Chief General Manager (Thermal)
Surat Lignite Power Plant - 4X125 MW, Unit - I to IV: Civil works for Construction of foundations, flooring and associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building - PEB) near existing Warehouse (Year: 2026-27).
312517
SLPP/Civil/WH/Sheds/2026
Open
Civil Works
Surat
₹2,950
Gujarat Industries Power Company Limited
₹87,000
10 Jun 2026
10 Jun 2026
10 Jun 2026
15 Jul 2026
10 Jun 2026
Any error in description or quantity or omission in the contract document shall not
vitiate the contract or release the contractor from executing the work comprised in
the contract according to scope of works, magnitude of the works, requirement of
materials, equipment, tools & tackles, labour, etc. Contractor has to complete the
work in accordance with the contract documents irrespective of any defects,
omissions or errors that may be found in the contract documents.
BIDDER shall inspect the site, examine and obtain all information required and satisfy
himself regarding matters such as access to site, communication, transport, working
condition including constraint of work place, working location & its distance, quantum
of dusting, temperature, importance of work, round the clock working conditions,
available access & approaches, safety requirements, types & approved makes of
material requirements, material storage requirements, work permit system, right of
way, water logging, high flood level in River, flow of water, during monsoon/dry
season in the River/Nallah, the type and number of equipment & facilities required
for the satisfactory completion of work, the quantity of various items of the work, the
availability of local labour, accommodation, available canteen & medical facilities,
requirements & availability of power supply, water supply & rates of material, local
working conditions, uncertainties of weather, obstructions & hindrances that may
arise, etc which may affect the work or cost thereof, etc… before submission of his
Ignorance of site conditions shall not be accepted by the GIPCL as basis for any
claim for compensation. The submission of a Bid by the BIDDER will be construed
as evidence that such an examination was made. Any later claims / disputes in regard
to rates quoted/offered shall not be entertained nor considered by the GIPCL.
The rate quoted by BIDDER shall be based on his own knowledge and judgment of
the conditions and hazards involved and shall not be based on any representations
of the GIPCL Engineer.
It is also desirable to study tender documents thoroughly before site visit.
5. ELIGIBILITY CRITERIA
The following criteria will be adopted for qualifying the Bidders for consideration of
the Bid for the further proceeding.
5.1 Bidder should possess minimum Three years of experience during last Six years
in similar nature of jobs, various type of Civil & Infrastructure works like Civil works
for (i) Construction of Industrial or Commercial Warehouse, (ii) Construction of
Industrial or Commercial Storage Sheds, Construction of Industrial or Commercial
Buildings, Multistoried Building, Mega Civil Constructions, etc… including Civil RCC
foundations, RCC Pavements/Flooring, etc… for Power Plant, Process Industries,
Corporations, Corporate, Institutes, Township and should enclose proof of the same.
Bidder shall submit necessary evidence for the same like self-attested copies of work
orders/Work Execution/Work Completion certificates from clients. The work
completion certificate shall comprise of Order value & Executed value. Bidders
should have executed the work directly. The work executed as a sub-contractor or
subletting agency shall not be taken in to consideration.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
5.2 Bidder should produce evidence of having successfully completed similar works
(as per above clause no. 5.1) during last Six years ending last day of the month
previous to the one in which tender is invited, satisfactory progress of ongoing
works etc… secured from clients along with self-attested copies of documentary
evidence preferably photo copies of work experience. The experience should be
either of the following:
a. One similar completed/executed work each costing not less than the
amount equal to Rs.68,41,403/-.
b. Two similar completed/executed works each costing not less than the
amount equal to Rs.41,04,842/-.
c. Three similar completed/executed works each costing not less than the
amount equal to Rs.27,36,561/-.
Note: For evaluation of the bid the executed value mentioned in the work
completion/work in progress certificate will be considered.
Bidder should specifically mention fulfilling of above criteria in his offer along
with details of work orders & work completion/execution certificates issued by
5.3 Tender fee: The tender fee shall be submitted through RTGS or through online
payment only as per details provided in clause no. 7 hereinunder. Demand Draft will
not be accepted for Tender Fee.
5.4 EMD: The EMD shall be submitted in the form of DD/RTGS/online or irrevocable
Bank Guarantee given by Bank as described in subsequent clause no.
5.5 Bidder should have separate Employees Provident Fund code number towards
registration of firm with RPF commissioner.
5.6 Attested copies of relevant documents duly signed & seal on each & every page shall
be submitted. GIPCL may verify the documents, experience certificates issued by
concern authority. After opening of technical Bid, if any required attested documents
found missing in the Technical Bid submitted by the Bidder, the tender inviting
authority may inform to that Bidder by E-mail to submit the missing required
documents within stipulated time limit. If Bidder/Bidders fail to submit within stipulated
time, their Bid will be declared technically disqualified and no further correspondence
will be entertained.
5.7 Bidder should have average annual turnover of Rs.41,04,842/- during last three
financial years (average of financial years of 2024-25, 2023-24 and 2022-23).
Bidder shall furnish annual audited financial statement duly certified by Chartered
Accountant for the last three financial years as above to demonstrate the financial
healthiness of the company. The balance Sheet and Profit & Loss Account must be
in the name of the company. Any type of MOU for this purpose will not be entertained.
Note: In case, the annual turnover is less than the statutory guideline which does not
require audit, the bidder shall submit the turnover certificate from Chartered
5.8 The Bidder has to submit INCOME TAX Permanent Account Number (PAN) and GST
registration number. Copies of the same shall be submitted.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
5.9 The net worth of the bidder should be positive as evidenced from audited
accounts of last financial year (2024-25), audited (or where, as per extant laws of
the land, audit is not applicable, certified) by a qualified Chartered Accountant who
should be a member of the Institute of Chartered Accountants of India.
5.10 In case Bidder is a Consortium/Joint deed of undertaking of company, the above
requirements/credential of consortium leader/bidder shall be considered unless
otherwise specifically mentioned in the tender.
5.11 If Bidder or its Partner(s) or Director(s) is /are/was Black Listed / Deregistered /
Stopped or banned from dealing in the past by any Govt, of Gujarat Undertakings /
Depts. / Authorities and Govt. of Gujarat supported companies / undertakings /
organizations, Bid of that party may be liable to be rejected. Bidder agrees and
undertakes to accept decision of GIPCL in this regard as final and binding on the
Bidder without any demur and that no further correspondence shall be done in this
regard at any stage. Bidder shall have to submit “Declaration for Contractual
Litigations” as amended in Annexure-H in Section-F / Form attached.
5.12 Bidder shall have to submit the “Declaration-cum-Undertaking for Compliance of
Safety Laws and Regulations” on his company letter head as amended in Annexure-
G in Section-F / Form attached.
If any Major Violation of any safety law(s) / Rule(s) is / are found during
the preceding Three (3) years, Bid of that party will be liable to be rejected.
Bidder agrees and undertakes to accept decision of GIPCL in this regard
as final and binding on the Bidder without any demur and that no further
correspondence shall be done in this regard at any stage.
If any of the details submitted in the prescribed Annexure-G & H in Section-
F / Form to the Bid is/are found to be false, incorrect at any time in future,
then the Contract awarded to that Bidder / Contractor shall be liable to be
terminated forthwith without any notice / correspondence and Bidder
agrees and undertakes to accept decision of GIPCL in this regards as final
and binding on the Bidder without any demur and that no further
correspondence shall be done in this regard at any stage. Further,
Performance / Security Deposit will also be liable to be forfeited. Any dues
to GIPCL from the Bidder / Contractor shall be recovered from the pending
bills or any other dues payable to the Bidder / Contractor, if any or
otherwise through any other recourse available under the Laws.
The Bidder shall submit all the evidences, documents, attested copies of work orders
& work completion certificates etc… as a proof with EMD & Tender Fee and also
provide the requisite details online for meeting the prequalification requirements.
GIPCL will verify the experience, performance, capability & strength of Bidders,
independently for executing the job. GIPCL may visit the site & consult the owner of
the industry/property where similar job is executed by the Bidder. GIPCL reserves
the right to accept/cancel/reject any/all Bids without assigning any reason thereof.
The tenders of qualified Bidder/Bidders shall only be considered for further
5.13 Site Visit is mandatory prior to submission of bid to understand the scope of work,
Technical requirements, working conditions, site conditions, equipments, tools &
tackles, labor deployment, associated risk, surrounding etc.
5.14 Bidder shall submit all supporting documents as per tender eligibility requirements.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
6. LANGUAGE OF BID
The Bid prepared by the Bidder, and all correspondence and documents relating to
the Bid exchanged by the Bidder and the Company, shall be written in the English
language. Any printed literature furnished by the Bidder, written in another language
shall be accompanied by an English translation for the purpose of interpretation of
7. EARNEST MONEY DEPOSIT (EMD) AND TENDER FEE
7.1 An EMD of Rs.87,000/- (Rupees Eighty-Seven Thousand only) and nonrefundable
Tender fee of Rs.2,950/- (Rupees Two Thousand Nine Hundred Fifty only), inclusive
of applicable GST shall accompany with Bid. Tender fee shall be submitted
through RTGS / online mode of payment only.
7.2 The EMD shall be submitted in the form of DD/irrevocable Bank Guarantee in favor
of Gujarat Industries Power Company Limited from all Nationalized Banks or Axis
Bank, ICICI Bank, HDFC Bank, Kotak Mahindra Bank, IndusInd Bank, Federal Bank,
Bandhan Bank, IDBI Bank and Karur Vysya Bank as per Performa of BG enclosed
with this tender document under Section-F (Annexure-C).
Bank for EMD DD Payable at :
1. Bank of Baroda Mosali, Dist: Surat
2. State Bank of India Nani Naroli, Branch Code:
3. Any Nationalized banks Surat
Alternatively, EMD & Tender Fee may also be submitted through RTGS mode of
payment by the bidders as per the details given below:-
1. BANK NAME:- State Bank of India
2. BRANCH:- Nani Naroli
3. IFSC CODE:- SBIN0013423
4. BENEFICIARY NAME: Gujarat Industries Power Company Limited
Also, EMD & Tender fee may be submitted through online payment gateway of
company’s website: www.gipcl.com (online Payment Form) as per detail
provided in Section-F (Annexure-J) herein under.
7.3 In case EMD is paid in the form of irrevocable BG, the same shall be valid for a period
of 180 days after the due date for submission of the bid
7.4 The EMD of the successful bidder will be returned after payment of Security Deposit
or submission of irrevocable PBG by successful bidder. Alternatively, EMD will be
converted into SD and successful bidder shall submit SD or performance bank
guarantee for the balance amount.
7.5 The earnest money deposit will be refunded to the unsuccessful/disqualified BIDDER
after the tender is finalized and after award of LOI/Work Order.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
7.6 Any bid not accompanied with EMD and Tender fee will be rejected. Tender fees and
EMD should be submitted to GIPCL.
7.7 No interest shall be payable on EMD.
7.8 The EMD will be forfeited if the BIDDER (i) withdraws his tender after acceptance or
(ii) withdraws his tender before the expiry of the validity date of the tender.
7.9 SCHEDULE OF EMD, TENDER FEE & OTHER SUPPORTING DOCUMENTS
Details/receipts of EMD & Tender fee Address for Submission: -
paid by RTGS/online or EMD in physical
form by way of DD/BG (as applicable) Chief General Manager (Thermal)
with other documents duly self-attested GUJARAT INDUSTRIES POWER CO. LTD.,
are to be submitted in physical form in (Surat Lignite Power Plant)
sealed cover as per details mentioned Village: Nani Naroli,
in NIT. Bid No. shall be mentioned at Taluka: Motamiya-Mangrol,
the top of cover/envelope. District: Surat.
PIN: 394 112, Gujarat.
E-Mail: [email protected]
8. SUBMISSION OF BIDS
A: MODE OF SUBMISSION
The bids shall be submitted online through website: https://tender.nprocure.com or
https://gipcltender.nprocure.com within the dates specified in the NIT along with the
details of tender fees, EMD in two parts as under:
(a) Pre-qualification and Techno-commercial Bid without price.
Further briefing of above Part (a) and (b) are as under;
(a) Pre-qualification and Techno-commercial Bid without price:
The tender document duly signed in all pages without price bid along with techno-
commercial deviations, if any, shall accompany the bid. The following Information
shall be provided in the techno commercial bid:
1. Qualification and experience of Site-in-charge.
2. Schedule of Deviation (Annexure-F in Section-F) Technical as well as
commercial, if any.
3. Qualification & experience of Supervisors/Engineers.
4. List of available equipments, tools & tackles which are required to perform the
scope of works as specified in this tender.
The following supporting documents shall also be submitted in physical form
along with EMD & Tender Fee:
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
1. The tender documents dully signed in all pages without price bid along with
techno-commercial deviations, if any.
2. Proof of experience meeting the minimum eligibility criteria as mentioned in
tender document.
3. Performance certificate issued by clients.
4. Previous work order copies.
5. Details of present work order (if any).
6. Turn over for the last three years, audited annual accounts/financial statements
i.e. profit & loss account and balance sheet and net worth certificate for last
financial year duly certified by a practicing CA will be required as specified in
clause nos. 5.7 & 5.9 above.
7. P.F. Number and Allotment Letter.
8. PAN Number / Copy of PAN card.
9. Goods & Service tax registration number/certificate copy.
10. Bidder should submit duly filled Annexure-E provided under Section-F of
Tender document.
11. Bidder should submit Annexure-F (Schedule of Deviation) under Section-F
either marking NIL or desired deviations.
12. Bidder should submit Declaration-cum-Undertaking for Compliance of Safety
Laws & Regulations and Contractual Disputes / Litigations as per Performa
Annexure-G & Annexure-H under Section-F.
13. Bidder should submit duly filled Annexure-K (List of Qualified Staff) & Annexure-
L (List of available equipment, tools & tackles) as provided under Section-F of
Tender document.
14. Bidder should submit Declaration-cum-Undertaking on Letterhead regarding
deployment of experienced Civil Engineer as per Performa Annexure-M under
15. Bank Mandate (if not submitted earlier) as per Annexure-N under Section-F duly
signed, & stamped by bidder and respective Bank, along with original cancelled
16. Vendor Registration Form (in case of first time bid participant of GIPCL’s
Tender) as per Annexure-O under Section-F.
17. Bidders should provide his User ID for e-Reverse auction on website:
https://e-auction.nprocure.com
1. Percentage Rate Price Bid shall be submitted only in soft form through e- portal
Note: The Estimate includes the cost of all manpower (skilled, semi-skilled,
unskilled), experienced / qualified Civil Engineer (site Engineer), experienced
site supervisors, tools, tackles, equipment, and any hired or outsourced
resources required for job-specific works.
It also covers all materials except those specifically listed / mentioned as free-
issue material in the Schedule of Rates (SoR) Section-E.
In addition, it includes all consumables, fuel, maintenance, spares,
transportation, loading/unloading, safe storage, mobilization and
demobilization, site supervision, housekeeping, and cleaning, Temporary site
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
infrastructure (offices, stores, toilets, fencing, etc.), quality control and testing
(including third-party testing), and insurance (CAR, Workmen Compensation,
and Third-Party Liability) are also covered.
The contractor shall comply with all statutory and legal requirements, including
labour laws (minimum wages, EPF, ESI, bonus, etc… as applicable), safety
regulations, and environmental norms. All applicable taxes and duties,
including GST, are deemed included. The total estimated SoR amount is
inclusive of GST, considered at the current rate of 18%. However, GST must
be shown separately in invoices, and any change in rate shall be adjusted at
actuals upon submission of valid proof.
2. The bidder’s percentage (%) offer shall be based on the Total Estimated
Amount, inclusive of GST. However, at the time of billing, GST shall be
shown separately in the invoice, with reverse calculation as per prevailing GST
laws. The applicable GST rate shall be charged at actuals, subject to
submission of valid documentary evidence, in line with the rates notified by the
Central Government.
3. The bidder shall quote the rates in the form of a percentage (%) as follows:
“At Estimated Value” or “_____ % below the Estimated Value” or “_____ %
above the Estimated Value”.
4. The quantities indicated in the Schedule of Rates (SoR) under Section-E are
tentative and based on preliminary concept drawings. These quantities are
subject to variation during actual execution, depending on site conditions and
final approved drawings.
The Bidder shall fill the Bid documents with utmost care in consonance with the
instructions contained in the Bid documents.
5. The quoted rates shall remain firm and fixed throughout the contract period
and any extension thereof, if required, for completion of the entire scope of
work. The rates shall not be subject to any escalation or adjustment on any
account, including but not limited to increases in the cost of materials, fuels,
statutory levies, Minimum Wage Rates (MWR), overheads, idle charges for
labour or machinery, or any other unforeseen expenses. No escalation or
compensation shall be payable to the contractor for any such revisions or
changes during the contract period / till completion of entire scope of work.
B: METHOD OF TENDERING/SIGNATURE ON BIDS
(i) The Bid must contain the postal address like name, residence & place of
business of the person/persons submitting the Bid and must be signed & sealed
by the Bidder with his/her usual signature. The name of all persons signing the
documents shall also be typed or printed below the signature on each page.
(ii) Bid by a joint venture/partnership firm must be furnished with full names of all
partners and be signed with the partnership name, followed by the signature and
designation of one of the authorized partners or other authorized
representative(s). A certified copy of the power of attorney authorizing such
partner or representative shall also be submitted.
(iii) Bids by a Corporation/Company must be signed with the legal name of the
Corporation/Company i.e. by the President/Managing Director/Secretary or
other person or persons authorized to Bid on behalf of such
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
Corporation/Company. A certified copy of the board resolution/power of attorney
authorizing such partner or representative shall also be submitted.
(iv) The Bidder's name stated on the proposal shall be the exact legal name of the
(v) Erasures or other changes in the Bid Documents shall be initialed by the person
signing the Bid.
(vi) Bids not conforming to the above requirements of signing shall be disqualified.
9. MODIFICATION AND WITHDRAWAL OF BIDS
a. The Bidder may modify or withdraw the bid prior to the deadline prescribed for
submission of bids.
b. No Bid shall be modified subsequent to the deadline for submission of Bids.
c. No Bid shall be withdrawn in the interval between the deadline for submission of
Bids and the expiration of the period of bid validity.
10. POLICY FOR BIDS UNDER CONSIDERATION
a. Bid shall be deemed to be under consideration immediately after opening of the
bid and till official intimation of award/rejection made by the Company to the
b. While the Bids are under consideration, Bidders and / or their representative or
other interested parties are advised to refrain from contacting by any means, the
Company. The OWNER, if necessary, will obtain clarifications on the Bids by
requesting for such information from any or all the Bidders, in writing as may be
necessary. The Bidder will not be permitted to change the price or substance of
the Bid after the Bid has been opened.
11. EFFECT AND VALIDITY OF THE BID
a. The Bid should be kept valid for acceptance for a period of one hundred and
eighty (180) calendar days from the last date of submission of Bids.
b. The submission of any Bid along with the required documents and specifications
shall constitute an agreement that the Bidder shall have no cause of action or
claim, against the Company for rejection of his Bid. The Company shall always
be at liberty to reject or accept any Bid or Bids at his sole discretion and any
action will not be called into question and the Bidder shall have no claim in that
regard against the GIPCL.
12. OPENING OF BIDS
12.1 The GIPCL will open the pre-qualification/Technical Bid/price Bid, as the case
may be, in presence of Bidder's representatives whenever such a procedure
has been specified. Otherwise the tender will be opened by the authorized
officers of GIPCL.
12.2 Preliminary Examination:
12.2.1 The Company will examine the Bids for any computational errors, for
sureties furnished by bidder, for authentication of documents
submitted and completeness of the Bids.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
12.2.2 Arithmetical errors will be rectified on the following basis:
If there is a discrepancy between the unit price and the total price that is
obtained by multiplying the unit price and quantity, the unit price shall prevail
and the total price will be corrected & will be binding to the bidders.
(a) If there is a discrepancy between the Total Bid Amount and the sum
of total prices, the sum of total prices shall prevail and the Total Bid
Amount will be corrected & will be binding to the bidders.
13. EVALUATION & COMPARISON OF BIDS
13.1 GIPCL shall evaluate the Bids received and accepted by it to ascertain the
lowest evaluated Bid in conformity with the specifications of the tender
13.2 The Technical Bids will be examined for minor matters regarding qualification
of bids. Subsequent to correspondence with the respective bidders, the
decision of Tender Committee will be final.
13.3 All responses to requests for clarifications shall be in writing and shall be
presented to the Company through e-mail or in a sealed envelope on or before
the given date requested by the Company. If the Technical clarifications sought
by the Company do not reach the Company on or before due date, the Bid will
13.4 The comparison of all the Bids shall be carried out with reference to the scope
of work as per the technical specification. Any deviation/omission shall be
evaluated at highest quoted price of the deviation/omission quoted by any of
the Bidder. In case a separate price (for omission) is not given by any other
Bidder, a reasonable price of the same shall be taken & the same shall be
binding to the Bidders.
13.5 The commercial deviation, if any, shall be loaded to bring all the Bids at par.
The loading shall be carried out at an interest rate of 2% above PLR of SBI.
13.6 A Bid to be substantially responsive shall be one which on evaluation confirms
to all the terms, conditions and specifications of the Bid documents without any
material deviation or reservation.
13.7 For the above referred purpose, a ‘material deviation’ shall be one which:
(a) Which affects in any substantial way the scope, quality or performance of
the contract, or
(b) Which limits in any substantial way and in a manner inconsistent with the
Bid documents, GIPCL’s right or the Bidder’s obligations, under the
(c) Whose rectification would affect unfairly the competitive position of other
Bidders presenting substantially responsive Bids.
14. RIGHT OF REJECTION OF TENDERS
14.1 GIPCL reserves the right to accept or reject any Bid or to cancel the Bidding
process and reject all Bids at any time prior to award of contract, without thereby
incurring any liability to the affected Bidder or Bidders or any obligation to inform
the affected Bidder or Bidders regarding the same.
14.2 Any Tender without EMD and Tender fee will be treated as non-responsive and
shall be rejected at the outset & no further correspondence shall be entertained
regarding this.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
14.3 GIPCL reserves the right to debar any Bidder from participation in future Bids if
such Bidder has quoted an abnormally low rate in the Bid document/price Bid.
15. AWARD OF CONTRACT.
15.1 GIPCL will award the contract to that bidder whose quotation has been
determined to be substantially responsive and evaluated as the lowest
quotation in conformity with the requirements of the specifications and
documents contained herein, provided further that the bidder is determined and
evaluated to be qualified to perform the contract satisfactorily.
15.2 The successful bidder shall be intimated of his/her selection through the Letter
of Intent or Letter of Award/ Work Order which shall be sent to him/her through
e-mail, courier, fax or registered mail.
15.3 GIPCL reserves the right to cancel/short close the contract during the contract
period without assigning any reason.
15.4 GIPCL reserves the right to split the contract quantity between vendors.
16. CONTRACT / COMPLETION PERIOD
16.1 The contract / completion period for scope of works of both the sheds shall be
06 (six) months from the date of issuance of the Letter of Intent (LoI) and/or
Work Order, whichever is earlier (except 03 months of peak Monsoon, i.e. July,
August & September).
16.2 GIPCL/Consultant shall issue RCC foundation construction drawings for both
the sheds within 30 days from date of LOI. Excavation, Construction of RCC
Foundation, Pedestals & Beams, Backfilling, etc... for both the sheds in all
respect including ready for handing over to PEB agency for erection of PEB
Structure: Within 03 Months from the date of release of Construction Drawings
for Foundation, Pedestals & Beams.
16.3 Balance Civil works for both the sheds as per scope of work: Within 02 Months
from the date of handing over of front.
16.4 GIPCL reserves the right to extend the contract period by up to an additional
(three) months on the same rates, terms, and conditions, without any price
escalation and without entering into a new contract on sole discretion of GIPCL
only. However, delay attribute to contractor beyond above schedules will
attracts penalty as LD (Liquidated Damages) as per specific clause mentioned
in Special Conditions of Contract (Section-D).
16.5 If the scope of work is not completed by the Contractor, necessary LD will be
deducted as per specific clause mentioned in Special Conditions of Contract
(Section-D) and in the interest of work completion, GIPCL will extend the
contract period appropriately (along with deduction of LD) as per contract
requirement on the same rates, terms, and conditions without any price
escalation or new contract on sole discretion of GIPCL.
16.6 GIPCL reserves the right to short-close the contract at any time by giving
(one) month’s notice, without assigning any reason.
17. ASSIGNMENT AND SUB-LETTING
The Contractor shall not directly or indirectly assign or sub-let total/any part of the
contract to any other party or agency.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
18. CONTRACTOR’S OBLIGATIONS
A: DEPLOYMENT & RESPONSIBILITY OF MANPOWER
(i) The Contractor shall deploy suitably qualified and sufficient manpower for timely
& satisfactorily execution of the works under the contract.
(ii) The Contractor shall deploy sufficient skilled, Semi-skilled and Un-skilled
manpower separately to properly complete the job in given/scheduled time.
(iii) The Contractor shall depute its own workmen/labour with proper identification to
enter the plant premises after ensuring that the jobs are scheduled.
(iv) At the time of deploying manpower, the Contractor shall strictly comply all the
applicable labour laws/Acts norms including but not restricted to the age of the
workers, women workers and shall also ensure that a police verification, security
check, pre-employment medical fitness check-ups & induction safety training for
all the workmen/labour engaged at the GIPCL site is done and necessary
documents regarding the same shall be submitted to the GIPCL’s authorized
representative/officer-in-charge. Any default in complying with the same or any
misrepresentation regarding compliance of the same shall compel GIPCL to
initiate appropriate civil or criminal proceedings regarding the same.
(v) The Contractor shall also comply with the safety requirements and provide his
workmen/labor with safety equipment like helmets, masks, gum boots and other
necessary PPEs for properly undertaking the operations involved under this
contract. Following are also to be issued by contractor
a) Safety shoes (standard approved ISI make)
b) Safety helmet (standard approved ISI make in yellow colour only)
c) Safety Goggles / face shield.
d) Ear plug / Ear muff.
e) Hand gloves like electrical hand gloves / cotton hand gloves /
Chemical hand gloves.
(vi) Contractor shall nominate /authorize senior experienced person in writing as site-
in-charge to co-ordinate with GIPCL engineer / operation team and who shall
bear overall responsibility for performance of the contract. Such person shall
remain available at site during execution of scope of work. Contractor has to
submit the authority letter and documentary proof for the same.
(vii) The Contractor shall appoint minimum required site supervisors who shall co-
ordinate with GIPCL’s Engineer-in-Charge for daily entrusted jobs. They have to
maintain daily records dully signed for the works carried out and duly certified by
concern Engineer-in-Charge. The Contractor, in co-ordination with the Engineer-
in-Charge, shall ensure the availability of adequate manpower, consumables,
materials, tools & tackles, etc… to carry out the job satisfactorily as per GIPCL’s
requirements as directed by Engineer-in-charge. As per the instruction of
Engineer-in-Charge, they have to allot the work and execute the same in
specified time limit.
(viii) During execution of the works, one or more jobs may be required to be done
simultaneously and the Contractor shall mobilize additional resources
(ix) During emergency or similar situations, the Contractor shall be required to
mobilize resources as per need within the period of 04 (four) hours or even earlier
of that, depending upon criticality and also during odd hours, as directed by
GIPCL. If the contractor fails to mobilize sufficient manpower to complete the job
in time, GIPCL will execute the job through other agency at the risk and cost of
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
the contractor with 10% supervision charges, including GST & the same will be
recovered from the Contractor’s bill.
Important Note: Whenever any of the Unit at SLPP remains under outage due
to any reason, the contractor shall mobilize sufficient work force at site within a
period of four hours from the time of intimation to the site-in-charge or via mail to
your office. Generation loss occurred due to want of manpower as well as
resources will be viewed very seriously and will invite appropriate punitive
measures as decided by competent authority.
(x) During working in high risk area like hot lines of steam/ water/ oil, the workman
must wear a suitable safety apron, safety belt, safety hand gloves and goggles.
It is the contractor’s/contractor’s supervisor’s responsibility to ensure it without
(xi) During unit overhauling, the contractor has to enhance the site manpower as per
the requirement to ensure the timely completion of work (During overhauling
period quantum of work increases substantially). For this, enhanced work shall
be completed by deploying additional manpower with supervisor as per site
necessity. Payment will be made on item rate basis only under respective
section. The work during the overhauling period is to be carried out round the
clock as per instructions of Engineer-in-charge. Contractor should mobilize
sufficient number of manpower with other required equipment/resources and
execute the work in all shifts with independent manpower after receipt of such
instructions. Contractor should not continue the same manpower for more than
B: TOOLS & TACKLES:
(i) All standard tools & tackles, standard Civil construction equipment, vehicles,
consumables, materials, etc… (Standard Civil construction equipment like but
not limited to AJAX Machine with weighment printing facilities, 02 bags capacity
Batching Mixture machines as a stand by arrangement, trimix concrete floater,
poker vibration, surface vibrator, Concrete needle Vibrators, Water Tanker,
Excavator, JCB, Roller, earth compactors, Heavy capacity dewatering pumps,
dumpers, tractor with trolley, level machine, total station for layout etc…) as
required to execute the contract are in the scope of the contractor) to execute
the contract are in the scope of the contractor (except specified free issue
materials as mentioned in specific items of SoR Section-E). The contractor
should ensure that all such tools & tackles/equipments/vehicle are in healthy &
working condition. All consumable items would be in the scope of the contractor.
The scope shall include deployment of complete Vacuum Dewatered Flooring
(VDF) system comprising vacuum pump, suction hoses, filter mats, screed
vibrators, needle vibrators, power trowels, leveling instruments, joint cutting
machines, and all ancillary equipment required for proper execution of VDF
Note: If work is suffered due to want of sufficient manpower, tools & tackles,
vehicle, equipments and/or required consumables/materials then 25% of the total
job cost including GST will be levied as a penalty for each and every instance.
(ii) For proper execution of the work as per the scope, the contractor is required to
maintain sufficient quantity of tools & tackles, equipments, etc… in good working
condition at site as per day to day work load and emergency situations to
complete the work in stipulated time.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
(iii) In case of breakdown of equipment, the contractor should work round the clock
for putting back the area in service immediately within minimum time. In case of
any emergency arising during night hours the contractor should be in a position
to mobilize the manpower immediately within minimum time.
(iv) Arrangement for lighting at the work spot has to be made by the contractor. He
has to arrange all lighting equipment such as power cable, hand lamps, supply
boards, cables, etc… as per requirement in sufficient quantity. The contractor
has to take prior approval for taking electrical power supply. The contractor
should keep hand lamps of 24Volt for confined space and sufficient quantity of
240 Volt halogen lamp for other area ensuring safety at work place.
(v) Pin sockets of IS standards should be used for all connections. For any accident
take place & any damage to the equipment and/or injury to human due to
carelessness in loose connection, contractors will be held responsible & liable
for any recovery/actions.
19. CLARIFICATION OF BIDDING DOCUMENTS
If any Bidder requires any further information or clarification in the Bidding
Documents, may notify the Company before one week of last date of submission of
online Bid, in writing or by E-mail at the GIPCL's mailing address [email protected]
as indicated in the 'Invitation to Bids'.
The GIPCL's response (including an explanation of the query) will be sent in writing
or by E-mail to all prospective Bidders who have received the Bidding Documents.
20. TIME SCHEDULE
The basic considerations and the essence of the 'Contract' shall be the strict
adherence to the time schedule for performing the specified 'Works'.
21. UNDERSTANDING AND CLARIFICATION ON DOCUMENTS AND SPECIFICATIONS
The Bidder is required to carefully examine the specifications & documents, all the
conditions and matters work wise & cost wise. If any Bidder finds any discrepancies
or omissions in the specifications and documents or is in doubt for any meaning of
any part, he shall request in writing for an interpretation/ clarification to the GIPCL.
All such interpretations and clarifications shall form a part of the Bid documents.
All the payments against the work order shall be in Indian currency and payable
through cheque or RTGS (online payment) system only based on submission of
required documents like bank mandate form with original cancelled cheque.
23. POINTS TO BE CONSIDERED DURING QUOTING ONLINE PRICE BID
a. The schedule of rates (Section-E) shall be read in conjunction with Instructions to
Bidders, General conditions of contract, Special conditions of contract, Technical
specifications and Bid Drawings.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
b. The quantities given in the schedule of rates (Section-E) are estimated and payment
will be made as per actual work carried out as per the rates of work order.
c. The method of measurement of completed work for payment shall be in accordance
with the method of measurement specified in the Tender in Section-D or as per
standard IS practice. Mode of measurement mentioned in Tender will be prevail.
d. No separate amount shall be payable for use of auxiliary equipment incidental to or
in day to day operation in the course of fulfillment of contractual obligation of the
Note: Interested bidders are requested to submit the online tender at least two days
in advance from the due date set for online submission of bid in order to avoid non-
participation of e-tender due to probable technical problem in e-tender system.
The quantities specified are estimated and for tendering purpose only. Payment will
be made, based on actual work done as certified by Engineer-in-charge of GIPCL.
Quantities of individual items may be revised during the course of contract period
based on any unavoidable alterations/deletions in concept as per approval of GIPCL.
Contractor shall not be entitled for any compensation on ground of such alteration in
given estimated quantities within overall limits of awarded contract price. GIPCL
reserves the right to operate or increase/decrease quantities in each item or omit any
item included in Schedule of Quantity at its discretion. Contractor shall have no claim,
whatsoever, on grounds of loss of anticipated profit etc. on account of the same.
After commencement of the work, GIPCL, for any reason may not require to be
carried out the whole/part of the work as specified in the tender, the ENGINEER-in-
charge shall inform the fact for thereof to the CONTRACTOR and contractor shall
have no claim for any payment or compensation whatsoever on account of any profit
or advantage which he might have derived from the execution of the work in full but
which he did not derive in consequence of the full amount of the work not having
been carried out nor shall he have any claim for compensation by reason of any
change having been made in the original specifications and instructions which shall
involve any curtailment of the work as originally contemplated.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
INSTRUCTIONS TO BIDDERS FOR ONLINE TENDERING & E-
REVERSE AUCTION
SR. DESCRIPTION
1. Tender documents are available only in electronic format and same can be
downloaded from the website: https://tender.nprocure.com or
https://gipcltender.nprocure.com and It can also be viewed from Company’s
website www.gipcl.com
2. Price bid should be submitted online through the website
https://tender.nprocure.com or https://gipcltender.nprocure.comonly. No
physical submission of price bid will be entertained as it should be furnished
3. Bidders who wish to participate in online tenders will have to procure / should
have legally valid Digital Certificate (Class III) as per Information Technology
Act-2000, using which they can sign their electronic bids. Bidders can procure
the same from any of the license certifying Authority of India or can contact
(n)code solutions- a division of GNFC Limited, who are licensed Certifying
Authority by Government of India
4. All bids should be digitally signed. The bidders are required to contact at the
below mentioned address for detailed training on on-line tendering and also
for requirement.
(n) Code Solutions - A division of GNFC Ltd.
403, GNFC Info tower, S.G Road,
Bodakdev, Ahmedabad – 380054 (Gujarat, India).
E-mail: [email protected], website: https://tender.nprocure.com
Interested bidders are requested to submit the online tender at least two days in
advance from the due date set for online submission of bid in order to avoid non-
participation in case of any technical issues (website and/or network) at last moments.
E-REVERSE AUCTION:
i. GIPCL reserves the right to conduct E-Reverse auction through (n) Procure platform.
ii. E-Reverse auction shall be conducted amongst (a) the lowest 50% eligible bidders
(rounded to the next higher whole number) from the total bids received OR (b) Minimum
three (03) lowest bidders, whichever is higher, shall be invited for participation in e-
Reverse Auction through n-procure platform.
iii. Opening Price (including GST), Decrement value and duration for the e-Reverse Auction
shall be informed to the qualified bidders before start of e-Reverse Auction.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
iv. After e-Reverse Auction process, L1 bidder shall be decided on Lowest Total Contract
Price (including GST).
v. To participate in e-Reverse Auction, Bidders have to create e-Auction USER ID on
website: https://e-auction.nprocure.com that the bidder shall be allowed to participate
the e-Reverse Auction.
vi. In case of any further information regarding online bidding or if a Bidder needs any
assistance in accessing/ submission of online bid/ clarification or if training is required for
participating in online e-reverse bidding, then the Bidder can contact the following office
for assistance or training:
(n) Procure Cell, (n) code solutions-A division of GNFC Ltd.,
403, GNFC Info tower, S.G. Road,
Bodakdev Ahmedabad – 380054 (Gujarat)
Fax: 079-26857321 / 40007533, Email: [email protected]
Bidder may visit https://tender.nprocure.com for information regarding e-tendering
registration process.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
GENERAL CONDITIONS OF CONTRACT
1. CONTRACT SECURITY DEPOSIT/ PERFORMANCE BANK GUARANTEE
As a Contract Security/Performance Bank Guarantee, the successful Bidder, to
whom the work is awarded, shall be required to furnish a Performance Bank
Guarantee (PBG)/Contract security deposit (SD) in favour of Gujarat Industries
Power Company Limited for an equivalent amount of ten percent (10%) of the
“Contract Price excluding taxes and duties” from all Nationalized Banks or Axis Bank,
ICICI Bank, HDFC Bank, Kotak Mahindra Bank, IndusInd Bank, Federal Bank,
Bandhan Bank, IDBI Bank and Karur Vysya Bank in the in the format attached in
SECTION-F, and it shall guarantee the faithful performance of the 'Contract' in
accordance with the terms and conditions specified in these documents and
specifications. Contract security deposit/PBG shall be submitted strictly within twenty-
one days from the date of LOI or work order, whichever is earlier.
The PBG/ Security Deposit shall be valid up to “Defect Liability Period” of 12 (Twelve)
months after the date of actual contract completion/contract expiry date (whichever
later) as certified by GIPCL (necessary BG extension/amendments should be carried
out by contractor accordingly as desired by GIPCL). The Contract security/Guarantee
amount shall be payable to the Company in Bidder's home currency without any
condition whatsoever. GIPCL reserves the right to forfeit Performance Bank
Guarantee (PBG)/Contract security deposit.
The Performance Bank Guarantee (initial security deposit) will be returned to the
Vendor/Contractor without any interest at the end of the “Defect Liability Period” after
completion of contract and on fulfilling contractual obligations throughout the “Defect
Liability Period”. However, any delay in submission of SD will result in equivalent late
release of entire SD after “Defect Liability Period”.
Bid security/EMD will be refunded to the successful bidder on receipt of Performance
2. RECOVERY CLAUSE
(i) In case of any damage of equipment/machinery due to negligence of
contractor or any other reasons attributed to contractor the decision of
Engineer-in-charge regarding the amount of recovery shall be final and
binding subject to a maximum of 10% of contract value, including GST.
Recovery will be affected from the monthly bills and/or retention
money/security deposit.
(ii) If the contractor fails to execute the work as per directions of Engineer (I/c)
within the time frame given in work order and as per day to day instructions
by Engineer-in-charge, GIPCL shall get the work done by third party at the
risk & cost of the contractor with 10% additional overhead charges of GIPCL,
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
3. DEDUCTIONS FROM CONTRACT PRICE
All costs, charges or expenses that GIPCL may have paid, for which, under the
contract the contractor is liable, shall be recovered by the GIPCL.
The contractor shall pay all such claims within 15 days of claim, failing which the
same shall be deducted from the bills of contractor.
4. TERMINATION OF CONTRACT BY GIPCL
Contractor shall be responsible for completing the jobs within agreed time schedule
and in case contractor fails to complete the given jobs related to this contract, GIPCL
will engage third party and will recover expenses from contractor’s R.A. bills, Security
Deposit and / or whatsoever for expenses incurred to complete the job along with
additional 10% overhead charges, including GST.
In case if contractor’s services are not found satisfactory with respect to mobilization
to meet emergency requirements, time bound activities, workmanship & safety
(OH&S policy of GIPCL) then GIPCL has right to terminate the contract at any time
by giving 15 days advance notice to contractor without assigning any reason and will
make the alternate arrangement at the risk & cost of contractor.
GIPCL may terminate the contract after due recoveries of pending jobs/damages
after giving 15 days advance notice to the contractor if any of the following events
i. Contractor is adjudged as insolvent.
ii. Contractor has abandoned the contract.
iii. Contractor fails to commence the works, or has, without any lawful excuse under
these conditions suspended the progress of the works for fourteen days after
receiving written notice from the OWNER to proceed.
iv. Contractor fails to proceed with the work with due diligence as per requirements
of the contract and failed to make such due progress as would enable the works
to be completed within the time agreed upon.
v. Contractor fails to remove materials from the site or to pull down and replace
works within 15 days after receiving written notice from the OWNER that the said
materials or work were condemned and rejected by the OWNER under these
vi. Contractor fails to the detriment of good workmanship or in defiance of the
OWNER/ENGINEER’S instructions to the contrary sublet any part of the
vii. Contractor has neglected or failed persistently to observe or perform any of the
acts, matters or things, which as per the contract are to be observed and
performed by the contractor.
viii. Contractor repetitively violating the safety norms for more than three incidents.
ix. Any major contradiction of applicable labour laws.
x. Any major deviations from contractual terms and conditions including quality of
xi. GIPCL reserves the right to terminate the contract without giving any reason
whatsoever and forfeit the PBG/SD.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
5. FAILURE & TERMINATION
If the CONTRACTOR after receipt of written notice from the GIPCL/ ENGINEER
requiring compliance, with such further drawings and / or the GIPCL /ENGINEER
instructions fails within seven days to comply with the same, the GIPCL /ENGINEER
may employ and pay other agencies to execute any such work whatsoever as may
be necessary to give effect thereto and all costs incurred in connection therewith shall
be recoverable from the CONTRACTOR by the GIPCL on a certificate by the
GIPCL/ENGINEER as a debt or may be deducted by him from any money due or to
become due to the CONTRACTOR.
If the contractor fails to execute the work or fails to mobilize the resources and
equipments as per direction of GIPCL/ENGINEER within time frame given and/or fails
to carry out progress of work as per agreed schedule of work planning and/or as per
directions of GIPCL / ENGINEER within the time frame given and/or violating the
GIPCL’s safety rules & regulations, GIPCL/ ENGINEER shall get the work done by
third party at the risk & cost of the CONTRACTOR with additional 10% overhead
charges of GIPCL, including GST and all costs incurred in connection therewith shall
be recoverable from the CONTRACTOR by the GIPCL /ENGINEER as a debt or may
be deducted by him from any money due or to become due to the CONTRACTOR.
In case if contractor’s services are not found satisfactory with respect to mobilization,
time bound activities, workmanship & safety (OH&S policy) then GIPCL has rights to
terminate the contract at any time by giving you 15 days advance notice without
assigning any reason and will make the alternate arrangement at the risk and cost of
the Contractor.
6. SETTLEMENT OF DISPUTES
a. Any disputes or difference of opinion between parties arising out of the contract
to the extent possible shall be settled amicably between the parties. If amicable
settlement cannot be reached all the disputed issues shall be resolved through
arbitration before a Sole Arbitrator appointed by Managing Director, GIPCL
according to the provisions of The Arbitration and Conciliation Act
(Amendment 2021), as amended from time to time. The place of arbitration shall
be at Vadodara/ Surat or any other place within state of Gujarat.
b. Work under the contract shall be continued by the contractor during arbitration
proceedings unless GIPCL shall order suspension thereof or any part thereof in
writing or unless the matter in such work cannot possibly be continued unless the
decision of the Arbitration proceedings is obtained.
7. INTERPRETATION OF CLAUSE
In case of disputes as regards interpretation of any of the clauses or specification,
the decision Chief General Manager (Thermal) / HoM will be final and binding on the
8. EMPLOYEE’S COMPENSATION INSURANCE
Contractor shall take all risk Insurance Policy to cover all his workmen/employees,
staff applicable under the Employee Compensation Act 1923 or any amendment
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
thereof from time to time as also insurance cover for third party liability. The contractor
shall keep the GIPCL indemnified from all liabilities arising out of his action in
pursuance of this contract. The E. C. Policy should be obtained from Surat
Jurisdiction and shall be assigned to GIPCL. EC policy should cover the specified
contract period.
9. STATUTORY REQUIREMENTS
a. COMPLIANCE OF LABOUR LAWS
The contractor shall at his own cost comply with the provision of labour laws, rules,
orders and notifications whether central or state or local as applicable to him or to
this contract from time to time. These Acts/Rules include without limitation the
1. Contractor shall be solely responsible and shall fully comply with all the provisions
of all the labour laws applicable such as the Minimum Wages Act, 1948, Contract
Labour (Regulation & Abolition) Act 1970, Factories Act, 1948, Payment of Bonus
Act 1965, Employees Provident Fund and Miscellaneous Provision Act
Industrial Dispute Act 1947, Workmen Compensation Act 1923, Payment of
Gratuity 1972, Interstate Migrant Workmen Act 1979, Equal Remuneration Act with
Rules, Order and Notifications issued/made there under and as amended from
2. All other Acts, Rules/Bye-Laws, Orders, Notifications etc. present or future
applicable to the contractor from time to time for performing the contract job.
2.1. The Contractor shall provide and be responsible for payment of Wages, Salaries,
Bonus, Social charges, Insurance, Food, Accommodation, Transport, Medical and
Canteen facilities and other statutory privileges and facilities to his personnel as
per law/rules/regulations and orders of the Central Government, State
Government, Local Authorities or other authorities as are in force from time to time.
All employees of the Contractor shall be employee of the Contractor.
2.2. The contractor shall have a valid license obtained from Licensing Authority under
the Contract Labour (Regulation & Abolition) Act,1970 as amended from time to
time at the time of execution of the contract covering all his employees working at
SLPP site and furnish the same failing which GIPCL may terminate the contract at
its sole discretion.
2.3. The Contractor shall at the time of execution of the contract have a EPF Code
Number obtained from the Authorities concerned under the Employees Provident
& Miscellaneous Provisions Act, 1952, as amended from time to time and remit
contributions in respect of the employees employed by him at SLPP Site to the
P.F office concerned every month failing which GIPCL will recover from the
outstanding payment to the contractor from GIPCL.PF code of Gujarat region
should be taken.
2.4. The Contractor shall maintain all records/registers required to be maintained by
him under various labour laws mentioned above and produce the same before the
Statutory Authorities whenever required.
2.5. The Contractor shall also submit periodical reports / returns to the various statutory
authorities such as those under the Contract Labour (Regulation & Abolition) Act-
1970, Employees Provident Fund Act, as amended from time to time, etc., under
intimation to HR & Admn. Dept.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
2.6. The Contractor shall not pay less than the Minimum Wages notified by the
Government from time to time to his employees of corresponding categories.
2.7. The Contractor shall be responsible for payment of overtime wages to his
workmen, if any, in case they are required to work beyond the prescribed hours
under law as per applicable rates.
2.8. The contractor shall take Workmen Compensation Insurance Policy for all his
employees working at GIPCL. The contractor shall indemnify the company against
any liability due to any work injury or accident to any of its employees.
2.9. The Contractor shall in the event any of his workmen / employee sustains any
injury or disablement due to an accident arising out of and in the course of his
employment, provide necessary medical treatment and pay compensation as
applicable, required under the Workmen’s Compensation Act, 1923 as amended
from time to time.
2.10. If any of the persons engaged by the Contractor misbehave with any of the officials
or the Company or commit any misconduct with regard to the property of the
Company or suffer from any serious communicable disease, the Contractor shall
replace them immediately.
2.11. The Contractor shall not engage / employ persons below the age of 18 years.
Employment of women shall be strictly according to applicable laws.
2.12. GIPCL will have right to deduct and disburse the claims of the individual / parties
being a principal employer on any account whatsoever in relation to their
employment with the contractor. The Security deposit will be released to the
contractor at the end of the contractual tenure subject to an undertaking by the
contractor that in the event any of his workmen or the heirs of workmen puts up a
claim for recovery of money due to him from the contractor before the appropriate
authority under the I.D.Act 1947 or under any other labour laws or for
compensation under the Workmen’s Compensation Act, 1923 as amended from
time to time and the appropriate authority has given a direction for making payment
the contractor will meet the same or indemnify GIPCL if in the event GIPCL pays
it as Principal Employer.
2.13. The contractor shall make payment of wages to his employees on fixed date within
the period specified under the applicable Law, in presence of representative of the
company. He will submit a true copy of wage sheet, attendance register and P.F.
remitted challans on monthly basis to HR&A dept. for verification and record.
2.14. The Contractor shall provide Safety items/kits to his employees such as safety
shoes, goggle, ear plug, hand gloves, safety belt etc, if any, required under law.
2.15. The contractor shall conduct pre-induction and periodic medical checkup of his
workmen as per applicable laws.
2.16. The contractor shall be solely responsible for any accident caused to his workers
and should adhere to all rules / regulations as per labour laws of Government and
other statutory laws as applicable.
2.17. The contractor should register himself under the Contract Labour Act, Employee
Compensation Act and PF Act, as amended from time to time (Code no. to be
mentioned) and submit the copy of registration certificate and should possess the
same from the date of commencement of work, failing which the contract is liable
to be cancelled. The E.C. Policy copy should be submitted to the GIPCL before
commencement of the work and Labour License should be obtained within one
week from the date of issue of form-V. Contractor should apply for Form-V
immediately after receipt of LOI. A copy of Labour License shall be submitted to
GIPCL, HR & A Department.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
2.18. Contractor shall have to insure his workmen /supervisors etc. under Group
Insurance scheme.
2.19. The Contractor shall be responsible for compliance of all statutory rules,
regulation, act enforced from time framed by the government such as Factory Act,
Employee Compensation Act, payment of ‘Wages Act’, Minimum Wages Act’,
Provident Fund Act, All Labour Laws Act, as amended from time to time in respect
of employees engaged by him for the work and shall have to maintain necessary
records. In case any amount becomes due to be payable by him to his employees
or to the Government under the above rules, regulation, Acts, GIPCL reserves the
right to recover the same from the running bill of the contract.
2.20. Documentary evidence of deposit of PF paid shall have to be produced by the
contractor along with the next bill.
2.21. Records as per the provisions of various statutory Acts will have to be maintained
by the contractor and submitted as and when required.
2.22. All employees of contractor should maintain due discipline and respect local
sentiments. GIPCL reserves the right to direct the contractor to remove any such
person who does not comply with it.
2.23. The list is indicative in nature and not an exhaustive one. Any
amendment/alteration/Notifications or addition to the existing Law or a new statute
shall automatically and immediately become applicable.
2.24. All laws, rules, regulations, notifications, etc. stated in this tender document shall
be applicable as amended from time to time. Where applicable self-certified true
copies of the required documents to be furnished, unless stated otherwise
b. LEGAL ASPECTS
1. Contractor shall maintain all register required under the Labour Laws and make the
payment as per the Minimum Wages Act, as amended from time to time to the
workers employed by him/her.
2. Contractor shall obtain requisite license to carry out this contract under the provisions
of Contract Labour Act, 1970, as amended from time to time and maintain necessary
records and registers under the said Act.
3. Contractor shall submit a copy of each of the registration certificates with respect to
Employees Provident Fund and Employee Compensation Act, as amended from time
to time within one week time, from the date of award of this contract.
4. Contractor’s employees, agent or sub-agent shall not smoke or light anything within
the premises of the GIPCL and carry match box / lighter or any other explosive and
/or inflammable material inside the plant.
5. Contractor shall abide by all the statutory rules and regulations like P.F, Labour Laws,
as amended from time to time, etc.
6. Contractor shall issue an appointment order to each casual labourer stating therein
the nature of job to be performed by him/her and fix time for which the concerned
labourers are likely to be deployed. Contractor shall also issue a temporary identity
card specifying the period for which the labourer has been deployed.
7. Contractor is fully liable for the persons engaged by him/her for above work; however,
GIPCL reserves the right to deduct any amount legally justified towards any liability
8. Contractor shall indemnify GIPCL from any liabilities arising out of the employment
of the manpower.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
9. If the contractor fails to complete the allocated job within specified time frame, GIPCL
shall get the work done by third party at the risk and cost of contractor.
10. PAYMENT OF WAGES
Contractor shall be responsible for compliance of all statutory rules, regulation, act
enforced from time framed by the government such as Factory Act, Employee
Compensation Act, payment of ‘Wages Act’, Minimum Wages Act’, Provident Fund
Act, Payment of Bonus Act, Labour Law Act, maternity benefit act, as amended from
time to time in respect of employees engaged by him for the work and shall have to
maintain necessary records.
In case any amount becomes due to be payable by him/her to his
employees/agencies or to the Government under the above rules, regulation, Acts,
GIPCL reserves the right to recover the same from the running bill of the contract.
11. ACCIDENT TO WORKMEN
Contractor shall be fully responsible for injury or death of any of your or third-party
workmen due to any act omission / indiscretion on contractor part while undertaking
the work and contractor shall fully abide by the statutory requirements of the
employee's compensation act.
GIPCL shall not be liable for any compensation due to accident, death or injury to
any of contractor’s workmen or any third party due to negligence, act or omission on
contractor part.
Contractor shall arrange & provide sufficient General area lighting as well as work
area specific lighting. Contractor shall also arrange DG set of required capacity for
day to day work requirements and lighting requirements in case any power supply
interruption from GIPCL.
13. NIGHT/SUNDAY/HOLIDAY SHIFT
The contractor shall depute qualified and adequate resources in night
shift/Sunday/holidays for any emergency job, which may come up at
night/Sunday/holiday.
14. SAFETY ASPECT
Contractor shall observe all the safety and security rules and regulation of the GIPCL
which are at present in force and which may come into force during the pendency of
the contract. Any violation of any rules and regulations will entail immediate
termination of the contract.
When contractor moves his/her lifting tools and tackles to the plant area, required
test certificates as per the Factories Act 1948, as amended from time to time and the
state factories rules has to be submitted to safety Dept. Safety Dept. will check the
certificates and if found okay, then only materials will be allowed to enter inside the
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
plant. Material inward gate pass will be made only after certification from Safety Dept.
Security Dept. will inform to Safety Dept., as & when such tools and tackles brought
at the gate for making entry in the maintenance site.
The contractor has to submit the list of required safety gears along with safety
equipments available with him/her to safety Dept. Safety Dept. will check for quantity
and quality of the safety gears and then allowed permission of work. Poor quality
material will not be allowed to take inside the Plant. If quantity of required safety
equipments is not satisfactory, contractor will not be allowed to carry out the work
using such safety gears inside the Plant for the work.
15. GENERAL SAFETY CLAUSES
1. The Contractor shall observe and comply, with regard to his workmen working at the
SLPP site, the safety norms as per the safety operating standards.
2. The Contractor shall ensure that his workmen are informed and trained regarding the
safety standards to be adopted while operating within the SLPP Plant & Mines
premises and the Contractor shall brief them regarding the same and use of the
Personal Protective Equipment (‘PPE’).
3. The Contractor shall issue safety shoes and safety helmet of IS standard to all his
workmen immediately on execution of the work and the contractor shall ensure that
his workmen wears the protective equipments at all times during the work operation.
Following brand of the safety shoes and helmet shall be issued to contract workmen.
Contractor shall issue safety shoes every year.
Sr No. Model Company Specifications
01. Tough Hat, HP-TH Sure Safety
IS : 2925 – 1984, ANSI / ISEA
03. PN 521 - Shelmet Karam
SR. No. Name of Manufacturer Model
SSTEELE (Strom) – Double Density or
1 Acme Fabrik Plast Co.
TRIMAX(Adjacent) – Double Density
2 Favourite Safety Products. Waves Nile D/D or FSP Nile DD
4. Other safety gears like ear plug, dust mask, hand gloves, safety goggles, gum boots,
full body safety uniform and belts, safety net etc. shall be issued and used as per the
job requirements. Safety helmet shall be of YELLOW COLOUR ONLY. Contractor
will procure safety shoes & safety helmet from a reputed company with at least
months’ guarantee and shall produce the guarantee certificate and IS standard
certificate to the safety department. Contractor should purchase safety shoes of
reputed brands. Safety shoes will be issued every year. IS certificate and guarantee
certificate must be obtained from the vendor and submitted to the Safety department.
Safety shoes should be heat, water, oil and chemical resistant, having an anti-
slippery sole of 15298- 2002 make.
5. It is the duty of contractor to ensure that his workmen are wearing required PPEs as
per work requirement. Contractor should ensure that their workers are wearing Safety
helmet, safety shoes, dust mask, goggles, ear plug etc. at all times when they are at
work throughout the contract period. The contractor may be asked to maintain the
PPE issue registers with signature of workmen.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
6. Contractor will reissue these PPEs in case of damage or misplacement of the same.
Replacement shall be made immediately.
7. The contractor shall be responsible for providing first aid or emergency medical help
and treatment to his workmen in the event of any accident or injury.
8. If it is observed that contractor is not issuing required PPEs timely and that of required
quality, GIPCL will issue the required PPEs to contract workers and back charge the
same with 25% overhead charges of GIPCL, including GST.
9. All lifting tools and tackles shall be duly certified by competent person in conformity
with the statutory requirements and certificate in form no. 10 as per rule 60 of Gujarat
Factories Rules, 1963 and section 29 of the Factories Act, 1948, as amended from
time to time shall be submitted every year before using such tools and tackles. In
case of purchase of new lifting tools and tackles, form no. 10 as per the said rules
shall be submitted before they are taken into use. All lifting tools and tackles shall be
of reputed make having International manufacturing standard and shall be
maintained in proper and workable condition.
10. The Contractor shall nominate one Safety Officer with required qualification for
supervising the daily job/ shutdown jobs for observing and maintaining the safety
aspects at site. He is solely responsible for any safety measures during maintenance
work. He has to ensure that all the workmen working at site are equipped with
essential PPE’s and proper safety arrangement is made at the SLPP site.
11. After mobilization of any tools & tackles to site, which includes chain pulley blocks,
D-shackles, wire ropes, winch machines, Mobile crane, Hydra etc. shall be offered
for inspection with all above statutory test certificate before using at site for any work.
They should use all tools and tackles only after certification by GIPCL
representative/safety officer.
12. When working at height, working on ceiling or roof covered with fragile materials, full
body harness safety belt, ladders and crawling boards, fall arrester, etc. shall be used
to prevent accident. Further, during working on height, contractor should arrange
proper scaffolding of still pipes, safety net, full body safety belt, fall arrestor system
etc. Advice and instructions of Engineer-in-charge/ safety in charge shall be strictly
complied with in this regard. All necessary safety precautions shall be taken by the
contractor to prevent accident and personnel injuries while working on height.
13. Flash back arrestors made of reputed manufacturer shall be provided on cutting torch,
on DA cylinders and on O2 cylinder. Cylinder caps also required for handling the
cylinders at the work at height area. Gas cylinders shall be transferred through gas
cylinder trolley only with cylinder cap and stored up right (vertical) position only. All
gas cylinders shall be hydro tested / certified as per gas cylinder rules 2004. Gas
cylinders shall be stored, handled as per gas cylinder rules
14. All vehicles shall be operated by licensed drivers only. All vehicles’ PUC to be tested
as per Government approved RTO guidelines. All Vehicles must be parked in Parking
space designated by GIPCL. If any vehicle is found inside the plant premises other
than the parking area such vehicles shall be handed over to Security dept. and their
entry shall be cancelled for movement inside the plant premises with immediate
15. All electrical equipment shall be in good condition and free from any defect. Electrical
tools & equipments i.e. welding machine, grinding and drill machine etc. may be
checked by the electrical engineer of the contractors regularly, every six month at
least and report to be submitted to concerned HOD and safety depts.
16. During hot work, contractor will use fire curtains like asbestos sheets or fire blankets
to prevent falling and spreading of sparks and hot material on and around the work
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
area. Contractor will procure and use such items. ELCB / RCCB shall be provided
with rating of 9-30 milli amperes on welding machine and all portable power tools.
17. The contractor shall fill – up Incident notification form (S-I), Incident Investigation form
(S-II) and near miss report within time limit as specified in forms, if any accident,
Incident, near miss occurred while working at SLPP site.
18. Major AMC / ARC contractor (Where the man power strength is more than 50 and
above) should appoint / nominate one qualified safety officer and he shall be
responsible for addressing all the safety related aspects of execution of contract jobs
and he will in close co ordination with safety officer of SLPP and attend all safety
related meeting such as safety committee, on job safety training etc. Where the
contractual man power is less than 50, the site incharge of the contractor will act as
a safety officer and he will perform all the duties of safety officer as mentioned above.
19. No loose connection / joints allowed in electrical cables during performance of any
20. Safety shoes to be issued to female employees also.
21. All the vehicles shall be fit as per RTO guidelines and valid fitness certificate is
required as per RTO guidelines.
22. The Contractor’s nominated safety officer shall be imparted regular on-job safety
training like tool-box talk etc. and submit a record of such training in safety dept,
respective dept and HR&A dept.
23. The Contractor shall comply all the new requirements related with safety as informed
by the HOD / Safety department from time to time.
24. Penalty to be imposed for Violation of safety norms is proposed as follows:-
The Contractor & Contract workmen shall strictly adhere to Safety standards /
Guidelines as per practices. The list provided below is an indicative list to explain the
principles behind safety practice.
If the contract workmen fail to comply with safety standards as per category A, B & C
below, penalty shall be levied on the contractor as per the table mentioned below:
Category Classification Examples / Cases Penalty
A PPEs Working without helmet, shoes, safety Rs.100 /- per instant.
Related belt, gloves etc.
B WI Related Failure to adhere to HSE
guidelines/plans, careless attitude in Rs.500 /- per
material handling, instant.
Machine being used with damaged
machine guard, unsafe electrical work - After three
workout plug top/improper electrical incidence,
joints/cables lying on ground, electrical Per incidence
equipment working without proper Rs.2500/-
earthing, machine being used without
machine guard, Welding machine Continuous
without ELCB / RCCB of proper rating, unsafe acts
Gas cylinder without test certificate, will disqualify
Cylinder cap, NRV / Flash back the contractor
arrester, Cylinder trolley etc. from further
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
Unsafe working practices at height participation
more than 3 meters in tender
Working without permit or non- with GIPCL-
compliance with permit conditions like SLPP.
hot work, height work etc. as applicable,
lifting tools and tackles being used
without third party inspection
certificates in form no. 9/10 as per
Factories Act – 1948 etc..
C Unsafe Breach of safe practices by a particular Suspend the entry gate
Practices person repeatedly for three times. pass for one week.
After two suspensions
his gate pass will be
Penalty so levied against the contractors and company employees will be used during the
observation of National Safety Day.
The contractor, workmen following good safety practices in their work area
continuously will be rewarded / honored on National safety day.
15.1 GENERAL ELECTRICAL SAFETY RULES & REGULATIONS
Electrical safety
a. All the electrical apparatus including welding machine (either 3-phase or single
phase) should be provided with Earth Leakage Circuit Breaker (ELCB/RCCB/RCBO)
of 30mA rating.
b. Bidder/Contractor should ensure periodic checking of ELCB provided in their
electrical apparatus.
c. Bidder/Contractor should ensure that there should not be any joint in the power
supply cable of any machine. All cables should be in good condition with no bare
insulation or frayed wires
d. Any power supply switchboard/extension boards brought by Bidder/Contractor
should have ELCB of 30mA rating and it should have sockets along with 3-pin plug.
e. Any type of cable brought by Bidder/Contractor should not have any joint and should
be of sufficient capacity for the respective job.
f. Bidder/Contractor to bring their own 24V rating portable hand lamps along with cable
of (apparatus should be having 230V / 24V transformer) for the temporary lighting
arrangement required at site for the respective jobs.
g. Bidder/Contractor should bring sufficient quantity no. of temporary light fixtures (230V
or 24 V as per requirement of job/contract), extension boards, cables to draw supply
from nearest power point.
h. Hand-held and portable machines shall be equipped with a built-in switch to switch
off power in case of emergency
i. Bidder/Contractor to ensure healthiness of their electrical equipment whenever
brought to GIPCL site and get them tested / verified by GIPCL Electrical Department
representatives before start using.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
j. Bidder/Contractor to ensure - All portable electric apparatus shall be regularly
examined, tested and maintained to ensure that the apparatus and leads are in good
k. Only three-core cable shall be used for single phase operated tools with the third core
connected to earth.
l. Ensure that all metallic portable appliances are provided with 3 pin plug and socket
connections with third pin be connected to the ground terminal where ever possible.
Also, the metal work of the apparatus is effectively earthed.
m. All cables and connections should be sound and of adequate capacity and properly
insulated while using any welding machine and other power connections.
n. The earthing arrangements should be properly made with earthing clamps or a bolted
terminal while using any welding machine
o. Electric holders when not in use, should be placed on an insulated hook or the holders
should be fully insulated while using any welding machine
p. Whenever the welder stops or leaves work for any appreciable time, the power supply
to welding machine shall be effectively disconnected while using any welding
q. GIPCL will provide either single phase OR 3-phase 3 wire power supply from the
nearby point at job site. Bidder/Contractor to supply the required cable between
GIPCL power supply point to equipment brought by Bidder/Contractor for the
specified job. Further, if Bidder’s/Contractor’s equipment requires 3-ph 4 wire supply
then they should derive 3-ph 4 wire supply from GIPCL 3-ph 3 wire supply system by
incorporating sufficient capacity transformer. Like for hydro jet cleaning system, mixer
machine, induction heating machine, SR machine etc., GIPCL will provide 3-ph 3 wire
r. Cable between welding machine to GIPCL power supply point should have cable
TOP plug towards GIPCL power supply point of Make BALS having rating as 63 Amp.
Contractors not following above electrical safety points at any point of time are liable to
penalty and their machine/ apparatus shall be seized by GIPCL.
16. REJECTION OF WORK
If, as a result of inspection, examination or testing, the GIPCL’s
Representative/Engineer decides that any materials, work or workmanship is
defective or otherwise not in accordance with the Contract, the GIPCL/Engineer/
GIPCL’s Representative may reject such plant, materials, work or workmanship and
shall notify the CONTRACTOR promptly, stating his reasons. The CONTRACTOR
shall then promptly make good the defect and ensure that the rejected item complies
with the Contract. If Contractor failed to rectify the rejected work or workmanship,
GIPCL/Engineer reserves the right to deduct or withhold amount against rejected
work or Workmanship. CONTRACTOR shall not entitle for any claim or release of
hold payment until rectify the defect up to satisfactory of GIPCL. If Contractor failed
to rectify any such defective work or workmanship, GIPCL reserve the right to rectify
at risk and cost of the CONTRACTOR and deducted by the GIPCL from any amount
due, or to become due, to the CONTRACTOR’s dues.
If the GIPCL’s Engineer/GIPCL’s Representative/Consultant requires such materials,
work or workmanship to be retested, the tests shall be repeated under the same
terms and conditions. If such rejection and retesting cause the GIPCL additional costs
for the traveling and lodging costs of GIPCL/Engineer’s personal for attending the
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
retest, such costs shall be recoverable from the CONTRACTOR by the GIPCL and
may be deducted by the GIPCL from any amount due, or to become due, to the
17. GENERAL TERMS AND CONDITIONS
a. All tools & tackles, labours, supervisors, materials (except specifically specified
free issue materials under respective items of SoR in Section-E), consumable
items, equipments, etc… to execute the contract are in the scope of the contractor.
The contractor should ensure that tools & equipments are in healthy condition.
b. The decision of the Engineer-in-charge shall be final and binding on the contractor
for defining the terms and condition included in this contract.
c. If the work is not found satisfactory, Engineer-in-charge reserves the right to take
suitable action.
d. Contractor shall depute full time independent experienced site-in-charge and
independent site supervisors/Engineer at site. They shall co-ordinate with GIPCL
engineer and shall bear overall responsibility of contract including taking daily work
instructions, work permits, gate-pass, receipt of MIV & specified free issue material
from GIPCL store, site executions, maintaining records of work, material, inward
challans, material & manpower gate-pass, joint measurement recording, billing etc...
Such person shall function from site office of contractor at SLPP.
e. Contractor shall also nominate one safety supervisor at site and shall submit
nomination of safety supervisor in writing before commencement of contract. Safety
supervisor shall arrange small safety talk on every day morning or whenever required
with all workers working under this contract. He shall coordinate with concern
Engineer-in-charge on daily basis and report daily observations, tool-box talk records
etc. The work shall not be allowed without deploying/nominating safety supervisor
and a penalty equal to Rs.1,000/- per day absent of nominated safety supervisor shall
be levied from Contractor.
f. Contractor shall strictly follow the existing work permit system of the GIPCL and any
future revisions.
g. The contractor has to take EC insurance policy for their workmen. The contractor has
to submit labour license (if applicable) and PF account number to the Engineer-in-
charge before start the work.
h. The contractor has to do the job timely. GIPCL shall not compromise in delay. In case
of delay of work without any valid reason, the GIPCL reserves the rights to carry out
the work by deploying other agencies at the risk & cost of contractor with additional
10% overhead charges.
i. Contractor shall mobilize the resources as per need within the period of four hours. If
the contractor fails to mobilize sufficient resources to complete the job in time, GIPCL
will execute the job through other agency at the risk and cost of the contractor with
additional 10% overhead charges including GST.
j. Contractor should mobilize all resources for efficient & smooth execution of contract
within seven to fifteen days from the date of issue of Letter of Intent/Work Order.
k. The prices / item rates quoted (based on quoted % above/equal or below SoR) shall
remain firm till completion of the contract and any agreed extensions thereafter and
shall not be subject to any escalation, idle charges for labour, machinery, overhead
expenses etc… due to any reason whatsoever. No price escalation / idle charges
shall be entertained due to delay in work on unavailability of work front, any changes
/ modification / alteration of plan, non-issue of work permit, holding of work permit for
any reason, unavailability of contractor’s supervisor/Engineer, unavailability of
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
contractor’s safety supervisor, violation of safety rules, unsafe act by any of
contractor’s worker, negligence & ignorance of safety & quality instructions of GIPCL
Engineer-in-charge or any other reason whatsoever.
l. Contractor must fulfill all the safety regulations and to take safety measures to avoid
hazards. Contractor shall arrange all standard adequate healthy safety PPEs like but
not limited to approved quality safety shoes & safety helmets, standard dust masks,
safety goggles, safety hand gloves, safety belts, fall arrestors, other required safety
tools, etc… as required and shall use exclusively under this contract for all the time
during working at specified locations failing which, the Engineer-in-charge may hold
the work and will take necessary action including penalty as decided. If the contractor
repeatedly violates safety rules/regulations (more than three successive incidents),
Engineer-in-charge may take necessary action against the contractor, including
appropriate financial penalty (Maximum of Rs.1,000/- per incident per man-day and
as per above clause no. 15) and/or termination of contract.
m. One or more jobs may be required to be done simultaneously and contractor shall
mobilize additional resources accordingly.
n. Timely completion of all jobs and works shall be the essence of this Contract.
Contractor should closely monitor each activities and complete the jobs as per the
time given by and under the supervision of the Engineer-in-charge and shall ensure
that sufficient manpower is deployed for the same.
o. The contractor has to complete the works as per the planning schedule and their
respective supervisor has to interact with Engineer-in-Charge for PTW (Permit to
work), work instruction, Return of permit.
p. The contractor has to submit daily reports / information of work carried out with details
of available manpower, equipments / material etc… as directed by Engineer-in-
q. Any job other than the listed jobs in work order shall be executed by the contractor
on instruction from GIPCL and payment shall be made to the contractor on respective
item rate only.
r. The Government of India has enacted the Micro, Small and Medium Enterprises
Development Act, 2006 (the “Act”) and the Act has come into force from October
2006. The Bidder shall confirm whether your organization is registered under the
Micro, Small and Medium Enterprises Development Act, 2006, as amended from time
to time. If your organization is registered under the Act, please specify the category
i.e., Micro Enterprise, Small Enterprise or Medium Enterprise under which it is
registered and kindly attach a copy of your registration certificate.
s. The Bidder shall provide details of registration along with copy of the registration
certificate issued by the District Industries Centre/Department of Industries, etc of the
respective State Government. It is to be noted that large scale industries and trading
firms have been excluded from the purview of the Act.
t. GIPCL is an ISO 9001-2015 (Quality), ISO 14001-2015 (Environment), 45001-2018
(OH&S) and 50001-2018 (EnMS) certified company, and GIPCL gives extreme
importance to maintain these global standards. Contractor shall be required to
observe these standards as amended time to time while working with GIPCL.
Contractor should ensure that his workmen/labour work in accordance with them.
18. CONTRACTOR’S SUPERVISION
The contractor shall, during the whole time the work is in progress, employ a qualified
experienced site-in-charge of the works with adequate experience in handing of jobs
of this nature and with the prior approval of the GIPCL / ENGINEER. Such in-charge
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
shall be constantly in attendance at the site during working hours. During
CONTRACTOR’S supervisory engineer absence during working hours, if
unavoidable, and also beyond working hours, when it may be necessary to give
directions, orders may be given by the ENGINEER / GIPCL and shall be received
and obeyed by the CONTRACTOR’S superintendent or Foreman who may have
charge of the particular part of the work in reference to which orders are given. If
requested to do so, the ENGINEER /GIPCL shall confirm such orders in writing. Any
directions, instructions or notices given by the ENGINEER / GIPCL to him, shall be
deemed to have been given to the CONTRACTOR. The representative of the
CONTRACTOR shall have all necessary powers to receive materials from the
GIPCL, issue valid receipts for the same, engage labour or purchase materials and
proceed with the work as required for speedy execution.
None of the CONTRACTOR’S Superintendents, engineers, supervisors or labour
should be withdrawn from the work without due notice being given to the GIPCL /
ENGINEER; further no such withdrawals shall be made if in the opinion of the GIPCL
/ ENGINEER such withdrawals will jeopardize the required pace of progress /
successful completion of the work.
The CONTRACTOR shall employ in or about execution of the work only such persons
as area careful, skilled and experienced in their respective trades, and the GIPCL
shall be at liberty to object to and require the CONTRACTOR to remove any person
employed by the CONTRACTOR in or about execution of works who in the opinion
of the OWNER misconducts himself or is incompetent or negligent in the proper
performance of his duties and all such persons shall not again be employed upon the
works without the prior permission of the GIPCL. Neither the CONTRACTOR and the
PURCHASER nor the ENGINEER shall hire or employ any employee of the other
party except by mutual consent.
19. CONTRACTOR TO REMOVE ALL OFFENSIVE MATTER IMMEDIATELY AND
All loose materials, wastage, packing materials, empty paint drums, cut pieces or
other matter of an offensive nature shall not be deposited on the surface, but shall at
once be carted away by the CONTRACTOR to some pit or place provided by him
away from the site of work and approved by local authorities.
As a part of the work included in this contract, the CONTRACTOR shall completely
remove and satisfactorily dispose of all temporary works & remove scaffolding
materials to the extent directed. He shall tear down and dispose of all temporary
works, shall remove or grade, to the extent directed, all plant and equipment, shall
satisfactorily dispose off all rubbish resulting from the operations under this contract
and shall do all work necessary to restore the territory embraced within the site of his
operations to at least as good order and conditions as at the beginning of the work
under this contract.
20. FACILITIES TO BE PROVIDED BY GIPCL
A. The Company shall provide the following facilities to the Contractor at the site:
a. Electricity & water at nearest available one point as available. Further distribution
to be done by contractor at their cost.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
b. Quarter/room & food for supervisors/engineers on chargeable basis in GIPCL’s
township as available. Food on chargeable basis at GIPCL’s Industrial Canteen
as available. If not available, contractor to make his own arrangement for lodging
and boarding locally or as appropriate at his cost.
c. Workshop facility as available at site only. However, contractor may visit the
workshop to ensure the existing facility. For the facilities other than available,
contractor has to carry out the job outside at their own cost.
d. GIPCL may also provide free hydra (based on availability) only for shifting of
heavy structural plates, beams, etc… and also erection of heavy structures,
etc… on discretion & directives of Engineer-in charge of GIPCL.
e. Space for contractor’s office & store as decided by GIPCL based on availability.
f. First aid facilities as available on chargeable basis. If not available contractor to
make his own arrangement for the same locally or as appropriate at his cost.
Apart from the above, no other facilities shall be provided by GIPCL.
B. GIPCL shall also conduct an orientation program appraising the workmen
regarding the safety norms and measures to be observed during work operations
at the plant site.
21. WORK CERTIFICATION
a. The work to be performed being a specialized nature, the contractor should be
fully conversant with modern practices and should be able to carry out works
independently of large thermal power plant. The contractor shall therefore be
required to engage qualified/ experienced personnel to undertake the work as per
specifications and requirement.
b. Contractor should maintain one computer with printer for keeping daily records
and maintain the data.
c. All the work measurements shall be jointly recorded in a measurement
sheet/register/relevant documents by the contractor / authorized representative
of the contractor and the Engineer-in-charge.
d. The measurements shall be clearly written indicating date of measurement,
location, reference to drawings, if any and jointly signed.
e. The Contractor shall be required to furnish satisfactory job completion report to
GIPCL. The submission of report should be on daily basis for executed works.
The monthly bill payment shall be released based on the certified reports of the
f. Inspection of work will be done by Engineer-in-charge or his authorized
representative. If the work is not found satisfactory Engineer-in-charge reserves
the right to take suitable action and shall be binding to the contractor.
22. FORCE MAJEURE
i. In the event of either party being rendered unable by Force Majeure to perform
any obligation required to be performed by them under this Contract, relative
obligation of the party affected by such Force Majeure shall be treated as
suspended during which the Force Majeure Clause lasts.
ii. The term “Force Majeure” shall have herein mean riots (other than among the
Contractor’s employee), Civil commotion, War (whether declared or not),
invasion, act of foreign enemies hostilities, civil war, rebellion, revolution,
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
insurrection, military coup, damage from aircraft, nuclear fission, embargoes,
quarantines, acts of god such as earthquake (above 7.0 magnitude on Richter
scales), lightning, unprecedented floods, fires not caused by the Contractors
negligence and other causes which the Contractor has no control and accepted
as such by GIPCL whose decision shall be final and binding. Normal rainy season
and monsoons are not Force Majeure.
iii. Upon occurrence of such causes and upon its termination, the party alleging that
it has been rendered unable as aforesaid, thereby, shall notify the other party in
writing by registered notice within 24 (twenty-four) hours of the alleged beginning
and ending thereof giving full particulars and satisfactory evidence in support of
iv. Time for performance of the relative obligation suspended by the Force Majeure
shall stand extended by the period for which such clause lasts.
v. If works are suspended by Force Majeure conditions lasting for more than two (2)
months, GIPCL shall have the option of cancelling this Contract in whole or part
thereof, at its discretion.
vi. The Contractor shall not claim any compensation for Force Majeure conditions
and shall take appropriate steps to insure men and materials utilized by it under
the Contract well in advance.
The Contractor shall indemnify and keep harmless GIPCL from and against all
actions, proceedings, claims, demands, losses, costs, damages and expenses
whatsoever which may be brought against or suffered by GIPCL which it may sustain,
pay or incur as a result of or in connection with the performance/ purported
performance/ non-performance of the contract by the Contractor. In case, in any
litigation pertaining to labour employed through contractor if any direction or order is
issued by court at any point of time the contractor shall comply with and implement
such direction or order whether passed at the time of award of contract or during the
pendency of contract.
Further, the Contractor shall indemnify the GIPCL against all consequences arising
and affecting GIPCL owing to the compliance of the orders by the Contractor.
24. GOVERNING LAW AND JURISDICTION
This tender document and contract shall be governed by the laws of India and the
Courts at Surat shall have jurisdiction regarding the same.
25. Where any portion of the General Condition of Contract is repugnant to or at variance
with any provisions of the Special Condition of Contract, then unless a different
intention appears, the provision of the Special Conditions of Contract shall prevail to
the extent of such repugnancy or variance.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
SPECIAL CONDITIONS OF CONTRACT
1. DETAIL SCOPE OF WORK
1.1 CIVIL WORKS
The scope of work under this contract shall broadly include, but not be limited to, the
execution and completion of all associated Civil works (foundations, footings, flooring,
associated area development works, etc…) at Surat Lignite Power Plant (SLPP) for
construction of two nos. of Pre-Engineered Building (PEB) Structural Storage Sheds
near warehouse.
Scope of work includes all Civil works for construction of new 02 nos. of PEB structural
storage sheds near existing warehouse at Surat Lignite Power Plant, Village; Nani
Naroli, Dist. Surat, as per detailed specification, drawing and as specified in item
nomenclature of Bill of Quantities.
The scope of work covered in this specification consists of collection of all site related
data, supply of all materials, labours, fuel, oils, equipment/machinery, AJAX Machine
with weighment printing facilities for concrete works, 02 bags capacity Batching
Mixture machines as a stand by arrangement, trimix concrete floater, poker vibration,
surface vibrator, Concrete needle Vibrators, Water Tanker, Excavator, JCB, Roller,
earth compactors, Heavy capacity dewatering pumps, dumpers, tractor with trolley,
level machine, total station for layout, cube testing machine and other laboratory
equipment’s as required for field quality control, all type of consumables, approved
construction materials, etc. as per detailed Technical Specifications for completion of
Civil work on item rate basis. The scope shall include deployment of complete Vacuum
Dewatered Flooring (VDF) system comprising vacuum pump, suction hoses, filter
mats, screed vibrators, needle vibrators, power trowels, leveling instruments, joint
cutting machines, and all ancillary equipment required for proper execution of VDF
flooring. The scope of work also includes fixing of structural materials like insert plate,
pipe sleeves, foundation bolts, etc… by using standard templates (provision for
providing required size & nos. of templates is included in scope of work with no any
additional payment), anchor bolt, edge angle, nuts & bolts, etc. as per details given in
the tender document. The scope works shall cover for all services required for
completion of Civil works in all respect. The scope will cover but not limited to the
following buildings / structures / systems / facilities.
The scope of work in general comprises all types of Civil Works, including but not limited to:
Area grading and site clearing,
Excavation including dewatering, backfilling, and compaction,
Foundations, plinth protections, drains & flooring,
Plain and Reinforced Cement Concrete (PCC & RCC) works,
Contractor shall explore possibility of available RMC in the vicinity (within about 20KM
lead from Surat Lignite Power Plant) for major concreting as directed by Engineer-in-
Masonry works, rubble soling, flooring, plastering, and tiling,
Civil painting,
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
Laying of Hume pipes,
Reinforcement & shuttering work for foundation, pedestal, plinth beam, lintel beam,
drain, coping, column, etc
RCC Pedestals including foundation bolt embedment / sleeve provision, Foundation
Non-shrink Grouting work.
Anchor fastening work.
Expansion joint work.
Coordination with utility agencies for water and temporary power connections, if
Coordination with PEB agency for proper layout marking, joint verification of layout,
anchor bolt alignment/fixing/grouting, etc… for timely completion of entire project for
construction of 02 nos. of PEB structural sheds near warehouse.
All works are to be carried out for construction of 02 nos. of PEB structural sheds near
warehouse at Surat Lignite Power Plant (SLPP), in accordance with the concept layout
plan provided as Bid Drawings with this tender. However, Bid Drawings are indicative and
for tendering purposes only. Final quantities will be based on approved Good For
Construction (GFC) drawings by GIPCL/Consultant. Estimated quantities are indicative and
may vary based on approved GFC. Bid Drawings are conceptual documents issued for
bidding purposes. Final Good For Construction (GFC) drawings will be issued by
GIPCL/Consultant after PEB design approval. However, grade of concrete of various items
shall be as per SoR (SECTION-E).
CIVIL WORKS FOR PEB STRUCTURE (Up to Finished Floor Level and Other as per
Site requirements). Civil works for the PEB sheds shall be limited up to finished floor
level (FFL), except walls, including:
Foundations (isolated/combined/pile, as applicable),
Ground beams and plinth beams,
Flooring up to finished floor level.
Plinth protection works
Roads & Drains work
2. Purpose: Storage of heavy materials with 10 MT capacity EOT Crane.
3. Size: Length 45 Meter, Clear span 25 Meter with Gable Roof without any intermediate
support. Total height about 10 Meter and working height 6-7 Meter.
5. Shed to be covered from top/roof and top sides (about 3 Meter for crane protection &
to avoid rain water ingress) with Galvalume sheets. All sides open.
6. Plinth level up to 300 mm from OGL.
6. Flooring required for heavy material storage.
7. RCC foundation design required (GIPCL will arrange & provide) based on PEB
structure design.
8. SBC at EL (-) 2.500 Meter is 137 KN/M2 (Kilo Newton per Square Meter).
2. Purpose: Only storage of heavy materials by movement of Hydra.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
3. Size: Length 45 Meter, Clear span 15 Meter with Gable Roof or shed roof without any
intermediate support and height 6 Meter.
4. Shed to be covered from top/roof and top sides (@ 1 Meter) with Galvalume sheets.
All sides open.
5. Plinth level up to 300 mm from OGL.
6. Flooring required for heavy material storage.
7. RCC foundation design required (GIPCL will arrange & provide) based on PEB
structure design.
8. SBC at EL (-) 2.500 Meter is 137 KN/M2 (Kilo Newton per Square Meter).
Quality Assurance & Control
All works shall be executed as per IS codes, CPWD specifications, and good industry
practices. The contractor shall deploy qualified site engineers and provide all test
reports (cube tests, compaction, material test certificates, etc.) as required.
Contractor should submit FQP (Field Quality Plan), within 15 days of LOI and before
any concrete work commences. Non-submission will force GIPCL to hold the works.
COMMON INFRASTRUCTURE & AREA DEVELOPMENT
Construction of internal rigid approach pavement with fly ash filling & rubble soling.
Fly ash filling & rubble soling works.
Construction of associated drains.
Provide a Plinth Protection on peripheral side of the both shed.
The works shall include, without limitation, the following:
Site development activities including area grading, clearing, leveling, excavation, and
backfilling, fly ash filling, etc…
Foundation works including RCC footings, pedestals, PCC, columns, beams, etc…
Superstructure works including all RCC works, RCC grade slab, Rubble soling,
masonry (brick/block) construction, and plastering.
Any temporary works, scaffolding, formwork, shuttering, or support systems required
for execution of the above.
Transportation, handling, and storage of all materials, machinery, and tools required
All other works as specified in the technical specifications, drawings, Schedule of
Rates (Section-E), and as may be reasonably inferred or directed by the Engineer-
in-Charge for the satisfactory completion of the scope of works.
The Contractor shall execute the works in full compliance with:
The technical specifications, drawings, standards, and codes provided in the
Tender, and Prevailing IS codes.
Instructions from the Engineer-in-Charge, and
All applicable statutory and regulatory requirements.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
This scope is comprehensive and inclusive of all activities required to deliver a fully
functional, structurally sound, and ready-for-use, whether or not each specific item is
mentioned herein but is required for the successful completion of the project.
All construction shall conform to relevant Indian Standards, CPWD norms, and
GIPCL’s safety and quality requirements, ensuring durability, hygiene, and
functionality of the facilities, following good standard Engineering practice for safety,
quality & workmanship.
GENERAL SPECIFICATIONS FOR CIVIL WORKS
A. Dismantling Work
All dismantling activities shall be carried out in a controlled manner strictly
as directed by the Engineer-in-charge to ensure safety and minimal
Prior written permission must be obtained from the Engineer-in-charge
before commencing any dismantling work.
In emergencies, the contractor shall arrange a compressor with a breaker
within 24 hours, without claiming additional payment except for breaker
The dismantling rates shall be comprehensive, covering labor, materials,
tools, breakers, debris disposal to designated external locations, and all
associated work.
B. Earthwork, Filling, and Dressing
The scope and rates for earthwork, filling, and dressing shall strictly follow
the item nomenclature detailed in the contract.
Rates shall be inclusive of all labor, materials, and machinery such as augers,
JCBs, tractors, dumpers, dewatering equipment, and other tools as specified.
Contractors must secure prior permits before starting excavation, ensuring
protection of underground cables and personnel safety.
Any damage to cables or pipes due to contractor negligence shall be repaired
at the contractor’s cost, recoverable from their bills.
For major excavation, contractors shall maintain accurate level records as
directed by the Engineer-in-charge.
Surplus excavated materials must be disposed of outside the premises
responsibly, maintaining site cleanliness.
C. Foundation and Concrete Work
Approved mix design shall be submitted and obtained prior to
commencement of concreting work.
Weigh batching shall be mandatory.
The contractor’s scope for foundation and concrete works aligns with the
item nomenclature, encompassing all designated locations.
Proper curing shall be carried out for a minimum period as per IS standards,
and no extra payment shall be made for the same.
Rates include labor, materials, tools, equipment, and all necessary resources.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
Samples of materials must be approved by the Engineer-in-charge prior to
supply and use at site.
Contractor shall maintain all equipment in proper working condition,
including standby arrangements to avoid delays.
Pour cards must be prepared and signed off by the Engineer before any major
concrete pours.
Quality control equipment and testing apparatus must be available onsite to
ensure compliance with standards.
Any defective or substandard work shall be dismantled and redone by the
Contractor at no extra cost.
D. Brickwork, RR Masonry, Plaster, and Flooring
Scope and rates shall correspond to the specified item nomenclature.
Contractor shall provide skilled masons for all brickwork, plaster, flooring,
Rates include labor, materials tools, tackles, and equipment.
All materials must be pre-approved by the Engineer-in-charge through
sample submission.
Only standard and approved brand materials are permitted for use.
E. Flooring (including VDF/Tremix flooring):
The Contractor shall deploy trained manpower and specialized equipment for
execution of Vacuum Dewatered Flooring (VDF).
Proper leveling, compaction, vacuum dewatering, and finishing shall be
ensured to achieve a dense, smooth, and crack-free surface.
Surface tolerances, panel layout, and joint cutting shall be carried out as per
approved drawings and instructions of the Engineer-in-charge.
Curing of flooring shall be carried out for the specified duration, and no extra
payment shall be made for the same.
Any undulations, cracks, or surface defects shall be rectified by the
Contractor at no extra cost.
The scope and rates shall be as per item nomenclature and include all labor,
materials, tools, tackles, and equipment.
Contractors must maintain detailed records of surface preparation and each
paint coat applied.
All painting materials require prior sample approval from the Engineer-in-
Only standard, approved brand paints and materials are allowed on site.
1.2 GENERAL SCOPE OF WORK
All works under this contract shall be executed strictly on an item rate basis
as per the detailed specifications and item descriptions outlined in Section-E
of the Schedule of Rates (SoR). The contractor is obligated to perform all work
within the stipulated time frame provided in the tender documents, ensuring
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
that all activities meet the highest standards of engineering, design,
workmanship, quality, and maintain proper line and level as directed by the
Engineer-in-Charge. The contractor shall mobilize adequate manpower,
equipment, and resources to ensure timely and efficient completion of the
entire scope of work.
All materials supplied by the contractor must be procured from reputed and
approved manufacturers and meet standard quality benchmarks. Prior to any
supply to the site, material samples must be submitted for approval by the
GIPCL Engineer-in-Charge, ensuring compliance with project requirements
and preventing substandard inputs.
It is understood that the contract’s scope is comprehensive and inclusive of
all works necessary for the complete and effective execution of the project,
even if certain tasks are not explicitly mentioned in the tender documents. This
includes any incidental or ancillary works that are essential to fulfill the
contract requirements within the agreed timelines. All works shall adhere to
the applicable specifications, safety norms, and legal and statutory
requirements, with strict enforcement to safeguard project quality and
Additionally, the contractor shall maintain on-site all statutory and legal
documentation related to the equipment, machinery, operators, and drivers
deployed under this contract. This includes but is not limited to registration
certificates (RC books), Pollution Under Control (PUC) certificates, vehicle
insurance policies, vehicle fitness certificates (where applicable), and valid
driving licenses. These documents must be readily available for inspection by
the Engineer-in-Charge upon request. Furthermore, vehicles including trailers
and hydraulic trolleys shall not exceed six years from the date of their RTO
passing certificate, ensuring safety and reliability of the fleet used on site.
1.3 SPECIFIC REQUIREMENT
The contractor shall possess and maintain an adequate number of good quality
standard machinery, equipment, tools, and tackles essential for executing scope of
These shall include, but are not limited to, AJAX Machine with weighment printing
facilities, 02 bags capacity Batching Mixture machines as a stand by arrangement,
trimix concrete floater, poker vibration, surface vibrator, Concrete needle Vibrators,
Water Tanker, Excavator, JCB, Roller, earth compactors, Heavy capacity dewatering
pumps, dumpers, tractor with trolley, level machine, total station for layout, cube
testing machine and other laboratory equipments as required for field quality control,
concrete breaker machines, hand carts or trolleys for internal movement of tools,
lifting tools and tackles such as ropes and chain pulleys, field test apparatus, and
other necessary equipment. The contractor is required to deploy these exclusively for
this contract throughout the entire duration of the project.
A detailed list of all available machinery, equipment, and tools & tackles deployed at
site shall be submitted by the contractor to the Engineer-in-Charge on a monthly basis
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
or as otherwise directed. This ensures transparency and enables timely monitoring
of resource adequacy.
Should there be any shortfall in machinery, equipment, or tools and tackles that
adversely affects the quality or progress of work, GIPCL reserves the right to impose
penalties, make recoveries, or retain payments from Running Account (RA) bills. The
quantum of such penalties or recoveries will be determined by the Engineer-in-
Charge, based on the extent of impact on the affected works.
Furthermore, to meet the daily operational needs under this contract, the contractor
must maintain a sufficient and functional set of tools and tackles in good working
condition at the site at all times. The tentative list provided is indicative and not
exhaustive, and the contractor shall ensure availability of all necessary equipment to
ensure smooth and uninterrupted progress of work.
LIST OF REQUIRED EQUIPMENTS, TOOLS & TACKLES
Sr. Description Probable Quantity
1. AJAX Machine with auto printing facilities of 1 no.
2. Excavator/ JCB 01 nos.
3. Earth compactors 02 nos.
4. Road Roller As required
5. Heavy capacity submersible dewatering pumps 03 nos. with sufficient
6. Dumpers, tractor with trolley 04 nos.
7. Water Tanker 01 no
8. Total Station survey instrument with staff 01 no.
9. Concrete mixer (2-bag capacity) with weighment 01 no
10. Electronic Concrete vibrator 6 nos.
11. Vibrator needles (60 mm) 4 nos.
12. Vibrator needles (40 mm) 4 nos.
13. Shuttering material 150 sqm
14. Staging & Scaffolding material As per requirement
15. Concrete cube mold 6 nos.
16. Concrete drill machine 1 no.
17. Hand trolley / Hand cart 2 nos.
18. Hand lamp with holder & 100 Meter four core cable 2 set
19. Plate vibrator 1 no.
20. Concrete breaker machine 1 no.
21. Ladder up to 10 meter 1 no.
22. Power supply cable with extension board, ELCB 100 RM minimum
23. Vacuum dewatering pump with water separator 4-5 nos.
24. Vacuum mats (filter mats set) Sufficient quantity
25. Screed vibrator / vibrating screed 1 no.
26. Power floater / power trowel (trimix machine) 1 no.
27. Groove cutter / joint cutting machine 1 no.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
NOTE:- The Contractor shall note that above list is not exhaustive and if any additional
tools & tackles or equipment, machinery etc., are required for proper performance
of the contract, the contractor shall also arrange the same immediately without
any extra cost to GIPCL.
1.4 FAILURE DURING EMERGENCY
During any emergencies, contractor shall have to carry out given works by deploying
additional resources within four-hour notice period failing which GIPCL reserves the
right to carry out this work by engaging other party or may impose appropriate penalty
in lieu of any direct or indirect losses occurred.
The expenditure occurred due to such situations, the Contractor will be held
responsible and the same will be recovered from the Contractor’s monthly bill / any
other pending bills/available dues along with 10% overhead charges with GST.
For repetitive failure in completion of specific works in specific time line for more than
three incidents, GIPCL reserve the right to terminate the entire contract by forfeiting
all pending dues, Security Deposit & other retention money (if any), after giving
days’ notice to the contractor & this will be binding to the contractor.
1.5 SPILLAGE OF MATERIAL
Contractor shall take due care to avoid any spillage of material while loading /
transporting / handling. To avoid spillage of material, overloading / heaping shall be
avoided by the contractors. Trolleys/trailers/Transport carrier shall be in good
condition & leak proof to avoid any leakage of materials.
In case of any spillage, contractor shall have to remove such carriers immediately from
site and contractor shall be responsible to clean up that area at their cost otherwise
GIPCL shall get the work done by other agency at contractor’s risk and cost with
additional 10% overhead charges with GST.
1.6 DISPOSAL OF MATERIAL
The contractor shall be fully responsible for the removal and proper disposal of all
surplus materials, debris, excavated earth, disposable scrap, and any other waste
generated during the execution of the work. Disposal shall be carried out strictly
outside the premises or at locations designated by relevant authorities, in full
compliance with prevailing GPCB (Gujarat Pollution Control Board) norms and
other applicable environmental regulations. GIPCL expressly disclaims any liability for
consequences arising from improper disposal by the contractor.
All other scrap materials shall be disposed of in GIPCL’s designated scrap yard as
instructed by the Engineer-in-Charge. The contractor shall maintain a record of such
scrap disposals in the prescribed standard format, duly authorized by GIPCL, to
ensure traceability and accountability.
Prior to final bill submission, the contractor is required to furnish a written undertaking
affirming that all materials have been disposed of responsibly outside the plant
premises or at designated sites in accordance with prevailing government guidelines.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
This undertaking shall indemnify and hold GIPCL harmless against any future
liabilities, claims, or consequences arising from improper disposal. The contractor’s
final payment shall be withheld until the receipt and acceptance of this undertaking by
1.7 SCOPE OF CONTRACTOR
1. The contractor shall provide and be fully responsible for all tools, tackles,
materials (except for any specifically identified free-issue materials as per the
Schedule of Rates), manpower, equipment, and other resources necessary to
execute the contract. The contractor must ensure that all tools, tackles, and
equipment are in sound working condition and maintained in a safe and
serviceable state throughout the contract period. The contractor has to arrange
transportation for lifting/shifting the materials at their own.
2. All consumable items required for the execution of work, including but not limited
to cloth, cotton waste, kerosene, gas, diesel, petrol, lubricants, welding
electrodes, fixtures, fasteners, and spare parts, shall be procured and supplied
by the contractor at no extra cost to the owner.
3. The contractor shall arrange and provide all necessary safety equipment and
Personal Protective Equipment (PPE) to their personnel for compliance with
applicable safety standards and to ensure safe working conditions on site.
4. It is the sole responsibility of the contractor to provide necessary facilities,
including accommodation, for their laborers and workforce at their own cost. No
additional claims related to labor accommodation shall be entertained by the
5. The contractor shall deploy qualified and experienced full-time site-in-charge
personnel along with adequate supervisors and engineers to manage day-to-day
execution of work. These personnel will be responsible for ensuring work
complies with specifications, coordinating with the Engineer-in-Charge, obtaining
necessary work permits, receiving and verifying materials issued by GIPCL,
supervising daily work progress, recording joint measurements and work reports,
preparing bills, managing manpower gate passes, and maintaining all statutory
and legal compliance records.
6. A separate contract shall be awarded for the fabrication and erection of the Pre-
Engineered Building (PEB) and associated structures above plinth or finished
floor level. The Civil contractor of this tender shall fully cooperate and coordinate
with the PEB contractor to ensure conformity with line and level requirements at
the plinth level.
7. The Civil contractor of this tender shall provide all necessary support,
coordination, and cooperation to the PEB contractor, Electrical agency,
Mechanical Agency, Staff & Workers associated to Warehouse/Store of GIPCL,
Security Personnel, etc… without any additional cost implications to GIPCL,
ensuring smooth interface and integration of works between all working agencies.
1.8 TO REMEDY DEFECTIVE WORK
If any part of the work, or the entire work, is found to be damaged or defective—
except when such damage arises solely from the actions or negligence of GIPCL—
or if latent defects that were not readily detectable through proper inspection appear
before final completion and acceptance, the contractor shall promptly and at their
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
own cost repair, replace, or rectify such damage or defects to the full satisfaction of
the Engineer/GIPCL.
Under no circumstances shall defective or substandard work be accepted or retained,
even if the contractor claims adherence to technical specifications. GIPCL maintains
a strict no-compromise stance regarding the quality of materials, workmanship, and
overall execution.
The contractor’s liability under this clause shall remain effective and enforceable
despite any certification, whether interim or final, or the passing of accounts by
GIPCL. This ensures that quality and durability are safeguarded beyond routine
project closeout processes.
Third party testing:-
Contractor shall arrange third party testing of his materials supplied at GIPCL-SLPP
for jointly collected random samples of materials and also concrete cubes as directed
by Engineer-in-charge. All cost towards testing shall be borne by the contractor. The
testing laboratory shall be as decided by GIPCL.
1.9 SAFE STORAGE OF MATERIALS
Contractor shall make all arrangement including construction of safe storage of all his
materials, shuttering & scaffolding, consumable items, tool & tackles, equipments,
PPEs, etc… whatsoever. Contractor shall be responsible for safe storage and
security of all his belongings including materials and may depute full time guard for
the security of all the items / materials to avoid pilferage, loss, damage & theft and he
shall be responsible for safety & security. In any case, GIPCL will not be responsible
for security & safety of items / materials / effects of contractor.
1.10 DAILY DIARY AND PROGRESS REPORT
A daily progress shall be provided to Engineer-in-charge. The CONTRACTOR will
supply general information every day at 9:00 hours for the day preceding. Day to day
instructions will be conveyed by GIPCL concern Engineer-in-charge to contractor’s
authorized site-in-charge / supervisor/s and contractor shall acknowledge same and
submit compliance on it as per requirement. A work instruction book may be
maintained by contractor for proper accounting & follow-ups. The CONTRACTOR’S
representative shall report every day to see these instructions and acknowledge
them. Such instructions / reports may also be executed / maintained digitally if
desired. The CONTRACTOR shall supply all information regarding availability of
manpower, equipments, tools, etc… and progress of work, as is required by the
OWNER for compiling the ongoing progress of work.
1.11 PLANNING & MONITORING OF WORK PROGRESS
1. After award of the work, Contractor has to submit schedule of work planning for
completion of work with resources (i.e. manpower and material) mobilization
planning within seven days.
2. Contractor shall mobilize the resources at site within 15 days from the date of LoI
or work order whichever is earlier. GIPCL will closely monitor the agreed schedule
against actual progress of work at site. If contractor failed to carry out work as per
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
agreed schedule and if contractor failed to mobilize required resources
(manpower & materials) within given / allowed time line by written communication,
GIPCL will execute the job through other agency at the risk and cost of the
contractor with additional 10% overhead charges including GST.
3. The owner of contractor / proprietor / partner should be present for periodic
progress review meeting & for further planning at office of GIPCL Surat Lignite
Power Plant as desired by Engineer-in-charge (probable on weekly basis).
It is not the intent to specify herein all the works in the scope of this contract. The
scope also includes all works necessary, which are not specifically mentioned here
but required, for completion of entire scope of work in all respect within time bound
period and are deemed to be included in the scope of the CONTRACTOR. All works
shall conform to the specification. The works shall conform to high standards of
quality and workmanship.
2. PRICE & RATES
This tender is based on the Schedule of Rates (SoR), and the final item rates will be
determined based on the lowest gross total price offered through the e-Reverse
Auction process, inclusive of GST.
Following the price discovery through the e-Reverse Auction, a pro-rata reduction will
be applied to the quoted prices of all SoR items. The resulting item rates shall be
comprehensive and inclusive of all costs, including but not limited to skilled and
unskilled labor, supervisors, engineers, safety supervisors, insurance, safety PPEs,
site safety arrangements, provision for site storage/site office, approved safety
equipment, all necessary tools, tackles, equipment, machinery, spares and
maintenance, staging, shuttering and scaffolding materials, hiring of specialized
equipment and outsourcing to experienced agencies, all materials except those
specifically issued free under the respective SoR items in Section-E, survey works,
site visits for work identification, transportation, communication, mobilization and
demobilization, loading, unloading, safe storage of materials, security and safety, fuel
and consumables, and idle charges for labor, operators, drivers, machinery, and
equipment due to unavailability of the work front, holding of work permits, or any
unavoidable circumstances. The rates also include all applicable taxes, duties,
royalties, rents, stamp duties, and other statutory levies imposed by Central, State,
Local, or Municipal authorities. (Note: Item rates exclude GST, which is accounted
for separately at 18% in the total estimated SoR value).
The item rates shall be deemed to cover all work as per specifications, including all
leads and lifts, contractor overheads, profits, and any other costs necessary for the
satisfactory and timely completion of the contract. Mobilization and demobilization
costs for manpower, equipment, and materials shall also be included. The rates shall
remain firm and fixed throughout the entire contract period and any extensions
granted, without any escalation, including idle charges for labor, machinery, or
overhead expenses, regardless of the reasons for delay, non-availability of work
front, or other circumstances.
The contractor shall comply with all applicable labor and industrial laws and
regulations at their own cost. In case of any default or non-compliance, GIPCL
reserves the right to withhold payments until all legal liabilities are resolved.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
The offered price must account for full mobilization of all required manpower, tools,
tackles, materials, equipment, vehicles, and consumables necessary for the timely
and satisfactory completion of the entire scope of work.
The contract quantity may increase or decrease based on day-to-day requirements;
however, the item rates will remain unchanged. Payments will be made based on the
actual quantities executed, as certified by GIPCL representatives.
3. CONTRACT / COMPLETION PERIOD AND LIQUIDATED DAMAGES
3.1 The contract / completion period for scope of works of both the sheds shall be
(six) months from the date of issuance of the Letter of Intent (LoI) and/or Work
Order, whichever is earlier (except 03 months of peak Monsoon, i.e. July, August &
3.2 GIPCL/Consultant shall issue RCC foundation construction drawings for both the
sheds within 30 days from date of LOI. Excavation, Construction of RCC
Foundation, Pedestals & Beams, Backfilling, etc... for both the sheds in all respect
including ready for handing over to PEB agency for erection of PEB Structure shall
be within 03 Months from the date of release of Construction Drawings for
Foundation, Pedestals & Beams. Foundation bolts with all required accessories will
be issued to Civil work agency by PEB agency: within 70 days for both the sheds
from the date of LoI.
3.3 Balance Civil works for both the sheds as per scope of work: Within 02 Months from
the date of handing over of front.
3.4 GIPCL reserves the right to extend the contract period by up to an additional
(three) months on the same rates, terms, and conditions, without any price
escalation and without entering into a new contract on sole discretion of GIPCL only.
However, delay attribute to contractor beyond above schedules will attracts penalty
as LD (Liquidated Damages) as per LD clause mentioned herein under.
3.5 If the scope of work is not completed by the Contractor, necessary LD will be
deducted as per LD clause mentioned herein under and in the interest of work
completion, GIPCL will extend the contract period appropriately (along with
deduction of LD) as per contract requirement on the same rates, terms, and
conditions without any price escalation or new contract on sole discretion of GIPCL.
3.6 GIPCL reserves the right to short-close the contract at any time by giving 01 (one)
month’s notice, without assigning any reason.
3.7 The Contractor should prepare a detailed activity wise detail time schedule jointly
with the Engineer-in-Charge within 07 days of receipt of LOI/Work Order as per
contract period with each milestone. The WORK shall be executed strictly as per
the time schedule which includes the time required for mobilization, testing,
rectification (if any) and completion of given scope of work in all respects in
accordance with Contract Document to the entire satisfaction of the Engineer-in-
3.8 The above detail time schedule (PERT/BAR network) shall be reviewed periodically
and reports shall be submitted by the Contractor as directed by the
Owner/Consultant. At any time, if contractor fails to execute the work or fails to
mobilize the resources and equipments as per agreed schedule of work planning
and/or as per directions of GIPCL / ENGINEER within the time frame, GIPCL shall
get the work done by third party at the risk & cost of the CONTRACTOR with
additional 10% overhead charges of GIPCL, including GST and all costs incurred in
connection therewith shall be recoverable from the CONTRACTOR by the GIPCL
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
/ENGINEER as a debt or may be deducted by him from any money due or to
become due to the CONTRACTOR.
3.9 In any case, contractor shall not be eligible to claim any compensation or
reimbursement or price escalation which attributed to poor progress, poor quality
work, rework, holding the work by GIPCL in case of decision or modification in
proposed layout or due to any whatsoever reason.
3.10 Contractor shall not have any right for time extension or compensation or price
escalation on account of delay due to late handing over of particular front by the
GIPCL or any other reason whatsoever. However, GIPCL at its sole discretion may
grant time extension only against the justifications submitted by the contractor in
3.11 In order to complete the works timely as per approved completion schedule,
contractor shall mobilize sufficient nos. of manpower & required material, resources,
tools & tackles etc at locations simultaneously, including independent site
3.12 DELAY AND EXTENSIONS OF TIME
3.12.1 The time allowed for carrying out the work as entered in the contract shall be
strictly observed by the CONTRACTOR and shall be deemed to be of the
essence of the contract on the part of the CONTRACTOR. The
CONTRACTOR shall be allowed admittance to the site on the ‘Date of
Commencement’ and he shall there upon and forthwith begin the work and
shall proceed with the work with due diligence.
3.12.2 The CONTRACTOR agrees that the work shall be commenced and carried on
at such points and in the order of precedence and at such times and seasons
as may be directed by the OWNER/ ENGINEER in accordance with the
schedule for completion of the work as outlined elsewhere. The
CONTRACTOR declares that he has familiarized himself with the site and
rights-of-way, with all the local conditions, and with all the circumstances
which may, or are likely to affect the performance and completion of the work,
and that he has allowed for such conditions. However, if a time schedule is
submitted by the CONTRACTOR so as to keep the phasing of work generally
in line with the time schedule drawn up and such time schedule after approval
from the OWNER/ENGINEER shall be accepted and complied with by the
CONTRACTOR and it shall form a part of the contract. The progress of work
will be checked at regular monthly intervals and the percentage progress
achieved shall be commensurate with the time elapsed after the award of the
3.12.3 If the CONTRACTOR shall desire an extension of time for completion of work
on the grounds of his having been unavoidably hindered in its execution or
any other ground, he shall apply in writing to the OWNER within 7 days of the
date of hindrance on account of which he desires such extension as
aforesaid. This application shall invariably be accompanied by sufficient
supporting valid documentation giving reasons for seeking such extension.
No application for such extension shall be entertained if it is not received in
sufficient time to allow the OWNER / ENGINEER to consider it and the
CONTRACTOR shall be responsible for the consequences arising out of such
3.12.4 No necessity for an extension of time is anticipated but if untoward or extra-
ordinary circumstances beyond the control of the CONTRACTOR should
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
arise, which in the opinion of the OWNER/ENGINEER should entitle the
CONTRACTOR to a reasonable extension of time; such extension may be
granted but shall not operate to release the CONTRACTOR from any of his
obligations. For purpose of this clause, untoward and extraordinary
circumstances are defined under clause 22.0 of General Condition of
Contract. Under above circumstances, only extension of time may be granted
but the CONTRACTOR will not be entitled to any additional compensation. In
case of strike or lockout, the CONTRACTOR shall, as soon as possible, give
written notice to the OWNER / ENGINEER, but the CONTRACTOR shall
delay and shall do all that may reasonably be required to the satisfaction of
the OWNER / ENGINEER to proceed with the work.
3.12.5 The OWNER shall have the right to require the discontinuance of the work, in
whole or in part, for such time as may be necessary, should the condition of
the weather or of flood or other contingencies make it desirable to do so in
order that the works shall be well and properly executed. The CONTRACTOR
shall have no claim for idle time, escalation etc. However, the OWNER will
grant such extension of time for completion of the contract as he may think
proper and sufficient in consequence of such delay.
3.13 LIQUIDATED DAMAGES (LD) FOR DELAY
3.13.1 In the event of the contractor failing to comply with the approved time schedule
and if failing to complete all Civil foundations (as specified in clause no.
of special condition of contract), he shall be liable to pay as compensation, a
sum equal to half percent (1/2%) of the “Total Contract Value” per week of
delay as Liquidated Damages (LD). Even if foundation works completed as
per above clause no. 3.2 but total works not completed within stipulated
contract completion period, LD at 0.50% of Total Contract Value per week of
delay will be recovered. However, the above amount of LD will be subject to
maximum of 10% of the Total Contract Value. The LD from R.A bill will be
deducted based on total contract value. However, at the end of contract, the
LD will be calculated based on the executed value as per final bill & excess
amount of LD deduction, if any, will be refunded back to the contractor.
3.13.2 The OWNER may without prejudice to any other method of recovery, deduct
the amount of such damages from any money due or which may become due
to the CONTRACTOR. In the event of extension of time being granted by the
OWNER in writing for completion of work, this penalty clause will be
applicable after the expiry of such extension period.
3.13.3 All sums payable by way of Liquidated Damages shall be considered as
reasonable compensation to be applied to the use of the OWNER without
reference to the actual loss or damage sustained and whether or not any
damage has been sustained.
3.14 RISK & COST CLAUSE - ENGAGEMENT OF THIRD PARTY FOR CIVIL
FOUNDATION WORKS ON CONTRACTOR'S DEFAULT
3.14.1 APPLICABILITY
This clause shall apply in the event the Contractor fails to complete the RCC civil
foundation works (including column pedestals, ground beams, and all associated
embedments/anchor bolts for both Shed-1 and Shed-2) within the stipulated completion
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
period of Three (03) months from the date of issue of Good-for-Construction drawings by
GIPCL/Consultant, as specified under Cl. 3.2 of this Section-D, or within any extended
period duly granted in writing by GIPCL.
This clause is without prejudice to and operates cumulatively with: (a) the Liquidated
Damages provisions under Cl. 3.13 of this Section-D; (b) the Security
Deposit/Performance Bank Guarantee provisions under Section-C; and (c) any other
rights and remedies available to GIPCL under this Contract, at law, or in equity.
3.14.2 NOTICE OF DEFAULT AND CURE PERIOD
Upon the Contractor's failure to achieve the foundation completion milestone within the
stipulated period, GIPCL shall issue a formal written Notice of Default (Notice-01) to the
Contractor by official email / registered post / speed post / courier with acknowledgement
due, specifying:
a. The nature and extent of the default, including the quantum of work remaining
b. A Cure Period of Seven (07) calendar days from the date of receipt of Notice-01,
within which the Contractor must demonstrate satisfactory progress — defined as
completion of not less than fifty percent (50%) of remaining foundation work within
the Cure Period - or submit an acceptable recovery programme with resource
deployment plan duly approved by GIPCL/Consultant.
c. GIPCL's intention to engage a Third Party at the Contractor's risk and cost if the
default is not remedied within the Cure Period.
If the Contractor remedies the default to GIPCL's satisfaction within the Cure Period,
GIPCL may, at its sole discretion, refrain from invoking this clause for that specific
instance of default. Such forbearance shall not constitute a waiver of GIPCL's rights for
any subsequent default.
3.14.3 ENGAGEMENT OF THIRD PARTY AT CONTRACTOR'S RISK AND COST
If the Contractor fails to remedy the default within the Cure Period specified in Cl. 3.14.2
above, GIPCL shall be entitled, but not obligated, to engage a Third Party agency
(hereinafter referred to as "Third Party Agency" or "TPA") to carry out all or part of the
remaining civil foundation works, including but not limited to:
a. RCC column footings and pedestals for Shed-1 and/or Shed-2;
b. Ground beams and grade slab as required;
c. Setting, fixing and grouting of foundation bolts, sleeves and anchor bolt embedments;
d. Non-shrink grouting under base plates after PEB column erection, if not completed
by the original Contractor;
e. Any other civil work directly associated with enabling the commencement of PEB
structural erection by the PEB Contractor.
The engagement of a Third Party Agency shall be at GIPCL's sole discretion and shall be
conducted through an appropriate procurement process as per GIPCL's rules and
prevailing financial powers. The Contractor shall have no right to object to the identity,
terms, or rates of the Third Party Agency engaged by GIPCL under this clause.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
3.14.4 CONTRACTOR'S FINANCIAL LIABILITY — RISK & COST RECOVERY
All costs and expenses incurred by GIPCL in engaging and executing the said works
through the Third Party Agency shall be entirely at the risk and cost of the original
Contractor (hereinafter in this clause referred to as "Defaulting Contractor"). The total
amount recoverable from the Defaulting Contractor under this clause shall be computed
TOTAL RECOVERABLE AMOUNT =
[ Actual Additional Cost to Third Party Agency (A) ]
[ 10% of (A) = GIPCL Overhead / Supervisory Charges (B) ]
[ GST applicable on (A + B) at prevailing statutory rate (C) ]
i.e., Total Recovery = A + B + C = A + 10%(A) + GST on (A + B)
For the purpose of this clause:
(a) "Actual Additional Cost of Third Party Agency" (A) shall mean the total extra amount
(over and above payable as per original contractor’s order rate/s) certified and paid /
payable by GIPCL to the Third Party Agency for the completed scope, including any
mobilization, testing, or incidental costs directly related to the works undertaken by
the TPA under this clause. It shall NOT include any amount attributable to work within
the Defaulting Contractor's own completed scope.
(b) "GIPCL Overhead / Supervisory Charges" (B) at the rate of Ten Percent (10%) of the
Actual Additional Cost (A) shall be levied by GIPCL to compensate for the additional
management, supervision, coordination, and administrative burden borne by GIPCL
as a result of the Contractor's default. This charge is not subject to negotiation or
reduction by the Contractor.
(c) "GST" (C) means Goods and Services Tax (including CGST + SGST or IGST as
applicable) levied on the gross taxable value of (A + B) at the rate prevailing on the
date of GIPCL's invoice / debit note to the Defaulting Contractor. The Defaulting
Contractor shall bear the full GST liability and shall not be entitled to input tax credit
on amounts recovered under this clause.
(d) The amount computed under this clause is in addition to and shall not be reduced or
offset against Liquidated Damages recovered under Cl. 3.13 of this Section-D. Both
recoveries operate independently and simultaneously.
Illustration (for reference only — not a cap on recovery):
Illustration (Example
Recovery Component Remarks
Certified payments to
(A) Actual Additional TPA Cost ₹
(B) GIPCL Overhead @ 10% of
Subtotal (A + B) ₹ 16,50,000 Base for GST
(C) GST @ 18% on (A + B) ₹ 2,97,000 At prevailing rate
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
Illustration (Example
Recovery Component Remarks
TOTAL RECOVERABLE from
₹ 19,47,000 pending bills / SD;
Defaulting Contractor
independent of LD
₹ (0.50% of Total Computed separately
(D) LD (simultaneously under
contract value per week per LD clause; also
in line with Cl. 3.13) recovered
CUMULATIVE RECOVERY Both operate
(Cl.3.14 + Cl.3.13) simultaneously
3.14.5 RECOVERY MECHANISM AND ORDER OF PRIORITY
GIPCL shall recover the amount computed under Cl. 3.14.4 from the Defaulting
Contractor through the following mechanisms, applied in the order listed below:
(i) First, by deduction from any pending Running Account (RA) bills / or other amounts
payable to the Contractor under this Contract at the time of or subsequent to the risk
& cost engagement - without any further notice, consent, or judicial order;
(ii) Second, if pending bills are insufficient to cover the full recovery, by invocation and
appropriation of the Contractor's Security Deposit / Performance Bank Guarantee
(PBG) furnished under Section-C of this Contract, to the extent of the outstanding
recovery amount;
3.14.6 TERMINATION OF CONTRACT AND FORFEITURE OF SECURITY DEPOSIT
Without prejudice to the recoveries effected under Cl. 3.14.4 and Cl. 3.14.5, GIPCL shall
further be entitled to terminate this Contract if any one or more of the following conditions
(a) The Defaulting Contractor has failed to remedy the foundation completion default
even after expiry of the Cure Period under Cl. 3.14.2 and GIPCL has been compelled
to engage a Third Party Agency under Cl. 3.14.3; OR
(b) The Contractor has abandoned the works or failed to mobilize resources within Seven
(07) days of a written direction by GIPCL/Engineer-in-Charge to recommence; OR
(c) Accumulated Liquidated Damages under Cl. 3.13.1 have reached the maximum cap
of Ten Percent (10%) of the Contract Value and the delay continues beyond such
(d) In the reasonable opinion of GIPCL/Engineer-in-Charge, the Contractor is not in a
position to complete the remaining civil works within a time that would permit
commencement of PEB structural erection without causing further compensable
delay to the PEB contractor.
Before exercising the right of termination, GIPCL shall issue a formal Termination Notice
to the Contractor by official email / registered post / speed post, providing a final cure
period of Fifteen (15) calendar days from the date of receipt of such notice. If the
Contractor fails to remedy the default within said fifteen days, GIPCL may, without any
further notice or formality, terminate this Contract by written order.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
Upon termination of this Contract under this clause, the following consequences shall
automatically ensue:
(i) The ENTIRE Security Deposit / Performance Bank Guarantee furnished by the
Contractor under Section-C shall stand forfeited in full forthwith — unconditionally,
without any deduction or apportionment, and without any requirement for further
notice, demand, or legal proceedings. The forfeiture of the Security Deposit shall be
in ADDITION to, and shall not be adjusted against, any Liquidated Damages already
recovered or recoverable under Cl. 3.13 or any Risk & Cost amounts already
recovered or recoverable under Cl. 3.14.4;
(ii) GIPCL shall take possession of the site, all temporary works, all materials brought to
site and paid for under RA bills, all shuttering, scaffolding, and plant & machinery
deployed at site by the Contractor, without any obligation to make further payment to
the Contractor for the same. Materials not paid for under RA bills may be used by
GIPCL/TPA at site without further payment to the Contractor to the extent of their
assessed value against the outstanding recovery;
(iii) Any amounts remaining payable to the Contractor (if any) after full deduction of: (a)
Risk & Cost amounts per Cl. 3.14.4; (b) Liquidated Damages per Cl. 3.13.1; (c) any
other outstanding dues, deficiencies, or liabilities under this Contract - shall be paid
to the Contractor within Ninety (90) days of issue of the final account, subject to
submission of a “No-Claim No-Arbitration” Certificate, Indemnity Bond and clearance
of all labour dues as per applicable statutory requirements, as per tender terms.
(iv) Termination under this clause shall be without prejudice to GIPCL's right to recover
any additional losses caused to GIPCL.
3.14.7 GIPCL'S OBLIGATION TO MITIGATE
GIPCL shall use reasonable commercial efforts to procure the Third Party Agency's
services at competitive market rates commensurate with the prevailing SoR / market rates
applicable for civil works of similar nature in the region. GIPCL's obligation to mitigate
shall, however, not extend to conducting a full public tender process for the Third Party
engagement if, in GIPCL's reasonable judgment, the exigency of the situation (particularly
the impact on the PEB Contractor's schedule) does not permit the time required for such
process. In such cases, GIPCL may engage the TPA through limited tender or negotiated
procurement as per its applicable financial powers and procurement procedures.
The Defaulting Contractor shall not dispute the reasonableness of GIPCL's procurement
procedure for the TPA on the ground that a cheaper alternative could have been found
through open tender, provided GIPCL can demonstrate that the procurement was carried
out in good faith and in the interest of timely completion of the Project.
3.14.8 NON-WAIVER
No delay or failure by GIPCL in exercising any right under this clause, and no partial
exercise of any right, shall constitute a waiver of that right or any other right of GIPCL
under this Contract. GIPCL's right to invoke this clause shall survive any extensions of
time granted to the Contractor under this or any other clause of this Contract.
3.14.9 CONTRACTOR'S OBLIGATIONS DURING THIRD PARTY ENGAGEMENT
During the period of TPA's operations under this clause, the Defaulting Contractor shall:
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
a. Not obstruct, interfere with, or delay the Third Party Agency's access to the site,
materials, or any portion of the works;
b. Immediately remove, upon GIPCL's written direction, any of its own plant, materials,
or personnel from areas where the Third Party Agency is required to operate;
c. Continue to be responsible for the safety and security of any works already completed
by it, to the extent not taken over by GIPCL or the TPA;
d. Provide to GIPCL/Engineer-in-Charge all drawings, specifications, mix designs,
purchase orders, and other contract documents relating to the works, within Forty-
Eight (48) hours of GIPCL's written request, to enable seamless handover to the TPA;
e. Remain jointly and severally liable with the TPA for the quality and completeness of
works that were jointly measured and certified by GIPCL - to the extent attributable
to materials or work previously supplied by the Defaulting Contractor.
Any failure by the Defaulting Contractor to comply with its obligations under this sub-
clause shall constitute a further breach entitling GIPCL to issue the Termination Notice
under Cl. 3.14.6 without further Cure Period.
CROSS-CONTRACT COORDINATION NOTE (Section-D, Cl. 3.14.10):
GIPCL reserves the right, upon termination or risk & cost engagement under this clause, to
assign the balance civil foundation works directly to the PEB Turnkey Contractor (appointed
under Bid No. SLPP/Civil/WH/PEB Sheds/2026) or any other agency - at negotiated rates
based on this Contract's SoR, without the requirement of a fresh public tender. Any costs so
incurred shall be recovered from the Defaulting Contractor under Cl. 3.14.4 above. The
Defaulting Civil Contractor shall have no claim whatsoever against GIPCL or the PEB
Contractor arising from such assignment.
Further, any delay costs imposed by the PEB Contractor on GIPCL, directly attributable to
Civil Contractor's failure to provide civil foundations within the stipulated period, shall be
recoverable from the Defaulting Civil Contractor as part of GIPCL's losses under this clause
- over and above the LD cap and Security Deposit forfeiture.
3.15 REQUIREMENTS TO ADHERE TIME SCHEDULE
The CONTRACTOR shall, within two weeks of receipt of the Letter of Intent, submit
to the OWNER for his approval, a detailed work schedule showing how he proposes
to carry out the work, specifically mentioning time periods as well as dates of
commencement and completion of each activity including mobilization schedule for
manpower & materials, equipment (as per requirements of scope & specifications)
and such approved schedules must be strictly adhered by the CONTRACTOR. The
schedules are to be reviewed periodically with the OWNER to ensure that the
completion date will be met or to institute corrective steps (at no extra cost to the
OWNER) to adhere to the completion dates.
The OWNER reserves the right to revise the schedule at his discretion in order to
keep up to the completion date and to suit the project requirement and such
alterations shall not entitle the CONTRACTOR to any extra payment.
Further following points to be adhered & followed as per requirements and directed
by Engineer-in-charge.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
The whole works must be proceeded with, within such sections and at such
times and in such order and manner as described in these specifications and
as directed by the ENGINEER-in-charge. No extra payment or relaxation in the
rates will be permitted on account of this.
The CONTRACTOR should furnish the ENGINEER-in-charge with weekly
progress reports on the Saturday of every week in the following format or format
jointly finalized:-
Item / activity Schedule for Actual Reasons for Steps taken to make
of work the week Progress short fall, if any up the short fall
Extension of contract period only under force majeure conditions for completion
of work shall be granted by the OWNER, equal to the time ‘Force Majeure’
conditions were in existence and as applicable to this contract (refer clause no.
22 of General Conditions of Contract.
Idle time charges or price escalation for any reason whatsoever shall not be
entertained by the OWNER.
If the CONTRACTOR fails to maintain the stipulated time of completion
specified herein above, he shall be liable to pay penalty as set out in above
clause no. 3.13 of LD. It shall be clearly understood that failure to meet interim
completion dates shall also attract penalty as per conditions of contract laid
down in this document.
Work / mobilization shall commence at the site within 15 days from the date of
receipt of the Letter of Intent or work order, whichever is earlier by arranging &
mobilizing required resources and materials and maintain necessary number of
machinery and equipment to guarantee the agreed rate of progress of the work
as per schedule.
Work covered under this specification shall be completed in all respects within
stipulated time of 06 months from the date of Letter of Intent (LOI), except
months of peak monsoon.
4. TERMS OF PAYMENT
A. Conditions of Payment:
The contractor shall raise the running invoices on monthly/quarterly basis in
duplicate, one original in physical form and soft copy in MS Excel format (soft copy
of measurement sheets & bill abstract with original joint measurement records shall
be submitted one week prior to submission of bill/invoice) as directed by Engineer-
in-charge in respect of the work performed or completed along with the documents
as mentioned hereinafter & in subsequent clauses.
However, respective R.A. Bill of contract shall only be entertained for 100% payment
as per following terms, only if contractor provides satisfactory progress of Civil
foundation works (minimum pro-rata completion of Civil foundation works for both
sheds with respect to actual quantities in line with GFC drawings and stipulated
completion period of foundations). GIPCL may decide & recommend for release of
partial payment of such R.A. bill/s as deemed to suit based on review of ongoing
progress of foundation works.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
On receipt of the invoice complete in all respects and with all the said documents, the
payment in respect of the same shall be made within 21 days of such receipt of a
complete invoice as per the following terms of payment:
(i) 100% of monthly RA bill along with 100% taxes shall be released against the
work executed duly certified by GIPCL. Income Tax (IT) will be deducted at
source from monthly RA bills as per the rules in force.
(ii) Contract Security deposit/irrevocable PBG at 10% of contract value
(excluding GST) shall be submitted as per clause no.: 1 of Section-C.
(iii) GST shall be paid along with bills after fulfillment of following terms.
(a) Submission of copy of registration certificate issued by GST Authority (to
be furnished only once).
(b) Citing the GST Registration no., HSN/SAC Code and the date of issue of
registration certificate on invoices.
(c) Citing GIPCL’s GST no. along with contractor’s GST registration no. and
the date of issue of registration certificate on invoices.
(d) Claim of GST amount with percentage (%) separately shown on the
(e) The contractor shall be required to submit the proof of payment of GST
of previous month/quarter, as may be applicable as & when demanded
by GIPCL/Owner/company.
(f) Contractor shall inform the GIPCL in the event of its registration
certificate is cancelled or discontinued for whatsoever reason.
(g) The contractor shall also mention on their invoice the HSN/SAC code as
applicable under the GST laws under which GST is levied and a self-
certified authentic third-party evidence (www.cbic-gst.gov.in) shall be
adduced to that effect by the contractor.
(iv) At the time of submission of the first RA Bill, the Contractor shall submit a
certificate from Engineer-in-charge regarding availability of tools & tackles,
equipments, vehicles, etc at site as per requirement of contract. The
Contractor shall also furnish the checklist as per ANNEXURE-A enclosed with
the Section-F of tender document along with the RA bill of respective month
(v) While making running account payment, the following deductions may be
made by GIPCL, if applicable:
a. Cost of materials issued, if any, by GIPCL and to the extent consumed in
b. Security deposit recoverable if any.
c. Advance on materials / work progress advance payments, if any.
d. LD/Penalty for delayed delivery, penalty for delayed execution of work,
recovery of charges for the work done by other contractor due to delay or
any other reason, if applicable.
e. Any other dues recoverable by GIPCL from the contractor under the
(vi) The contractor, along with monthly RA/final bill shall submit copy of P.F.
Challan, wages register, attendance sheet & ECR statement indicating the
employee and employer's P.F contribution with respect of employees
employed by him for the contract at GIPCL site along with format for
submission of these documents provided in Section-F (Annexure-I).
(vii) The Contractor shall submit his Final Bill within a period of four months of the
expiration or earlier termination of the contract or any extensions that may be
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
granted by GIPCL to the Contractor. GIPCL shall not entertain any bill for any
work item after expiration of period of four months. After the final bill amount
is certified by GIPCL for payment and the same is made known to the
contractor by GIPCL & accepted by contractor, “No claim - No arbitration
certificate” to be submitted to GIPCL to release the Final Bill.
(viii) The Contractor shall include all his claims in the Final Bill submitted by him
and accordingly the final bill submitted by the Contractor shall be deemed to
be inclusive of all and whatsoever the claims that the Contractor may have
from GIPCL. The Contractor shall not be entitled to claim any amounts which
are not mentioned in the Final Bill and the Contractor shall be deemed to have
waived any claims not mentioned in the Final Bill and shall not be entitled to
recover the same from GIPCL subsequent to the submission of the Final Bill
on any account and GIPCL shall stand absolved of all its liabilities in respect
of any such claims not raised by the Contractor in his Final Bill.
B. Validity and Uniformity of Rates
The rates shall be valid and shall remain unaltered and firm for the Contract Period
and for any agreed extension thereof.
5. SUBMISSION OF TECHNICAL DOCUMENTS TO THE ENGR-IN-CHARGE
Contractor shall submit following documents to the Engineer-in-charge for verification
purpose of the bill:-
(i) Measurement sheet along with joint record of work done (JMR) & bill
abstract duly signed by authorized representative of contractor and GIPCL
Engineer in standard Measurement Book / sheet.
(ii) Contractor’s Material Inward challan copies, duly signed & stamped by GIPCL
material Gate security personnel.
(iii) Material test reports, field test reports etc… as per GIPCL’s approved quality
plan for specific major works or as directed by Engineer-in-charge.
(iv) Any other required documents and/or records in support of claim made by
contractor in his bill as directed by Engineer-in-charge.
The bill will not be entertained without submission of above documents.
6. SUBMISSION OF STATUTORY COMPLIANCES WITH EACH BILL
Contractor shall submit the bill/s of work carried out along with following documents.
(i) Copy of statutory compliance like labour license, wages payment register, EC
Policy, PF paid Challan with ECR, TRRN confirmation by EPFO/Bank, Bank
statement, etc… along wage certificate pertaining to respective bill period /
previous month/s of bill period with Annexure-I provided in Section-F.
(ii) Notarized Indemnity Bond in case of Final bill.
(iii) No claim - No arbitration certificate as per PRO-FORMA (Annexure-D in Section-
F), after the final bill amount is certified by GIPCL for payment and the same is
made known to the contractor by GIPCL & accepted by the contractor.
Bill submitted without any of the above documents shall not be processed for
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
7. MEASUREMENT & DAILY REPORTS
Measurement Standards:
All work shall be measured as completed (finished) work in accordance with the item
nomenclature defined in the SoR (Schedule of Rates in Section-E), Detailed Technical
Specifications (Section-G) and as per relevant IS codes and standard industry practices.
Where there is repugnant to or at variance with any provisions of the relevant IS codes and
this tender document, then unless a different intention appears, the provision of the
conditions & specifications of this Tender documents / contract shall prevail to the extent of
such repugnancy of variance.
Joint Measurement Recording (JMR):
Joint measurements shall be recorded immediately upon completion of each
identifiable and measurable scope item of work.
These measurements must be signed jointly by GIPCL's Engineer-in-Charge (or
authorized representative) and the contractor's site representative.
The original signed Joint Measurement Records (JMRs) shall be submitted along
with each RA bill. Bills without original JMRs will not be processed for payment.
Theoretical Weight Consideration (for Steel Items):
For fabricated structural steel and reinforcement steel, standard theoretical unit
weights (as per IS standards) shall be adopted for measurement and billing
No rolling tolerance or weight variation from supplier shall be considered for
additional payment.
Daily Records & Reporting Infrastructure:
To ensure timely and accurate billing, the contractor shall:
Maintain a computer system with a printer at the site for keeping daily logs,
measurement data, manpower deployment, and work progress.
Submit daily work progress reports and job completion/measurement reports
as and when required by GIPCL.
Ensure that monthly/RA billings are strictly based on certified measurements
recorded through JMRs.
Inspection and Quality Review:
All executed works are subject to inspection by the Engineer-in-Charge or their
authorized representatives.
If any work is found unsatisfactory or deviating from approved specifications,
GIPCL reserves the right to:
o Reject the work,
o Withhold payment,
o Or initiate rectification at the contractor’s cost and risk.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
Such decisions shall be binding on the contractor.
Dispute Resolution on Measurement:
In case of any dispute or disagreement regarding the mode or basis of measurement for
any item, the decision of the Engineer-in-Charge shall be final and binding on the
8. MOBILIZATION AND EXECUTION
a) Timely Mobilization:
The contractor shall mobilize necessary manpower, tools, equipment, and
materials within 24 hours of receiving intimation or requirement from GIPCL for
any assigned work. Delays in mobilization shall attract suitable action, including
penalties, at the discretion of GIPCL.
b) Deployment of Qualified Supervision Team:
The contractor shall deploy an adequate number of experienced site supervisors
and engineers, responsible for:
Execution of the assigned works within the stipulated time and as per approved
technical specifications,
Ensuring compliance with safety and quality norms,
Coordinating closely with GIPCL’s Engineer-in-Charge and respective area
representatives,
Obtaining daily work certification and clearance for measurements.
c) Scalable Resource Mobilization:
The volume and nature of work may vary significantly throughout the contract. The
contractor shall be prepared to scale up or down resources (manpower,
equipment, etc.) promptly as per GIPCL’s instructions and site requirements,
without any delay or additional cost implication to GIPCL.
d) Accommodation of Contractor’s Workforce:
The contractor shall make adequate accommodation and welfare arrangements
for all personnel deployed by them at their own cost. GIPCL shall not be responsible
for providing or arranging accommodation, transportation, or any logistical support
for the contractor’s manpower.
9. ENGINEER-IN-CHARGE / OWNER TO DIRECT WORK AND ORDER
ALTERATIONS, MODIFICATIONS, DELETIONS
9.1 The Engineer-in-charge shall have the right to direct the manner in which all
work under this contract shall be conducted in so far as may be necessary to
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
secure the safe and proper progress and the specified quality of work, and all
work shall be done and all material shall be furnished to the satisfaction and
approval of the OWNER.
9.2 Additional drawings and explanations to exhibit or illustrate details may be
provided by the OWNER and shall be so provided whenever necessary and
if consistent with the drawings and specifications shall be binding upon the
CONTRACTOR. The written decision of the OWNER as to the true
construction and meaning of the drawings and specifications and of such
additional drawings and explanations shall be binding upon the
9.3 If at any time the CONTRACTOR’S methods, materials, or equipment appear
to the OWNER to be unsafe, inefficient or inadequate for securing the safety
of the workmen or the public, the quality of work or the rate of progress
required, he may order the CONTRACTOR to increase their safety, efficiency
and adequacy, and the CONTRACTOR shall comply with such orders. If at
any time the CONTRACTOR’S working force and equipment are, in the
opinion of the OWNER, inadequate for securing the necessary progress, as
herein stipulated, the CONTRACTOR shall, if so directed, increase the
working force and equipment to such an extent as to give reasonable
assurance of compliance with the schedule of completion. The failure of the
OWNER to make such demands shall not relieve the CONTRACTOR of his
obligations to secure the quality, the safe conducting of the work, and the rate
of progress required by the contract, and the CONTRACTOR alone shall be
and remain liable and responsible for the safety, efficiency, and adequacy of
his methods, materials, working force, equipment and timely completion of job
irrespective of whether or not he makes any change as a result of any order
or orders received from the OWNER.
9.4 The OWNER / ENGINEER shall have the power to make any alteration in,
omissions from, additions to the original specifications, drawings, designs and
instructions that may appear to him to be necessary or advisable during the
progress of the work and the CONTRACTOR shall be bound to carry out the
work in accordance with any instructions that may be given to him in writing
by the OWNER / ENGINEER and such alterations, omissions, additions or
substitutions shall not invalidate the contract. Any altered, additional or
substituted work which the CONTRACTOR may be directed to do in the
manner above specified as part of the work, shall be carried out by the
CONTRACTOR on the same conditions in all respects on which he agreed to
do the main work and at the same rates as are specified in the tender for the
main work, unless such alterations are not identical with items of work and
form extra items.
9.5 The time for completion of the work shall be extended in the time proportion
that the altered, additional or substituted work bears to the original contract
and the decision of the OWNER shall be conclusive and binding on the
10 SETTING OUT WORKS
10.1 The CONTRACTOR shall set out the works and shall be responsible for the
true and perfect setting out of the same and for the correctness of the
positions, levels, dimensions and alignment of all parts thereof. If at any time,
any error shall appear during the progress of any part of the work, the
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
CONTRACTOR shall at his own expenses rectify such error, if called upon,
to the satisfaction of the OWNER.
10.2 The CONTRACTOR shall provide all facilities, instruments and attendance to
the OWNER or his deputed representative to check his work. Instruments
brought by the CONTRACTOR shall be in good working condition and are
subject to approval of the OWNER. Checking in part or full or any setting out
or any line or level by the OWNER shall not in any way relieve the
CONTRACTOR of his responsibility o for the correctness thereof.
10.3 The CONTRACTOR shall establish and maintain base lines and bench marks
adjacent of the various sections of work. All such marks and stakes must be
carefully preserved by the CONTRACTOR, and in case of their destruction by
him or any of his employees, they will be replaced at the CONTRACTOR’S
10.4 The CONTRACTOR shall be responsible for the accuracy of all dimensions
within the various sections of the work according to the figures of dimensions
on the drawings/actual.
11. DEFECT LIABILITY PERIOD
Even after checking, supervising, witnessing and approving the works, materials, test results,
etc… whatsoever by GIPCL Engineer and / or consultant in part or full or any setting out or
any line or level by the OWNER shall not in any way relieve the CONTRACTOR of his
responsibility for the correctness thereof and for his obligations during Defect Liability Period
and Contractor will be fully liable till successful completion of Defect Liability Period.
The Defect Liability Period for the entire scope of work shall be one (01) year from the
date of completion and acceptance of the work, as certified in writing by the Engineer-in-
During this period, if any defect, deficiency, settlement, or failure in workmanship,
materials, or performance arises in any part of the work already executed, the contractor
shall, upon receiving written intimation from GIPCL, rectify the same at no additional cost,
within seven (07) calendar days.
If the contractor fails to attend to or complete the rectification within the stipulated 7-
day period, GIPCL reserves the right to:
Carry out the rectification through a third party or departmentally,
Recover the full cost incurred for such rectification from any dues payable to the
contractor or from the Security Deposit, and/or
Impose other contractual remedies as deemed fit.
In case of delays beyond 7 days, GIPCL shall have the right to:
Delay the release of the Security Deposit by an equivalent number of days until
satisfactory rectification is completed,
Or withhold a proportionate amount of the security deposit equivalent to the estimated
cost of pending rectification works.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
The contractor shall remain fully liable for all such defects arising due to poor
workmanship, non-compliance with specifications, use of substandard materials, or any
negligence attributable to him or his subcontractors, vendors, or labour.
12. CONSTRUCTION DRAWINGS
12.1 One set of the drawings and specifications shall be furnished by the OWNER
to the CONTRACTOR, and OWNER shall furnish, within such time as he may
consider reasonable, one copy of any additional drawing/s which in his
opinion may be necessary for the execution of any part of the work. Such
copies shall be kept on the works and the OWNER and their representatives
shall at all reasonable times have access to the same, and they shall be
returned to the OWNER by the CONTRACTOR before the issue of the
certificate for the balance of his account under the contract. This contract and
the signed drawings shall remain in the custody of the OWNER, and shall be
produced by him at his office as and when required by the OWNER or by the
12.2 Whenever final drawings, plans and complete details are not ready, the
CONTRACTOR will have to proceed with the work as and when drawings are
released. The CONTRACTOR will have absolutely no claim whatsoever on
the score of delay in the issue of drawings. The CONTRACTOR shall have
no claim for any compensation due to delay in the issue of drawings. In case
the work is retarded or even stopped temporarily for lack of details and
construction drawings to proceed with, the CONTRACTOR would be given
extension of time to the extent his work has been held up for want of drawings.
The OWNER/ENGINEER decision in regard to time allowed on this account
shall be final and binding.
13. CERTIFICATE OF VIRTUAL COMPLETION
The works shall not be deemed to be completed in any respect until a formal
Certificate of Virtual Completion is issued in writing by the Engineer-in-
Charge/Owner. This certificate will only be issued after the contractor has fulfilled
the following conditions to the satisfaction of GIPCL:
1. Substantial Completion of All Works: All scope items as per the contract and SoR
must be completed in accordance with technical specifications, drawings, and quality
2. Clearing of Site: The site must be cleared of all debris, surplus materials,
construction waste, tools, equipment, and temporary facilities not required for DLP.
3. Submission of Required Documents: The contractor must submit all statutory
documents, test reports, as-built drawings, material reconciliation statements, and
any other documentation required under the contract.
4. Engineer’s Inspection & Approval: GIPCL’s Engineer-in-Charge shall inspect the
completed works and, upon being satisfied that the works meet contractual
obligations (excluding minor items not affecting occupancy or use), shall issue the
Certificate of Virtual Completion.
5. Start of Defect Liability Period: The Defect Liability Period shall commence from
the date of issue of the Certificate of Virtual Completion and not before.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
Note: Issuance of this certificate does not relieve the contractor of any responsibilities related
to correction of defects or contractual liabilities under other clauses.
14. QUANTITY OF WORK
The quantities specified in the Schedule of Rates (SoR) are indicative and meant for
tendering purposes only. Payment will be made based strictly on the actual work
executed and certified by the Engineer-in-Charge at the agreed item rates,
irrespective of the initially estimated quantities.
GIPCL reserves the unrestricted right to increase, decrease, or omit any item in the
SoR at its discretion, and the contractor shall have no claim for loss of anticipated
profits, overheads, or compensation arising from such changes.
The contractor is required to deploy adequate skilled, semi-skilled, and unskilled
manpower, tools, tackles, materials, and consumables as per the workload and
emergency requirements throughout the contract period to complete the work
satisfactorily. The quantities of individual items may vary to any extent depending
upon project requirements; however, the item rates shall remain firm and unchanged
throughout the contract duration and any extensions granted. It is the contractor’s
responsibility to execute the entire scope of work to the full satisfaction of the
Engineer-in-Charge, adhering to all specifications, safety norms, quality standards,
and timelines, regardless of any variation in quantities.
15. GENERAL CONDITIONS OF CONTRACT
General Conditions of Contract (Section-C) and detail specification prepared by the
company will be applicable for this contract. The same is enclosed herewith. Bidders
are advised to go through the same.
Where any portion of the general conditions of contract is repugnant to or at variance
with any provisions of the special conditions of contract, then unless a different
intention appears, the provision of the special conditions of contract shall prevail to
the extent of such repugnancy of variance.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
SCHEDULE OF RATE & PRICE BID
(Bidder’s offer in % to be quoted online only through website:
https://tender.nprocure.com)
Estimated Item Rate Estimated
Item BRIEF ITEM DESCRIPTION UNIT
Quantity without Amount (Rs.)
A CIVIL WORKS FOR PEB SHED-1
1 Area grading in all type of soil up to grade
level/required level, including cutting of
unwanted vegetations as directed by Engineer-
in-charge by manual means and transportation
and disposal of excavated material to the dump
sites within the lead up to 03 (three) kms.
Including maximum lift of 1.0 mtr. Clearing and 1683.000 SQM 14.76
grubbing includes uprooting rank vegetation
grass bushes, shrubs, sapling and trees girth up
to 300 mm removal of stumps of trees cut earlier
and disposal of unserviceable materials all
including and also as per detailed
specifications.
2 Earthwork in excavation in all kinds of soil for
foundations, flooring, forming drains,
excavation in trenches, etc (including hard rock
requiring chiselling or blasting if any) including
all lifts, in both wet and dry conditions,
dewatering of surface and subsurface water,
shoring, planking and strutting (if required)
disposal / stacking of surplus excavated soil etc.
within a lead of 5000 m and as per
specifications and directions of the Engineer-in-
charge (The measurement for payment shall be
the theoretical excavation volume only as per
drawing i.e. for the volume of the block of the 752.000 CUM 200.00
bottom excavation having the depth and
maximum dimensions of the foundation
structures including mud mat as per drawing.
The contractor shall take into account in his
offer, the provision for any excess excavation
for necessary working space, steps, sloping etc.
required for excavation safely and other & re-
filling the side slope/working space etc) for
depth up to avg. 1.50 m all including and also
as per detailed specifications (Depth of
excavation is to be measured from existing avg.
3 Same as above for Excavation for b) depth from
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
4 Providing and laying about 230mm thick rubble
soling to proper line, level and slope below
beam, flooring including hand packing,
wedging, binding/filling all joints using bed
materials, watering, ramming, manually
compacting, dressing, etc. complete as per
drawing, specification and instruction of the
Engineer-in-charge and also as per detailed
specifications (Bed material / fly ash of required 315.000 CUM 1,695.68
quantity shall be issued at free of cost from silo
of GIPCL-SLPP on specific request as
available. The rate is including loading,
unloading and necessary transportation of fly
ash up to work site in truck mounted closed
container and the remained/unused quantity of
fly ash shall be removed from site by the
contractor as directed).
5 Providing and laying in position plain cement
concrete as levelling course under foundations,
Plinth Beam, trenches, concrete bedding, plinth
protection etc... at any depth and at elevation as
per drawing including preparing and ramming
the base before placing the concrete, curing,
compacting, dewatering (if required), including 162.000 CUM 4,100.00
form work etc. all complete as per drawing and
as directed by Engineer-in-charge for the
Nominal Mix 1:3:6 (1 cement : 3 sand : 6 graded
stone aggregates 40 mm nominal size) all
including and also as per detailed
specifications.
6 Providing and laying reinforced cement
concrete Grade M25 (Design Mix - minimum
cement content 390 kg per CUM) with graded
stone aggregates 20 mm nominal size
confirming to IS 456 for RCC Works including
preparing the base before placing of concrete
and finishing smooth, including mixing & placing
concrete in position, watering, compacting,
vibrating, curing, dewatering (if required),
embedment, edge angles, insert plates, pipe
sleeves, anchor bolts etc... wherever
necessary, providing construction joints,
leaving cut-outs / pockets including all labours, 141.000 CUM 5,900.00
supervision, materials, equipments, tools &
tackles etc. all complete as per detail technical
specifications, drawings and as directed by
Engineer-in-Charge, all including and also as
per detailed specifications (Supply of cement
and all other construction materials shall be in
the scope of contractor, however, excluding
cost of formwork and reinforcement for RCC
and shall be paid in specific respective item as
under) for reinforced concrete work in
Foundations, footings, Base of columns and
Mass concrete (finish type F1).
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
7 Same as above item of RCC Grade M25 for
Beams, Girders etc… up to finished floor level 37.000 CUM 5,800.00
(finish type F2).
8 Same as above item of RCC Grade M25
(Design Mix - minimum cement content 390 kg
per CUM) for Columns, Pedestals, Pillars posts 6.000 CUM 5,800.00
and struts, up to finished floor level (finish type
9 Providing formwork of ordinary timber planking
so as to give a rough finish including centring,
shuttering, strutting and propping, providing,
provision for required openings/ cut-outs/
pockets, etc. complete as per detailed
specifications and as directed by Engineer-in-
charge etc. Height of propping and centring
below supporting floor to ceiling not exceeding
4 M and removal of the same for in-situ
reinforced concrete and plain concrete work in
Foundations, Footings Bases of Columns etc.
and Mass concrete.
10 Providing formwork to give fair & smooth finish
for exposed concrete surface using sheeting
formed from tongued and grooved
boards/plywood / steel sheets for column,
beams, pedestals, walls, coping, facias, fins,
etc. including centring, shuttering, strutting and
propping, providing, provision for required
openings/ cut-outs/ pockets, etc. complete as
per detailed specifications and as directed by
Engineer-in-charge etc. Height of propping and
centring below supporting floor to ceiling not
exceeding 4 M and removal of the same for in-
situ reinforced concrete and plain concrete work
in Sides and soffits of Beams, Beam
Haunchings, cantilevers, Girders Bressumers
and Lintels not exceeding 1 M in Depth.
11 Earthwork in backfilling around foundation, pits,
trenches, filling under floors and other
substructures with selected available excavated
material, compacting / watering the backfilling in
layers of about 20 cm at desired locations
including carting of backfill material from areas
where it is stacked, spreading evenly the
unused excavated material in the stacking yard
after backfilling complete as per detailed
specifications and directed by Engineer-in- 114.000 CUM 124.72
charge. The measurement for payment shall be
the theoretical excavation volume paid in item
no. 2 & 3 less volume of concrete as per
drawing. The contractor shall consider in his
rate the provision for any excess backfilling for
excavated area for necessary working space,
steps, sloping etc. required for excavation
safely and other & re-filling the side
slope/working space etc.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
12 Providing and laying machine laid Trimix
(Vacuum Dewatered) Concrete Flooring M30
grade (Design Mix - minimum cement content
410 kg per CUM) with 20mm downgraded stone
aggregates confirming to IS 456 in correct line
& level and finishing the surface of placed
concrete by poker vibration and surface
vibrator, adding of Fosroc make Nito floor
hardener at the rate of 1.00 Kg/Sqm at top of
finished surface, making of construction joint for
size about 10mm wide and 50mm deep
(average) at about 5mx4m interval in
longitudinal and transverse direction
respectively or as per drawings or as
appropriately site suitable as directed by Engr-
in-charge (by cutting groove in hardened
concrete by cutter machine and filling bitumen
mixed with sand in cut groove) curing etc.
complete for all lead & lift as directed by
Engineer-in-charge, all including and also as
per detailed specifications. The rate shall be
including cost of all the construction materials
(except Reinforcement which will be paid in
respective item), labours, supervision,
materials, equipments and tools & tackles.
Shuttering, side channels shall be included.
13 Providing and fixing TMT/HYSD (FE 500D
CRS) bar reinforcement for R.C.C. work
including supplying of bars of required diameter,
straighten, handle, cut bend, crank, fix and tie in
position as per approved drawings or as
directed by Engineer-in-charge with the using of
cover blocks of same grade of concrete in all
RCC items of work including cost of GI binding
wire 18SWG double knot, including cost of all
required labours, supervision, materials and
equipments, tools & tackles, etc., all complete 39.000 MT 71,000.00
as directed by Engineer-in-charge, all including
and also as per detailed specifications..
Measurement shall be done according to
standard IS practice including authorized
lapping at theoretical weight for different
sections including bending, binding and placing
in position etc. complete for RCC works. No
payment shall be made for reinforcement used
for chairs, spacers & fixing bolts. No payment
for binding wires.
14 Brick masonry work using common burnt clay
building bricks having crushing strength not less
than 35 kg/Sq.Cm. in foundation, plinth, walls
including provision of standard metallic
scaffolding in cement mortar 1:1.5 (1- cement 1.000 CUM 5,650.00
:1.5 -fine sand) including scaffolding wherever
necessary, curing, raking joints, etc. complete
as per detailed specifications and drawings or
as directed by Engineer-in-charge.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
15 Providing & Laying cement plaster with cement
mortar 1:4 (1 cement, 4 sand), 15mm average
thick to interior/exterior faces of walls, beams,
bends, moulds, etc... including providing and
applying lime punning with properly slaked fat
lime @ 2.2kg/sq.m to the plaster work when it is
still green and finishing the area to a smooth
and even finish. Rate should also include
provision of grooves, including provision of
standard metallic scaffolding, curing and
finishing smooth complete all including and also
as per detailed specifications. Rate also
includes hacking of RCC surfaces and providing
and fixing chicken mesh at junction of RCC and
masonry and for electrical conduits (actual area
shall be measured).
16 Finishing wall with 100% acrylic weatherproof
exterior emulsion paint 2 coat (Asian Paints -
Apex Weatherproof or Berger - Weather Coat)
of approved colour and shade, over a coat of
compatible exterior grade primer/sealer on
newly plastered surfaces to give required shape 74.000 SQM 220.00
even shade after thoroughly brushing the
surface to remove all dirt, and remains of loose
powdered materials, etc... complete including
provision of standard metallic scaffolding, etc as
per detailed specifications.
17 Providing & filling expansion joints in between
RCC elements by 25 mm thickness SILFEX pre
molded compressible filler board in black
colour, of approved make (Supreme industries
or equivalent) confirming MORTH specification
(Clause 1015), having minimum density of
Kg/ Cum, non staining with less than 1% water 6.000 SQM 3,154.00
absorption & compression recovery of 93%
minimum as per the detailed specifications and
filling with bitumen tar and sand mixture to finish
the top surface including all material, labour,
transportation, tools & tackles etc complete as
directed by Engr-in-charge.
18 Labour charge for placing, aligning, fixing in
position to correct lines and levels all types of
mild steel embedment such as plate inserts,
pipe sleeves, foundation bolt/assemblies, edge
protection angles, etc, in RCC, all as per
specifications and as shown in construction
drawings and as directed by the Engr-in-charge
and also as per detailed specifications using
steel templates, etc. as required (providing
required size & nos. of templates is included in
scope of work and same shall be used for fixing
inserts and will not be measured and not be
paid). Threaded part of bolt shall be protected
by using Grease & solid plastic bags.
Transportation of Foundation bolt form godown
etc. shall be in the scope of contractor.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
19 Grouting of the bases of equipment/stanchions
including anchor bolt pocket/ pipe sleeves etc.
with using ready mix approved make non-
shrinkage free flow grout (CONBEXTRA GP2
ready mix grout) as per manufacturer’s
instructions, including labour, tools, plant, 2.000 CUM 67,700.00
shuttering, curing, roughening/ chipping of
concrete to required level where necessary etc.
complete as per detailed specifications and as
directed by Engr-in-charge.
20 Supplying and fixing anchor fasteners of HILTI
or Fischer or other approved make in RCC
beams, columns and slabs including
scaffolding, drilling holes etc. complete as per 11.000 EACH 265.00
manufacturer's specification and as directed by
the Engineer-in-charge as per specifications for
12 mm dia. standard anchor fasteners.
21 Supplying and fixing anchor fasteners of HILTI
or Fischer or other approved make in RCC
beams, columns and slabs including
scaffolding, drilling holes etc. complete as per 11.000 EACH 380.00
manufacturer's specification and as directed by
the Engineer-in-charge as per specifications for
16 mm dia. standard anchor fasteners.
TOTAL TENDER COST FOR SHED-1 CIVIL WORKS (A)
B CIVIL WORKS FOR PEB SHED-2
22 Area grading in all type of soil up to grade
level/required level, including cutting of
unwanted vegetations as directed by Engineer-
in-charge by manual means and transportation
and disposal of excavated material to the dump
sites within the lead up to 03 (three) kms.
Including maximum lift of 1.0 mtr. Clearing and 1189.000 SQM 14.76
grubbing includes uprooting rank vegetation
grass bushes, shrubs, sapling and trees girth up
to 300 mm removal of stumps of trees cut earlier
and disposal of unserviceable materials all
including and also as per detailed
specifications.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
23 Earthwork in excavation in all kinds of soil for
foundations, flooring, forming drains,
excavation in trenches, etc (including hard rock
requiring chiselling or blasting if any) including
all lifts, in both wet and dry conditions,
dewatering of surface and subsurface water,
shoring, planking and strutting (if required)
disposal / stacking of surplus excavated soil etc.
within a lead of 5000 m and as per
specifications and directions of the Engineer-in-
charge (The measurement for payment shall be
the theoretical excavation volume only as per
drawing i.e. for the volume of the block of the 371.000 CUM 200.00
bottom excavation having the depth and
maximum dimensions of the foundation
structures including mud mat as per drawing.
The contractor shall take into account in his
offer, the provision for any excess excavation
for necessary working space, steps, sloping etc.
required for excavation safely and other & re-
filling the side slope/working space etc) for
depth up to avg. 1.50 m all including and also
as per detailed specifications (Depth of
excavation is to be measured from existing avg.
24 Same as above for Excavation for b) depth from
25 Providing and laying about 230mm thick rubble
soling to proper line, level and slope below
beam, flooring including hand packing,
wedging, binding/filling all joints using bed
materials, watering, ramming, manually
compacting, dressing, etc. complete as per
drawing, specification and instruction of the
Engineer-in-charge and also as per detailed
specifications (Bed material / fly ash of required 179.000 CUM 1,695.68
quantity shall be issued at free of cost from silo
of GIPCL-SLPP on specific request as
available. The rate is including loading,
unloading and necessary transportation of fly
ash up to work site in truck mounted closed
container and the remained/unused quantity of
fly ash shall be removed from site by the
contractor as directed).
26 Providing and laying in position plain cement
concrete as levelling course under foundations,
Plinth Beam, trenches, concrete bedding, plinth
protection etc... at any depth and at elevation as
per drawing including preparing and ramming
the base before placing the concrete, curing,
compacting, dewatering (if required), including 90.000 CUM 4,100.00
form work etc. all complete as directed by Engr-
in-charge for the Nominal Mix 1:3:6 (1 cement :
3 sand : 6 graded stone aggregates 40 mm
nominal size) as per detailed specifications.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
27 Providing and laying reinforced cement
concrete Grade M25 (Design Mix - minimum
cement content 390 kg per CUM) with graded
stone aggregates 20 mm nominal size
confirming to IS 456 for RCC Works including
preparing the base before placing of concrete
and finishing smooth, including mixing & placing
concrete in position, watering, compacting,
vibrating, curing, dewatering (if required),
embedment, edge angles, insert plates, pipe
sleeves, anchor bolts etc.. wherever necessary,
providing construction joints, leaving cut-outs /
pockets including all labours, supervision,
materials, equipments, tools & tackles etc. all
complete as per detail technical specifications,
drawings and as directed by Engineer-in-
Charge, all including and also as per detailed
specifications (Supply of cement and all other
construction materials shall be in the scope of
contractor, however, excluding cost of formwork
and reinforcement for RCC and shall be paid in
specific respective item as under) for reinforced
concrete work in Foundations, footings, Base of
columns and Mass concrete (finish type F1).
28 Same as above item of RCC Grade M25
(Design Mix - minimum cement content 390 kg
per CUM) for Beams, Girders etc… up to
finished floor level (finish type F2).
29 Same as above item of RCC Grade M25
(Design Mix - minimum cement content 390 kg
per CUM) for Columns, Pedestals, Pillars posts 3.000 CUM 5,800.00
and struts, up to finished floor level (finish type
30 Providing formwork of ordinary timber planking
so as to give a rough finish including centring,
shuttering, strutting and propping, providing,
provision for required openings/ cut-outs/
pockets, etc. complete as per detailed
specifications and as directed by Engineer-in-
charge etc. Height of propping and centring
below supporting floor to ceiling not exceeding
4 M and removal of the same for in-situ
reinforced concrete and plain concrete work in
Foundations, Footings Bases of Columns etc.
and Mass concrete.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
31 Providing formwork to give fair & smooth finish
for exposed concrete surface using sheeting
formed from tongued and grooved
boards/plywood / steel sheets for column,
beams, pedestals, walls, coping, facias, fins,
etc. including centring, shuttering, strutting and
propping, providing, provision for required
openings/ cut-outs/ pockets, etc. complete as
per detailed specifications and as directed by
Engineer-in-charge etc. Height of propping and
centring below supporting floor to ceiling not
exceeding 4 M and removal of the same for in-
situ reinforced concrete and plain concrete work
in Sides and soffits of Beams, Beam
Haunchings, cantilevers, Girders Bressumers
and Lintels not exceeding 1 M in Depth.
32 Earthwork in backfilling around foundation, pits,
trenches, sewer lines, filling under floors and
other substructures with selected available
excavated material compacting / watering the
backfilling in layers of about 20 cm at desired
locations including carting of the backfill
material from areas where it is stacked,
spreading evenly the unused excavated
material in the stacking yard after backfilling
complete as per detailed specifications and
directed by Engineer-in-charge. The
measurement for payment shall be the
theoretical excavation volume paid in item no.
23 & 24 less volume of concrete as per drawing.
The contractor shall take into account in his rate
the provision for any excess backfilling for
excavated area for necessary working space,
steps, sloping etc. required for excavation
safely and other & re-filling the side
slope/working space etc.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
33 Providing and laying machine laid Trimix
(Vacuum Dewatered) Concrete Flooring M30
grade (Design Mix - minimum cement content
410 kg per CUM) with 20mm downgraded stone
aggregates confirming to IS 456 in correct line
& level and finishing the surface of placed
concrete by poker vibration and surface
vibrator, adding of Fosroc make Nito floor
hardener at the rate of 1.00 Kg/Sqm at top of
finished surface, making of construction joint for
size about 10mm wide, 50mm deep at about
5mx4m interval in longitudinal and transverse
direction respectively or as per drawings or as 117.000 CUM 6,450.00
appropriately site suitable as directed by
Engineer-in-charge (by cutting groove in
hardened concrete by cutter machine and filling
bitumen mixed with sand in cut groove) curing
etc. complete for all lead & lift as directed by
Engineer-in-charge, all including and also as
per detailed specifications. The rate shall be
including cost of all the construction materials
(except Reinforcement which will be paid in
respective item), labours, supervision,
materials, equipments and tools & tackles.
Shuttering, side channels shall be included.
34 Providing and fixing TMT/HYSD (FE 500D
CRS) bar reinforcement for R.C.C. work
including supplying of bars of required diameter,
straighten, handle, cut bend, crank, fix and tie in
position as per approved drawings or as
directed by Engineer-in-charge with the using of
cover blocks of same grade of concrete in all
RCC items of work including cost of GI binding
wire 18SWG double knot, including cost of all
required labours, supervision, materials and
equipments, tools & tackles, etc., all complete 20.000 MT 71,000.00
as directed by Engineer-in-charge, all including
and also as per detailed specifications..
Measurement shall be done according to
standard IS practice including authorized
lapping at theoretical weight for different
sections including bending, binding and placing
in position etc. complete for RCC works. No
payment shall be made for reinforcement used
for chairs, spacers & fixing bolts. No payment
for binding wires.
35 Brick masonry work using common burnt clay
building bricks having crushing strength not less
than 35 kg/Sq.Cm. in foundation, plinth, walls
including provision of standard metallic
scaffolding in cement mortar 1:1.5 (1 cement 1.000 CUM 5,650.00
:1.5 fine sand) including scaffolding, curing,
raking joints, etc. complete as per detailed
specifications, drawings as directed by Engr-in-
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
36 Providing & Laying cement plaster with cement
mortar 1:4 (1 cement, 4 sand), 15mm average
thick to interior/exterior faces of walls, beams,
bends, moulds, etc... including providing and
applying lime punning with properly slaked fat
lime @ 2.2kg/sq.m to the plaster work when it is
still green and finishing the area to a smooth
and even finish. Rate should also include
provision of grooves, including provision of
standard metallic scaffolding, curing and
finishing smooth complete all including and also
as per detailed specifications. Rate also
includes hacking of RCC surfaces and providing
and fixing chicken mesh at junction of RCC and
masonry and for electrical conduits (actual area
shall be measured).
37 Finishing wall with weather proof exterior
emulsion paint on wall surface (two coats) to
give an required shape even shade after
thoroughly brushing the surface to remove all
dirt, and remains of loose powdered materials,
etc... complete. This includes two coats of 100%
acrylic weatherproof exterior emulsion paint
such as Asian Paints - Apex Weatherproof or
Berger - Weather Coat, of approved colour and
shade, over a coat of compatible exterior grade
primer/sealer on newly plastered surfaces
including provision of standard metallic
scaffolding, all including and also as per
detailed specifications.
38 Providing & filling expansion joints in between
RCC elements by 25mm thick SILFEX
premolded compressible filler board in black
colour (Supreme or equivalent) confirming
MORTH Clause 1015), having minimum density
of 95 Kg/ Cum, non-staining with less than 1% 6.000 SQM 3,154.00
water absorption & compression recovery 93%
minimum as per the detailed specifications and
filling with bitumen tar and sand mixture to finish
the top surface etc complete as directed by
Engineer-in-charge.
39 Labour charge for placing, aligning, fixing in
position to correct lines and levels all types of
mild steel embedment such as plate inserts,
pipe sleeves, foundation bolt/assemblies, edge
protection angles, etc, in RCC, all as per
specifications and as shown in drawings as
directed by the Engr-in-charge using steel
templates, etc. as required (providing required 3300.000 KG 45.00
size & nos. of templates is included in scope of
work and same shall be used for fixing inserts
and will not be measured and not be paid).
Threaded part of bolt shall be protected by
using Grease & solid plastic bags.
Transportation of Foundation bolt form godown
etc. shall be in the scope of contractor.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
40 Grouting of the bases of equipment/stanchions
including anchor bolt pocket/ pipe sleeves etc.
with using ready mix approved make non
shrinkage free flow grout (CONBEXTRA GP2
ready mix grout) as per manufacture’s
instructions, including labour, tools, plant, 2.000 CUM 67,700.00
shuttering, curing, roughening/ chipping of
foundation concrete to required level where
necessary etc. complete as per detailed
specifications and as directed by Engineer-in-
41 Supplying and fixing anchor fasteners of HILTI
or Fischer or other approved make in RCC
beams, columns and slabs including
scaffolding, drilling holes etc. complete as per 11.000 EACH 265.00
manufacturer's specification and as directed by
the Engineer-in-charge as per specifications for
12 mm dia. standard anchor fasteners.
42 Supplying and fixing anchor fasteners of HILTI
or Fischer or other approved make in RCC
beams, columns and slabs including
scaffolding, drilling holes etc. complete as per 11.000 EACH 380.00
manufacturer's specification and as directed by
the Engineer-in-charge as per specifications for
16 mm dia. standard anchor fasteners.
TOTAL TENDER COST FOR SHED-2 CIVIL WORKS (A)
C AREA DEVELOPMENT WORKS
43 Earthwork in excavation in all kinds of soil for
foundations, flooring, forming drains, road,
pavements, area development works, etc
(including hard rock requiring chiselling or
blasting if any) including all lifts, in both wet and
dry conditions, dewatering of surface and
subsurface water, shoring, planking and
strutting (if required) disposal / stacking of
surplus excavated soil etc. within a lead of
m and as per specifications and directions of the
Engineer-in-charge (The measurement for
payment shall be the theoretical excavation
volume only as per drawing i.e. for the volume 275.000 CUM 200.00
of the block of the bottom excavation having the
depth and maximum dimensions mentioned in
drawing including mud mat as per drawing. The
contractor shall take into account in his offer,
the provision for any excess excavation for
necessary working space, steps, sloping etc.
required for excavation safely and other & re-
filling the side slope/working space etc) for
depth up to avg. 1.50 m all including and also
as per detailed specifications (Depth of
excavation is to be measured from existing avg.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
44 Filling of dry fly ash/bed ash up to required level
on prepared surface of road, foundation, drain,
area development works, etc... at all depth
including loading, unloading transportation,
spreading in a layer of about 300mm thick or as
directed, dressing, watering, compacting and
levelling in required line & level etc. complete as
per detailed specification and as directed by
Engineer-in-charge. Fly ash of required quantity
shall be issued at free of cost from silo of
GIPCL-SLPP on specific request as available.
The rate is including loading, unloading and
necessary transportation of fly ash up to work
site in truck mounted closed container and the
remained/unused quantity of fly ash shall be
removed from site by the contractor as directed.
45 Providing and laying about 230mm thick rubble
soling to proper line, level and slope below
beam, flooring including hand packing,
wedging, binding/filling all joints using bed
materials, watering, ramming, manually
compacting, dressing, etc. complete as per
drawing, specification and instruction of the
Engineer-in-charge and also as per detailed
specifications (available rubbles from
LHS/ELHS areas will be allowed to use at free
of cost. The rate is including loading, unloading,
necessary transportation at work place &
segregation of suitable size stone/breaking to
required size stone etc. and the 127.000 CUM 750.00
remained/unused quantity of rubbles shall be
removed from site by the contractor as directed.
Also, Bed material will be issued at free of cost,
as per availability, near work site up to possible
extent. Fly ash / bed ash of required quantity
shall be issued at free of cost from silo of
GIPCL-SLPP on specific request as available.
The rate is including loading, unloading and
necessary transportation of fly ash/bed ash up
to work site in truck mounted closed container
and the remained/unused quantity of fly ash
shall be removed from site by the contractor as
TOTAL TENDER COST FOR AREA DEVELOPMENT WORKS (C)
TOTAL ESTIMATED VALUE OF TENDER-1 (A + B + C) without GST
TOTAL ESTIMATED SOR VALUE TENDER-1 with 18% GST
Note: Bidders have to quote their offer in % (+, - or equal) on above total estimated SoR value in
online Price Bid only. The quoted percentage rate on above SoR item rates (Section-E of this tender)
shall be inclusive of all labour cost, equipments, materials (except specified free issue materials by
GIPCL in respective items), supervision, consumables, tools, tackles, profit & overheads, all taxes &
duties (including GST), etc… Item rate shall be firm for entire duration of contract period and any
approved extensions.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
My rates are as under (only to be quoted online on (n)Procure).
At estimated value
OR _______ %age above the estimated value
OR _______%age below the estimated value.
Note:- (1) Percentage rate offer/bid price on SoR value including GST shall be quoted through online (n)-
Procure only. Hard copy of price bid shall not be considered/accepted.
(2) Evaluation of tender & E-Reverse Auction will be done on gross total quoted amount with GST.
SEAL & SIGNATURE OF TENDERER : __________________________________
NAME OF AUTHORISED PERSON : __________________________________
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
LIST OF ANNEXURES & FORMS
CHECKLIST FOR PASSING THE BILLS
For the month of :
1) Work Order / P.O. No. & :
2) Nature of work :
3) Duration of Work Order : From to
4) Maxi. No. of manpower per day : M F Total
deployed in the month.
5) Details of Labour License : Valid up to for
6) Details of E.C Policy : Valid up to for
7) Documents attached for verification : Wage & Attendance Sheets.
for the previous month. Yes/No
P.F Challan Yes/No
8) Documents attached for verification : Bonus Payment Register
(in case of Final Bill) Yes/No
: Leave wage register Yes/No
9) Security Deposit / Retention Money : Yes / No if yes, Rs.
Date : Signature of Contractor
with official stamp
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
PROFORMA FOR CONTRACT SECURITY-CUM-PERFORMANCE GUARANTEE
BY SELLER / CONTRACTOR
(To be executed on non-judicial stamped paper of approximate value)
1. WHEREAS Gujarat Industries Power Company Limited having its office at PO:
Ranoli, Dist. Vadodara – 391 350, Gujarat State, India (hereinafter referred to
as “The Company/Owner” which expressions shall unless repugnant to the
subject or context includes its legal representatives, successors and assigns)
has entered into a contract with M/s. ………………………………..
………………………….(hereinafter referred to as “Contractor(s)/ Seller(s)”
which expression shall unless repugnant to the subject or context includes their
legal representatives, successors and assigns ) for
…………………………….on the terms and conditions as set out inter alia, in
the Company’s contract No./ work order
No.……………………………………………..date …………and various
documents forming part thereof hereinafter referred to as the “said contract”
which expression include all amendments, modifications and/ or variations
thereto and where as the Contractor(s)/ Seller(s) has agreed for due execution
of the entire contract and guarantees its performance including any parts
executed through any other agencies/ subcontractors
AND WHEREAS one of the conditions of the “said contract” is that
“contractor(s)/seller(s) shall furnish to the owner a Bank Guarantee from a
bank for….% (……….percent) of the total value of the “said contract” against
due and faithful performance of the “said contract” including performance
guarantee obligations of the contractor(s)/seller(s) for execution/ supplies
made under the “said contract.”
2. We …………………………….Bank having its branch office at ……….……..do
hereby agree and undertake to pay the amount due and payable under this
guarantee without any demur merely on a demand from the Company stating
that in the opinion of the Company, which is final & binding, the amount claimed
is due by reason of default made by the Contractor(s)/ Seller(s) in performing
any of the terms & conditions of the said Contract including defect liability
obligations, in fulfilling the performance guarantee obligation or loss or damage
caused to or would be caused to or suffered by the Company by reason of any
breach by the said Contractor (s)/ Seller(s) of any of the terms & conditions of
the contract. Any such demand made on the Bank by the owner shall be
conclusive as regards the amount due and payable by the Bank under this
guarantee. However our liability under this guarantee shall be restricted to Rs.-
3. We undertake to pay to the Company any money so demanded not
withstanding any dispute or disputes raised by the contractor(s)/ Seller(s) in
any suit or proceeding pending before any office, court or tribunal relating
thereto our liability under this present guarantee being absolute and
unequivocal. The payment so made by us under this bond shall be a valid
discharge of our liability for payment there under. Our liability to pay is not
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
dependent or conditional on the owner proceeding against the Contractor(s)/
4. The guarantee herein contained shall not be determined or affected or
suspended by the liquidation or winding up, dissolution or change of
constitution or insolvency of the said Contractor(s)/ Seller(s) but shall in all
respect and for all purposes be binding and operative until payment of all
money due or liabilities under the said contract(s)/ Order(s) are fulfilled.
5. This guarantee will remain valid up ____________________ days or
______________ whichever is earlier. The Bank undertakes not to revoke this
guarantee during its currency without previous consent of the
OWNER/PURCHASER and further agrees that if this guarantee is extended
for a period as mutually agreed between contractor & owner/purchaser, the
guarantee shall be valid for a period so extended provided that a written
request for such extension is received before the expiry of validity of
6. We ……………Bank further agree with the Company that the company shall
have the fullest liberty without our consent and without affecting in any manner
our obligations hereunder to vary any of the terms and conditions of the said
Contract(s)/ Order(s) or to extend the time of performance by the said
Contractor(s) Seller(s) from time to time or to postpone for any time or from
time to time any of the powers exercisable by the Company against the said
Contractor(s)/ Seller(s) and to forbear or enforce any of the terms and
conditions relating to the said Contract(s)/ Order(s) and we shall not be
relieved from our liability by reason of any such variation, or extension being
granted to the said Contractor (s) / Seller(s) or for any forbearance, act or
omission on the part of the Company or any indulgence by the Company to
the said Contractor(s)/ Seller(s) or by any such matter or thing whatsoever
which under the law relating to sureties would, but for this provision, have
affect of so relieving us.
7. Notwithstanding anything contained herein before, our liability shall not exceed
Rs…………….(Rupees…………only) and shall remain in force
till..……..Unless a demand or claim under this Guarantee is made on us within
three months from the date of expiry we shall be discharged from all the
liabilities under this guarantee.
Corporate Seal of the Bank
By its constitutional Attorney
Signature of duly Authorized person
On behalf of the Bank
With Seal & Signature code
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
PROFORMA FOR BANK GUARANTEE FOR EARNEST MONEY DEPOSIT
(To be executed on non-judicial stamped paper of approximate value)
1. WHEREAS M/s.Gujarat Industries Power Company Limited having its Corporate
Office at PO: Ranoli, Dist. Vadodara – 391 350, Gujarat State, India (hereinafter
called “The Company Owner” which expression shall unless repugnant to the subject
or context includes its legal representatives, successors and assigns) has issued
tender paper vide its Tender No…………………………for ------------------------
(hereinafter called “the said tender”)to M/s.……………………………(hereinafter
called the said Tenderer(s)” which expression shall unless repugnant to the subject
or context includes their legal representatives, successors and assigns and as per
terms and conditions of the said tender, the tenderer shall submit a Bank guarantee
for Rs.………. (Rupees……………..only) towards earnest money in lieu of cash.
2. We ……………………………..Bank having its branch office at
……… do hereby undertake to pay the amount due and payable under this guarantee
without any demur, merely on a demand from the Company stating that in the opinion
of the company which is final and binding, the amount claimed is due because of any
withdrawal of the tender or any material alteration to the tender after the opening of
the tender by way of any loss or damage caused to or would be caused or suffered
by the Company by reason of any breach by the said tenderer(s) of any of the terms
and conditions contained in the said tender or failure to accept the letter of Intent
Agreement or that the amount covered under this Guarantee is forfeited. Any such
demand made on the Bank by the owner shall be conclusive as regards the amount
due and payable by the Bank under this guarantee, However, our liability under this
guarantee shall be restricted to an amount not exceeding
Rs………………..(Rupees………………..only).
3. We undertake to pay to the Company any money so demanded not withstanding any
dispute or disputes raised by the tenderer (s) in any suit or proceeding pending before
any office, court or tribunal relating thereto our liability under this present guarantee
being absolute and unequivocal. The payment so made by us under this bond shall
be a valid discharge of our liability for payment there under. Our liability to pay is not
dependent or conditional on the owner proceeding against the tenderer.
4. The guarantee herein contained shall not be determined or affected or suspended by
the liquidation or winding up, dissolution or change of constitution or insolvency of
the said tenderer(s) but shall in all respect and for all purposes be binding and
operative until payment of all money due or liabilities under the said contract(s)/
Order(s) are fulfilled.
5. We ……………..Bank Ltd. further agree that the guarantee herein contained shall
remain in full force and effect during the period that would be taken for the finalization
of the said tender and that it shall continue to be enforceable till the said tender is
finally decided and order placed on the successful tenderer(s) and or till all the dues
of the company under or by virtue of the said tender have been fully paid and its
claims satisfied or discharged or till a duly authorized officer of the company certifies
that the terms and conditions of the said tender have been fully and properly carried
out by the said tenderer (s) and accordingly discharges the guarantee.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
6. That the Owner Company will have full liberty without reference to us and without
affecting this guarantee to postpone for any time or from time to time the exercise of
any of the power of the owner under the tender.
7. Notwithstanding anything contained herein before, our liability shall not exceed
Rs…………………. (Rupees…………………………only) and shall remain in force
till…………….. (Date to be filled up shall be 180 days from the date of submission of
Corporate Seal of the Bank
By its constitutional Attorney
Signature of duly Authorized person
On behalf of the Bank
With Seal & Signature code
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
PRO-FORMA CERTIFICATE
(No claim, No arbitration)
Chief General Manager (Thermal)
Gujarat Industries Power Company Limited,
Surat Lignite Power Plant,
Village: Nani Naroli, Ta. Mangrol,
Dist. Surat – 394110 (Gujarat).
We hereby confirm with free consent as under:-
1. The measurements certified in final bill is full and final. We accept all the certified
measurements and no claim related to the measurement is left.
2. The payment certified in that or above referred LoI / contract is full and final. We accept
this, and no claim related to payment is left.
3. The rates of the LoI / contract and its amendments are firm till completion of contract and
extension period. We shall not claim any escalation against these rates.
4. Along with the contract referred, the ARBITRATION CLAUSE also perishes i.e. we will
not resort to arbitration.
5. No extra items are left to be settled.
6. We do not have any claims against any item related to the LoI than those items certified
7. We are accepting the recoveries or hold amount from our bills, if any, made by GIPCL
against non compliance or as decided by GIPCL within terms & conditions of contract.
8. We have paid royalties, taxes for all the materials procured by us, for carrying out the
works for above LoI and we indemnify GIPCL from any liability arising thereof.
9. In case of any disputes arising in future related to payment of royalties, all liabilities of
settlement of dispute and its payment if any, will be borne by us.
10. We have paid wages to all the workmen who were deployed by us for carrying out above
referred work as per prevailing Minimum wages act. We have also fulfilled all
requirements of the P.F. Act. We have maintained all records necessary as per the
statutory requirements. We hereby indemnify GIPCL from any disputes arising in future
related to payment of labours, Provident Fund, etc.. and confirm that all liabilities of
settlements of disputes and their payment is our responsibility.
The above confirmation will come into effect as soon as payment from final bill after due
recoveries will be received by us.
Signature, Stamp and date.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
PARTICULARS OF THE BIDDER
Sr. Particulars Please provide
No. information here.
1. Name of Bidder
2. a. Registered Office Address:
b. Address for Correspondence:
3. Contact Details:
Contact Person Name
Telephone No. :
Year of establishment
5. User ID for e-reverse auction on website:
https://e-auction.nprocure.com
COMPANY SEAL SIGNATURE …………………
DESIGNATION ……………..
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
GUJARAT INDUSTRIES POWER COMPANY LIMITED
(Surat Lignite Power Plant)
Schedule of Deviation from Technical Specification and Commercial Terms
All the deviations from the terms & conditions of contract shall be filled by BIDDER
clause by clause in this schedule.
Sr. No SECTION CLAUSE AS PER DEVIATION
The bidder here by certifies that the above mentioned are the only deviations from OWNER’s
Tender enquiry. The bidder further confirms that in the events any other data and information
presented in the BIDDER’s proposal and accompanying documents are at variance with
specific requirements laid out in the OWNER’s Tender Document, then the latter shall govern
and will be binding on the BIDDER for quoted price.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
Declaration cum Undertaking for Safety Laws and Regulations Compliance
(To be submitted on Company’s Letter Head)
I ______________________ on behalf of ………Name of Party/Company………..hereby confirm,
agree and undertake that all the Statutory and Safety Laws and Regulations of the applicable
Authority/ies shall be strictly followed for all types of works at the site during the period of the Contract,
if awarded to me.
Signed and Stamped by the
Authorized Signatory of the Bidder
Declaration for Contractual Litigations
(To be submitted on Company’s Letter Head)
Please Tick (√) whichever is correct option
I ______________________ on behalf of ………Name of Party/Company………..hereby confirm that
a. Not invoked legal recourse e.g. litigation against any Govt, of Gujarat Undertakings
/ Depts. / Authorities and Govt. of Gujarat supported companies / undertakings /
organizations for the last three( 03) years. There are no ongoing/pending legal
matter(s) with any of the Govt. of Gujarat Undertakings / GoG supported
Companies, including GIPCL.
Please Tick ( )
b. Invoked legal recourse e.g. litigation against any Govt, of Gujarat Undertakings /
Depts. / Authorities and Govt. of Gujarat supported companies / undertakings /
organizations for the last three( 03) years.
Please Tick ( )
If “b” is applicable, please submit the details for the same.
The above is true, as on date, to the best of my knowledge. Any breach/ false statement in this regard
shall amount to disqualification of the Bid being submitted herein.
Signed and Stamped by the
Authorized Signatory of the Bidder
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
CERTIFICATE OF COMPLIANCE BY CONTRACTOR
(To be submitted with each monthly bill on letter head along with labour compliance records)
of.........................to .......................... at Gujarat Industries Power Company Limited – Surat
Lignite Power Plant, Nani Naroli. I undertake to be bound by all the provisions of the Contract
Labour (Regulation & Abolition) Act 1970 and the Contract Labour (Regulation & Abolition)
Rules 1972, The Employees’ Provident Funds and Miscellaneous Provisions Act
Minimum Wages Act 1948, Payment of Wages Act 1936 and Payment of Bonus Act
and all other applicable labour laws in so far as the provisions are applicable to me in respect
of the employment of contract labour by me for the month of ................................
Authorized Signature with Stamp
Place: Nani Naroli
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
10.0 ANNEXURE-J
PROCEDURE FOR MAKING ONLINE PAYMENT OF EMD/SD/TENDER FEE
1. For making online payment, first go to the website: www.gipcl.com
2. Then, click on the caption/link as can see like:
“Click here for Making Online Payment of EMD/SD, Advance for Ash, Advance for DM
(The link is visible as horizontal highlighted in “Blue” shade below Tenders - News & Update
3. After clicking the link the new page will open. On this page, no need to enter User Name
and Password. Directly click on “Payment Form” given below the sign in option.
4. After clicking the “Payment Form”, the vendor has to enter the details asked which will be
self-explanatory. It is desired that all the information may be filled correctly so that the
payment made can be tracked.
If the some required fields are not known/available, vendor may write “Not Available” and
then proceed. E.g. some information like Party code is not available to vendor or GST No.
not available with vendor.
Optional Note: Although mentioned as above can be proceeded with “Not available”, It will
be appreciated that regular vendors may obtain the party code from Materials Dept. or
Concerned Person, so that the vendor can be identified. The same party code may be used
for future transactions also.
After entering the details, click on SUBMIT Button.
5. The vendor/Party will be redirected to Payment Gateway.
By selecting the desired payment mode, payment can be made:
6. After making the payment, the receipt will be generated which has to be shared with
Concerned Person of GIPCL.
Important Note: Please note that for making online payment through the above gateway,
the charges* as below will be applicable, which has to be borne by Vendor/Party making the
Payment Mode Charges
Net Banking Rs.9 + GST
Credit Card 0.75% + GST
International Card 3.00% + GST
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
11.0 ANNEXURE-K
List of qualifying staff to be submitted with physical documents
Sr. No. Name of Supervisor/Engineer Qualification Experience
Contractor / Authorized Representative’s
Signature, Company’s / Organization’s Seal & Date
12.0 ANNEXURE-L
List of Tools & Tackles to be submitted with physical documents
Sr. No. Description Nos. Status
Contractor / Authorized Representative’s
Signature, Company’s / Organization’s Seal & Date
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Civil works for Construction of foundations,
flooring & associates General Civil works for 02 nos. of new Structural Storage Sheds (Pre-Engineered Building
- PEB) near existing Warehouse (Year: 2026-27)”. Bid No.: SLPP/Civil/WH/Sheds/2026.
13.0 ANNEXURE-M
(To be submitted on Company’s Letter Head)
Shri C. S. Jadeja
Chief General Manager (Thermal),
Surat Lignite Power Plant,
Gujarat Industries Power Company Limited (GIPCL),
At: Nani Naroli, Taluka – Mangrol, Dist. Surat – 394110, Gujarat.
Subject: Undertaking for Deployment of Full-Time Site Civil Engineer for Bid No.:
SLPP/Civil/WH/Sheds/2026.
With reference to the above-mentioned Tender Bid No. SLPP/Civil/WH/Sheds/2026 issued
by Gujarat Industries Power Company Limited (GIPCL) for “Civil works for Construction of
foundations, flooring & associates General Civil works for 02 nos. of new Structural Storage
Sheds (Pre-Engineered Building - PEB) near existing Warehouse (Year: 2026-27)”, we, the
undersigned, hereby submit this Undertaking in the manner and to the extent set forth herein.
DECLARATION BY THE BIDDER
We hereby unconditionally and irrevocably undertake that:
If the work under the above Bid No. SLPP/Civil/WH/Sheds/2026 is awarded to us, we shall
deploy, on a full-time basis, at least one (1) experienced Civil Engineer exclusively at
the Project Site, GIPCL Surat Lignite Power Plant, Nani Naroli, Surat, for the entire
duration of the execution of the scope of work assigned to us under the Contract, until the
issuance of the Project Completion Certificate by GIPCL / acceptance of work by GIPCL.
SPECIFIC COMMITMENTS
1. Full-Time Deployment: The Civil Engineer proposed to be deployed shall be present
at the Project Site on all working days throughout the construction phase of the Project.
Any absence exceeding three (3) consecutive working days shall require prior written
approval from GIPCL.
2. Qualification & Experience: The Civil Engineer so deployed shall possess the
following minimum qualifications and experience:
■ Degree / Diploma in Civil Engineering from a recognized University / Institute.
■ Minimum 03 (three) years of post-qualification experience in execution and
supervision of Civil construction projects / similar works (RCC foundation, flooring,
etc… in proper line & level as per constructions drawings, quality control, following
Technical specifications, etc…).
■ Prior experience in similar projects shall be preferred.
3. Scope of Responsibility: The deployed Civil Engineer shall, inter alia, be responsible
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
EMD BG Format.pdf
T1_Tender Document_Civil_PEB_Sheds_2026-27.pdf
Bid Drawing-1_PLOT Key Plan Shed-1 and Shed-2.pdf
Bid Drawing-2_Shed-1 Plan and Elevation.pdf
Bid Drawing-3_Shed-1 Footing.pdf
Bid Drawing-4_Shed-1 Ground Beam and Grade Slab.pdf
Bid Drawing-5_Shed-2 Plan and Elevation.pdf
Bid Drawing-6_Shed-2 Footing.pdf
Bid Drawing-7_Shed-2 Ground Beam and Grade Slab.pdf
Bid Drawing-8_Road cross section between sheds.PDF
Amendment-1 Civil.pdf
CORRIGENDUM
Download all tender documents and submit your bid