fraudulent practices in completing
for the contractor, or in execution.
37.2 Furthermore, Bidders shall be aware of the provision stated in Sub- Clause 59.2 of the
Conditions of Contract.
APPENDIX TO ITB
Clause Reference with respect to Section –I
1. The Name of the Employer is [ Cl.1.1]
Chief Officer LIMBADI Nagarpalika
2. The last five years.
3. This Annual Financial Turnover Amount is Rs. [Cl.4.5.3 (a)]
4. Value of Work is Rs.
6. The cost of electric work is Rs.
7. The cost of water supply / sanitary works is
8. Liquid assets and / or availability of credit facilities is Rs. ………… [Cl.4.5.6 ]
9. Price level of the financial year …………… [Cl. 4.5.2]
10. The pre-bid meeting will take place at …………. [Cl. 9.2.1]
11. The technical Bid will be opened at the office of the ……………………on dt
12. Address of the Employer: …………..
13. Identification :
( name of Contract)
- Bid reference No 0 of 2026-27 of LIMBADI Nagarpalika- ( insert number)
- Do not open before 00.00. 2026 at 14.00 Hrs - ( time and date )
14. The bid should be submitted latest by As stated on online NIT [Cl. 20.1 & 20.2]
15. The bid will be opened at …………………………… As stated on online NIT [Cl. 23.1 ]
16. The Bank Draft in favor of ………………………..
17. Escalation factors (for the cost of works [Cl.4.5.2]
executed and financial figure to a common base value) for works completed
Year Financial Year Multiplying factor
Base year of inviting tender 2025-2026
#LIST OF KEY PLANT & EQUIPMENT TO BE DEPLOYED ON CONTRACT WORK
[Reference CL. 4.5.5]
The contractors shall also give a list of machineries in his possession and which they propose to use on
Sr. Plant or Location Age of Make Capacity Approximate Remark
No. Machinery Machinery Value
List of Key Personnel to be deployed on Contract Work (Reference Cl. 4.5.4)
# Employment of a qualified site Engineer by the Contractor.
The Contractor shall employ full-time technically qualified staff during the execution of this work as
1. Two graduate Civil Engineers and three diploma Civil Engineers when cost of the work to be
executed is more than Rs.50 lakhs.
2. One graduate & two Diploma, Civil Engineers when the cost of the work to be executed is more
than Rs.15 lakhs but less than Rs.50 lakhs.
3. Minimum one Diploma Civil Engineer when the cost of work is less than Rs.15 lakhs but more than
4. Minimum two Diploma Civil Engineers for the work when the cost of work to be executed is less
than Rs. 5 lakhs. The Engineer so employed for the Government work must have sufficient
experience to handle the work independently. Such an Engineer shall have to stay at the site of
work and he shall not be entrusted with other duty except this work.
In case the contractor or partner of the contractor firm is a Civil Graduate Engineer, Employment of
a separate Engineer will not be necessary provided that the Engineer partner himself attends the
execution of the work on the site.
Within 15 days of issue of work-order the Contractor will have to furnish to the Chief Officer-in-
charge of the work the Name, Qualifications, copy of marksheet, Colour Photograph and the
appointment order issued such engineers engaged for this contract work. If 15 days after issue of
work order such designated Site Engineers do not resume or do not remain present on site of work,
the recovery at the rate of Rs.15,000-00 per month per Engineer will be made from the
bills/deposit/dues of the contractor. Such recovery shall be non-refundable.
QUALIFICATION INFORMATION
QUALIFICATION INFORMATION
The information to be filled in by the Bidder in the following pages will be used for the purpose of
post qualification as provided for in Clause 4 of the Instruction to Bidders. This information will not be
incorporated in the Contract.
1. For Individual Bidders
1.1 Constitution or legal status of Bidder
Place of registration
Principal place of business
Power of attorney of signatory of Bid
1.2 Total value of Civil engineering constructions
Work performed in the last five years
Work performed as prime contractor, work performed in the past as a nominated sub-contractor
will also be considered the sub-contract involved execution of all main items of work described in
the bid documents, provided further that all other qualification criteria are satisfied (in the same
name) on works of a similar nature over the last five years** and in current year before the
submission of the bid.
Project Name of Description Contract Value of Date Stipulated Actual date of Remark
Name the of work No. contract of period of completion* explaining
Employer (Rs. issue completion reasons for
Crore) of delay &
order Completed
*Attach certificate(s) from the Engineer(s)in-charge
** Immediately preceding the financial year in which bids are received.
#1.3.2 Quantities of work executed as prime contractor, work performed, in the past as a nominated sub-
contractor, will also be considered provided the sub-contract involved execution of all main
items of work described in the bid document, provided, further that all other qualification criteria
are called (in the same name and style) in the last seven years** and in current year before the
submission of the bid.
Year Name Name of Quantity of work performed (Cum/MT) Remarks*
of the the Cement Masonry Earth Bituminous (indicate
work Employer Concrete Works Work contract Ref)
1.4 Information on Bid Capacity (works for which bids have been submitted and works which are yet
to be completed) as on the date of this bid.
(A) Existing commitments and on-going works:
Description Place Contract Name & Value Stipulated Value of Anticipated
of works & No. Address of Contract Period of Works* of
State Employer (Rs. Cr) Completion remaining completion
*Attach certificate (s) from the Engineer(s) in-charge
** Immediately preceding the financial year in which bids are received.
1.5 Availability of key items of Contractors Equipment for carrying out the works (Ref. Clause 4.5.5).
The Bidder should list all the information requested below.
Item of Requirement Availability Proposals Remarks
Equipment NO Capacity Owned/ Nos/. Age/ (from
Leased to be Capacity Conditions whom to
1.6 Qualifications and experience of key personnel required for administration and execution of the
contract. Attach biographical data. Refer also to Sub Clause 9.1 of the Conditions of Contract.
Position Name Qualification Year of Year of experience
Experience in the proposed
(General) position
Project Manager &
1.7 Proposed sub-contract and firms involved
Sections of the works Value of Sub- Sub-Contractor (Name Experience in
Contractor & similar work
Attach copies of certificates on possession of valid license for executing water supply/ sanitary
work/ building electrification works.
1.8 Financial reports for the last five years: balance sheets, profit and loss statements, auditors’
reports (in case of companies/corporations), etc. List them below and attach copies.
1.9 Evidence of access to financial resources to meet the qualification requirements: cash in hand,
lines of credit, etc. List them below and attach copied documents.
1.10 Name, address, and telephone, telex, and fax numbers of the Bidders bankers who may provide
references if contacted by the Employer.
1.11 Information on Litigation history in which the Bidder is involved.
Other Party (ies) Employer Cause of Amount Remarks showing
Dispute Involved Present Status
1.12. Statement of compliance under the requirements of Sub Clause 3.2 of the instruction to Bidders.
(Name of Consultant engaged for project preparations is * .......................................................... )
1.13 Proposed work method and schedule. The Bidder should attach descriptions, drawings and
charts as necessary to comply with the requirements of the Bidding documents. (Refer ITB Clause
1.15 Quality Assurance Plan
3. Additional Requirements
3.1 Bidders should provide any additional information required to fulfill the
requirements of Clause 4 of the Instructions to the Bidders, if applicable.
(ii) Undertaking
(iii) Update of original prequalification application. (*)
(iv) Copy of original prequalification application (**)
(v) Copy of prequalification letter (***)
* Delete, if prequalification has been carried out.
** Fill the Name of Consultant.
*** Delete, if prequalification has not been carried out.
SAMPLE FORMAT FOR EVIDENCE OF ACCESS TO OR AVAILABILITY OF CREDIT
(CLAUSE 4.5.6 OF ITB)
BANK CERTIFICATE
This is to certify that M/s. is a reputed company
with a good financial standing.
If the contract for the work, namely is awarded to the
above firm, we shall be able to provide overdraft/credit facilities to the extent of Rs. To meet
their working capital requirements for executing the above during the contract period.
Senior Bank Manager
Address of the Bank
1. I, the undersigned, do hereby certify that all the statements made in the required
attachments are true and correct.
2. The undersigned also hereby certifies that neither our firm M/s.
have not abandoned/Blacklisted/
Debarred from any work of Government of Gujarat/Government of India/any Board or
Corporation under Government of Gujarat/Government of India nor any contract awarded to
us for such works have been rescinded, during last five years prior to the date of this bid.
3. The undersigned hereby authorize(s) and request (s) any bank, person, firm or corporation to
furnish pertinent information deemed necessary and requested by the Department to verify
this statement or regarding any (our) competence and general reputation.
4. The Undersigned understands and agrees that further qualifying information may be
requested, and agrees to furnish any such information at the request of the Department/
Project implementing agency.
(Signed by an Authorized Officer of the Firm)
Title of Officer
I, the undersigned do hereby undertake ................. that our firm M/s
up to 25% of the value of the work during implementation of the contract.
(Signed by an Authorized officer of the firm)
Title of officer
CONDITIONS OF CONTRACT
Conditions of Contract
Table of Contents
A General D. Cost Control
1 Definitions 37 Bill of Quantities
2 Interpretation 38 Changes in the Quantities
3 Language and Law 39 Variations
4 Engineer’s Decisions 40 Payments for Variations
5 Delegations 41 Cash Flow Forecasts
6 Communications 42 Payment Certificates
7 Sub-Contractors 43 Payments
8 Other Contractors 44 Compensations Events
9 Personnel 45 Tax
10 Employer’s & Contractor Risk 46 Currencies
11 Employers Risks 47 Price Adjustment
12 Contractor’s Risk 48 Retention
13 Insurance 49 Liquidated damages
14 Site Investigations Reports 50 Bonus
15 Queries about the Contract 51 Advance Payment
16 Contractors to Construct the works 52 Securities
17 The Works to be Completed By 53 Deleted
the Intended Completion Date
18 Approval by the Engineer 54 Cost of Repair
20 Discoveries E. Finishing the Contract
21 Possession of the Site 55 Completion
22 Access to the Site 56 Taking Over
23 Instructions 57 Final Account
24 Disputes 58 Operating and Maintenance
25 Procedure for Disputes
26 Replacement of Dispute Review 59 Terminations
60 Payment upon Terminations
B. Time Control 61 Property
27 Programme 62 Release from Performance
28 Extensions of the Intended
completion date
29 Deleted F. Special Conditions of
30 Delays Ordered by The 63 Labour
Engineer 64 Compliance with labour regulations
31 Management Meetings 65 Arbitration
32 Early Warning
C. Quality Control
33 Identifying Defects
35 Correction of Defects
36 Uncorrected Defects
CONDITIONS OF CONTRACT
1.1 Terms which are defined in the Contract Data are not also defined in the Conditions of Contract
but keep their defined meaning.
Bill of Quantities means the priced and completed Bill of Quantities forming part of the
Compensation Events are those defined in Clause 44 hereunder
The Completion Date is the date of completion of the Works as certified by the
Engineer in accordance with Sub Clause
The Contract is the contract between the Employer and Contractor to execute,
complete and maintain the Works till the completion of Defects Liability Period. It consists of
the documents listed in Clause 2.3 below.
The Contract data defines the documents and other information which comprise the
The Contractor is a person or corporate body whose Bid to carry out the Work has
been accepted by the Employer.
The Contractor’s Bid is the completed Bidding document submitted by the Contractor
to the Employer and includes Technical and Financial Bids.
The Contract Price is the price stated in the Letter of Acceptance and thereafter as
adjusted in accordance with the provisions of the Contract.
Days are calendar days: months are calendar months.
The Defects Liability Period is the period named in the Contract Data and calculated
from the Completion Date.
The Employer is the party who will employ the Contractor to carry out the Works.
The Engineer is the person named in the Contract Data (or any other competent
person appointed and notified to the contractor to act in replacement of the Engineer) who is
responsible for supervising the Contractor, administering the Contract, certifying payments due
to the Contractor, issuing and valuing Variations to the Contract, awarding extensions of time,
and valuing the Compensations Events.
Equipment is Contractor’s machinery and vehicles brought temporarily to the site to
construct the Works.
The Initial Contract Price is the Contract Price listed in the Employer’s Letter of
The Intended Completion Date is the date on which it is intended that the Contractor shall
complete the Works. The Intended Completion Date is specified in the Contract Data. The
Intended Completion Date may be revised only by the Engineer by issuing an extension of time.
Materials are all supplies, including consumables, used by the contractor for
incorporation in the works.
Plant is any integral part of the work which is to have mechanical, electrical, electronic or
chemical or biological functions.
The Site is the area defined as such in the Contract Data.
Site Investigation Reports are those which were included in the Bidding documents and
are factual interpretive reports about the surface and subsurface conditions at the site.
Specifications means the Specifications of the works included in the Contract and any
modification or addition made or approved by the Engineer.
The Start Date is given in the Contract Data. It is the date when the Contractor shall
commence execution of the works. It does not necessarily coincide with any of the Site
Possession Dates.
A Subcontractor is a person or corporate body who has a Contract with the Contractor to
carry out a part of the work in the Contract which includes work on the Site.
Temporary Works are works designed, constructed, installed, and removed by the
Contractor which are needed for construction or installation of the Works.
A Variation is an instruction given by the Engineer, which varies the Works. The Works
are what the Contract requires the Contractor to construct, install,
and turn over to the Employer, as defined in the Contract Data.
2. Interpretation
2.1 In interpreting these Conditions of Contract, singular also means plural, male also means
female or neuter and the other way around. Heading have no significance. Words have
their normal meaning under the language of the Contract unless specifically defined. The
Engineer will provide instructions clarifying queries about Conditions of Contract.
2.2 If sectional completion is specified in the Contract Data, references in the Conditions of
Contract to the Works, the Completion date, and Intended Completion Date apply to any
Section of the Works (other than references to the Completion Date and Intended
Completion date for the whole works)
2.3 The documents forming the Contract shall be interpreted in the following order of
(2) Letter of Acceptance, notice to proceed with works
(3) Contractor’s Bid
(4) Contract Data
(5) Conditions of Contract including Conditions of Contract
(6) Specifications
(8) Bills of quantities and
(9) Any other document listed in the Contract Data as forming part of the Contract.
3. Language and Law
3.1 The language of the Contract and the law governing the Contract are stated in the
4. Engineers Decisions
4.1 Except where otherwise specifically stated, the Engineer will decide contractual matters
between the Employer and the Contractor in the role representing the Employer.
5.1 The Engineer may delegate any of his duties and responsibilities to other people after
notifying the Contractor and may cancel any delegation after notifying the Contractor.
6. Communications
6.1 Communications between parties which are referred to in the conditions are effective
only when in writing. A notice shall be effective only when it is delivered (in terms of
Indian Contract Act).
7. Sub-Contracting
7.1 The Contractor may subcontract any portion of work, up to a limit specified in contract
data, with the approval of the engineer but may not assign the Contract without the
approval of the Employer in writing. Subcontracting shall not alter the Contractor’s
obligations. Sub-contracting of supply or specific items of work is not allowed.
7.2 The sub-contractor must be registered in appropriate class and category for the part of
work to be subcontracted.
8. Other Contractors
8.1 The Contractor shall cooperate and share the Site with other contractors, public
authorities, utilities and the Employer between the dates given in the Schedule of other
Contractor. The Contractors shall as refer to in the Contract Data, also provide facilities
and services for them as described in the Schedule. The employer may modify the
schedule of other contractors and shall notify the contractor of any such modifications.
9.1 The Contractor shall employ the key personnel named in the Schedule of Key Personnel
as referred to in the Contract Data to carry out the functions stated in the Schedule or
other personnel approved by the Engineer. The Engineer will approve any proposed
replacement of key personnel only if their qualifications, abilities, and relevant
experience are substantially equal to or better than those of the personnel listed in the
9.2 If the engineer asks the Contractor to remove a person who is a member of the
Contractor Staff or his work force stating the reasons the Contractor shall ensure that the
person leaves the Site within seven days and has no further connection with the work in
10. Employer’s and Contractors Risks
10.1 The Employer carries the risk which these Contract states are Employer’s risks, and the
Contractor carries the risks which these Contracts states are Contractors risk.
11. Employer’s Risks
11.1 The employer is responsible for the excepted risks which are (a) in so far as they directly
affect the execution of the Works, the risks of war, hostilities, invasion, act of foreign
enemies, rebellion, revolution, insurrection or military or usurped power, civil war, riot
commotion or disorder (unless restricted to the Contractor’s employees), and
contamination from any nuclear fuel or nuclear waste or radioactive toxic explosive.
12. Contractor’s Risks
12.1 All risks of loss of or damages to physical property and of personal injury and death
which arise during and in consequence of the performance of the Contract other than
the excepted risks are the responsibility of the Contractor.
13.1 The Contractor shall provide, in the joint names of the Employer and the Contractor,
insurance cover from the Start date to the end of the Defects Liability Period, in the
amounts and deductibles stated in the Contract data for the following events which are
due to the Contractor’s risks:
(a) Loss of or damage to the works, Plant and materials,
(b) Loss of or damage to Equipment
(c) Loss of or damages of property (expect the Works, Plant, Materials and
Equipment) in connection with the Contract; and
(d) Personal injury or death.
13.2 Policies and certificates for insurance shall be delivered by the Contractor to the Engineer
for the Engineer’s approval before the Start Date. All such insurance shall provide for
compensation to be payable in the types and proportions of currencies required to
rectify the loss or damage incurred.
13.3 If the Contractor does not provide any of the policies and certificates required, the
Employer may affect the insurance which the Contractor should have provided and
recover the premiums the Employer has paid from payments otherwise due to the
Contractor or, if no payment is due, the payment of the premiums shall be a debt due.
13.4 Alterations to the terms of an insurance shall not be made without the approval of the
13.5 Both parties shall comply with any conditions of the insurance policies.
14. Site Investigation Report
14.1 The Contractor in preparing the Bid shall rely on any site Investigation reports referred
to in the Contract Data, supplemented by any information available to the Bidder.
15. Queries about the Contract data
15.1 The engineer will clarify queries on the Contract Data
16. Contractor to Construct the Works
16.1 The Contractor shall construct and install the works in accordance with the specification
17. The Works to be completed by the Intended Completion Date
17.1 The Contractor may commence execution of the Works on the Start Date and shall carry
out the Works in accordance with the programme submitted by the Contractor, as
updated with the approval of the Engineer, and complete them by the Intended
Completion date
18. Approval by the Engineer
18.1 The Contractor shall submit Specifications and Drawings showing the proposed
Temporary works to the Engineer, who is to approve them if they comply with the
Specifications and drawings.
18.2 The Contractor shall be responsible for design of temporary works.
18.3 The Engineer’s approval shall not alter the contractor responsibility for design of the
Temporary works.
18.4 The Contractor shall obtain approval of third parties to the design of the Temporary
works where required.
18.5 All Drawings prepared by the Contractors for the execution of the temporary or
permanent work are subject to prior approval by the Engineer before their use.
19.1 The Contractor shall be responsible for the safety of all activities on the Site.
20. Discoveries
20.1 Anything of historical or other interest or of significant value unexpectedly discovered on
the site is the property of the Employer. The contractor is to notify the engineer of such
discoveries and carry out the Engineer’s instructions for dealing with them.
21. Possession of the Site
21.1 The Employer shall give possession of all parts of the site to the Contractor. If possession
of a part is not given by the date stated in the Contract Data the Employer is deemed to
have delayed the start of the relevant activities and this will be a Compensation Event.
21.2 If within 25% of the time limit of the project, 80% of possession of the site is not handed
over to the Contractor, then contractor/ Employer may fore-close the contract.
Contractor/Employer has to foreclose the work within 30 days after lapse of 25%-time
limit and after 30 days foreclosure option will be closed.
22. Access to the Site
22.1 The Contractor shall allow the Engineer and any person authorized by the Engineer
access to the Site, to any place where work in connection with the Contract is being
carried out or is intended to be carried out and to any place where materials or plants
are being manufactured/ fabricated/ assembled for the works.
23. Instructions
23.1 The Contractor shall carry out all instructions of the Engineer pertaining to works which
comply with the applicable laws where the site is located.
23.2 The Contractor shall permit the Employer to inspect the Contractor’s accounts and
records relating to the performance of the Contractor and to have them audited by
auditors appointed by the Employer, if so required by the Employer.
24.1 If the Contractor is of the view that a decision taken by the Engineer was either outside
the authority given to the Engineer by the Contract or that the decision was wrongly
taken, the decision shall be referred to #Chief Officer(Higher Authority)within 14 days of
the notification of the Engineer's decision. If the issue is not resolved, any party can refer
the matter for conciliation within 15 days from the decision given by the #Chief Officer.
(a) For the work up to Rs.100 Cr., if any of the parties is not satisfied with the decision
of the #Chief Officer, both the parties have to refer to the Regional Commissioner
Municipality concern for the conciliation process.
(b) For the work more than Rs.100 Cr., if any of the parties is not satisfied with the
decision of the #Chief Officer, both the parties have to refer to the #ACEO GUDM,
Gandhinagar for the conciliation process.
If the dispute is not resolved through the conciliation process, he may refer the dispute
to Gujarat Public Works Contract Dispute Arbitration Tribunal. If the Contractor fails to
refer a claim / dispute to the Higher Authority within 14 days of the notification of the
Engineer's decision, the Contractor shall not be entitled to any additional payment/claim
if he doesn’t follow the above sequence in stipulated time and he should not stop the
25. Procedure for Disputers
25.1 The arbitration shall be conducted in accordance with the arbitration procedure
stated in the Special Conditions of Contract.
26. Replacement of Dispute Review Expert
26.1 Should the Dispute Review Expert resign or die, or should the Employer and the
Contractor agree that the Dispute Review Expert is not fulfilling his functions in
accordance with the provisions of the Contract, a new Dispute Review Expert will be
jointly appointed by the Employer and the Contractor. In case of disagreement between
the Employer and the Contractor, within 30 days, the Dispute Review Expert, shall be
designated by the Appointing Authority designated in the Contract Data at the request of
either party, within 14 days of receipt of such request.
B. TIME CONTROL
27.1 Within the time stated in the Contract Data the Contractor shall submit to the Engineer
for approval a Programme showing the general methods, arrangements orders, and
timing for all the activities in the works along with monthly cash flow forecast.
27.2 An update of the Programme shall be a programme showing the actual progress
achieved on each activity and the effect of the progress achieved on the timing of the
remaining work including any changes to the sequence of the activities.
27.3 The Contractor shall submit to the Engineer, for approval an updated programme at
intervals no longer than the period stated in the Contract data. If the Contractor does not
submit an updated programme within this period, the Engineer may withhold the
amount stated in the Contract data from the next payment after the date on which the
overdue programme has been submitted.
27.4 The Engineer’s approval of the programme shall not alter the Contractor’s obligations.
The Contractor may revise the programme and submit it to the Engineer again at any
time. A revised programme is to show the effect of Variations and Compensations
28. Extension of the Intended Completion Date
28.1 The Engineer shall extend the Intended Completion Date if a compensation Event occurs
or a Variation is issued which makes it impossible for completion to be achieved by the
Intended Completion Date without the Contractor taking steps to accelerate the
remaining work and which would cause the Contractor to incur additional cost.
28.2 The Engineer shall decide whether and by how much to extend the Intended Completion
Date within 35 days of the Contractor asking the Engineer for a decision upon the effect
of a compensation event or Variation and submitting full supporting information. If the
Contractor has failed to give early warning of a delay or has failed to cooperate in dealing
with a delay, the delay by this failure shall not be considered in assessing the new
Intended Completion Date.
28.3 The Engineer shall within 14 days of receiving full justification from the contractor for
extension of Intended Completion Date refer to the Employer his decision. The employer
shall in not more than 21 days communicate to the engineer the acceptance or otherwise
of the Engineer’s decision. If the employer fails to give his acceptance, the Engineer shall
not grant the extension and the contractor may refer the matter under Clause
30. Delays Ordered by the Engineer
30.1 The Engineer may instruct the Contractor to delay the start or progress of any activity
within the works.
31. Management Meetings
31.1 Either the Engineer or the Contractor may require the other to attend a management
meeting. The business of a management meeting shall be to review the plans for
remaining work and to deal with matters raised in accordance with the early warning
31.2 The Engineer shall record the business of management meetings and is to provide copies
of his record to those attending the meeting and to the Employer. The responsibility of
the parties for actions to be taken is to be decided by the Engineer either at the
management meeting or after the management meeting and stated in writing to all who
attended the meeting.
32. Early Warning
32.1 The Contractor is to warn the Engineer at the earliest opportunity of specific likely future
events or circumstances that may adversely affect the quality of the work, increase the
Contract price or delay the execution of works. The Engineer may require the contractor
to provide an estimate of the expected effect of the future event or circumstance on the
contract price and completion date. The estimate is to be provided by the Contractor as
soon as reasonably possible.
32.2 The Contractor shall cooperate with the Engineer in making and considering proposals
for how the effect of such an event or circumstance can be avoided or reduced by
anyone involved in the work and in carrying out any resulting instruction of the Engineer.
C. QUALITY CONTROL
# 33. Identifying Defects/ Defect liability period
33.1 : Defect liability period : The contractor shall be responsible to make good and remedy at
his own expense any defect which may develop or may be noticed before the period
mentioned hereunder from the certified date of completion. The Engineer in charge shall
give the contractor a notice in writing about the defects and the contractor shall make
good the same within 15 days of receipt of the notice. In the case of failure on the part of
the contractor, the Engineer- in-charge may rectify or remove or re-execute the work at
the risk & cost of the contractor. The Engineer-in-charge shall be entitled to appropriate
the whole or any part of the amount of security deposit towards the expenses, if any,
Incurred by him in rectification, removal or re-execution. The Defects Liability period
shall be as under….
(a) For all works costing up to Rs. 50,000 (amount put to tender), the period shall be
Months from the certified date of completion.
(b) For all works costing more than Rs. 50,000 and up to Rs. 1 crore (amount put tender),
the period shall be 36 (Thirty Six) months from the certified date of completion or one
monsoon, whichever is later.
(c) For major projects costing more than Rs. 1 crore, the period shall be 36 Months from
the certified date of completion which should include three monsoons.
(d) For original building works the defect liability period will be 4 years or elapse of
monsoon period following date of possession of building taken over by user agency
following the certified date of completion, whichever is later.
For the purpose of deciding the monsoon period, the 30th September shall be treated as
Modified vide R & B D Circular No. PAC-11-102008-2076-N dated 31/8/2009,
PRCH/102013(2976) 2759-N, Dated 27/05/2013 and Circular No.TNC/10/2016/Clause
17A (Correction/(1)C Dated 12/05/2016]
33.2 Free maintenance guarantee period for works of Road/Bridge construction
(a) For resurfacing work of road free maintenance guarantee period one year from the
date of completion.
(b) In case of widening of the road/strengthening of the road/bridge, the contractor
shall have to give four years free maintenance guarantee from the certified date of
completion. During this period the contractor shall visit the site every six months
along with the concerned Section Officer / Deputy Chief Officer and will examine the
work already carried out in this contract like road work, jungle cutting, side
shoulders, side gutter, road furniture, patta etc. and will prepare Km. wise inspection
report duly signed by all concerned and any defect observed shall be done within
days by the contractor at his risk and cost as per the direction of Engineer in charge.
The contractor needs to do videography of these visits and require to submit at the
time of release of FMG. If B.T. the surface during the maintenance period of 4 years
is worn out then agency shall have to provide renewal coating as per tender item as
directed by the Engineer-in- charge. The amount equivalent to 5% of each running
bill shall be withheld and will be released after the free maintenance guarantee
period (i.e. 4 years) is over.
However, this amount shall be released against fixed deposit or bank guarantee
pledged in the name of Chief Officer after completion certificate of work is issued.
(1) The flakiness and elongation index (combined) for coarse aggregates under no
circumstances shall exceed the allowable limit set forth in the relevant clause for the
material in question.
(2) 2% of the amount eligible for the payment of bituminous items shall be withheld till
the miscellaneous items like earthwork in embankment / cutting for side shoulders,
side gutters, kilometer / indicator / guard stones, sign boards etc. are completed in
all respect by the contractor. After completion of the miscellaneous items, the above
said 2% withheld amount shall be released.
(Govt. of Gujarat's G.R. No.: TNC-10-2013-3(Part-3)/C, Dtd. 13/12/2013).
(3) Videography for the surface under Maintenance Guarantee is to be done as per Govt.
letter No.: SSR/10/2015-16/26/C, Dtd. 26/11/15 for the work costing more than Rs.
(4) Setting up of adequate laboratory & deployment of quality engineers.
The contractor shall have to set up the laboratory with adequate equipment. Till the
setting up of adequate laboratory is completed & reported of this to the engineer
(subject to due verification by engineer’s representative) by contractor in writing,
Rs.2,00,000/- shall be withheld. The qualified quality Engineer shall be deployed
exclusively for this contract by the contractors. If quality Engineer is not deployed by
contractor within one month after the date of work order, the amount equivalent to
Rs.20,000 per month shall be recovered till the actual deployment of quality
engineer. The amount so recovered towards the deployment of quality engineers
shall not be refunded.
(5) Asphalt work will have to be cross checked as per G.R. No.: RGN/60/2006/35/C,
dtd.31/05/07 before final bill is paid.
(6) Maintenance during Construction Period
During the Construction Period, the Contractor shall maintain, at his own risk and
cost, the existing lane(s) of the road so that the traffic worthiness and safety thereof
are at no time materially inferior as compared to their condition 10 (ten) days prior
to the date of the Agreement, and shall undertake the necessary repair and
maintenance works for this purpose; provided that the Contractor may, at his cost,
interrupt and divert the flow of traffic if such interruption and diversion is necessary
for the efficient progress of works and conforms to Good Industry Practice;
provided further that such interruption and diversion shall be undertaken by the
Contractor only with the prior written approval of the Chief Officer which approval
shall not be unreasonably withheld. For the avoidance of doubt, it is agreed that the
Contractor shall at all times be responsible for ensuring safe operation of the road.
33.3 The Engineer shall check the Contractor’s work and notify the Contractor of any defects
that are found. Such checking shall not affect the Contractor’s responsibilities the
Engineer may instruct the Contractor to search for a Defect and to uncover and test any
work that the Engineer considers may have a Defect.
34.1 If the engineer instructs the Contractor to carry out a test not specified in the
Specification to check whether any work has a Defect and the test shows that it does, the
Contractor shall pay for the test and any samples. If there is no defect the test shall be a
Compensation Event.
34.2 #1% of the amount of work done should be deducted from R.A. Bill of the contractor for
testing the quality of material workmanship, irrespective of actual charges.
34.3 Agency has to establish testing laboratory on site for the various test to be carried out in
the work for this purpose agency shall construct a pukka laboratory building with all
facility on site at location specified by the engineer in charge.
35. Correction of defects
35.1 The engineer shall give notice to the Contractor of any defects before the end of the
defects Liability Period, which begins at Completion and is defined in the contract data.
The Defects Liability Period shall be extended for as long as Defects remain to be
35.2 Every time notice of a Defect is given, the Contractor shall correct the notified defect
within the length of time specified by the Engineer’s notice.
36. Uncorrected Defects
36.1 If the Contractor has not corrected a defect within the time specified in the Engineer’s
notice, the Engineer will assess the cost of having the Defect corrected, and the
Contractor will pay this amount.
D. COST CONTROL
37. Bill of Quantities
37.1 The bill of Quantities shall contain items for the constructions, installation, testing
and commissioning work to be done by the Contractor.
37.2 The bill of Quantities is used to calculate the Contract price. The Contractor is paid for
the quantity of the work done at the rate in the Bill of Quantities for each item.
38. Change in the Quantities
38.1 The Engineer shall have power to make any alterations in or addition to the original
specifications , drawings, designs and instructions that may appear to him to be
necessary or advisable during the progress of the work and the contractor shall be bound
to carry out the work in accordance with any instruction in this connection which may be
given to him in writing signed by the Engineer and such alteration shall not invalidate the
contract and any additional work which the contractor may be directed to do in the
manner above specified as part of the work shall be carried out by the contractor on the
same conditions in all respects on which he agreed to do the main work and at the same
rate as are specified in the tender for the main work.
Except that when the quantity of any item exceeds the quantity as in the tender by more
than 10%, the contractor will be paid for the quantity in excess of 10%, at the rate
entered in the SOR of the year during which the excess in quantity is first executed.
39.1 All Variations shall be included in updated programmes produced by the Contractor.
40. Payments for Variations
40.1 If the additional or altered work includes any class of work for which no rate is specified
in this contract, then such class of work shall be carried out as under.
(i) At the rate derived from the item within the contract which is comparable to the one
involving additional or altered class of work; where there are more than one comparable
items, the item of the contract which is nearest in comparison with regard to class or
classes of the work involved shall be selected and the decision of the Chief Officer as to
the nearest comparable item shall be final and binding on the contractor.
(ii) If the rate cannot be derived in accordance with (i) above, such class of works shall be
carried out at the rate entered in the Schedule of Rates of the division for the year in
which the tender was received, increased or decreased by the percentage by which the
tender amount is more or less as compared to the amount arrived at the rates in the
“Schedule of Rates” of the Division in the year in which the tender was received. If the
Schedule of rates of the Division does not contain all the items, the percentage increase
or decrease of the tender shall be calculated considering such items which were included
in the “Scheduled Rates” of the division for the year and for materials consumed on such
item the rate to be charged would be the basic rate taken into account for fixing the rate
in S.O.R. referred to above.
(iii) If it is not possible to arrive at the rate from (i) and (ii) above, such class of work shall be
carried out at the rate decided by the competent authorities on the basis of detailed rate
analysis after hearing the contractor before a Committee of two Chief Officers stationed
at the same place or the nearest place.
40.2 If the additional or altered work, for which no rate is entered in the “Schedule of Rates”
of the Division is ordered to be carried out before the rate is agreed upon, then the
contractor shall within seven days of the date of receipt by him of the order to carry out
the work, inform the Engineer-in-charge of the rate, which it is his intention to charge for
such class of work and if the Engineer in charge does not agree to this rates, he shall by
notice in writing be at liberty to cancel his order to carry out such class of work and
arrange to carry it out in such manner as he may consider it advisable, provided always
that if the contractor shall commence work or incur any expenditure in regard thereof
before the rates shall have been determined as lastly herein before mentioned, then in
such cases he shall only be entitled to be paid in respect of the work carried out or
expenditure incurred by him prior to the date of the determination of the rate as
aforesaid according to such rate or rates as shall be fixed by the Engineer-in-charge. In
the event of the dispute, the decision of the Chief Officer of the Circle shall be final.
Where, however, the work is to be executed according to the designs, drawings
and specifications recommended by the contractor and accepted by the competent
authority, the alternation above referred to shall be within the scope of such designs,
drawings and specifications appended to the tenders.
The time limit for the completion of the work shall be extended in the proportion
that the increase in the cost occasioned by alterations bears to the cost of the original
work and the certificate of the Engineer-in-charge as to such proportion shall be final and
41. Cash Flow Forecasts
41.1 When the programme is updated, the contractor is to provide the engineer with an
updated cash flow forecast.
42. Payment certificates.
42.1 The Contractor shall submit to the Engineer monthly statements of the estimated value
of the work completed less the cumulative amount certified previously.
42.2 The Engineer shall check the Contractor’s monthly statement within 14 days and certify
the amount to be paid to the Contractor after taking in to account any credit or debit for
the month in question in respect of materials for the works in the relevant amounts and
under conditions set forth in sub-clause
32.3 of the Contract Data (secured Advance).
42.3 The value of work executed shall be determined by the Engineer.
42.4 The value of work executed shall comprise the value of the quantities of the items in the
Bill of Quantities completed.
42.5 The value of work executed shall include the valuation of variations and compensation
42.6 The Engineer may exclude any item certified in a previous certificate or reduce the
proportion of any item previously certified in any certificate in the light of later
43.1 Payments shall be adjusted for deductions for advance payments, retention, other
recoveries in terms of the contract and taxes at source, as applicable under the law. The
Employer shall pay the Contractor the amounts certified by the Engineer within 28 days
of the date of each certificate.
43.2 Payment of GST (prevailing rates) on the amount payable under the contract to the
Contractor will be made by the Employer. Hence, it is the responsibility of the contractor
to pay the GST to the concerned Authority.
43.3 Items of the works for which no rate or price has been entered in will not be paid by the
Employer and shall be deemed covered by other rates and prices in the Contract.
44. Compensation events
44.1 The following are compensation Events unless they are caused by the Contractor:
(a) The Employer does not give access to a part of the Site by the site Possession
date stated in Contract data to the Contractor
44.2 In case of compensation event occurs and it prevents the work being completed beyond
the Intended Completion Date then Authority will approve EOT with eligible contractual
price escalation.
45.1 The rates quoted by the Contractor must be inclusive of all taxes prevailing on due date
of bid submission except GST. However, any subsequent changes in the tax structure by
Government after due date of bid submission will be compensated (+/-) on availability or
submission of actual documentation. Contractor will have to intimate Engineer regarding
changes occurred in the tax structure after bid submission. If the contractor fails to
provide such information and if any financial obligation may arise due to change in tax
structure, same will be recovered from the contractor.
45.2 GST will be paid separately on the bills. Hence, it is the responsibility of the contractor to
pay the GST to the concerned Authority.
46. Currencies.
46.1 All payment shall be made in Indian Rupees.
47. Price Adjustment
47.1 Contract price shall be adjusted for increase or decrease in rates and price of labour,
materials, fuels and lubricants in accordance with the following principles and
procedures and as per formula given in the contract data:
(a) The price adjustment shall apply for the work done from the start date given in the
contract data up to end of the initial intended completion date or extensions granted
by the Engineer and shall not apply to the work carried out beyond the stipulated
time for reasons attributable to the contractor.
(b) The price adjustment shall be determined during each month from the formula given
in the contract data.
(c) Following expressions and meanings during to the work done during each month
R = Total value of work done during the month. It would include the amount of
secured advance granted, if any, during the month less the amount of secured
advance recovered, if any during the month. It will exclude value for works executed
under variations for which price adjustment will be worked separately based on the
terms mutually agreed.
47.2 To the extent that full compensation for any rise or fall in costs to the contractor is not
covered by the provisions of this or other clause in the contract, the unit rates and prices
included in the contract shall be deemed to include amounts to cover the contingency of
such other rise or fall in costs.
48.1 The Employer shall retain from each payment due to Contractor the proportion stated in
the Contract Data until Completion of the whole of the Works.
48.2 On Completion of the whole of the Works half the total amount retained is repaid to the
48.2 On Completion of the whole of the Works half the total amount retained is repaid to the
Contractor and half when the Defects Liability Period has passed and the Engineer has
certified that all Defects notified by the Engineer to the Contractor before the end of this
period have been corrected.
48.3 On completion of the whole works, the contractor may substitute retention money with
an “on demand” Bank guarantee.
In case, Contractor requests for refund of the Retention Money deducted by the
Employer under the provision of this clause, Employer shall consider the said request of
the Contractor provided that the refund hereunder shall be made in tranches of not less
than 1% (One Percent) of the Contract Price and Contractor furnishes an irrevocable and
unconditional Bank guarantee for an equal amount substantially in the format of Bank
Guarantee for Performance Guarantee enclosed with SBD and valid up to 60 day beyond
the scheduled / extended Defects Liability Period. On completion of the whole works, the
contractor has however an option to submit a fresh irrevocable and unconditional Bank
Guarantee for an amount equal to 5% of the total value of work executed substantially in
the format of Bank Guarantee for Performance Guarantee enclosed with SBD and valid
up to 60 days beyond the Defect Liability Period and yet refund the Retention Money
Bank Guarantee submitted for refund of Retention Money.
49. Liquidated Damages
49.1 The Contractor shall pay liquidated damages to the Employer at the rate per day stated
in the Contract Data for each day that the Completion Date is later than the Intended
Completion Date (for the whole works or the milestone as stated in the contract data).
The total amount of liquidated damages shall not exceed the amount defined in the
The total amount of liquidated damages shall not exceed the amount defined in the
Contract Data. The Employer may deduct liquidated damages from payment due to the
Contractor. Payment of liquidated damages does not affect the Contractor’s liabilities.
49.2 If the Intended Completion Date is extended after liquidated damages have been paid,
the Engineer shall correct any overpayment of liquidated damages by the Contractor by
adjusting the next payment certificate. The Contractor shall not be entitled for any
interest on the over payment calculated from the date of payment to the date of
49.3 If the contractor fails to comply with the time for completion as stipulated in the tender,
then the contractor shall pay to the employer the relevant sum stated in the Contract
Data as Liquidated damages for such default and not as penalty for everyday or part of
day which shall elapse between relevant time for completion and the date stated in the
taking over certificate of the whole of the works on the relevant section, subject to the
limit stated in the contract data.
The employer may, without prejudice to any other method of recovery deduct
the amount of such damages from any monies due or to become due to the contractor.
The payment or deduction of such damages shall not relieve the contractor from his
obligation to complete the works on from any other of his obligations and liabilities
under the contract.
49.4 If, before the Time for Completion of the whole of the Works or, if applicable any
Section, a Taking Over Certificate has been issued for any part of the Works or of a
Section, the liquidated damages for delay in completion of the remainder of the Works
or of that Section shall, for any period of delay after the date stated in such Taking-Over-
Certificate, and in the absence of alternative provisions in the Contract, be reduced in the
proportion which the value of the part so certified bears to the value of the whole of the
Works or Section, as applicable. The provisions of this Sub-clause shall only apply to the
rate of liquidated damages and shall not affect the limit thereof.
50.1 If the contractor achieves completion of the whole of the works prior to the intended
Completion Date prescribed in Contract Data the Employer shall pay to the contractor a
sum stated in Contract Data as bonus for every completed month but subjected to
maximum amount as stated in Contract Data; which shall elapse between the date of
completion of all items of works as stipulated in the contract, including variations
ordered by the Engineer and the time prescribed in Clause
50.2 Bonus shall be paid only to works amounting to above INR 5 crore with time limit of the
works is equal or more than 6 months. The bonus would be paid as under
% of Time Saved % of Initial Contract Price
entitled for Bonus
Less than 10% 0%
51. Advance Payment.
51.1 The Employer shall make advance payment (not to be paid less than two installments
except in special circumstances for which the reason to be Recorded in writing) to the
Contractor of the amounts stated in the Contract Date by the date stated in the Contract
Date, against provision by the Contactor of an Unconditional Bank Guarantee in a form
and by a bank acceptable to the Employer in amounts and currencies equal to be at least
110% of the advance payment. The guarantee shall remain effective until the advance
payment has been repaid, but the amount of the guarantee shall be progressively
reduced by the amounts repaid by the Contractor. The Mobilization advance would be
deemed as interest bearing advance at an interest rate of 10 % to be compounded,
51.2 The Contractor is to use the advance payment only to pay for Equipment, plant and
Mobilization expenses required specifically for execution of the Works. The Contractor
shall demonstrate that advance payment has been used in this way by supplying copies
of invoices or other documents to the engineer.
51.3 The advance payment shall be repaid by deduction proportionate amount from
payments otherwise due to the Contractor, following the schedule of completed
percentages of the Works on a payment basis. No account shall be taken of the advance
payment or its repayment in assessing valuations of work done, variations, price
adjustments, Compensation Events, or Liquidated damages.
51.4 Secured Advance
The Engineer shall make advance payment in respect of materials intended for but not yet
incorporated in the works in accordance with conditions stipulated in the contract Data.
52.1 The performance Security (including additional security for unbalanced bids) shall be
provided to the Employer no later than the date specified in the Letter of Acceptance
and shall be issued in an amount and form and by a bank or surety acceptable to the
Employer, and denominated in Indian Rupees. The performance Security shall be valid
until a date 60 days from the date of expiry of Defects Liability Period and the additional
security for unbalanced bids shall be valid until a date 28 days from the date of issue of
the certificate of completion.
54. Cost of Repairs.
54.1 Loss or damage to the Works or Materials to be incorporated in the Works between the
Start date and the end of Defects Correction periods shall be remedied by the Contractor
at the Contractor’s cost if the loss or damages arises from the Contractor’s acts or
E. FINISHING THE CONTRACT
55.1 The Contractor shall request the Engineer to issue a Certificate of Completion of the
works and the Engineer will do so upon deciding that the work is completed.
56. Taking Over
56.1 The Employer shall take over the Site and the Works within seven days of the Engineer
issuing a certificate of Completion.
57. Final Account
57.1 The Contractor shall supply to the Engineer a detailed final account of the total amount
57.1 The Contractor shall supply to the Engineer a detailed final account of the total amount
that the Contractor considers payable as full and final settlement of all claims under the
Contract for items before the end of the Defects Liability Period. The Engineer shall issue
a Defect Liability Certificate and certify any final payment that is due to the Contractor
within 56 days of receiving the Contractor's account if it is correct and complete. If it is
not, the Engineer shall issue within 56 days a schedule that states the scope of the
corrections or additions that are necessary. If the Final Account is still unsatisfactory after
it has been resubmitted, the Engineer shall decide on the amount payable to the
Contractor and issue a payment certificate, within 56 days of receiving the Contractor’s
revised account.
57.2 If reversal in characteristic of tender (L1 becoming L2) on account of excesses and savings
in final account is observed, the Engineer/Employer shall be at liberty to restrict the final
payment of BOQ items to the lowest amount evaluated of the bids considering the final
quantities and the rates quoted including the rebates if any. Payment of variation items
shall however be made at the rates approved by the Employer, within 90 days from the
physical completion of work.
58. Operating and Maintenance Manuals
58.1 If “as built” drawings and/or operating and maintenance manuals are required, the
Contractor shall supply them by the dates stated in the Contract data.
58.2 If the Contractor does not supply the Drawings and/or manuals by the dates stated in the
Contract data, or they do not receive the Engineer’s approval, the Engineer shall withhold
the amount stated in the Contract Data from payments due to the Contractor.
59. Termination
59.1 The Employer or the Contractor may terminate the Contract if the other party causes a
fundamental breach of the Contract.
59.2 Fundamental breaches of Contract include, but shall not be limited to the following:
1. The contractor stops work for 28 days when no stoppage of work is shown on the
current programme and the stoppage has not been authorized by the Engineer
2. The Engineer instructs the Contractor to delay the progress of the Works and the
instructions is not withdrawn within 28 days;
3. The Employer or the Contractor is made bankrupt or goes into liquidation other than
for a reconstructions or amalgamation
4. A payment certified by the Engineer is not paid by the Employer to the Contractor
within 56 days of the date of the Engineer’s certificate
5. The Engineer gives Notice that failure to correct a particular Defect is a fundamental
breach of Contract and the Contractor fails to correct it within a reasonable period
of time determined by the Engineer;
6. The Contractor does not maintain a security which is required;
7. The Contractor has delayed the completion of works by the number of days for
which the maximum amount of liquidated damages can be paid as defined in the
Contract data; and
8. If the Contractor, in the judgment of the Employer has engaged in corrupt or
fraudulent practices in competing for or in executing the Contract.
For the purpose of this paragraph: “corrupt practice” means the offering, giving,
receiving or soliciting of anything of value to influence the action of a public official in the
procurement process or in contract execution. “Fraudulent practice” means a
misrepresentation of facts in order to influence a procurement process or the execution
of a contract to the detriment of the borrower, and includes collusive practice among
Bidders (prior to or after bid submission) designed to establish bid prices at artificial non-
competitive levels and to deprive the Borrower of the benefits of free and open
59.3 When either party to the Contract gives notice of a breach of contract to the Engineer for
a cause other than those listed under Sub Clause 59.2 above, the Engineer shall decide
whether the breach is fundamental or not.
59.4 Notwithstanding the above, the employer may terminate the Contract for convenience.
60. Payment upon Termination
60.1 If the Contract is terminated because of a fundamental breach of Contract by the
Contractor, the Engineer shall issue a Certificate for the value of the work done less
advance payments received up to the date of the issue of the certificate, less
other recoveries due in terms of the contract, less taxes due to deducted at source as per
applicable law and less the percentage to apply to the work not completed as indicated
in the Contract data. Additional Liquidated Damages shall not apply. If the total amount
in the Contract data. Additional Liquidated Damages shall not apply. If the total amount
due to the Employer exceeds any payment due to the Contractor the difference shall be
a debt payable to the Employer.
60.2 If the Contract is terminated at the Employer’s convenience or because of a fundamental
breach of Contract by the Employer, the Engineer shall issue a certificate for the value of
the work done, the cost of balance material brought by the contractor and available at
site, the reasonable cost of removal of equipment, repatriation of the Contractor’s
personnel employed solely on the works, and the Contractor’s cost of protecting and
securing the Works and less advance payment received up to the date of the certificate,
less other recoveries due in terms of the contract and less taxes due to deducted at
source as per applicable law.
61.1 All materials on the Site, Plant Equipments, Temporary Works and Works are deemed to
be property of the Employer, if the Contract is terminated because of a Contractor’s
62. Release from Performance
62.1 If the Contract is frustrated by the outbreak of war of by any other event entirely outside
the control of either the Employer or the Contractor the Engineer shall certify that the
Contract has been frustrated. The Contractor shall make the Site safe and stop work as
quickly as possible after receiving this certificate and shall be paid for all work carried out
before receiving it and for any work carried out afterwards to which commitment was
F. SPECIAL CONDITIONS OF CONTRACT
The Contractor shall, unless otherwise provided in the Contract, make his own
arrangements for the engagement of all staff and labour, local or other, and for their
payment of housing, feeding and transport.
The Contractor shall, if required by the Engineer, deliver to the Engineer a return
in detail, in such form and at such intervals as the Engineer may prescribe, showing the
staff and the numbers of the several classes of labour from time to time employed by the
Contractor on the site and such other information as the Engineer may require.
64. COMPLIANCE WITH LABOUR REGULATIONS
During continuance of the contact, the Contractor and his sub- contractor shall
abide at all times by all existing labour enactments and rules made thereunder,
regulations, notification and bye laws of the State or central Government or local
authority and any other labour law (including rules), regulations, bye laws that may be
passed or notifications that may be issued under any labour law in future either by the
State or the Central Government or the local authority. Salient features of some of the
major labour laws that are applicable to the construction industry are given below. The
Contractor shall keep the Employer indemnified in case any action is taken against the
Employer by the competent authority on account of contravention of any of the
provisions of any Act or rules made thereunder, regulations or notifications including
amendments. If the Employer is caused to pay or reimburse, such amounts as may be
necessary to cause or observe, or for observance of the provisions stipulated in the
notifications/bye laws/Acts/Rules/regulations including amendments, if any, on the part
of the Contractor, the Engineer/employer shall have the right to deduct any money due
to the Contractor including his amount of performance security. The Employer/Engineer
shall also have the right to recover from the Contractor any sum required or estimated to
be required for making good the loss or damage suffered by the Employer.
The employees of the Contractor and the Sub-Contractor in no case shall be treated as
the employees of the Employer at any point to time.
SALIENT FEATURES OF SOME MAJOR LABOUR AND OTHER LAWS APPLICABLE TO
ESTABLISHMENTS ENGAGED IN BUILDING AND OTHER CONSTRUCTIONS WORK
A) Workmen Compensation Act 1923 :- The Act provides for compensation in case of injury by
accident arising out of and during the course of employment.
B) Payment of Gratuity Act. 1972 :- Gratuity is payable to an employee under the Act on
satisfaction of certain conditions on separation if an employee has completed 5 years service
or more on death, the rate of 15 days wages for every completed year of service. The Act is
applicable to all establishments employing 10 or more employees.
C) Employees P.F. and Miscellaneous Provision Act 1952:- The Act Provides for monthly
contributions by the employer plus workers @ 10% or 8.33% The benefits payable under the
1. Pension or family pension on retirement or death, as the case may be.
2. Deposit linked insurance on the death in harness of the worker.
3. Payment of P.F. accumulation on retirement/death etc.
D) Maternity Benefit Act 1951 :- The Act provides for leave and some other benefits to women
employees in case of confinement or miscarriage etc.
E) Contract Labour (Regulation & Abolition) Act 1970 : The Act provides for certain welfare
measures to be provided by the Contractor to contract labour and in case the Contractor fails
to provide, the same are required to be provided, by the Principal Employer by Law. The
principal Employer is required to take Certificate of Registration and the Contractor is
required to take license from the designated Officer. The Act is applicable to the
establishments or Contractor of Principal Employer, if they employ 20 or more contract
F) Minimum Wages Act 1948 :- The Employer is supposed to pay not less than the Minimum
Wages fixed by appropriate Government as per provisions of the Act, if the employment is a
scheduled employment. Construction of Building, Roads, Runways are scheduled
G) Payments of wages Act 1936:- It lays down as to by what date the wages are to be paid,
when it will be paid and what deductions can be made from the wages of the workers.
H) Equal remunerations Act 1979 :- The Act provides for payment of equal wages for work of
equal nature to Male and Female workers and for not making discrimination against female
employees in the matter of transfer, training and promotions etc.
I) Payments of Bonus Act 1965 :- The Act is applicable to all establishments employing 20 or
more employees. The Act provides for payments of annual bonus subject to a minimum of
8.33% of wages and maximum of 20 % of wages to employees drawing Rs. 3500/- per
month or less. The bonus to be paid to employees getting Rs, 2500/- per month or above Rs.
3500/- per month shall be worked out by taking wages as Rs. 2500/- per month only.
The Act does not apply to certain establishments. The newly set-up establishments are
exempted for five years in certain circumstances. Some of the State Governments have
reduced the employment size from 20 to 10 for the purpose of applicability of this Act.
J) Industrial Disputes Act 1947 :- The Act lays down the machinery and procedure for
resolutions of Industrial disputes, in what situations a strike or lock-out becomes illegal and
what are the requirements for laying off or retrenching the employees or closing down the
K) Industrial employment (standing Orders) Act 1946 :- It is applicable to all establishments
employing 100 or more workmen (employment size reduced by some of the State and
Central Government to 50). The Act provides for laying down rules governing the conditions
of employment by the Employer on matters provided in the Act and get the same certified
by the designated Authority.
L) Trade Unions Act 1926:- The Act lays the procedure for registration of trade unions of
workmen and employers. The Trade Unions registered under the Act have given certain
immunities from civil and criminal liabilities.
M) Child Labour (Prohibition & Regulation Act 1986 :- The Act prohibits employment of
children below 14 years of age in certain occupations and process and provides for
regulation of employment of children in all other occupations and processes. Employment
of Child labour is prohibited in Building and Construction Industry.
N) Inter – State Migrant workmen’s (Regulation of Employment & Conditions of service) Act
1979:- The Act is applicable to an establishment which employs 5 or more inter-state
migrant workmen through an intermediary (who has recruited workmen in one state for
employment in the establishment situated in another state).The inter-state migrant
workmen, is an establishment to which this Act becomes applicable, are required to be
provided certain facilities such as housing, medical aid, traveling expenses from home upto
the establishment and back, etc.
O) The Building and Other Construction workers (Regulation of employment and Conditions
of Service) Act 1996 and the Cess Act of 1996:- All the establishments who carry on any
building or other constructions work and employ 10 or more workers are covered under this
All such establishments are required to pay cess at the rate not exceeding 2% of the cost of
construction as may be modified by the government. The Employer of the establishment is
required to provide safety measures at the Building or construction work and other welfare
measures, such as canteens, First Aid facilities, Ambulance, Housing accommodations for
workers near the workplace etc. The Employer to whom the Act applies has to obtain a
registration certificate from the Registering Officers appointed by the Government.
P) Factories Act 1948 :- The Act lays down the procedure for approval of plans before setting
up a factory, health and safety provisions, welfare provisions, working hours, annual earned
leave and rendering information regarding accidents or dangerous occurrences to
designated authorities. It is applicable to premises employing 10 persons or more with aid
of power or 20 or more persons without the aid of power engaged in the manufacturing
Q) Royalty charges-The contractor shall pay the royalty to the competent authority as per rule.
The royalty charges paid shall be borne by the contractor and shall not be reimbursed by
R) Following Pollution control Acts and amendments made thereof from time to time shall
1. Water (Preservation and control of Pollution) Act,
2. Air (Prevention and Control of Pollution Act
3. Environmental (Protection) Act
The contractor must commit to adopting Environmental management plan for best
energy use, waste management, the reduction of pollution as in EMS (Environmental
Management system)ISO-14001-
65. ARBITRATION (GCC Clause 24)
The procedure for arbitration will be as follows: -
24.1 If the Contractor is of the view that a decision taken by the Engineer was either outside
the authority given to the Engineer by the Contract or that the decision was wrongly
taken, the decision shall be referred to #Chief Officer (Higher Authority) within 14 days of
the notification of the Engineer's decision. If the issue is not resolved, any party can refer
the matter for conciliation within 15 days from the decision given by the #Chief Officer.
(a) For the work up to Rs.100 Cr., if any of the parties is not satisfied with the decision of
the #Chief Officer, both the parties have to refer to the # Regional Commissioner
Municipality concerned for the conciliation process.
(b) For the work more than Rs.100 Cr., if any of the parties is not satisfied with the
decision of the Chief Officer, both parties have to refer to the #ACEO GUDM,
Gandhinagar for the conciliation process.
If the dispute is not resolved through the conciliation process, contractor may
refer the dispute to Gujarat Public Works Contract Dispute Arbitration Tribunal. If the
Contractor fails to refer a claim / dispute to the Higher Authority within 14 days of
the notification of the Engineer's decision, the Contractor shall not be entitled to any
additional payment/claim if he doesn’t follow the above sequence in stipulated time.
However, during such period, he would not stop the work in any case.
Item marked “N/A” do not apply to this Contract. Clause Reference With respect
1. The Employers is [CL.1.1]
Name : Chief Officer LIMBADI Nagarpalika
Address: Nagar Seva Sadan – LIMBADI Pasvari rod, Di. Porbaandar
Name of authorized Representative (will be intimated later)
2. The Engineer is ………………………
Name of Authorized Representative: …………………………
3. The Defects Liability Period is 3 years from the date of [CL.1.1&33]
4. The Start Date shall be 1st days for the date of issue of the Notice to proceed [CL.1.1]
5. The Intended Completion Date for the whole of the works is [CL.1.1,17&2]
12 Months after start of work with the following milestones:
Milestone dates: [CL.2.2& 49.1]
Physical works to be completed Period from the start date
Percentage of work
Mile stone Time Time in days
6. The Site is located at LIMBADI town [CL.1.1]
7. The name and identification number of the Contract is: [CL.1.1]
8. The works consist of Designing, providing, supplying, lowering, laying & jointing sewer [CL.1.1]
collecting system including house connection work, along with all allied Electro-
Mechanical works Including Operation & Maintenance of 2 Years for sewage Network
and allied works under _____ Scheme for project, District : LIMBADI with items as
per B.O.Q. The works shall, inter alia, include the following, as Specified or as
Any Other Items as required to fulfill all contractual obligations as per the Bid documents.
10. The following documents also form part of the Contract [CL.2.3(9)]
11. The law which applies to the Contract is the law of Union of India [ CL.3.1]
12. The language of the Contract documents is English [CL.3.1]
13. Limit of subcontracting [CL.3.1]
14. The Schedule of Other Contractors [CL.8]
15. The Schedule of Key Personnel As per Annex – II to Section I [CL.9]
16. The minimum insurance cover for physical property, injury and death is Rs. 5 lakhs per [CL.13]
occurrence with the number of occurrences limited to four. After each occurrence, the
contractor will pay an additional premium necessary to make insurance valid for four
occurrences always.
17. Site Investigation report [CL.14]
18. The Site Possession dates shall be…………………………. [CL.21]
19. The period for submission of programme for approval of the engineer shall be 21 days [CL.27.1]
from the issue of Letter of Acceptance.
20. The period between program updates will be 90 days. [CL27.30]
21. The amount to be withheld for late submission of an updated programme shall [CL.27.30]
be Rs One (1) lakhs.
22. The following events shall also be Compensation Events [CL.44]
Substantially adverse ground conditions encountered during the
course of execution of work not provided for in the bidding document.
(i) Removal of underground utilities detected subsequently.
(ii) Significant changes in classification of soil requiring additional mobilization by
the contractor, e.g. ordinary soil to rock excavation.
(iii) Removal of unsuitable material like marsh, debris dumps, etc. not caused by the
(iv) Artesian condition
(v) Seepage, erosion landslide
(vi) River training requiring protection of permanent work
(vii) Presence of historical, archeological or religious structures, monuments
interfering with the works.
23. The currency of the Contract is Indian Rupees [CL. 46]
24. The formula (e) for adjustment of prices are as under: [CL.47]
If any of the commodities like Cement, Steel or Bitumen are not found
applicable in a work, the weight component of that commodities {i.e.
‘Cement’ (Pc), ‘Steel’ (Ps) or ‘Bitumen' (Pb) as indicated in SBD for the
purpose of Price Adjustment} shall be clubbed with the weight
component of ‘Other Material’ (Pm), such that the gross % weight of
the components shall remain as 100% .
R = value of work as defined in Clause 47.1 of Conditions of Contract
Adjustment for labour component
(i) Price adjustment for increase or decrease in the cost due to
labour shall be paid in accordance with the following formula:
VL = Increase or decrease in the cost of work during the month
under consideration due to changes in rates for local
L0 = The consumer price index for industrial workers for the State
on 28 days preceding the scheduled date of opening of
technical Bids as published by Labour Bureau, Ministry of
Labour, Government of India
Li = The consumer price index for industrial workers for the State
for the month under consideration as published by the
Labour Bureau, Ministry of Labour, Government of India.
Pl = Percentage of labor component of the work.
Adjustment for cement component.
(ii) Prices adjustment for increase or decrease in the cost of
cement procured by the contractor
Vc = Increase or decrease in the cost of work during the
month under consideration due to changes in rates for
C0 = The all India wholesale price index for Ordinary Portland
Cement on 28 days preceding the scheduled date of
opening of technical bid as published by the Office
of the Economic Adviser,
Department for Promotion of Industry and Internal Trade,
Ministry of Commerce & Industry.
Ci = The all India average wholesale price index for Ordinary
Portland Cement for the month under consideration as
published by Office of the Economic Adviser, Department for
Promotion of Industry and Internal Trade, Ministry of
Commerce & Industry.
Pc = Percentage of cement component of the work
Adjustment for steel component
(iii) Price adjustment for increase or decrease in the cost of steel procured by the
contractor shall be paid in accordance with the following formula
Vs= Increase or decrease in the cost of work during the month under consideration
due to changes in the rates for steel
So= The all India wholesale price index for steel (Mild Steel - Long Products Rebars)
on 28 days preceding the date of opening of Bids as published by the Office of the
Economic Adviser, Department for Promotion of Industry and Internal Trade,
Ministry of Commerce & Industry.
Si= The all India average wholesale price index for steel (Mild Steel - Long Products
Rebars) for the month under consideration as published by Office of the
Economic Adviser, Department for Promotion of Industry and Internal Trade,
Ministry of Commerce & Industry.
Ps = Percentage of steel component of the work
Note : For the application of this clause, the index of Mild Steel- Long products
Rebars has been chosen to represent the steel group.
Adjustments of bitumen component
(iv) Price adjustment for increase in the cost of bitumen shall be paid in
accordance with the following formula
Vb = Increase or decrease in the cost of work during the month under
consideration due to changes in rates for bitumen.
Bo = The official retail price of bitumen at the IOC depot at the nearest
centre on the day 28 days prior to the scheduled date of opening of
Bi = The official retail price of bitumen of IOC depot at the nearest centre
for the 15th day of the month under consideration.
Pb = Percentage of bitumen component of the work
Adjustment of POL (fuel and lubricant) component
(v) Price adjustment for increase or decrease in cost of POL (fuel and
lubricant) shall be paid in accordance with the following formula
Vf = Increase or decrease in the cost of work during the month under
consideration due to changes in rates for fuel and lubricants.
Fo = The official retail price of High Speed Diesel (HSD) at the existing
consumer pumps of IOC at the nearest centre on the day 28 prior to the
date of opening of Bids.
Fi = The official retail price of HSD at the existing consumer pumps of IOC
at the nearest centre for the 15th day of the month of the under
Pf = Percentage of fuel and lubricants component of the work
Note: For the application of this clause, the price of High-Speed diesel Oil has
been chosen to represent the fuel and lubricants group.
Adjustment for Construction Machinery
(vi) Price adjustment for increase or decrease in the cost of plant and
Machinery spare procured by the Contractor shall be paid in accordance
with the following formula
Vp= Increase or decrease in the cost of work during the month under
consideration due to changes in rates for plant and machinery spares
P0 = The all India wholesale price index for manufacturer of machinery for
mining, quarrying and Construction for the month under consideration as
published Office of the Economic Adviser, Department for Promotion of
Industry and Internal Trade, Ministry of Commerce & Industry.
Pi = The all India average wholesale price index for manufacturer of
machinery for mining, quarrying and Construction for the month under
consideration as published Office of the Economic Adviser, Department
for Promotion of Industry and Internal Trade, Ministry of Commerce &
Pp = Percentage of plant and machinery spares component of the work.
Note: For the application of this clause, index of Heavy Machinery and parts has
been chosen to represent the Plant and Machinery Spares group
Adjustment of other materials Component
(vii) Price adjustment for increase or decrease in cost of local materials other
than cement, steel, bitumen and POL procured by the contractor shall be
paid in accordance with the following formula
Vm = Increase or decrease in the cost of work during the month under
consideration due to change in rates for local materials other than
cement, steel, bitumen and POL.
M0 = The All Indian wholesale price index (all commodities) on 28 days
preceding the scheduled date of opening of technical Bids, as published by
the Office of the Economic Adviser, Department for Promotion of
Industry and Internal Trade, Ministry of Commerce & Industry.
Mi= The All India wholesale price index (all commodities) for the month
under consideration as published by the Office of the Economic Adviser,
Department for Promotion of Industry and Internal Trade, Ministry of
Commerce & Industry.
Pm = Percentage of local material components (other than cement, steel,
bitumen and POL) of the work.
The following percentage will govern the price adjustment for the entire
6. Plant & Machinery Spares Pp………………………….2%
7. Other Materials – Pm…………………………………….55%
25. The proportion of payments retained (retention money) shall be 6% {CL. 48}
from each bill subject to a maximum of 5% of final contract price.
26. Amount of Liquidated damages for For Whole of work {CL.49} delay
in completion of works (1/2000)th of the Initial contract
price, rounded off to the nearest
Thousand, per day. For sectional
Completion (wherever specified In item
6 of Contract data) (1/2000)th of initial
contract price for #5 km Section,
rounded off to the nearest thousand
27. Maximum limit of liquidated damages 10 percent of the Initial {CL. 49}
For delay in completion work Contract Price rounded off to
the nearest thousand
28. Amount of Bonus for early completion Amount of bonus for early
completion of work shall be given as
per CL.50 of Section-3
29. Maximum limit of bonus for early 5 percent of the Contract {CL. 50}
Completion of work Price
30. The amount of the advance payment are: {CL. 51 & 52}
#Nature of Advances Amount (Rs.) Conditions to Be
i Mobilization 10% of the contract On submission of unconditional
Price Bank Guarantee. (to be drawn
before the end of 20% of the
contract period). The contractor
may furnish four bank guarantees
of 2.5 % of each valid for the full
ii Equipment 90% for new and 50% of After equipment is brought to site
depreciated value for old (provided the Engineer is satisfied
equipment. Total amount That the equipment is required for
equipment. Total amount That the equipment is required for
will be subject to a performance of the contract) and
maximum of 5% of the on submission of unconditional
Contract Price Bank Guarantee for
amount of advance
iii Secured Deleted
Brought to site
(The advance payment will be paid to the Contractor no later than 28 days after
fulfillment of the above conditions).
31. Repayment of advance payment for mobilization and equipment {CL. 51.3}
The advance loan shall be repaid with percentage deduction from the interim
payments certified by the Engineer under the Contract. Deduction shall commence in
the next Interim Payment Certificate following that in which the
total of all such payments to the Contractor has reached not less than 20 percent of
the Contract Price or 6 (six) months from the date of payment of first installment of
advance, whichever period concludes earlier, and shall be made at the rate of
percent (collectively for both Mobilization Advance and Equipment Advance) of the
amounts of all Interim Payment Certificate until such time as the loan has been
repaid, always provided that the loan shall be completely repaid prior to the expiry of
the original time for completion pursuant to Clause 17 and
33. The securities shall be for the following minimum amounts equivalent {CL. 52} As a
percentage of the Contract Price:
Performance Security for 5 percent of contract price plus Rs. …………….. (to be decided
after evaluation of the bid) as additional security in terms of ITB Clause
The standard form of Performance security acceptable to the Employer shall be an
unconditional Bank Guarantee of the type as presented in Section 8 of the Bidding
34. The Schedule of Operating and maintenance Manuals…..N/A. {CL. 58}
35. The date by which “as– built” drawings (in scale as directed) in 2 sets {CL. 58} are
required within 28 days of the issue of certificate of completion of the whole or
section of the work, as the case may be.
36. The amount to be withheld for failing to supply “as built” drawings {CL. 58} by the
Date required is Rs Two (2) Lacs.
37. The following events shall also be fundamentals breach of contract: {CL.59.2} “The
Contractor has contravened Sub- clause 7.1 and Clause 9 of GCC”
38. The percentage to apply the value of the work not completed representing {Cl 60} the
Employer’s additional cost for completing the Works shall be 20 per cent.
TECHNICAL SPECIFICATION
Description of the Works:
1. We offer to execute the Works described above and remedy any defects therein in
conformity with the conditions of Contract, specification, drawings, Bill of Quantities and
Addenda for the sum (s) of
2. We undertake, if our Bid is accepted, to commence the Works as soon as is reasonably
possible after the receipt of the Engineer’s notice to commence, and to complete the
whole of the Works in the Contact within the time stated in the document.
3. We agree to abide by this Bid for the period of 120 Days from the date fixed for
receiving the same, and it shall remain binding upon it and may be accepted at any time
before the expiration of that period.
4. Unless and until a formal Agreement is prepared and executed this Bid, together with
your written acceptance thereof, shall constitute a binding contract between us.
5. We understand that you are not bound to accept the lowest or any tender you may
------- duly authorized to sign bids for and on behalf of -----------------------------------
(in block capitals or typed)
BILL OF QUANTITIES
BILL OF QUANTITIES
1. The bill of Quantities shall be read in conjunction with the Instructions to Bidder,
Conditions of Contract, Technical Specifications and Drawings.
2. The quantities given in the Bill of Quantities are estimated and provisional, and are
given to provide a common basis for bidding. The basis of payment will be the actual
quantities of work ordered and carried out, as measured by the Contractor and
verified by the Engineer and valued at the rates and prices tendered in the priced Bill
of Quantities, where applicable, and otherwise at such rates and prices as the
Engineer may fix within the terms of the Contract.
3. The rates and prices tendered in the priced Bill of Quantities shall, except in so far as
it is otherwise provided under the Contract, include all constructional plant, layout,
supervision, materials, erection, maintenance, insurance, profit, taxes and duties,
together with all general risks, liabilities and obligations set out or implied in the
4. The rates and prices shall be quoted entirely in Indian Currency.
5. A rate or prices shall be entered against each item in the Bill Quantities, whether
quantities are stated or not. The cost of Items against which Contractor has failed to
enter a rate or price shall be deemed to be covered by other rates and prices entered
in the Bill of Quantities (in case of Item rate contract).
6. The whole cost of complying with the provisions of the Contract shall be included in
the items provided in the priced Bill of Quantities, and where no Items are provided
the cost shall be deemed to be distributed among the rates and prices entered for
the related items of Work.
7. General direction and descriptions of work and materials are not necessarily
repeated or summarized in the Bill of Quantities. References to the relevant sections
of the contract documentation shall be made before entering rates or prices against
each item in the Bill of Quantities.
8. The method of completed work of payment shall be in accordance with the
specification for Road and Bridge works. For building works specifications for building
are to be followed.
9. Errors will be corrected by the Employer for any arithmetic errors pursuant to
Clause 29 of the Instructions to Bidder.
10. Rock is defined as all materials which, in the opinion of the Engineer, required
blasting, or the use of metal wedges and sledgehammers, or the use of compressed
air drilling for its removal, and which cannot be extracted by ripping with a tractor of
at least 150 kw with a single rear mounted heavy duty ripper.
Limbadi Nagarpalika
Annual Based Rate Contract
ItemNo. Description Quantity Rate Per
1 Preparing surface by Brushing with wire brushes for 1.00 28.04 Sqm.
removing caked mud etc. sweeping with brooms and
finally fanning the cleaned surface with gunney bags to
remove all loose dirt etc.(i) Water bound
macadamsurface (New)
2 Box cutting the road surface to proper slope and 1.00 205.35 Cum.
camber for making a base for road work including
removing the excavated stuff and depositing on the
road side slope as directed upto 50Mt.lead.
3 Loading, unloading, and carting hard murrum or soil 1.00 284.43 Cum.
manually or by mechanical effort, with an initial lead up
to 10 km.(i) Lime, murrum, building rubbish
4 Providing , Laying, Spreading and Compacting stone 1.00 1107.00 Cum.
aggregates of specific size to water bound macadam (
GRADE - II ) ( 63 mm to 45 mm ) specification
including spreading in uniform thickness , hand
packing , rolling with 3- wheeled steel / vibratory
roller 8 - 10 tonnes in stages to proposer grade and
camber , applying and brooming requisite type of
screending / binding materials to fill up the
interstices of coarse aggregates , watering and
compaction to the required density.
5 Providing and laying cement concrete 1:3:6 (1- 1.00 2926.96 Cum.
Cement : 3- coarse sand : 6- hand broken stone
aggregates 40 mmnominal size) and curing complete For
6 Providing and laying controlled cement 1.00 3892.00 Cum.
concreteM.200 and curing complete excluding the
cost of formwork and reinforcement for reinforced
concrete work in (A) Foundations, footings, Base of
columns and Mass concrete.
7 Providing and laying controlled cement 1.00 4172.90 Cum.
concreteM.250 and curing complete excluding the
cost of formwork and reinforcement for reinforced
concrete work in (A) Foundations, footings, Base of
columns and Mass concrete.
Limbadi Nagarpalika
Annual Based Rate Contract
ItemNo. Description Quantity Rate Per
8 Trimix concrete for curing complete including cost of 1.00 676.75 Cum.
formwork and Trimix process providing extra labour
charges for the trimix vacuum dewatering service
process on cement concrete road surface by using
vacuum dewatering pump floater surface vibrator
with rough finish to concrete surface
9 Providing 12mm thick pre. Moulded bitumineous 1.00 548.31 Cum.
filler joints as as directed with bitumen cap etc
complete. For filler joints
10 Providing TMT Bar FE 415 reinforcement for R.C.C. 1.00 66.59 Kg.
work including bending, binding and placing in
position complete
11 Providing and laying Compacted G.S.B. 150mm 1.00 986.84 Cum.
thick compacted granual sub base coarse Grade - II
Two Layer material of unscreened quarry material
including spreading,watering rolling & consolidationetc.
12 Providing and supplying evenly priming coat with 1.00 96.00 Sqm.
Emulsion SS1 @ rate of 7.5 Kg/10 Sq.M.
(including heating the bitumen including the cost
13 Providing and laying and rolling of 37.50mm thick 1.00 3037.00 MT.
using asphalt grade VG-40 for tack coat at the rate of5.0
kg/10 sq.mt on existing B.T surface and usingB.T
chips for required gradation with the asphalt of grade
VG-40 at the rate of 1.99% i.e 19.90 kg/M.T by
weight of mix including heating and mixing in Drum
Mix Plant,transportation the mix and spreading
the same by paver finisher and consolidation as
per MOST specification including cost of all
material,fuel,labour,tools and plantsetc.using by
contractor own mix plant etc.
Limbadi Nagarpalika
Annual Based Rate Contract
ItemNo. Description Quantity Rate Per
14 Providing & Laying 50 mm thick B.M. with B.T. 1.00 3450.21 MT.
Aggregate as per M.O.R.T & H specification & RS1
asphalt grade for tack coat @ 2.5kg/10 smt & mixing @
34.00kg/M.T. i.e. 3.40% by weight of total mix
including heating the aggregate & asphalt in
contunious batching drum mix plant and spreading
the same by paver finisher & consolidation with
vibratory rollar including providing all materials
equipment, tools & plants, fire wood, oil, kerosene,
labour charge etc. complete using contractor's own
machinary drum mix plant & paver finisher etc.
15 Providing an d laying 20mm thick Mixed seal 1.00 5151.99 MT.
surface using stone chipping and aggregates as per
MORT&H gradation and bitumen grade 60/70 for
mixing at the rate of 50.90% by total weight of mix
including heating the aggregates and asphalt by
contimuous batching of drum mix plant and
spreading the same by paver finisher and
consolidation with vibratory roller and flusing sand
0.30CuM/100SqMt including providing all materials,
equipments, tools and plant, oil, derosene, firewood,
labour charges etc. comp. using contractor's
ownmachineries.
16 Providing and laying asphalt painting on BT surface with 1.00 30.00 Sqm.
bitumen VG 40 rate 5 kg per 10smt by
mechanical sprayar and spreding the stone dust on
prepared surface at the rate of0.03 cmt/10smt and
rolling with smooth wheeled and penumiatic
rollerand brushing etc. completed.
Limbadi Nagarpalika
Annual Based Rate Contract
ItemNo. Description Quantity Rate Per
17 Road marking with hot applied thermoplastic paints with 1.00 364.08 Sqm.
reflectorising glass beads on bitumin surface
providing and laying a hot applied thermoplastic
compound 2.5 mm thick including reflectorising
glass beads @ 250gms per sqm area, thickness
of2.5mm is excluding of surface applied glass beds as per
IRC:35-2015. The finished surface to be level,
uniform and free from streaks and holes. zebra
patta/bump patta lane/center line/ edge line/cut patta. The
white color marking should provide liminance
coefficinet on cemend road shalll be min
mcd/m2/lux and Asphalt road shall be min
mcd/m2/lux during the service life during the day
time. The marking should meet the performance
criteria for night time reflectivity, wet reflectivity and
skid resistance as mentioned in the section-15 of IRC 35-
2015. Warranty for the Retro reflectivity should be
18 Cat Eye / Road Stud / RPM: Supplying Raised 1.00 215.25 No.
Pavement Markers made of polycarbonate and ABS
moulded body and reflective panels with Micro
prismatic lens (No Glass bead lens) capable of
providing total internal reflection of the light entering the
lens face and shall support a load of 13635 kgs. tested in
accordance to ASTM D 4280 Type H and complying
to Specifications of Category A of MORTH
Circular No RW/NH/33023/10-97 Ð DO IIIDt 11.06.
1997. The height, width and length shall not exceed
20 mm, 130 mm and 130 mm and with minimum
reflective area of 13 Sqcm on each side andthe slope
to the base shall be 35 +/- 5 degree. The body of the
marker should having finger grip for easy and accurate
placement and application with epoxy / bituminous
Adhesive as recommended by the manufacturer of
the marker. The color of the marker should be as per the
IRC 35-2015 and as directed by Engineer-in-charge.
19 Providing and fixing pre-cast Rubber Dye / steel Dye 1.00 677.11 Sqm.
inter locking concrete block 60mm thick with grade of
concrete M300 pnumatic compressed / vibrated
mechanically and as per approved design Confirming to
IS 15658 : 2006 including 35 mm Sand layer for
levelling and filling the joint with sand in proper line and
level as per guidlines of IRC : SP 63-2018 etc. Complete.
Limbadi Nagarpalika
Annual Based Rate Contract
ItemNo. Description Quantity Rate Per
20 Providing and fixing pre-cast concrete kerb stone of gray 1.00 358.06 Rmt.
cement based concrete block 30cm length,30cm height
and 15cm thick of M250 grade concret as per approved
design and including excavation for fixing in proper line
and level,filling the joint with C:M 1:3 (1cement:3fine
sand) etc complete [Dividerblock]
21 Providing and fixing pre-cast concrete kerb stone of gray 1.00 334.00 Rmt.
cement based concrete block 45cm length,45cm height
and 10cm thick of M250 grade concret as per approved
design and including excavation for fixing in proper line
and level,filling the joint with C:M 1:3 (1cement:3fine
sand) etc complete (Both Side) [Curbstone]
22 Renovation of manhole by increasing the height at 1.00 3374.00 Nos.
top including cost of excavation, refitting of manhole
cover/frame curing etc. complete, including all
carting and providing of material which is required
for purpose (excluding manhole frame and cover) For
all type manhole by providing RCC 1:2:4
Partition walls with required reinforcement 25 cm
thick and circular opening with 500mm clear dia and0.40
SECURITIES AND OTHER FORMS
BID SECURITY (BANK GUARANTEE)
WHEREAS, ---------------------------------------- (name of Bidder) (hereinafter called the “The
Bidder”) has submitted his bid Dated ------------------------ (Date) for the construction of ----
--------- (Name of Contractor hereinafter called “the Bid”)
KNOW ALL PEOPLE by these presents that We -------------------------------------------------
(name of Bank) of--------------------------------------------------- (name of country) having our
registered office at -------------------------------------------------------( hereinafter called
“the bank”) are bound unto --------------------------------------------(name of Employer)
(hereinafter called “The Employer”) in the sum of ------------------------------------------------ *
for which payment well and truly to be made to the said Employer the Bank itself, his
successors and assigns by these presents.
SEALED with the Common Seal of the said Bank this ---------------------- day of --------------20
THE CONDITIONS of these obligations are:
(1) If after Bid opening the Bidder withdraws his bid during the period of Bid validity
specified in the Form of Bid;
(2) If the Bidder has been notified of the acceptance of his bid by the Employer
during the period of Bid Validity:
A Fails or refuses to execute the Form of Agreement in accordance with the
Instructions to Bidders, if required; or
B. Fails or refuse to furnish the Performance Security, in accordance with the
Instructions to Bidders; or
C. does not accept the correction of the Bid Price pursuant to Clause
(Correction of Errors)
We undertake to pay to the Employer up to the above amount upon
receipt of his first written demand, without the employer having to substantiate his
demand, provided that in his demand the Employer will note that the amount
claimed by him is due to him owing to the occurrence of one or any of the three
conditions, specifying the occurred conditions or conditions.
This Guarantee will remain in force up to and including the date ------------------------- **
days after the deadline for submission of Bids as such the deadline is stated in the
Instructions to Bidders or as it may be extended by the Employer, notice of which
extension (s) to the Bank is hereby waived. Any demand in respect of this guarantee
should reach the Bank not later than the above date
(Signature, name and address)
* The Bidder should insert the amount of the guarantee in words and figures
denominated in Indian Rupees. This figure should be the same as shown in Clause
16.1(Bid Security) of the Instructions to Bidders.
**45 days after the end of the validity period of the Bid. Date should be inserted by
the Employer before the Bidding documents are issued.
PERFORMANCE SECURITY
contractor) (hereafter called “the Contractor”) has undertaken, in pursuance of
--------- (name of Contract and brief description of Works) (hereinafter called “The
AND WHEREAS it has been stipulated by you in the said Contract that the
Contractor shall furnish you with a Bank Guarantee by a recognized bank for the sum
specified therein as security for compliance with his obligation in accordance with the
AND WHEREAS we have agreed to give the Contractors such a bank Guarantee:
NOW THEREFORE we hereby affirm that we are the Guarantor and responsible to you on
behalf of the Contractor, up to a total of ------------------------------------------
(amount of guarantee)* -------------------------------- (in words), such sum being payable in
types and proportions of currencies in which the Contract prices is payable, and we
undertake to pay you, upon your first written demand and without cavil or argument,
any sum or sums within the limits of ---------------------------------------- (amount of
guarantee) as aforesaid without your needing to prove or to show grounds or reasons for
your demand for the sum specified therein.
We hereby waive the necessity of your demanding the said debt from the contractor
before presenting is with the demand.
We further agree that no change or addition to or other modification of the terms of the
Contract to of the Works to be performed thereunder or of any of the Contract
documents which may be made between your and the Contractor shall in any way
release us from any liability under this guarantee, and we hereby waive notice of any
such charge, addition or modifications.
This guarantee shall be valid until 60 days from the date of expiring of the Defect
Liabilities period.
Signature and Seal of the guarantor ----------------------------- Name
*An amount shall be inserted by the Guarantor, representing the percentage the
Contract price specified in the Contract denominated in Indian Rupees.
ADDITIONAL PERFORMANCE SECURITY
[Clause 34.1. (A)]
contractor) (hereafter called “The Contractor”) has undertaken, in pursuance of
--------- (Name of Contract and brief description of Works) (hereinafter called “The
AND WHEREAS it has been stipulated by you in the said Contract that the
Contractor shall furnish you with a Bank Guarantee by a recognized bank for the sum
specified therein as security for compliance with his obligation in accordance with the
AND WHEREAS we have agreed to give the Contractors such a bank Guarantee:
NOW THEREFORE we hereby affirm that we are the Guarantor and responsible to you on
behalf of the Contractor, up to a total of ------------------------------------------
(amount of guarantee)--------------------------------- (in words), such sum being payable in
types and proportions of currencies in which the Contract prices is payable, and we
undertake to pay you, upon your first written demand and without cavil or argument,
any sum or sums within the limits of ---------------------------------------- (amount of
guarantee) as aforesaid without your needing to prove or to show grounds or reasons for
your demand for the sum specified therein.
We hereby waive the necessity of your demanding the said debt from the contractor
before presenting is with the demand
We further agree that no change or addition to or other modification of the terms of the
Contract to of the Works to be performed thereunder or of any of the Contract
documents which may be made between your and the Contractor shall in any way
release us from any liability under this guarantee, and we hereby waive notice of any
such charge, addition or modifications.
This guarantee shall be valid until 28 days from the project completion date.
Signature and Seal of the guarantor ----------------------------- Name
BANK GUARANTEE FOR ADVANCE PAYMENT
In accordance with the provisions of the Conditions of Contract, sub-clause
51.1 (“Advance Payment”) of the above mentioned Contract, -------------------------------
------------------- (name and address of Contractor) (hereinafter called- “the
Contractor”) shall deposit with (name of
Employer) a bank guarantee his proper and faithful performance under the said
Clause of the Contract in an amount of------------------------------- (amount of Guarantee)* -
We, the-------------------------------------(bank of financial institution), as instructed
by the Contractor, agree unconditionally and irrevocably to guarantee as primary
obligator and not as Surety merely, the payment to ---------------------------------------- (name
of Employer) on his first demand without whatsoever right of obligation on our part and
without his first claim to the Contractor, in the amount not exceeding ---
We further agree that no change or addition to or other modifications of the terms of the
Contractor or Works to be performed thereunder or of any of the Contract documents
which may be made between --------------------------------- (name of Employer) and the
Contractor, shall in any way release us from any liability under this guarantee, and we
hereby waive notice of any such change, addition or modifications.
This guarantee shall remain valid and in full effect from the date of the advance
payment under the Contract until -------------------------------------- (name of employer)
receives full repayment of the same amount from the contractor.
Signature and Seal
Name of Bank/ Financial Institution
* An amount shall be inserted by that Bank or Financial Institution representing the amount
of the Advance Payment, and denominated in Indian Rupees.
Letter of Acceptance
(Letter head paper of the Employer)
(Name and address of the Contractor)
This is to notify you that your Bid dated for execution of
the (Name of the contract and identification number, as given
in the Instructions to Bidders) for the Contract Price of Rupees
( ) (amount in words and figures) as corrected and modified in accordance
with the Instructions to Bidders* is hereby accepted by our agency.
You are requested to furnish performance security, in the form detailed in para
34.1 of ITB for an amount equivalent to Rs. within 10 days of the receipt of this
letter of acceptance up to beyond 60 days from the date of expiry of defects Liability
period i.e. up to and the Additional Performance Security for an
amount equivalent to Rs. shall be valid beyond 28 (twenty-eight) days of
Project Completion Date i.e. up to and sign the contract, failing which
action as stated in Para 34.3 of ITB will be taken.
Yours Faithfully
Authorized Signature Name
and title of Signatory Name
* Delete “Corrected and” or and modified if only one of these actions applies. Delete as
corrected and modified in accordance with the Instructions to Bidders, if corrections or
modifications have not been affected.
Issue of Notice to proceed with the work
(Letterhead of the Employer)
(Name and address of the Contractor)
Pursuant to your furnishing the requisite security in ITB Clause 34.1 and
signing of the Contract for the construction of
at a bid Price of Rs.
You are hereby instructed to proceed with the execution of the said works in accordance
with the contract documents.
Yours faithfully
(Signature, name and title of signatory authorized To
sign on behalf of Employer)
This agreement, made on the day of between
(name and address of Employer) (Hereinafter called “the
Employer) and (name and address of
contractor) hereinafter called “the Contractor” of the other part.
Whereas the Employer is desirous that the Contractor execute
Name and identification number of contract (hereinafter called “the works”) and the
employer has accepted the Bid by the Contractor for the execution and completion of
such works and the remedying of any defects therein, at a cost of Rs.
NOW THIS AGREEMENT WITNESSETH AS FOLLOWS
1. In this Agreement, words and expression shall have the same meanings as are
respectively assigned to them in the conditions of contract hereinafter referred to
and they shall be deemed to form and be read construed as part of this Agreement.
2. In Consideration of the payment to be made by the Employer to the contractor as
hereinafter mentioned, the Contractor hereby covenants with the Employer to
executive and complete the works and remedy any defects therein in conformity in
all aspects with the provisions of the contracts.
3. The employer hereby covenants to pay the Contractor in consideration of the
execution and completion of the works and the remedying the defects wherein
contract price or such other sum as may become payable under the provisions of the
Contract at the times and in the manner prescribed by the contract.
4. The Following documents shall be deemed to form and be ready and construed as
part of this Agreement viz
i) letter of Acceptance
ii ) Notice to proceed with the works:
iii ) Contractor’s Bid
iv ) Conditions of contract: General and Special
v) Contract Data
vi) Additional conditions
viii ) Bill of Quantities and
ix ) Any other documents listed in the Contract
data as forming part of the Contract.
In witness whereof the parties there to have caused this Agreement to be
executed the day and year first before written
The Common seal of
Was hereunto affixed in the presence of :
Signed, sealed and Delivered by the said
In the presence of
Binding signature of Employer
Binding Signature of Contractor
(For Investment)
I, the undersigned do hereby undertake that our firm M/s
…………………………………………………..……………………………….. would invest a minimum cash up to
25% of the value of the work during implementation of the contract.
(Signed by an Authorized officer of the firm)
Title of officer
I, the undersigned do hereby undertake that our firm M/s ……………………………………
……………..……………………………….. agree to abide by this bid for a period ................................. days
for date fixed for receiving the same and it shall be binding on us and may be accepted at
any time before the expiration of that period.
(Signed by an Authorized officer of the firm)
Title of officer
DOCUMENTS TO BE FURNISHED BY BIDDER
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
00_NIT_LIMBADI (2nd Attempt).pdf
01_VOLUME-I SBD BOOK AND BOQ 240826.pdf
02_SPECIFICATION OF ROAD WAORK.pdf
03_SPECIFICATION OF BUILDING.pdf
04_TEST REQUIRE FOR CONSTRUCTION MATERIAL.pdf
05_GST RESOLUTION NEW.pdf
06_PARIPATRA 01.pdf
07_PARIPATRA 02.pdf
08_PARIPATRA 03.pdf
09_PARIPATRA 04.pdf
10_PARIPATRA 05.pdf
11_PARIPATRA 06.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].